selection and implementation of a post-closure …the questa mine • surface open pit and...
TRANSCRIPT
![Page 1: SELECTION AND IMPLEMENTATION OF A POST-CLOSURE …The Questa Mine • Surface Open Pit and Underground Molybdenum Mine, near Taos, New Mexico • Began as an underground mine in the](https://reader033.vdocuments.us/reader033/viewer/2022053020/5f2b55c43a776f0fa848cc3b/html5/thumbnails/1.jpg)
SELECTION AND IMPLEMENTATION OF A POST-CLOSURE MINE DEWATERING SYSTEM
CHEVRON MINING INC, QUESTA MINE, NEW MEXICO
Tim Cox, Joe Gilbert, Arcadis U.S., Inc.
Mine Design, Operations, and Closure ConferenceButte, MontanaMay 2017
![Page 2: SELECTION AND IMPLEMENTATION OF A POST-CLOSURE …The Questa Mine • Surface Open Pit and Underground Molybdenum Mine, near Taos, New Mexico • Began as an underground mine in the](https://reader033.vdocuments.us/reader033/viewer/2022053020/5f2b55c43a776f0fa848cc3b/html5/thumbnails/2.jpg)
© Arcadis 2016
Presentation Outline
• Background
• Mine Dewatering Alternatives and Evaluation
• Selection of Dewatering Alternative
• Borehole Drilling
• Well Installation and Perforation
• Water Conveyance
• Summary
![Page 3: SELECTION AND IMPLEMENTATION OF A POST-CLOSURE …The Questa Mine • Surface Open Pit and Underground Molybdenum Mine, near Taos, New Mexico • Began as an underground mine in the](https://reader033.vdocuments.us/reader033/viewer/2022053020/5f2b55c43a776f0fa848cc3b/html5/thumbnails/3.jpg)
© Arcadis 2016
The Questa Mine• Surface Open Pit and Underground Molybdenum
Mine, near Taos, New Mexico
• Began as an underground mine in the early 1900’s, Open Pit in the mid 1960’s, then back to underground mining in the mid-1980’s
![Page 4: SELECTION AND IMPLEMENTATION OF A POST-CLOSURE …The Questa Mine • Surface Open Pit and Underground Molybdenum Mine, near Taos, New Mexico • Began as an underground mine in the](https://reader033.vdocuments.us/reader033/viewer/2022053020/5f2b55c43a776f0fa848cc3b/html5/thumbnails/4.jpg)
© Arcadis 2016
Background
• Previous underground mine dewatering included pumping via a decline (6,000 ft) to the surface
• The mine was closed in June of 2014, which included permanent closure of the underground workings
• A new surface-based method of maintaining water levels in the underground mine was needed
Decline
Hazleton Pump at the bottom of the Decline
![Page 5: SELECTION AND IMPLEMENTATION OF A POST-CLOSURE …The Questa Mine • Surface Open Pit and Underground Molybdenum Mine, near Taos, New Mexico • Began as an underground mine in the](https://reader033.vdocuments.us/reader033/viewer/2022053020/5f2b55c43a776f0fa848cc3b/html5/thumbnails/5.jpg)
© Arcadis 2016
Mine Dewatering Alternatives New System in the Decline New Well Field
Installing Pumps in Existing Shaft #1 Installing Pumps In Existing Shaft #2
![Page 6: SELECTION AND IMPLEMENTATION OF A POST-CLOSURE …The Questa Mine • Surface Open Pit and Underground Molybdenum Mine, near Taos, New Mexico • Began as an underground mine in the](https://reader033.vdocuments.us/reader033/viewer/2022053020/5f2b55c43a776f0fa848cc3b/html5/thumbnails/6.jpg)
© Arcadis 2016
Evaluation of Dewatering Alternatives
• The four alternatives were evaluated for:
• Capital Expenditures (CAPEX)• Operational Expenditures
(OPEX)• Pump and piping
considerations• Safety of the system• Timing for closure of the
underground• Likelihood of overall success
![Page 7: SELECTION AND IMPLEMENTATION OF A POST-CLOSURE …The Questa Mine • Surface Open Pit and Underground Molybdenum Mine, near Taos, New Mexico • Began as an underground mine in the](https://reader033.vdocuments.us/reader033/viewer/2022053020/5f2b55c43a776f0fa848cc3b/html5/thumbnails/7.jpg)
© Arcadis 2016
Dewatering AlternativesDecline
Pumping for Shafts #1 or #2
New Well Field
![Page 8: SELECTION AND IMPLEMENTATION OF A POST-CLOSURE …The Questa Mine • Surface Open Pit and Underground Molybdenum Mine, near Taos, New Mexico • Began as an underground mine in the](https://reader033.vdocuments.us/reader033/viewer/2022053020/5f2b55c43a776f0fa848cc3b/html5/thumbnails/8.jpg)
© Arcadis 2016
Selected Approach –New Dewatering Well Field• Capital costs comparable or
less than other alternatives
• Lower operational costs
• Reliable technology - well and pump components
• Could be installed quickly, allowing the underground mine to close sooner
• Required no personnel in the underground mine
• Used proven drilling technologies
![Page 9: SELECTION AND IMPLEMENTATION OF A POST-CLOSURE …The Questa Mine • Surface Open Pit and Underground Molybdenum Mine, near Taos, New Mexico • Began as an underground mine in the](https://reader033.vdocuments.us/reader033/viewer/2022053020/5f2b55c43a776f0fa848cc3b/html5/thumbnails/9.jpg)
© Arcadis 2016
New Dewatering Well Field• The location of the well field was
near Shaft #2
• Three wells equipped with electronic submersible pumps would be installed in the lowermost Haulage Level of the underground mine
• Three wells were installed to provide redundancy
• Well screens and pump depths coincide with the lowermost Haulage Level, approximately 1,200 feet below grade
White = Lowermost Haulage LevelBlue = Upper Grizzly Level
Shaft #2
DWW-3
DWW-2
DWW-1
![Page 10: SELECTION AND IMPLEMENTATION OF A POST-CLOSURE …The Questa Mine • Surface Open Pit and Underground Molybdenum Mine, near Taos, New Mexico • Began as an underground mine in the](https://reader033.vdocuments.us/reader033/viewer/2022053020/5f2b55c43a776f0fa848cc3b/html5/thumbnails/10.jpg)
© Arcadis 2016
Dewatering Well Drilling Plan• Advance borehole using conventional mud
rotary and reaming techniques through unconsolidated material and weathered bedrock
• Pilot borehole driven using real-time measurement-while-drilling (MWD) instrumentation and directional tooling
• Ream piloted borehole to prescribed diameter to the Haulage Level
• Below the Haulage Level, the borehole was advanced using air/foam mud mixtures
Drilling Rig
PDC Pilot Bit
![Page 11: SELECTION AND IMPLEMENTATION OF A POST-CLOSURE …The Questa Mine • Surface Open Pit and Underground Molybdenum Mine, near Taos, New Mexico • Began as an underground mine in the](https://reader033.vdocuments.us/reader033/viewer/2022053020/5f2b55c43a776f0fa848cc3b/html5/thumbnails/11.jpg)
© Arcadis 2016
Borehole Drilling
• Pilot boreholes used real-time directional drilling to ensure that the borehole was advanced into the Haulage Level within a 4-foot diameter target
10.75-inch pilot bit and 17-inch reaming reamer in the Haulage Level
![Page 12: SELECTION AND IMPLEMENTATION OF A POST-CLOSURE …The Questa Mine • Surface Open Pit and Underground Molybdenum Mine, near Taos, New Mexico • Began as an underground mine in the](https://reader033.vdocuments.us/reader033/viewer/2022053020/5f2b55c43a776f0fa848cc3b/html5/thumbnails/12.jpg)
© Arcadis 2016
Well Casing Installation• 9.625-inch LTC production casing and
guide shoe inside 18-inch surface/ conductor casing
• Cement baskets were placed at intervals after review of caliper logs
• The upper 500 feet of borehole annulus was grouted
Casing and Guide Shoe
![Page 13: SELECTION AND IMPLEMENTATION OF A POST-CLOSURE …The Questa Mine • Surface Open Pit and Underground Molybdenum Mine, near Taos, New Mexico • Began as an underground mine in the](https://reader033.vdocuments.us/reader033/viewer/2022053020/5f2b55c43a776f0fa848cc3b/html5/thumbnails/13.jpg)
© Arcadis 2016
Drilling Lessons Learned
• Collaboration among Chevron Mining Inc., Chevron’s Midcontinent Business Unit Drilling & Completions, and Arcadis was critical in developing a sound drilling and well installation plan
• Pilot hole and MWD was instrumental in establishing borehole trajectory
• Two reams were needed due to bedrock geology
• A shock sub used in the borehole assembly that increased penetration rates
• A caliper tool and log was used to locate placement of cement basket, and minimized the amount of grout used
![Page 14: SELECTION AND IMPLEMENTATION OF A POST-CLOSURE …The Questa Mine • Surface Open Pit and Underground Molybdenum Mine, near Taos, New Mexico • Began as an underground mine in the](https://reader033.vdocuments.us/reader033/viewer/2022053020/5f2b55c43a776f0fa848cc3b/html5/thumbnails/14.jpg)
© Arcadis 2016
Well Perforation• Wells casings were perforated at
the interval within the Haulage Level, about an 18-foot long interval
• Prior to perforation, wells were fitted with a bridge plug, filled with water, and then perforated
• Wells were perforated using an 18-foot long perforation gun, 216 perforations or a 12-shot per foot geometry
Unfired Perforation Gun
![Page 15: SELECTION AND IMPLEMENTATION OF A POST-CLOSURE …The Questa Mine • Surface Open Pit and Underground Molybdenum Mine, near Taos, New Mexico • Began as an underground mine in the](https://reader033.vdocuments.us/reader033/viewer/2022053020/5f2b55c43a776f0fa848cc3b/html5/thumbnails/15.jpg)
© Arcadis 2016
Pump Installation
• The historical inflow to the underground mine was 250 gpm -each well was designed to pump at that rate
• 14-stage Baker Hughes HC10,000 electrical submersible pumps were installed with 4.5-inch coupled, internally plastic coated tubing
• Each pump was fitted with a well lift gauge (transducer) to measure water levels
• Pumps were placed just below the Haulage Level
Pump Assembly Prepared for Installation
![Page 16: SELECTION AND IMPLEMENTATION OF A POST-CLOSURE …The Questa Mine • Surface Open Pit and Underground Molybdenum Mine, near Taos, New Mexico • Began as an underground mine in the](https://reader033.vdocuments.us/reader033/viewer/2022053020/5f2b55c43a776f0fa848cc3b/html5/thumbnails/16.jpg)
© Arcadis 2016
Water Conveyance• The three wells are connected to a manifold and HDPE discharge pipeline
• The discharge pipeline conveys water from the well field down to an existing pump station where it is pumped up to the former mill for treatment
![Page 17: SELECTION AND IMPLEMENTATION OF A POST-CLOSURE …The Questa Mine • Surface Open Pit and Underground Molybdenum Mine, near Taos, New Mexico • Began as an underground mine in the](https://reader033.vdocuments.us/reader033/viewer/2022053020/5f2b55c43a776f0fa848cc3b/html5/thumbnails/17.jpg)
© Arcadis 2016
Summary• The new well field met all evaluation
considerations and lead to the successful and timely shut down of the underground mine
• A collaborative effort combining directional and conventional drilling techniques ensured that each borehole reached its target
• The new dewatering system allows for safe, surface-based, and long-term management of water levels
• The wells were started in August 2016 and are successfully pumping to manage water in the underground mine