seismic remediation of dams in california, an engineering geology perspective

35
Seismic Remediation of Dams in California, An Engineering Geology Perspective William A. Fraser, P.G., C.E.G. Chief, Geology Branch CA Division of Safety of Dams PO Box 942836 Sacramento, CA 94236-0001 [email protected] Abstract Over the past 25 years a number of dams in California have been analyzed for seismic stability and have required remediation to improve their seismic stability. Embankment dams are subject to slope failure under earthquake loading which causes deformation and settlement of the dam crest, potentially resulting in uncontrolled release of the reservoir. Detailed review of a dams design and construction history is an essential component of predicting its future seismic performance. Embankment dams with liquefiable alluvial foundations are perhaps the most common cause of seismic instability. Older embankment dams constructed of poorly compacted soils and dams constructed using hydraulic fill methods are also problematic. These dams are usually remediated by improving the foundation strength and constructing a buttress against the 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

Upload: karyn-m-heim

Post on 10-Feb-2017

583 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Seismic Remediation of Dams in California, An Engineering Geology Perspective

Seismic Remediation of Dams in California, An Engineering Geology Perspective

William A. Fraser, P.G., C.E.G.

Chief, Geology Branch

CA Division of Safety of Dams

PO Box 942836

Sacramento, CA 94236-0001

[email protected]

Abstract

Over the past 25 years a number of dams in California have been analyzed for seismic

stability and have required remediation to improve their seismic stability. Embankment

dams are subject to slope failure under earthquake loading which causes deformation

and settlement of the dam crest, potentially resulting in uncontrolled release of the

reservoir. Detailed review of a dams design and construction history is an essential

component of predicting its future seismic performance. Embankment dams with

liquefiable alluvial foundations are perhaps the most common cause of seismic

instability. Older embankment dams constructed of poorly compacted soils and dams

constructed using hydraulic fill methods are also problematic. These dams are usually

remediated by improving the foundation strength and constructing a buttress against the

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

Page 2: Seismic Remediation of Dams in California, An Engineering Geology Perspective

embankment slope and improved foundation. Concrete arch dams become

overstressed when the seismic loads exceed the tensile strength of the concrete

resulting in cracking of the concrete. Remediation of a concrete arch dam usually

involves thickening of the arch with additional concrete section to improve its seismic

performance. Multiple arch dams rely on buttresses that are susceptible to cross-

channel toppling causing loss of support for the arch. The remediation of a multiple

arch dam often involves filling the area between the buttresses with mass concrete to

resist toppling. This paper presents case histories of several of remediation projects

that the author has worked on during his over 25 years with the California Division of

Safety of Dams, emphasizing the role of the engineering geologist in seismic

remediation.

Seismic Remediation of Dams in California, An Engineering Geology Perspective

Introduction

Since 1929, the California Division of Safety of Dams (DSOD) has supervised the

design, construction, maintenance and operation of non-Federal dams in California.

California is one of the more seismically active areas in the United States and

earthquakes are one of the more severe loading conditions dams need to withstand. It

is not surprising that DSOD dedicates significant resources to insuring jurisdictional

dams perform well in major earthquake events.

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

Page 3: Seismic Remediation of Dams in California, An Engineering Geology Perspective

As part of the project team, engineering geologists play an important role in

characterizing the seismic hazard of a given site and characterizing the site conditions

needed to evaluate a dam’s ability to resist seismic loading. Engineering geologists also

play an important role in the design and construction of the remedial measures that are

taken to improve a dam’s seismic performance. This paper discusses the author’s

vision of the role of engineering geologists in these civil engineering activities.

Identification of Dams with Seismic Deficiencies

The design and construction history of a dam is one way to recognize a potentially

deficient dam. In the first half of the 20th century, neither the ability to predict

earthquake loads nor the tools to evaluate the performance of dams under seismic

loading were available. Seismic design was only a minor consideration as compared to

static stability and seepage considerations. Unfortunately, some designs and

construction practices of that day resulted in dams which often proved to be poor

performers under earthquake loading. Two such designs are multiple arch dams and

hydraulic fill dams.

Hydraulic fill dams consist of sand, silt, and clay soils transported and placed by

hydraulically sluicing though an often elaborate conveyance system of flumes

constructed for the project (Photo 1). The sluiced soils were usually ponded between

two dumped rockfill dikes placed at the upstream and downstream toes of the dam

under construction. This technology was an outgrowth of the hydraulic mining industry,

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

Page 4: Seismic Remediation of Dams in California, An Engineering Geology Perspective

once a common mining technique in California outlawed in 1888. This approach was

used to build many dams in California through the 1930’s before mechanized

construction equipment was readily available. However, slope failures of hydraulic fill

dams during construction were not uncommon due to the lack of compaction and high

consolidation pore pressure. Their seismic deficiency was fully appreciated during the

1971 San Fernando Earthquake when the upstream slope and the crest of the Lower

San Fernando Dam slumped into the reservoir. Although the dam was badly damaged,

the reservoir was not released fortunately averting a catastrophic flood in urban Los

Angeles.

A multiple arch dam consists of a series of concrete buttresses which support a series

of concrete arch barrels between the buttresses (Photo 2). The design was popular in

the early 20th century because it required a smaller volume of concrete compared to a

massive concrete gravity dam. However, the buttresses of multiple arch dams can

topple when subjected to earthquake loading in the cross channel direction resulting in

the loss of support for the arches and release of the reservoir.

A second way that a potentially unstable dam can be recognized is by a history of poor

static performance or evidence of deterioration. Dams that perform marginally under

static conditions are likely to also perform poorly under earthquake loading. Excessive

movements of the embankment in response to changes in reservoir storage or a history

of instability are all symptomatic of a dam that will likely prove to be deficient under

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

Page 5: Seismic Remediation of Dams in California, An Engineering Geology Perspective

earthquake loading. A poorly maintained dam, such as a concrete dam with evidence

of deterioration of the concrete, could also prove to be seismically deficient.

A third approach to identifying seismically deficient dams is by periodic reassessment of

seismic stability. In California, dams which pose high consequences of failure have

historically been reassessed for their seismic stability every 25 to 30 years. This level of

scrutiny is warranted due to the periodic advancements in geology, engineering

seismology, and engineering practice. New seismic sources such as blind thrusts faults

have been recognized in California as recently as the 1980’s, increasing design loading

in some areas of California. The ability to characterize earthquake loading continues to

improve. The dense strong motion accelerometer network has provided many more

earthquake recordings resulting in improved ground motion prediction equations. While

peak ground acceleration remains a common intensity measure, the use of multiple

intensity measures can better describe the characteristics of the expected earthquake

motions. Studies of the performance of soils during historic earthquakes have led to

improved ability to predict future performance of those soils under future earthquake

loading. Finally, the analytical tools used to evaluate seismic performance of dams

have improved. Greater computational processing power has allowed the use of

software which contains complex constitutive models that simulate the changes in

engineering properties that occur as the earthquake proceeds.

Since 1999, DSOD has had an ongoing reevaluation program to identify dams that are

candidates for seismic reassessment. Considering there are more than 1250 dams of

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

Page 6: Seismic Remediation of Dams in California, An Engineering Geology Perspective

jurisdictional size in California, dams with the greatest seismic exposure combined with

the highest consequence of failure are evaluated first.

The approach used by DSOD to evaluate seismic exposure involves determining the

peak ground acceleration (PGA) probabilistically, which increases as the seismic

exposure increases. In a probabilistic analysis, sites essentially accumulate PGA (or

any intensity measure) as earthquakes from various seismic sources near the site are

sequenced through time. The timing of earthquakes is a function of the slip rates for

nearby faults. Therefore, a listing of dams by increasing PGA (at a constant return

period and site condition) essentially ranks dam sites in order of increasing seismic

exposure. The 500-year return period was chosen so sites which accumulate seismic

hazard quickly are emphasized. An improvement to this approach would be to perform

the probabilistic seismic hazard analysis using a time-dependent fault model that

considers the earthquake recurrence cycle on a fault and time since the last event. This

was the motivation for beginning the reanalysis program with the Hayward fault, in light

of the well-publicized analysis by the USGS that placed a very high probability of a

future event on that fault in the next 30 years.

Dams in high hazard-high consequence categories are then initially screened by a team

consisting of a design engineer and engineering geologist for attributes that suggest

seismic fragility, that is, the potential for poor performance during a seismic event. The

dams identified by this initial screening are given a detailed file review of site geology,

design, construction, and maintenance history. The file review is followed by an

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

Page 7: Seismic Remediation of Dams in California, An Engineering Geology Perspective

independent characterization of the seismic hazard and site conditions and an

evaluation of the dam’s performance under the design earthquake load. If the dam is

found to be of marginal or inadequate stability, the owner is notified and asked to

undertake a reevaluation of the seismic stability. This effort usually involves additional

field exploration using current standards to better characterize the dam and its

foundation so more confident seismic stability analyses can be performed.

Role of the Engineering Geologist in the Reevaluation of Dams with Potential

Seismic Instability

Poor compaction of earthfill is a common cause of seismic instability in older

embankment dams. The earliest dams in California were compacted by livestock.

Even the early rolled-fill dams sometimes lacked the compaction effort to sufficiently

improve shear strength to resist earthquake loading. Many early embankment dams

were designed without internal drainage to reduce the level of saturation within the dam.

The combination of poor embankment compaction and development of a high saturation

level within the embankment has resulted in many embankment dams proving to be

deficient when analyzed for seismic stability. Engineering geologists are typically

involved in the field investigations, which include field description, field testing, and

undisturbed sampling of the embankment and foundation soils, as well as the

installation of piezometers to determine the level of saturation in the embankment.

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

Page 8: Seismic Remediation of Dams in California, An Engineering Geology Perspective

A very common reason for seismic deficiency is the presence of potentially liquefiable

alluvium in the foundation of embankment dams. Dams built before the 1960’s often

have alluvium in their foundations that was left in place purposely by the designers of

that era to promote internal drainage. The alluvium is strong under static conditions, but

under earthquake shaking the saturated alluvium may lose strength resulting in seismic

instability.

The investigation and characterization of the alluvium involves engineering geologists

working in conjunction with geotechnical engineers. Although, the extent of the alluvium

is sometimes shown on the as-built plans for the dam, the existence and extent is

sometimes completely unknown and its limits and thickness must be learned through

exploration. Sonic drilling or other methods that provide continuous sampling of the soil

mass is critical at this stage. The potential for triggering liquefaction of cohesionless

alluvium is evaluated through an understanding the gradation and penetration

resistance of the alluvium. Depending on the gradation of the soil, one or more of the

penetration resistance field tests is used to determine if the soil will liquefy. Current

practices use the Standard Penetration Test (SPT) and Cone Penetration Test (CPT)

for sandy and silty soils and Becker Hammer Penetration Test (BPT) for gravelly soils.

Cohesive alluvium and colluvium is not prone to classic liquefaction, but these soils can

also lose strength and are evaluated by the laboratory testing of undisturbed samples.

If the alluvium proves to be liquefiable, its post-liquefaction residual strength is also

determined by empirical relations that use penetration resistance. Practical

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

Page 9: Seismic Remediation of Dams in California, An Engineering Geology Perspective

considerations often require that variable foundation soils be grouped and characterized

together within a generalized strength model. A key contribution made by the

engineering geologist is the use of geomorphologic and time-stratigraphic principals to

assist in defining packages of foundation soils with similar engineering properties. For

example, the different depositional environments produce soil deposits with unique

gradations (i.e., fluvial, colluvial or aolian) and logically can be the basis for grouping

penetration resistance test intervals in a foundation strength model. Also, older alluvium

should possess greater relative density than recent alluvium and these materials can be

distinguishing by elevated position above the modern drainage at sites experiencing

uplift through geologic time. In deep sedimentary basins where deposition has been

occurring over long periods of time, older alluvium can be recognized by the soil profiles

that have developed prior to burial by younger alluvium. Recognizing the depositional

environment is essential to characterizing the strength of unconsolidated materials and

will often provide the framework for confident strength modelling of a dam foundation.

In California, concrete dams rarely have alluvium in their foundations. The most

common cause of seismic deficiency in concrete dams is overstressing of the concrete

under earthquake shaking. Similar to rock, concrete has considerable compressive

strength but much less strength in tension. Strong earthquake shaking can induce

stresses that exceed the tensile strength of the concrete and cause the concrete to

crack. This is especially problematic for arch dams that are generally thin and therefore

more susceptible to failure from cracking. Although the analysis of concrete

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

Page 10: Seismic Remediation of Dams in California, An Engineering Geology Perspective

overstressing is beyond the scope of the paper, I do present the remediation of Big Bear

Dam where the multiple arch dam was remediated for seismic stability.

Concrete dams are susceptible to sliding on continuous planar discontinuities that are

adversely oriented with respect to the dam and topography. Bedding planes in folded

sedimentary rock are especially problematic because they are usually continuous over

the scale of a dam foundation and are often filled with weak clay gouge developed

during the folding of the rock mass. Joints are generally not as continuous as bedding,

but can be problematic because they usually occur with multiple orientations. The

orientation of jointing relative to the foundation excavation surface influences the shear

strength of the foundation surface, and wedges formed by adversely intersecting joints

can be unstable under the loading imposed by the dam and reservoir.

Geologists contribute to the characterization of the foundation rock strength by

identifying the presence, orientation, and condition of the discontinuities. Many larger

dams have detailed geologic maps of the foundation showing discontinuities and their

orientations as revealed by the extensive construction excavations. Additional

description of the discontinuities can be made by visual observation test pits and

logging of rock core. Orientation is determined by direct measurement with a Brunton

compass or borehole orientation techniques, such as acoustic or optical televiewers.

Structural geology principals are used to confidently project the position of the

discontinuities away from known points. A sometimes difficult characterization is

determining the shear strength of bedding plane gouge or weathering product on a joint

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

Page 11: Seismic Remediation of Dams in California, An Engineering Geology Perspective

surface. A confident assessment usually involves using multiple approaches such as

visual observation of discontinuity roughness and infilling, laboratory testing, and back-

calculating observed slope performance.

Finally, engineering geologists are involved in the seismic hazard assessment and

development of ground motions used in the engineering analysis. This activity involves

either a deterministic or probabilistic hazard assessment, or a combination approach to

develop target ground motion intensity parameters. Multiple intensity measures are

developed such as peak ground acceleration, response spectra, Arias intensity, peak

ground velocity, and significant duration. Generally, for dams in high seismic regions

with high consequence of failure, an 84th percentile deterministic loading from the

controlling seismic source is used for dam safety evaluations. A probabilistic seismic

hazard assessment can also be used to develop intensity measures or to estimate the

return period associated with the deterministic design load. Risk analysis methods are

becoming more common, which require a variety of seismic loading conditions up to or

near the point of failure. Most modern analyses use acceleration time histories as the

basis for the earthquake motion. Natural earthquake recordings are usually modified by

spectral matching or linear scaling to represent safety evaluation earthquake levels. For

scenarios such as Magnitude 8 events where natural records are not available,

synthetic time histories are being used increasingly.

Seismic Remediation Approaches

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

Page 12: Seismic Remediation of Dams in California, An Engineering Geology Perspective

If a dam is found to require seismic remediation, several stabilization approaches are

available and chosen on a case-by-case basis. To illustrate some of these remediation

techniques, this section will present several cases histories of dams that have been

remediated during the past 25 years.

An initial determination is needed to decide if the existing dam can be salvaged. In

some cases a deficient dam is so poorly built it is unwise to attempt to remediate it. If

the dam has very poor documentation, was built in multiple stages, has a history of

failure, or has had unsuccessful remediation attempts it may be best to build a

completely new dam.

If an existing dam can be confidently modeled and analyzed, approaches are available

to improve its stability. For embankment dams, these techniques include providing

buttresses, removing and replacing weak soils, and in-situ remediation of weak soils.

Often a combination of these techniques is used. For concrete dams, remediation

techniques typically involve various ways of thickening the concrete section to better

distribute earthquake induced stresses and change the dynamic response of the

structure. Other techniques involve post-tension anchoring, providing or improving

drainage, foundation grouting, upstream liners, and lowering the dam crest.

New Calaveras Dam

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

Page 13: Seismic Remediation of Dams in California, An Engineering Geology Perspective

The Calaveras dam, owned by the City and County of San Francisco, is located near

Sunol, California. The 220-foot high dam retains a 100,000 acre-foot reservoir, which is

a major component of the Hetch Hechy Aqueduct that provides water to San Francisco

and other Bay Area communities. The dam is essentially within the Calaveras fault

zone located about 1000 feet from the main trace.

The original Calaveras Dam was partially built by hydraulic fill methods and completed

in 1925. Two construction issues complicated confident characterization of the original

dam. The engineering properties of the hydraulic fill material changed when a new

source area was used mid-way through construction, and more significantly, the

hydraulic fill was placed too quickly and the embankment failed during construction.

When work was resumed several years later, the remaining hydraulic fill section was

reshaped and a compacted rolled-fill was used to construct the upper portion of the

dam. The dam is founded on Franciscan mélange and Tertiary-age Temblor sandstone

with alluvium beneath the channel section.

The dam was found to be seismically deficient in the 1970’s and remediated using an

approach no longer favored today. In 1999 the dam was again identified as a candidate

for seismic reanalysis because of continued embankment deformations in response to

reservoir loading cycles and its close proximity to the Calaveras fault. An extensive

geotechnical investigation was performed in 2001 to characterize the engineering

properties of the embankment and its alluvial foundation. Because of its complex

construction history, the material properties varied widely making confident

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

Page 14: Seismic Remediation of Dams in California, An Engineering Geology Perspective

characterization difficult. The new engineering analysis indicated the dam was unstable

under the relatively high design earthquake loads appropriate for the site. It was

decided to construct a replacement dam rather than attempt to remediate the existing

dam again. In the interim, the water storage against the existing dam is restricted to a

level which assures no uncontrolled release of the reservoir in the event of a major

earthquake.

A modern earthfill-rockfill dam, located immediately downstream of the existing dam,

was designed. The existing dam functions as a coffer dam during construction (Photo

3). Since the project is within the Calaveras fault zone, an extensive investigation of

the faulting involving field mapping, geomorphic terrain analysis, and paleoseismic

trenching was undertaken to identify the active fault traces as part of the design review.

An extensive exploration program was also performed to identify the available

construction materials and to investigate geologic hazards and dam foundation issues.

The replacement dam requires a completely new spillway and substantial modifications

to the existing low-level outlet. The replacement dam is currently under construction

with an expected completion date of 2018. The existing dam will then be partially

removed to a configuration which poses no impact to the safety or operation of the new

facility in the event of a major earthquake.

Crane Valley Dam

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

Page 15: Seismic Remediation of Dams in California, An Engineering Geology Perspective

Crane Valley Dam, owned by Pacific Gas and Electric Company, is a 145-foot high

hydraulic fill dam built in 1910. The dam impounds Bass Lake, a 45,410 acre-foot

popular recreation area near Mariposa, California.

The dam was suspected of seismic instability because of its hydraulic fill design and

evidence of continuing deformation under static conditions despite earlier efforts to

stabilize the dam. The investigation to evaluate the dam began in 2004, which included

exploration of the dam and its foundation using both conventional land-based and

barge-mounted drill rigs (Photo 4). The hydraulic fill was predicted to liquefy and the

dam was found to deform excessively under the relatively low design loads appropriate

for the Sierra Nevada. The reservoir was then restricted to a level at which the potential

for uncontrolled release during an earthquake was eliminated.

The remediation of Crane Valley Dam is an example of buttressing the slopes of an

embankment dam. Rockfill buttresses for both the upstream and the downstream slope

were designed. In general, the buttressing approach involves construction of a well-

compacted earthfill or rockfill section placed against the existing dam and founded on a

high shear strength foundation surface. The design of the buttress considers the

strength of the existing dam and its foundation, as well as the strength buttress to be

built. The size of the buttress is then optimized to reduce deformations to an acceptable

level. The design often considers the effect of removing a portion of the existing dam to

provide a more strategic location for the buttress and the addition of internal drainage to

insure the buttress is not saturated.

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

Page 16: Seismic Remediation of Dams in California, An Engineering Geology Perspective

To be effective, the buttress must be founded on high strength material to resist

excessive deformations resulting from sliding along a low strength surface beneath the

buttress. The Crane Valley site is weathered granitic rock overlain by residual soils and

colluvium. The likely presence of reservoir silt should always be expected in the vicinity

of the upstream toe. The design called for the removal of all reservoir silt, colluvium and

residual soils, providing a severely weathered rock foundation for both the upstream

and downstream buttresses.

At Crane Valley, engineering geologists played an important role in recognizing the

depth to severely weathered rock within the footprints of the buttresses. A detailed

predetermination of the elevation of the top of severely weathered rock was important to

this project because of the short construction season and the need to design an

effective dewatering system to allow excavation for the downstream buttress while

maintaining storage in the reservoir. To accomplish this, an additional exploration

program consisting of closely spaced test pits and borings was performed to identify the

top of severely weathered rock. The exploration also included an additional phase of

barge-based exploration on the upstream side (Photo 5). In this granitic rock,

determination of acceptable foundation was based primarily on visual observations, that

is, recognizing textural characteristics associated with severely weathered rock and the

unacceptable overlying materials in the test pits and boring samples.

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

Page 17: Seismic Remediation of Dams in California, An Engineering Geology Perspective

On the downstream side, foundation excavations of about 10 feet were needed to reach

severely weathered rock foundation. The characteristics of the foundation rock could be

confirmed by visual inspection of the exposures (Photo 6). The granitic site location in

the high Sierra allowed a high shear strength buttress comprised of clean coarse rockfill

to be specified. The rockfill was then placed and compacted by conventional methods.

On the upstream side, dredging was performed (Photo 7) using an instrumented

excavator down to the elevation of the top of severely weathered rock as predetermined

through closely spaced exploration. Excavations of up to 20 feet were required to

encounter severely weathered rock. The upstream buttress was placed by

systematically dumping the rockfill from a barge through a few tens of feet of water.

The final configuration of upstream buttress was confirmed using sonar and manual

depth probing.

Sunset North Dam

Sunset North Dam, owned by the City and County of San Francisco, is a lined and

covered 275 acre-foot reservoir built in 1938 within an urban setting in the Sunset

District of San Francisco. A 74-foot high embankment dam forms the northwestern

corner of the reservoir, with the remaining sides of the reservoir created largely by cut.

The dam is founded on up to 20 feet of dune sand and alluvium overlying Franciscan

Formation metamorphic rock. The site is approximately 5 kilometers from the San

Andreas fault.

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

Page 18: Seismic Remediation of Dams in California, An Engineering Geology Perspective

Because of its deposition by wind, dune sand is especially clean and poorly graded

which increases its susceptibility to liquefaction if saturated (Photo 8). The dune sand

was recognized during original construction and the records indicate that the sand was

either removed or recompacted to a dense condition, especially beneath the lined

portions of the reservoir. However in the late 1990’s, subsurface exploration revealed

that saturated medium dense dune sand and alluvium still existed beneath the

downstream portion of the Sunset North embankment. After an extensive piezometric

and geotechnical investigation, the dune sand and underlying alluvium were found to be

liquefiable and embankment deformations were judged to be unacceptably large under

the design loading.

Because the urban setting of this reservoir severely limited construction staging areas,

removal and replacement of the dune sand was considered impractical and a program

of insitu foundation remediation using Cement Deep Soil Mixing (CDSM) was

developed.

CDSM is a technique that involves a large specialty drill rig that bores several

overlapping auger holes approximately 3 to 5 feet in diameter (Photos 9). The holes are

advanced to target depth, and upon withdrawal cement slurry is injected and mixed with

the native materials creating soil-cement columns. The columns are configured in a

box-like cell arrangement with roughly 45% of the foundation material within each cell

made into CDSM columns. The approach does not prevent liquefaction of the untreated

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

Page 19: Seismic Remediation of Dams in California, An Engineering Geology Perspective

foundation material; however, the strength and arrangement of the columns provide

sufficient shear strength to limit embankment deformations. A berm is often placed over

the treated foundation area to further improve stability.

The advantage of deep soil mixing for foundation improvement is that columns with

predictable dimension and shear strength characteristics are built. Since there is no

attempt to improve the density of the alluvium itself, extensive field testing of the pre

and post treatment condition of the alluvium is not needed. The quality control

standards do include core drilling of a fraction of the CDSM columns to test their

strength and evaluating the percent recovery as a proxy for consistent field mixing of the

cement within the column. A potential disadvantage of the technique is that the cells

can decreases the permeability of the remediated foundation and care must be taken to

provide sufficient drainage to avoid increasing the phreatic line beneath the downstream

portion of the embankment.

At Sunset North, a total of 8000 linear feet of CDSM columns arranged in 27 cells were

constructed. The work was staged from three temporary benches excavated into the

downstream slope of the dam (Photo 10). The columns extend from the base of the

dam through the dune sand, alluvium and several feet into the Franciscan formation

rock. Because of the high costs of the column construction, the actual depth to rock

throughout the remediation area was important to avoid constructing the columns

unnecessarily deep. A map contouring the elevation of the top of rock based on the

extensive existing exploration was helpful for an initial assessment and the

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

Page 20: Seismic Remediation of Dams in California, An Engineering Geology Perspective

instrumented performance of the CDSM drill confirmed when rock was encountered on

a column-by-column basis. After the foundation improvement was completed the

embankment rebuilt to its original configuration. Similar CDSM methods were employed

at San Pablo Dam, and will be used at Perris Dam to limit seismic deformation due to

potentially liquefiable foundation alluvium.

Bear Valley Dam

Bear Valley Dam, owned by the Big Bear Municipal Water District, was originally

constructed as a multiple arch dam in 1911. The dam retains the 74,000 acre-foot Big

Bear Lake an important recreational area in the San Bernardino Mountains. The dam is

founded on granitic rock.

The dam was determined to be seismically deficient in the early 1980’s due to buttress

weakness in the cross channel direction. The approach selected to strengthen the dam

was to fill the downstream side of each arch barrel with mass concrete block against

both the arch and the two lateral buttresses that support each arch barrel. This

approach essentially transfers the earthquake induced stresses to the new mass

concrete blocks, essentially converting the multiple arches into a gravity structure. The

remediation was designed for both a M8.0 event on the San Andreas fault and a M6.0

local event on the Bear Creek fault. The highest loadings from these two scenarios

were applied in both the channel parallel and cross channel directions.

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

Page 21: Seismic Remediation of Dams in California, An Engineering Geology Perspective

The stabilization was constructed during the summer of 1988. The inclined arches

prevented the use of mechanical equipment to perform the excavation. Because of the

restricted access, hand excavation was required to remove the soil debris and severely

weathered rock to prepare the foundation for the mass concrete. The contractors used

picks, shovels and wheel barrows to excavate the material. Care was taken to not

undercut the foundation support of the existing arches or buttresses. The mass

concrete blocks were ultimately placed on a clean and unyielding surface of moderately

to slightly weathered rock (Photo 11). Finally, a formed narrow interface between the

existing arches and each mass concrete block was grouted to make the structure

monolithic.

A major remediation is a special opportunity to improve the understanding of the

foundation geology of a facility, and these observations are especially important for

older dams without geologic documentation during construction. During the

remediation, I performed detailed geologic mapping of the excavated foundation surface

at a scale of 1 inch equals 20 feet to improve the geologic documentation for this dam

(Figure 1). Geologic mapping of the buttress foundation excavation has become routine

practice DSOD staff during the construction of dam remediation measures.

The remediated dam was tested during the 1992 M6.6 Big Bear earthquake with an

epicenter just several kilometers from the dam. The dam performed well during this

major earthquake and the timely remediation of the dam just a few years earlier may

have averted a potential disaster.

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

Page 22: Seismic Remediation of Dams in California, An Engineering Geology Perspective

Acknowledgments

The author would like to thank the management of the California Division of Safety of

Dams for supporting this paper. I would like to thank the numerous geologists and

engineers I have had the pleasure to work with on the seismic remediation efforts in

California. I would especially like to thank Senior Engineering Geologist James

Lessman for his work on the Sunset North and Calaveras Dams, and Senior

Engineering Geologist Chris Tracy for his work on Crane Valley Dam. I also thank Mark

Schultz, Wallace Lam and Karyn Heim for their thoughtful reviews which improved this

manuscript.

Selected References

AMEC Geomatrix, Inc., 2012, Revised Final Design Report, Seismic Retrofit of Crane

Valley Dam: Consultant’s report prepared for Pacific Gas and Electric Company.

Bruce, Donald A., (editor), 2013, Specialty Construction Techniques for Dam and Levee

Remediation: CRC Press.

Fraser, William A., 2001, Engineering Geology Considerations for Specifying Dam

Foundation Objectives: in Ferriz, H., and Anderson, R., (editors), Engineering Geology

Practice in Northern California, AEG Special Publication 12.

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

Page 23: Seismic Remediation of Dams in California, An Engineering Geology Perspective

Olivia Chen Consultants, 2001, Sunset Reservoir North Basin Stability Assessment:

Consultant’s report prepared for San Francisco Public Utilities Commission.

R.W. Beck and Associates, 1987, Report on the Structural Analysis of Rehabilitation,

Bear Valley Dam Project: Consultant’s report prepared for Big Bear Municipal Water

District.

Schafer Dixon and Associates, Inc., 1987, Multiple Arch Dam Photographs, Big Bear

Lake, California: Consultant’s report prepared for Big Bear Municipal Water District.

URS Corporation, 2006, Design Basis Memorandum Calaveras Dam Replacement

Project, Final Design: Consultant’s report prepared for San Francisco Public Utilities

Commission.

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

Page 24: Seismic Remediation of Dams in California, An Engineering Geology Perspective

1

2

3

4

5

6

7

Page 25: Seismic Remediation of Dams in California, An Engineering Geology Perspective

1

2

3

4

5

6

7

8

9

10

11

12

Page 26: Seismic Remediation of Dams in California, An Engineering Geology Perspective

1

2

3

4

5

6

7

Page 27: Seismic Remediation of Dams in California, An Engineering Geology Perspective

1

2

3

4

5

6

7

8

9

10

11

12

13

Page 28: Seismic Remediation of Dams in California, An Engineering Geology Perspective

1

2

3

4

5

6

Page 29: Seismic Remediation of Dams in California, An Engineering Geology Perspective

1

2

3

4

5

6

7

8

9

10

Page 30: Seismic Remediation of Dams in California, An Engineering Geology Perspective

1

2

3

4

5

6

7

8

9

10

11

Page 31: Seismic Remediation of Dams in California, An Engineering Geology Perspective

1

2

3

4

5

6

7

8

9

10

11

Page 32: Seismic Remediation of Dams in California, An Engineering Geology Perspective

1

2

3

4

5

6

7

8

9

10

11

Page 33: Seismic Remediation of Dams in California, An Engineering Geology Perspective

1

2

3

4

5

6

7

8

9

10

11

12

Page 34: Seismic Remediation of Dams in California, An Engineering Geology Perspective

1

2

3

Page 35: Seismic Remediation of Dams in California, An Engineering Geology Perspective

1

2

3