seiaa karnataka checklist for building & … · b. khatha certificate 9 c. mutation copy 8 ......

104
SEIAA – KARNATAKA CHECKLIST FOR BUILDING & CONSTRUCTION PROJECTS Name of the Project: “Development of Residential Apartment with club house” Sl. No. DOCUMENTS / 1. Form -1 2. Form -1 A 3. Environmental management plan [EMP] 4. Conceptual Plan [Site Plan] 5. Topo sheet Duly marking the project site with 10Km Radius 6. Original Village Maps duly marking project site. Adjacent village maps of the project site is located at vicinity of the village boundary 7. Latest Google Map Duly marking the project site 8. CDP Duly marking the project site 9. Latest Site Photographs 10. Land Documents a. Sale Deed b. Khatha Certificate c. Mutation Copy d. Land allotment Letter in case of KIADB/SEZ NA e. Survey Sketch, Podi etc., f. R.T.C g. Joint development agreement if Applicable h. Other-GPA i. Gazette Notification regarding land acquisition under section 4(1) & 4 (6) of the Karnataka Land revenue Act in case of Area development/ Township Projects NA j. List of Survey No's and Extent in case of Area development/ Township Projects NA k. Disputes if any and copy of documents/ orders there off 11. Copy of earlier E.C/Sanction Plan in case of Expansion and Modification Projects 12. Certified report of the status of compliance of the conditions stipulated in the E.C from the regional office of MoEF& CC NA 13. Latest Traffic study Report 14. Comparative statement of the project profile between the existing and the proposed with difference thereof in case of Expansion and Modification project NA 15. Copy of Clearance obtained from other Regulatory Authority a. NOC regarding water supply from the competent Authority-Acknowledgment copy b. NOC from Airport Authority c. NOC from Fire and Emergency Department d. MOU regarding supply of treated water for construction a per FEE 188 ENV 2003 dated 14.08.2003 and As per NGT Direction in O.A 222 of 2014 dated 04.05.2016 with the prospective supplier and water quality analysis report e. MoU Letter/Approval letter from GAIL regarding supply of CNG for Generator set f. Applicability of CRZ Notification and Clearance /recommendations from the competent Authority NA g. Other Specify 16. Accreditation certificate for Consultant –Stay order copy enclosed 17. Letter of Authorization issued by the company, Partnership/proprietor if the authorized signatory other than the proprietor himself for filing of application before SEIAA NA 18. DD towards processing fee in accordance with G.O No. FEE 46 EPC 2013, dated 10.05.2013 amended from time to time

Upload: buibao

Post on 05-Jun-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

SEIAA – KARNATAKA

CHECKLIST FOR BUILDING & CONSTRUCTION PROJECTS

Name of the Project: “Development of Residential Apartment with club house”

Sl.

No. DOCUMENTS /

1. Form -1

2. Form -1 A

3. Environmental management plan [EMP]

4. Conceptual Plan [Site Plan]

5. Topo sheet Duly marking the project site with 10Km Radius

6. Original Village Maps duly marking project site. Adjacent village maps of the project

site is located at vicinity of the village boundary

7. Latest Google Map Duly marking the project site

8. CDP Duly marking the project site

9. Latest Site Photographs

10. Land Documents

a. Sale Deed

b. Khatha Certificate

c. Mutation Copy

d. Land allotment Letter in case of KIADB/SEZ NA

e. Survey Sketch, Podi etc.,

f. R.T.C

g. Joint development agreement if Applicable

h. Other-GPA

i. Gazette Notification regarding land acquisition under section 4(1) & 4 (6) of the Karnataka Land revenue Act in case of Area development/ Township Projects

NA

j. List of Survey No's and Extent in case of Area development/ Township Projects NA

k. Disputes if any and copy of documents/ orders there off

11. Copy of earlier E.C/Sanction Plan in case of Expansion and Modification Projects

12. Certified report of the status of compliance of the conditions stipulated in the E.C from

the regional office of MoEF& CC

NA

13. Latest Traffic study Report

14. Comparative statement of the project profile between the existing and the proposed with

difference thereof in case of Expansion and Modification project

NA

15. Copy of Clearance obtained from other Regulatory Authority

a. NOC regarding water supply from the competent Authority-Acknowledgment copy b. NOC from Airport Authority

c. NOC from Fire and Emergency Department

d.

MOU regarding supply of treated water for construction a per FEE 188 ENV 2003 dated

14.08.2003 and As per NGT Direction in O.A 222 of 2014 dated 04.05.2016 with the

prospective supplier and water quality analysis report

e. MoU Letter/Approval letter from GAIL regarding supply of CNG for Generator set

f. Applicability of CRZ Notification and Clearance /recommendations from the competent

Authority NA

g. Other Specify

16. Accreditation certificate for Consultant –Stay order copy enclosed

17. Letter of Authorization issued by the company, Partnership/proprietor if the authorized

signatory other than the proprietor himself for filing of application before SEIAA

NA

18. DD towards processing fee in accordance with G.O No. FEE 46 EPC 2013, dated

10.05.2013 amended from time to time

SEIAA – KARNATAKA

CHECK LIST FOR BUILDING & CONSTRUCTION PROJECTS

Sl. No. PARTICULARS INFORMATION

1. Name & Address of the Project

Proponent

Mr. K. S. Satyanarayana Reddy

Chief Executive Officer,

M/s. DSR Infrastructure Pvt. Ltd.

No. 220, “DSR DIYA ARCADE,

1st

Floor, 9th

Main Road,

H. R. B. R. Layout 1st

Block, Kalyan Nagar,

Bengaluru – 560 043

2. Name & Location of the Project

“Development of Residential Apartment with club

house”

At Khatha No. 48/2807/29-A,

Site No. 29-A,

Karnataka Housing Board Layout,

Yelahanka New Town,

Bengaluru North Taluk,

Bengaluru

3. Co-ordinates of the Project Site Latitude : 13 Deg 06 Min 24.74 Sec N

Longitude : 77 Deg 34 Min 51.18 Sec E

4. ENVIRONMENTAL SENSITIVITY

a.

Distance from periphery of nearest

Lake and other water bodies (Lake,

Rajakaluve, Nala etc.,)

Puttenahalli lake is 460m away from the project site

boundary

b.

Type of water body at the vicinity of

the project site and Details of Buffer

provided as per NGT Direction in

O.A 222 of 2014 dated 04.05.2016,

if Applicable.

Puttenahalli lake is 460m away from the project site

boundary

5. TYPE OF DEVELOPMENT

a.

Residential Apartment / Villas /

Row Houses / Vertical Development

/ Office / IT/ ITES/ Mall/ Hotel/

Hospital /other

Residential Apartment

b. Residential Township/ Area

Development Projects

NA

6. Plot Area (Sqm) 8,989.37 Sqm

7. Built Up area (Sqm) 37,512.5 Sqm

8.

Building Configuration [ Number of

Blocks / Towers / Wings etc., with

Numbers of Basements and Upper

Floors]

Proposed project is coming up with 212 No. of

residential units sprawled across 2B+GF+13UF &

club house in GF.

9. Number of units in case of

Construction Projects

212 No. of residential units

10.

Number of Plots in case of

Residential Township/ Area

Development Projects

NA

11. Project Cost (Rs. In Crores) Rs. 55 Crores

12. Recreational Area in case of -

Residential Projects / Townships

13. DETAILS OF LAND USE (SQM)

a. Ground Coverage Area 2,605.63 Sqm

b. Kharab Land -

c.

Total Green belt on Mother Earth

for projects under 8(a) of the

schedule of the EIA notification,

2006

2349.99 Sqm

d. Internal Roads & Hardscape 2,278.20 Sqm

e. Paved area -

f. Others Specify Road widening area = 1238.28 Sqm

Surface parking = 517.27Sqm

g.

Parks and Open space in case of

Residential Township/ Area

Development Projects

-

h. Total 8989.37Sqm

14. DETAILS OF DEMOLITION DEBRIS AND / OR EXCAVATED EARTH

a.

Details of Debris (in cubic

meter/MT) if it involves Demolition

of existing structure and Plan for re

use as per Construction and

Demolition waste management

Rules 2016, If Applicable

Existing sheds will be demolished; brick bat waste of

245cum and Concrete waste of 61cum will be used

within the site.

b.

Total quantity of Excavated earth

(in cubic meter)

15,634 m3

c.

Quantity of Excavated earth propose

to be used in the Project site (in

cubic meter)

15,634 m3

d. Excess excavated earth (in cubic

meter)

-

e.

Plan for scientific disposal of excess

excavated earth along with

Coordinate of the site proposed for

such disposal

Excavated soil is used within the project site

15. WATER

I. Construction Phase

a. Source of water

Domestic water requirement will be sourced from

External Tanker water suppliers & for construction

activities sourced from STP tertiary treated water

b. Quantity of water for Construction

in KLD

18 KLD

c. Quantity of water for Domestic

Purpose in KLD

7.5 KLD

d. Waste water generation in KLD 7.1 KLD

e. Treatment facility proposed and

scheme of disposal of treated water

Domestic sewage generated during construction phase

will be discharged to UGD

II. Operational Phase

a. Total Requirement of Water in

KLD

Fresh 103 KLD

Recycled 54 KLD

Total 157 KLD

b. Source of water BWSSB

c. Waste water generation in KLD 141 KLD

d. STP capacity 145 KLD

e. Technology employed for Treatment Sequential Batch Reactor (SBR) Technology

f. Scheme of disposal of excess treated

water if any

Excess 57 KLD will be used for avenue plantation/

construction work.

16. INFRASTRUCTURE FOR RAINWATER HARVESTING

a.

Capacity of sump tank to store Roof

run off

100 m3

b. No's of Ground water recharge pits 15 Nos.

17. Storm water management plan

Internal garland drains will be provided within the site

in order to carry out the storm water into the recharge

pits and will be managed within the site, excess runoff

will be routed in to the external storm water drain.

18. WASTE MANAGEMENT

I. Construction Phase

a. Quantity of Solid waste generation

and mode of Disposal as per norms

The domestic solid wastes will be minimal as there is

no provision of labor colony; the generated domestic

solid waste will be handed over to outside vendors.

Construction debris -38m3

This will be reused within the site for road and

pavement formation

II. Operational Phase

a.

Quantity of Biodegradable waste

generation and mode of Disposal as

per norms

332 kg/day

This will be segregated at household levels and will be

processed in proposed organic waste converter.

b.

Quantity of Non- Biodegradable

waste generation and mode of

Disposal as per norms

222kg/day

Recyclable wastes will be handed over to authorized

waste recyclers

c.

Quantity of Hazardous Waste

generation and mode of Disposal as

per norms

Waste Oil Generation : 0.364 L/ running hour of DG

Hazardous wastes like waste oil from DG sets, used

batteries etc. will be handed over to the authorized

hazardous waste recyclers.

d.

Quantity of E waste generation

waste generation and mode of

Disposal as per norms

E-Wastes will be collected separately & it will be

handed over to authorized E-waste recyclers for

further processing.

19. POWER

a.

Total Power Requirement -

Operational Phase

1,225 kW

b. Numbers of DG set and capacity in

KVA for Standby Power Supply

750 kVA – 2 Nos.

c. Details of Fuel used for DG Set 314.28 L/hr

d.

Energy conservation plan and

Percentage of savings including plan

for utilization of solar energy as per

ECBC 2007

1) Solar heaters

2) Solar lightings

3) LED

4) Cu. Wound transformer

The overall energy savings is around 26.69 %

20. PARKING

a. Parking Requirement as per norms 250 Nos.

b.

Level of Service (LOS) of the

connecting Roads as per the Traffic

Study Report

Doddaballapura Rd Existing Changed

Towards

Doddaballapur

B A

Towards Yelahanka C B

c. Internal Road width (RoW) 6 m

28

Annexure – 1(a): Land use details

Existing land use:

The land use pattern planned for the Planning District 3.07 Yelahanka for the

planning year 2015 is as enumerated in the following table. It is observed that the

proposed project site is located in Mutation Corridor zone. The overall land use

proposed for the contained planning district as per the Revised Master plan (RMP)-

2015, is shown in the above fig.

PROJECT

SITE

29

Land use Allocation as per RMP - 2015

Land Use Area in

Hectare % of Total

Residential (main) 1750.27 55.24

Residential (Mixed) 103.30 3.26

Commercial (Central) - -

Commercial (Business) 1.54 0.05

Mutation Corridor 44.24 1.40

Commercial Axes 19.08 0.60

Industrial 220.07 6.95

High Tech - -

Public and Semi Public 282.11 8.90

Green (Parks & open Spaces) 310.19 9.79

Traffic & Transportation 398.38 12.57

Public utilities 39.10 1.23

Unclassified - -

Total 3168.29 100.00

30

Aerial view covering 500 m radius

Latitude : 13 Deg 06 Min 24.74 Sec N

Longitude : 77 Deg 34 Min 51.18 Sec E

31

Topo map covering 10km radius

10 km

PROJECT

SITE

Scale: 1cm: 0.5km 20cm: 10km

TOPO SHEET NOS.:

57G12 & 57G8

32

Table: Land Use within the site

Sl. No. Land use Area in Sqmt In %

I Total Site Area 8989.37

Road widening area 1238.28 II Net Site area 7751.09 100

Land use Breakup in Percentage (%)

1. Ground coverage area 2605.63 33.62 2. Landscape area 2349.99 30.32 3. Drive way area 2278.20 29.39 4. Surface parking 517.27 6.67

Annexure 1(b): Views of the project site

33

Annexure 1(c): Geotechnical Report

34

Annexure 1(d): Floor wise distribution of Residential Apartment

Sl. No. Floors No. of units

1. Basement 2 00

2. Basement 1 00

3. Ground floor 04 units+ Club

House

4. First floor 16

5. Second floor 16

6. Third floor 16

7. Fourth floor 16

8. Fifth floor 16

9. Sixth floor 16

10. Seventh floor 16

11. Eighth floor 16

12. Ninth floor 16

13. Tenth floor 16

14. Eleventh floor 16

15. Twelfth floor 16

16. Thirteenth floor 16

17. Terrace floor --

Total 212

35

Annexure 1(e): Waste Management

CONSTRUCTION PHASE:

1. SOLID WASTE GENERATION

Construction waste is generated during construction works. It mainly consists

of earth, stones, bricks, inert and non-biodegradable material such as concrete,

plaster, metal, wood, plastics etc & small quantity of domestic solid waste. The

retrievable items such as bricks, wood, metals are recycled; the domestic waste will be

segregated and will not be allowed to mix with construction waste. The construction

earth and other wastes will be used for landscaping within the site premises.

2. DOMESTIC SEWAGE

The domestic sewage generated would be is about 7.1 KLD during construction;

which will be discharged to existing UGD.

OPERATION PHASE:

1. SOLID WASTE GENERATION

The solid wastes generated during operation phase can be categorized under

three groups:

Wet Garbage like Food waste, Lawn mowing wastes etc.

Dry Garbage such as Paper, Plastic, Bottles, etc.

Sludge from Sewage Treatment Plant (STP)

Domestic/Residential Waste:

This category of waste comprises the solid wastes that originate from single and

multi – family household units. These wastes are generated as a consequence of

household activities such as cooking, cleaning, repairs, hobbies, redecoration, empty

containers, packaging, clothing, old books, writing/new paper, and old furnishings.

Households also discard bulky wastes such as furniture and large appliances which

cannot be repaired and used.

Central Pollution Control Board (CPCB) has sponsored a survey to ascertain the

status of municipal solid waste disposal in metro cities, Class-I cities and Class-II

36

towns of India. As per the survey, the per capita generation of solid waste was found to

vary from 0.019 kg/day to 0.747 kg/person/day. A nominal value estimated for

Bengaluru is 0.1 to 0.5 kg/person/day and the same has been considered to estimate

the quantity of domestic solid waste generated due to this proposed project.

The quantity and typical characteristics of domestic solid waste likely to be

generated during operational phase are given in following table. The composition of

garbage in India indicates lower organic matter and high ash or dust contents. It has

been estimated that recyclable content in solid wastes varies from 13 to 20% and

combustible material is about 80-85%.

Quantity and characteristics of Domestic Solid waste

Quantity per day 554 kg

Physical Characteristics Range (% by weight)

Paper 0.81

Plastic 0.5-0.9

Metals 0.3-0.9

Glass 0.3-0.9

Ash, Fine Earth, Stones 25-45

Vegetables, Leaves 40-75

Chemical

Characteristics Range (% by weight)

Moisture content 40-45

Total nitrogen 0.5-0.65

Phosphorous (as P2O5) 0.5-0.85

Potassium (as K2O) 0.7-0.8

Organic matter 32-40

Calorific value (kcal/kg) 800-1050

Source: Nationwide survey sponsored by CPCB to ascertain the status of municipal

solid waste disposal in Indian cities

37

GENERATION:

Sl. No.

Description Population Per capita

considered in kg/Day

Total Waste kg/day

Organic Waste kg/day

In-Organic Waste kg/day

Residential & Club house

1. Residential

Apartment

1060

(212 units

*5persons)

0.5 kg/day/person 530 318 212

2. Club House 159

(15% of Total population)

0.15kg/day/person 24 14 10

Total 554 332 222

STP Sludge 7

The total quantity of solid wastes generated from the proposed project will be

554 kg/day, which will be disposed off safely.

Management:

Biodegradable wastes:

Biodegradable wastes will be segregated at household levels and will be

processed in proposed organic waste converter.

Non-biodegradable Wastes:

The recyclable portion like plastics, glass, metals etc. will be given to the waste

recyclers.

Hazardous wastes like waste oil from DG sets, used batteries etc. will be

handed over to the authorized hazardous waste recyclers.

E-Wastes will be collected separately & it will be handed over to authorized E-

waste recyclers for further processing.

38

2. SEWAGE TREATMENT PLANT

The sewage generated is about 141 KLD, 90% of the domestic water

requirement. This sewage will be treated in a Sewage Treatment Plant with designed

capacity of 145 KLD using Sequential Batch Reactor Technology. Sufficient area for

this plant has been earmarked in the layout plan. The treated water will be utilized for

secondary purposes like gardening & for flushing.

Following is the treatment scheme for 145 KLD of sewage. Various treatment

units which have been envisaged in this sewage treatment plant are explained below.

Table: Raw Sewage Characteristics

pH 6-8.5

Suspended Solids 150 mg/L

BOD5 250-300 mg/L

COD 400-600 mg/L

Oil & Grease 5 – 10 mg/L

NH4-N 20 mg/L

N- Total 30 mg/L

Treatment Methodology:

The methodology adopted for treatment of domestic sewage is based on

Sequencing Batch Reactor (SBR) Technology and preliminary treatment for screening,

followed with tertiary treatment by filtration & disinfection.

The system is designed for operating up to a maximum of 3 cycles in 24 hours

period.

DESIGN:

1. Bar Screen Chamber:

The floating and suspended matter is removed in this unit. The Bar rack with

following dimensions will be provided to reduce the load on the subsequent treatment

units.

Velocity: 0.6 m/s

Angle of Inclination: 60 degree.

Size: 0.6 m X 1.5 m X 1.0 m

39

2. Equalization Unit:

This unit acts as both collection sump and equalization unit. In this, flow will

be equalized to have a uniform concentration.

Design:

Flow - 145m3/day

Average flow hour - 145/17 = 8.53 m3/hr

Provided equalization tank with a HRT of 8 hours (holding tank)

Volume required - (145/17)*8 = 68.23 m3

Provided a tank of 70,000 Lt. Capacity

Tank dimensions - 3.8m X 3.7m X 5.0m

Free board - 0.5 m

3. Sequencing Batch Reactor:

A sequencing batch reactor (SBR) is a Fill – and – Draw Activated – Sludge

treatment system. The unit processes involved in the SBR and conventional activated

– sludge systems are identical. Aeration and sedimentation /clarification are carried

out in both systems. However, there is one important difference. In conventional

plants, the processes are carried out simultaneously in separate tanks, whereas in

SBR operation the processes are carried out sequentially in the same tank.

Process Description:

As currently used, all SBR systems have five steps in common that are carried

out in sequence as follows:

1. Fill

2. React (aeration)

3. Settle (sedimentation/clarification

4. Draw (decant)

5. Idle

Sludge wasting is another important step in the SBR operation that greatly

affects performance. Wasting is not included as one of the five basic process steps

because there is no set time period within the cycle dedicated to wasting. The amount

and frequency of sludge wasting is determined by performance requirements, as with a

conventional continuous – flow system. In a SBR operation, sludge wasting usually

occurs during the settle or idle phases. A unique feature of the SBR system is that

40

there is no need for a return activated – sludge (RAS) system. Because both aeration

and settling occur in the same chamber, no sludge is lost in the react step, and none

has to be returned from the clarifier to maintain the sludge content in the aeration

chamber.

Design:

Average Flow - 145m3/day

Average BOD Load - 36kg/day

No of tanks - 1 No

Fill time - 4 hr

React time - 3 hr

Total aeration time - 5 hr

Settle time - 0.5 hr

Decant Time - 0.5 hr

Cycle Time - 8 hr

Total SRT - 17 d

Tank Volume - 81 m3

Size of the tank - 4.5m X 4.5m X 4m

Fill Volume/Cycle - 48.3 m3

Fill Volume/tank volume - Ratio 0.6

Decant depth - 2.4 m

MLSS - 4000 mg/l

F/M - 0.07

Volumetric BOD load - 0.45kg/m3.d

Decant pumping rate - 1.61m3/min

Total aeration time/d-tank - 15 hr

Average O2 transfer rate - 3.8 kg/h

4. Decant Tank:

Design:

Flow - 145m3/ day

Average Flow - 18 hr

Detention Time - 6 hr

41

Volume required - (145/18)*6 = 48.33 m3

Tank demission - 3.5m X 3.5m X 4.0m

Free board - 0.5 m

5. Filter Press:

The sludge from the SBR tank is dewatered using Filter press.

Capacity - 10.0 cum/day

No. - 1

M.O.C - Mechanical

6. Sludge Collection Tank:

Design:

Flow - 145m3/ day

Average Flow - 18 hr

Detention Time - 6 hr

Volume required - (145/18)*6 =48.33m3

Tank demission - 3.5m X 3.5m X 4.0m

Free board - 0.5 m

7. Pressure Sand Filter & Activated Carbon Filter:

It is used to remove the minute suspended solids, including escape particulate

BOD from SBR tank.

Total flow = 145 m3/day

* Duration of pumping assumed = 12 hr/day

* Pumping rate = 12.1m3/hr

* Surface loading considered = 10 m3/ m2/hr

* Area of filter required = 1.2 m2

* Diameter of filter required = 1.3 m

* Number of sand filters = 1

* Number of carbon filters = 1

* Height of shell = 1.0 m

* Media for sand filter : Pebbles, grit, silt, gravel, and coarse & fine sand.

* Media for Carbon filter : Pebbles, gravel and activated carbon.

42

8. Chlorination:

Chlorinator Tank of 100 Liters capacity with 4–6 LPM Pump shall be

incorporated to disinfect the treated water.

9. Treated Water Sump:

To collect filtered effluent and facilitates to pump garden and other purposes.

Design:

Flow - 145m3/ day

Average Flow - 18 hr

Detention Time - 6 hr

Volume required - (145/18)*6 = 48.33 m3

Tank demission - 3.5m X 3.5m X 4.0m

Free board - 0.5 m

The STP specifications are summarized in the following Tables

Table: List of Civil Structures

The treated sewage characteristics are given in the following Table.

Table: Sewage Characteristics after Treatment

Parameters Standards

pH 6-9.0

BOD5 <10 mg/L

COD <50 mg/L

TSS <20 mg/L

NH4-N < 5 mg/L

N-Total < 10 mg /L

Turbidity < 2 NTU

Fecal Coliform < 100 MPN/100mL

The flow diagram of the STP based on SBR Technology is depicted below

Sl. No. Unit name Dimension of Unit Unit in Nos.

1. Bar Screen Chamber 0.6m X 1.5m X 1.0m 1 No.

2. Equalization tank 3.8m X 3.7m X 5.0m 1 No.

3. SBR tank 4.5m X 4.5m X 4.0m 1 No.

4. Decant tank 3.5m X 3.5m X 4.0m 1 No.

5. Sludge Collection Tank 3.5m X 3.5m X 4.0m 1 No.

6. Treated water sump 3.5m X 3.5m X 4.0m 1 No.

43

FLOW SHEET OF SEWAGE TREATMENT PLANT

Raw Sewage Bar Screen Chamber

Equalization Tank

SBR

Tank

Decant Tank

Sludge

Filter Press Sludge for

manure

Extracted water

Pressure Sand Filter

Activated Carbon Filter

Treated Water Tank

For Flushing, Gardening, Vehicle washing and common

area floor washing

Chlorine Dosing

Backwash

44

Annexure 1(f): Traffic volume

PREPARED BY,

M/s. CONSORTIA OF INFRASTRUCTURE ENGINEERS

VIJAYANAGAR, BENGALURU-40

EMAIL: [email protected]

TRAFFIC IMPACT ASSESSMENT STUDIES

FOR

PROPOSED RESIDENTIAL DEVELOPMENT

AT

YELAHANKA, DODDABALLAPURA ROAD

BANGALORE NORTH TALUK,

BANGALORE.

TIA

Before Const

During Const

Traffic Projection

After Const

Road Geometrics

Road Connectivity

Speed

Impact in V/C &

LoS

Addition Trucks

(const materials)

Requirements for

operation

Traffic data from tpt. dept

Mathematical Modeling

IRC Method for Projection

Projected Traffic

V/C & LoS

Modified

scenario

of V/C &

LoS

Parking

Traffic

Flow

Logistics

Impact

Changed

Scenario

if any for

reduction

in V/C

&LoS

Traffic

Mgm

measure

TRAFFIC IMPACT STUDIES

Traffic Volume V/C & LoS

Project Site

GOOGLE MAP

Project Site

LOCATION PLAN

SITE PLAN

Project site is located along Doddaballapura road near Rail wheel factory.

Doddaballapura road is 30.1 m RoW with (3+3) lanes CW which connects to

Doddaballapura on one side and Yelahanka on another side.

As per BDA-CDP/ NHAI, Doddaballapura road is gett ing widened to 45 m, (3+3) lanes

MCW, (2+2) lanes SR, Footpath,Drainage etc….With area separator & median.

Being a national highway, all type of vehicles including trucks will use the same RoW

way.

The project can also be accessed from other places of Bangalore city such as Yelahanka,

Ramagondanahalli ,Govindapura,NH-7, Jalahalli etc.,

However the entire traffic generated from the project will falls to Doddaballapura road.

ROAD CONNECTIVITY

Road

ROW(m)

Pavement

Surface

Condition

Street

lights

Drainage

in mRoad

RemarksCW (m)

L R Marking SignsLanes

Shoulder

Doddaballapura

Road

(3+3 lanes

divided)

30.1

Good A5 m

FCD

5 m

FCDA A -

10+10

3+3

-

ROAD GEOMETRIC SCENARIO

Note: A – Available NA – Not Available

PHOTOS OF STUDY ROADS DATE:19/05/2018

Doddaballapur

Doddaballapur roadYelahanka

Doddaballapura

Doddaballapura road (3+3lanes divided) Doddaballapura road (3+3lanes divided)

Doddaballapura road (3+3lanes divided) Doddaballapura road (3+3lanes divided)

Yelahanka

Doddaballapura

Yelahanka

Yelahanka

Road Towards

2 Wh 3 Wh4 Wh

(C,J,V)

Buses/

LorriesTrucks

Ma

xMin

Ma

xMin

Ma

xMin

Ma

xMin

Ma

xMin

Doddaballap

ur Road

(3+3 lanes

divided)

Doddaballa

pur58 51 26 18 64 52 36 22 46 38

Yelahanka 47 42 20 14 55 40 28 17 42 34

SPEED SPECTRUM MEASURED FOR THE STUDY ROAD (KMPH)

Time 2Wh 3Wh 4Wh B/L Trucks Total V/C

7:00-8:00 am 187 (94) 21 (16) 79 (79) 25 (75) 8 (32) 320 (295) 0.09

8:00-9:00 am 268 (134) 29 (22) 105 (105) 42 (126) 12 (48) 456 (435) 0.13

9:00-10.00 am 379 (190) 33 (25) 216 (216) 56 (168) 14 (56) 698 (654) 0.20

10:00-11:00

am404 (202) 56 (42) 172 (172) 88 (264) 25 (100) 745 (780) 0.24

4:00-5:00 pm 225 (113) 17 (13) 86 (86) 31 (93) 10 (40) 369 (344) 0.10

5:00-6:00 pm 458 (229) 62 (47) 160 (160) 72 (216) 17 (68) 769 (720) 0.22

6:00-7:00 pm 320 (160) 59 (44) 186 (186) 63 (189) 28 (112) 656 (691) 0.21

7:00-8:00 pm 281 (141) 47 (35) 143 (143) 51 (153) 34 (136) 556 (608) 0.18

REAL TIME TRAFFIC SCENARIO ALONG DODDABALLAPUR ROAD

TOWARDS DODDABALLAPURA (3-LANES)

Note: The highest peak observed is 780 PCU’s/hr as per IRC-106:1990 dur ing 10:00 am to

11:00 am

The traffic projections are made as per IRCconsidering the vehicular growth taking place from past

5 years.

VEHICLE COMPOSITION AND TRAFFIC FLOW DISTRIBUTION ALONG

DODDABALLAPUR ROAD TOWARDS DODDABALLAPURA (3-LANES)

2Wh

54%

3Wh

8%

4Wh

23%

B/L

12%

Trucks

3%

295435

654780

344

720 691608

0

200

400

600

800

1000

7.00-8.00 am 8.00-9.00 9:00-10:00 10:00-11:00 4:00-5:00 pm 5:00-6:00 6:00-7:00 7:00-8:00

PC

U's

/hr

TIME

0.09

0.13

0.20

0.24

0.10

0.22 0.210.18

0.00

0.05

0.10

0.15

0.20

0.25

7.00-8.00 am 8.00-9.00 9:00-10:00 10:00-11:00 4:00-5:00 pm 5:00-6:00 6:00-7:00 7:00-8:00

V/C

Time

VARIATION OF V/C OVER STUDY PERIOD

Note: The highest peak observed is 1406 PCU’s/hr as per IRC-106:1990 dur ing 5:00 pm to 6:00 pm.

REAL TIME TRAFFIC SCENARIO ALONG DODDABALLAPUR ROAD

TOWARDS YELAHANKA (3-LANES)

Time 2Wh 3Wh 4Wh B/L Trucks Total V/C

7:00-8:00 am 286 (143) 24 (18) 135 (135) 67 (201) 11 (44) 523 (541) 0.16

8:00-9:00 am 327 (164) 37 (28) 182 (182) 138 (414) 14 (56) 698 (843) 0.26

9:00-10.00 am 578 (289) 48 (36) 246 (246) 86 (258) 17 (68) 975 (897) 0.27

10:00-11:00

am490 (245) 64 (48) 405 (405) 142 (426) 22 (88) 1123 (1212) 0.37

4:00-5:00 pm 304 (152) 32 (24) 339 (339) 73 (219) 27 (108) 775 (842) 0.26

5:00-6:00 pm648

(324)54 (41) 467 (467) 130 (390) 46 (184) 1345 (1406) 0.43

6:00-7:00 pm 536 (268) 33 (25) 496 (496) 105 (315) 53 (212) 1223 (1316) 0.40

7:00-8:00 pm 487 (244) 28 (21) 384 (384) 94 (282) 64 (256) 1057 (1187) 0.36

VEHICLE COMPOSITION AND TRAFFIC FLOW DISTRIBUTION ALONG

DODDABALLAPUR ROAD TOWARDS YELAHANKA (3-LANES)

2Wh

48%

3Wh

4%

4Wh

35%

B/L

10%

Trucks

3%

541

843 897

1212

842

1406 13161187

0

200400

600

8001000

1200

14001600

7.00-8.00

am

8.00-9.00 9:00-10:00 10:00-11:00 4:00-5:00

pm

5:00-6:00 6:00-7:00 7:00-8:00

PC

U's

/hr

TIME

0.16

0.260.27

0.37

0.26

0.43 0.400.36

0.00

0.05

0.10

0.15

0.20

0.25

0.30

0.35

0.40

0.45

7.00-8.00 am 8.00-9.00 9:00-10:00 10:00-11:00 4:00-5:00 pm 5:00-6:00 6:00-7:00 7:00-8:00

V/C

Time

VARIATION OF V/C OVER STUDY PERIOD

Road Towards V C Existing V/C LOS

Doddaballapur

Road

(3+3 lanes divided)

Doddaballapur 780 3300 0.24 B

Yelahanka 1406 3300 0.43 C

V/C LOS Performance

0.0 - 0.2 A Excellent

0.2 - 0.4 B Very Good

0.4 - 0.6 C Good

0.6 - 0.8 D Fair/Average

0.8 - 1.0 E Poor

1.0& Above F Very Poor

REAL TIME TRAFFIC SCENARIO FOR STUDY ROADS

V= Volume in PCU’s/hr, C= Capacity in PCU’s/ hr, LOS = Level of Service

Note: IRC is accepting the fact that , in Indian roads the real congestion star ts when V/ C ratio is >1, i.e., for

forced flow. Till this limit the road is free for traffic movement without any impediments. Hence it is

acceptable as normal upto V/ C =1 and the per formance will be taken as good only.

The addition of 8 Lorr ies per day carrying construction vehicle do not change any

significantly the traffic flow. Hence OK.

V/ Cdur ing construction (Lor r ies) = 0.24, 0.43.

The present level of service will remain “B & C” along Doddaballapura Road towards

Doddaballapur and Yelahanka respectively.

Number of trucks coming to the site (Off peak hours).

Day time –8 no’s.

The addit ion do not make any significant change for traffic movement at any given time.

Vehicles car rying construction mater ials will be well covered to prevent any spillage.

Vehicles hired for construction mater ial will be in good condit ion and conforms to noise

and air emission standards.

Vehicles will operate only dur ing non peak hours.

DURING CONSTRUCTION

Type No. of Units No. of Cars Per UnitTotal

Nos

Residential

212No. of units B/ W 50

to 225 Sqm212

Visitor ’s car parking (10%) 21

Club House (845.12

sqmt) 1 car / 50sqmt 17

Total no. of car parking required (Including visitor parking) 250

Parking provided 251

PARKING LOGISTICS

FLOW CHART OF TRAFFIC/ TRIPS DISTRIBUTION

From project

100 %

To Doddaballapura Road

40%

To Yelahanka

60 %

Doddaballapura Road

100 %

TRAFFIC FLOW LOGISTICS

Since the activity is Residential, the vehicles will move from & to the Project between

8:00 am to 11:00 am as egress & 6:00 pm to 9:00 pm as ingress.

Total traffic generated from this project = 251 PCU’s.

Therefore, the hour ly volume in PCU’s will be 251/ 3 = 84 PCU’s/hr.

This hour ly generated traffic of 84 PCU’s/hr will be distr ibuted as follows.

out of 84 PCU’s/hr, 60% of the traffic will moves along Doddaballapura Road towards

Yelahanka and 40% of the traffic will moves towards Doddaballapura.

i.e.,60% x 84 = 50 PCU’s/hr will move along Doddaballapura road towards Yelahanka.

40% x 84 = 34 PCU’s/hr will move along Doddaballapura road towards

Doddaballapura.

Road Towards

Existing scenario Modified traffic scenario

V C V/C LOS V V/C LOS

Doddaballap

ur Road

(3+3 lanes

divided)

Doddaballapur 780 3300 0.24 B780+34

= 8140.25 B

Yelahanka 1406 3300 0.43 C1406+50 =

14560.44 C

MODIFIED V/C AND LOS AFTER ADDING GENERATED

TRAFFIC TO EXISTING TRAFFIC

PEDESTRIAN FLOW MANAGEMENT & SAFETY

Pedestr ians are considered as most Vulnerable Road Users (VRU) as the accidents are

increasing on pedestr ians. Hence pedestr ians safety must be considered as top pr ior ity

in traffic engineer ing.

As per IRC, a minimum of 1.8 m wide neatly paved, well i lluminated and leveled footpath

must be made available for pedestr ians.

The under ground drain is covered by slabs and used for pedestr ian movement .

Presently due to very less pedestr ians use the footpath being a highway, hence they are

very safe.

30.1 m wide road is gett ing widened to 45 m as said ear lier and Exist ing footpath will be

continued

This width can accommodate more than 5040 ped/ hr in each direction of footpath

being more than 5m wide.

RECOMMENDED PEDESTRIAN SIDE WALK CAPACITY AND

LEVEL OF SERVICE (IRC 103-2012)

Width of side

walk in

(meter)

Design Flow in number of Person per hour

In Both Direction All in one direction

LOS B LOS C LOS B LOS C

1.8 1350 1890 2025 2835

2.0 1800 2520 2700 3780

2.5 2250 3150 3375 4725

3.0 2700 3780 4050 5670

3.5 3150 4410 4725 6615

4.0 3600 5040 5400 7560

PROJECTED TRAFFIC FOR NEXT THREE YEARS BASED ON

INDIVIDUAL VEHICULAR GROWTH AS PER IRC : 37-2001

(EXPONENTIAL GROWTH IS CONSIDERED)

Road

Vehicle

Type2Wh 3Wh 4Wh

Buses/

LorriesTrucks

Total% Growth

8.95 13.90 6.26 7.71 0.50Towards

Doddaballapur

Road

(3+3 lanes

divided)

Doddaballapur522

(261)

83

(62)

206

(206)

110

(330)

25

(100)

946

(959)

Yelahanka838

(419)

80

(60)

560

(560)

162

(486)

47

(188)

1687

(1713)

Note : Consider ing the neighbor ing development if any along with traffic growth potential

based on the socio-economic growth. The equation as recommended by IRC to work out the

future generated traffic.

MODIFIED V/C & LOS

Road Towards

Projected Traffic for next

Three years

Modified V/C and LOS after

adding the generated traffic

V C V/C LOS V C V/C LOS

Doddaballapur

Road

(3+3 lanes

divided)

Doddaballapur 959 3300 0.29 B959+34 =

9933300 0.30 B

Yelahanka 1713 3300 0.52 C1713+50

= 17633300 0.53 C

BDA-CDP MAP

Project site

PROJECT

SITE

CHANGED SCENARIO-1 (ROAD WIDENING)

Note: As per BDA-CDP map, Doddaballapur road is getting widened to 45m from 30.1 m with

6 lanes main CW (3+3) lanes, 2 lane Service road on both direct ion, with central

median, footpath, shoulder etc with total of 5 lanes on each side.

Road Towards

Modified V/C and LOS after

adding the generated traffic

Changed scenario-1 after

Road widening

V C V/C LOS V C V/C LOS

Doddaballap

ur Road

Doddaballapur 993 3300 0.30 B 993 5500 0.18 A

Yelahanka 1763 3300 0.53 C 1763 5500 0.32 B

CONSOLIDATED V/C AND LEVEL OF SERVICE FOR

CHANGED SCENARIOS

Road Towards

Existing

traffic

scenario

Changed

V/C and

LOS by

adding

generated

traffic

Projected

traffic after

Three years

Modified

V/C and

LOS by

adding the

generated

traffic

Changed

Scenario -1,

After Road

Widening

V/C LOS V/C LOS V/C LOS V/C LOS V/C LOS

Doddaballa

pur road

Doddaballapur 0.24 B 0.25 B 0.29 B 0.30 B 0.18 A

Yelahanka 0.43 C 0.44 C 0.52 C 0.53 C 0.32 B

TRAFFIC AND PEDESTRIAN MANAGEMENT IN FRONT OF

THE PROJECT SITE (EXISTING)

TRAFFIC AND PEDESTRIAN MANAGEMENT IN FRONT

OF THE PROJECT SITE (AFTER WIDENING)

TRAFFIC MANAGEMENT MEASURES & INTERVENTIONS

As per CDP map, Doddaballapura road is gett ing widened to 45 m from 24 m with 6

lanes main CW (3+3 lane), 2 lane Service road (with total of 5 lanes) on both direction,

with central median, footpath, shoulder etc

All precautionary measures are ensured for the safety of construction laborers while

working at the site.

Adequate sign & guide posts for traffic as per IRC (Indian Roads Congress) or ITE

(Instituteof Transpor tation Engineers USA) to be installed along the study roads.

Road marking (edge markings in yellow and lane markings in broken white), STOP lines

etc must be clear ly painted so as to guide the dr ivers along the study Roads.

45

Annexure – 2(a): Water Demand

WATER DEMAND DURING CONSTRUCTION

Water for construction will be sourced from BWSSB STP tertiary treated water

Table-2a.1 shows details of the water requirement during construction period.

The water used for construction gets consumed into chemical reactions with

cement and also partly gets evaporated. Hence, there will be no wastewater generation

from curing or mixing processes. However, there will be discharge of domestic

wastewater to the tune of 7.1m3/day. The domestic wastewater will be discharged to

existing UGD.

Table 2a.1: Water Requirement for construction purpose

Sl. No. Activity Quantity of Works (m3)

Rate of water usage m3/m3

Total requirement (m3)

1. Concrete curing 18,005 0.9 16,204

2. Mortar mixing and

curing for block work

83 0.8 67

3. Mortar mixing and

curing for plastering

145 0.07 10

4. Floor finishes 1,780 0.05 89

5. Sprinkling for dust

suppression -- -- 289

6. Roof works 1, 385 0.05 69

Total 16,728

7. Domestic 250

Labours/day 30 L/day 7.5 KLD

Construction Period 36 Months

No. of Working Days /Month 26

Total No. of Working Days 936

Average Water Consumption Per Day (for Construction) 17.87 ≈ 18 KLD

Average Water Consumption Per Day (for Domestic) 7.5 KLD

Source: Civil Engineering Handbook and Indian Building Handbook

46

WATER REQUIREMENT DURING OPERATION

Sources of Water:

The water will be sourced from the BWSSB. The detailed total water

requirement, based on the number of residential units and other facilities to be

provided, during operation phase is estimated as in below Table 2a.2.

Table 2a.2: Water Requirement Break up

The total water requirement for the project during operation phase is around

157 KLD. It is proposed to use the treated sewage for secondary purposes such as

toilet flushing to the amount of 54KLD. Hence, the net fresh water demand would be

about 103 KLD which will be supplied by BWSSB. During the rainy season the net

Sl. No. Purpose Particulars Total in KLD

I. Total Water Requirement 212 units x 5 Personnel x

135 LPCD 143

II.

Total Water Requirement for club House

(Considering 15% of total population – 159Nos.)

159 Personnel x 45 LPCD 7

III. Total Water Requirement for Maintenance Staff & visitors

159 Personnel x 45 LPCD 7

Total Water Requirement 157

1. Fresh water requirement for units 212 units x 5 Personnel x

90 LPCD 95

2. Fresh Water Requirement for club

House 159 Personnel x 25 LPCD 4.0

3. Fresh Water Requirement for

Maintenance Staff & visitors 159 Personnel x 25 LPCD 4.0

Net Domestic Water Requirement 103

1. Recycled Water for flushing 212 units x 5 Personnel x

45 LPCD (-) 48

2. Club House – Recycled Water for

flushing 159Personnel x 20 LPCD (-) 3

3. Maintenance Staff & visitors - Recycled Water for flushing

159 Personnel x 20 LPCD (-) 3

Total Flushing Water Requirement (-) 54

Total Water Requirement = 157 KLD

47

fresh water requirement will be fulfilled by harvested roof rain water. Water balance

chart during the operation phase is shown in the Fig. 2a.1.

Fig. 2a.1: WATER BALANCE CHART

Total Water Demand For

Entire Project

157 KLD

Sewage Generated @ 90%

141 KLD

STP Capacity –

145 KLD

Excess to Construction

works/Avenue plantation

- 57 KLD

Rec

yclin

g w

ater

Vehicle Cleaning

Purpose -8KLD

Floor Washing

Purpose - 3 KLD

STP Treated Water

141 KLD

For Landscaping

– 19 KLD

D

Fresh

Water

103 KLD Flushing

Water 54 KLD

BWSSB /

Harvested Roof Rain

water during the Rainy

season

48

Annexure 2(b):

Construction Material Resources Requirement

Annexure 5(a):

Emission load from DG set and construction equipments during

construction phase using HSD

Pollutant

Concrete

Mixers

(2 x 3.73

kW/Hr)

Concrete

Pump

(2 x 44.74

kW/Hr)

JCB

Excavator

(1 x 50

kW/Hr)

D G Set

(40kW/Hr)

Earth

Rammers

(1x3.75

kW/Hr)

NOx (@9.2 g/

KW-hr) 68.63 823.21 460 368 34.5

PM (@0.3 g /

KW-hr) 2.24 26.84 15

12 1.12

HC (@1.3 g /

KW-hr) 9.70 116.32 65

52 4.875

CO (@3.5 g /

KW-hr) 26.11 313.18 175 140 13.125

Sl. No. DESCRIPTION UNIT QUANTITY

1. Cement Bags 1,76,170

2. Ready mix concrete CMT 13,009

3. Sand CMT 13,822

4. Aggregates CMT 15,305

5. Steel MT 2,238

6. Solid Blocks Nos. 2,83,704

7. Flush shutter SMT 2,550

8. Glass SMT 3,241

9. Vitrified Tiles SMT 24,250

10. Glazed Tiles SMT 8,360

11. Aluminium KGS 29,550

12. Roof installation Brick Batcoba SMT 17,618

49

Annexure 5(b):

Emission Parameters of the Air Pollution Sources during operation

Sl. No. Stack Details DG sets

(750 KVA- 2No)

1. No. of Stacks (DG Sets) 1

2. Stack height (m) 5.5 m (ARL)

3. Stack top internal diameter (m) 0.2

4. Stack exit temperature (ºC) 536

5. Flow rate (cum/sec) 1.98

6. Stack exit velocity (m/sec) 28.05

7. NO2 emission, in g/s 3.06

8. SPM emission, in g/s 0.10

9. HC emission, in g/s 0.44

10. CO emission, in g/s 1.16

11. SO2 emission, in g/s 0.7

Annexure – A2 (a): Rainwater Harvesting Facilities

As the growth of Bengaluru city is far ahead of the rate at which the water

supply system is being upgraded, it becomes necessary to think of alternative source

of water for the daily needs for secondary purposes like washing, gardening etc. In

these lines, rain water harvesting is gaining importance and has been a part of

building by-laws.

As the project location is blessed with fairly good rainfall, it is planned to collect

the storm water at different gradients of the location. There will be rainfall runoff from

building roof-tops, roads and pavements and greenbelt area. Necessary provision will

be made to collect the quantity of rainfall runoff during the most rainy day of season.

Necessary rain harvesting pit / recharge pit at regular intervals have been envisaged.

The facilities to be established for rainwater harvesting include carriage (piping)

system, pre-treatment unit (filtration) and a storage tank.

50

Design details:

Rational formula for calculating runoff: Q= (CIA)/360

Q = Runoff in m3/sec

I = Intensity of rainfall in mm/hr.

A= Area in sqmt.

C = Co – efficient of run off as below

Intensity of rain fall = 80 mm/ hr

Runoff Coefficients:

Roof top : 1.0

Landscape/Garden : 0.3

Drive Way : 0.6

Total Roof Area : 1991.85 Sqm

Path way/road area : 2795.47 Sqm

Landscape : 2349.99 Sqm

Terrace Area Run-off:

Runoff = Q = (Terrace Area * Intensity of rain fall * Co-efficient of runoff)

(1991.85 Sqm * 0.04 m *1) = 79.67 say 80 cum

Roof rain water collection sump of capacity 100 cum will be provided and same

will be utilized for domestic purpose after prior treatment.

Total Run-off from Hardscape & driveway:

I = Intensity of rainfall : 0.04 m

A = Drive way area : 2795.47 Sqm

C = Co – efficient of runoff : 0.6

Q = Runoff = 0.6 X 0.04 X 2795.47 = 67.09 say 67 cum

Total Run-off from Landscape Area:

I = Intensity of rainfall : 0.04 m

A = Landscape area : 2349.99 Sqm

C = Co – efficient of runoff : 0.3

Q = Runoff = 0.3 X 0.04 X 2349.99 = 28.19 say 28cum

51

Therefore the total runoff from the site is: 67+ 28 = 95cum

Recharge pit calculation:

Data assumed:

Infiltration rate is 25 cm/hr = 0.25 m /hr

Recharge pit of 1.2 m diameter is considered = 1.2 m

Area of bottom surface of soak pit: πd2/4 = 1.13 m2

Area of wetted perimeter of soak pit: π x D x d = π X 3.0 X1.2= 11.3 m2

Total area of per soak pit: 1.13 + 11.3 = 12.43 m2

Total water permeability/pit/hour: 12.43 X 0.25 = 3.11cum/hr

Total number of percolation pits required: 95 /3.11= 30 Nos.

Hence, 15 Nos. of recharge pits have been provided to recharge the ground

water within the site. Excess runoff water will be routed to the external storm water

drain.

52

Annexure A3: List of Species Proposed

List of Shrubs & Ground Covers Proposed For Landscape

Sl. No Name of the Shrubs Ground Covers

1. Acalypha wilkesiana Alternanthera green

2. Allamanda yellow Bamboo grass veriegatted

3. Antigonon leptopus Belbergia

4. Cassia alata Cupeas purple

5. Hamelia patens Eranthemum nigram

6. Ixora coccinea Hemigraphis colorata

7. Murraya exotica Mentha spp

8. Nerium oleader Ocimum basilium

9. Pissonia alba Opiophogan green

10. Plumbago capensis Salvia officianalis

Sl.

No.

Name of the Species Common name In Nos.

Shading trees

1 Terminalia arjuna Arjuna tree 5

2 Pongamia pinnata Honge 5

3 Azadiracta Indica Neem Tree 5

Flowering trees

4 Bauhinia purpurea Purple camel’s foot 10

5 Cassia spectabilis Scented shower 10

6 Millingtonia hortensis Indian cork tree 10

7 Michelia champaca Champaka tree 10

8 Plumeria rubra Temple Tree 10

9 Plumeria alba Caterpillar tree 10

10 Erythrina indica Indian coral tree 10

Fruit bearing trees

11 Phyllanthus emblica Indian gooseberry 5

12 Syzygium cumini Nerale 5

13 Psidium guajava Guava 10

14 Mangifera indica Mavu 10

15 Syzygium jambos Pannerale 5

16 Annona squomosa Custard apple 5

Total 125

53

Annexure 10: ENVIRONMENTAL MANAGEMENT PLAN

10.1 INTRODUCTION

The Environmental Management Plan (EMP) is aimed at mitigating the possible

adverse impact of a project and ensuring the existing environmental quality. The EMP

converse all aspects of planning, construction and operation of the project relevant to

environment. It is essential to implement the EMP right from the planning stage

continuing throughout the construction and operation stage. Therefore the main

purpose of the Environmental Management Plan (EMP) is to identify the project

specific activities that would have to be considered for the significant adverse impacts

and the mitigation measures required.

The construction phase impacts are mostly short term, restricted to the plot

area and not envisaged on the larger scale. In the operational phase the environmental

impacts are due to continuous operation of the project, hence, the emphasis in the

Environment Management plan (EMP) is to minimize such impacts. The following

mitigation measures are recommended in order to synchronize the economic

development of the project area with the environmental protection of the region.

The emphasis on the EMP development is on the following;

Mitigation measures for each of the activities causing the environmental

impact.

Monitoring plans for checking activities and environmental parameters and

monitoring responsibilities.

Role responsibilities and resource allocation for monitoring; and

Implementation of the scheduled plan.

Environmental management plan has been discussed in the following sections

separately for Construction phase and Operational phase:

10.2 EMP DURING CONSTRUCTION PHASE

During construction phase, the activities which need to be monitored and

managed from the point of pollution are explained in detail in the subsequent

sections.

54

10.2.1 LEVELLING AND SITE CLEARANCE

The proposed project site consist of about 50 nos. of different species of trees,

removing of this vegetative cover is only in building foot print area, where construction

takes place, other peripheral vegetation will be retained as it is and majorly used for

landscaping. Existing sheds will be demolished; brick bat waste of 245cum and

Concrete waste of 61cum will be used within the site. As per the site scenario; site has

a level difference of 3.5 m, so levelling and excavation will be done for basement

preparation with of best management plan to minimize the excavated earth.

Table 10.1: Environmental Management during Levelling and Site Clearance

Environmental Impacts

Mitigation Remarks

Noise generation:

Caused due to

Excavators and

Bulldozers

Most optimum no. of operation by the

heavy equipment.

Selection of equipment with less noise

generation to be used.

The earth moving equipment shall be

periodically checked and maintained for

noise levels. The workers shall be provided

with adequate PPE such as ear plugs to

reduce impact of high noise levels.

To reduce noise level,

Equipment provided

with noise control

devices is only used.

Dust generation:

Levelling

operations results

in the emission of

the dust.

The site cleared shall be periodically

watered to reduce emission of dust

particles.

Barricades will be provided all around the

site to suppress the dust.

The workers shall be provided with PPE

such as nose masks and goggles to reduce

impact on health.

The construction water

requirement will be met

through tertiary treated

water from BWSSB STP.

55

10.2.2 TRANSPORTATION OF CONSTRUCTION MATERIALS

During the transportation of construction materials, minimum no. of vehicles

will be used. Most optimum route is planned to reduce the impact of transportation

activity on the environment.

Table 10.2: Environmental Management during Transportation

Environmental Impacts

Mitigation

Noise generation Quality fuel will be used.

Periodic maintenance of vehicles is required.

Dust generation Quality packaging of the construction materials.

Construction materials shall be covered with

tarpaulin sheets to prevent the material from

being air borne.

The vehicle speed shall be regulated.

Watering to the wheels of the construction vehicle

will be done while entering to the construction

site.

The workers transporting materials shall be

provided with PPE such as nose masks to reduce

impact of air borne dust on their health.

Vehicular

emissions

Periodic emission check for vehicles is required.

Clean fuel shall be used for vehicles.

10.2.3 CONSTRUCTION ACTIVITIES

During the construction work, the following impacts are identified to monitor

and mitigate the level of impact.

56

Table 10.3: Environmental Management during Construction

Environmental impacts

Mitigation Remarks

Noise generation Selection of less noise generating equipment.

Personnel Protective Equipment (PPE) such

as ear plugs and helmets shall be provided

for construction workers.

The working hours shall be imposed on

construction workers.

Implementation

responsibility:

Contractor –

Civil Works.

Dust generation PPE in the form of nose masks shall be

provided for construction workers.

Use of water sprays to prevent the dust from

being air borne.

Providing barricades all around the project

site.

Implementation

responsibility:

Contractor

Water Discharge

from

construction

works

Sewage generated will be discharged to

existing UGD

Implementation

responsibility:

Contractor

Air Emissions

from

construction

machinery

Periodic check and regular maintenance of

construction machinery for emissions.

Clean fuel shall be used in equipments.

Implementation

responsibility:

Contractor

10.2.3.1 WASTEWATER DISCHARGE

The sewage generated from the construction labours during construction is

estimated to be about 7.1 KLD. This will discharged to existing UGD.

10.2.3.2 DISPOSAL OF EXCAVATED EARTH

The excavated earth which is generated during construction will be reused for

development of landscape and pavement area formation therefore there will not be any

solid waste problem from the generation of excavated earth.

57

10.2.3.3 PERSONNEL SAFETY SYSTEM

It is planned to adopt the safe working practices which shall govern all

construction works undertaken throughout the project. Following Safety Aids to all

labourers will be provided:

Safety Helmets

Safety Belts

Safety Shoes

Hand gloves

Gumboots while concreting

Safety Goggles while welding/ Stone dressing etc.

Face masks and full body kit while Pest control

Implementation of Safety procedures such as:

Using proper lifting techniques.

Using Safe Scaffolds.

Hot work permits for Fabrication and welding.

BUDGETARY ALLOCATION FOR EMP DURING CONSTRUCTION

Sl. No. EMP Aspects Cost

Capital Investment In Lakh

1. Barricades all round the site 1.0

Total 1.0

During Construction Lakhs/annum

1. Purchase of water from external authorized

suppliers 3.0

2. Disposal of Solid Waste from project site 2.5

3. Plantations of saplings around the periphery

and maintenance 5.0

4. Environmental Monitoring – Air, water, Noise 1.0

5. EMP cell 2.5

Total 14

10.3 EMP DURING OPERATION PHASE

Following are the identified operational phase activities in the impact

assessment, which may have impact on the environment.

58

1. Air quality

2. Water quality

3. Noise quality

4. Solid waste disposal

5. Landscape development

6. Storm water management

10.3.1 AIR QUALITY MANAGEMENT

The air pollutants likely to be emanated from the proposed project are SPM,

SO2, NO2, HC and CO mainly due to burning of liquid fuel (HSD) in DG.

Exhaust from DG set will be emitted from stack of adequate height for

dispersion of gaseous pollutants. The green belt development is also proposed covering

about 30.32% of the net plot area. Following table presents the EMP for air quality

management during operation phase.

Table 10.4: Air Quality Management during Operation Phase

Environmental

Impacts Mitigation

DG set Equipment selected will ensure the exhaust emission

standard as prescribed as per the latest amendments

from the CPCB.

DG will be used as stand-by unit.

Periodic check and maintenance.

Ambient air

quality

Ambient air quality monitoring as per the prescribed

norms at regular interval.

10.3.2 WATER QUALITY MANAGEMENT

Water requirement of the project will be met through BWSSB, as mentioned

earlier. Water balance is presented in Annexure 2(a).

The sewage generated from the proposed project is about 141 KLD which will be

treated in the proposed STP of capacity 145 KLD. The treatment scheme for domestic

effluents generated from project has also been discussed in Annexure 2(a). The STP

59

treated water will be reused for flushing, gardening etc. Following table presents the

EMP for water quality.

Table 10.5: Water Quality Management during Operation Phase

Environmental impacts Mitigation

Effluent from domestic water

consumption

Treated with proposed state-of-the-art sewage

treatment plant to produce tertiary treated water;

this will be ultimately reused for secondary

purposes such as for flushing, gardening, vehicle

washing and for common area floor washing.

Water conservation measures will be encouraged.

10.3.3 NOISE MANAGEMENT

High noise generating units such as DG set will be provided with acoustic

enclosures. Landscape on the project boundary will further act as noise barrier and

helps in attenuation of noise. Following table presents the EMP for noise levels.

Table 10.6: Noise Management during Operation Phase

Environmental Impacts

Mitigation

Noise from DG set

area

Acoustic enclosures will be provided to DG set.

DG set will be installed in an area (utility section)

where the access will be restricted.

The use of PPE (ear plugs) will be mandatory in this

area.

Selection of equipment to ensure that the residual

noise level of < 65 dB (A).

Noise levels will be checked periodically using a noise

dosimeter.

10.3.4 SOLID WASTE MANAGEMENT

The solid wastes generated during operation phase can be categorized under

three types:

60

Wet Garbage: Food waste, Lawn mowing wastes etc

Dry Garbage : Paper, Plastic, Bottles, etc.

Sludge from Sewage Treatment Plant (STP)

The solid waste generated in the premises is estimated to be about 554 kg/day.

Out of 554 kg, 332kg (60%) will be biodegradable waste & 222kg (40%) will be

recyclable wastes. Further this biodegradable wastes will be segregated at household

levels and will be processed in organic waste converter and the recyclable wastes such

as plastic materials, glass & metal wastes will be handed over to the waste recyclers.

The sludge from the STP is estimated to be about 7 kg/day and will be used as

manure for gardening purpose.

The various mitigation measures to be adopted during collection and disposal of

wastes are as follows:

It is preferable that the container and bins used for collection of waste should

be of closed type so that the waste is not exposed and thus the possibility of

spreading of disease through flies and mosquitoes is minimized.

Collection system should be properly supervised so that quick and regular

removal of waste from the dustbin is practiced.

Door to door collection shall be done in each unit to collect the solid wastes.

The biodegradable wastes will be processed in organic waste converter,

recyclable wastes such as plastic materials, glass & metal wastes are handed

over to the waste recyclers; e-waste will collected separately and handed over to

authorize e- waste recyclers for further processing.

10.3.5 LANDSCAPE DEVELOPMENT

Vegetation is the natural extension of the soil ecosystem on a site. It can provide

summer shade, wind protection, and a low-maintenance landscape that is adapted to

the local environment.

Following approach will be adopted for vegetation and ground management.

It is planned to include an ecologically knowledgeable landscape architect as an

integral member of the design team.

61

Preservation of existing vegetation, especially native plants, will possibly be

incorporated. Avoid fencing off property where possible to make landscape available to

community increasing project integration.

Decrease paving and monoculture lawns.

Avoid replacing mature trees with young seedlings.

Protect existing plants during construction. Delineate the “drip line” around

trees and demark or fence off areas to avoid damage.

Contain heavy equipment and stockpiling areas to predefined areas.

Design new plantings as diverse communities of species well adapted to the

site. Plant native species of varying ages. Select vegetation that attracts wildlife.

Avoid invasive species and monocultures (same species, same age).

10.3.6 STORM WATER MANAGEMENT

As the project location is blessed with fairly good rainfall, it is planned to collect

the storm water at different gradients of the location. There will be rainfall runoff from

building roof-tops, roads and pavements and landscape area. Necessary provision will

be made to collect the quantity of rainfall runoff during the most rainy day of season.

Necessary rain harvesting pit /recharge pit at equal intervals around the periphery of

the site have been envisaged. A garland drains with RCC precast perforated cover will

be provided around the periphery of property. The details of the rain water harvesting

facilities are interpreted in the early section.

10.3.7 HEALTH, RISK AND DISASTER MANAGEMENT

Public health and safety

Since all the construction related activities shall be confined to the project site,

minimal health related impacts are envisaged within the project influenced area

during the construction stage.

At the project site on an average of 250 persons will be engaged, who face direct

exposure to dust and noise generated from the construction activity. This is likely to

cause health related affects such as asthma, bronchitis etc. and hearing impairments

respectively.

To minimize these anticipated impacts, suitable actions like

Use of water sprinklers to prevent dust from being air borne.

62

Providing suitable personal protective equipments (PPE) like mouth mask

with filters, nose mask, helmets etc.

Periodic health check up camp for the labourers will be arranged.

Provision of safety belts.

In case of injury, on site medical treatment and transport will be organized.

Employing a safety engineer.

Due to operation of the proposed project, there will be enhancement in public

health and safety.

Regular visit of resident medical officer to take care of the first aid and

primary medication in case of emergency for apartment occupants and

labourers.

First aid kit with primary medicines will always be available in the medical

centre.

Display of action plan and preparedness measures during emergency

situations.

Risk and disaster management plan

Disaster is an unexpected event due sudden failure of the system, external

threats, internal disturbances, earth quakes, fire and accidents. Thus an

appropriate management plan shall be incorporated.

Precautions

Once the likelihood of the disaster is suspected, preventive actions

should be undertaken by the project in-charge.

Conditional maintenance of equipments, materials, and expertise for use

during emergency.

The electrical systems shall be provided with automatic circuit breakers

activated by over current.

Fire extinguishers are provided at pre-notified locations inside the

apartments.

Proper escape routes are planned and displayed in the public domain.

Selected representatives are given proper training to guide other

inhabitants during fire accidents.

63

Periodic awareness programme is conducted for the occupants on their

roles during emergency situations.

Important telephone numbers like police authorities, fire department and

hospitals etc. of use during emergency situations are made available.

10.3.8 EMP IMPLEMENTATION SCHEDULE

Phased according to the priority, the implementation schedule is presented in

below table.

Table 10.7: Implementation Schedule for EMP

Sl. No. Recommendations Requirement

1. Air pollution control measures Before commissioning of respective units

2. Water pollution control measures Before commissioning of the project

3. Noise control measures Along with the commissioning of the

project

4. Solid waste management During commissioning of the project

5. Green belt development Stage-wise implementation

The responsibility of EMP implementation lies with the project promoter for a

period of 3 years. Once the project is established, the EMP responsibility will be

properly handed over with clearly defined procedures and guidelines.

10.3.9 ENVIRONMENTAL MONITORING ROUTINES

A comprehensive monitoring programme is suggested in below table:

Table 10.8: Monitoring Schedule for Environmental Parameters

Sl. No. Particulars Monitoring

frequency

Duration of

monitoring

Important

parameters for

monitoring

I. Air Quality

1. Ambient Air monitoring

Project premises Once in a month 24 hourly

sample

PM, SO2, NO2

2. Stack Monitoring Once in a month Grab SO2, SPM, NO2,

HC, CO

II Water and Wastewater Quality

1. Water Quality

64

i. Ground water at two

locations (up-gradient and

down-gradient) of treated

effluent discharge area/

land

Once in a month Grab As per KSPCB

requirements

2. Waste water quality

i. Inlet to STP Daily Composite -

ii. Treated effluent prior to

discharge

Daily Composite -

III Soil Quality

1. Within project premises at

1 location on effluent

discharging area / land

Once in a month Composite

Sample

As per KSPCB

requirements

2. Ecological preservation

and up-gradation

Seasonal Visual

observations

Survival rate

IV Noise Monitoring

1. Project premises Once in a month Day and Night As per KSPCB

requirements

10.4 ENVIRONMENTAL LEGISLATIONS

There are many Environmental Acts & Rules which are formulated by Ministry

of Environment and Forests (MoEF) for the prevention of Environmental squalor and

are to be compiled by the Industry. All the regulations are not applicable to all. The

Act and Rules which are to be constantly perused and followed by the Industry are

enumerated in the following section.

Table 10.9: Particulars of Environmental Legislations

Year of

Enactment LEGISLATION

1974 The Water (Prevention and Control of Pollution) Act.

1975 The Water (Prevention and Control of Pollution) Rules.

1988 The Water (Prevention and Control of Pollution) as amended.

1981 The Air (Prevention and Control of Pollution) Act.

1987 The Air (Prevention and Control of Pollution) and as amended.

1986 The Environment (Protection) Rules.

65

1991 The Environment (Protection) Rules (Amended).

10.4.1 ENVIRONMENT PROTECTION ACT & RULES

Among the various notifications coming under the Environment (Protection) Act,

following are the notifications applicable to this project:

Table 10.10: Notifications under Environmental Protection Act & Rules

YEAR OF

NOTIFICATION RULES

1989 The Hazardous Waste (Management & Handling) Rules

2000 & 2003 The Hazardous Waste (Management & Handling) Rules

(amended)

1992/1993 Environmental Statement

2000 Noise Pollution (Regulation & Control) Rules and

Amendment Rule 2006

2000 Municipal Solid Wastes (Management & Handling) Rules

2002 D.G. Rules

2008 The Hazardous Wastes (Management, Handling &

Transboundary Movement) Rules

The Hazardous Waste (Management & Handling) Rules 1989 (latest amendment

2008)

The DG Set Waste/used oil is included in the schedule-1 of list of Hazardous

Waste under Serial No.5 which states as under:

“Used/spent oil (category No.5.1) generated from industrial operations.

Using mineral/synthetic oil as lubricant in hydraulic systems or other

applications”.

Used oil defined under Rule 3 (34) means any oil derived from crude oil or

mixtures containing synthetic oil including used engine oil, gear oil, hydraulic oil,

turbine oil, compressor oil, industrial gear oil, heat transfer oil, transformer oil, spent

oil and their tank bottom sludge and suitable for re-refining, if it meets the

specifications laid down in Schedule 5, but does not include waste oil.

Responsibility of the occupier and operator of a facility for handling of the

wastes is delineated as under:

66

1. The Occupier and the operator of a facility shall be responsible for proper

collection, reception, treatment, storage and disposal of hazardous wastes listed

in schedule –1, 2 and3 {Rule 4(1)}

2. It shall be the responsibility of the occupier and the operator of a facility, to

take all steps to ensure that the wastes listed in schedule 1,2 and 3 are

properly handled and disposed of without any adverse effects to the

environment {Rule 4(3)}.

3. Hazardous wastes shall be collected, treated, stored and disposed of only in

such facilities as may be authorized for this purpose {Rule 5(1)}.

4. Every occupier handling, or a recycler recycling, hazardous wastes shall make

application in Form-1 to the Member Secretary, State Pollution Control Board

or committee, as the case may be or any Officer designated by the State

Pollution Control Board of committee for the grant of authorization for any of

the said activities { Rule 5(2) }.

5. The Occupier or operator of a facility shall ensure that the hazardous wastes

are packaged, based on the composition in the manner suitable for handling,

storage, and transport and the labeling and packaging shall be easily visible

and be able to withstand physical conditions and climatic factors {Rule 7(1)}.

6. Packaging, labeling and transport of hazardous wastes shall be in accordance

with provisions of the rules made by the Central Government under the Motor

Vehicles Act 1988 and other guidelines issued from time to time { Rule 7(2)}.

7. All Hazardous waste containers shall be provided with a general label as given

in Form-8 of Hazardous Waste (Management Handling) Rules 1989 as amended

there after {Rule 7(3)}.

8. The Occupier shall prepare six copies of the manifest in Form 9 comprising of

colour code indicated below (all six copies to be signed by transporter) {Rule

7(4)}.

9. The Occupier generating hazardous waste and operator of a facility for

collection, reception, treatment, transport, storage and disposal of hazardous

waste shall maintain records of such operations in Form-3 {Rule 9(1)}.

67

10. The occupier or an operator of a facility shall send annual reports to the State

Pollution Control Board or committee in Form-4 {Rule 9(2)}.

11. Where an accident occurs at the facility or on a hazardous waste site or during

transportation of hazardous waste the occupier or Operator of a facility shall

report immediately to the State Pollution Control Board or committee about the

accident in Form-5 {Rule 10}.

12. No owner or occupier generating non-ferrous metal waste specified in schedule

4 or generating used oil or waste oil of ten tons or more per annum shall sell or

auction such non-ferrous metal wastes, used oil or waste oil to a registered re-

refiner or recycler, as the case may be, who undertakes to re-refine or recycle

the waste within the period of validity of his certificate of registration (Rule

20(1)).

Table 10.11: Colour Code for the manifest copies

Copy number with

Colour Code Purpose

Copy 1 (White) To be forwarded by the occupier to the State

Pollution Control Board or Committee.

Copy 2 (Yellow) To be retained by the occupier after taking

signature on it from the transporter and rest of

the four copies to be carried by the transporter

Copy 3 (Pink) To be retained by the operator of the facility after

Signature

Copy 4 (Orange) To be returned to the transporter by the operator

of Facility after accepting waste

Copy 5 (Green)

To be returned by the operator of the facility to

State Pollution Control Board/Committee after

treatment and disposal of wastes

Copy 6 (blue) To be returned by the operator of the facility to the

occupier after treatment and disposal of wastes.

ENVIRONMENTAL STATEMENT:

Under rule 14 of the Environmental Protection Rules 1986, every person

carrying on an industry, operation or process requiring Consent under Section 25 of

Water (Prevention and Control of Pollution) Act, 1974 (6 of 1974) or under Section 21

of the Air (Prevention and Control of Pollution) Act 1981 (14 of 1981) or both or

68

authorization under the Hazardous Waste (Management & Handling) Rules 1989

issued under the Environment (Protection ) Act, 1986 (29 of 1986) shall submit an

Environmental Statement Report for the financial year ending the 31st March in Form-

V to the concerned State Pollution Control Board on or before 15th Day of September

every year.

BUDGETARY ALLOCATION FOR EMP DURING OPERATION

Sl. No. EMP Aspect Cost in Rs

Capital Investment In Lakh

1. Sewage Treatment Plant 30.0

2. Rainwater harvesting facilities 10.0

3. Landscape development 10.0

4. Acoustic & Stacks for DG sets 5.0

5. Organic Waste Converter 3.0

Total 58

Operation Investment Lakh/ Annum

1. STP Maintenance 3.0

2. Landscape Maintenance 2.0

3. OWC Maintenance 1.5

4. EMP Cell 2.5

5. Environmental Monitoring-Air, Water, Noise 1.0

Total 10