(see paragraph-6) form 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over...

108
(See Paragraph-6) FORM 1 Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any' at the last part of the Form1. Please note that all such Annexures must be part of single pdf document. (I)Basic Informations S.No. Item Details 1. Name of the Project Kirthai Stage-ll HEP (930 MW) 2. Project Sector River Valley and Hydroelectric Projects 3. Location of the project District Kishtwar, J&K 4. Shape of the project land point uploaded GPS file 10 km radius topo map (Annexure - I) 5. Brief summary of project Brief Summary of Project (Annexure - II) 6. State of the project Jammu & Kashmir Details of State of the project S.no State Name District Name Tehsil Name (1.) Jammu & Kashmir Kishtwar Paddar 7. Town / Village Kiddur 8. Plot/Survey/Khasra No. 52 C 3 9. S. No. in the schedule 1(c) River Valley projects 10. Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled 930 MW Underground Power House (6x140)MW Dam toe Power House (2x35+2x10)MW 11. New/Expansion/Modernization New 12. Category of project i.e. 'A' or 'B' A 13. Does it attract the general condition? If yes, please specify No 15. Does it attract the specific condition? No 16. Is there any litigation pending against the project? No 17. Nearest railway station along with distance in kms. Udhampur 210 km 18. Nearest airport along with distance in kms Jammu – 310 km

Upload: others

Post on 13-Oct-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

(See Paragraph-6)

FORM 1

Note : If space provided against any parameter is inadequate, Kindly upload supporting document

under 'Additional Attachments if any' at the last part of the Form1. Please note that all such

Annexures must be part of single pdf document.

(I)Basic Informations

S.No. Item Details

1. Name of the Project Kirthai Stage-ll HEP (930 MW)

2. Project Sector River Valley and Hydroelectric Projects

3. Location of the project District Kishtwar, J&K

4. Shape of the project land point uploaded

GPS file

10 km radius topo map (Annexure - I)

5. Brief summary of project Brief Summary of Project (Annexure - II)

6. State of the project Jammu & Kashmir

Details of State of the project

S.no State Name District Name Tehsil Name

(1.) Jammu & Kashmir Kishtwar Paddar

7. Town / Village Kiddur

8. Plot/Survey/Khasra No. 52 C 3

9. S. No. in the schedule 1(c) River Valley projects

10.

Proposed capacity/area/length/tonnage to

be handled/command area/lease

area/number or wells to be drilled

930 MW

Underground Power House (6x140)MW

Dam toe Power House (2x35+2x10)MW

11. New/Expansion/Modernization New

12. Category of project i.e. 'A' or 'B' A

13. Does it attract the general condition? If

yes, please specify No

15. Does it attract the specific condition? No

16. Is there any litigation pending against the

project? No

17. Nearest railway station along with

distance in kms. Udhampur 210 km

18. Nearest airport along with distance in kms Jammu – 310 km

Page 2: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

19. Nearest Town/City/District Headquarters

along with distance in kms Kishtwar, 65 km

20.

Details of alternative sites examined

No shown on a toposheet

Initially three alternative dam axis were selected across the

river Chenab downstream of village Kirthai in consultation

with geologists from GSI. But a high storage dam at any of

these sites would have submerged Padder valley

comprising of some villages and agricultural & forest lands.

One more site was selected upstream of this valley, but the

storage available at any site above the valley was

comparatively less than that at any downstream site. In

order to finalize the dam axis, expert team comprising of

Engineering Geologists from GSI and Designers from CWC

visited the project site in May 1989. The experts during the

time of the visit observed that though a dam and power

house upstream of Padder valley at Gulabgarh would in

itself be a feasible project, it will not fully utilize the power

potential available in the reach. It was therefore suggested

that Dam at Gulabgarh can be constructed as Stage I of

the entire scheme and relatively lower pick up dam (100 m

high) can be located downstream of the valley. This would

avoid submergence of the Padder valley and would tap the

balance power potential.The comparative study was made

by taking into consideration all the alternatives and finally

it was decided to have a storage dam at Gulabgarh with

underground power house at Gulabgarh itself (Kirthai H.E.

Project Stage I) and a lower dam near Silpar or Kidur with

underground power house at Lidrary (Kirthai H.E. Project

Stage II)

21. Whether part of interlinked projects?

No

22.

Whether the proposal involves approval /

clearance under the Forest Conservation

Act, 1980 ?

Status of Application for Forest Clearance

Yes, yet to be submitted

23.

Whether the proposal involves

approval/clearance under the wildlife

(Protection)Act,1972?

No.

24.

Whether the proposal involves

approval/clearance under the C.R.Z

notification,2011? No

25.

Whether there is any Government

Order/Policy relevant/relating to the site?

Project comes under the provisions of Annexure-D of

Indus water treaty and the project area comes under

Forest Act

26.

Whether there is any litigation pending

against the project and/or land in whichNo

the project is proposed to be set up? No

27. Project Cost(in lacs) 515800 lakh

Page 3: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

II. Activity

1. Construction, operation or decommissioning of the Project involving actions, which will cause

physical changes in the locality (topography, land use, changes in water bodies, etc.)

S.No Information/Checklist confirmation

Yes/No

Details there of (with approximate

quantities/rates, wherever possible) with

source of information data

1.1

Permanent or temporary change in land

use, land cover or topography including

increase in intensity of land use (with

respect to local land use plan)

Yes

The land use of private land being used for

establishing colonies shall not change as it will

continue under land use class agriculture &

settlement but the land use of private land coming

under submergence shall change from agriculture

to water body. The land use class of private land

required for new road construction shall change in

to bult-up land use. The underground components

falling in forest area will not cause any impact on

the land use. Similarly, the land use of forest area

diverted for dump areas and quarry sites will not

cause any impact on land use as these shall

continue to be under forest land use class.

However, forest land and revenue land coming in

submergence shall have its land use changed

permanently in water body

1.2 Clearance of existing land, vegetation and

buildings?

Yes

Clearance of existing vegetation at various

project component sites during construction

phase is envisaged.

1.3 Creation of new land uses?

Yes

Muck dumping sites presently under open forest

or wasteland would be used temporarily before

being converted to plantations.

1.4 Pre-construction investigations e.g. bore

houses, soil testing?

Yes

Pre-construction activities like Bore Hole,

Drifting, geological testing as suggested by GSI

has been carried out.

1.5 Construction works? Yes

The project shall comprise of:

• 121 m high concrete gravity dam, with

overall length 219.80 m at top.

• 93 m long over flow section with 5 bays with

radial gates(9mx12.248m).

• A power intake to convey the regulated

discharge through 4 number, 6.4 m diameter,

intake tunnels of varying length leading to

four desilting chambers.

• 4 flushing tunnels / ducts (3.6mx2.5m)

• 10.5 m diameter 4.289 km long HRT

• 31.6 m diameter surge shaft

• Pressure shafts (3 No,5.25m diameter,827m

long),

• Unit penstocks to feed six number generating

units (140 MW each)

• Underground power house of cavity size

187.5 m X 22 m X 49.7m on the left bank of

the Chenab.

Page 4: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

• 11.25 m diameter 352.5m long circular tail

race tunnel

• A Power intake to feed dam toe powerhouse

(90MW).

1.6 Demolition works? No The project does not entail any demolition works.

Besides, the structure coming under

submergence.

Temporary Labour sheds for Labourer at some

places shall be created during construction phase,

which will be demobilized before commissioning.

1.7 Temporary sites used for construction works

or housing of construction workers? Yes

Temporary labour camps would be required for

construction phase.

1.8

Above ground buildings, structures or

earthworks including linear structures,cut

and fill or excavations and fill or excavations Yes

Above ground structures shall include project

components like dam, power intake, desilting

arrangement and surface power house (90MW)

besides permanent and temporary buildings and

roads. The description of such components has

been provided in 1.5

1.9 Underground works including mining or

tunneling? Yes

Construction of Head race tunnel as water

conductor system from dam to power house &

underground powerhouse, besides

Desilting and flushing system.

1.10 Reclamation works? Yes

Reclamation works would involve reclamation of

quarry and muck dumping sites because of

project activities which will be done on

completion of civil work. Adequate provision

based on detailed estimate has been made for

Muck Management, Restoration Plan for Quarry

Sites, Landscape and Restoration Plan under

EMP.

1.11 Dredging? No No dredging is involved

1.12 Offshore structures? No Not Applicable

1.13 Production and manufacturing processes? No Hydro power generation is proposed by utilizing

head and the available discharge in the river

1.14 Facilities for storage of goods or materials? Yes Project is not a goods manufacturing or

production unit. However, during project

construction/operation, storage for materials

would be needed.

1.15

Facilities for treatment or disposal of solid

waste or liquid effluents?

Yes

Project process does not entail generation of solid

or liquid waste. However, sewerage and solid

waste will be generated from project colony and

labour camp for which sewerage treatment plant

and septic tank have been proposed respectively.

Municipal Solid waste would be disposed as per

MSW Rules 2016 for which Sanitation and solid

waste management plan has been formulated

under EMP. However, as far as disposal of muck

(generated from the project components) is

concerned, a separate muck management plan

has been prepared under EMP

Page 5: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

1.16 Facilities for long term housing of

operational workers? Yes

The operational staff would be housed in the

colonies mentioned above as upon commissioning

of the project construction staff would be shifted

out. Suitable sewerage and solid waste disposal

mechanism has been suggested for the project

colony in the EMP.

1.17 New road, rail or sea traffic during

construction or operation? Yes

New approach road during construction and

operation phase.

No rail / sea traffic is involved.

1.18

New road, rail, air water borne or other

transport infrastructure including new or

altered routes and stations, ports, airports

etc? No

No new road except realignment of existing

Kishtwar – Gulabgarh - Sansari road in about a

stretch of 4.5km length under submergence will

be required. However, for transportation of

machinery, widening and strengthening of

existing road shall be required. For executing

various civil works roads will be made for linking

the works site to other site and to job facility

areas.

1.19

Closure or diversion of existing transport

routes or infrastructure leading to changes

in traffic movements?

No

There would not be any closure or diversion of existing

roads or routes leading to any traffic diversion

1.20 New or diverted transmission lines or

pipelines? Yes

Transmission line for evacuation of power. New

pipelines shall be laid for providing drinking water

supply to colonies / labour camps.

1.21

Impoundment, damming, culverting,

realignment or other changes to the

hydrology of watercourses or aquifers?

Yes

The proposed dam shall impound water on u/s.

With the formation of the reservoir, the

hydrology of the River shall be affected.

1.22 Stream crossings? No No stream is proposed to be crossed by any cross-

drainage work. The HRT shall be aligned with their overt

well below the natural stream level near the stream

crossing

1.23 Abstraction or transfers of water from

ground or surface waters? Yes

River water after leaving environmental flow will

be diverted through HRT for power generation.

No consumptive use involved and entire diverted

water will be released back into the river after

powerhouse.

1.24

Changes in water bodies or the land surface

affecting drainage or run-off? Yes

Formation of reservoir will effect a change in

water body and the land surface.

Environmental flow as per MOEF guidelines has

been allowed to take care of d/s effect / change.

1.25

Transport of personnel or materials for

construction, operation or

decommissioning?

Yes

Construction would entail, transportation of

construction material locally and from outside.

During construction, the resident labour from

labour camps shall be daily transported to the

work site and on de commissioning, the personnel

shall be shifted from the project site except the

persons required for operation phase

1.26 Long-term dismantling or decommissioning

or restoration works? Yes

Project does not involve any long terms

dismantling of its components. However, batching

plant, stone crushers, temporary work shops,

Page 6: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

labour sheds shall be dismantled after

commissioning of the project.

1.27

Ongoing activity during decommissioning

which could have an impact on the

environment?

No

No decommissioning activity is warranted

1.28

Influx of people to an area in either

temporarily or permanently? Yes

About 2100 persons shall be employed during

peak construction phase. However, during

operation phase only 100 to 150 technical

staff/labour shall be required.

1.29 Introduction of alien species? No Only indigenous species will be planted

1.30 Loss of native species or genetic diversity? No

1.31 Any other actions? No

The aspect prescribed in the TOR have been

complied.

2. Use of Natural resources for construction or operation of the Project (such as land, water,

materials or energy, especially any resources which are non-renewable or in short supply):

S.No. Information/Checklist Confirmation Yes/No Details thereof (with approximate

quantities/rates, wherever possible) with

source of information data

2.1 Land especially undeveloped or

agricultural land (ha)

Yes 43 ha private land

2.2 Water (expected source & competing

users) unit: KLD

Yes

200 KLD water will be required for drinking /

domestic purpose which will be drawn from the

existing springs/local khad. The requirement of

about 300 KLD of water for construction purpose

shall be met from the main river as well as the

seepage water from the tunnel.

2.3 Minerals (MT) No No minerals shall be used for the construction of

the project except the minor minerals i.e.

boulder, sand and bajri.

2.4

Construction material – stone,

aggregates, sand / soil (expected source –

MT)

Yes

Approximately 20.76 lac cum and 10.38 lac cum

coarse and fine aggregate respectively shall be

required besides graded filter material (0.22 lac

cum) and impervious material i.e. clay 0.30 lac

cum as construction material. The requirement

shall be partly met from the excavated material

and from the rock-in-situ quarry sites.

2.5 Forests and timber (source – MT)

Yes

The conventional use of fuel wood by the labour

shall be totally banned and it will be substituted

through use of LPG/ Kerosene. Timber shall be

required only for construction works in buildings.

2.6

Energy including electricity and fuels

(source, competing users) Unit: fuel (MT),

energy (MW)

Yes

Construction power (25 MW) shall be met from

the existing transmission network in the area. 467

LPG cylinders (7.5 MT/month) shall be used as

fuel in lieu of fuel wood. The demand of POL and

HSD oil shall be met from outside.

Page 7: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

2.7 Any other natural resources (use

appropriate standard units)

Yes

Use of solar heater and light in the project area has

been provided in the EMP.

3. Use, storage, transport, handling or production of substances or materials, which could be

harmful to human health or the environment or raise concerns about actual or perceived risks

to human health

S.

No. Information/Checklist confirmation

Yes/No

Details thereof (with approximate

quantities/rates, wherever possible) with

source of information data

3.1

Use of substances or materials, which are

hazardous (as per MSIHC rules) to human

health or the environment (flora, fauna,

and water supplies

Yes

Explosives will be used for blasting in construction

of roads, surface excavation in hard rocks as well

as underground works. Explosive shall be stored

in properly located magazines and shall be

transported through explosive van. All

precautions as laid down under relevant rules

shall be followed

3.2

Changes in occurrence of disease or affect

disease vectors (e.g. insect or water borne

diseases)

Yes

There is a slight possibility of increase in some

vector population due to impoundment of water.

However, owing to low temperature and high

altitude of the project area, the possibility of

occurrence of such disease is very remote.

3.3 Affect the welfare of people e.g. by

changing living conditions?

Yes

The project will open new vista of employment

and increase business which will lead to better

living conditions. Besides this, it is proposed to

spend 0.5% cost of the project for local area

development works through LADA. There will be

better living conditions due to opening of

employment in the area. Project will uplift the

economy of the local people by direct and indirect

employment opportunity. Besides this the PAF

shall be properly compensated and rehabilitated

as per RFCTLARRA, 2013

3.4

Vulnerable groups of people who could be

affected by the project e.g. hospital

patients, children, the elderly etc.

No

No hospital, school exists nearby the project area

and the nearest PHC is at Atholi.

3.5 Any other causes No None

3 Production of solid wastes during construction or operation or decommissioning (MT/month)

S.No. Information/Checklist confirmation Yes /

No

Details thereof (with approximate

quantities/rates, wherever possible) with

source of information data

4.1 Spoil, overburden or mine wastes Yes Surface as well as underground excavation shall

result in generation of excavated muck and

overburden waste. Part of the excavated material

shall be consumed as aggregate material as well as

back fill material and the rest shall be disposed

properly at designated muck sites located away

from the water bodies.

4.2 Municipal waste (domestic and or

commercial wastes)

Yes

Solid municipal waste shall be generated from

project colony and labour camps. The collected

bio-degradable waste will be disposed at suitable

landfill sites, organic waste will be suitably

processed to for compost while the non-bio-

degradable waste shall be incinerated. Commercial

Page 8: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

waste shall be stored and periodically disposed by

auction.

4.3 Hazardous wastes (as per Hazardous

Waste Management Rules)

No

No hazardous waste will be produced

4.4 Other industrial process wastes No No other industrial process wastes will be

generated during construction and operational

stages.

4.5 Surplus product No In view of HEP, no surplus product will be

produced.

4.6 Sewage sludge or other sludge from

effluent treatment

Yes

Effluent is not generated in hydro-electric

generation. However, liquid effluent shall be

generated from the project colonies and labour

camps which will be suitably processed through STP

and septic tanks/soak pits respectively. The liquid

effluent after treatment shall be discharged into

nearby stream.

4.7 Construction or demolition wastes

Yes

About 30.26 lakh cum muck shall be generated

during construction phase of which approximately

70% shall be consumed and the rest will be

suitably disposed at suitable sites. The waste like

the roofing material, wooden sections and panel of

the doors shall be retrieved and the balance in the

form of rubbles of the stone masonry work or the

CC blocks of the walling shall be used wherever

needed by the project authority.

4.8 Redundant machinery or equipment Yes The work shall be carried out contractually, therefore, the construction agency shall remove from the site all the redundant plant and equipment from the site after completion of the work.

4.9 Contaminated soils or other materials No No contamination of the soil or other materials is envisaged during construction or in operation phase. The POL shall be stored in proper containers and inside sheds / stores provided with suitable flooring and equipped with fire protection arrangements.

4.10 Agricultural wastes No No agriculture waste is produced during hydro-electric generation.

4.11 Other solid wastes No -

5. Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)

S.No.

Information/Checklist confirmation Yes/ No

Details thereof (with approximate quantities/rates, wherever possible) with source of information data

5.1

Emissions from combustion of fossil fuels

from stationary or mobile sources

Yes There will be emissions from use of vehicles and construction equipment which will be limited to project site only. The maximum incremental GLC in respect of PM10 & NOx was 9.9 ug/cum and 0.14 ug/cum respectively.

5.2 Emissions from production processes No Hydro power generation process does not lead to any emission.

5.3

Emissions from materials handling

including storage or transport

Yes The use of transport vehicle for carriage of material shall lead to emission. However, there will be no emission during material handling except for the dust

Page 9: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

pollutants during handling of cement bags, which will be controlled.

5.4 Emissions from construction activities

including plant and equipment

Yes There will be emissions from use of vehicles and construction equipment which will be limited to project site. The maximum GLC due to excavation activity and crushing of aggregates was found to be 15.07 ug/cum inside dam complex and there was insignificant increase 0.08 ug/cum in the nearby village.

5.5

Dust or odours from handling of materials

including construction materials, sewage

and waste

Yes Dust/odours may be produced from handling of material, municipal waste and sewage waste.

5.6 Emissions from incineration of waste Yes Emission shall be produced during incineration of the non-bio-degradable solid waste at the incinerator site.

5.7

Emissions from burning of waste in open

air (e.g. slash materials, construction

debris)

No No burning of material is proposed at any site other than the incinerator site.

5.8 Emissions from any other sources No -

6. Generation of Noise and Vibration, and Emissions of Light and Heat:

S.No. Information/Checklist confirmation

Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data

6.1 From operation of equipment e.g.

engines, ventilation plant, crushers

Yes Noise and Vibrations will be generated during operation of drilling equipment and blasting and other construction equipment. During operation phase, there shall be high noise levels at the turbine and generator floors. However, the impact shall be on the workers who will be engaged in shifts. There shall be no impact to human/animal population in areas outside the power house main access tunnel (MAT).

6.2 From industrial or similar processes No No industrial process is involved in hydro-electric generation.

6.3 From construction or demolition

Yes Noise and Vibrations will be generated during operation of drilling equipment and blasting and other construction equipment.

6.4 From blasting or piling

Yes There shall be setting up of ground vibrations and instantaneous increase in noise level (air overpressure) during blasting. The noise modeling has shown that the noise level of 91 dB(A) at the dam site gets highly attenuated to 40 dB(A) about 1200m from it. The value of PPV was assessed as 0.70 mm / sec at about 500 m from the blasting site and is within the prescribed limit by DGMS. There shall be no piling activity during construction phase.

6.5 From construction or operational traffic

Yes The movement of tippers for transportation of muck and transit concrete mixtures during construction shall cause noise and vibration. During O&M phase there shall be no increase in noise and vibration level as the only operational traffic shall be the staff bus deployed for movement of shift workers and also the inspection vehicles.

Page 10: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

6.6 From lighting or cooling systems No No heat and light emissions except during welding operation are generated during the construction phase of a hydro-electric project. However, some heat may be generated inside the power house for which proper cooling system shall be provided.

6.7 From any other sources Yes Low intensity heat generation are anticipated in the transformer cavern of the power house for which proper air-conditioning and cooling system shall be devised.

7. Risks of contamination of land or water from releases of pollutants into the ground or into

sewers, surface waters, groundwater, coastal waters or the sea:

S.No.

Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data

7.1

From handling, storage, use or spillage of

hazardous materials

No Handling, storage or use of explosive will not contaminate land / water. The oil spillage from the POL shall be collected in the settling tank and the oil separated before disposal of the liquid.

7.2

From discharge of sewage or other

effluents to water or the land (expected

mode and place of discharge)

No The liquid effluent shall be generated from the project colonies and labour camps which will be suitably processed through STP and septic tanks/soak pits respectively. The liquid effluent after treatment shall be discharged into nearby khad.

7.3 By deposition of pollutants emitted to air

into the land or into water

Yes Excavation in the hard rock by drilling and blasting and the running of excavators and loaders shall cause fugitive dust as well as gaseous emissions which get deposited on land and water.

7.4 From any other sources No -

7.5

Is there a risk of long term buildup of

pollutants in the environment from these

sources?

No No incidence of long term builds up of pollutants is expected as the project is likely to be completed within a time frame of 60 months including the pre-construction activities. Moreover, the project area is in remote location and due to openness of the area, the pollutant load is cleared on daily basis.

8. Risk of accidents during construction or operation of the Project, which could affect human

health or the environment

S.No.

Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data

8.1

From explosions, spillages, fires etc from

storage, handling, use or production of

hazardous substances

Yes Since explosives are to be used for blasting during tunneling as well as the surface excavation in hard rocks, the attendant risk is always there. To avoid accident due to handling of explosives, proper precautionary and safety measures as suggested in relevant Act and codes shall be adopted.

8.2 From any other causes Yes During tunneling, due to formation of chimney, overhead rock falls cannot be ruled out.

Page 11: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

8.3

Could the project be affected by natural

disasters causing environmental damage

(e.g. floods, earthquakes, landslides,

cloudburst etc)?

Yes The topography of the lease area is such that it cannot be affected due to disaster in the form of flood and land slide. The lease area lies within Seismic Zone-IV as per seismic zoning map of India (IS: 1893: 2002).

9. Factors which should be considered (such as consequential development) which could lead

to environmental effects or the potential for cumulative impacts with other existing or

planned activities in the locality

S.

No.

Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data

9.1

Lead to development of supporting utilities,

ancillary development or development

stimulated by the project which could have

impact on the environment e.g.:

• Supporting infrastructure (roads,

power supply,waste or waste water

treatment, etc.)

• Housing development

• extractive industries

• supply

industries

• Other

Yes

No No No No

Road from Kishtwar-Gulabgarh on which dam site is located shall involve widening and strengthening.

9.2

Lead to after-use of the site, which could have

an impact on the environment

No None of the sites has any potential for after use except the muck disposal site which will be provided with vegetal cover.

9.3 Set a precedent for later developments No -

9.4

Have cumulative effects due to proximity to

other existing or planned projects with similar

effects

Yes The tail race of Kirthai-I HEP (390 MW) is about 2.5 km u/s of the tip of the reservoir of Kirthai – II HEP (930 MW). The diversion structure of proposed Kiru HEP (624 MW) is located about 1km d/s of the TRC of Kirthai – II HEP. Thus, the free flow stretch of the river in both cases is more than 1km.

(III) Environmental Sensitivity

S.No.

Areas Name / Identity

Aerial distance (within 15km.) Proposed project location boundary

1

Areas protected under international

conventions, national or local legislation for

their ecological, landscape, cultural or other

related value

Kishtwar National

Park

(40 km)

2

Areas which are important or sensitive for

ecological reasons - Wetlands, watercourses or

other water bodies, coastal zone, biospheres,

mountains, forests

None The project area lies in mountainous terrain of lesser Himalayas while the catchment lies in Greater Himalayas. There are no sensitive areas like wetland, coastal zone and biosphere.

3

Areas used by protected, important or

sensitive species of flora or fauna for

breeding, nesting, foraging, resting, over

wintering, migration

None None

Page 12: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

4 Inland, coastal, marine or underground waters None Due to topography of the area, there are no inland, coastal and marine water.

5 State, National boundaries No Neither International Boundary with China nor the nearest State boundary with Himachal Pradesh lies within 15km of the project site.

6

Routes or facilities used by the public for

access to recreation or other tourist, pilgrim

areas

Kishtwar Gulabgarh

road

The present route is being used by local populace and the route also, leads to pilgrim area of Macheal Yatra.

7 Defence installations No There are no defence

installations in or around the project area.

8 Densely populated or built-up area None The project area is scarcely populated or built-up area

9

Areas occupied by sensitive man-made land

uses (hospitals, schools, places of worship,

community facilities)

None No such facility or sensitive area falls in or around project area.

10

Areas containing important, high quality or

scarce resources. (ground water resources,

surface

resources, forestry, agriculture, fisheries,

tourism, minerals)

None Project area does not contain any important, high quality or scarce resource.

11

Areas already subjected to pollution or

environmental damage. (those where existing

legal environmental standards are exceeded)

None

12

Areas susceptible to natural hazard which

could cause the project to present

environmental problems (earthquakes,

subsidence, landslides, erosion, flooding or

extreme or adverse climatic conditions) similar

effects

Yes There is a possibility of cloud burst which can result in enormous discharge leading to barrage failure. Besides this, the project lies in seismic zone – IV, Earthquake of high intensity cannot be ruled out

(IV) PROPOSED TERMS OF REFERENCE FOR EIA STUDIES

1 Uploaded Proposed TOR File Uploaded earlier approved ToR

2 Uploaded scanned copy of covering letter Uploaded Covering Letter

3 Uploaded Pre-Feasibility report(PFR) Uploaded DPR

4 Uploaded additional attachments (only single pdf file) Uploaded copy of Form-1

(V) Undertaking

The aforesaid application and documents furnished here with are true to my knowledge

Page 13: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey
Page 14: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Annexure – I : 10 km radius topo map

Page 15: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Annexure II : Brief Summary of Project

Kirthai HEP Stage – II (930 MW): An Overview

The need for the Kirthai HEP, Stage-II, installed capacity 930 MW, in the lower reach of the

Chenab Basin, which stores 10360 MW power potential being 85.7% of the total hydropower

potential of the state, has therefore been considered in context of power shortage in the

Northern region in general and in the country as whole. The project has been conceptualized

as a run-of-the-river under the ambitions cascading development programme of hydropower in

the Chenab basin

It envisages utilization of river water through average net head of 225.1 m for generation of

annual energy of 3159.72 MU at 90% dependability, through an underground powerhouse

(6X140MW) to be located on the left bank of the Chenab near Lidrara Nalla and a dam toe

power house with average net head of 99.95m for generation of annual energy of 307.19 MU,

thereby resulting into an annual generation of 3466.19 MU. The project comprises of 121 m

high concrete gravity dam (from the river bed level), with overall length 219.80 m at top i.e. El

1766 masl and consisting of 93 m long over flow section. The sluice spillway, with 5 bays fitted

with radial gates(9mx12.248m), with crest at El 1712.5 masl, has been designed to pass the

PMF of 9660 cumec. A power intake with invert level at El 1731.80 masl shall convey the

regulated discharge through 4 number, 6.4 m diameter, intake tunnels of varying length leading

to four desilting chambers (440mx19mx24.87m) which in turn are joined to four flushing

tunnels/ducts (3.6mx2.5m) to escape silt laden water into the river. Appropriate HRT manifold

shall be provided from which 10.5 m diameter 4.289 km long HRT, with invert level at the start

El 1725.00 masl, shall take off to convey 413.47 cumec discharge to 31.6 m diameter surge

shaft connected at its lower end to concrete lined steel liner pressure shafts (3 No,5.25m

diameter,827m long), each further bifurcating to unit penstocks to feed six number generating

units of 140 MW capacity each under a net rated head of 225.1 m and housed in an

underground power house of cavity size 187.5 m X 22 m X 49.7m on the left bank of the

Chenab. The discharge through draft tubes shall be led to the river through 11.25 m

diameter352.5m long circular tunnel with average outfall at El 1530 masl For dam toe

powerhouse a Power intake shall be provided in the dam block-9 to exploit the environmental

flow release of 99.71 cumec at a net head of 99.95 m at the dam toe power house. The water

from the powerhouse shall be conveyed through 51m longTRC. The reservoir FRL has been

fixed at El 1764 masl from the consideration of submergence alone. The Minimum Draw Down

Level (MDDL) has been estimated at 1750.75 m, from consideration of the live storage of 17

MCM, available between the proposed FRL and MDDL, to be adequate for peaking operation

of the station for about 44 hours in a week with flows corresponding to the minimum mean

discharge (MMD) and releases within the daily volume restrictions of 50% to 130% of the

corresponding daily inflows permissible within the scope of the Indus Water Treaty. The

average load factor of the operation of the main power house during lean period would be

about 10.1%% ensuring peak operation of the power house for about 2.4 hours daily. Annual

Plant Load factor of the main station would be about 43.00%. The firm power from the project

shall be118.8 MW. The power generated will be helpful in mitigation of the power shortage in

Northern Grid. The project, proposed to be completed in five years’ time frame, shall require

1200 persons including professionals, technical, skilled and unskilled labours during the peak

construction stage.

The general layout map is given below:

Page 16: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

General Layout Plan of the Project

Page 17: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

No.J-1 201 1 I 612012 -lA-lMinistry of Environment & Forests

Government of lndia(lA-l Division)

Paryavan Bhavan

CGO.Complex, Lodi RoadNew Dethi - 110 003

Date: 5th June, 2013

To,

The Chief EngineerCl &DWing,JammuJ&D Power development CorporationKhuttar Market Sec'3 ExtionTrikuta NagarJammu - 180 012

Subject: Kirthai Stage-ll HEP (930 MW) Project in Kishtwar District of Jammu &

Kashmir U/ttls. J&K Power Development Corporation - for Scoping/TOR -

regarding.Sir,

This is with reference to your letter no. Cl&D/571-1117165'79 dated 6.2.2012 and

9.1.2013 on the above mentioned subject.

Z. The proposal was eartier submitted for scoping ctearance for 990 MW. The ftow

series have been approved by CWC on 1.9.2011. The flow series corresponding tomonsoon flow in 90/. dependab[e year ranged from 673.7 to 1038.8 m3/sec, and a design

discharge of 512 m3/sec'with bifuication of 413.47 m3/sec for 840 MW (6x140 MW) main

undergiound powerhouse and 99.17 m3/sec for 90 MW dam'toe powerhouse has been

adopt6d. 20% retease in lean season ftow ranging from 50 to 70 cumec was reported

adequate to meet the downstream retease. As a resutt of downward revision of capacity

from 990 MW to 930 MW, there witt be no submergence of Paddar Vattey. The projectproposal was considered by Environment Appraisat Committee (EAC) for,River Vattey and

hydroetectric Projects in iis meetings hetd on 30-31't March, 2012 &.1-2nd February, 2013-

The comments ani observations of EAC on the proposal may be seen in the minutes of the

meetings, which are avaitabte on the web-site of this Ministry.

3. tt is noted that the project envisages construction of a 121 m high concrete gravity

dam across river (165 m from the deepest foundation levet) Chenab to generate 930 MW

of hydropower. The catchment area of the project is 9987 Sq. Km. Totat tand requirementis about'416.25 ha, out of which 227.25 ha is forest [and, 40 ha is government land and

149 ha is private tand. Totat submergence area is about 331 ha. (Of which 155 ha isforesttand). An unflerground powerhouse is proposed with 6 units of 140 MW each + 90 MW

(2$b MW ; 1x10 MW) auxitiary dam-toe powerhouse facititate to release ofenvironmental ftows is atso proposed. About 15 famities witl be futty affected due to thisproject. Tota[ cost of the project is about Rs. 6087.48 Crores.

Page 18: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

4. Based on recommendations of the EAC, the Ministry of Environment & Forestshereby accords ctearance for pre-construction activities at the proposed site as per theprovisions of 'the Environmental lmpact Assessment Notification, 2006 and subsequentamendment, 2009 atong with the fottowing Terms of Reference {TOR) for preparation ofEIA/EMP report. The EIA/EMP report shoutd contain the information in accordance withprovisions & stiputations as given in the Annexure-1. White preparing the EIA/EMP reportprevaiting norms shoutd be foltowed with respect to environmentat ftows, muck disposalsites and other parameters.

The Committee expressed its satisfaction over reduction in capacity from 990 MWto 930 MW as with this; land requirements and submergence area have come down,thereby saving Peddar vatley. The committee thus, agreed to the downward revision ofthe capacity of project to 930 MW subject to the fottowing conditions/additionat TORs:

. Keeping in view the proximity of protected forest [and, the Environmental Sensitivityis to be properly assessed and reftected in the EIA

o The EIA/EMP shoutd atso inctude the foltowing:

(i) Enumeration of atl ptant species betonging to atl groups, especiatty trees - number oftrees of eacli species and their volume in the submergence area; (ii) Studies onEconomic vatuation and Ecosystem Services will be carried out on the forest tost (iii)EMP: For Compensatory afforestation tree species affected in the forest witt be utitizedfor ptanting.

. Land cover and land-use pattern shoutd be given with Fatse Cotour Composition (FCC)o Flora of the Project Area: "29 taxa of flowering plants" appears to very [ow. Detaits

about Gymnosperms, Pteridophytes, shrubs and herbs are-to be presented in the EIAreport.

o The sampting locations are to be given.. Sampting tocations for ftorat/faunal studies appeared to be inadequate. Champion &

Seth (1968) shoutd be fottowed for forest typeso Environmental Evaluation: detaits of the environmentat evatuation should be given

and detaits of forest land/flora and fauna have to be presented in the EIA reporto Proposed Engineering and Biotogical measures: Use Coir mats - geotextiles on stopes

to prevent soil erosion and for raising plantations.. A study on environmentat ftow retease needs to be inctuded. Draw a separate cotumn

giving environmental ftow, spitt ftow, turbine ftow and ftow through the dam-toepowerhouse. Check the total retease d/s dam as per the prescribed norms. ln anycase retease of minimum environmental ftow must mimic the pre-dam flow patternof the river for sustaining the aquatic bio-diversity together with downstream userneed and accordingty, water withdrawal for power generation is to be regutated.Minimum environmental ftow retease would be 20Yo of average of four tean months oflean period and 20-30% of flows during non-tean and non-monsoon periodcorresponding to 90% dependabte year. The cumulative environmental ftow reteasesinctuding spittage during the monsoon period shoutd be about 30% of the cumulativeinflow during the monsoon periods corresponding to90/o dependabte year.

. The estimated PMF shown as 8140 cumec, whereas, the peak ftood hydrograph shows7440 cumce. This needs to be exptained/ reconciled in the EIA report.

Page 19: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

5. The Consuttant engaged for preparation of EIA/EMP report has to be registeredwith Quatity Councit of lndia (QCI)/NABET under the scheme of Accreditation &Registration of MoEF. This is a pre'requisite.

6. Consultants shatt inctude a "Certificate" in EIA/EMP report regarding portion ofEIA/EMP prepared by them and data provided by other organization(s)/ laboratoriesinctuding status of approval of such laboratories.

7. The draft EIA/EMP report prepared as per the above Terms of References shoutdbe submitted to the State Potlution Control Board / Committee concerned forconducting Pubtic Hearing /Consuttation as per the provisions stiputated in EIA

Notification of 2006.

8. Att issues discussed in the Pubtic Hearing/Consuttations shoutd be addressed and

incorporated in the EIA/EMP Report. Final EIA/EMP report shoutd be submitted to theMinistry for Environmental Ctearance onty after incorporating these issues.

9. The TOR wi[[ remain vatid for a period of 2 years from the date of issue of thistetter for submission of EIA/EMP report atong with pubtic consuttation.

10. ln casq of any change in the Scope of the Project such as capacity enhancement,shifting of dam site/powerhouse and change in submergence etc., fresh scoping

ctearance has to be obtained by the project proponent.

11. lnformation pertaining to Corporate Environmental Responsibitity and

Environmentat Poticy shatt be provided in the EIA/EMP Report as per this Ministry'scircutar dated 19.5.2012.

12. This has approval of the Competent Authority.

(B. B. Barman)Director

Copy to:1. The Secretary. Ministry of Power, Shram Shakti, Bhawan, Rafi Marg, New Dethi-12. The Adviser (Fower), Ptanning Commission, Yojna Bhawan, New Dethi'110 001.3. The Principal Secretary (MPP & Power), Government of Jammu & Kashmir, Srinagar.4. The Secretary, Department bf Environment, Government of Jammu & Kashmir, Srinagar.5. Chief Engineer, Project Appraisat Directorate, Central Etectricityr Authority, Sewa

Bhawan, R.K. Puram, New Dethi- 110 066.6. The Regional Office, Ministry of Environment & Forest, Chandigarh.7. The Member Secretary, Jammu & Kashmir State Poltution Control Board, Parivesh

Bhavan, Gtadni, Transport Nagar, Narwat, Jammu'180 006.NIC Cett - with a request to uptoad in MoEF's websitePS to JS (AT)/Director (lA-l)/PVSRaoGuard fite.

(8. B.Barman)Director

8.9.10

Page 20: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

n,I

(1)

Q)

' Annexure-l:

TERMS OT REI'ERENCE FOR CONDUCTING EIYVIRONMENT IMPACTASSESSMENT STUDY tr'OR 6A' CATEGORY HYDRO POWER PROJECTS AND

TNTORMAiTON TO BE INCLUDED IN EIA/EMP REPORT

Scoue of EIA Studies

-

The EIA Report should identi$/ the relevant environmental concerns and focus on potential --

impacts that may change due to the construction of proposed project. Based on the baseline ---

data collected for tluee (3) seasons (Pre-monsoon, Monsoon and Winter seasons), the status

of the existing environment in the area and capacity to bear the impact'on this should be

analysed. Based on this analysis, the mitigation measures for minimizing the impact shall be

suggested in the EIA/EMP study.

Details of the ProiecJ and Site

General introduction about the proposed project.

Details of project and site giving L-sections of all U/S and D/S projects of Chenab Riverwith atl relevant maps and figures. Connect such information as to establish the total

length of interferenci of Natural River, the total length of tunneling of the river and the

committed unresfricted release from the site of diversion into the main river.

A map of boundary of the project site'giving details of protected areas in the vicinity.ofproject location.Looation details on a map of the project area with contours indicating main project

features. The project layout shall be superimposed on a. contour map of ground

elevation showing main project features (viz. location of dam, Head works, main cana1,

branch canals, quarrying etc.) shall be depicted in a scaled map.

Layout details and map of the project along with contours with projgct components

clearly marked with proper scale maps of at least a l:50,000 scale and printed at least onA3 scale for clarity.Existence of National Park, Sanctuary, Biosphere Reserve etc. in the study area, if any,

should be detailed and presented on a map with distinct distances from the projectcomponents.j' Drainage pattern and map of the river catchment up to the proposed project site.

o Delineation of critically degraded areas inthe directly draining catchment on the basis ofsilt Yield lndex as per the methodology of All India Soil and Land Use Survey of India.

o Soil characteristics and map of the project area.

o Geological and seismo-tectonic details and maps of the area swounding the proposed

project site showing location of dam site and powerhouse site.. Rernote Sensing studies, interpretation of *t ttit imagery, topographic sheets along

with ground verification shall be used to develop the land use/land cover pattem of the

study,*ing overlaying mapping techniques viz. Geographic Information System (GIS),False Color composite (FCC) generated from satellite data of project area.

o Land details including forests, private and other land.o Demarcation of snow fed and rain fed areas for a realistic estimate of *re water

availability

?a

Page 21: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

o Different riverine habitats like rapids,substaturn - bedrocks, rocks, boulbers,the study.

poolsn side pools and, variations in the riversand/silt or clay etc. need to be covered under

To know the present status of environment in the area" baseline data with respect toenvironmental components air, water, noise, soil, land;qiiJ"gy-iaii"ai".*it-ifi;;;Ifaqna), wildlife, socio-economic status etc.-should be collected-witl, io f* radius of the*Tn components of the project/site i.e. dam site ani d*"iirr;;;r. The air quality andnoise are to be monitored at such locations which are

^r"rir"r*r"iJr-v-& ecologically more

::*itive in the study area. The baseline studies should be,collected for 3 sgasons (pre-Monsoon, Monsoon and Post Monsoon seasons). rrr" stoay;;;-;ff;,"*r?rr".i,r*o Catchment area up-to the dam site.o Submergence Area

'Project area 91th" direct impryt-area should comprise of area falling within l0 km radiusfrom the periphery of rmr*oir, land coming *d;; submergence and *;;.;;;#;;dam upto the point where Tail Race Tunnel (rnD meets th;;.'-:-- '

o Downstream upto.10 km from tip of Tail Race Tunner (TRT).

(4) Details of the Methodolow

The methodology followed for collection of base line data along with details of number ofsamples and their locations in the map should be included, Study-area rfroufO be demarcatedproperly on tlie appropriate scale map. sampling sites shoula u. aepi.teiJoffiffi;;;parameter d,l,

ry9qer -legends. For forest classification, ctrarriion and S"A frq6s)classification should be followed.

(5) Methodolow for collection of Biodiversitv Data

- The number of sampling locations should be adequate to get a reasonable idea of thediversity and other attributes of flora and fauna. ftre'guiOing rd".6ffii;il1;;,,2*;tt tqav area (larger area should have larger numbEr of sampling tocatioiJ) i,irjT#r;;idiversity at the location, as known from sec,6ndury ro*".s (b"g. ealtern ii*auy* and lowaltitude sites should have a larger number of sampiing roruui"i-"*ine-il-tieilriaiilri,U;t'

- The entire area should be divided in grids of 5km X 5km preferuuty on a GIS domain.There afrei zsw of the grids should be iandornly selected zu r'*rpfinetri^]rr"rr -nafii;;;

be in the directly affected area (gnds- including-project components r"or, * i.re*uii]rrrr;powerhouse, tunnel, canal etc.) arra ure remuinlng fi tilr.j;i;;;;;Gr* of influencein 10 km radius form project components). At srich chosen location, th";;il;r#;;;sampling units (e.g. quadrats in case of flora/ransects in;;;i6;tffi;;;;;id;;;species area curves and the details of

!re.sag9 @raphs and ru*rruti* nu*Ler of species ina tabulated form) should be provided i.n the ereieiort. S;;;fth; ;;;;; ,lr;;-ds*;;;not be completely.overlapping with the study *.u uo*a*i"r. E;;;r-A;;;;ffiJEcounted and consid:t

9 tol seiecting 25Yo of ihegrids. rrr. r-*u., "i'-*iOr;;6, "rirv.jmay oome out as a decimal_number (i.e. it has an integral and a fractionjprrtl *fri;f,,h;"J;

be rounded to the next whole numbei.

- The conventional sampling is likely to miss-the presence of rare, enoangered and threatened(R.E'T.) species since they often occur in low densities and d d; ;if.*ri-rp;;;;

Page 22: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

(

dr

usually secretive in behaviour. Rgaching the conclusion abggt the _absence

of such species

in the stgdy area based on such *"thodology is misleading. trt is very important to

Jb.ir**t tfr" rt"t6 of such species owing to tireir high conservation value. Hence likely

pid;oiiort, species shor,rl'rl be ascertained fr_om seoondarv sources by a p1op9r literature'r*ry for the said area including referring to field guidgs which are.now available for many

t*ona*i. grorpr in India. Bven titerattne tom studies/surveys h,9. larger landscapes

which include the study area for the concemed project must be relferred to siRce most

species from adjoining iatchments is likely to be present in the catchments in qu9{i9na $6ct suctr literature fofo the entire state can be referred to. Onoe a listing of possible R.E.T. rrp*i6 iorm the said area is developed, species specific methodologies should be adopted to

t.-'

;;.d; flr;ir'pr.rro.. in the study area wtrictr iould be far more conclusive as.compared

to the conventional sampling. If the need be, modern methods like camera ilapping can b9

resorted to, particulanf foi areas in the eastern Himalayas and fo1 secretive/noctumal

species. A ietraited listiiry of the literature referred to, for developing lists of R.E.T. species

,i.ofA be providea in ttrJgtA reports..

. The R.E.T. species rdferred to in this point should include species listed in Schedule I and III ;iyiiAi.fe furotection) Act, 1972 and those listed in the red data books (BSI, ZSI and

IUCN). '

(6) Comnonents of the EIA Stirdv

Various aspects to be studied and provided in the EIAIEMP report are zls follows:

A. Physical and Chemical Environment.'Geological&GeophysicalAspectsandSeismo-Tectonics:

o Physipal geography, Topography, Regional Geological aspects and structure of the

Catchment.o Tectonics, seismicrry and history of past earttrquakes in the area. A site specific

earthquake design shall be sent for approval of the NCSDP (N{ional csmmittee ofSeismic Design Parameters, Cental water commission, New Delhi for large dams.

o Landslide zone or area prone to landslide existing in the study area should be

examined. :

. Presence of important economic mineral deposit, if any.

Justification for location & execution of the project in relation to structural

components (dam height)..

fmpact of project on geological environment.

Meteorolory; Air and Noise!

o Meteorology (viz. Temperature, Relative humidity, wind speed/direction etc.) to be

collected fio* o"*"st IMD station... Ambient Air Quality with parameters viz. Suspended Particulate Matter (SPM),

Respirable Suspinded Particul4te Matter (RSPM) i.e. suspended particulate materials

<10 microns, Sulphur Dioxide (SO, and Oxides of Nitogen (NOx) in the study area

at 6locatiqns.. f*irting

"oir. levels and traffic deniity in the study arca at6 locations

Soil Characteristics

Page 23: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

o soil classification, physic4 p.*qr.t:rs (viz., texture, porosity, bulk densiry and

::g^P.tgng capacity) and chemi.d la'#t '' (yi;.'ii,;il;hfi'.onductivity,magnesiumr calcium, total alkalinity, chlorides, ro&ror, potassium,

"rgr*ir r*U"i,

available potassium, available phosphorur, aAR, -nfid;;;;ijiiiry,

etc.) i6

Remofe sensing and GIS Studies

t Generation of thematic mlps viz., slope map, drainage frop, soil map, land use andap, eto. Based on these, trro*uti, *up;;;.*;i;r"t iriiv *+-ri""ri

De prepaxed

Water Quatity

o w-ater quality for both surface water.and ground ;;t"r "i iU physical parameters

(pH, temperature, erectricar conductivity, I5s)l (ii) chemic.l pararriil;(Afifit,Hardness, BOD, COD, NO2, pOa,_.CI,'3O+, iii K Ca, Mg, Sifioa, Oif'[Gre;1,phe.aolic corirpounds, residual sojium r*ug*irl Gtii

-Bril;;lU; ;.;;;,- g"rPI: Tgf cotifoun) and (1v) Heavy Metals (pb, is,'n& ca, Crfitotur cq cu,

o Delineation of sub and micro-watersheds, their locations and extent based on the AlllIndia Soil *t!q9 Uje S,rvey o.f rn&a telSrUSl O"p"*.i;;sffiffi;Govemment of India. Erosion levels in eacir *ioo-#atersii"o*Jft;tild;imicro-watershed through silt yield ford;(su) *.rrr.a

"f Alsius:

r-'v"'!r*EYu vr

Water Enyironment & Hydrolory

' Hy'dro-Meteorology ofge project viz..precipitation (snowfall, rainfaU), temperature,relative humidity, etc. Hydro-meteoroligi.ur rtuo.r'tr il;;i;#;'areu sr,oura ue

fgl}-Pd along-with real time telemetry and data *dritio" il,.* l"r inflows :

' [ff:f,il?*n*o water availability for the project, sedimentationrate, etc.o Basin characteristics - :

o CatasJrophic events like cloud bursts and flash floods, if any, should be documented.o For estimation of Sedimentation Rate, direct sampling of iu.r no;is-rfir'd.;;{d"q the_EIA studv, The study.rlorld b";;;;tJ il*#t;;;ffi:

o let up a G&D monitoring station and a few rain i.g. r",ions in the catchment areaforcol1ectingdata.dtrringtheinvestigation.o-'o-,--,-_-.-o Flow series, l'0 daily withgoyo,T5% and50% dependabre years dischargeso Information on the lO-daily flow basis for th9 ed per cent dependable i** a" no*iniercepted at the dam, theho* ai*rte;i; til;H;; ior* and the ,pr11 #ffii;;

the environmental flow and additional flow towards downstream of6;-d*, ilth;o The minimum pnvironmental flow shall be2}Yoof the flow of four conseoutive lean l

months of 90Yo -dependabre

yeag 30yo "ith; ;r;-rrg, monsoon flow. The fl;; fb,remaining months shall be in between 2o-30yo, i.p."a"g ;;- th. ;;;;;;;11il

yelireaents. A site specific study shall be currieJ orffi;;;pr* Jr**i'*ior.' Pdplogical studies/data asi approved by cwc shall be utlir.j in iii.-inrpu*tion of ,

EIA/EMp reporr. Actuar hydrological annual yi;il;;), d; b, ;i;;ii rriiliii."'

Page 24: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

.it.li/a1 \." rlttrl +,,i .1

!.'i

.l

o Sedimentaiion data available with CWC may be used to find out the loss in storageover the years.

o A minimum'of I km distance from the tip of the reservoir to the tail race tunnelshould be maintained between upsteam and downsteam projects.

C Biological Environment

Besides primqfy studies, review of secondary datalliterature published for project area onflora & fauna including RET species shall be reported in EIA/EMP repofi.

Flora

o Characterization of forest types (as per Champion and Seth method) in the study areaand extent of each forest lype as per the Forest Working Plan.

o Dooumentation of all plant species i.e. Angiosperm, Gymnospbrm, Pteriodophytes,Bryophytes (all groups). ,

. General u.g.tutitn profile and floral diversity oovering all groups of flora includinglichens and orchids. A species wise list may be provided.

o Assessment of plant species with respect to dominance, densrty; frequency,abundance, diversity index, similarity index, importance value index (IVI) , ShannonWeiner index etc. of the species to be provided. Methodology used for ealculatingvanous diversity indices along with details of locations if quadrates, size oiquadrates etc. to be reported within the study area in different ecosystems.

. Existence of National park, Sanctuary, Biosphere Reserve etc in the study area, ifany, should be detailed

o F.conomically important species like medicinal plants, timber, fuel wood etc.. Details of endemic species found in the project area.. Flora under RET categories should be documented using Intemational Union for the

Conservation of Nature and Natural Resources (IUCN) criteria and Botanioal Surveyof India's Red Data list along-with economic significance. Species diversity

"r*Lfor RET species should be given;. Cropping pattern and Horticultural Practices in the study area.

i

Fauna:

o Fauna study and inventorisation should be carried out for all groups of animals in thestudy area. Their pre:sent status atongwith Schedule'of the species.

'1 . Documentation of fauna plankton (phyto and zooplankton), periphyton, benthos and

o lnformation (authenticated) on Avi-fauna and wildlife in the study area.o status'of avifauna their residenu migratory/ passage migrants etc.o Documentation of butterflies, if any, found in the area.o Details of endemic species found in the project area.o RET species-voucher specimens should be collected along-with GPS readings to

facilitate rehabilitation. RET faunal species to be classified as per IUCN Redbatalist and as per different schedule of Indian Wildlife (Protection) Act,1972.

o Existence of barriers and corridors, iiany, for wild.animals.o Compensatory afforestation to'compenrut. tlr" green belt area that will be removed,' ifany, as part of the proposed project development and loss of biodiversity.. Ciillection of primary data on agricultural activity, crop and their productivity and

inigation facilities components.

Page 25: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

o For categoization of sub-catchment into various erosion ,classes and for theoonsequent CAT plan, the entire catchment (Indiarr Portion) is to be considered andnot only the directly the draining catchment

Aquatic Ecolory

.invertebrates, zooplankton,

o Fish and fisheries, their migration and breeding grounds.o Fish diversrty composition and maximum length & *eight of' the measured

populations to be studies for estimation of environmental flow; ,

o Conservation status of aquatic fauna.o Sampling for aquatic ecology and fisheries and fisheries must be conducted duringthree seasons - Pre-monsoon (summer), monsoon and winter. Sizes (engh &weight) of important fish species need'io be collected and Ur.rOiog=*i ffiir;

E Socio-Economic

-' Collection of baseline data on human settlements, health status of the community: and existing infrastructtue facilities for social welfare includin!. rorir6g df

population. -t ^Cotte"tion

of information with respgct to social awareness about the developmentalactivity in the area and social welfare measures existing and proposed byprojectproponent.

r Colleciion of information on sensitive habitat of historical;.uft*f and religious andecological importance.

' The socio-economic survey/ profile within 10 km of the study area for demographicprofile; Economic Stucture; . Developmental Profile; Agricultural prttices;Infrastructure, education facilities; health and sanitation facilities; availablecommunication network etc.

o Documentation of demographic, Ethnographic, Economic Structure anddevelopment profile of the area.

o Information on Agricultural Practices, Cultural and aesttretic sites, lnfrastructurefacilities etc. e

o Informatio.n on the dgpendence of the local people on minor forest produce and theircattle gazingrights in ttre forest land.

' List o1 all -th;

Project Affected Families with their name, og€, educationalqualification, family size, sex, religion, caste, sources of incomelf*a & house

loldings, other properties, occupation, source of income, house/lanil to be acquiredfor the project and house/land left with the family, any other property, possession of

o Special attention has to be given to vulnerable groups li.ke women, aged persons etc.

(7) Impact Prediction and Mitisation Measures

The adverse impact.due to the propose,cl p*jrrl should be assessed and effective mitigationsteps to abate these impacts should be described.

Air Environment

Page 26: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey
Page 27: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

o Positive and negative impacts likely to.be accrued due to the project are listed.(S) Environmental Management plans j

l' catchment Area Treatment (cef) -r{an should be prepared micro-watershed wise.Identification,o{ free arainine/ oif:1r., d;;irirg;;i,-ent-.based upon :Remore sensing andGeographical Information svstlm rcrsi*.tt"a"i"gi"iia suaiil"tyfiki'Inde{ (syl) method ofAISLUS' Deptt' of Agriculture, Govt. "r

mJiu .oriiJ*ith ground,survey. Areas or watershedsfalling under 'very severe' and''ssvrr4 .r;ri.r;;grries should be provided and rgquired to betreated' Both biological as well as engineering *"d;"s should be proposed in consultation withstate Forest Depar[nent for ** rrqiiring ddrr;;-iear-wise ,riirdureorwork and monelaryallocation'strouta be prwided. rvritigation ;.d;;; ctrect s.hifting cultivation in the oatclrmentarea with provision for alternative ui'a u.ttrr rg'i.uitu*ipr"*lres should be included. .2' compensatory Afforestation shall be prepare! by ttre srate Forest "*;;;;

t ,r", of theforest land proposed to be diverted or conrtu"iion;f tilr projecl * p", ii', ilrest (conservation)Act' 1980' choice of plants for afforestation should-inciri; ili,l"ff iiC ,pgoirs,, if any. Thiswill be a part of the foiest clearance proposal.

' 3' Biodiversif and wildlife conservati* "14 .IUaygement

plan for the conservation andproservation ol.t*t endangered or endemio- flo'iaufaunal species or some National ,Pa'lc/sanctuarvl Biosphere Reslrve "r;td;;;;iL; ir. s"iriirlu. ur"*ua directry orindireotly by construciion ofthe prqiect, tr,* riit"6r" cinservatioiiaJrruriirrrould be prepared inconsultation with the state Foresi Drp"iliilil;d*;;ffiffiH?l"ri|6, detals. suitabreconservation techniques (in*itu/ex-situ) *ilii;;"p"*i und* the plan and the areas where suchconservation is proposed will be marked on u prgj"riLyort *up.

4' Fisheries conseryation and Managemer, Pl;-; rr".* fisheries nianagernent measuresshould be prepared for river *o ,.r""*oii. ir tt r .""rlrrtio.n or fish ladder/ fish-way etc. is notfeasible then measures for reservoir nrt rri.r *iiiuu"ffirca. The plan will detail out tho numberof hatchtiries' nurseriest' rearilg ponds .rc. propgrcd"qn'd9r the plan with proper drawings. trf anymigratory fish species is gettifu'atrertrg tfi fi1ii,ilfo routes,.time/season of upstream anddownstream migration, spiwnin-g grounds etc will ur al.uriua in aetaits. -----

5' Resettlement and Rehabilitation Ptan needed to be prepared on the basis of findings of thesocio-economic survey coupled withtheoutcomr-"t*[it;.ooruituti"n r,riil rr* nan:packageshall be prepared afteiconsrttationi"itr, the reprrs;diies orure project affected families and ttreState Government. Detailed budgetary estimates are to ue provided. Resettlements site should beidentified. rhe pran wlr arso il;rpd;;ffirililulior*"* strategies;6' Green Belt Devetopment Plan along tho periphery of the reservoiq uppr*rt ioads around ttrecolonies and other project.o*ponrnL,

loca pr*i"p*bs^m1st be suggested with physical andfinancial details' A iayout -up tt o*iog the propos"J'rito ro, developing the green belt should beprepared - :7 ' Reservoir Rim Treatment Ptan for stabilization of land sride / land- slip zones, if any, around thereservoir pe.pheY is to.be-prepared based onE;td ;riry of golory of the reservoirrim area. ,suitable engineering and biotogicut ,r*rr. f#;;rr;;;; ofidentified slip zones to bo:suggestedwith phvsical and financial scf,edule. a"t;;"p ;hffig the landstide/landslip zones shalt beprepared and appended in the chapter. ' r, qrv

lqrvouue'r'urfrD"r @'vr eucu us

8' Muck Qisposat PIan suitable sites for -dlqning of excavated materials should be identified, in l

consultation with state Pollution contror Boi';;J atrtr'F";J6rd;;lin *u.t disposalsites should be minimum 30;-;*"v;;irrTriri'"ffi The quantiry of,muck to bo generatedand the quantity of muck ry"potta?o te utilized rh"ll b; c-arcutatea in "orJt tion with the projectauthorities. Detairs of each dumping ,itu "ir. _i;;;""b. dl;ffiil;tu.r that can bedumped etc' should be worked'ouiana discussed ioidii*. pr"ii i"rirr,uuilitation of muckdisposal- sites should also be given. rh' i-ili;rl;;;'filr#;il;;'iTisposal sites,and

Page 28: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

'1

lnI .i- - 11:. (' \.; -l:i

l:1 approach roads should be given. Th" pl* *r.at fye npsfcal and financial details of the medsures

proposed. Layout map showing the dumping sites'vis-d-vis other project components will be

prepared and appended in the chapter.

g. Restoration plan for Quarry Sites and landscaping of colony areas, working areas, roads. etc'-ffii[ ;i *ru

"oarreltii, e aggregate/clay etc. t"ifuir"a for construction of the projeot *9 +"

,o"p"tuy qo*i"rhir"r;houi-ri6 identified for the project should be.discussed along'with the

Engineering and Biological measures proposed. for.ttreii restoration with physical-and financial-d&"i-;y"";i ilp sho"wing quarry sites vis-d-vis other project oomponents, should be prepared.

10. Study of Design Earthquake Parameters: A site specific study of earthquake parameters shou! *

be dorre. Results of the site specific earthquake design parameters should be approved by National

Committee.of Seismic Design Parameters, Central Water Commission (NCSDP), New Delhi'

ll. Dam Break Analysis and Disaster Management Plan The outputs oldT break model should^ -

il;il;;J*itf, upp-priate graphs and-maps clearly bringing oq the impact of Dam Break

;il;t,r il iAentid,'ininautioi *r^, population and structues likely to be affected d}e t9

catastrophic floods in the event of dam irifrr., DMPwill be prepared lith the help of Dam B**;;rr[:-Mr.imurq water level that would be attained at various points on the downstream in

ou* tf du,n Ureat witt be marked on a detailed contour map of the downsteam area, to show the

extent of inundation. The action plan will include Emergency Action and Management plan

inolud-ing measures like preventive action notification, warning procedure and action plan for co-

ordination with various authorities

12. Water, Air and Noise Management Plans to be implemented during construction and post-

construction periods.

13. Public Eealth Delivery Plan including the provisions of drinking y1eT-.:upqly.for local-t p"prLtiqorhdf be in thi EIA/EMP Report. Status of the gxisting medicalfacilities in the project

ird" shail be discussed. possibilities of itrengthening of existing medical facilities, construction offfi *rAi"A infr*troeture etc. will be

"*plo..d after assessing the need of the labour force and

' local populace.

14-. Labour Management Plan for their Health and Safety.

'15. Sanitatign and Solid waste management plan for domestic waste from colonies and labour oamps

re. il."r Area Development plan to be formulated in consultation with the Reyepug offrcials.and

Village Pancatrayats. Appropriate schemes shall be prepared under EMP for the Local Area

Development Plan with sufficient financial provisions.

17. Environmental safeguards during construction activities including Road Construction.

18. Energr Conservation Measures for the w-o$ f9rc9 -during construction with physical

-a1dfrnaniial daails. Alternatives will be proposed for the labour force so that the exploitation of the

natural resource (wood) for the domestic and commercial use is curbed.

19. Environmental Monitoring Programme tp monitol thg mitigatory measures implemerrkd T.!htproject site is required will be pripared. Provision for Environment Management Cell should be

ir"a,". The plah wiil spef out the aspects, required to be .-qoolitored, monitoring

indicatorypararmeters with respect to each aspect and the agenoy responsible for the mo:ritoring ofthat particular aspeot throlghout the project implementation.

20. A summary of Cost Estimates for all the plans, cost for implementing all the Environmental

Management Plans.

Page 29: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

KIRTHAI HYDRO ELECTRIC PROJECT

STAGE – II

( Jammu & Kashmir )

DETAILED PROJECT REPORT

VOLUME – 0

EXECUTIVE SUMMARY

OCTOBER , 2015

Page 30: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

CONTENTS

CHECK LIST A

SALIENT FEATURES I

EXECUTIVE SUMMARY 9

1.1. Introduction 1

1.2. Access to the Project Area 2

1.3. Climatic Conditions in the Project Area 2

1.4. Historical Background of the Project 2

1.5. Earlier Proposals 3

1.6. Alternative studies 4

1.7. Splitting of Kirthai storage scheme into two stages 5

1.8. Kirthai Hydro Electric Project stage-I 5

1.9. Kirthai Hydro Electric Project Stage-II 6

1.10. Study of alternative dam sites for stage-II 6

1.11. Selection of Dam Site and Power house 7

1.12. Proposal for revision of DPR 7

1.13. Important Project Features 8

1.14. Need for the Project 14

1.15. Direct Benefit 15

1.16. Geological and Seismic Studies of Project area: 17

1.17. Construction material : 21

1.18. Hydrological studies 21

1.19. Power Potential Studies 27

1.20. Land and Population Affected by the Project: 33

Page 31: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

1.21. Environmental Aspects 34

1.22. Project Headquarters and Residential Accommodation at Project Site 35

1.23. Project Set Up 36

1.24. Evacuation of Power to be generated at Kirthai Hydro Electric Project Stage-II 37

1.25. Construction Programme 37

1.26. Interstate / International Aspects 37

1.27. Cost Estimate 40

1.28. Cost of Energy Generation 40

1.29. Photographs of the Project site Error! Bookmark not defined.

Page 32: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

CHECK – LIST

Page 33: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Check List Page A

CHECK LIST

I GENERAL DATA

1 Name of the Project Kirthai Hydro Electric

Project-II

2 Location

a State(s) Jammu & Kashmir.

b Districts(s) Kishtwar

c Taluka(s)/Tehsil(s) Padder

d Longitude/Latitude

Longitude 760 - 04' - 37" E to 760

- 00' - 52" E

Latitude 330 - 18' - 41" N to

330 - 19' - 20" N

e Survey of India Topographical Map reference

No.(s)

Degree Sheet SOI

No. 52c

f Earthquake Zone Zone- IV

g Complete address for Correspondence along

with Pin Code/e-mail

Chief Engineer (IBO),

CWC, Block IV, 6th

Floor,KendriyaSadan,

Sector-9,

Chandigarh160009.

[email protected]

3 Category of the project

a Power Project / Multipurpose Power Project

b Storage/Run of the river Run of the River

Scheme

II PLANNING

4 Has the Master plan for overall development of

the river basin been prepared and stages of

basin development discussed?

Yes

Page 34: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Check List Page B

5 Have the alternative proposals (including set

of smaller developments viz-a-viz a single

large development) been studied and their

merits and demerits discussed?

Yes

6 Does the scheme fit in the overall development

of the river basin and has its priority in the

overall development of the basin been

discussed?

Yes

7 Have the other Departments concerned with

the development been informed?

Yes

8 Is the present scheme proposed to be

executed in stages? If so, are its various

stages of execution and development

discussed in the report?

Yes, The Project

Kirthai HE Project is

being developed in

two stages i.e KHEP-I

and KHEP-II

9 Are the effects of the scheme on the riparian

rights & existing upstream and downstream

projects etc. discussed?

Yes

10 Has the provision for municipal and industrial

water supply been made?

NO

III INTERSTATE AND INTERNATIONAL

ASPECTS

11 Are there any International/ Interstate issues

involved? If so, have these issues been

identified and present status of agreement or

tribunal decision indicated specially in respect

of

No international/

interstate aspect

involved.

a Sharing of water No interstate aspect

involved.

b Sharing of cost No interstate aspect

involved.

c Sharing of benefits (irrigation, flood control, No interstate aspect

Page 35: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Check List Page C

power etc.) involved.

d Acceptance of the submergence by the

upstream state(s)

No interstate aspect

involved.

e Acceptance by the upstream state(s) of

compensation of land coming under

submergence

No interstate aspect

involved.

f Settlement of oustees No interstate aspect

involved.

g Any other No

IV SURVEYS

12 Have the detailed topographical surveys been

carried out for the following items and maps

prepared as per prescribed scales

a River surveys Yes

b Reservoir surveys Yes

c Head-works surveys(dam(s),dyke(s), etc.) and

auxiliary components)

Yes

d Plant and Colonies sites Yes

e Canal (s), branch canal(s) and water

distribution system

NA

f Major canal structures NA

g Power house, switch-yard, surge shaft,

tailrace

Yes

h Tunnel(s), Adit(s), Penstocks etc. Yes

i Surveys (detailed and sample) of areas of the

command for OFD and drainage works

NA

j Soil surveys Yes

k Surveys for soil conservation Will be done at

Preconstruction Stage

Page 36: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Check List Page D

l Any other surveys i.e. archaeological, right of

way, communication etc.

Yes

V GEOLOGICAL INVESTIGATIONS

13 Have the geological surveys for the following

items been carried out and report on geology

of the following appended?

a Region as a whole Yes

b Reservoir Yes

c Headwork and energy dissipation area Yes

d Power house and appurtenances Yes

e Intakes and regulators Yes

f Major canal structures NA

g Tunnel(s),Penstock(s),hill(s) etc. Yes

h Communication routes Yes

i Any other

VI SEISMIC INVESTIGATIONS

14 Has the seismicity of the region been studied

andco-efficient of vertical/ horizontal

acceleration for the various structures

discussed?

The region falls in

Zone-IV. The study of

site specific seismic

spectra has been done

by CWPRS and The

designs have been

done

accordingly.

15 Has the approval of the Standing Committee

for recommending design of seismic

coefficients for River Valley Project been

obtained?

16 Is there possibility of liquefaction of

foundations? If so whether liquefaction studies

been carried out?

No

VII FOUNDATION INVESTIGATIONS

Page 37: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Check List Page E

17 Have the detailed foundation investigations

(including in-situ tests and laboratory tests) for

the following structures been carried out and

detailed report(s) appended?

a Earth and rock fill dam(s) NO

b Masonry/concrete dam(s) Yes

c Barrage(s)/Weir(s)/head regulators) etc. NA

d Canal( s) & Canal Structures NA

e Power House(s), Tunnel (s), Transformer

Cavern, Desilting chamber (s), Surge

tank(s)/shaft(s), Intake(s).

Yes

f Pump House(s) Yes

g Any other Complete foundation

investigation for

Concrete Dam was

done

18 Are there any special features affecting the

designs?

No

VIII CONSTRUCTION MATERIAL SURVEYS

19 Have the surveys and laboratory tests for the

following construction materials been carried

out and report(s) appended?

a Soils for impervious, semi-pervious and

pervious zones of earth and rock-fill dam(s)

NA

b Sand Yes

c Rock and coarse aggregates Yes

d Bricks and tiles Standard Items will be

used

e Pozzolona Standard Items will be

used

Page 38: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Check List Page F

f Cement and lime stone Standard Items will be

used

g Steel Standard Items will be

used

h Any other Survey and laboratory

tests for rock

material has

done

fill

been

20 Have the sources for each of the above

material been identified and need etc.

indicated?

Yes

21 Have the proposals for procurement of scarce

materials been indicated?

No such item

IX HYDROLOGICAL AND METEOROLOGICAL INVESTIGATIONS

22

(a)

Have the hydrological and meteorological

investigations been carried out and status of

following data discussed in report?

i Rainfall Yes

ii Temperature Yes

iii Sunshine No

iv Gauge & Discharge Yes

v Sediment Yes

vi Water quality Yes

vii Evaporation Yes

22

(b)

Has the above data been collected

&appended?

Yes

X HYDROLOGY

23 Is the hydrology dealt with in detail in a

separate volume? Have its brief details been

included in this Report?

Yes

Page 39: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Check List Page G

24 Have an index map and bar chart showing

locations of various hydro-metric, climatic and

rainfall stations existing/ongoing/planned

water resources projects and the data

availability at those stations been attached?

No

25 Have required detail note about project specific

hydro-meteorological data

Yes

observatories been attached.

26 Have required detail in case of Himalayan

rivers, if project being planned in upper

reaches, the satellite imageries of project

catchment especially one during snowmelt

period (March-May) and one during monsoon

(June-September) period been attached?

No

27 Are detail notes about quality, consistency,

Processing and gap filling of the data

included.

Yes

28 Have hydrological studies been carried out for

the following:

a To establish the availability of water for the

benefits envisaged?

Yes

b To determine design flood for the various

structures (spillway, barrage etc.)

Yes

c Sediments storage Yes

d Design flood for diversion during construction Yes

e Tail water rating curve Yes

f Evaporation rates from reservoirs/concerned

area

Yes

g Command area rainfall Not applicable

29 Has the Ground Water Potential (existing use

and additional availability) been indicated?

No

Page 40: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Check List Page H

30 Have the studies regarding reservoir

sedimentation been carried out and revised

elevation-area capacity curves been used in

the simulation studies (Working Table)?

Yes

31 Have the ecological requirements of water

such' as low flow augmentation and water

quality control etc. and water requirement for

Domestic, industrial use and power

Yes

generation (thermal, hydel, nuclear)been

considered and included in the Project Report

and incorporated in the simulation studies?

32 Have the details of the simulation studies

(Working Tables) and conclusions arrived

from the various alternatives explaining the

factors and assumptions been included and

discussed?

Yes

33 Has the number of failures for different

aspects been indicated?

Yes

34 Have the likely desirable and undesirable

Changes in the hydrologic regime due to the

project been brought out in the report?

Yes

35 Is the criteria adopted for selection of the

construction diversion flood discussed?

Yes

36 Has the basis for determining the storage

capacity been discussed?

Yes

37 Have integrated working tables (for more than

one reservoir in the system) been prepared?

Not applicable

38 Has carry over storage been provided? If so,

whether studies for most economic carry over

storage been done?

Not applicable

Page 41: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Check List Page I

39 Have the flood routing studies been carried

out?

Yes

40 Have the back water studies been carried

out?

Yes

XI LAND ACQUISITION AND RESETTLEMENT OF OUSTEES

41 Have the type and quantum of land proposed

to be acquired in the submerged area, project

area required for rehabilitation of the oustees

been detailed?

Yes

42 Is the basis for provision for land

compensation indicated?

No, will be taken at

pre-construction stage

43 Have the rehabilitation measures, amenities

and facilities to be provided to the Project

affected Persons been discussed and whether

their provisions included in the report? Are

these in accordance State's policy/project,

specific policy/draft national policy for

rehabilitation and resettlement?

Yes

44 Are the basis of land acquisition of the

submerged area upto FRL/MWL etc.

discussed

Yes

XII DESIGNS

45 Does the state have established a Central

Design Organization and State level

multidisciplinary Advisory Committee and

whether its' composition has been indicated in

the report?

Not applicable, design

is carried out CWC.

by

46 Has the selection of final location of the head

works and appurtenances, in preference to

the other sites investigated, been discussed?

Yes

Page 42: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Check List Page J

47 Have the layout of the project viz location of

headworks, workshop sheds; offices, colonies

etc, been finalized and discussed?

Yes

48 Has the layout of the various major

components of the head works been

discussed in the light of site features, geology,

foundation characteristics etc?

Yes

49 Have the detailed designs been prepared for

the following components and got vetted by

CDO?

a Earth or rock fill dam, masonry or concrete Detail design is

dam, spillway, Barrage, weir etc. and

appurtenances.

prepared by Design

wing of CWC.

Detail design is

prepared by Design

wing of CWC

b Energy dissipation arrangements, training

walls etc.

c Openings through dams-galleries head

regulators penstocks other outlets, sluices

d Regulators.

e Canal and water conductor system

f Canal structures

g Pump house ,intake structures

h Power House, tunnels, surge shaft

i Instrumentation

j Power evacuation arrangement Prepared by CEA

k Design of Hydro Mechanical equipments Detail design is

prepared by Design

wing of CWC

Page 43: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Check List Page K

50 Have the salient features of the above

components and the assumptions made in

the design of above components of the

project been indicated and their basis

discussed?

Yes

51 Have any model studies been carried out for

location of the dam, spillway and other

appurtenances and checking the design profile

of the spillway, energy dissipation

arrangements location of outlets/ regulators

etc?

Model studies will be

carried out in Pre-

construction stage.

52 Has the final alignment of canal(s) and branch

canals(s) been discussed in the light of various

alignments studied?

Not Applicable

a Does the canal design provide for meeting

requirements of rush irrigation?

Not Applicable

b Have any intermediate storages and tail tanks

been considered to reduce the canal

capacities?

No

53 Are the canals and distribution system being

lined and if so what is the minimum capacity of

the channel proposed to be lined?

Not Applicable

54 Is the location of canal structures on main and

branch canals fixed after detailed surveys of

the final alignments?

Yes

55 Are the regulation arrangements of the

offtaking channel both near and away from the

cross regulators discussed?

NA

56 Are sufficient escapes including terminal

escapes provided on the main/branch canal

distributaries/minors?

NA

Page 44: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Check List Page L

57 Have the basis for adopting water way for the

cross drainage works been discussed?

NA

58 Have the proposals for rating the canal

section by providing standing wave flumes,

rating of the falls, broad crested

weirs,Vnotches etc. been discussed for the

canal and distribution system?

NA

59 Have any model studies for major canal

structure(s) been carried out and if so are the

results discussed and incorporated in the

design?

Model studies will be

carried out in Pre

construction stage.

XIII FLOOD CONTROL AND DRAINAGE

60 Have the various flood control components of

the Hydro Electric project been indicated?

Yes

61 Have the damage areas in pre-project & post

project situations been identified and flood

intensities worked out at each of the damage

Yes

centre(s) which gets affected?

62 Have the following flood aspects been

discussed?

a Flood cushion in the reservoir Yes

b Maximum moderated flood out flows over the

Spillway etc. andits frequency.

Yes

c Existing and proposed safe carrying capacities

of the channel below the dam after

construction of flood embankment, channel

improvement, river diversion etc.

Yes

d Synchronized moderated peak floods due to

release from the dam upstream and

unintercepted catchment upto the damage

centres.

Yes.

Page 45: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Check List Page M

e Average annual expenditure incurred on flood

relief works.

Yes

f Area and population affected/likely to be

affected before/after the project.

Yes

g Estimated saving in annual loss of life,

property, cattle, crops etc. (evaluated in terms

of money) due to flood control.

Yes

63 Have the following drainage aspects of

command area been discussed?

a Existing Surface and sub-surface drainage

network and problems of the drainage,

congestion, water logging, alkalinity/salinity If

any.

No

b Studies on sub soil water table (premonsoon,

post-monsoon etc.).

No

c Maximum intensity of 1, 2 and 3 day rainfall. Yes

d Deficiencies in farm drains. Not applicable

e Deficiencies in existing natural drains. No

f Proposal for improvement of drainage/water

logging / alkalinity/salinity of the area along

with justification thereof.

Will be taken up at

pre-construction

stage.

g Identification of the area in Command which

will get benefited due to execution of drainage

net- work and benefits thereof in terms of relief

from crop damage, increased yields etc.

Will be taken up at

pre-construction

stage.

XIV. NAVIGATION

Page 46: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Check List Page N

64 Is the present scheme for remodeling of the

existing facilities and/or extension of the

navigable reach or establishing new navigable

reach?

Not applicable.

65 Is the existing inland transport system being

fully utilized? If not, have the bottlenecks in its

fully utilization been identified and discussed?

Not applicable.

66 Have the surveys for goods and passenger

traffic been carried out and discussed?

Not applicable.

67 Is the extent of modification required in the

existing system discussed and justified?

Not applicable.

68 Do design for the canal section and structures

take into account the navigation

requirements?

Not applicable.

69 Have the proposals to develop the new

scheme and phases of development in the

different reaches been discussed?

Not applicable.

70 If the area is being served by inland water

transport, have the following been discussed:

a The existing toll rates and registration fees for

the crafts (size wise).

Not applicable.

b Proposals for revision of tollage rates and Not applicable.

fees, if any.

c Concurrence of the competent authorities

for revision of rates and fees.

Not applicable.

d Proposal to subsidies the tariff, tollage, craft

registration fee, passenger fare etc. to attract

traffic.

Not applicable.

71 Has the State Inland Water Authority been

consulted while finalizing the scheme and its

view point discussed?

Not applicable.

Page 47: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Check List Page O

72 Has economic justification and viability of the

navigation component of the multipurpose

project been discussed?

Not applicable.

XV. POWER

73 Have the following points been discussed?

a Availability of the power generating capacity in

the state as well as in the region from different

sources.

Yes

b Total energy available and peaking capacity of

the system in the state as well as in the region

from different sources.

Yes

c Integrated operation of the system and present

status of utilization in the state as well as in the

region.

Yes

d Surplus and shortfalls in the system in the

state as well as in the region.

Yes

e Future plans of power development from

different sources in the State/ region.

Yes

f Fitment of the scheme in planning of power

development of the State/ region.

Yes

g Energy generated from the project firm power,

seasonal power and total power.

Yes

h Proposal for transmission lines connecting to Yes

the existing system/ grid.

i Project cost per KWH installed and per KWH

generated at bus bar as compared to the

different hydro- electric, thermal generation

and gas projects and different sources in the

State as well as in the region to justify the

power component of the project.

Not available.

Page 48: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Check List Page P

j Whether the proposed addition to the

transmission system has been shown on a

geographical map. Whether options

considered for the proposed addition have

been discussed with statement of justification

for the selected option after carrying out

supporting studies covering load flow studies,

short- circuit studies (three phase and single

phase and stability studies.

Yes

k *Whether sufficient' Surplus off Peak power is

available for pumping of water from lower to

upper reservoir.

Not applicable

l *Actual off peak energy requirement of

proposed scheme.

Not applicable

m *Cost of peak-and off peak energy

(*for pumped storage schemes only)

Not applicable

XVI CONSTRUCTION PROGRAMME AND PLANT AND MANPOWER

PLANNING.

74 Are the major components of work proposed

to be done departmentally or through

contractor?

Through Contractors.

75 Have the various alternative construction

programme been studied and proper

Yes

justification furnished for the final programmed

adopted?

76 Has the proposed construction programme

been prepared and synchronized for timely

completion of each of the major component of

work?

Yes

77 Have the year-wise quantities of the following

materials of construction been worked out for

various components of the project.

Yes

Page 49: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Check List Page Q

a Excavation separately in soft and hard strata Yes

b Earthwork in filling impervious, semi- pervious

and pervious

Yes

c Rockfill for dam toe, riprap etc. Yes

d Stone for masonry Yes

e Coarse aggregate for concrete Yes

f Sand for filter, masonry/concrete Yes

g Gravel for Filter Yes

h Steel of various sizes and type Yes

i Cement-normal, quick/slow setting with or

without pozzolona, special types

Yes

j Lime-surkhi-pozzolona Yes

k Scarce material-special steel Yes

l Other material-fuel, electricity, explosive etc Yes

78 Have the year wise quantities to be executed

by machine/ labour for each of the major

component been worked out for each of the

above material?

Yes

79 Have the labour intensive items of the various

major components of the project been

identified and the quantities of such items

worked out?

Yes

80 Have PERT chart or CPM diagrams for Yes

construction programme of various

components been made and included in

report? Has organizational setup and

frequency for project monitoring been

indicated in the Report?

XVII FOREIGN EXCHANGE

Page 50: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Check List Page R

81 Have the details of the plant and machinery,

spares, instruments and scarce materials to

be imported worked out?

NA, all machineries

and scarce materials

are indigenous.

82 Has the phasing of imports and source (s) of

imports been discussed item wise?

Not applicable

83 Are the imports to be affected under foreign

grants/credits or internal resources of the

country?

Not applicable

84 Is the scheme covered under State sector or

Central sector?

Central sector

XVIII FINANCIAL RESOURCES

85 Has the concurrence of the State Finance

Department been obtained?

Not applicable

86 Is the scheme included in the Five Year/

Annual Plan? If not what is the present position

regarding its inclusion in the plan?

Will be included at

appropriate stage.

87 Whether the scheme has already been

started? If so, is the present stage of

construction indicated?

No

88 Have the year wise requirement of funds

been indicated?

Yes

89 Is the scheme covered or proposed to be

covered under any foreign assistance/ aid

agreement?

No

XIX ESTIMATE

90 Is the separate volume of estimate attached Yes

as appendix?

91 Is the year to which the rates adopted in the

estimate relate to indicated?

Yes

Page 51: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Check List Page S

92 Have the analysis of rates for various major

items of work for the major components of the

project been furnished and with basis of

analysis described?

Yes

93 Are the provision for the following items

made on the basis of sample survey and

subestimates:

a Distributaries, minor and sub-minors Yes

b Water courses Yes

c Drainage Yes

d CAD Works Yes

XX REVENUE

94 Are the bases for the following sources of

revenues furnished?

a Betterment levy and proposal for its recovery Yes

b Irrigation cess Not applicable

c Flood protection cess Yes

d Crop wise water rates Not applicable

e Sale of water for village/ city/industrial/ power/

water supply

Not applicable

e Miscellaneous

95 Have these rates been compared with the

existing rates at the other projects in the

State/ region?

Yes

96 In case the rates are being enhanced, has

the concurrence of the concerned

department(s) been obtained?

Not applicable

97 Have the organizational set up for the

collection of revenue been indicated?

No

Page 52: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Check List Page T

XXI B.C RATIO

98 Is the allocated cost for the following

components of the multipurpose project

worked out and basis therein furnished?

As KHEP-II is a Hydro

Electric Project

a Irrigation Not applicable

b Power Not applicable

c Flood Control Not applicable

d Navigation Not applicable

e Water supply Not applicable

f Any other No

99 Have the various departments of the State/

Centre agreed to the sharing of the above

allocated cost?

Will be taken up on the

basis of this DPR

100 Have the crop wise benefits been worked out

for irrigated and un-irrigated crops being

grown before project in consultation with the

agriculture department and statement

furnished?

Not applicable

101 Have the crop wise benefits been worked out

for proposed cropping pattern after the

introduction of irrigation in consultation with

the agriculture department and statement

furnished?

Not applicable

102 Is the B.C. ratio of Irrigation Projects

acceptable or otherwise justified?

Not applicable

103 Is the B.C. Ratio for Flood Control Projects

acceptable or otherwise justified?

Not applicable

104 Is the B.C. ratio for power component of the

project acceptable or otherwise justified?

Not applicable

105 Have the financial and economic return Yes

Page 53: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Check List Page U

statements been furnished keeping in view the

phasing of development?

106 Are the benefits other than those considered in

the B.C. Ratio and financial return statement

been identified?

Yes

107 Is the benefit from Gall per land, if proposed,

based on lease rates admissible and

statement from concerned Central/State

authorities furnished?

Not applicable

108 Are the benefits from fisheries, horticulture, if

proposed, based on lease rates admissible

and statement from concerned Central/ State

authorities furnished.

Not applicable

XXII ECOLOGICAL ASPECTS

109

a

Is the area likely to have any of the

following environmental and ecological

problems due to the altered surface water

i Excessive sedimentation of the reservoir and

the upper reaches of the river andits tributaries

tailing into reservoir.

No

ii Water logging, salinity/ alkalinity No

iii Quality of surface and ground water Will not effect.

iv Ground water recharge Will not effect

v Health hazards-water borne diseases,

industrial pollution etc.

No

vi Submergence of important minerals No

vii Submergence of monuments/

archaeological sites

No

viii Fish culture and aquatic life Will improve

ix Plant life (flora) Will not effect

x Wild Life Will not effect

Page 54: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Check List Page V

xi Migratory birds Will attract

xii National parks and sanctuaries Will not effect

xiii Seismicity due to filling of reservoir Will not effect

xiv Likely change in the regime of the river No

xv Any other

109

b

Have the environmental and forest

clearances from MOE&F been obtained? If not

what is status thereof?

Under process.

XXIII COLONIES AND BUILDINGS

110 Has the planning of the colony/ building been

done keeping in view the ultimate use for

optimum utilization of investment?

Yes

111 Has an estimate of the extent of higher cost

involved been made and details discussed?

Not applicable

112 Are the permanent buildings being constructed

required for maintenance of the project only?

Yes

113 Can the buildings other than required for

maintenance of the project being constructed

be put to some other use after the completion

of the project by the department or any other

agencies?

Permanent colony has

been planned based

on the requirement of

operation of the

Project after

executionand rest of

structures were

planned as temporary

and semi permanent.

114 Have the interested agencies been consulted

in planning of the buildings to suit their

requirements later on?

Will be consulted at

pre-construction

stage.

XXIV PUBLIC PARTICIPATION AND COOPERATION

115 Have the proposals for disposal of temporary

buildings been discussed?

Not applicable

Page 55: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Check List Page W

116 Are the possibilities of these been discussed

In:

a Planning Will be discussed at

pre-construction stage

b Construction Will be discussed at

pre-construction stage

c Improved agricultural practices NA

d Any other

117 Have-public debates about utility of projects

been: held and the response thereof outlined

in the Report?

Will be done at

preconstruction stage

Page 56: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

S A L I E N T

Page 57: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey
Page 58: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey
Page 59: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-I-A: Salient Features Page I

SALIENT FEATURES

The following salient features (and any others) as applicable to the project, shall be

furnished:

1 Name of the project KIRTHAI HYDRO

ELECTRIC PROJECT – II

(KHEP – II)

2 Type of project HYDRO-ELECTRIC

3 Location

Tehsil Padder

District Kishtwar

State Jammu & Kashmir

3.1 River Basin

a) Name CHANDRA BHAGA

(CHENAB)

b) Located In

i) State(S) Jammu & Kashmir (J&K)

ii) Countries (if International River) India

3.2 River Chenab

3.3 Name of village near the Head-works Village: Kirthai

Tehsil : Padder

3.4 Location of Head-works

(a) Longitude 760 - 04' - 37" E

(b) Latitude 330 - 18' - 41" N

(c) Seismic Zone IV

3.5 Location of Power House

(a) Longitude 760 - 00' - 52" E

(b) Latitude 330 - 19' - 20" N

(c) Seismic Zone IV

3.6 Project area reference to Degree Sheet SOI No. 52c

3.7 Access to the project Name Distance

a) Airport Jammu 298 km

b) Rail head Udhampur 232 km

4 International/ Interstate aspects of the project

4.1 Submergence due to

projects

In J&K 1.4 km2

Page 60: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-I-A: Salient Features Page II

4.2 Catchment area at Headwork Site 9987 km2

4.3 State-wise / Country-wise details of

catchment area

a) Up to International Border 29050 km2

b) In Himachal Pradesh 7844 km2

c) In Jammu & Kashmir 21206 km2

4.4 Upstream Projects

i) Future Projects Kirthai-I, Barinium, Shuas,

Reoli-Seli

4.5 Downstream Projects

i) Projects Completed Dul-Hasti, Baglihar, Salal

ii) Projects Under Construction Ratle, Sawlakote

iii) Future Projects Kiru, Kwar

5 Hydrology

5.1 Catchments area at headwork site 9987 km2

5.2 Climatic Data

5.2.1 Name of Station(s)and period of record

S.No Names Period of Record

1. Gulabgarh 1992 2015

2. Koksar 1983 2015

3. Tandi 1974 2015

4. Udaipur 1974 2015

5. Arthal 1967 1991

6. Premnagar 1967 2015

5.3 Seismic Coefficients

a) Horizontal 0.219g

b) Vertical 0.146g

5.4 Design Flood (m3/s) 9600

5.5 Mean Minimum Discharge (m3/s) 58.22

Page 61: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-I-A: Salient Features Page III

6 Reservoir

6.1 Water Levels (El-m)

a) Full Reservoir Level (FRL) 1764.00 m

b) Minimum Draw Down Level (MDDL ) 1750.75 m

c) Invert Level for Power Intake 1731.80 m

6.2 Free board (m) 2

6.3 Live Storage 17 MCM

7 Submergence

7.1 Land and property submerged at MWL

a) Revenue villages affected (no.)

(i) Fully ‘Nil’

(ii) Partially 2 no’s (Liae & Kirthai)

b) Land affected (ha)

(i) Gross 140

(ii) Govt. 33

(iii) Private 37

(iv) Forest 70

c) Buildings/houses

(No.)

(i) Houses 5 no’s

(ii) Govt. ‘nil’

(iii) Temples ‘nil’

(iv) Mosques ‘nil’

(v)Govt school s ‘nil’

(vi) Pvt. school ‘nil’

(viii)Lift

Irrigation

‘nil’

d)Tube Wells (No.) ‘nil’

Page 62: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-I-A: Salient Features Page IV

e) Road (km.) under submergence 4.5

8 Headworks

8.1 Type of Dam Concrete

8.2 Height of Dam (m) 121.00

8.3 EL of Dam at top (m) 1766.00

8.4 Length of Dam at top (m) 219.80

8.5 Length of Dam at the river bed (m) 68.00

8.6 Width of Dam at Top (m) 11.50

8.7 Spillway (overflow section)

a) Location of spillway In Dam Body

b) Type of spillway Sluice Spillway

c) Length (m) 93

e) Max height above the deepest

foundation (m)

121

f) Crest level (EL-m) 1712.50

g) Number of gates 5

h) Type of gate Radial

i) Size of gate (mxm) 9 x 12.248

j) Energy dissipation arrangement Ski-Jump type

8.8 U/S Coffer Dam

a) Height of U/S coffer dam (m) 25.50

b) EL of top (m) 1680.10

8.9 D/S Coffer Dam

a) Height of D/S coffer dam 10.50

b) EL of top (m) 1662.10

8.10 Diversion tunnels

a) Total number of diversion tunnels One

b) Diameter of each diversion tunnel

(m)

10.50

c) Length of diversion tunnel (m) 600.20

Page 63: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-I-A: Salient Features Page V

9 Power

9.1 Installed Capacity (MW)

a) Main Power House (MW) 840

b) Dam Toe Power House (MW) 90

9.3 Firm Power (MW) 118.80

9.4 Head Race Tunnel

a) Length (m) 4289

b) Shape Circular

c) Size (m) 10.5 Ø

d) Lining Type PCC upto RD 4.00 m

RCC Beyond RD 4.00 m

e) Thickness of Lining (m) 0.6

f) Design Discharge (m /s) 413.47

g) Invert Level (EL-m) 1725.00 (at RD 0.0)

9.5 Intake

a) Type Bell Mouth

b) Size (m)(after Bell Mouth Transition) 5.785 m x 6.40 m

b) No. of Intakes Four

c) Intake Gates

i) No. of Service Gates Four

ii) No. of Emergency Gates Four

f) Design Discharge (m3/s) 124.04

g) Invert Level (EL-m) 1731.80

9.5.1 Intake Tunnels

a) No. of Intake Tunnels Four

b) Dia. (m) 6.4

9.6 Desilting Chamber

a) No. of Desilting Chambers Four

b) Size (m) 440 x19 x 24.874(depth)

Page 64: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-I-A: Salient Features Page VI

3

c) Efficiency 90 % (to be finalized

after the model study

report)

d) Type of Gate Fixed wheel with

upstream skin plate and

upstream seals (HRT

side)

e) No. of Bays 4

f) Clear Width of Gate (m) 4.70

g) Clear Height of Gate (m) 6.40

h) Sill Level (EL-m) 1728.97

i) Design Head (m) 35.03

9.6.1 Silt Flushing Tunnels

a) No. of Silt Flushing Tunnels Four

b) Opening Size 3.6 m x 2.5 m

9.7 Surge tank/shaft

a) Nos. & location (HRT) One, At HRT RD 4289m

b) Type, height (m), & size (m) Circular, 91.875 m high

& 31.6 Ø

c) Top level (EL-m) 1800.00

d) Bottom level (EL-m) 1723.00

9.8 Penstocks/pressure shafts:

a) Number, diameter & length of

Pressure Shaft

3 Nos, 5.25 m Dia &

827 m long

b) Liner type Steel Liner

c) Grade of steel ASTM 537 CL-

II/ASTM517 Gr F

d) Bifurcation/trifurcation Bifurcation

9.9 Main Power House

a) Type Under Ground

Page 65: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-I-A: Salient Features VII

b) Average Gross Head (m) 232.08

c) Average Net Head (m) 225

d) Design Discharge (m3/s) 413.47

e) Dimensions (m) 187.5 x 22 x 49.7

f) Unit capacity (MW) - 140

g)Installed capacity (MW) 840

h) Type of turbine Francis

i) Type of PH crane EOT

j) Number and size of draft tube 6 Nos. With 5.1 m Dia.

9.9.1 Tail Race Tunnel

a) Length (m) 352.50

b) Maximum tail water level (EL-m) 1532.50

c) Minimum tail water level (EL-m) 1527.50

d) Average tail water level (EL-m) 1530.00

10 Dam Toe Power House

a) Intake In Dam Body (NOF

Block 9)

b) Size of Intake 4.555 m wide and 5.80

m high

c) Penstock Dia. (m) 5.8

d) Bifurcation/Trifurcation 5.8 m dia. bifurcated into

2 penstocks of 5.1 m dia.

and 2.7 m dia. 5.1 m dia.

penstock further divides

into two unit penstocks of

3.6 m dia. each, 2.7 m

dia. penstock further

divides into two unit

penstocks of 2.7 m dia.

each

e) Type Surface

f) Average Gross Head (m) 103.04

g) Average Net Head (m) 99.95

h) Design Discharge (m3/s) 99.71

Page 66: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-I-A: Salient Features VIII

i) Dimensions (m) 78.525 x 24 x 36.5

j) Unit capacity (MW) 2 x 10 + 2 x 35

k)Installed capacity (MW) 90

l) Type of turbine Francis

m) Type of PH crane EOT

10.1 Tail Race Channel

a) Length (m) 51

b) Maximum tail water level (EL-m) 1658.30

c) Minimum tail water level (EL-m) 1656.00

d) Average tail water level (EL-m) 1657.15

11 Estimated Cost of Project ( In Crores) 5158.00

12 Cost of Power Generation (`/Unit) 2.06

Page

Page 67: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

EXECUTIVE SUMMARY

Kirthai Hydro Electric Project Stage-

II

930MW (6 x 140 + 2 x 35 + 2 x 10) MW

DETAILED PROJECT REPORT

EXECUTIVE SUMMARY

October 2015

Page 68: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey
Page 69: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 1

EXECUTIVE SUMMARY

1.1. Introduction

The state of Jammu & Kashmir lies between 32 17’ to 37 05' North latitude

and 72 26' to 80 30' East longitude. The geographical area of the state is 2,

22,236 Sq.km. The population of the state as per the census of 2011 is

12541302 persons, with population density of 124 persons per sq. km and

decadal population growth rate of 23.64%.

Kirthai Hydro Electric Project Stage-II is a run of the river scheme on the River

Chenab and is located in tehsil Padder of district Kishtwar of Jammu and

Kashmir. The proposed dam site is about 13 km downstream of Kirthai Hydro

Electric Project Stage-I. Kishtwar town is about 58 Km downstream of the

proposed dam site. The dam site is located at 33 18’ 41’’ N and 76 04’ 37”E.

The Powerhouse is proposed at Lidrari which is about 8 km downstream of the

dam site. The power house site is located at 33 19’ 20’’ N and 76 00’ 52”E.

The location plan of the project is presented at Annexure-1. The lay out plan

of the project is presented in Annexure-2.

Total Installed capacity of Kirthai Hydro Electric Project Stage-II has been

proposed as 930 MW.The Firm Power of the project is about 118.80 MW. The

installed capacity of main power house is 840 MW and that of Dam toe power

house is 90 MW. The water from the dam would be diverted to an underground

power house near Lidrari on the left bank of the Chenab river through 4.289 km

long HRT for power generation with an installation of 6 units of 140 MW each

operating under a net head of about 225m.The annual energy generation

benefits from the project at the main power house which is underground have

been estimated as 3160 MU in 90% dependable year with annual design

energy generation benefits as 3055.89MU. The average load factor of

operation of the main power house during lean period would be about 10.1%

ensuring peak operation of the main power house for about 2.4 hours daily.

Annual Plant load factor of the main power house would be about 43%.

Page 70: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 2

In addition, a dam toe power house with 2 units of 35 MW each and another 2

units of 10 MW each have also been envisaged to utilize the flows to be

released directly from the dam into the river for environmental purpose. The

annual and the design energy generation benefits at the dam toe power house

have been estimated at about 307.19 MU and 296.17 MU respectively in 90%

dependable year.

1.2. Access to the Project Area

As of now, the proposed Project site can be approached from Jammu Airport

and Jammu Railway Station through Jammu - Kishtwar National Highway up to

Kishtwar, which is 240 km away from Jammu. Beyond Kishtwar up to Project

site there exist an all weather road maintained by BRO. The dam site is 58 km

away from Kishtwar and power house site is 50 km away from Kishtwar . Both

dam site and power house site of the project are on road head of existing

Kishtwar -Gulabgarh- Sansari road . Nearest railway station is Udhampur which

is 232 km from Project site.

1.3. Climatic Conditions in the Project Area

The climate of Project site is temperate. There is snowfall during winter season

and summer is very pleasant. The average monthly rainfall is about

1048mm.The winter is very cold and recorded temperature in winter is very low.

1.4. Historical Background of the Project

To utilise the share of water of river Chenab as per Indus Water Treaty, a

perspective plan for power potential of Chenab Basin was initiated and 14

schemes were identified during the 1st meeting of Chenab Co-ordination

Committee under the erstwhile Ministry of Irrigation and Power, Govt. of India

held on 19-11-1961. The fourteen schemes identified were as under.

Table 1 Schemes identified by Chenab Co-ordination Committee S.No. Name of

Scheme

Name of

river

Installed

capacity

Catchment area

(Sq.Km)

Investigation

assigned to

1 Baglihar Chenab 450 17325 CWC

Page 71: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 3

2 Bardang Chenab 115 4817 H.P

3 Bursar Marusudar 1020 2937 CWC

4 DulHasti Chenab 390 10500 CWC

5 Gypsa Chenab 240 1311 H.P

6 Kirthai Chenab 750 6625 CWC

7 Naunatoo

Naigad

Chenab 400 9959 J&K

8 PakalDul Marusudar 1000 2965 CWC

9 Raoli Chenab 500 H.P

10 Rattle Chenab 180 14600 CWC

11 Salal Chenab 345 21497 J&K

12 Sawalkot Chenab 600 19480 CWC

13 Seli Chenab 165 5750 H.P

14 Thirot Chenab H.P

Out of these 14 schemes identified for investigations, Central Water

Commission (CWC) was entrusted with the responsibility of investigations of 6

schemes, whereas Govt. of J&K and Govt. of Himachal Pradesh (H.P) were

allocated 3 and 5 schemes respectively. Central Water Commission completed

the investigations of all the 6 schemes as entrusted to it.

Govt. of J&K and Govt. of H.P could not complete the investigation work as

assigned to them. As Govt. of J&K could not do the investigation work for the

Kirthai H.E. Project, the investigation work of this scheme was also handed over

to CWC by Govt. of J&K in July 1988.

1.5. Earlier Proposals

The Kirthai Storage scheme was originally proposed to create 0.6 MAF storage

on the river Chenab as permitted under the Indus Water Treaty between India

and Pakistan (1960). Initially, it was envisaged to have a 212 m high concrete

dam near village Kirthai (76º-6’-12” E, 32º –17’-10” N) in Padder valley of Distt.-

Kishtwar, J&K, so that the wider portion of the river valley between Kirthai and

Atholi could be utilized for optimum possible storage. It was proposed to provide

8 km long Head Race Tunnel (HRT) with underground Power House located at

Lidrari (76º-1’-6”E & 33º-10’-33”N) to produce 750 MW power. The scheme

remained under preliminary investigations by the Power Development

Page 72: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 4

Department, J&K, from year 1977 to 1988, when it was taken over by the

Central Water Commission in 1988 for feasibility studies.

After taking over the work of investigation of Kirthai Storage scheme by Central

Water Commission, it was found that the proposed Dam axis will submerge the

beautiful Padder Valley, the only valley in the upper reaches of the Chenab

with, agriculture land of about 643 hectares and forest area of about 1760

hectares. Central Water Commission tried to identify alternative dam sites with

power house at Lidrari.

1.6. Alternative studies

Four alternative dam sites across River Chenab were identified and studied by

Central Water Commission in consultation with the GSI. The entire four

alternatives are shown at Annexure-3.

1st Alternative Site was located downstream of village Kirthai with underground

power house at Lidrari. For this alternative three dam sites all downstream of

village Kirthai were studied.

2nd Alternative Dam Site was identified upstream of Gulabgarh suspension

bridge. This site was located near Gulabgarh. The river Chandra Bhaga

(Chenab) flows through a deep gorge for a few kilometers upstream of the

suspension bridge. The proposed dam axis was 250 m upstream of the

Gulabgarh bridge. The site was studied for a high concrete dam and 18 km long

Headrace Tunnel was proposed leading to an underground power house near

Lidrari nallah.

3rd Alternative Dam Site was same as of alternative 2nd but power house site

was within or near the body of dam.

4th alternative Dam Site was identified at Silper/Kidur with underground power

house at Lidrari.

All these alternatives were studied in detail by CWC in association with GSI and

a high dam at any of the alternative was not found feasible. The 1st alternative

Page 73: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 5

had proposed dam site downstream of Kirthai village and high dam at any of

proposed locations of this alternative would have submerged land of Padder

Valley. The 2nd alternative had proposed dam site upstream of Gulabgarh

Bridge. The problem of submergence of Padder valley was avoided but the

proposed 18km long Headrace Tunnel had to cross many nallahs on its way.

The Geological features en-route would have posed many tunneling problems

besides non-availability of suitable construction Adits. Though some locations

for adits are available, these would be very long. The completion of such a long

Head Race Tunnel would invite innumerable construction problems.

After detailed comparative study of all the four alternatives it was found that

combination of 3rd and 4th is best for this scheme. This combination allows full

exploitation of power potential available in this reach of Chenab river and would

avoid submergence of precious land of Padder valley.

1.7. Splitting of Kirthai storage scheme into two stages

After detailed desk studies and visits of inter-disciplinary teams of CWC, GSI &

CEA, Kirthai storage scheme was decided to be split into two stages i.e.

Kirthai Hydro Electric Project stage-I and Kirthai Hydro Electric Project StageII.

Both the stages have been proposed to be run of the river schemes. The Dam

site of Kirthai Hydro Electric Project Stage-II was proposed near Silper or Kidur

with Underground Power House at Lidrari.

1.8. Kirthai Hydro Electric Project stage-I

The dam site of stage-I was proposed about 250m upstream of Gulabgarh

Bridge. Soon after finalizing the Dam axis and Power House locations, CWC

started detailed field investigation. Field investigation work of the project was

affected considerably due to non-conducive conditions in the state during 1993-

99 due to which work remained suspended during that period. Hence, the DPR

of the Project could be submitted in 2003. Keeping in view the provisions of

Indus Water Treaty, Kirthai H.E Project stage-I has been planned as run of the

river scheme and only 3 M cum of storage for peaking purpose has been

provided. The installed capacity of the Project was proposed as 240 MW (4 X

Page 74: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 6

60) MW in DPR. A 160m high concrete dam with central spillway and

Underground Power House just downstream of Dam axis on left bank was

proposed for stage-I Project. The DPR of this Project has been handed over to

JKSPDC and at present it is in pre-construction stage. PMF Studies of Kirthai

–I was revised by CWC and PMF value was increased from 7400 cumec to

9140 cumec. The installed capacity of this project is now increased from

240MW to 390MW.

1.9. Kirthai Hydro Electric Project Stage-II

The releases from stage-I project was planned to be utlised by constructing

another project about 13 to 14 kms downstream of Gulabgarh. In addition, this

proposed project would utilize the flows of Bhutnala and Hanswar nala also,

which bring considerable flows even in the lean season. The power house site

for the Stage-II Project have been planned just upstream of Lidrari nallah

junction with the river Chenab. The power house would be Underground

structure and tail water would be carried to the main river through a Tail Race

Tunnel (TRT).

1.10. Study of alternative dam sites for stage-II

Two possible sites for Dam of Kirthai-II Project have been identified by CWC

and GSI viz. one near the place called Silpar about 5 km downstream of Kirthai

village and another just upstream of Kiddur Nala confluence which is about 1

km downstream of Silpar. The two alternatives are discussed as below:

1.10.1. Dam Axis near Silpar

This site is about 5 km downstream of Kirthai village. This site was found

suitable for a rock-fill dam also but clay for impervious core was not available

in that area. This site has granitic gneiss rock on both the banks. The width of

river bed at this site is about 70m. The river bed is approximately at EL. 1675

m and top of dam can be kept at EL.1760 m or so. The length of dam at dam

top would be around 250 m. The river reach is straight downstream of this dam

site for some length to ensure suitable energy dissipation. The length of tunnel

upto the underground power house near Lidrari would be approx. 6.0 km. It

Page 75: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 7

may be possible to have a number of construction Adits 300-400 m long each

to facilitate construction of tunnel.

1.10.2. Lower Dam Axis U/S of Kidur Nallah

This site is about 1000 m downstream of above site and is suitable for a

concrete gravity Dam. The river gorge is deep and narrow and the rock exposed

on both the banks indicates availability of granitic gneisses on both the banks.

1.11. Selection of Dam Site and Power house

Both the sites were studied in detail by CWC and GSI and based on

technoeconomic comparison, the site U/S of Kidur Nallah was selected. This

site has geological advantage over site at Silpar. Length of HRT and width of

dam is less for this site as compared to site at Silpar. The power house site was

also shifted 80m towards HRT on advice of GSI because on earlier site it was

found that lateral cover was not sufficient because of Lidrari nallah .Detailed

field investigations were started by CWC from 1998-99 but progress was

hampered considerably due to security issues because of militancy. The dam

and power house sites of Kirthai-II projects were located in isolated places away

from inhabited area and practically it was very difficult to carry out field

investigation works in project area due to security reasons. The Staff of CWC

tried their best and submitted the DPR in July 2010 after completing the field

works.The installed Power Potential of the Project was 990MW (6X165).

EIA and EMP studies of the project are being carried out by developer of the

project i.e. JKSPDC.

1.12. Proposal for revision of DPR

While carrying out power potential studies of the project it was felt by CWC,

CEA & JKSPDC that the intermediate Nallahs/ streams joining the river will be

sufficient for environmental flows. However, when JKSPDC made a

presentation in MoEF in March 2012, it was desired by MoEF that the exact

quantity of flows in these Nallahs/ streams be given. Since, there is no gauge

or discharge site of state or CWC on these Nallahs/ streams, the exact quantity

Page 76: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 8

of flows could not be given. However, an attempt was made to work out the

discharge with catchment area proportion. It was found out that the catchment

area of major Nallahs between downstream of Kirthai-II to outfall of TRT was

very less and was not sufficient for environmental flow as per latest guidelines

of MoEF. As per latest guidelines of MoEF, environmental flow releases should

be 20% of average of 4 lean months of 90% dependable years and 30% of

monsoon period from June to September.

A meeting was taken by Member (Hydro), CEA on 22.08.2012 at CEA, Sewa

Bhawan, New Delhi to review the status of DPR of Kirthai Hydro Electric Project

Stage-II. In this meeting representatives from JKSPDC, CWC, GSI & CSMRS

had participated and discussed the issue of environmental flow releases. It was

discussed that if environmental flow is released as per latest guidelines of

MoEF then there will be an overall effect on most of the parameters of the

project. GSI, Delhi has also raised certain observations regarding additional

drilling and drifting. It was decided in the meeting to carry out the additional

investigation works and revise the DPR.

Hydrology (N) directorate of CWC revised the PMF of Kirthai Hydro Electric

Project Stage-II from 7440 cumec to 9600 cumec on 20.2.2013. Power potential

studies of the project were revised based on latest guidelines of MoEF for

releasing of environmental flow. However, to utilise this flow to be released

directly from the dam into the river for environmental purpose, a dam toe power

house (located close to the dam site) have been envisaged with an installation

of 2 units of 35 mw and another 2 units of 10 MW .But still the installed capacity

of the project including capacity at dam toe power house was reduced to

930MW due to requirement of sufficient release of water for environmental

purposes.

1.13. Important Project Features

1.13.1. Concrete Dam:

A Concrete Dam 121m high has been proposed for Kirthai Hydro Power Project

Stage-II. The length of dam at top is 219.8 m .The overall length of the spillway

Page 77: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 9

section of the dam is 93 m comprising five numbers sluices each of 9m width

with crest elevation at El.1712.50 m and one maximum overflow spillway ogee

type of 4 m width, with crest elevation at El. 1760.00 m. The overall length of

the non overflow section of dam would be 126.80 m extending on both sides of

spillways. Considering Free Board requirements, the top of the dam has been

kept at El. 1766.00m. A 1.0 m high solid parapet wall has been provided on the

upstream side

1.13.2. Coffer Dams and Diversion Tunnel

For the purpose of managing the river during excavation of foundation and initial

construction of concrete Dam, a Diversion Tunnel of diameter 10.5m has been

proposed on the right bank of the river. Length of diversion tunnel is 600.20 m.

For diverting the water through diversion tunnel an upstream coffer dam of

25.50 m height has been proposed. The height of downstream coffer dam has

been kept at 10.5 m.

1.13.3. Spillway

The spillway is located centrally in the river portion. The overall length of the

spillway is 93 m with 5 nos. sluice bays of 9 m each and piers of 4.5 m width

each. The crest elevation of the sluice spillway has been kept at El. 1712.50m.

The sluice spillway has been designed for a peak flood of 9600 cumecs which

corresponds to PMF. A maximum overflow spillway of 4 m

Page 78: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 10

width has been provided in the pier of sluice. The crest elevation of the ogee

portion is at El. 1760.00m. The maximum overflow spillway has been designed

to pass logs and debris.

If the reservoir gets silted up to the crest level, there is possibility of boulders

rolling down over the spillway glacis. To avoid any damage to the spillway

surface due to rolling boulders, suitable protective arrangement has been

proposed by way of providing 0.5m thick high strength silica fume M50 grade

of concrete on the crest & glacis and around the sluice.

Energy dissipation arrangement

Various alternatives were considered for arriving at a suitable Energy

Dissipation Arrangement. It is found that only ski-jump type energy dissipation

arrangement will be effective. Further the bed rock is competent to withstand

the scour thrust.

Ski-Jump Bucket

A trajectory ski-jump bucket of radius 42.50m with invert elevation at

El.1678.75m and lip angle of 35 has been found to be sufficient for energy

dissipation purpose.

1.13.4. Power Intake

The FRL and MDDL of the Project reservoir have been kept at 1764.00 m and

1750.75 m respectively. The invert level of Intake is required to be kept

sufficiently low for preventing vortex formation at the entrance and sucking of

air into the tunnel at the lowest pond level (MDDL). For satisfying the above

requirements the center line of Intake has been kept at EL 1735.00 m.

Four Nos Bell Mouth intakes with invert level at EL 1731.80 m have been

proposed through the hill on the left bank of the reservoir. The design discharge

for the scheme has been worked out as 413.47 cumecs. The opening area of

size 5.785 m (width) x 6.40 m (height) has been provided after bell mouth

transition. Four numbers of power intake tunnels of 6.40 m dia. circular section

Page 79: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 11

have been provided to draw 124.04 cumec discharge (including 20% for silt

flushing discharge) off taking from intake to feed four nos. of underground

desilting chambers spaced at 65 m c/c. The length of the four intake tunnels

varies from 916.62 to 1022.98m. Concrete lining has been provided in the

intake tunnels. Lining has been designed for internal water pressure and has

been checked for external water pressure. Metal trash racks are proposed to

be provided in front of the intakes for preventing entry of floating debris of size

larger than 75 mm

1.13.5. Desilting Chambers

Provision of four nos. underground desilting chambers of size 440 m x 19 m x

24.874 m (depth) each have been made to remove the silt particles of size

greater than or equal to 0.2 mm at 90% efficiency. To facilitate the construction

of desilting chambers, a construction adit of size 7 m x 7 m Dshaped has been

proposed which will bifurcate into two adits of size 7 m x 7 m each to reach at

top and hopper portions of the chamber.

The silt deposited at the bottom of the desilting chamber is to be collected and

transported through the silt flushing conduit provided at the bottom. After

coming out from desilting chamber this conduit has been provided with a gate

to regulate the required discharge. All the four nos. of silt flushing tunnels, after

the gate, join into a single tunnel which finally drops the silt back into the river

Chandra Bhaga (Chenab). The outlet of the flushing tunnel would be sufficiently

d/s of the dam to obtain the required head for flushing while being above the

maximum river water level at the outlet location.

1.13.6. Head Race Tunnel

One circular tunnel of diameter 10.50m and length 4.289 km is proposed to

carry design discharge of 413.47 cumecs from Desilting Chambers to the

Underground Power House. It is proposed to provide two nos. of construction

adits for the HRT one each at start & end. A total number of four working faces

would be available for construction of the HRT. The slope of HRT has been

worked on the basis of the analysis of surge shaft for down surge case.

Page 80: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 12

The HRT is proposed to be constructed with a gradient of 1 in 296. The invert

level of HRT at RD 0.0 has been fixed in such a way that in no case during its

filling, the air is trapped between intake gate and HRT.

1.13.7. Construction Adits

The D- shaped section of size 7m x 7m has been adopted for the adits with a

mild slope towards adit portals to facilitate gravity flow of the seepage water.

The lengths of construction adits at upstream & downstream location of HRT

are 391.5m & 469.9m respectively.

1.13.8. Surge Shaft

Considering the geology and topography of the area, location of power house

complex, bore hole data and maximum surge level etc. the center line of

31.60m dia. Surge shaft has been located at RD 4289 m of HRT. From the

analysis, the maximum up-surge level works out as EL1790 m and minimum

down-surge level as EL. 1728 m. Accordingly, the top of the surge shaft has

been fixed at EL.1800 m giving sufficient water cushion over the maximum

upsurge level. Similarly a sufficient water cushion has been provided at the

junction of HRT with the surge shaft bottom. The over-all height of surge shaft

works out to 91.875 m and dia of surge shaft is 31.60 m. The surge shaft is

provided with a dome of size 37 m x 37 m with its top at EL. 1815.00 m. Three

nos. pressure shafts of 5.25 m diameter each off-take from the surge shaft at

centerline EL. 1711m. One Butterfly Valve Chamber of size 94 (L) X 12 (W) X

20.875 (H) has been provided downstream of Surge Shaft at 30m distance to

enable dewatering of the pressure shafts, when required, for carrying out

maintenance/ repair works for pressure shafts and main inlet valves.

A 7m x 7m D shaped Construction Adit of length 469.9m has been provided

towards the end of HRT for construction of both the surge shaft and HRT.

1.13.9. Pressure Shaft

Underground vertical/ horizontal pressure shafts have been proposed to convey

the water under high pressure from surge shaft to the power house.

Page 81: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 13

Considering the amount of discharge and head involved, as well as the number

of turbines to be fed, it has been decided to provide three steel lined pressure

shafts of 5.60m dia each. These Pressure shafts would emanate horizontally

and radially (60 apart) from the surge shaft at centerline EL 1715.75m. The

shafts would become parallel to each other after attaining a center line distance

of 35m between them. After traversing a horizontal distance, these shafts will

bend downwards vertically and run horizontally at EL.1521 m (center line of the

turbine nozzles), each pressure shaft bifurcating further, near the power house,

to a size of 3.75m dia, to feed the six generating units.

An 8m x 9m D shaped Construction Adit in the bottom horizontal portion of

pressure shafts has been provided for construction of pressure shafts and lying

of bifurcation pieces of steel liner.

1.13.10. Power house

Six units, each of 140 MW capacity with vertical axis Francis Turbine have been

proposed to be installed in the power house located on the left bank. The size

of Power house has been proposed as 187.50 (L) x 22m (W) and 49.70m (H)

respectively. The centre line of machine hall is kept at EL 1521m and the top

EL of Power House is 1557.50m.The generating units would be spaced at 22m

center to center.

The water emanating of the turbine/power house is carried through a circular

draft tube of 5.10 m. All the six draft tubes are provided with a gate, which will

be operated from transformer hall.

The Transformer and GIS Bay would be in an underground cavern located at

40m d/s of the power house cavern. The size of transformer & GIS cavern is

191 m (L) x 18 m (W). It accommodates 20 unit transformers at EL. 1534.00m

which is same as the service bay level. Gas insulated switches (GIS)

equipments will also be installed in this cavern at an EL. of 1543.50m.

Page 82: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 14

The water emanating from the draft tube fed into the river Chandra Bhaga

(Chenab) through 10.50 m dia TRT of 352.50 m length. The invert level of outfall

has been kept at E.L.1523.00 m which is below the TWL of 1527.50 m.

1.13.11. Dam Toe Power House

A dam toe power house has been planned for a design discharge of 99.71

cumecs. Four units of capacity, two of 35 MW each and two of 10MW each

have been proposed to be installed with vertical axis Francis Turbine in the

surface power house. Power House is planned on right bank of the river at the

toe of dam block number 9. Power Intake for dam toe power house has been

provided in the dam block. A 5.8m diameter steel penstock starts downstream

of intake gate transition, comes out at dam fall and runs down to EL 1650. A

bifurcation piece is provided to bifurcate 5.8m diameter penstock into two

penstocks of 5.1m dia. and 2.7m dia. penstocks. Further 5.1m dia. penstock

drops down to EL 1649m and bifurcates into two unit penstocks of dia. 3.6m

each. Similarly, 2.7m dia. penstock also bifurcates into two unit penstocks of

1.8m dia. each. Penstocks are covered with M15 grade of concrete below EL

1667m.A surface power house is provided in front of dam block number 9. The

bottom of power house is at EL 1639.5m. Service bay and machine hall has

been provided at EL 1658.30m. Transformer hall and GIS have been provided

behind the power house at EL 1659 m and EL 1667 m respectively.

Draft tubes of these machines are provided with a gate which will be operated

from the deck at EL 1659 m. The dimensions of surface Dam Toe Power house

is 78.525m X 24 X 36.5 m(H).

Tail race channel has been provided in form of draft tube which discharges the

power house discharge into river. It has a slope of 4(H): 1 (V) and has weir at

EL 1656m which is the minimum tail water level.

1.14. Need for the Project

Kirthai Hydro Electric Project Stage-II is a run of river scheme having both direct

and indirect benefits. Hydro power generation is the major direct benefit of the

Page 83: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 15

Project. In addition to this, there will be indirect benefits also such as fillip in

tourism, infrastructure development in the form of roads and buildings. Besides

this the Project will have a potential for employment generation which will help

in the socio-economic development of the people of the region in particular and

state in general.

1.15. Direct Benefit

1.15.1. Power:

The estimated hydro power potential of the State is 20,000 MW, out of which

about 16480 MW have been identified. Out of the identified potential, only

2456.2 MW i.e. 15 % (of identified potential) has been exploited so far,

consisting of 760.46 MW in State Sector from 21 power projects, 1680 MW from

four power projects under Central Sector i.e. {690 MW Salal, 480 MW Uri-I, 390

MW Dulhasti and 120 MW Sewa-II Hydel Projects} and 17.5 MW from two

private sector projects. The installed capacity of 760.46 MW from state sector

projects includes the 450 MW of Baglihar Phase–1. Due to resource

constraints, exploitation of the potential economic rejuvenator like hydro power

has been very steady. Besides, due to the constraints imposed by the

provisions of Indus Water Treaty between India and Pakistan preventing

storage of the water of Jhelum, Chenab and Sindh Rivers, these projects have

been constructed as run of the River projects. The State is therefore under

perpetually energy deficiency and has to rely on power purchase from Northern

Grid to meet its requirement particularly in winters, when its own generation

recedes and demand peaks. The graph given below depicts the identified,

harnessed and under construction power potential by J&K State and Central

Government.

Page 84: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage

DPR: Vol-0: Executive Summary Page 16

-II (930 MW)

Figure 1 Power Potential by J&K and Central Govt. (Source: J&K State HEP Development Policy 2011)

The demand and availability scenario (Energy in MU) of J&K is tabulated below:

Table 2 Demand and availability scenario (Energy in MU) of J&K YEAR 2007-08 2008-09 2009-10 2010-11 2011-12 2012-13

Energy

Requirement

(MU)

14037.00 14750.0 15656.0 16544.00 17323.0 17842.69

Energy availability

(MU) 8743.96 9147.21 10238.00 10667.00 11091.26 11465.58

Energy deficit

(MU) 5293.04 5602.79 5418.00 5877.00 6207.59 6282.66

Energy deficit (%) 37.71 37.99 34.61 35.52 35.83 35.21

The demand and availability scenario (Peak power - MW) of J&K is tabulated

below:

Table 3 Demand and availability scenario (Peak power - MW) of J&K YEAR 2007-08 2008-09 2009-10 2010-11 2011-12 2012-13

Energy Requirement (MW)

2020 2120 2247 2369 2500 2600

Energy availability (MW)

1350 1340 1407 1492 1788.9 1900

Page 85: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 17

YEAR 2007-08 2008-09 2009-10 2010-11 2011-12 2012-13

Energy

(MW) deficit 670 780 833 877 711.10 700

Energy

(%) deficit 33.17 36.79 37.07 37.02 28.44 26.92

The figure shows that from 2007-08 to 2012-13 the actual demand has

increased from 14037 MU to 17842.69 MU respectively. The power shortfall

has increased at an alarming rate. Recognizing the urgency and need of

development of hydro power, implementation of this project becomes very

important. The power of Kirthai Hydro Electric Project Stage-II will increase the

power availability of northern grid and J&K state will be benefited by this

additional power.

1.15.2. Indirect Benefits

1. Tourism

The artificial lake with a big water spread shall become one of the biggest

recreational spots in Padder area. It will attract more tourists for Machail Mata

yatra and hence increasing the tourist inflow and thereby increased revenue

collection from the region.

2. Infrastructure Development

Infrastructure like roads, bridges, buildings etc. will be built at a large scale at

the construction stage of the project which will ultimately benefit the local

population.

3. Employment generation

This project will create immense potential for employment generation as lot of

manpower both skilled and unskilled would be required during as well as after

the Construction of the project.

1.16. Geological and Seismic Studies of Project area:-

All the components of the project are located on the Pias Granite which is

intruded within the Kishtwar Window. The Kishtwar Window is a conspicuous

structural element of Higher Himalaya. It exposes Dul Quartzite enveloped by

Page 86: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 18

Salkhala Formation, which is tectonically overlain by the high grade

metamorphites (Central Crystalline rocks) along the trace of Main Central

Thrust. The rocks of Kishtwar Window are overriding the younger Salkhala

Formation along Kiaji Thrust.

Geology of Dam site :- River width along the dam axis is about 85 m. River

bed level as observed on the right bank is about 1660 m above m. s. l. Left side

hill slope upto road level i.e., RL 1717 m is almost vertical and 15 m from the

slope edge, slope is slightly less steep (65°).Right bank abutment slope is

comparatively less steep (40°) upto dam top. Above the dam top slope is steep

and high. Both the abutments appear to be quite stable. However, a prominent

joint set trending N50º to 55ºW –S50º to 55ºE and dipping 50º to 80º towards

SW i.e., towards river side, is recorded. Opening along this joint set is noticed

upto 20 cm. To avoid stability problems along the joint plane, removal of

unstable rock blocks are felt necessary. At the dam site, granite gneisses with

thin to thick pegmatite veins intruded in the rocks of Kishtwar Window are

exposed. The rocks are generally fresh, massive and hard. Four set of joints

have been recorded in the area but no major structural discontinuity in the form

of thrust or fault has been noticed at dam site. The dam axis is aligned in N83°W

to S83°E direction. The dip and strike of the foliation in the rock units along the

dam axis is N35ºW-S35ºE and dip 45º towards NE. No major structural

discontinuity has been noticed at the dam site and adjoining area and none is

expected at foundation grade. Geotechnical studies have indicated that rocks

exposed at the dam site are quite competent for the proposed dam.

Geology of Diversion tunnel:- The 600.20 m long diversion tunnel with a

diameter of 10.5 m is proposed to divert water of the Chenab River during the

construction of the dam. It is aligned through a ridge along right bank near the

dam axis. The hill slope towards the river varies from 50° to as steep as 70°.

The area along the proposed tunnel is occupied by granite gneisses with thin

partings of schistose rock. The general trend of the foliations varies from

N15°W-S15°E to N55°W-S55°E dipping 30° to 70° North-Easterly. The tunnel

alignment will more or less follow the strike of the foliations of rock mass, due

to which the rock exposed at the inlet portal may continue for the major part of

Page 87: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 19

the tunnel except near the out let portal where the tunnel makes a bend.

Reversal of the dip has also been recorded in the area due to folding.

Geology of Intake and Desilting chamber:- The detailed geological mapping

of the intake gates and desilting chambers was carried out on 1:1000 scale.

Both the components are located in the granite gneisses of Pias Granite which

is hard and fresh at the surface. The subsurface exploration of the dam body

was carried out which is located in the similar setup of rocks. The drift along the

left abutment of the dam axis is very near to the desilting chamber. No adverse

geological conditions were recorded during 3 D logging of drifts.

Geology of Head Race Tunnel (HRT) :- Headrace tunnel (HRT) is proposed

through left bank ridge made up of jointed to massive granite gneisses. Studies

reveal that 4.289 km long HRT along the left bank of Chenab river is aligned in

favorable Geological condition, almost cutting across the foliation / bedding

trend of the rock units represented by granite gneisses of Pias Granite, phyllites

and quartzite of Kishtwar Window exposed along the tunnel alignment. Two

thick bands of quartzite and phyllites of Kishtwar Window measuring 290 m and

950m are exposed along the HRT after crossing the Kidur nala and near

Shasho village. The minimum cover over HRT under Kidur nala is about 50 m

and maximum cover is in the order of 950 m. No major problem is anticipated

during the excavation of the tunnel except some wedge failures due to the

presence of shear seams which may cause over break.Water seepage problem

where the alignment is passing below perennial nalas cannot be ruled out.

Geology of Underground Power house :- The proposed powerhouse will be

located on the left bank hill just upstream of confluence of the Chenab River

with Lidrari nala. Detailed geological mapping of the underground power house

and tail race tunnel covering an area of about 0.075 sq. km was done. The

studies have revealed that massive and competent granite gneisses are

expected in the proposed underground power house and tail race tunnel. Rocks

are traversed by three prominent joints which are widely spaced. These joints

are also associated with shear zone varying in thickness from a few centimeters

to 3.5 m.The adjoining area also exposes phyllites and graphitic phyllite,

quartzites of Lopara Formation and Pias Granite as intrusive. The Lopara

Page 88: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 20

Formation is the oldest rock unit in the area and occupies the lower most

Stratigraphical position and show comparatively higher grade of metamorphism

and is represented by slates, phyllites and graphitic phyllites. The

granite/granite gneisses, occurring as intrusive bodies, are the other rock units

in the area. The granites are medium to coarse grained and foliated. The

general trend of the foliation is N45°W - S45°E and dip varying from 30° to 45°

north-easterly. The overall rock quality is good. Granitic gneisses are exposed

in the area of the Tail Race Tunnel (TRT) and traversed by joint.

Geology of Reservoir area :- Traverse geological mapping of reservoir area

was carried out along the rim of the reservoir to identify the major structural

features, landslide zone, low topography area and any submergence of mineral

deposits .The rocks exposed in reservoir area are white Quartzite, phyllite,

sericite schist, granite and granite-gneiss of Kishtwar Window. The general

trend of foliation is N35°W/25°NE. Three sets of joints have been recorded. The

rocks are generally massive and compact. The rocks are in blocky in nature.

Minor shear zone have been noticed during mapping. Tectonically, two major

thrusts namely Kijai thrust and Atholi thrust are passing through the area which

is upstream of the reservoir tail. No impacts of these thrusts have been noticed.

Minor shear zone and shear seams have been noticed. From the overall

assessment of the reservoir area and its periphery,it is inferred that there is no

possibility of water leakage in the adjoining valleys or basins as the water divide

along northern as well as southern periphery is above 4000 m above MSL

whereas, FRL of the reservoir is at 1764 m above MSL. Since the reservoir

periphery is occupied by slope debris/river terraces at places particularly in the

tail part of the reservoir, after filling of the reservoir sliding at some points along

the periphery is anticipated this may not have any effect on the competency of

the reservoir but may add to the siltation problems in the reservoir.

Seismic Studies of Project area: - The Kirthai Hydro Electric Project Stage-II

(KHEP-II) is located in the highly seismic Himalayan tectonic province, which is

having complex geological setup. The region of the project site has been

subjected to several large magnitude(≥ 7.0) earthquakes such as the 4th April

1905 Kangra and 19th January 1975 Kinnaur earthquakes and the relatively

recent 8th October 2005 event of magnitude 7.6 in the KashmirKohistan region

Page 89: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 21

near the India-Pakistan border to name a few. The project site is located in

seismic zone IV as per the zoning map of India (IS: 18932002, Part-1). Site-

specific design ground motion for KHEP-II site has been estimated by CWPRS

Pune by carrying out detailed analysis of the data on seismotectonic and

geological features and past seismicity in the region.

The site-specific horizontal design seismic coefficient for the dam is found to be

0.219 g dam. The corresponding vertical design seismic coefficients can be

taken as 0.146 g.

1.17. Construction material :

Five quarry sites for coarse and fine aggregate were identified in association

with GSI and CSMRS. The location of these quarry sites is given in below table.

Table 4 Location of the quarry sites Quarry site

number

Location

1 Road side opposite CWC old camp at village Kirthai

2 2.5 Km Upstream from Dam Axis near Trinalah.

Quarry site

number

Location

3 500 m Downstream from Shasu village

4 1km Downstream from Shasu village

5 1 Km downstream of Power House Lidrari

1.18. Hydrological studies

Chandra and Bhaga rivers join near Tandi in the districts of Lahul and Spiti in

Himachal Pradesh to form river Chenab. The Chandra and Bhaga originate

from the south-west and north-west faces of Baralacha Pass respectively in the

Himalayan canton of Lahaul and Spiti valley in Himachal Pradesh. Thereafter,

the river enters Padder area of Kishtwar district in J&K and is joined by

Bhutnallah at Gulabgarh. Chenab is also known as Chanderbhaga in upper

reaches up to Bhandarkot (Kishtwar).The River flows between steep cliffs of

high mountain up to project site. The river drains a catchment area of about

9987Km2 upto project site. The catchment area of the river up to dam site is

presented at Annexure 4.

Page 90: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 22

The estimated hydro power potential of the Jammu and Kashmir State is 20,000

(MW), out of which about 16480 MW have been identified. A major portion of

this hydro power potential i.e. about 9017MW is on river Chenab, which is a

veritable goldmine for the state, waiting to be harnessed. Cascade

development of hydro-power in Chenab Basin is shown in Annexure 5.

Water Availability Studies: The following stations discharge data has been

considered in water availability studies of the project:

Table 5 Discharge data has been considered in water availability studies Sr.

No.

Udaipur

( CA- 5764

Sq km)

Arthal

(CA- 7760

Sq km)

Benzwar

(CA- 10687

Sq km)

Premnagar

(CA- 15490

Sq km)

Gulabgarh

(CA- 8530

Sq km)

1 1973-2008 1973-1990 1967-2003 1967-2010 1991-2009

The data at Arthal is limited up to the period 1990 and it will be advisable to use

the updated data therefore the use of Arthal data for the purpose of

development of flow series at the project site in the first instance is ignored.

The consistency of data of Gulabgarh and Premnagar has been checked at first

instance and Regression analysis has been carried out between Gulabgarh and

Premnagar data for the following periods from 1990-91 to 2008-09:

1. June - October

2. November - February

3. March – May

The R value has been found 0.8684, 0.4024 and 0.8532 for the periods June

to October, Nov to February and March to May respectively.

Then, Regression analysis was carried out between Udaipur and Benzwar data

from 1973-74 to 2002-03 and R value found to be 0.8749, 0.6408 and 0.8944

for the periods June to October, Nov to February and March to May

respectively.

The results of the Regression analysis carried out between Benzwar and

Premnagar sites from 1968 to 2003 has been found better regression

Page 91: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 23

coefficients as R value obtained was 0.9063, 0.7271 and 0.9270 for the periods

June to October, Nov to February and March to May respectively.

Since the correlation between Benzawar and Premnagar sites have been found

better out of these combinations and also the data considered is of longest

period (1967-68 to 2002-03); and also as the catchment area up to Benzwar

site is close to the catchment area of the dam site of kirthai-II H.E Project, the

data of Benzwar site has been considered as base data and the data for the

period 2003 to 2010 at Benzwar has been derived considering the relationship

so developed between Benzwar and Premnagar for the periods June to

October and March to May due to good correlation coefficients mentioned as

below:

June to October

YB = 0.6242X+38.117 R=0.9063

March to May

YB = 0.5531X-26.108 R=0.9270

The relationship for the period November to February where the correlation

coefficient is poor, the data of Benzwar has been derived on 10 daily

coefficients to the remaining 8 months volume of flow with Premnagar annual

flow for the respective year. The completed data series was transposed at

project site Kirthai-II on the basis of catchment area proportion and the flow

series at the project site for the period 1967-68 to 2009-10 have been

completed.

Dependable flow at 50% and 90% has also been computed. The 90%

dependability is found to be 8908 MCM (1971-72) and the 50% dependability

is 11630 MCM (1982-83).

Design Flood Studies.

Page 92: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 24

Methodology

As the height of the proposed dam is more than 30m, the dam is classified as

high dam and design flood for fixing the spillway capacity will be Probable

Maximum Flood (PMF).

The Kirthai Hydro Electric Project Stage-II dam is proposed approximately 13

km downstream of the proposed Kirthai Hydro Electric Project Stage-I dam site.

The catchment area of Kirthai Hydro Electric Project Stage-II is 9987 sq.km and

catchment area of Kirthai Hydro Electric Project Stage-I is 8530 sq.km

respectively. The design flood for the Kirthai stage-II project is computed in two

steps. The PMF hydrograph of Kirthai stage-I is routed up to

Page 93: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage

DPR: Vol-0: Executive Summary Page 25

-II (930 MW)

Kirthai stage II and the contribution of intermediate catchment area between

two projects is added to arrive at needed PMF hydrograph of Kirthai Stage-II

project. The PMF of the Project is calculated as 9600 cumec.

Figure 2 PMF Hydrograph at KHEP-II Dam Site

Sedimentation Studies:

No site specific data is available. However, sediment data has been observed

by CWC in the basin at the sites mentioned below in Table 6 along with periods

of data availability.

Table 6 Sediment data observed by CWC at various sites in the basin

S.No. Site Stream CA(sq.km) Period

1 Tandi Bhaga 1530 1977-78 to 2014-15

2 Ghousal Chandra 2490 1978-79 to 2014-15

3 Benzwar Chenab 10687 1972-73 to 2002-03

4 Tillar Marasudar 2800 1968-69 to 1994-95

5 Sirshi -do- 3335 1968-69 to 1994-95

6 Kuriya -do- 3960 1969-70 to 1989-90

7 Premnagar Chenab 15490 1968-70 to 2014-15

Page 94: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 26

S.No. Site Stream CA(sq.km) Period

8 Dhamkund -do- 18750 1968-69 to 2014-15

9 Akhnoor -do- 21808 1971-72 to 2014-15

10 Jammur

Tawi Tawi 2168 1977-78 to 2014-15

Analysis of sediment data

After analysis of sediment data, the average annual sediment rate of sites have

been worked out, which is given in Table 7 below. Benzawar site is located

quite close to this project site where average annual sediment rate, based on

observed data of 30 years, has been computed as 0.8625 mm/yr. Since, Kirthai

H.E. Project (stage-I) has been planned for a sediment rate of 1.072 mm/yr, the

same rate has been used for Kirthai HEP-II also for computation of sediment

volumes for various time horizons.

Table 7 Average Annual sediment rate at different sites (without bed load)

S.No Name sites Average annual sediment rate

(mm/yr)

1 Tandi 0.249

2 Ghousal 0.320

3 Gulbargah 0.599

4 Benzawar 0.8625

5 Tillar 0.301

6 Sirshi 0.677

7 Kuriya 0.63

8 Prenagar 0.974

9 Dhamkund 1.304

10 Akhnoor 0.751

11 Jammu 1.120

Estimation of New Zero Elevation and Revised Capacities using

Empirical Area-Reduction Method.

Kirthai Hydro Electric Project Stage -II is downstream of Kirthai H.E. project

stage-I. As per MOWR guidelines, only existing or under construction projects

Page 95: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 27

are to be considered as trapping sediment on the u/s of a dam under planning.

However, as per BIS code, projects having same priority as the projects under

study may be considered as trapping the sediment. Accordingly, sedimentation

studies of Kirthai-II dam have been carried out considering both the scenarios,

i.e. with and without Kirthai-I HE Project.

Case-A-Entire catchment upto Kirthai-II contributing to the sediment inflow

(without Kirthai-I project)

Case-B- Kirthai-I is trapping sediment and balance is coming to Kirthai-II. New

Zero elevation after 70 years of sedimentation works out to 1746.3 m in Case-

A and 1741.4m in Case-B and the same are recommended for design

purposes.

1.19. Power Potential Studies

Input Parameters for Study

Studies for assessment of power benefits have been carried out by Central

Electricity Authority (CEA), New Delhi taking into account the Environment

Flows as well as without Environment Flows for which flow data is available.

The following parameters have been considered for the studies:

Table 8 Parameters considered for power potential studies

Main Power

House

Dam toe Power

House

Hydrological

Year

June to May June to May

Maximum permissible Full Reservoir Level (FRL)

1764 m 1764 m

Minimum Draw Down

Level (MDDL)

1750.75 m 1750.75 m

Head losses in WCS 3% 3%

Average Tail

Water Level

1527.5 m

(Constant)

From EL 1656.0 m

to EL 1658.3m.

Average Gross Head 232.08 m 103.04 m

Average Net Head 225.1 m 99.95 m

Main Power

House

Dam toe Power

House

Overall TG Efficiency 92% (Constant) 92% (Constant)

Page 96: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 28

Dependability Criteria 90% 90%

Selection of FRL & MDDL

Kirthai Stage-II is located immediately downstream of the Kirthai Stage-I.

Therefore, dam height for Kirthai Stage-II would be governed by tail water level

of the upstream stage viz. EL-1784m. However, in order to avoid submergence

of fertile areas of Padder Valley, it has been decided to restrict the dam height

corresponding to FRL as EL 1764m. As such, the FRL for the Kirthai Stage-II

HE Project has been selected as 1764m.

Minimum mean discharge (MMD) for project has been worked out as 58.22

cumecs .Based on the availability of the above flows and Environment Flows of

10.98 cumecs, weekly operation of the plant has been carried out taking into

consideration volume restrictions as per Annex-D of the Indus Water Treaty.

The permissible Pondage, as per provisions of the Treaty, would be 18.54 MCM

i.e. twice the Pondage required for firm power however Pondage of 17 MCM is

being proposed for Kirthai-II.

From the area-capacity characteristics of the reservoir it is observed that based

on the above Weekly Pondage requirement of 17 MCM, MDDL for the project

would work out as 1750.75 m.

Firm Power & Installed Capacity

As per the Treaty, Firm Power means “the hydro-electric power corresponding

to the minimum mean discharge at the site of a plant”. Based on the minimum

mean discharge of 58.22 cumecs available at Kirthai-II, the Firm Power of the

project, as per the Treaty, works out as about 118.80 MW.

Power Output and Energy Potential for ROR project is proportional to the

natural inflow pattern. Energy Potential of Kirthai Hydro Electric Project StageII

has been worked out on 10-daily basis for the entire study period corresponding

to FRL-1764 m and MDDL-1750.75. Results of the studies are summarized in

below:

Page 97: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 29

Table 9 Unrestricted Annual Energy Potential

S.No. Year Unrestricted Annual Energy

Potential (MU)

S.No. Year Unrestricted Annual Energy

Potential (MU)

1 1967-68 6170.06 23 1989-90 7988.79

2 1968-69 7935.22 24 1990-91 7688.05

3 1969-70 6287.18 25 1991-92 7288.71

4 1970-71 5562.58 26 1992-93 6492.85

5 1971-72 5140.6 27 1993-94 6298.09

6 1972-73 6167.84 28 1994-95 5574.1

7 1973-74 8290.94 29 1995-96 6483.96

8 1974-75 5004.11 30 1996-97 5573.83

9 1975-76 7251.5 31 1997-98 4964.44

10 1976-77 6270.6 32 1998-99 7074.58

11 1977-78 7637.3 33 1999- 7227.6

12 1978-79 8214.22 34 20002000-

01 6368.12

13 1979-80 7045.18 35 2001-02 6652.34

14 1980-81 7191 36 2002-03 7840.51

15 1981-82 6960.61 37 2003-04 6783.27

16 1982-83 6702.05 38 2004-05 5171.14

17 1983-84 7800.38 39 2005-06 7252.87

18 1984-85 6644.96 40 2006-07 6581.23

19 1985-86 6719.67 41 2007-08 5115.02

20 1986-87 7302.63 42 2008-09 5689.64

21 1987-88 7637.21 43 2009-10 5968.14

22 1988-89 8096.24

Maximum 8290.94 MU (1973-74)

Minimum 4964.44 MU (1997-98)

Average 6700.22 MU

It is seen from the results of the studies that unrestricted annual energy potential

at Kirthai Hydro Electric Project Stage-II site varies from a maximum of 8291

MU (Year 1973-74) to a minimum of 4964 MU (Year 1997-98). The average

annual energy potential has been estimated as 6700 MU.

The pattern of annual and lean period unrestricted energy potential in all the

years is presented in Graph-I.

Page 98: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 30

Selection of 90% Dependable Year

Power Output and Energy Potential for ROR project is proportional to the

natural inflow pattern. As such, corresponding to each alternative dam height

scenario, the 90% dependable year would remain the same. Therefore, for

selection of 90% dependable year for Kirthai H.E. Project Stage-II, the

unrestricted annual energy potential from the project corresponding to entire

flow period of 43 years has been arranged in descending order as given below:

Table 10 Selection of 90% Dependable Year

S.

No.

Year Unrestricted

Energy

Potential (MU)

S.

No.

Year Unrestricted

Energy

Potential (MU)

1 1973-74 8290.94 23 2001-02 6652.34

2 1978-79 8214.22 24 1984-85 6644.96

3 1988-89 8096.24 25 2006-07 6581.23

4 1989-90 7988.79 26 1992-93 6492.85

5 1968-69 7935.22 27 1995-96 6483.96

6 2002-03 7840.51 28 2000-01 6368.12

7 1983-84 7800.38 29 1993-94 6298.09

8 1990-91 7688.05 30 1969-70 6287.18

S.

No.

Year Unrestricted

Energy

Potential (MU)

S.

No.

Year Unrestricted

Energy

Potential (MU)

Page 99: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 31

9 1977-78 7637.30 31 1976-77 6270.60

10 1987-88 7637.21 32 1967-68 6170.06

11 1986-87 7302.63 33 1972-73 6167.84

12 1991-92 7288.71 34 2009-10 5968.14

13 2005-06 7252.87 35 2008-09 5689.64

14 1975-76 7251.50 36 1994-95 5574.10

15 1999-2000 7227.60 37 1996-97 5573.83

16 1980-81 7191.00 38 1970-71 5562.58

17 1998-99 7074.58 39 2004-05 5171.14

18 1979-80 7045.18 40 1971-72 5140.60

19 1981-82 6960.61 41 2007-08 5115.02

20 2003-04 6783.27 42 1974-75 5004.11

21 1985-86 6719.67 43 1997-98 4964.44

22 1982-83 6702.05

90% Dependable Year = (n+1)*0.9 = 39.60 say 40th Year

viz. 1971-72

From above table, it is seen that the year 1971-72 would constitute 90%

dependable year. The unrestricted energy potential in 90% dependable year is

5140.60 MU.

Environment Releases

In absence of any specific study relating to the Environment releases, the same

have been proposed by CEA as under in their studies: Table 11 Environment

releases

Monsoon Period

(June to Sept.)

- 30% of the flow during the month

Non-monsoon Period

(Oct. to May)

- 20% of the average flow during Dec. to

Mar. in 90% dependable year.

Based on the above, the net flows have been worked out during 90%

dependable year and utilized for carrying out power potential studies have been

carried out for the project

Selection of Unit Size

The Main Power House is envisaged for operation as a peaking Station. For

selection of the unit size at the Main Power House, alternative unit sizes of 84

MW, 105 MW and 140 MW have been considered. However, the unit size of

140 MW has been proposed for the Main Power House since transportation of

the same to the site is unlikely to impose constraints. The smaller size units are

Page 100: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 32

likely to result in increased cost of civil works as well as E&M equipment.

Accordingly an installation of 6 units of 140 MW each is proposed at Kirthai

Hydro Electric Project Stage -II main power house.

With the above installation, the total discharge requirements from reservoir for

peaking would be about 413.47 cumecs and the unit discharge would be around

69 cumecs for main power house.

Further, the Dam Power House (to be located close to the dam site) has been

envisaged for operation as a Base Load Station and would be operated in order

to optimally utilize the Environment releases from the dam for power

generation. Based on the pattern of the power generation it is proposed to have

2 units of 10 MW each and another 2 units of 35 MW each at the Dam Power

House.

Conclusion

Summary of the power potential studies is given below:

Table 12 Summary of the power potential studies

Main Power

House

Dam

Power House

Full Reservoir Level (FRL) EL 1764.00 m EL 1764.00 m

Minimum Draw Down

Level (MDDL)

EL 1750.75 m EL 1750.75 m

Pondage between FRL &

MDDL

17 MCM 17 MCM

Head losses in Water

Conductor System

3% 3%

Tail Water Level EL 1527.5 m

(Constant)

From EL 1656.0m to

EL 1658.3m.

Average Gross Head 232.08 m 103.04 m

Average Net Head 225.1 m 99.95 m

Main Power

House

Dam

Power House

Design Discharge 413.47 cumec 99.71 cumec

Installed Capacity 840 MW 90 MW

Unit Size 140 MW 2x 10 + 2x35 MW

Unit Discharge 68.91 cumec Unit

Size

Discharge

(cumec)

10 MW 11.1

Page 101: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 33

35 MW 38.8

Overall TG Efficiency 92% (Constant) 92% (Constant)

Annual Energy in 90% Dep.

year

3159.72 MU 307.19 MU

Design Energy 3055.89 MU 296.17 MU

1.20. Land and Population Affected by the Project:

Kirthai Hydro Electric Project Stage-II is a run of river scheme and it has

pondage of 17MCM only. Reservoir area of the project is only 2.25 sq.km and

length of reservoir is about 9.8 km. Due to construction of this project some

portion of existing Kishtwar - Gulabgarh- Sansari road from dam site to Kirthai

village is likely to be submerged. The total length of existing road under

submergence is about 4.5km from Dam site to Kirthai. The tail end of the

existing road under submergence will be about 0.5 km downstream of Village

Kirthai JKSPDC in association with BRO is conducting survey for realignment

of the submerged road. Overall land requirement for the project is 225.25 ha

out of which 142.25 ha is forest land, 40.00 ha is govt. land and 43.00 ha is

private land. The land under submergence of the project is 140.00 ha out of

which 70.00 ha is forest land, 33.00 ha is govt. land and 37.00 ha is private

land. The breakup of land required including submergence area, land in respect

of different project components, colonies and offices, road, muck disposal area

and borrow / quarry area is given below in table .

Table 13 Land Requirement of Submergence and Project Component

Sr.

No.

Component Area of Land, ha Total, ha

Forest Govt. Private

1 Submergence 70.00 33.00 37.00 140.00

2 Project Components 24.00 - - 24.00

Sr.

No.

Component Area of Land, ha Total, ha

Forest Govt. Private

3 Quarry Sites 18.40 - - 18.40

4 Muck Disposal Sites 12.85 - - 12.85

5 Colony area - 4.00 4.00 8.00

6 Batching plant/ store

/ steel yard

2.0 3.00 1.00 6.00

7 Road / Access roads 15.00 - 1.00 16.00

Page 102: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 34

Total 142.25 40.00 43.00 225.25

Private land requirement for the project is 43 ha. The FRL of the project has

been fixed in such a way that there is a minimum displacement of the people

and loss of agriculture land. A reconnaissance survey of the area covering 10

km aerial radius from the dam axis has been conducted and it is found that

within the aerial radius of 10 km, 12 villages exist, out of which only 2 villages

shall be partially affected. Kirthai and Liae villages will be partially affected by

the project. The number of the project affected families to be displaced shall be

about 5 and these are the families whose house is near to the river.

1.21. Environmental Aspects

As per the available information, there is no protected area i.e. National Parks,

Wildlife Sanctuaries or similar eco-sensitive zones within the project area.

JKSPDC is conducting EIA & EMP studies. R/R plan for Kirthai-II H.E. Project

will be prepared based on National Rehabilitation and Resettlement Act, 2013.

All affected landowners will be entitled to a combination of compensation

package and resettlement assistance, depending upon the nature of ownership

of their land and the scope of impacts. Assistance and other support to the

affected families and people will be provided so that they can regain their

previous standard of living, even improve if possible, within a reasonable

transition period. Steps will be taken to improve overall quality of life of affected

population through better infrastructure, medical and educational facilities etc.

Affected Families will be resettled to a new location. New Resettlement sites

shall be finalized by the Project authorities in consultation with state

government and affected families and it will be developed with all the basic

infrastructural facilities well before the filling of reservoir.

Social Impact Assessment (SIA) of project if required will be conducted at

preconstruction stage as per Rehabilitation and Resettlement Act, 2013.

Environmental Management Plan (EMP) enumerating the set of measures to

be adopted to minimize the adverse impacts will be prepared. The most reliable

way to ensure the implementation of EMP is to integrate the management

measures in the overall project planning, designing, construction and operation

Page 103: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 35

phases. Based on the predicted environmental impacts, appropriate

environmental management plans will be formulated before the start of the work

for construction of the project. The compensatory afforestation, Green Belt

Development, Management of the muck generated, Solid waste management,

Fisheries Management plan, Willdlife and Biodiversity Management plan,

Disaster Management plan ,Environmental Monitoring plan, Catchment Area

treatment plan will be prepared.

1.22. Project Headquarters and Residential Accommodation at Project Site

The main office complexe cum project headquarter, and residential colony of

the project is proposed in Kadhal area near the terrace of Kirthai village. For

workshops and other non residential buildings, land of Kadhal and surrounding

area will be utilized. Kadhal is located about 1 km above the existing Kishtwar

- Gulabgarh road near Village Kirthai. Kadhal is about 5km from dam site and

suitable land is available at the said location. The proposed Residential

Complex at Kadhal on left bank terrace of River Chenab will accommodate

different types of dwelling units for the officers and staff. The provision for

school, dispensary, field hostels, bank, post office, telephone exchange and

CISF office etc has also been kept .Some of the semi permanent buildings like,

stores, steel yard, mechanical and electrical workshop, fabrication workshop,

cement store, equipment yard, hydro mechanical workshop, electromechanical

workshop, precast yard etc are proposed near Dam and Power house site.

Both, temporary and permanent types of residential buildings have been

planned. About eight hectare of total land is proposed to be acquired for

construction of residential colony, field hostel, guest houses, parks etc in

Kadhal. Field hostel is also proposed near dam site and power house site. The

proposed Khadal colony will be able to accommodate the staff for whole of the

project including dam & power house. During construction two temporary

colonies are also proposed for the labourers and artisans, one near dam site

another near power house site. These colonies will be dismantled after

completion of the Project. The staff for O&M purpose will stay in permanent

colony at Kadhal after completion of the project. The field hostel at dam site

Page 104: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 36

and power house site will continue to function even after commissioning of the

project for visiting staff on duty.

1.23. Project Set Up

The construction organization for implementation of Kirthai Hydro Electric

Project Stage-II is proposed to be headed by the officer of the rank of General

Manager. The General Manager would be assisted by three Chief Engineers

i,e Chief Engineer, Civil, Chief Engineer, Electro-Mechanical and Chief

Engineer Human Resources Management. Chief Engineer, Civil will look after

the Civil works of River Diversion, Concrete Dam, Power House and

infrastructure. Chief Engineer, Electro-Mechanical will look after the works of

Workshop, Mechanical, Hydro-Mechanical and Electro Mechanical. Chief

Engineer Human Resources Management will look after the works of General

Administration, Procurement, Stores Logistics, Liasioning, Finance and

Vigilance. Accordingly, the manpower requirement for execution of Works has

been worked out and distributed into the ten dedicated teams/ modules. It is

proposed to organize the works at site in the following ten (10) modules.

Module 1 – Procurement, Stores and Logistics

Module 2 – Workshop, Mechanical and Hydro-Mechanical Works

Module 3 – Power House and Infrastructure

Module 4 – Concrete Dam

Module 5 – River Diversion and Works

Module 6 – Project Monitoring

Module 7 – Liasioning and Administration

Module 8 – Finance

Module 9–Electro Mechanical Work

Module 10– Vigilance

Page 105: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 37

1.24. Evacuation of Power to be generated at Kirthai Hydro Electric Project

Stage-II.

The evacuation of power from Chenab basin project in Jammu and Kashmir

was discussed and agreed in the 31st Standing Committee Meeting (SCM) on

Power System Planning of Northern Region (NR) held on 2nd January 2013

and subsequently in the 32nd Standing Committee Meeting of Power System

Planning of NR held on 31st August 2013. For Kirthai Hydro Electric Project

Stage-II the following transmission system was agreed as a part of high

capacity common corridor – I for hydropower projects located in Chenab basin,

J&K.

(i) 400 kV D/C (Quad HTLS Conductor – Equivalent to about 3000 MW)

line from Kirthai Hydro Electric Project Stage-II to Kishtwar Pooling

station.

(ii) Termination of 400 kV D/C (Triple HTLS Conductor –Equivalent to about

1500MW) line from Reoli Dugli HEP (HP) at generation switchyard of

Kirthai Hydro Electric Project Stage-II.

Switchyard capacity of Kirthai Hydro Electric Project Stage-II must be able to

handle about 3000 MW power generated by the generation projects located in

upstream of the Kirthai II generation project. It is proposed that the GIS

switchyard equipment and XLPE cables provided may be designed for carrying

4000 Amps current. 400 kV, 125 MVAR Bus Reactor is proposed. From the

proposed Kishtwar pooling station the power of Kirthai Hydro Electric Project

Stage-II will be evacuated to Kishenpur grid.

1.25. Construction Programme

The Project is scheduled to be completed in 60 months after getting all the

statuary clearances and Financial Closure. The infrastructure facilities shall be

developed concurrently with the process of obtaining various Government

clearances.

1.26. Interstate / International Aspects

Kirthai Hydro Electric Project Stage-II does not involve any interstate aspect.

Page 106: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 38

The river Chenab, on which Kirthai Hydro Electric Project Stage-II is envisaged

for execution, crosses international boundary between India and Pakistan. It is

Western River of Indus Basinand falls in the purview of Indus Water Treaty

1960.

Since the Kirthai H.E. Project is proposed on river Chenab which is a Western

river, Water Resources Project on this river is guided by the Annexure “D” and

Annexure “E” of the Indus water treaty which deals with the provisions regarding

generation of H.E. Power and storage of water by India on the Western rivers.

Indus Water Treaty has XII Articles with VIII Annexures.

Kirthai Hydro Power Project Stage-II is a run of river scheme and is within the

provision of Indus Water Treaty. It is planned and designed as per Article III

Annexure D and Annexure E of the Treaty.

Minimum mean discharge (MMD) for the Project is calculated as per Annex.-D

of the Treaty as under:

“The average discharge for each 10-day period (1st to 10th, 11th to 20th and

21st to the end of the month) will be worked out for each year for which

discharge data, whether observed or estimated, are proposed to be studied

for purposes of design. The mean of the yearly values for each 10-day period

will then be worked out. The lowest of the mean values thus obtained will be

taken as the minimum mean discharge.”

Based on the above, average flows have been obtained for each 10-daily period

and minimum of these flows represents MMD which has been worked out as

58.22 cumecs.

Firm Power of the Project has also been worked out as per Treaty.

As per the Treaty, Firm Power means “the hydro-electric power corresponding

to the minimum mean discharge at the site of a plant”. Based on the minimum

mean discharge of 58.22 cumecs available at Kirthai-II, the Firm Power of the

project, as per the Treaty, works out as about 118.80 MW.

Page 107: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage-II (930 MW)

DPR: Vol-0: Executive Summary Page 39

Based on the availability of the Minimum mean discharge (MMD) and

Environment Flows of 10.98 cumecs, weekly operation of the plant will be

carried out taking into consideration volume restrictions imposed as per

Paragraph 15 of Part-3 of Annex-D of the Treaty.

As per Annex-D of the Treaty, the works connected with run-of-river Plant on

Chenab river at a site above Ramban are to be so operated that

(i) The volume of water received in the river upstream of the Plant, during

anyperiod of seven consecutive days, shall be delivered into the river below the

Plant during the same seven day period, and

(ii) In any one period of 24 hrs. within that seven-day period, the volume

delivered into the river below the plant shall not be less than 50%, and not more

than 130% of the volume received above the plant during the same 24 hour

period.

(iii) The period of 24 hours shall commence at 8 AM daily and the period

ofseven consecutive days shall commence at 8 AM on every Saturday.

Page 108: (See Paragraph-6) FORM 1environmentclearance.nic.in/writereaddata/modification/...• 93 m long over flow section with 5 bays with radial gates(9mx12.248m). • A power intake to convey

Kirthai H.E. Project Stage

Permissible Pondage, as per provisions of the Treaty, would be 18.54 MCM i.e.

twice the Pondage required for firm power however a Pondage of 17 MCM is

being proposed for Kirthai-II. Based on the above Weekly Pondage requirement

of 17 MCM, MDDL for the Project has been worked out as 1750.75 m. The

design of dam has been carried out as per Annexure D of Paragraph 8 of Part-

3 of treaty.

1.27. Cost Estimate

The total cost of the Project is estimated to Rs 5158.00 Crore at August, 2015

Price Level.

The abstract of the project (unit wise) is as under:-

Cost of the Project

(` in lakhs)

Unit Cost

Unit -I Head works 175599.04

Unit-III Power Plant & Appurtenant Works 340218.96

Total Project Cost : 515818.00

1.28. Cost of Energy Generation

The cost of energy generation in a 90% dependable year at 8% discount rate

works out to be 2.06/ unit. In addition, cost of energy for 10 % and 12 % discount

rates have been worked out which are 2.51/ unit and 3.00/unit respectively.