sediment management experiences - a case from nepalich.no/opplastet/dokumenter/conference...
TRANSCRIPT
Content
• Introduction & project background
• Sediment design criteria & operational
problems
• Research initiation with data collection and
analysis
• Operational strategies for improvements
• Conclusion
Jhimruk Project
Type of Power Project : Run of River Project
Installed Capacity : 12 MW
Net Head : 205 m
Discharge : 7.05 m3/s (2.35 m3/s/unit)
Energy : 72 GWh
Catchments area : 645 sq. km
Settling basin : 2 nos 5.5x5x42m
Turbine units and type: 3 nos, Horizontal Francis
Rated unit capacity : 4 MW
Turbine speed : 1000 rpm
Commissioning : 17 August 1994
Sediment design & Operational problems
No sediment data during the design
Settling basin designed by proven technology
Design sediment criteria met
Severe sediment problems during operation
Turbine
wear
Data: Mineralogical studyQ
uart
z co
nte
nt
[%]
0
10
20
30
40
50
60
70
80
Wes
t S
eti
Jh
imru
k
Ra
pti
Kh
ola
Ma
di
Rev
er
Ga
nah
a
Aru
n K
hola
Mod
i-2
Mod
i -
1
Aa
dh
i K
hola
Tin
au
Ku
lek
han
i
Ch
itla
ng
Palu
ng
Bagm
ati
Ma
na
hara
Dh
ob
i
Gau
r
Rosh
i
Dh
ad
Kh
ola
Kh
imti
Kh
imti
Kh
ola
Ta
ma
kosh
i
Ph
edi
Do
lal
Gh
at
Su
nk
osh
i
Sa
pta
Kosh
i
Ka
rna
li
West Rapti Gandaki
Tin
au Bagmati Bagmati
Kathmandu
Koshi
Source: B. Thapa, PhD Thesis at NTNU, 2004
Sediment/Efficiency Measurements & Analysis
Efficiency measurements at Jhimruk Hydro power plant
60
65
70
75
80
85
90
95
1 1,5 2 2,5 3 3,5 4 4,5
Generator Power [MW]
Hyd
rau
lic E
ffic
ien
cy [
%]
11th November 2003
1st September 200370
75
80
85
90
95
100
0 50 100 150 200 250
Particle Diameter
Pe
rce
nt
fin
er
29.09.2003
15.09.2003
06.09.2003
[mm]
0
4 000
8 000
12 000
16 000
20 000
24 000
27.0
8.03
03.0
9.03
10.0
9.03
17.0
9.03
24.0
9.03
01.1
0.03
08.1
0.03
15.1
0.03
22.1
0.03
29.1
0.03
05.1
1.03
12.1
1.03
Date [dd.mm.yy]
Se
dim
en
t c
on
ce
ntr
ati
on
[P
PM
]
Maximum value :21,594 ppm
13th September
Sediment Load through
one turbine: 6,900 tons
Plant Operation Strategy
Silt Concentration (ppm) Generation (MW)
Below 1500 Full generation
Between 1500 and 3000 Reduced generations
1500 to 2000 – 3 units
2000 to 2500 – 2 units
2500 to 3000 – 1 unit
Above 3000 Complete shutdown
Energy Loss due to Sediment
S.N
.
Months PPM Level Duration of
reduced
operation or
shutdown (Hrs)
Energy Lost due
to high PPM
(MWh)
1 Ashadh
(June-July)
1500 - 3000 6.33 34.54
Above 3000 79.99 959.88
2 Shrawan
(July-Aug)
1500 - 3000 89.32 525.52
Above 3000 105.53 1266.36
3 Bhadra
(Aug-Sept)
1500 - 3000 61.14 426.11
Above 3000 124.92 1499.04
4 Aswin
(Sept-Oct)
1500 - 3000 3.45 25.67
Above 3000 34.02 408.24
Total 504.69 5145.36
Approx. Revenue loss of Rs. 28 million
Turbine Repair Cost
-
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
2064/65 2065/66 2066/67 2067/68 2068/69 2069/70 2070/71 2071/72
Turbine Parts Repair Cost (in million NRs.)
Turbine Parts Repair Cost (mil. NRs.)
Change in Maintenance Period
Month
Pla
nt E
ffic
iency
1 2 3 4 5 6 7 8 9 10 11 12
Sta
rt m
on
so
on
En
d m
on
so
on
Extra generation Maintenance
• Ceramic Spray Coating (R-Type) One runner and one set of side cover were also coated with Ceramic (R-type)
material but was not satisfactory. Guide vanes were not coated, as it tends to
bend while heating for treatment.
• GE Research and DevelopmentGE had used seven (7) type of coating on different guide vanes and
experimented one of the turbine. The results revealed that one of the coating
withstand the silt erosion.
• Spare Runner SetThree sets of turbine parts that are subject to erosion were kept as spare to
reduce the annual maintenance time. Eroded runner can be replaced within few
hours
Initiatives for reducing silt erosion for
Optimizing Generation
Conclusion
• Jhimruk River is one of the high sediment carrying rivers in Nepal containing
high percentage of hard and abrasive mineral.
• Proven sediment design criteria of 90% trapping of 0.2 mm by settling basin is
satisfactorily met. However the excessive war and tear of the turbines induced
by the sediment continued requiring research initiation to address the causes
and consequences.
• So a general knowledge of sediment is not sufficient when it comes to dealing
with sediment management and problems in run-of-river hydropower plants.
• Data collection and analysis indicated hard mineral particles finer than 0.2 mm
are responsible for erosion and damage to turbines
• Experiences over the years have shown that it was necessary to reduce the
power production or completely shut down the plant to avoid the excessive
erosion and losses due to silt (quartz)
• We welcome innovative ideas for operating the plant at full capacity during the
wet season!