section 30(a) directive external audit report
TRANSCRIPT
![Page 1: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/1.jpg)
T · +27 21 702 2884 26 Bell Close, Westlake Business Park F · +27 86 555 0693 Westlake 7945, Cape Town NCC Environmental Services (Pty) Ltd | Reg. No: 2007/023691/07 | VAT No. 4450208915
REAL GROWTH FOR PEOPLE, PLANET AND BUSINESS www.ncc-group.co.za
PREPARED FOR:
Saldanha Bay Municipality
DATED:
14 October 2020
PREPARED BY:
NCC Environmental Services (Pty) Ltd
T · 021 702 2884
Section 30(A) Directive External Audit Report
Langebaan Well Field Water Augmentation Project
Saldanha Bay Municipality, Western Cape
Project. No. : Q327/2020
DEADP Ref No.: 16/6/F4/17/3140/17
Condition 6.3.1.2 (Second Report)
![Page 2: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/2.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 2 Reg. No: 2007/023691/07
DECLARATION OF INDEPENDENCE
I, Nicholas Gates, as duly authorised representative of NCC Environmental Services (Pty) Ltd (NCC), hereby
confirm my independence (as well as that of NCC) as an auditor and declare that neither I nor NCC have any
interest, be it business, financial, personal or other, in any proposed activity, application or appeal in respect
of which Saldanha Bay Municipality has appointed as External Auditor, other than fair remuneration for
worked performed, specifically in connection with the Environmental Management Programme issued to
Saldanha Bay Municipality (SBM). I further declare that I am confident in the results of the report undertaken
and the findings as a result of it – as is described in my attached report.
Signed:
Nicholas Gates
14 October 2020
SHEQ Consultant – NCC Environmental Services (Pty) Ltd
![Page 3: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/3.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 3 Reg. No: 2007/023691/07
LIABILITY DISCLAIMER AND CONFIDENTIALITY CLAUSE
All inspections conducted, as well as reports and recommendations provided by NCC are purely advisory. They
are primarily intended for the purpose of assisting clients in loss control, risk management as well as health,
safety and environmental procedures.
Observations and recommendations are the result of practices and conditions observed and information made
available to us in various forms at the time of our visit. They do not purport to refer to or guarantee compliance
with local or government regulations which may be applicable to such practices and conditions. This report
should not be considered a definitive listing of all existing hazards nor an absolute solution to all indicated
hazards, or hazards present from time to time in the Client Organisation. The report should always be
considered in its entirety; individual sentences, paragraphs or sections of the report should not be used in
isolation.
This report should not be reproduced except in its entirety, including this liability disclaimer or contents
reproduced or disclosed to any third party without the prior written approval of NCC.
NCC assumes no responsibility for any losses incurred as a result of the implementation, management, and
operation of recommended health, safety and environmental systems, processes, procedures.
![Page 4: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/4.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 4 Reg. No: 2007/023691/07
DOCUMENT CONTROL
TITLE: Section 30(A) Directive External Audit Report: Condition 6.3.1.2
PROJECT: Langebaan Well Field Water Augmentation Project
LOCATION: Hopefield, Western Cape
CLIENT: Saldanha Bay Municipality
CONSULTANT: NCC Environmental Services (Pty) Ltd
DOCUMENT NUMBER: NCC/SBM/Audit/LWFWAP/2020/01
REVISION: 02
DATE: 13/10/2020
Revision Date Description
Rev.00 03/08/2020 Original
Rev.01 07/08/2020 Adjustment of overall percentage rating
Rev.02 13/10/2020
Inclusion of Section 6.1.1. Mitigation against Environmental Impacts Associated with Interventions to address Point 3.1.1. of DEADP feedback
Inclusion of 6.2.1. Compliance with Section 7 of the EMPr to address Point 3.2.1. & 3.2.2. of DEADP feedback
Addition of Hydrogeological Report (Annexure D)
Addition of Water Use Licence (Annexure E)
Addition of ECO reports (Annexure F)
Addition of Induction Attendance Register (Annexure G)
Addition of DEADP Correspondence (Annexure H)
Proof Of Distribution (Annexure I)
![Page 5: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/5.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 5 Reg. No: 2007/023691/07
TABLE OF CONTENTS
1 INTRODUCTION ................................................................................................................ 6
1.1 Audit Scope and Purpose......................................................................................................................7
2 BACKGROUND .................................................................................................................. 8
2.1 Project Background ..............................................................................................................................8
2.2 Auditor Background ..............................................................................................................................9
3 METHODOLOGY .............................................................................................................. 10
3.1 Audit Process ..................................................................................................................................... 10
3.2 Observation and Recommendation Determination .......................................................................... 11
3.3 Findings .............................................................................................................................................. 11
3.4 Audit Tables and Compliance Ratings ............................................................................................... 12
4 ASSUMPTIONS AND LIMITATIONS ................................................................................... 13
5 CONSULTATION PROCESS ................................................................................................ 13
6 FINDINGS ........................................................................................................................ 14
6.1 Section 30A Directive ........................................................................................................................ 14
Mitigation against Environmental Impacts Associated with Current Intervention ...................... 14
6.2 EMPr .................................................................................................................................................. 15
Compliance with Section 7 of the EMPr ....................................................................................... 16
7 CONTRIBUTION TO CURRENT WATER SUPPLY ................................................................. 20
8 SUMMARY ...................................................................................................................... 21
8.1 SUMMARY GRAPHICS ........................................................................................................................ 22
9 REPORT DISTRIBUTION LIST ............................................................................................ 23
ANNEXURE A – SECTION 30A DIRECTIVE TABLE ........................................................................... 24
ANNEXURE B – EMPR TABLE ....................................................................................................... 26
ANNEXURE C – PHOTOGRAPHS .................................................................................................. 49
ANNEXURE D – HYDROGEOLOGICAL REPORT .............................................................................. 53
ANNEXURE E – WATER USE LICENCE ........................................................................................... 54
ANNEXURE F – ECO REPORTS ..................................................................................................... 55
ANNEXURE G – CONTRACTORS INDUCTION ................................................................................ 56
ANNEXURE H – DEADP CORRESPONDENCE ................................................................................. 57
ANNEXURE I – PROOF OF DISTRIBUTION TO RELEVANT AUTHORTIES .......................................... 58
![Page 6: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/6.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 6 Reg. No: 2007/023691/07
1 INTRODUCTION
NCC Environmental Services (Pty) Ltd (hereafter referred to as the “NCC”) were appointed by Saldanha Bay
Municipality (Hereafter referred to as the “SBM”) to conduct an external audit in terms of compliance with
the conditions stipulated in the Section 30A Directive, including an approved Environmental Management
Programme (EMPr), issued as part of its Water Resilience Projects located within the boundaries of the
Saldanha Bay Municipality.
This audit focuses on the Langebaan Road Well field intervention only and aims to address Condition 6.3 of
the issued Section 30A Directive which states:
‘The municipality must submit audit reports (per measures or intervention to be implemented)
to this Department for the commenting purposes and acceptance. Copies of these audit reports
must also be submitted to the Department of Water and Sanitation, Heritage Western Cape, and
the Department of Environmental Affairs: Oceans and Coasts for record purposes.’
The direction further outlines requirements for each audit type in Condition 6.3.1.1 and Condition
6.3.1.2
After discussions with the Department of Environmental Affairs and Development Planning (DEADP) it
was understood that the audit required for Condition 6.3.1.1 has been completed and submitted to the
Department in the form of the ECO close out report therefore only a report required for Condition
6.3.1.2 will be compiled.
The requirements include:
‘A second audit report within three (3) months of completion of an emergency measure or
intervention (per measure or intervention). This second audit report must inter alia confirm how
the measures or interventions implemented have contributed to the addressing the current
water supply emergency situation and improved the water supply security in the areas within the
jurisdiction of the municipality. This second audit report must also detail how all environmental
impacts associated with each measure or intervention implemented have been mitigated’
A site visit was conducted on the 1st July 2020 after which a report was compiled and serves to document the
External Audit proceedings, and is a record of all observations, recommendations and conclusions made during
the engagement.
![Page 7: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/7.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 7 Reg. No: 2007/023691/07
1.1 Audit Scope and Purpose
Although SBM have been exempted from having to acquire an Environmental Authorisation they were
required to produce a Generic Environmental Management Programme (EMPr) in compliance with Section
24N of NEMA requirements.
In accordance to Regulation 34 of the NEMA: EIA Regulations, 2017, as amended, the holder of an
authorisation1 must, for the period during which the environmental authorisation and EMPr, and where
applicable the closure plan, remain valid—
a) Ensure that the compliance with the conditions of the environmental authorisation and the EMPr, and
where applicable the closure plan, is audited; and
b) Submit an environmental audit report to the relevant competent authority.
As such, the scope of the environmental audit report will be based on assessing the conditions of the EMPr,
and where applicable, the closure plan. The Section 30A Directive will also be considered for this audit.
The purpose of the environmental audit is to address the legal requirements to report on the level of
compliance with above mentioned conditions, report on the objectives and outcomes of EMPr and the extent
to which it were achieved. In addition, any new impacts or risks will be assessed, the effectiveness of the EMPr
will be evaluated, and shortcomings or any changes in the EMPr identified.
1 Not applicable for this audit as a result of the Section 30A Directive issued
![Page 8: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/8.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 8 Reg. No: 2007/023691/07
2 BACKGROUND
2.1 Project Background
On average the municipality uses 37ML of water per day, this includes all domestic and commercial users. The
current usage allocation is approximately 60% Industrial vs 40% domestic. Restrictions put in place showed a
significant reduction in daily consumption. Restriction measure continue, to further reduce consumption.
More interventions were however required to ensure sustainability of SBM supply
During the droughts which the Western Cape suffered from SBM implemented various water augmentation
projects. As part of the interventions the Langebaan Road and Hopefield well fields were established. Both
well fields formed part of the Municipalities Water Intervention Plan (WIP) and was approved with a Section
30A directive. Both projects have been implemented in totality with an Environmental Control Officer (ECO)
forming part of the project team. The ECO compiled monthly reports and a Final Closure report.
Section 6.3.1.2 of the section 30A Directive requires a second audit within 3 months of completion of an
emergency intervention.
The Langebaan Wellfield, traditionally referred to as Langebaan Phase 1, was completed in October 2018 and
involved the addition of four (4) boreholes to an existing four (4) borehole network. This existing system feeds
in to bulk water system originating from the Berg River.
Supply from Western Cape Water Supply System (WCWSS) with its abstraction point being Misverstand dam
was 20 427 000 mᵌ/a prior to the interventions. SBM had to aim to reduce demand to 20.35 ML/day during
level 6 water restrictions which was deemed impossible without major economic damage, due to business and
industry being the SBM’s biggest consumers. Before the drought SBM was utilising 37ML/day which was
already above the previous allocation before the increased allocation figure above
Where possible existing farm roads were utilized to ensure minimal impact on vegetation.
Only Borehole 4 required a new access route in order to gain access.
The Contractor used a portion of the landowner’s property as a laydown area. This was located within the
farmer’s storage area.
No external audit was conducted during the construction period due to the short time frame for construction.
Construction was from April 2018 to July 2018. The ECO Closure Audit Report, for Condition 6.3.1.1 was
completed in October 2018.
![Page 9: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/9.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 9 Reg. No: 2007/023691/07
2.2 Auditor Background
Nicholas Gates has been working in the Environmental Management Sector for 11 years during which auditing
has been one of his core functions. He has undergone various training courses such as Lead Auditing and SHEQ
IMS Auditors through institutions such as DQS and ISTEC Safety. Over the years he has gained extensive
experience across the various sectors from Mining, Construction, Energy, etc. either being part of an auditing
team and as lead auditor on a number of projects. Clients include Municipalities, Private Companies,
individuals, SOE’s, etc. and range between the auditing of Landfills, Renewable Energy Projects, etc. against
Environmental Authorisations, Environmental Management Plans and Water Use Licences.
![Page 10: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/10.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 10 Reg. No: 2007/023691/07
3 METHODOLOGY
This section provides an overview of the methods employed by NCC in providing observations,
recommendations and conclusions derived from audit procedures conducted.
Section 6 of the Environmental Management Programme provides for various Performance Specifications
relating to Environmental Management, this would have been used by the Contractor to guide them in
assisting with the mitigation against environmental damage.
It was also highlighted that the Performance Specification tables detailed within Section 6 of the EMPr will be
audited by the WRECO and Environmental Auditor.
3.1 Audit Process
The site visit, data reviews and report drafting were conducted by NCC’s environmental compliance audit
team. The site audit included the following procedures:
Site Inspection (held on the 1st July 2020), which included:
i. Access Routes;
ii. Infrastructure Maintenance; and
iii. Rehabilitated areas;
Review of Available Site Specific Reports and Documents
i. Review and identification of any audit findings;
ii. Review of ECO reports;
iii. Review of Method Statements; and
iv. Review of remedial measures implements.
Compilation of Audit Report which includes key findings and recommendations
i. A comprehensive report is compiled after site inspection and review of all data, relevant reports,
and interviews.
The report provides recommendations on non-compliance identified during the compliance audit.
![Page 11: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/11.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 11 Reg. No: 2007/023691/07
3.2 Observation and Recommendation Determination
All recommendations were made according to the following observations within the period that the Auditor
was on site. Observations were based on, and are limited to, the following information sources:
i. Available documentation and records received prior, subsequent, or during the site visit;
ii. Observations made by the audit team during physical site inspections; and
iii. Information received from both direct and cross-referenced interviews conducted with responsible
staff.
3.3 Findings
Key observations as conveyed in Section 6 of this report highlight areas of non–compliance as well as aspects
that require prioritised attention. Each point under this section identifies the observation which it is pertinent
to.
The purpose of these summarised commentaries is to allow SBM to identify common management challenges
that are affecting compliance with the conditions of the documentation audited.
Where findings and recommendations pertaining to the site are deemed significant through compliance status
or performance, they are documented as specific issues in the report. All site specific observations and
recommendations are correspondingly recorded in the audit table (see Annexures A).
As per Section 34(4) of the EIA Regulations, where the findings of the environmental audit report such as:
(a) insufficient mitigation of environmental impacts associated with the undertaking of the activity; or
(b) insufficient levels of compliance with the environmental authorisation or EMPr and, where applicable
the closure plan;
the holder must, when submitting the environmental audit report to the competent authority include
recommendations for consideration to amend the EMPr or closure plan in order to rectify the shortcomings
identified in the environmental audit report.
Any recommendations to amend must be subjected to a public participation process prior to submitting to the
competent authority.
![Page 12: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/12.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 12 Reg. No: 2007/023691/07
3.4 Audit Tables and Compliance Ratings
The audit table in Annexure A captures all observations and recommendations made in relation to all
conditions stipulated in both Directive and EMPr. They provide the reader with more detailed information in
terms of what the stipulated requirements are in relation to the organisation’s assessed current compliance
status, according to the observations recorded by the auditor during the site visit.
Ratings are calculated based on a scoring system whereby each auditable condition is provided with a score
as highlighted in the table below. The rating system adopted is that which is utilized by the Western Cape
Department of Environmental Affairs and Development Planning (DEADP) whereby each auditable condition
is provided with a score in order to ensure consistency with future auditing and monitoring.
Description Status
Indicator Compliance
Rating Scoring Action
Compliant C 2 85%-100% Minor Improvements Required
Partially Compliant
PC 1 65%-84% Improvement Required
Non-Compliant NC 0 0-64% Major Improvements Required
Not Applicable / Audited
NA - - No Improvements Required or not
relevant at time of audit
Table 1: Compliance Scoring
Each condition has been ascribed a priority indicator of Non-compliant (Red), Compliant (Green) Partially
Compliant (Yellow), and Not Auditable/Audited (Grey) to assist the reader in determining areas that require
attention to ensure compliance is achieved.
Areas that have been shaded indicate that they are sub-condition requirements, they are necessary in order
for the condition to be compliant, non-compliant or not audited/applicable. They have been broken down to
indicate which areas of the condition need to be rectified.
An overall rating is calculated to provide the reader with the overview of the facilities compliance to the
relevant documentation however each condition should be viewed and dealt with on their own merits as the
rating does not provide for, or calculate the severity or impact which might be presented.
For example a site may have an overall rating of 97% which is perceived as good however the 3% worth of
non-compliant conditions may pose a significant impact
![Page 13: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/13.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 13 Reg. No: 2007/023691/07
4 ASSUMPTIONS AND LIMITATIONS
The compliance audit and report are based upon the assumptions that:
i. Documentation provided to the auditor by SBM was factual and true.
ii. Evidence provided through interviews was factual and true.
iii. The audit is based purely on the conditions as stipulated in the Directive and EMPr issued to SBM’s.
iv. No independent physical or chemical testing, or verification of any description was conducted by the
auditor or NCC as part of the compliance review.
v. Reports were randomly sampled in order to accommodate time constraints
vi. Where visual observations of equipment were not possible either due to the location or complexity to
access the auditor has used other means to determine compliance, either through written evidence
from service providers which utilize the instruments or through interviews with SBM employees whom
work with the equipment.
vii. Specialist studies may run on a different cycle to that of the external audits therefore aligning with
audit findings, however these can be address in following audits.
5 CONSULTATION PROCESS
The consultation process undertaken during the course of carrying out the environmental audit based on
correspondence between the auditor and project representatives.
No consultation with external stakeholders was undertaken.
The final audit report will be distributed to the following Departments as per the requirement of the Directive.
Western Cape Department of Environmental Affairs and Development Planning
Department of Water and Sanitation
Heritage Western Cape
Department of Environmental Affairs: Oceans and Coasts
A meeting was held on the 29th June 2020 with the Department of Environmental Affairs and Development
Planning to discuss any additional audit requirements that the Department may have.
It was confirmed that on a Condition 6.3.1.2 Audit was required for this water intervention project.
![Page 14: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/14.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 14 Reg. No: 2007/023691/07
6 FINDINGS
Based on the audit conducted, it was established that the ability of the Directive and in particular the EMPr
(and where applicable, the closure plan) was achieved in terms of:
i. Sufficiently provide for the avoidance, management and mitigation of environmental impacts
associated with the undertaking of the activity on an on-going basis;
ii. Sufficiently provide for the avoidance, management and mitigation of environmental impacts
associated with the closure of the facility; and
iii. Ensure compliance with the provisions of environmental authorisation, EMPr, and where applicable,
the closure plan.
6.1 Section 30A Directive
As per the requirement on the Directive a Water Supply Emergency Intervention Plan was required in terms
of Condition 6.2.1, this was provided to the Auditor and use to inform the various water intervention
measures. Further details can be found in Table 1.
Mitigation against Environmental Impacts Associated with Current Intervention
Pre-Construction
No formal botanical or heritage assessments completed prior to construction, however a Hydrogeological
Report as part of a Water Use Licence was compiled
It was indicated that portions of the project was located on active farmland with little indigenous
vegetation as identified by the Municipality Environmental Department, however it was indicated
that a small portion of the project did impact on indigenous vegetation. The layout of the road
(width) and pipe installation areas were kept to a minimum with the use of existing farms roads and
servitude areas as far as possible. To a large extent existing farm roads were utilised for the pipe
route.
Various documents were drafted and tasks by the Contractor prior. This included SHE Plan, Heritage Recovery
Procedure, and staff induction.
Construction
Topsoil was stockpiled separated from subsoil and designated as a no-area.
![Page 15: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/15.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 15 Reg. No: 2007/023691/07
An Environmental Control Officer (ECO) was appointed to oversee the construction phase of the project and
monitor adherence to the EMPr.
An ECO conducted site inspection and compiled monthly monitoring reports. No major issues were highlighted
in the sampled reports and it was indicated by the ECO that the site was generally well managed.
The ECO reports highlighted that topsoil was set aside and designated as a no go area to be used for
rehabilitation.
Existing access roads were utilized where possible to minimize unnecessary clearance of vegetation.
Rehabilitation
After completion of construction t was spread on impacted areas to support regrowth of vegetation
Rehabilitation was conducted post-construction whereby topsoil was spread on impacted areas to support
regrowth of vegetation. The ECO conducted a site visit and compiled a final close out report whereby no major
issues were identified and regrowth was evident.
6.2 EMPr
Section 6 of the Generic EMPr, Performance Specifications: Environmental Management, was the section
audited against. This is specified in the EMPr where it indicates:
‘Section 6 of the Environmental Management Programme provides for various Performance
Specifications relating to Environmental Management, this would have been used by the
Contractor to guide them in assisting with the mitigation against environmental damage.’
Further details can be found in Table 2 & Table 3.
All applicable conditions were audited and the final percentage rating was measured against these conditions,
which excluded not applicable conditions.
The tables below highlight any the short comings of any conditions which were not deemed fully compliant.
Only conditions deemed non-compliant or partially complaint are displayed, the full audit table is found as
Annexure A.
![Page 16: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/16.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 16 Reg. No: 2007/023691/07
Compliance with Section 7 of the EMPr
The project employed a number of best practice options highlighted in Section 7 of the EMPr in order to satisfy
the auditable conditions and outcomes as set out in Section 6.
This project addressed compliance in addressing this section through implementing the following various
measures:
(i) Application for Water Use Licence
(ii) Induction of Contractor;
(iii) Identification and demarcation of No-Go areas;
(iv) Environmental budget for Construction Monitoring and Rehabilitation was set aside;
(v) Appointment of an External Environmental Control Officer;
(vi) Laydown Areas located in previously disturbed area;
(vii) Clearing of vegetation only in development footprint areas (Operational Access routes and boreholes
points);
(viii) Topsoil stored and maintained;
(ix) Waste management on site;
(x) Unobtrusive lights installed;
(xi) Hazardous Substance management;
(xii) No indication of unapproved fires;
(xiii) All boreholes points fences;
(xiv) Construction was undertaken during normal working hours;
(xv) Batching undertaken in dedicated area; and
(xvi) Rehabilitation with placement of topsoil on disturbed areas.
All the above was referenced in the ECO reports (Monthly or Close Out)
The Generic EMPr provided adequate measures for the avoidance, management, and mitigation of
environmental impacts associated with this intervention project, however it must be noted that not all
conditions were applicable to this project due to type of intervention (boreholes), location (inland) and relative
low impact of the project coupled with the generic nature of the EMPr.
![Page 17: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/17.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 17 Reg. No: 2007/023691/07
Table 1: Directive findings
Condition No.
Description
Co
mp
lian
ce
Par
tial
ly
Co
mp
lian
t
No
n-c
om
plia
nt
No
t A
pp
licab
le /
N
ot
Au
dit
ed
Finding Recommendations Timeframe
(If Applicable)
General Requirements
6.3.1.2
A second audit report within three (3) months of completion of an emergency measure or intervention (per measure or intervention). This second audit report must inter alia confirm how the measures or interventions implemented have contributed to the addressing the current water supply emergency situation and improved the water supply security in the areas within the jurisdiction of the municipality. This second audit report must also detail how all environmental impacts associated with each measure or intervention implemented have been mitigated’
0 An audit was not conducted 3 months post completion of intervention
This audit will satisfy this condition N/A
![Page 18: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/18.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 18 Reg. No: 2007/023691/07
Table 2: EMPr findings – PSEM4 Planning
PSEM4 Planning
Outcomes Identify and proposing suitable development options for the Emergency Water Resilience project resulting from strategic needs assessment, from where single option is selected.
Responsibilities Employer Agents’ professional team / Saldanha Bay Municipality
Timeframes On-going during planning
Performance Indicator
Target
Co
mp
lian
ce
Par
tial
ly
Co
mp
lian
t
No
n-c
om
plia
nt
No
t A
pp
licab
le /
N
ot
Au
dit
ed
Comments Recommendations Timeframe
(If Applicable)
1) Specialist input
a) Include all possible / associated activities within the various environmental permitting processes.
1 A water use licence was obtained for this project Only specialist Geohydrological report was drafted. No ecological or heritage studies were considered.
Project complete N/A
b) Assess possible environmental impacts on the terrestrial and marine environment.
0 No terrestrial specialist input was obtained prior to construction
Project complete Rehabilitation was completed post-construction in order to restore disturbed areas
N/A
2) Identifying and assessing all
impacts
a) Include Engineer and construction experienced Environmental Planner to inform the environmental permitting process
0 No additional permits were considered or obtained prior to construction
Project complete. No further action required N/A
3) Scope definition
a) Consider potential associated activities which may require the environmental permitting.
1
A Water Use Licence was applied for and received for this project. No heritage, or floral permits were considered or received for this project.
Project complete. No further action required N/A
c) Where applicable, conduct the needed specialist investigations and complete the required environmental permitting requirements to obtain approval from the various competent authorities.
1 Only specialist Geohydrological report was drafted and a water use licence was obtained for this project No ecological or heritage specialists were considered.
Project complete. No further action required N/A
![Page 19: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/19.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 19 Reg. No: 2007/023691/07
Table 3: EMPr findings – PSEM6 Pre-Construction
PSEM6 Pre-Construction
Outcomes Finalisation of relevant appointments / activities to an extent that development commencement is assured.
Responsibilities Contractor to draft Method Statements (as detailed in Table 1 of Annexure 4) and implement; WRECO to approve and supervise; and Independent Auditor to audit. Saldanha Bay Municipality Land Use Planning and Development Control department to be requested which Method Statements they wish to review and given the opportunity to do so.
Timeframes Method statement compiled and approved prior to commencement of activity. Implementation and compliance to be undertaken continuously.
Performance Indicator
Target
Co
mp
lian
ce
Par
tial
ly
Co
mp
lian
t
No
n-c
om
plia
nt
No
t A
pp
licab
le /
N
ot
Au
dit
ed
Comments Recommendations Timeframe
(If Applicable)
1) Search and Rescue
The Contractor shall undertake all activities associated with the search and rescue operation and have these completed prior to the commencement of construction related activities.
0 No Search & Rescue was conducted prior to construction
None. Rehabilitation has been conducted to restore the affected areas to as best as possible
N/A
2) Photographic record
Comprehensive photographic record of site and environs to be taken prior to any on site work.
0 No evidence that photographic evidence was taken prior to construction
Project complete. No further action required N/A
6) Approvals The Employers Agent (WRECO) shall ensure all approvals have been obtained.
0 No heritage approvals were obtained prior to construction
Project complete. No further action required N/A
![Page 20: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/20.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 20 Reg. No: 2007/023691/07
7 CONTRIBUTION TO CURRENT WATER SUPPLY
It was indicated in the SBM Water Intervention Plan that the West Coast District Municipality (WCDM) already
exceeded their current allocation from the Berg River for the last number of years (Pre-2018). The WCDM
applied for an increase in the license volume to 30 Million kl/annum in 2011, but awarding of this license was
still pending at the time of writing of the report. A water balance indicated that a shortfall would have been
experienced shortly after the report was published. By 2040 the shortfall will increase to 7.616 million kl/a
under low growth scenario to 11.229 million kl/a under high growth scenario if no intervention is put in place.
Water supply as per approved WULA’s prior/during implementation of groundwater projects.
To recap the supply from Western Cape Water Supply System (WCWSS) with its abstraction point being
Misverstand dam was 20 427 000 mᵌ/a prior to the wellfield intervention. SBM had to aim to reduce demand
to 20.35 ML/day during level 6 water restrictions which was deemed impossible without major economic
damage, due to business and industry being the SBM’s biggest consumers. Before the drought SBM was
utilising 37ML/day which was already above the previous allocation.
Water supply prior to implementation of groundwater projects.
Source Supply
(mᵌ/annum) Supply
(ML/day)
WCWSS 20 427 000 55.96
Existing Langebaan Road Boreholes (x4) 1 350 000 3.70
Total 21 777 000 59.66
Water supply after implementation of groundwater projects.
Source Supply
(mᵌ/annum) Supply
(ML/day)
WCWSS 20 427 000 55.96
Langebaan Road Aquifer (x8) boreholes. 4 old and 4 new
4 380 000 12
Hopefield well field X10 new boreholes 1 602 350 4.39
Total 26 409 350 72.35
The commissioning of the added an additional 3 030 000 mᵌ from the Langebaan intervention has significantly
increased the quantity available to the Municipality during times of need.
![Page 21: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/21.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 21 Reg. No: 2007/023691/07
8 SUMMARY
In terms of the results and findings of the audit on the SBM Water Intervention measure, Langebaan Phase 2,
it was found that the site is mostly compliant with conditions issued to the project, this can be seen in the
score of 77% compliance across both sets of documentation.
Any findings should however be placed in context of the full audit and each condition and its rating should be
looked at individually and dealt with accordingly.
Majority of the conditions of the EMPr were deemed not applicable as they were addressed in the Close out
Audit conducted by the ECO and deemed acceptable by the Department.
All non-compliant and partially-compliant findings observed were applicable during the pre-construction
phases, this was as a result of general misunderstanding of the Section 30A Directive by SBM and DEADP.
Rehabilitation of the disturbed areas seems to be positive with regrowth in majority of the areas.
Every effort has been made to ensure the site is run effectively and efficiently with minimal impact to the
environment and surrounds.
The project has positively contributed to the water supply as highlighted in Section 7.
Rehabilitation activities have contributed to the mitigation of environmental impacts along with measures
implemented during the Construction phase as monitored by the ECO.
![Page 22: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/22.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 22 Reg. No: 2007/023691/07
8.1 SUMMARY GRAPHICS
Compliance Table
No. Phase Compliant
Partially Compliant
Non-compliant
Not Applicable / Not Audited
1 Directive 5 0 1 1
2 Planning 1 3 2 2
3 Design 4 0 0 14
4 Pre-Construction 3 0 3 2
5 Construction 10 0 0 217
6 Decommissioning 0 0 0 19 Total 23 3 6 255 Audited Conditions 23 3 6 - Scoring 2 1 0 - Total Scores 46 3 0 - Compliance Rating Totals 71.9% 4.7% 0% - Percentage Break Down 8% 1% 2% 89%
Overall Compliance Rating 77%
Table 4: Overall Compliance Rating Table
Graph 1: Overall Breakdown Graph
Compliant, 23, 8%
Partially Compliant, 3, 1%
Non-compliant, 6, 2%
Not Applicable / Not Auditted, 255, 89%
Audit Breakdown
Compliant Partially Compliant Non-compliant Not Applicable / Not Auditted
![Page 23: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/23.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 23 Reg. No: 2007/023691/07
9 REPORT DISTRIBUTION LIST
PREPARED BY:
Nick Gates
Environmental Auditor
NCC Environmental Services (Pty) Ltd
M · 073 1998 431
Recipient Attention Issued Format
SBM David Wright Y Electronic
DEADP Keagan-leigh Adriaanse Y Electronic
DEADP Naadiya Wookey Y Electronic
DWS Mr. R. Khan Y Electronic
HWC Mr. M. Dlamuka ℅ Ms. W. Dhansay Y Electronic
DEA: O&C Dr. J. Mphepya ℅ Mr. Y. Peterson Y Electronic
![Page 24: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/24.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 24 Reg. No: 2007/023691/07
ANNEXURE A – SECTION 30A DIRECTIVE TABLE
![Page 25: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/25.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 25 Reg. No: 2007/023691/07
Condition No.
Description
Co
mp
lian
ce
Par
tial
ly
Co
mp
lian
t
No
n-c
om
plia
nt
No
t A
pp
licab
le /
No
t A
ud
ite
d
Comments Recommendations Timeframe
(If applicable)
6.1 - General Requirements
6.1
Monthly updates must be submitted to this Department, the Department of Water and Sanitation, Heritage Western Cape and the Department of Environmental Affairs: Oceans and Coast on the status of the water supply emergency situation within the municipal area and the progress being made on the implementation of emergency measures or interventions to address the water supply emergency situation. This monthly update must be submitted before the last working day of each month.
2
Monthly reports, including Section 30A Directive updates, have been sent to DEADP and provided to the auditor.
6.2 - Pre-implementation requirements
6.2.1
It is accepted that the municipality is in the process of finalizing a Water Supply Emergency Intervention Plan to address the current water supply emergency situation and to ensure resilience with respect to water supply security into the future. This Water Supply Emergency Intervention Plan, must set out list of measures or interventions that will fall within the ambit of this Section 30A Directive, describe each measure or intervention and explain how each measure or intervention specifically links to the current water supply emergency situation, as well as indicating the timeframe over which the measure or intervention will be implemented. This Water Supply Emergency Intervention Plan must be submitted to this Department for acceptance before commencing with any of the listed activities. Copies of the Water Supply Emergency must also be provided to the Department of Water and Sanitation, Heritage Western Cape and the Department of Environmental Affairs: Oceans and Coasts for their information. The Water Supply Emergency Intervention Plan must demonstrate how it relates to the Water Demand Supply Management Plan included in the Municipality's Integrated Development Plan.
2
Water Supply Emergency Intervention Plan is available Correspondence from DEADP was received
6.2.2
A generic Environmental Management Programme (EMPr) must be finalized as soon as is reasonably possible and submitted to this Department for acceptance before commencing with any of the listed activities, and copies of this EMPr must also be submitted to the Department of Water and Sanitation, Heritage Western Cape and the Department of Environmental Affairs: Oceans and Coasts.
2 Generic EMPr was accepted on the 1st February 2018
6.2.3
Method Statements for each of the measures or interventions to be implemented, as part of the Water Supply Emergency Intervention Plan, must be finalized as soon as is reasonably possible and submitted to this Department for acceptance before commencing with any of the listed activities. Copies of these method statements must also be submitted to the Department of Water and Sanitation, Heritage Western Cape and the Department of Environmental Affairs: Oceans and Coasts.
2 Method statement accepted on the 26th March 2018
6.3.1.1
A first audit report within six (6) months of the commencement of an emergency measure or intervention (per measure or intervention to be implemented), how section 2 of the NEMA has been considered and how the best practicable environmental option has been selected from alternatives.an emergency measure or intervention (per measure or intervention). This second audit report must inter alia confirm how the measures or interventions implemented have contributed to the addressing the current water supply emergency situation and improved the water supply security in the areas within the jurisdiction of the municipality. This second audit report must also detail how all environmental impacts associated with each measure or intervention implemented have been mitigated’
2 DEADP confirmed the ECO Close out report satisfied this condition
6.3.1.2
A second audit report within three (3) months of completion of an emergency measure or intervention (per measure or intervention). This second audit report must inter alia confirm how the measures or interventions implemented have contributed to the addressing the current water supply emergency situation and improved the water supply security in the areas within the jurisdiction of the municipality. This second audit report must also detail how all environmental impacts associated with each measure or intervention implemented have been mitigated’
0 An audit was not conducted 3 months post completion of intervention
This audit will satisfy this condition N/A
6.4.1
A final audit report must be submitted, within six (6) months of completion of all measures or interventions (as per the Water Supply Emergency Intervention Plan) implemented to address the current water supply emergency situation. This final audit report must inter alia confirm how all the risks associated with the water supply emergency situation have been addressed and how all of the measures or interventions implemented have contributed to ensuring the future resilience of water supply security by the municipality. It must further indicate what future interventions that may fall outside the scope of the Directive are planned, to maintain such resilience in to the future.
NA To be completed at the end of all interventions
![Page 26: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/26.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 26 Reg. No: 2007/023691/07
ANNEXURE B – EMPR TABLE
![Page 27: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/27.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 27 Reg. No: 2007/023691/07
PSEM4 Planning
Outcomes Identify and proposing suitable development options for the Emergency Water Resilience project resulting from strategic needs assessment, from where single option is selected.
Responsibilities Employer Agents’ professional team / Saldanha Bay Municipality
Timeframes On-going during planning
Performance Indicator Target
Co
mp
lian
ce
Par
tial
ly C
om
plia
nt
No
n-c
om
plia
nt
No
t A
pp
licab
le /
No
t A
ud
ite
d
Findings Recommendations Timeframe
(If applicable)
1) Specialist input
a) Include all possible / associated activities within the various environmental permitting processes.
1 A water use licence was obtained for this project Only specialist Geohydrological report was drafted. No ecological or heritage studies were considered.
Project complete. No further action required
N/A
b) Assess possible environmental impacts on the terrestrial and marine environment.
0 No terrestrial specialist input was obtained prior to construction
Project complete Rehabilitation was completed post-construction in order to restore disturbed areas
N/A
2) Identifying and assessing all impacts
a) Include Engineer and construction experienced Environmental Planner to inform the environmental permitting process
0 No additional permits were considered or obtained prior to construction
Project complete. No further action required
N/A
3) Scope definition
a) Consider potential associated activities which may require the environmental permitting.
1 A Water Use Licence was applied for and received for this project. No heritage, or floral permits were considered or received for this project.
Project complete. No further action required
N/A
b) Consider potential Contractor requirements within environmental permitting process, e.g. site camp locality and possible lay down areas.
NA Not applicable. Address above
c) Where applicable, conduct the needed specialist investigations and complete the required environmental permitting requirements to obtain approval from the various competent authorities.
1 Only specialist Geohydrological report was drafted and a water use licence was obtained for this project No ecological or heritage specialists were considered.
Project complete. No further action required
N/A
4) Sustainability
a) Planning shall emphasise sustainable development, local procurement and jobs.
NA It was indicated by the Municipality that local labour were employed
b) Planning includes site locations owned by the Saldanha Bay Municipality, and/or already disturbed sites to minimise the environmental and social impact of the projects
2 The project was for the extension of an existing borehole next work and is located adjacent to the main bulk water supply system.
![Page 28: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/28.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 28 Reg. No: 2007/023691/07
PSEM5 Design
Outcomes Integrating environmental and sustainable requirements within the design to an extent that environmental protection and sustainable development are assured for the Emergency Water Resilience project.
Responsibilities Employer Agents’ professional team / Saldanha Bay Municipality
Timeframes On-going during conceptual and detailed design
Performance Indicator Target
Co
mp
lian
ce
Par
tial
ly
Co
mp
lian
t
No
n-c
om
plia
nt
No
t A
pp
licab
le /
N
ot
Au
dit
ed
Comments Recommendations Timeframe
(If applicable)
1) Compliance Review a) Undertake an environmental compliance review if the environmental permitting process was undertaken by an external third party.
NA Construction complete
2) Inform Design a) Ensure EMPr, environmental authorisation and any other approval/permit requirements are obtained and inform the design for the Emergency Water Resilience project.
NA Construction complete
3) Reviews of designs a) The Environmental Planner, where applicable, shall review the final designs. NA Construction complete
4) Aesthetics
a) Design of the Emergency Water Resilience project shall restrict sky glow, light spill and glare.
2 Where applicable only security lighting is in place
b) In accordance with the building regulations the proposed temporary plant associated with the temporary containerised desalination projects shall not exceed a maximum element height of approximately 6.5m.
NA Not a desalination project
c) Where possible and required (as per site-specific project) pipelines will be buried, otherwise is will be stabilised as specified in the engineering specifications.
2 All piping has been buried
5) Air quality
a) Design of the Emergency Water Resilience project shall enable compliance with National Ambient Air Quality Standards, Saldanha Bay Municipality Air Quality Management By-law and National Dust Control Regulation requirements, as amended.
NA Construction complete
b) Emergency generators shall be deployed to run on low sulphur diesel fuel to limit the impact of sulphur emissions to the ambient air quality.
NA Construction complete
6) Noise control
a) Design of the Emergency Water Resilience project shall enable compliance with Western Cape Noise Control Regulation requirements, as amended.
NA This is a borehole network project used only for high demand. No noise experienced during site inspection
c) Allowable Noise Limits:
- The noise limits for an industrial zone is 70dBA daytime and 60dBA night-time (when measured on the boundary).
NA This is a borehole network project used only for high demand. No noise experienced during site inspection
- For residential, it is 50dBA daytime and 40bBA night-time. NA This is a borehole network project used only for high demand. No noise experienced during site inspection
- Also there is a 50dBA restriction on machinery in a residential area. NA This is a borehole network project used only for high demand. No noise experienced during site inspection
7) Water quality and quantity
8) Water efficiency
a) Design shall enable compliance with all applicable water quality (SANS 241: 2015) and quantity regulatory requirements, as amended.
2 A water use license has been obtained
b) All designs to comply with Construction Regulations 10400XB. 2 Project was overseen by Professional Engineer team
c) Water abstraction for construction purposes, washing of machinery and vehicles are strictly prohibited.
NA Construction complete
9) Energy efficiency a) All designs to comply with Construction Regulations 10400XA. NA Construction complete
b) Installation of photo-voltaic panels (if required). NA Not Applicable
10) Waste management a) Design of the Emergency Water Resilience project shall reduce waste
generation whilst promoting re-use and recycling, where possible. NA Construction complete
![Page 29: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/29.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 29 Reg. No: 2007/023691/07
PSEM6 Pre-Construction
Outcomes Finalisation of relevant appointments / activities to an extent that development commencement is assured.
Responsibilities Contractor to draft Method Statements (as detailed in Table 1 of Annexure 4) and implement; WRECO to approve and supervise; and Independent Auditor to audit. Saldanha Bay Municipality Land Use Planning and Development Control department to be requested which Method Statements they wish to review and given the opportunity to do so.
Timeframes Method statement compiled and approved prior to commencement of activity. Implementation and compliance to be undertaken continuously.
Performance Indicator Target
Co
mp
lian
ce
Par
tial
ly
Co
mp
lian
t
No
n-c
om
plia
nt
No
t A
pp
licab
le /
N
ot
Au
dit
ed
Comments Recommendations Timeframe
(If applicable)
1) Search and Rescue The Contractor shall undertake all activities associated with the search and rescue operation and have these completed prior to the commencement of construction related activities.
0 No Search & Rescue was conducted prior to construction
None. Rehabilitation has been conducted to restore the affected areas to as best as possible
N/A
2) Photographic record Comprehensive photographic record of site and environs to be taken prior to any on site work.
0 No evidence that photographic evidence was taken prior to construction
Project is complete N/A
3) Alignment to engineering requirements
The approved EMPr and any other regulatory requirements shall be aligned with engineering requirements.
2 EMPr was approved by DEADP. EMPr is aligned to various SANS standards, along with Municipal By Laws
4) Budget The Contractor shall make provision for adequate budget for construction site environmental management requirements.
NA Construction complete
5) Tender review The Employers Agent (WRECO) shall ensure an environmental review of all tender submissions is undertaken.
NA Not audited
6) Approvals The Employers Agent (WRECO) shall ensure all approvals have been obtained.
0 No heritage approvals were obtained prior to construction Project is complete. N/A
7) Environmental Compliance Monitoring
The Saldanha Bay Municipality shall appoint a competent and knowledgeable WRECO; and where required, an Environmental Auditor.
2 A designated WRECO has been in appointed, David Wright. NCC have been contracted as external Auditors
8) Contractors Environmental Officer a) The Contractor shall appoint a competent and knowledgeable Contractors Environmental Officer.
2 An ECO was appointed for the duration of the contract
![Page 30: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/30.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 30 Reg. No: 2007/023691/07
PSEM7 Aesthetics Management
Outcomes Preserve aesthetics of the surrounding environment to assure the development does not become a nuisance to local communities; or negatively impacts upon the environment.
Responsibilities Contractor to draft Method Statement and implement; WRECO to approve and supervise; and Independent Auditor to audit.
Timeframes Method statement compiled and approved prior to commencement of activity. Implementation and compliance to be undertaken continuously.
Performance Indicator Target
Co
mp
lian
ce
Par
tial
ly C
om
plia
nt
No
n-c
om
plia
nt
No
t A
pp
licab
le /
N
ot
Au
dit
ed
Comments Recommendations Timeframe
(If applicable)
1) Dust levels a) Dust generation shall not exceed the regulated dust thresholds. NA Construction complete. No major issues identified in ECO Close Out Report
2) Rehabilitation of impacted works areas.
a) All areas impacted upon through construction related activities shall be rehabilitated.
NA Construction complete. No major issues identified in ECO Close Out Report
3) Stockpile management
a) Stockpiles are not to be higher than 2m. NA Construction complete. No major issues identified in ECO Close Out Report
b) Stockpiles shall be stabilised with no evidence of erosion. NA Construction complete. No major issues identified in ECO Close Out Report
4) Visual impact of works areas on surrounding
environment
a) No grievances from stakeholders. NA Construction complete. No major issues identified in ECO Close Out Report
b) Maintain good housekeeping practices. NA Construction complete. No major issues identified in ECO Close Out Report
5) Light pollution
a) No light shining into surrounding properties. NA Construction complete. No major issues identified in ECO Close Out Report
b) No grievances from stakeholders. NA Construction complete. No major issues identified in ECO Close Out Report
6) Litter
a) Record of daily litter clean up. NA Construction complete. No major issues identified in ECO Close Out Report
b) No litter to be found on site. NA Construction complete. No major issues identified in ECO Close Out Report
c) No grievances from stakeholders. NA Construction complete. No major issues identified in ECO Close Out Report
![Page 31: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/31.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 31 Reg. No: 2007/023691/07
PSEM8 Dust Management
Outcomes Preserve air quality levels to an extent that public health; safety and environmental protection are assured.
Responsibilities Contractor to draft Method Statement and implement; WRECO to approve and supervise; and Independent Auditor to audit.
Timeframes Method statement compiled and approved prior to commencement of activity. Implementation and compliance to be undertaken continuously.
Performance Indicator Target
Co
mp
lian
ce
Par
tial
ly
Co
mp
lian
t
No
n-c
om
plia
nt
No
t A
pp
licab
le /
N
ot
Au
dit
ed
Comments Recommendations Timeframe
(If applicable)
1) Monitoring
a) Identify all dust sources. NA Construction complete. No major issues identified in ECO Close Out Report
b) Assess effectiveness of dust control measures. NA Construction complete. No major issues identified in ECO Close Out Report
c) Provide suitable data to demonstrate compliance with regulatory requirements.
NA Construction complete. No major issues identified in ECO Close Out Report
d) Ensure all monitoring equipment is calibrated as per manufacturer’s specifications.
NA Construction complete. No major issues identified in ECO Close Out Report
e) Ensure all monitoring is undertaken by suitably qualified and competent individuals.
NA Construction complete. No major issues identified in ECO Close Out Report
f) Dust fall out monitoring shall be undertaken along the perimeter fence and aligned with prevailing wind directions.
NA Construction complete. No major issues identified in ECO Close Out Report
2) PM10 inhalable particulates only monitored
upon Saldanha Bay Municipality instruction.
a) PM10 monitoring shall be in accordance with GNR 1210, National Ambient Air Quality Standards, of 24 December 2009, as amended.
NA Construction complete. No major issues identified in ECO Close Out Report
b) PM10 shall be monitored at sensitive (rural) receptors when construction related activities occur within 250 m of the receptors.
NA Construction complete. No major issues identified in ECO Close Out Report
c) PM10 shall also be measured at active construction related areas and at additional sites indicated by the WRECO.
NA Construction complete. No major issues identified in ECO Close Out Report
d) Monitoring shall be conducted/undertaken as per the regulated frequencies.
NA Construction complete. No major issues identified in ECO Close Out Report
g) PM10 levels shall not exceed the prescribed levels. NA Construction complete. No major issues identified in ECO Close Out Report
h) PM10 monitoring shall be undertaken within work areas aligned with prevailing wind directions.
NA Construction complete. No major issues identified in ECO Close Out Report
3) Dust nuisance levels.
a) Suspended (actual) dust levels shall not exceed 600 mg/m2/day. NA Construction complete. No major issues identified in ECO Close Out Report
b) The Contractor shall respond to all grievances relating to dust and air quality.
NA Construction complete. No major issues identified in ECO Close Out Report
4) Dust fallout only monitored upon Saldanha
Bay Municipality instruction.
a) Indicative dust fallout (i.e. suspended dust concentrations that will result in fallout) shall be monitored in terms of the GNR 827, National Dust Control Regulations of 1 November 2013, as amended.
NA Construction complete. No major issues identified in ECO Close Out Report
b) Actual dust fallout shall be verified through sampling at sites as prescribed by theWRECO.
NA Construction complete. No major issues identified in ECO Close Out Report
![Page 32: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/32.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 32 Reg. No: 2007/023691/07
PSEM9 Earthworks Management
Outcomes Maintain earth works practices in a manner that public health; safety and environmental protection are assured.
Responsibilities Contractor to draft Method Statement and implement; WRECO to approve and supervise; and Independent Auditor to audit.
Timeframes Method statement compiled and approved prior to commencement of activity. Implementation and compliance to be undertaken continuously.
Performance Indicator Target
Co
mp
lian
ce
Par
tial
ly
Co
mp
lian
t
No
n-c
om
plia
nt
No
t A
pp
licab
le /
N
ot
Au
dit
ed
Comments Recommendations Timeframe
(If applicable)
1) Topsoil and subsoil handling and management.
a) Soil horizons stockpile separately. NA Construction complete. No major issues identified in ECO Close Out Report
b) Stockpiles no higher than 2 m and kept weed free. NA Construction complete. No major issues identified in ECO Close Out Report
2) Water resource management
a) Water resources shall not be negatively impacted upon through sedimentation / contamination.
NA Construction complete. No major issues identified in ECO Close Out Report
3) Prevention of contamination.
a) Stockpiles shall be kept free of contamination by oils/fuels and other harmful substances.
NA Construction complete. No major issues identified in ECO Close Out Report
4) Reinstatement of previous land use practices.
a) No complaints from stakeholder’s. NA Construction complete. No major issues identified in ECO Close Out Report
b) No erosion. NA Construction complete. No major issues identified in ECO Close Out Report
5) Placement of stockpiles within specifically demarcated
areas.
a) No stockpiles within the 1:20 flood line of a watercourse or within 50m of delineated wetland.
NA Construction complete. No major issues identified in ECO Close Out Report
b) No stockpiles within specified no-go areas. NA Construction complete. No major issues identified in ECO Close Out Report
c) No stockpiles in vegetated areas, unless otherwise approved by the relevant decision-making authorities.
NA Construction complete. No major issues identified in ECO Close Out Report
![Page 33: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/33.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 33 Reg. No: 2007/023691/07
PSEM10 Erosion Management
Outcomes Preserve soil and vegetation cover to an extent that minimal loss of soil through erosion can be assured.
Responsibilities Contractor to draft Method Statement and implement; WRECO to approve and supervise; and Independent Auditor to audit.
Timeframes Method statement compiled and approved prior to commencement of activity. Implementation and compliance to be undertaken continuously.
Performance Indicator Target
Co
mp
lian
ce
Par
tial
ly
Co
mp
lian
t
No
n-c
om
plia
nt
No
t A
pp
licab
le /
N
ot
Au
dit
ed
Comments Recommendations Timeframe
(If applicable)
1) Erosion prevention.
a) All gradients > than 1:2 (vertical: horizontal) stabilised within one week of their exposure.
NA Construction complete. No major issues identified in ECO Close Out Report
b) Formalised storm water structures must be designed and implemented along roads susceptible to erosion.
NA Construction complete. No major issues identified in ECO Close Out Report
c) Slopes > 1:1 must have additional anti-erosion mechanisms (berms, silt traps and fences or geo-textiles).
NA Construction complete. No major issues identified in ECO Close Out Report
d) No evidence of erosion or damage to erosion control devices. NA Construction complete. No major issues identified in ECO Close Out Report
e) No collapse/subsidence of banks at water crossings or steep slopes. NA Construction complete. No major issues identified in ECO Close Out Report
f) No significant changes to ground level, drainage patterns or vegetative cover as a result of erosion or sedimentation.
NA Construction complete. No major issues identified in ECO Close Out Report
2) Control alien invasive species.
a) Records of monthly alien invasive species clearing. NA Construction complete. No major issues identified in ECO Close Out Report
b) The Contractor shall keep the development footprint free of alien invasive species.
NA Construction complete. No major issues identified in ECO Close Out Report
3) Existing land use protection.
a) No evidence of disturbance outside of development footprint area. NA Construction complete. No major issues identified in ECO Close Out Report
4) Rehabilitation of impacted areas.
a) The Contractor shall attain rehabilitation targets. NA Construction complete. No major issues identified in ECO Close Out Report
5) Water quality as indicator of levels of soil erosion.
a) The Contractor shall attain prescribed water quality targets. NA Construction complete. No major issues identified in ECO Close Out Report
6) Storm water a) Monitor and maintain storm water infrastructure and review storm water
management initiatives, where applicable. NA Not applicable
![Page 34: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/34.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 34 Reg. No: 2007/023691/07
PSEM11 (Marine and Terrestrial) Fauna and Flora Management
Outcomes Preserve the environment to an extent that fauna and flora are protected; and prevention of alien invasive species infestation can be assured.
Responsibilities Contractor to draft Method Statement and implement; WRECO to approve and supervise; and Independent Auditor to audit.
Timeframes Method statement compiled and approved prior to commencement of activity. Implementation and compliance to be undertaken continuously.
Performance Indicator Target
Co
mp
lian
ce
Par
tial
ly
Co
mp
lian
t
No
n-c
om
plia
nt
No
t A
pp
licab
le /
N
ot
Au
dit
ed
Comments Recommendations Timeframe
(If applicable)
1) Reduction of extent of impacts.
a) No evidence of disturbance outside of the approved development footprint.
NA Construction complete. No major issues identified in ECO Close Out Report
2) Identification and protection of ecologically sensitive areas.
a) All sensitive marine and terrestrial environments shall be identified and afforded appropriate protection.
NA Construction complete. No major issues identified in ECO Close Out Report
b) No go areas are clearly demarcated and adhered to. NA Construction complete. No major issues identified in ECO Close Out Report
3) Identification and protection of species.
a) Proof of training of staff for identification and rescue and relocation of known conservation worthy species.
NA Construction complete. No major issues identified in ECO Close Out Report
b) No unauthorised collection of or disturbance to marine and terrestrial fauna and flora.
NA Construction complete. No major issues identified in ECO Close Out Report
c) Search and rescue operations shall include consultation with the Saldanha Bay Municipality’s Biodiversity Management Branch.
NA Construction complete. No major issues identified in ECO Close Out Report
4) Landowner requirements
a) No grievances from landowners. NA Construction complete. No major issues identified in ECO Close Out Report
b) Each indigenous tree, shrub or bulb removed through search and rescue operations shall be replanted in the area from where it came or in an area as advised by the Saldanha Bay Municipality Land Use Planning and Development Control.
NA Construction complete. No major issues identified in ECO Close Out Report
5) Wildlife and livestock management.
a) Access to individual land portions shall be controlled through the appropriate use of gates.
NA Construction complete. No major issues identified in ECO Close Out Report
b) All livestock injuries or fatalities shall be investigated, recorded and reported to the WRECO and the respective landowner
NA Construction complete. No major issues identified in ECO Close Out Report
c) The Contractor shall restrict vehicle speeds within the development footprint to prevent faunal fatalities.
NA Construction complete. No major issues identified in ECO Close Out Report
6) Management of alien invasive species.
a) Proof of scheduled removal of alien invasive vegetation. NA Construction complete. No major issues identified in ECO Close Out Report
b) Chemical control of invasive species to be undertaken under the auspices of a Department of Agriculture, Forestry and Fisheries (DAFF) authorised Pest Control Officer (PCO).
NA Construction complete. No major issues identified in ECO Close Out Report
c) No alien invasive vegetation growth within development footprint. NA Construction complete. No major issues identified in ECO Close Out Report
7) Pipelines into the sea and brine
a) Obtain Authorisations from relevant competent authorities NA Not Applicable to this Project
b) Compliance with conditions of the competent authority assured NA Not Applicable to this Project
![Page 35: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/35.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 35 Reg. No: 2007/023691/07
PSEM12 Fire Management
Outcomes Prevent and control fires to an extent that public health; safety; property and environmental protection are assured.
Responsibilities Contractor to draft Method Statement and implement; WRECO to approve and supervise; and Independent Auditor to audit.
Timeframes Method statement compiled and approved prior to commencement of activity. Implementation and compliance to be undertaken continuously.
Performance Indicator Target
Co
mp
lian
ce
Par
tial
ly
Co
mp
lian
t
No
n-c
om
plia
nt
No
t A
pp
licab
le /
N
ot
Au
dit
ed
Comments Recommendations Timeframe
(If applicable)
1) Number of fires. a) Zero (0) fires. NA Construction complete. No major issues identified in ECO Close Out Report
2) Emergency preparedness.
a) Proof of annual update and approval of the fire management response plan.
NA Construction complete. No major issues identified in ECO Close Out Report
b) Proof of management review of fire preparedness and response before onset of fire season.
NA Construction complete. No major issues identified in ECO Close Out Report
c) Proof of six-monthly fire and emergency drills every six months and effectiveness thereof audited.
NA Construction complete. No major issues identified in ECO Close Out Report
d) Emergency response plan implemented. NA Construction complete. No major issues identified in ECO Close Out Report
e) Safety management plan implemented NA Construction complete. No major issues identified in ECO Close Out Report
3) Adequate fire protection measures.
a) Proof of Municipal Fire Chief being informed. NA Construction complete. No major issues identified in ECO Close Out Report
b) Compliance with SANS 10131. NA Construction complete. No major issues identified in ECO Close Out Report
c) Fire-fighting equipment shall be available at all high risk or points of storage of flammable products.
NA Construction complete. No major issues identified in ECO Close Out Report
d) Proof of examination / inspection of fire extinguishers on a continual basis.
NA Construction complete. No major issues identified in ECO Close Out Report
e) All activities undertaken shall be managed to mitigate risk of fire. NA Construction complete. No major issues identified in ECO Close Out Report
f) Smoking only allowed in designated areas approved by the Contractor’s EO.
NA Construction complete. No major issues identified in ECO Close Out Report
4) Compliance with regulatory and procedural requirements.
a) Storage of hazardous/flammable materials and substances to comply with national, provincial and local regulatory requirements.
NA Construction complete. No major issues identified in ECO Close Out Report
b) Proof of reporting of fire incidences to authorities. NA Construction complete. No major issues identified in ECO Close Out Report
c) No fires within the development footprint. NA Construction complete. No major issues identified in ECO Close Out Report
d) No build-up of flammable material on or adjacent to the development footprint.
NA Construction complete. No major issues identified in ECO Close Out Report
5) Adequate fire protection measures in place in rural areas.
a) Fire breaks in place, in consultation with respective landowners, the width of which to be determined by the Fire Protection Association (FPA).
NA Construction complete. No major issues identified in ECO Close Out Report
b) Proof of membership/registration with the local FPA. NA Construction complete. No major issues identified in ECO Close Out Report
c) Presentation of the Fire Danger Index (FDI) for the area. NA Construction complete. No major issues identified in ECO Close Out Report
![Page 36: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/36.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 36 Reg. No: 2007/023691/07
PSEM13 Hazardous Substance Management
Outcomes Preserve the receiving environment, well-being of staff and local communities through appropriate hazardous substance storage, handling, and disposal and pollution prevention.
Responsibilities Contractor to draft Method Statement and implement; WRECO to approve and supervise; and Independent Auditor to audit.
Timeframes Method statement compiled and approved prior to commencement of activity. Implementation and compliance to be undertaken continuously.
Performance Indicator Target
Co
mp
lian
ce
Par
tial
ly
Co
mp
lian
t
No
n-c
om
plia
nt
No
t A
pp
licab
le /
N
ot
Au
dit
ed
Comments Recommendations Timeframe
(If applicable)
1) Adequate measures implemented for the
containment of hazardous substances.
a) All hazardous substance storage areas shall be equipped with appropriate spill kits and fire-fighting equipment.
NA Construction complete. No major issues identified in ECO Close Out Report
b) All hazardous substances shall be stored in well ventilated secondary (impermeable) containers / bunds capable of 110% of the volume of the container. A tap-off system shall be installed through which leakages and spills can be removed.
NA Construction complete. No major issues identified in ECO Close Out Report
c) All staff required to handle and use such hazardous substances shall receive adequate training.
NA Construction complete. No major issues identified in ECO Close Out Report
d) All necessary approvals with respect to hazardous substances shall be obtained from the appropriate authorities and shall comply with standard fire safety regulations.
NA Construction complete. No major issues identified in ECO Close Out Report
e) All chemicals shall be stored in specifically designed, lockable storage areas where reactive substances are classed and segregated. Storage shall comply with the manufacturers Material Safety Data Sheet (MSDS) and local and national legislative requirements.
NA Construction complete. No major issues identified in ECO Close Out Report
f) Hazardous waste and waste fuels and oils shall be stored in appropriate containers that will not corrode or leak. These containers shall be properly marked to indicate contents.
NA Construction complete. No major issues identified in ECO Close Out Report
g) Waste manifest (proof of safe disposal) should be obtained and kept onsite (shown to the WRECO acting as the Employer’s Agent & Site Manager).
NA Construction complete. No major issues identified in ECO Close Out Report
2) Hazardous substance management.
a) All hazardous substances stored on site shall be recorded within a checklist.
NA Construction complete. No major issues identified in ECO Close Out Report
b) All hazardous substances shall be labelled according to the chemical hazard rating and adequate signage be displayed indicating the appropriate management measures to be implemented in the event of a spill/fire.
NA Construction complete. No major issues identified in ECO Close Out Report
c) Only specifically trained personnel shall be permitted to use and handle the hazardous substances. Certificates of training shall be provided to the WRECO for final approval.
NA Construction complete. No major issues identified in ECO Close Out Report
d) Substances used shall be the least environmentally harmful chemical available for the undertaking of specific duties/requirements.
NA Construction complete. No major issues identified in ECO Close Out Report
3) Incident management
a) Ensure that the necessary materials and equipment for dealing with oil, fuel and hazardous substance spills, leaks and fires are available on site and up to date at all times.
NA Construction complete. No major issues identified in ECO Close Out Report
b) The following symbolic safety signs shall inter alia be depicted: “No Smoking”, “No Naked Lights” and “Danger”.
NA Construction complete. No major issues identified in ECO Close Out Report
c) These signs shall conform to the requirements of SANS 1186-1 and are to be prominently displayed in and around the storage area.
NA Construction complete. No major issues identified in ECO Close Out Report
d) The volume and contents of the tanks shall be displayed using the emergency information system detailed in SANS 10232-1.
NA Construction complete. No major issues identified in ECO Close Out Report
e) Signage containing clearly displayed emergency contact numbers shall be provided.
NA Construction complete. No major issues identified in ECO Close Out Report
![Page 37: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/37.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 37 Reg. No: 2007/023691/07
4) Fire fighting a) Suitable fire-fighting equipment shall be stored in close proximity and all personnel be made aware of the dangers of burning chemicals/smoke inhalation.
NA Construction complete. No major issues identified in ECO Close Out Report
5) Personnel protection
a) No smoking shall be permitted in the vicinity of the store/s and adequate fire-fighting equipment shall be provided at hazardous substance storage and dispensing areas.
NA Construction complete. No major issues identified in ECO Close Out Report
b) All staff working with hazardous substances shall wear PPE. NA Construction complete. No major issues identified in ECO Close Out Report
6) Sewage management a) No environmental contamination due to sewage management. NA Construction complete. No major issues identified in ECO Close Out Report
7) Cement / Concrete management
a) Cement / concrete shall only to be mixed within WRECO approved localities.
NA Construction complete. No major issues identified in ECO Close Out Report
b) Waste cement / concrete shall only be disposed of at WRECO approved localities.
NA Construction complete. No major issues identified in ECO Close Out Report
c) Facilities used to wash plant / equipment used in the mixing / transporting / placement of concrete shall be Employer Agent approved.
NA Construction complete. No major issues identified in ECO Close Out Report
![Page 38: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/38.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 38 Reg. No: 2007/023691/07
PSEM14 Heritage Management
Outcomes Preserve heritage resources to an extent that no loss, defacement or damage thereof can be assured.
Responsibilities Contractor to draft Method Statement and implement; WRECO to approve and supervise; and Independent Auditor to audit.
Timeframes Method statement compiled and approved prior to commencement of activity. Implementation and compliance to be undertaken continuously.
Performance Indicator Target
Co
mp
lian
ce
Par
tial
ly
Co
mp
lian
t
No
n-c
om
plia
nt
No
t A
pp
licab
le /
N
ot
Au
dit
ed
Comments Recommendations Timeframe
(If applicable)
1) Protection of heritage resources.
a) No removal, damaging or alteration to heritage resources, unless proof of consultation with a heritage specialist and approval from HWC is in place.
NA Construction complete. No major issues identified in ECO Close Out Report
b) All buildings and or structures older than 60 years shall require a permit should they be changed or demolished.
NA Construction complete. No major issues identified in ECO Close Out Report
c) Maritime archaeology (i.e. shipwrecks) require a permit should they be removed or disturbed.
NA Construction complete. No major issues identified in ECO Close Out Report
2) Management of chance finds.
The relevant authorised heritage professional (either archaeologist or palaeontologist), as specified by the heritage authority, must oversee and monitor ground clearing and earth moving activities. In addition, all on-site construction personnel should be given a short course on how to recognize archaeological artefacts, fossils and other heritage material.
NA Construction complete. No major issues identified in ECO Close Out Report
No heritage material may be removed from the site, except by the heritage professional and only if permitted to do so by a heritage authority.
NA Construction complete. No major issues identified in ECO Close Out Report
When high concentrations of heritage material (fossils, stone artefacts, midden material etc.) are uncovered, construction activities should stop in the locality of the find and the heritage professional called in to assess the find. These finds should immediately be reported to the relevant heritage authority (South African Heritage Resources Agency (021 462 4502) / or Heritage Western Cape (021 483 9692), including the West Coast Fossil Park (022 766 1606) when fossils are discovered) must be notified and all works temporarily stopped. Burial remains must not be disturbed or removed until inspected by an archaeologist.
NA Construction complete. No major issues identified in ECO Close Out Report
Should any activity be required off shore, the SAHRA maritime unit would need to be consulted to ensure no maritime archaeology (i.e. shipwrecks) would be affected.
NA Construction complete. No major issues identified in ECO Close Out Report
a) Records of chance findings shall be kept. NA Construction complete. No major issues identified in ECO Close Out Report
b) Where chance finds are unearthed, proof of work being stopped and proof of consultation with heritage specialist and HWC shall be kept on site.
NA Construction complete. No major issues identified in ECO Close Out Report
c) The unearthing of graves must immediately be reported to the WRECO, the South African Police Service and HWC. An archaeologist shall be notified and the area shall be cordoned off from all works until the archaeologist has completed an investigation and proposed recommendations, in consultation with HWC.
NA Construction complete. No major issues identified in ECO Close Out Report
![Page 39: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/39.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 39 Reg. No: 2007/023691/07
PSEM15 Land Owner Liaison
Outcomes Preserve the rights of affected landowners to an extent that no significant grievances are raised.
Responsibilities Contractor to draft Method Statement and implement; WRECO to approve and supervise; and Independent Auditor to audit.
Timeframes Method statement compiled and approved prior to commencement of activity. Implementation and compliance to be undertaken continuously.
Performance Indicator Target
Co
mp
lian
ce
Par
tial
ly
Co
mp
lian
t
No
n-c
om
plia
nt
No
t A
pp
licab
le /
N
ot
Au
dit
ed
Comments Recommendations Timeframe
(If applicable)
1) Communication with landowners.
a) Communications register (for grievances) shall be kept at the site office. NA Construction complete. No major issues identified in ECO Close Out Report
b) No reports of complaints not being dealt with promptly. NA Construction complete. No major issues identified in ECO Close Out Report
c) Minutes of meetings held with local community members and other stakeholders.
NA Construction complete. No major issues identified in ECO Close Out Report
d) Notify landowners in advance in the event of construction related activities likely to cause disruptions to current land use practices.
NA Construction complete. No major issues identified in ECO Close Out Report
2) Safety of the work environment.
a) PPE is available and worn by staff and visitors. NA Construction complete. No major issues identified in ECO Close Out Report
b) The site, together with all excavations shall be safe guarded. In addition, barriers and warning signs shall be placed around all excavations.
NA Construction complete. No major issues identified in ECO Close Out Report
c) Site boundary fence shall display relevant signage. NA Construction complete. No major issues identified in ECO Close Out Report
d) Demarcate “no-go” areas and restrict access. NA Construction complete. No major issues identified in ECO Close Out Report
3) Gates. a) Maintain status of gates (keep “closed” gates closed; and “open” gates open).
NA Construction complete. No major issues identified in ECO Close Out Report
4) Landowner database.
b) Maintain a database of landowners contact details. NA Construction complete. No major issues identified in ECO Close Out Report
c) New landowners shall be briefed on the construction programme. NA Construction complete. No major issues identified in ECO Close Out Report
5) Provision of skills training. a) Provide suitable training to all employees to ensure no grievances lodged. NA Construction complete. No major issues identified in ECO Close Out Report
6) Site camp. a) The site camp shall obtain all relevant approvals prior to establishment. NA Construction complete. No major issues identified in ECO Close Out Report
7) Working hours to approve and supervise; and Independent Auditor to audit.(*AS COPIED
FROM EMPR) NA
Construction complete. No major issues identified in ECO Close Out Report
![Page 40: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/40.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 40 Reg. No: 2007/023691/07
PSEM16 (MISSING) (ASSUMED NOISE)
Outcomes Not Included in EMPr
Responsibilities Not Included in EMPr
Timeframes Method statement compiled and approved prior to commencement of activity. Implementation and compliance to be undertaken continuously.
Performance Indicator Target
Co
mp
lian
ce
Par
tial
ly
Co
mp
lian
t
No
n-c
om
plia
nt
No
t A
pp
licab
le /
N
ot
Au
dit
ed
Comments Recommendations Timeframe
(If applicable)
1) Notification of sensitive receptors.
a) Sensitive receptors shall be notified of the timing and duration of the construction related activities and the potential noise nuisance it may cause.
NA Construction complete. No major issues identified in ECO Close Out Report
b) Respond to all noise related grievances received and implement mitigation measures.
NA Construction complete. No major issues identified in ECO Close Out Report
2) Noise levels.
a) Noise levels shall be monitored to comply with SANS 10103:2008 and Occupational Health and Safety Act requirements.
NA Construction complete. No major issues identified in ECO Close Out Report
b) Design of the Emergency Water Resilience project shall enable compliance with Western Cape Noise Control Regulation requirements, as amended.
NA Construction complete. No major issues identified in ECO Close Out Report
d) Allowable Noise Limits: NA Construction complete. No major issues identified in ECO Close Out Report
- The noise limits for an industrial zone is 70dBA daytime and 60dBA night-time (when measured on the boundary).
NA Construction complete. No major issues identified in ECO Close Out Report
- For residential, it is 50dBA daytime and 40bBA night-time. NA Construction complete. No major issues identified in ECO Close Out Report
b) there is a 50dBA restriction on machinery in a residential area. NA Construction complete. No major issues identified in ECO Close Out Report
3) Deviations from normal construction related activity
conditions.
a) All construction related works shall be undertaken during normal prescribed / agreed daylight hours.
NA Construction complete. No major issues identified in ECO Close Out Report
b) All works that deviate from normal construction related conditions shall be reported and actions initiated to mitigate against recurrence of the incident.
NA Construction complete. No major issues identified in ECO Close Out Report
4) Vibration a) Vibration monitoring shall be in compliance with regulatory requirements (BS 7385-2 (ISO 4866) Evaluation and measurement for vibration in buildings – Part 2: guide to damage levels from ground-borne vibration).
NA Construction complete. No major issues identified in ECO Close Out Report
![Page 41: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/41.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 41 Reg. No: 2007/023691/07
PSEM17 Rehabilitation Plan
Outcomes Reinstate impacted areas to an extent that agricultural; commercial, recreational and environmental protection are assured.
Responsibilities Contractor to draft Method Statement and implement; WRECO to approve and supervise; and Independent Auditor to audit.
Timeframes Method statement compiled and approved prior to commencement of activity. Implementation and compliance to be undertaken continuously.
Performance Indicator Target
Co
mp
lian
ce
Par
tial
ly
Co
mp
lian
t
No
n-c
om
plia
nt
No
t A
pp
licab
le /
N
ot
Au
dit
ed
Comments Recommendations Timeframe
(If applicable)
1) Restoration of soil profile at disturbed areas.
a) Where restoration of indigenous vegetation is to take place, topsoil and surface management needs shall be in accordance with a restoration plan as agreed with the Saldanha Bay Municipality’s Biodiversity Management Branch
2 All disturbed areas have had their profiles returned to previous state
2) Rehabilitation of steep slopes.
a) Stabilisation of steep slopes shall be a priority, with engineered solutions being investigated to ensure slope stabilisation.
NA No steep slopes in the project area
3) Removal of alien invasive vegetation species.
a) Proof of scheduled removal of alien invasive species re-establishing on cleared areas, stockpiles and throughout rehabilitation shall be undertaken
NA Disturbed area have be rehabilitated prior to ECO compiling close out report
4) Site specific rehabilitation requirements.
a) Proof of discussions with landowners about specific rehabilitation requirements. All vegetative matter removed during the search and rescue operation shall be replanted in the area that they were rescued from or in an area determined in consultation with the Saldanha Bay Municipality Biodiversity Management Branch.
2 Disturbed area have be rehabilitated prior to ECO compiling close out report
5) Reinstatement of watercourse soils.
a) The final placement of layers of soil on the watercourse bed shall match the pre-disturbance profile.
NA No water courses disturbed
b) Replaced soil shall be compacted and at the same level as adjacent soil. NA No water courses disturbed c) Water resistant layers must be determined before disturbance shall be
reinstated. NA No water courses disturbed
6) Appropriate re vegetation with correct seed mix.
a) The seed mix for use in rehabilitation shall be an approved mix of indigenous species common to the area. The seed mix shall contain pioneer, sub-climax and climax species. Contractor shall inform the WRECO to deviations from this seed mix prior to the purchase of seed. The Saldanha Bay Municipality Land Use Planning and Development Control shall be consulted with regard to seed mixes and restoration methodologies where indigenous vegetation is to be re-established.
2 Regrowth of disturbed areas was observed.
7) Timing of rehabilitation
actions. a) Seeding operations shall coincide with rainfall events or as part of a
managed watering programme. 2 Rehabilitation coincided on completion of construction
8) Vegetated cover of rehabilitated areas shall
correlate with the cover of the surrounding natural vegetation.
The below targets only applicable where grass cover is prescribed: 2 Regrowth of disturbed areas was observed. a) A 50% grass cover shall be achieved within 1 month of the onset of the
next growing season following hydro seeding and 80% cover within 2 months thereafter. Minimum of 60% mature vegetation cover being achieved during the first growth season. Minimum of 80% mature vegetation cover achieved at the end of the maintenance period. Canopy cover shall be used to determine ground cover percentage.
NA
b) Grass shall set seed over a minimum of two seasons. NA
![Page 42: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/42.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 42 Reg. No: 2007/023691/07
PSEM18 Social Aspect
Outcomes Preserve good relations with neighbouring communities to an extent that maximum social benefits, and minimum negative impacts are assured.
Responsibilities Contractor to draft Method Statement and implement; WRECO to approve and supervise; and Independent Auditor to audit.
Timeframes Method statement compiled and approved prior to commencement of activity. Implementation and compliance to be undertaken continuously.
Performance Indicator Target
Co
mp
lian
ce
Par
tial
ly
Co
mp
lian
t
No
n-c
om
plia
nt
No
t A
pp
licab
le /
N
ot
Au
dit
ed
Comments Recommendations Timeframe
(If applicable)
1) Communication with local community and stakeholders.
a) Communications register shall be kept on site. NA Construction complete. No major issues identified in ECO Close Out Report
b) No reports of grievances not being dealt with promptly. NA Construction complete. No major issues identified in ECO Close Out Report
c) Minutes of meetings held with local community members and other stakeholders.
NA Construction complete. No major issues identified in ECO Close Out Report
2) Representative workforce/equitable
procurement.
a) Employ a “local first” employment policy. NA Construction complete. No major issues identified in ECO Close Out Report
b) Procurement policy targets provided by the WRECO shall be met. NA Construction complete. No major issues identified in ECO Close Out Report
3) Safety of the work environment.
a) Personal Protective Equipment (PPE) is available and worn by staff and visitors.
NA Construction complete. No major issues identified in ECO Close Out Report
4) Exit Strategy.
a) Proof of training for skills required in the greater area that can be used after construction related activities have ended.
NA Construction complete. No major issues identified in ECO Close Out Report
b) Report detailing intentions for materials (for example wood and other building material) or structures no longer required that can be donated to the local community, with the approval of the WRECO.
NA Construction complete. No major issues identified in ECO Close Out Report
![Page 43: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/43.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 43 Reg. No: 2007/023691/07
PSEM19 Soil Management
Outcomes Preserve soil to an extent that erosion and contamination prevention is achieved; and topsoil volumes for rehabilitation can be assured.
Responsibilities Contractor to draft Method Statement and implement; WRECO to approve and supervise; and Independent Auditor audit.
Timeframes Method statement compiled and approved prior to commencement of activity. Implementation and compliance to be undertaken continuously.
Performance Indicator Target
Co
mp
lian
ce
Par
tial
ly
Co
mp
lian
t
No
n-c
om
plia
nt
No
t A
pp
licab
le /
N
ot
Au
dit
ed
Comments Recommendations Timeframe
(If applicable)
1) Topsoil and subsoil handling and management.
a) Soil horizons (stockpile separately) NA Construction complete. No major issues identified in ECO Close Out Report
b) Stockpiles shall be no higher than 2 m and kept weed free. NA Construction complete. No major issues identified in ECO Close Out Report
c) Prevent erosion of soil. NA Construction complete. No major issues identified in ECO Close Out Report
2) Prevention of contamination. a) Stockpiles free of contamination by oils/fuels and other harmful
substances. NA
Construction complete. No major issues identified in ECO Close Out Report
3) Reinstatement of land use practices.
a) Reinstate land use to former land use practise. NA No changes to the land use prior to construction
4) Placement of stockpiles within specifically demarcated
areas.
a) No stockpiles within the 1:20 flood line or within 50 meters of delineated wetlands.
NA Construction complete. No major issues identified in ECO Close Out Report
b) No stockpile outside of areas indicated in the construction diagrams. NA Construction complete. No major issues identified in ECO Close Out Report
5) Spoil disposal. a) No spoil disposed of anywhere other than designated spoil areas or at a
registered landfill. Proof of disposal is to be kept on file. NA
Construction complete. No major issues identified in ECO Close Out Report
6) Construction programme a) In the event construction occurs during the rainfall season, measures
shall be implemented to minimise disruption of the soil profiles. These shall be removed and impacted areas re-vegetated.
NA Construction complete. No major issues identified in ECO Close Out Report
![Page 44: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/44.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 44 Reg. No: 2007/023691/07
PSEM 20 Sustainable Management
Outcomes Preserve critical resources to an extent that the optimisation of energy-use; protection and conservation of water can be assured.
Responsibilities Contractor to draft Method Statement and implement; WRECO to approve and supervise; and Independent Auditor to audit.
Timeframes Method statement compiled and approved prior to commencement of activity. Implementation and compliance to be undertaken continuously.
Performance Indicator Target
Co
mp
lian
ce
Par
tial
ly
Co
mp
lian
t
No
n-c
om
plia
nt
No
t A
pp
licab
le /
N
ot
Au
dit
ed
Comments Recommendations Timeframe
(If applicable)
1) Energy efficient construction site office building design a) The Contractor shall ensure site offices and associated buildings comply
with Construction Regulations 10400XA.
NA Construction complete. No site office in place
2) Electricity conservation NA Construction complete. No site office in place
3) Water conservation a) The Contractor shall ensure all facilities comply with Construction
Regulations 10400XB. NA Construction complete.
4) Dust suppression a) The Contractor shall implement dust suppression measures using non
potable water. NA Construction complete.
![Page 45: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/45.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 45 Reg. No: 2007/023691/07
PSEM21 Traffic Management
Outcomes Preserve road traffic levels to an extent that public health; safety and environmental protection are assured.
Responsibilities Contractor to draft Method Statement and implement; WRECO to approve and supervise; and Independent Auditor to audit.
Timeframes Method statement compiled and approved prior to commencement of activity. Implementation and compliance to be undertaken continuously.
Performance Indicator Target
Co
mp
lian
ce
Par
tial
ly
Co
mp
lian
t
No
n-c
om
plia
nt
No
t A
pp
licab
le /
N
ot
Au
dit
ed
Comments Recommendations Timeframe
(If applicable)
1) Traffic management.
a) No accidents or incidents. NA Construction complete. No issues identified in ECO Close Out Report
b) No complaints from the public. NA Construction complete. No issues identified in ECO Close Out Report
2) Landowners have access to properties.
a) The Saldanha Bay Municipality to supply all landowners with access to their properties via agreed temporary servitudes, where applicable.
2 Landowner has access on site.
3) Road traffic safety.
a) Road condition shall be retained in an acceptable condition on all routes.
2 Roads deemed in good working order
b) Appropriate signage provided, where applicable. 2 Signage in place
4) Prevention of environmental degradation.
a) No new roads constructed outside of the development footprint. 2 Majority of internal access routes utilized existing farm roads. Any other roads where within the Development footprint.
b) No new roads constructed without the approval of the WRECO within the development footprint.
2 Majority of internal access routes utilized existing farm roads. Any other roads where within the Development footprint.
c) No evidence of disturbance by vehicles outside of the development footprint.
NA Construction complete. No major issues identified in ECO Close Out Report
d) No environmental degradation due to storm-water run-off from access and temporary roads. Runoff from roads must be managed to avoid erosion and pollution problems. Where necessary, silt traps should be installed to minimise silt from entering the storm water or sewerage systems.
2 No evidence of environmental degradation
e) Dust entrainment shall comply with prescribed dust regulations. NA Construction complete. No major issues identified in ECO Close Out Report
f) The width of the access and temporary servitude roads shall be kept to a minimum.
NA Construction complete. No major issues identified in ECO Close Out Report
![Page 46: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/46.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 46 Reg. No: 2007/023691/07
PSEM22 Training Programme
Outcomes Foster skills transfer, environmental awareness, health and safety awareness and materials and equipment skills.
Responsibilities Contractor to draft Method Statement and implement; WRECO to approve and supervise; and Independent Auditor to audit.
Timeframes Method statement compiled and approved prior to commencement of activity. Implementation and compliance to be undertaken continuously.
Performance Indicator Target
Co
mp
lian
ce
Par
tial
ly
Co
mp
lian
t
No
n-c
om
plia
nt
No
t A
pp
licab
le /
N
ot
Au
dit
ed
Comments Recommendations Timeframe
(If applicable)
1) Provision of effective training.
a) All employees shall receive general construction related work skills training required to enable them to work safely and effectively, including:
NA Construction complete. No contractor on site
· Basic Environmental Awareness Training.
· Spill and emergency management.
· Health and safety.
· Emergency drills.
· Fire-fighting.
· Disaster management.
· Heritage resource and grave identification.
2) Training.
a) All staff shall:
NA Construction complete. No contractor on site
· be inducted prior to commencing work;
· receive regular task based / skills training;
![Page 47: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/47.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 47 Reg. No: 2007/023691/07
PSEM23 Waste Management
Outcomes Embrace waste hierarchy principles to an extent that waste generation is reduced; reuse and recycling is promoted; all waste streams receive responsible treatment; and safe disposal is assured.
Responsibilities Contractor to draft Method Statement and implement; WRECO to approve and supervise; and Independent Auditor to audit.
Timeframes Method statement compiled and approved prior to commencement of activity. Implementation and compliance to be undertaken continuously.
Performance Indicator Target
Co
mp
lian
ce
Par
tial
ly
Co
mp
lian
t
No
n-c
om
plia
nt
No
t A
pp
licab
le /
N
ot
Au
dit
ed
Comments Recommendations Timeframe
(If applicable)
1) Proper waste disposal.
a) Proof of waste generated, reused, recycled and disposed of, including disposal certificates, shall be kept on site.
NA Construction complete. No contractor on site
b) No contamination of soil, air and water due to inappropriate waste management.
NA Construction complete. No contractor on site
c) Disposal of hazardous waste shall be conducted by a licensed contractor / professional service provider.
NA Construction complete. No contractor on site
d) Store and handle all hazardous materials and waste in accordance to their respective material safety data sheets.
NA Construction complete. No contractor on site
e) Waste to be disposed of at registered landfill site. NA Construction complete. No contractor on site
f) No build-up / accumulation of waste permitted. NA Construction complete. No contractor on site
g) The waste manifest shall be kept on record for auditing purposes. NA Construction complete. No contractor on site
2) Waste reduction.
a) Reduce disposal of recyclable or reusable materials to landfill sites by 50%. Such recyclable and reusable material shall include:
NA Construction complete. No contractor on site
· steel; NA Construction complete. No contractor on site
· aluminium; NA Construction complete. No contractor on site
· paper; NA Construction complete. No contractor on site
· plastic; and NA Construction complete. No contractor on site
· oil. NA Construction complete. No contractor on site
b) An approved recycling company shall be appointed to manage the respective collection and recycling and or re use of waste materials.
NA Construction complete. No contractor on site
3) Environmental contamination.
a) All waste streams stored in appropriately marked containers. NA Construction complete. No contractor on site b) Containers of hazardous waste and waste oils shall be stored in a bunded, weatherproof area.
NA Construction complete. No contractor on site
c) No evidence of contamination by waste. NA Construction complete. No contractor on site d) All spills to be reported and included within reports to be submitted to the WRECO.
NA Construction complete. No contractor on site
4) Good housekeeping
a) Weather and scavenger proof bins provided at all points where waste is to be generated.
NA Construction complete. No contractor on site
b) No evidence of litter. NA Construction complete. No contractor on site c) Chemical ablution facilities at a ratio of 1:15 shall be placed within 50 m of all work areas.
NA Construction complete. No contractor on site
d) Chemical ablution facilities not within 32 m of a watercourse. NA Construction complete. No contractor on site
e) Chemical ablution facilities kept in clean user friendly state. NA Construction complete. No contractor on site
f) Chemical ablution facilities shall be secured. NA Construction complete. No contractor on site
![Page 48: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/48.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 48 Reg. No: 2007/023691/07
PSEM224 Water Management (Numbering error noted, should read PSEM24)
Outcomes Preserve water quality levels and quantity used / discharged to an extent that the integrity of affected water resources is assured.
Responsibilities Contractor to draft Method Statement and implement; WRECO to approve and supervise; and Independent Auditor to audit.
Timeframes Method statement compiled and approved prior to commencement of activity. Implementation and compliance to be undertaken continuously.
Performance Indicator Target
Co
mp
lian
ce
Par
tial
ly
Co
mp
lian
t
No
n-c
om
plia
nt
No
t A
pp
licab
le /
N
ot
Au
dit
ed
Comments Recommendations Timeframe
(If applicable)
1) Watercourse water quality. a) Less than 10% change between values measured 300 m upstream and within 50m downstream of where construction related activities are to occur.
NA No water courses affected
2) Variables and frequencies to be monitored as per regulated
prescribed minimum requirements.
b) Water quality monitoring during period when contaminated water is being released into a watercourse / environment.
NA No water courses affected
3) Contaminated water
monitoring.
a) Values for variables measured shall fall below the specific requirements, before release into the receiving environment.
NA No water courses affected
4) Variables and frequencies to be monitored as per regulated
prescribed minimum requirements.
NA No water courses affected
5) Water management.
a) No storm water flowing through site (unless in a dedicated storm water channel).
NA Construction complete. No contractor on site
b) No storm water flowing onto areas of low / poor stabilisation. NA No water courses affected
c) Control erosion on all construction areas. NA No water courses affected
d) Prevent contamination of water resources. NA No water courses affected
e) Obtain necessary regulatory approvals prior to commencement of works. NA No water courses affected f) Introduction of formalised anti erosion and storm water management works within areas susceptible to erosion. These works shall be properly maintained.
NA No water courses affected
g) Construction related activities within, across, under or immediately adjacent to watercourses, wetlands; and areas subject to flooding, are to be programmed to occur during the dry months.
NA No water courses affected
h) No handling of hazardous substances without necessary personal protective and spill containment equipment and procedures in place.
NA No water courses affected
i) Volumes of both water abstraction and use shall be recorded and reported upon.
NA No water courses affected
j) Clean water and dirty water systems shall be managed independently and kept separate.
NA No water courses affected
k) No water shall be discharged into the municipal storm water system without prior authorisation and compliance with regulated prescribed minimum requirements. Where necessary, silt traps should be installed to minimise silt from entering the storm water or sewerage systems
NA No water courses affected
l) Non potable water shall be used for all construction related activities, unless approved by the WRECO.
NA No water courses affected
![Page 49: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/49.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 49 Reg. No: 2007/023691/07
ANNEXURE C – PHOTOGRAPHS
![Page 50: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/50.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 50 Reg. No: 2007/023691/07
Photo 1: Signage still in place identifying project
Photo 2: It was indicated roads similar to this were used where possible.
![Page 51: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/51.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 51 Reg. No: 2007/023691/07
Photo 3: Interconnecting pipelines utilized existing internal routes where possible
Photo 4: Housing station for one of the boreholes. Security fencing in place.
![Page 52: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/52.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 52 Reg. No: 2007/023691/07
Photo 5: Chlorine building upgraded with fencing. The building was existing from previous 4 boreholes
![Page 53: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/53.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 53 Reg. No: 2007/023691/07
ANNEXURE D – HYDROGEOLOGICAL REPORT
![Page 54: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/54.jpg)
Page 1 of 33
REPORT
Version 1
20 February 2018
Hydrogeological report for Langebaan Road Aquifer: Support document for
Water Use License application.
Prepared for:
Saldanha Bay Municipality
Contact person: David Wright
Prepared by: Dr JM Nel for UWC
![Page 55: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/55.jpg)
Page 2 of 33
Table of Contents 1 INTRODUCTION ...................................................................................................................... 4
1.1 Background ....................................................................................................................... 4
1.2 SCOPE OF WORK............................................................................................................. 4
2 BASELINE INFORMATION .................................................................................................. 4
2.1 PHYSICAL ENVIRONMENT ......................................................................................... 4
2.1.1 Locality ...................................................................................................................... 4
2.1.2 Rainfall ....................................................................................................................... 6
2.1.3 Topography .............................................................................................................. 7
2.2 GEOLOGY ........................................................................................................................... 7
2.2.1 Regional geology .................................................................................................... 7
2.2.2 Local geology ........................................................................................................... 7
2.3 HYDROGEOLOGICAL INFORMATION .................................................................. 10
2.3.1 Regional Groundwater Occurrence ............................................................. 10
2.3.2 Local Aquifers ...................................................................................................... 11
3 EXISTING WELLFIELD: HISTORY.................................................................................. 12
4 Groundwater Levels ........................................................................................................... 13
5 GROUNDWATER RECHARGE .......................................................................................... 15
5.1 Literature Values ......................................................................................................... 15
5.2 Chloride Mass-Balance (CMB) Method ............................................................... 15
6 GROUNDWATER QUALITY .............................................................................................. 16
7 PROPOSED Langebaan Road WELLFIELD EXPANSION ....................................... 22
7.1 Conceptual wellfield design .................................................................................... 23
7.2 Water available from total wellfield .................................................................... 25
8 GROUNDWATER RESOURCE STATUS– Langebaan Road Aquifer Unit .......... 26
8.1 GROUNDWATER REQUIREMENT ......................................................................... 27
8.2 GROUNDWATER SUPPLY ......................................................................................... 27
8.3 Wellfield management .............................................................................................. 27
8.4 Groundwater monitoring and management plan ........................................... 28
9 Groundwater Monitoring ................................................................................................. 28
9.1 Water Levels .................................................................................................................. 28
![Page 56: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/56.jpg)
Page 3 of 33
9.1 Water quality ................................................................................................................ 29
9.2 Abstraction volumes .................................................................................................. 29
10 Summary and Recommendations ................................................................................. 32
10.1 Summary .................................................................................................................... 32
11 References .............................................................................................................................. 33
![Page 57: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/57.jpg)
Page 4 of 33
1 INTRODUCTION
1.1 Background
Saldanha Bay Municipality (SBM) appointed the Institute for Water Studies at the University of the
Western Cape to provide specialist hydrogeological input related to the yield of the Langebaan Road
and Elandsfontein Aquifer systems as part of potential emergency water supply, but also as longer term
water supply to Saldanha Bay Municipality.
As part of the emergency water supply measures, the expansion of the Langebaan Road wellfield must
be evaluated to alleviate the water shortage of the SBM. The upgrading of the existing and expansion
of the Langebaan Road wellfield is identified as wellfield 1A (existing boreholes) and 1B (new boreholes)
respectively, with other potential wellfields further away named wellfields 2 and 3. The additional water
available from the Langebaan Road 1B wellfield will be supplied into the WCDM pipeline.
Various hydrogeological studies have been conducted in the past in the Langebaan and Elandsfontein
areas. These include investigations by the Department of Water and Sanitation (DWS), CSIR, local
municipalities and private consultants. These, together with existing geological maps and water
monitoring datasets from DWS were consulted to inform the baseline information for this study.
1.2 SCOPE OF WORK
The following scope of work has been agreed on by the client (SBM) and the Institute for Water Studies:
Compile a geohydrological report for the Langebaan Road wellfield to support the Water Use
License Application by the Saldanha Bay Municipality for groundwater supply of 15 120m3/day
(5.53 x 106 m3/year).
2 BASELINE INFORMATION
2.1 PHYSICAL ENVIRONMENT
2.1.1 Locality
The Langebaan Road Aquifer (LRA) is located between the lower sections of the Berg River and
Saldanha Bay. The Langebaan Road Aquifer falls within the Berg Water Management Area, specifically
in quaternary catchment G10M (Figure 2.1).
The topography of the Berg WMA varies considerably, with consequential impact on the climate of the
region. Rainfall is highest on the mountain ranges where the mean annual precipitation is as high as
3000 mm per annum, whilst the coastal sections receives as little as 300 mm per annum.
The aquifer system is bordered by the Berg River to the north, the Salt River to the east and the
Elandsfontein Aquifer System to the south.
![Page 58: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/58.jpg)
Page 5 of 33
Figure 2.1: Location of Langebaan Road Aquifer Wellfield.
![Page 59: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/59.jpg)
Page 6 of 33
2.1.2 Rainfall
Langebaan is situated in a semi-arid Mediterranean climate, with winter rainfall falling between the
months of May and August (Figure 2.2). The study area generally has higher evaporation than mean
annual rainfall and most of the region has an annual rainfall of less than 280mm (DWAF, 2008) (Figure
2.2).
Figure 2.2: Monthly rainfall at Langebaan Road 185-IR.
Figure 2.3: Annual rainfall at Langebaan Road 185-IR.
![Page 60: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/60.jpg)
Page 7 of 33
2.1.3 Topography
The Langebaan Road Aquifer area has an elevation of approximately 60 mamsl, with a relatively flat
surface The landscape in the Langebaan Road area is not greatly varied. It is characterised by sand
covered plains, fixed dunes, surface limestone ridged and some unvegetated dunes. The Vredenburg
headland, the Darling hills and some isolated koppies are all made up of granite (eg. Vlaeberg and
Konstabelkop) or related instrusives, and reach heights of up to 450m. Otherwise the regional
topography is generally flat to slightly undulating and does not reach elevations beyond 120m
(Timmerman, 1985).
2.2 GEOLOGY
2.2.1 Regional geology
The Langebaan area is dominated by unconsolidated to semi-consolidated sediments that overlay the
basement rock of the Malmesbury Group unconformably (Figure 2.4). The Malmesbury Group consists
of shale outcropping to the west of the wellfield area and along the N7 road from Cape Town to
Piketberg. Deeply weathered shales of the Malmesbury Group and granite plutons of the Cape Granite
form part of the basement rocks.
The Berg River flows approximately parallel to and east of the regional contact between Malmesbury
Group and the Cape Granite suit. The Sandveld Group consists of Springfontyn, Velddrif, Langebaan
and Witzand Formations and extends from False Bay to Saldanha.
2.2.2 Local geology
The coarse Elandsfontyn Formation sand and gravel (do not confuse with the Elandsfontein aquifer
unit) were deposited in a number of paleo-channels, which can be correlated with old courses of the
Kulders-, Berg- and Groen Rivers. These deposits were subsequently covered by clays and peat. The
thickness of the Cenozoic sediments varies between 0 and 120m, with the greatest thicknesses
occurring between Langebaan Lagoon and Hopefield (Timmerman, 1985).
The stratigraphic column of the local geology according to Roberts (2006) is shown in Figure 2.5. The
cenozoic stratigraphy is shown in Table 2.1. Within the Langebaan road wellfield region three formations
are present, namely (in order of oldest to youngest):
the Elandsfontyn Formation, (not be confused with the Elandsfontyn Aquifer or the
Elandsfontein Farm)
the Varswater Formation and
the overlying Langebaan Formation.
![Page 61: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/61.jpg)
Page 8 of 33
Figure 2.4: Surficial Geology of the Langebaan Road Aquifer and surrounding area.
![Page 62: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/62.jpg)
Page 9 of 33
Figure 2.5: Lithostratigraphic classification (adapted from Roberts, 2006)
![Page 63: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/63.jpg)
Page 10 of 33
Table 2.1: Stratigraphy of the Cenozoic (65 Ma to present) sediments between
Saldanha and the Berg River (DWAF, 2008).
GROUP FORMATION ORIGIN DESCRIPTION
Bredasdorp
Summary: Clean
sand, calcareous
sands, and calcrete.
Witzand Aeolian Semi consolidated calcareous dune sand
Langebaan
Limestone
Aeolian
Consolidated calcareous dune sand. The
Aeolian deposit accumulated during the last
glacial lowering of sea level when vast tracks
of un-vegetated sand lay exposed on the
emerging sea floor.
Velddrif Marine Beach sand. Associated with the last
interglacial sea level rise with 6-7 m above
present level.
Springfontyn Aeolian Clean quartzitic sands, a decalcified dune
sand. Dominates in the coastal zone.
Sandveld
Summary: Basal
gravel overlain by
clay, overlain by
various sands with
peat /clay layers.
Varswater Various subdivisions are proposed in
literature (for a summary see Rogers, 1980).
Deposits include a coarse basal beach gravel
member, peat layers, clay beds, rounded
fine to medium quartzes sand member and
palatal phosphate rich deposits.
Varswater sediments do not extend further
than 15 km inland of Saldanha Bay
(reaching ~halfway to the Berg River)
(Timmerman, 1985b).
Elandsfontyn Fluvial Coarse fluvial sands and gravels, deposited
in a number of palaeochannels filling
depressions. The deposits were
subsequently covered by clays and peat.
2.3 HYDROGEOLOGICAL INFORMATION
2.3.1 Regional Groundwater Occurrence
The Berg WMA does host extensive aquifers. The Klipheuwel and Malmesbury Groups are typically not
known for their high groundwater potential. However, in places – particularly where fracture/fault
systems are well developed – the groundwater potential is very high. In favourable geological settings
borehole yields from these groups can be about 5 ℓ/s and higher whilst the average borehole yield is
lower. The Cape Granites are typically low yielding (~ 1 ℓ/s) and these yields are only obtainable in
highly weathered and faulted zones. Otherwise the granite is very solid and a non-aquifer.
The significant features from the hydrostratigraphy and the palaeotopography that dictate the
groundwater flow regime in the area are (DWAF, 2008):
![Page 64: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/64.jpg)
Page 11 of 33
The lower (semi-) confined aquifer unit occurs in the palaeo-channels and is unlikely to be
connected between the LRAS and the EAS, as a basement elevation of at least 0 mamsl
separates the two palae-channels.
The upper aquifer unit (UAU) is continuous across the area.
The clay unit confining the LAU is absent along the SW coastline and in the vicinity of the Berg
River.
2.3.2 Local Aquifers
The Langebaan Road Wellfield falls within the Berg River hydrogeological unit of the Sandveld Group
Aquifer. The geological depositional environments and controls determine the most significant
groundwater occurrences. Two significant aquifers exist within the area: the Langebaan Road Aquifer
System (LRAS), which is situated in the northern palaeo-channel and the Elandsfontein Aquifer System
(EAS), which is situated in the southern palaeo-channel.
The LRAS is formed by the thick sand and gravel layers of the Elandsfontyn Formation. The confining
layer is formed by the Elandsfontyn clay and peat. A shallow, unconfined aquifer of lesser extent exists
in the top Bredasdorp calcerous layers.
The clay layer that separates the Elandsfontyn Formation and the Varswater Formation creates (semi)
confined conditions in the basal gravels (GEOSS, 2010). The confined Lower Aquifer Unit (LAU) is the
most significant aquifer in the Langebaan Road area and is generally restricted to paleochannels, which
defines the LRAS and the EAS.
For the Langebaan Road area the geology and hydrogeology are summarized in Table 2.2 (Weaver,
1998a):
Table 2.2: Summary of the geology and hydrogeology of the Langebaan Road
Wellfield.
Lithostratigraphic Unit Aquifer Type
Approximate thickness (m)
Transmissivity (m2/day)
Formation Member
Bredasdorp Sand, calcrete Unconfined 10 to 20 <100
Elandsfontyn 1) clay 2) sand & gravel
1) Aquitard 2) Confined
20 to 30 40 to 60
<1 +-1000
Granite Bedrock
![Page 65: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/65.jpg)
Page 12 of 33
3 EXISTING WELLFIELD: HISTORY
Extensive drilling and exploration work was done by DWAF from the mid 1980’s for a period of 10 years.
Documented groundwater assessment studies in the Saldanha Bay/Langebaan Road Area already
started in 1974. The potential of the groundwater resources in the primary aquifers was not only
investigated, but also confirmed as very favourable. The following is a list of the main groundwater
exploration studies:
Timmerman, L.R.A. 1985. Possibilities for the development of groundwater from the cenozoic
sediments in the Lower Berg River region. Geotechnical Report GH3374, Directorate:
Geohydrology, Department of Water Affairs, Cape Town.
Timmerman, L.R.A. 1985a. Preliminary report on the geohydrology of the Grootwater Primary
Aquifer Unit between Yzerfontein and the Modder River, Geotechnical Report GH3372,
Directorate: Geohydrology, Department of Water Affairs, Cape Town.
Timmerman, L.R.A. 1985b. Preliminary report on the geohydrology of the Langebaan Road and
Elandsfontyn Aquifer Units in the Lower Berg River Region, Geotechnical Report GH3373,
Directorate: Geohydrology, Department of Water Affairs, Cape Town.
Weaver JW and Fraser L (1998a). Langebaan Road Aquifer Unit – Drilling and Testing of New
Wellfield. Technical Report ENV/S-C98042. Division of Water, Environment and Forestry, CSIR,
Stellenbosch, South Africa.
The existing wellfield at the Langebaan Road Aquifer was officially established for the DWS in 1998.
Recommendations by Weaver for the sustainable abstraction (based on pumping test interpretation)
from the wellfield are summarised in Table 3.1.
Table 3.1: Recommendations for borehole abstraction – LRA.
Borehole
Number
Pumping rate
(l/s)
Pumping rate
(m3/day)
No of hours pumping per
day x days of year
G45632* 25 2160 24 x 365
G45633** 25 2160 24 x 365
G45634* 25 2160 24 x 365
G45636*** 20 1728 24 x 365
*Equipped, pumped
** Equipped, on standby
*** Not equipped, standby
Following these recommendations, the Langebaan Road wellfield became operational in 1999,
providing an additional 4 000m3/day to the water supply for Saldanha Local Municipality. In 2008
and 2009 artificial recharge was tested at the wellfield, showing that it could be a viable option for
the long term sustainable management of the groundwater resources. Monthly abstraction figures
![Page 66: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/66.jpg)
Page 13 of 33
(Figure 3.1) were available for the period September 2005 to September 2015, with the periods of
no pumping can clearly be extinguished.
Figure 3.1: Total Monthly abstraction for LRA wellfield.
4 GROUNDWATER LEVELS
The water level trends (as recorded in DWS monitoring programme) for the Langebaan Road Wellfield
area are illustrated in Figure 4.1. Water levels response to the local abstraction show drops in water
level of about 10m for the different monitoring holes. Good recovery of the water levels are observed
during pump shutdowns and maintenance events. Currently only monthly hand readings is taking place
at the wellfield due to failure of the data loggers.
Additional available drawdown of 20m to a depth of 35m below casing is available at the wellfield before
the confining conditions of the wellfield are influenced.
![Page 67: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/67.jpg)
Page 14 of 33
Figure 4.1: Water level trends for DWS monitoring boreholes in LRA wellfield area.
![Page 68: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/68.jpg)
Page 15 of 33
5 GROUNDWATER RECHARGE
The effective groundwater recharge from rainfall is the portion of rainfall that reaches the groundwater.
The remainder of the rainfall comprises surface water runoff, evapotranspiration and soil moisture. The
effective rainfall-recharge is dependent on the catchment geology, soils, surface run-off and stream
morphology but most importantly for the study area, the effective storage.
As the size of the sub-catchment falls within the G10M quaternary drainage area, the rainfall is seen
to be equal across the site, i.e. 14mm/annum.
Two general approaches were utilized to estimate the groundwater recharge in the study area:
• Literature values; and
• Calculation using chloride as an environmental tracer – so called chloride mass-balance
method (CMB method).
5.1 Literature Values
Based on the literature review, a conservative average recharge of 8.2% was taken for the study
area. In Table 5.1 is a summary of the recharge values obtained from the literature review.
Table 5.1: Recharge calculation values from literature for Langebaan Road Aquifer
area.
SOURCE Mean Annual
Precipitation (MAP)
Recharge
(% of MAP)
Recharge
(mm/year)
GRA II, 2005* 300 5.4 16.2
Timmerman 280 15 42
Weaver,1997 305 8 24.4 *For Quatenary catchment G10M
5.2 Chloride Mass-Balance (CMB) Method
Environmental tracers such as chloride (Cl) are produced naturally in the Earth’s atmosphere and are
used to estimate recharge rates. Input of chloride occurs in the soil both in rainfall and as dry fallout.
Most plant species do not take up significant quantities of the chloride from soil water, thus chloride is
concentrated by evapotranspiration in the root zone. In the simplest case of piston flow of water in the
unsaturated zone, the chloride concentration in soil water should increase through root zone to a
constant value.
Under steady state conditions flux of chloride at the surface is equal to the flux of chloride beneath the
root zone, thus:
P*Cp = R*Cs,
where Cp = chloride concentration in precipitation Cs = chloride concentration in groundwater
R = mean annual recharge (mm) P = mean annual precipitation (mm).
![Page 69: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/69.jpg)
Page 16 of 33
The mean annual precipitation (MAP) is 300mm for the study area, with chloride concentration in the
rain water ranging from 5 to 10 mg/l and chloride concentration in groundwater ranging between 114
and 209mg/l (DWS monitoring). The output rainfall recharge obtained by substituting these values then
ranges between 13 and 14mm per year.
6 GROUNDWATER QUALITY
Based on field data from various studies in the area over the last 20 years, the water quality of the
aquifer is good (less than 100 mS/m). Generally the water quality of the LAU is better than that of the
UAU but from the field EC measurements it suggests that all the groundwater is of a good quality.
The upper and lower aquifer units of the study area have different water qualities. Groundwater quality
is good in the Lower Aquifer Unit (LAU) with ECs <100 mS/m. Groundwater from the upper aquifer is
rich in Na/Cl, and has a higher EC than the lower aquifer.
A summary of the groundwater quality analyses for the DWS monitoring stations at the Langebaan
Road Aquifer is provided in Table 6.1. For each of the stations, the first documented analysis as well as
the most current analysis are listed in order to detect prominent changes, in the overall groundwater
quality at the wellfield.
Time series EC is plotted to evaluate if any significant changes in total salts in the system are evident
(Figure 6.1). Most of the boreholes do not show any significant change in Electrical Conductivity, except
for borehole G46032 showing an increase in salts between 2006 and 2010. The increase in salinity does
not seem to be related to the pumping at the wellfield, but rather the impact of nearby waste water
treatment works.
![Page 70: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/70.jpg)
Page 17 of 33
Table 6.1: Summary of chemistry analysis results, DWS NGA database for Langebaan Road Aquifer.
Parameter
(mg/l)
SANS
241-1:
2015
G46032 G45632 G46105 G46029 G46028 G46059
1999 2016 2003 2012 2002 2008 1999 2016 1999 2016 2001 2016
pH 5-9.7 7.88 8.5 7.995 8.199 8.102 9.91 8.47 8.3 8.39 8.3 8.286 8.4
Electrical
Conductivity
(mS/m)
<170 71.7 84.5 60.4 62 69.6 58.3 71 71.1 116 80.8 96.5 68.3
Total Alkalinity
as CaCO3 NS
132.5 151.70 109.12 117.96 138.40 64.01 162.2 169 234.3 167.5 159.77 119.8
Chloride as Cl <300 141.1 198.6 115.08 118.73 114.83 144.64 116 144 206.8 136.7 209.14 139
Sulphate as SO4 <500 18.6 23.6 11.60 10.77 9.39 9.82 <4 <4 39.8 14.9 10.071 16.4
Magnesium (Mg) NS 7.1 9.6 5.74 5.96 5.61 2.12 9.5 11 16.2 10.5 4.02 7.1
Fluoride as F <1.5 0.44 0.49 0.34 0.39 0.25 0.70 0.91 0.95 0.35 0.87 3.42 0.85
Nitrate as NO3 <11 <0.04 <0.1 <0.11 <0.05 0.04 0.04 <0.04 <0.1 1.23 0.16 <0.04 0.199
Sodium (Na) ≤200 75.1 89.8 65.55 65.43 71.56 109.94 81.2 79.3 113.7 81.2 165.21 78.8
Aluminium (Al) ≤0.3 <0.035
<0.008
0.091 <0.006
<0.052 0.013 <0.035 0.015 <0.035 <0.008 0.07 0.008
Iron (Fe) ≤2 0.016
0.005
0.014
0.037
0.003 0.009 0.003 0.005 0.003 0.005 0.382 0.005
Manganese (Mn) ≤0.4 0.006
0.002
0.006
<0.003
0.002 0.002
0.002
<0.002
0.002
<0.002
<0.003 <0.002
Copper (Cu) ≤2 0.01 0.05 0.022 0.016 <0.011
0.003 0.01 <0.005
0.01 0.05 <0.019 <0.005
Zinc (Zn) ≤5 <0.004
<0.005
<0.007
0.032 <0.007
<0.004 <0.004
<0.005
<0.004
<0.005
<0.005
<0.005
![Page 71: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/71.jpg)
Page 18 of 33
Figure 6.1: Electrical conductivity (EC) trends at the LRA wellfield.
Borehole G46032 is situated in the upper aquifer near the Langebaan Road Airfield wastewater treatment,
and this increase of salt concentrations could be as a result of the impact of the sewage water irrigation at
the treatment works. The nitrate concentrations typically associated with sewage water follows a similar
trend to the Electrical Conductivity (Figure 6.2).
Figure 6.2: Electrical Conductivity and Nitrate for G46032 in Langebaan Road upper
aquifer.
![Page 72: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/72.jpg)
Page 19 of 33
Consistent monitoring at regular intervals at all of these boreholes will ensure that changing trends are
picked up in advance and adaptive measures be put in place if necessary. Land use activities like irrigation
and wastewater treatment can influence the groundwater quality of the upper aquifer, but should not
influence the lower aquifer. Early warning water quality monitoring in the protection zone of the wellfield
should be conducted to ensure the water quality for drinking water purposes. Studies identifying recharge
areas for the lower aquifer will be important to improve management and prevent contamination reaching
the water supply boreholes.
A Piper diagram (Figure 6.3) was constructed with the same DWS water quality monitoring data. The
Langebaan Road Wellfield has a sodium chloride type of water and this is expected because this area
receives coastal rainfall. The high bicarbonate and calcium content in the water is most likely from the
calcarenite and the lime rich shells, which are present within the geology of this area. Calcarenite is a
type of limestone that is composed of transported sand-sized, carbonate grains, which have accumulated
as coastal sand dunes (Khalifa, Mohamed et al 2009). When this calcium carbonate rich geology comes
in contact with water it dissociates and bicarbonate is formed.
In general the water chemistry in the past is similar to that of the present but this is not evident in
boreholes G46059 and G46105. In 2001, borehole G46059 was more saline (with approximately 90%
sodium and 70% chloride in 2001) than in 2016. In 2008 borehole G46105 was more saline (with
approximately 90% sodium and 80% chloride in 2008) than in 2002.
Spatial distribution of the EC values from the DWS water quality database are plotted in Figure 6.4. The
lower aquifer shows low EC values of between 57 and 78 mS/m. The upper aquifer contains slightly more
salts around the Langebaan Road air force base and ranges between 61 and 614 mS/m. Various samples
from unknown depths are available and ranges from 60 to 1021 mS/m.
![Page 73: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/73.jpg)
Page 20 of 33
Figure 6.3: Piper diagram of LRA borehole: initial vs current.
![Page 74: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/74.jpg)
Page 21 of 33
Figure 6.4: Electrical conductivity for upper and lower aquifer of samples available from DWS database.
![Page 75: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/75.jpg)
Page 22 of 33
7 PROPOSED LANGEBAAN ROAD WELLFIELD EXPANSION
It is realistic to expect that additional groundwater from the Langebaan Road wellfield can
be abstracted, based on the historical sustainable yield assessments and available drawdown
in the aquifer.
Timmerman (1985) estimated a short-term abstraction rate at 53 400 m3/day (19.5 M m3/a)
from the Langebaan Road aquifer based on a 15% recharge using the average rainfall data
that was available in 1985 (1985b). As this value was based on average rainfall measurements
available at the time of the study and a slight over estimation of recharge rates, this available
volume is very likely to be non-sustainable as a result of climate change and an improved
knowledge of the system. This abstraction rate (19.5 M m3/a) is therefore not recommended.
Using the capture principle, Seyler (2016) proposed that between 3.5 to 5.5 M m3/a may be
available for abstraction from the wellfield without significant impact on the aquifer or the
environment, compared to the production abstraction rate of 1.1 M m3/a. This translates to
9 590 - 15 070 m3/day (15Ml/day), see Figure 7.3.
A summary for previous assessments of the potential yield of the Langebaan Road Aquifer, is
provided in Table 7.1:
Table 7.1: Potential yield of the Langebaan Road Aquifer
Report Potential Yield
(Mm3/year)
Timmerman, 1985 30 (longterm)
19 (short term)
Weaver, 1998 7.8
Seyler, 2016 3.5 – 5.5
Some limitations to the pump and pipe infrastructure currently in place at the wellfield can
be overcome through the increase of both the number of boreholes and the pipe sizes
supplying the West Coast District municipality pipeline.
Additional abstraction boreholes are recommended to spread the drawdown over a number
of abstraction points to limit localised impacts of the higher abstraction rate, Figure 7.4.
![Page 76: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/76.jpg)
Page 23 of 33
7.1 Conceptual wellfield design
The current Langebaan Road 1A wellfield production boreholes are spread out and about
300m apart. All of these boreholes must be equipped to address the emergency water supply
needs.
Three (3) additional production boreholes, at 600m apart, must be installed in a northerly
direction (Figure 7.2). Figure 7.1 shows a cross section with the relative placement of the
boreholes from each other. The clay layer separating the upper and lower aquifer is expected
to become thinner, while the bedrock topography is expected to become deeper across the
section.
Figure 7.1: Conceptual cross-section at Langebaan Road Aquifer for existing
and proposed expansion of wellfield.
![Page 77: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/77.jpg)
Page 24 of 33
Figure 7.2: Position of cross-section line across LRA.
![Page 78: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/78.jpg)
Page 25 of 33
7.2 Water available from total wellfield
The new expanded and upgraded combined wellfield 1A and 1B will have a maximum
abstraction rate of 175 l/s (15 120 m3/d) based on the limit of the pump and pipe
infrastructure.
Realistically this maximum supply is only needed until the winter rainfall starts and some
surface water becomes available. A reduction in the abstraction rate to 100 l/s (8 640 m3/d)
is expected during winter months.
For the water use license, it is recommended that the total volume of 175 l/s (15 120 m3/d)
is allocated to the Saldanha Bay Municipality on condition that the water level response to
the abstraction do not reach the bottom of the clay layer. The development of Langebaan
Road wellfields 2 and 3, as well as the Hopefield B wellfield should be considered as part of
the long term water supply and the spatial distribution of abstraction points to limit the local
drawdown.
The immediate need for the current drought situation is an allocation of 3.7 M m3 for 2018
and a maximum of 5.53 M m3 for the following years (Figure 7.4). It is realistic to expect that
less water will be abstracted when surface water becomes more available.
Figure 7.3: Proposed daily abstraction rates or LRA for short term.
![Page 79: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/79.jpg)
Page 26 of 33
Figure 7.4: Cumulative abstraction per year from LRA 1A and 1B.
8 GROUNDWATER RESOURCE STATUS– LANGEBAAN ROAD AQUIFER UNIT
The geological setting is favourable for the occurrence of groundwater. The volume
requested for abstraction is 5.53 x 106 m3/year.
For approximately the last two (2) years, no abstraction has taken place form the existing
wellfield.
Based on the testing completed during previous investigations as well as the monitoring of
the wellfield during the period it was operational, the license application volume is
considered to be within the sustainable supply volume of the aquifer.
The boreholes have been tested originally (Weaver, 1998) to determine the sustainable yield
that can be abstracted from the aquifer system. The yield test indicated that a sustainable
abstraction rate of 7.8 x 106 m3/a could be achieved from the aquifer system.
The groundwater is of good quality, with EC-values below 100 mS/m from production in 1999
until 2016 (latest analysis results).
![Page 80: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/80.jpg)
Page 27 of 33
8.1 GROUNDWATER REQUIREMENT
The SBM requires the groundwater supply of 5.53 Mm3/year from the Langebaan Road 1A and
B wellfields, which will be distributed by the municipality for domestic and industrial users.
8.2 GROUNDWATER SUPPLY
A yield of 5.53 x 106 m3/a can be obtained from the planned expansion of the wellfield. Seven
(7) boreholes will be utilized to abstract the required volume, and the scheduling for the short
term is discussed in Section 6. This will need to be closely monitored to ensure sustainable
supply.
Hence, the sustainable groundwater supply of 5.53 x 106 m3/a is requested in this license
application.
Table 8.1: Recommended groundwater supply from Langebaan Road Aquifer.
Borehole ID
Recommended
abstraction rate
(l/s)
Pump inlet
Pumping
period/Schedule (number
of hours/day x days/year)
G45632 25 35 24 x 365
G45633 25 35 24 x 365
G45634 25 35 24 x 365
G45636 20 50 24 x 365
LRA-1B1 25* 35* 24 x 365
LRA-1B2 25* 35* 24 x 365
LRA-1B3 25* 35* 24 x 365
* Proposed
Once the proposed infrastructure and hydraulic testing for Langebaan Road Wellfield 1B has
been established, a hydrogeological report will be submitted to the DWS, containing borehole
and drilling data, pumping test results, hydrochemical analyses and yield recommendations.
8.3 Wellfield management
The cumulative abstraction from the wellfield needs to be carefully managed as the boreholes
are abstracting from the same resource. A detailed monitoring plan is discussed in the next
section of this report.
![Page 81: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/81.jpg)
Page 28 of 33
8.4 Groundwater monitoring and management plan
In terms of DWAF’s overarching water quality management objectives which are (1) protection
of human health and (2) the protection of the environment, the significance of this aquifer
classification is that if any potential risk exists, measures must be triggered to limit the risk to
the environment and other users.
A detailed groundwater monitoring plan is presented in Section 9 of this report.
9 GROUNDWATER MONITORING
9.1 Water Levels
The current Langebaan Road Wellfield 1A monitoring boreholes provide good information
regarding the wellfield response to abstraction, but limited data regarding the responses
towards the Elandsfontein Aquifer to the east and the main Langebaan Road Aquifer towards
the north. The existing monitoring will provide early warning to wellfield drawdown limitations,
but not regarding sustainable resource use.
The monitoring network therefore will need to be expanded to include additional data. Based
on the interpretation of the aquifer structure and basement topography it is recommended that
at least three (3) additional monitoring boreholes be drilled to provide data for management
of the LRA, update of the numerical model and provide data regarding the interaction between
the different aquifer horizons.
Three sites have been identified, expanding the current monitoring network with two (2) lower
aquifer and one (1) upper aquifer monitoring borehole. These are summarised in Table 9.1 and
their positions are indicated on Figure 9.1.
Table 9.1: Additional recommended monitoring boreholes.
Coordinates (WGS84) Borehole Name
Aquifer Unit Depth Lat Long
-32.973864° 18.205147° LRA1B-1M Lower Aquifer 80
-32.970600° 18.184800° LRA1B-2M Lower Aquifer 80
-32.978600° 18.199100° LRA1B-3M Upper Aquifer 20
Continuous monitoring using electronic data loggers should be implemented and maintained
on the existing LRA 1A as well as the new LRA 1B monitoring boreholes. Daily logging intervals
is recommended.
![Page 82: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/82.jpg)
Page 29 of 33
9.1 Water quality
The additional flow rates can result in unwanted water quality changes due to inflow from
adjacent low yielding formations with different water quality and should be monitored. Some
early waring protection zone monitoring should also be implemented to protect the drinking
water resources from surface activities in the catchment.
Quarterly water quality monitoring on all the production boreholes should be conducted. The
analyses should include Anions, Cations and a trace metal scan. On a bi-annual interval
additional water isotopes 2H and 18O and selected contaminants of emerging concern (Atrazine,
Glyphosate, AMPA) should be included. These additional analyses will form a good baseline
with a view on potential future artificial recharge with surface water and treated wastewater.
9.2 Abstraction volumes
Each of the production wells should be equipped with a flow meter. The total volume abstracted
should be recorded on a monthly interval.
9.3 Monitoring report
A monitoring report with the abstraction volumes, water level response and water quality
changes should be submitted to the Department every year.
The monitoring data should be stored in an acceptable format in a database with sufficient
backup and provided to the Department on an annual basis.
Hard copies of field sheets and laboratory reports must be kept safe so that they can be made
available to the Department or other stakeholders on request.
9.4 Monitoring committee
A monitoring committee should be put in place that includes the surrounding stakeholders,
including the stakeholders from the Elandsfontein aquifer system. The monitoring committee
should meet at least every six (6) months to discuss monitoring results and management of
the wellfield.
The monitoring requirements stipulated in the monitoring protocol must be agreed upon by the
relevant stakeholders that form part of the monitoring committee.
9.5 Numerical model Updates
A regional flow model and a wellfield model be developed and kept up to date with the most
recent monitoring data for wellfield and aquifer management purposes.
Amongst others the flow model should be used to determine the capture zones for the wellfiled
following best practice local and international guidelines to protect the drinking water to the
wellfield.
![Page 83: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/83.jpg)
Page 30 of 33
It is recommended that the numerical flow model be updated against the new monitoring data
on an annual basis. This will provide improved certainty to DWS regarding the sustainable use
of the Langebaan Road aquifer system.
![Page 84: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/84.jpg)
Page 31 of 33
Figure 9.1: Existing and proposed monitoring boreholes at LRA.
![Page 85: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/85.jpg)
Page 32 of 33
10 SUMMARY AND RECOMMENDATIONS
10.1 Summary
The geological setting in the Lower Aquifer of the Langebaan Road Aquifer is favourable for the
occurrence of groundwater. The volume requested for abstraction by the Saldanha Bay Municipality
is 15 120 m3/day or 5.53 x 106 m3/year.
Based on the numerical modelling and aquifer testing completed during previous investigations as
well as the monitoring of the wellfield during the period it was operational, the license application
volume 5.53 x 106 m3/year is considered to be within the sustainable supply volume of the aquifer.
A yield of 5.53 x 106 m3/a can be obtained from the planned expansion of the wellfield. Seven (7)
boreholes will be utilized to abstract the required volume. This will need to be closely monitored to
ensure sustainable supply.
The groundwater in the lower aquifer is of good quality, with EC-values between 57 and 78 mS/m.
Monitoring of both water level drawdown response and water quality changes are required to improve
predictions of the system behaviour under these increased abstraction rates. Water levels should not
be allowed to drop below the clay layer and water quality should be monitored to ensure that drinking
water quality is maintained.
Additional monitoring boreholes will be required to provide data for local management of the aquifer,
update of future numerical models and interaction between the different aquifer horizons. Studies
investigating the recharge areas for the lower aquifer will be important to improve management of
the sustainable yield and to protect the aquifer from contamination.
The development of Langebaan Road wellfields 2 and 3, as well as the Hopefield B wellfield should
be considered as part of the long term water supply and the spatial distribution of abstraction points
to limit the local drawdown.
It is recommended that the numerical model be updated every 12 months. This update can then
calibrate against the stresses induced by the expanded wellfield and provide improved certainty for
any future abstraction requirements.
![Page 86: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/86.jpg)
Page 33 of 33
11 REFERENCES
Department of Water Affairs, 2008. Umvoto Africa in association with Ninham Shand. The Assessment
of Water Availability in the Berg Catchment (WMA19) by means of Water Resource Related Models:
Groundwater Model Report Volume 6, Langebaan Road and Elandsfontein Aquifer System Model. Report
no P WMA 19/000/00/0408.
GEOSS, 2010. Geohydrological Prospecting Scoping Report for a phosphate prospecting permit
application, Elandsfontein No 349, Malmesbury Magisterial District, West Coast. GEOSS project no
2010/07-623.
Roberts, D.L., 2006. Lithostratigraphy of the Varswater Formation (Sandveld Group). South Africa
Committee for Stratigraphic Lithostratigraphic Series.
Timmerman, L.R.A. 1985a. Preliminary report on the geohydrology of the Grootwater Primary Aquifer
Unit between Yzerfontein and the Modder River, Geotechnical Report GH3372, Directorate:
Geohydrology, Department of Water Affairs, Cape Town.
Timmerman, L.R.A. 1985b. Preliminary report on the geohydrology of the Langebaan Road and
Elandsfontyn Aquifer Units in the Lower Berg River Region, Geotechnical Report GH3373, Directorate:
Geohydrology, Department of Water Affairs, Cape Town.
Timmerman, L.R.A. 1985c. Possibilities for the development of groundwater from the Cenozoic
sediments in the Lower Berg River Region, Geotechnical Report GH3374, Directorate: Geohydrology,
Department of Water Affairs, Cape Town.
Seyler, H., Witthüser, K., & Holland, M. 2016. The Capture Principle approach to Sustainable
Groundwater Use Incorporating Sustainability Indictors and Decision Framework for Sustainable
Groundwater Use, Report to the WATER RESEARCH COMMISSION (Project nr. K5/2311/1), Draft Final
Report September 2016.
Weaver JW and Fraser L. 1998a. Langebaan Road Aquifer Unit – Drilling and Testing of New Wellfield.
Technical Report ENV/S-C98042. Division of Water, Environment and Forestry, CSIR, Stellenbosch,
South Africa.
![Page 87: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/87.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 54 Reg. No: 2007/023691/07
ANNEXURE E – WATER USE LICENCE
![Page 88: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/88.jpg)
![Page 89: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/89.jpg)
![Page 90: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/90.jpg)
![Page 91: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/91.jpg)
![Page 92: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/92.jpg)
![Page 93: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/93.jpg)
![Page 94: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/94.jpg)
![Page 95: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/95.jpg)
![Page 96: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/96.jpg)
![Page 97: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/97.jpg)
![Page 98: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/98.jpg)
![Page 99: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/99.jpg)
![Page 100: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/100.jpg)
![Page 101: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/101.jpg)
![Page 102: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/102.jpg)
![Page 103: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/103.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 55 Reg. No: 2007/023691/07
ANNEXURE F – ECO REPORTS
![Page 104: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/104.jpg)
THE LANGEBAANWEG AQUIFER GROUNDWATER
INFRASTRUCTURE PROJECT, HOPEFIELD, WESTERN
CAPE.
DEA&DP Ref: 16/6/F4/17/3140/17
FORMAL ECO AUDIT REPORT
Prepared for:
Saldanha Bay Municipality
Private Bag X12
Vredenburg
7380
Prepared by:
Guillaume Nel Environmental Consultants
P.O. Box 2632
Paarl
7620
Tel: 021 870 1874
Fax: 021 870 1873
Cell: 072 157 1321
E-Mail: [email protected]
4 June 2018
![Page 105: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/105.jpg)
Page | i
ABBREVIATIONS
DEA .............................................................................. Department of Environmental Affairs
DEA&DP ............................ Department of Environmental Affairs and Development Planning
DEAT ....................................................... Department of Environmental Affairs and Tourism
DWS ...................................................................Department of Water Affairs and Sanitation
EA .............................................................................................. Environmental Authorization
EAP ......................................................................... Environmental Assessment Practitioner
ECO ........................................................................................ Environmental Control Officer
EIA .................................................................................. Environmental Impact Assessment
EMP ....................................................................... Environmental Management Programme
DEO .................................................................................. Designated Environmental Officer
GNEC .................... .................................................Guillaume Nel Environmental Consulting
I&AP ..................................................................................... Interested and Affected Parties
RE…..………………………….………….……………………… ................ …Resident Engineer
INTRODUCTION
The INFORMAL report is distributed internally to the main Contractor and appointed
Consulting Engineers on a fortnightly basis in order to ensure continuous improvement with
regards to environmental related matters. The aim is furthermore, to increase the contractor’s
compliance rating in terms of the approved project EMP. The aim of the informal reports are
therefore to assist in identifying environmental related issues and/or concerns in order to take
corrective action on a weekly basis, as environmental degradation is more likely to occur
should Contractors only receive ECO reports on a monthly basis.
This FORMAL report incorporates the findings of the informal reports and furthermore may
include corrective measures/actions which were taken by the contractor and/or Consulting
Engineers. The formal report, which is submitted to the competent authority as well as other
relevant role players and stake holders are prepared on a monthly basis.
![Page 106: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/106.jpg)
Page | ii
PROJECT DESCRIPTION
The Langebaanweg Aquifer Groundwater Infrastructure Project is situated approximately 16
km southwest of Hopefield and can be reached via a dirt farm road off the R45. This project is
a disaster management project (drought relief) and it entails a 5.1km long 400mm rising main,
3x borehole pumps, 3x MCC buildings and bulk electrical supply.
The consulting engineers : Element Consulting Engineers
The appointed contractor : Afriline Civils
![Page 107: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/107.jpg)
Page | iii
The findings during the environmental audit conducted on the 17th of May 2018, according to the Environmental Management Programme (EMP),
are listed below:
MAJOR ENVIRONMENTAL FINDINGS ACCORDING TO THE ENVIRONMENTAL MANAGEMENT PROGRAMME (EMP)
No. Requirements (EMP) Findings Photos Mitigation
1 No major findings were
found during the audit.
![Page 108: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/108.jpg)
Page | 1
GENERAL FINDINGS
No-Go areas
All areas outside the approved development area are strict No-Go areas. Rivers (including
their riparian zones) and wetlands should be treated as No-Go areas outside the approved
footprint and appropriately demarcated as such. No construction machinery or work force is
allowed in the No-Go areas. Please ensure that no machinery or workforce go beyond the
construction footprint. Please note that topsoil is also seen as No-Go area.
Topsoil
Topsoil must be deemed to be the top layer of soil containing organic material, nutrients and
plant/grass seed. For this reason it is an extremely valuable resource for the rehabilitation of
vegetation of disturbed areas. All topsoil should be windrowed (preferred option) to the one
side of the trench and the subsoil to the other side. The backfilling of the subsoil must be done
before the spreading of the topsoil over the disturbed area. Please ensure that topsoil in not
contaminated with construction material. If topsoil is to be stockpiled the stockpiles may not
be higher than 2m. Topsoil management is of the utmost importance when construction takes
place within the natural vegetation area.
Toilets
Please ensure that the construction site is equipped with a sufficient amount of chemical toilets
for the amount of workers on site. At least 1 chemical toilet per 15 workers is required no more
than 150m away from the construction activities. All chemical toilets have to be properly
secured to prevent the toilet from falling over in windy conditions. Penalties will be issued if
workforce is found not using the provided toilets or for a lack of sufficient amount of toilets.
The toilets were secured to the ground and the amount was sufficient.
![Page 109: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/109.jpg)
Page | 2
Fuel storage
If fuel is to be stored on site in the form of a bowser, the bowser must be maintained by the
fuel supplier and/or Contractor and is to be kept clean and leak free. The bowser is to be kept
on site with a drip tray at all times and please ensure that drip trays are used during refuelling
of machinery and generators. A drip tray was found underneath the bowser.
Dust/silt
Please appoint someone to clean the road at the entrance to the site should the need arise.
At the moment dust suppression on site is not a major concern as the construction works takes
place on a farm. As soon as the works takes place close to R45 dust suppression should be
monitored. Please ensure that alternative measures to using potable water are considered for
dust suppression.
Cement
Small and large scale cement batching must be done on mortarboards and/or on plastic
sheeting that serves an impermeable surface to prevent cement water from infiltrating the soil.
Please ensure that mortarboards and plastic sheeting are properly positioned to prevent any
surface runoff. No cement batching may be done directly on the soil as cement water is highly
alkaline and may change the pH of the soil causing decreased soil fertility. Mostly premix
concrete will be used on site. The entire site must be monitored for any concrete spillages, if
any spillages are found, they must be removed from site and be disposed of at a registered
Waste Landfill site or be used as fill material for the road. No concrete spillages/remains may
![Page 110: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/110.jpg)
Page | 3
be spoiled on site. No concrete truck chutes would be permitted to be washed on site. Batching
was done on mortarboards.
Litter
All construction litter, except empty cement bags, must be placed within a litter structure or
bin. Empty cement bags must be placed within a weatherproof bin. The litter structures and
bins must be properly enclosed to prevent any litter from blowing around on site. Please
monitor the soil around the enclosure for any excessive cement water potentially flowing into
the surrounding natural vegetation. Please ensure that a sufficient amount of bins or litterbags
is placed where the workforce is working. Please conduct regular chicken parades to remove
litter from site. Please ensure that empty cement bags are placed within an enclosed bin to
prevent cement leaching during rainy events.
Rubble
Please ensure that the construction rubble do not mix with the topsoil/subsoil as the
construction rubble must be removed from site. Concrete rubble may be disposed at a General
waste facility. Please ensure that rubble is removed on a regular basis.
Erosion and sedimentation control
Silt traps have to be utilized during all dewatering activities to prevent siltation of watercourses
or storm water systems. Silt traps either have to partially filter the suspended solids or allow
settlement in a manageable location. Please ensure that silt traps are being used during
dewatering.
![Page 111: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/111.jpg)
Page | 4
MAJOR AREAS OF CONCERN
No major areas of concern were found on site.
CONCLUSION
The construction activities at the site during the time of audit were well managed. The general
impression of the site was orderly and tidy.
Compiled by:
Divan Opperman
for GNEC
![Page 112: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/112.jpg)
Page | 5
PRINCIPLES OF THE EMP WHICH WERE AUDITED
The EMP was compiled using the following concepts and implementation requirements so that
the higher principles of sustainable development are realised: The EMP can therefore be seen
as a flexible and responsive document.
Continuous improvement. The project proponent (or implementing organisation) must be
committed to review and to continually improve environmental management, with the
objective of improving overall environmental performance.
Broad level of commitment. A broad level of commitment will be required from all levels of
management as well as the workforce in order for the development and implementation of
this EMP to be successful and effective.
Flexible and responsive. The implementation of the EMP must be responsive to new and
changing circumstances, i.e. rapid short-term responses to problems or incidents. The EMP
is a dynamic “living” document and thus regular planned review and revision of the EMP
must be carried out.
Integration across operations. This EMP is integrated across existing line functions and
operational units such as health, safety, and environmental departments in a
company/project. This is done to change the redundant mindset of seeing environmental
management as a single domain unit.
Legislation. It is understood that any development project during its construction phase is
a dynamic activity within a dynamic environment. The Developer, Engineer, Contractor,
and sub-contractor must therefore be aware that certain activities conducted during
construction may require further licensing or environmental approval, e.g. river or stream
diversions, bulk fuel storage, waste disposal, etc. The Contractor must consult the RE,
EO and ECO on a regular basis in this regard.
![Page 113: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/113.jpg)
THE LANGEBAANWEG AQUIFER GROUNDWATER
INFRASTRUCTURE PROJECT, HOPEFIELD, WESTERN
CAPE.
DEA&DP Ref: 16/6/F4/17/3140/17
FINAL CLOSURE ECO REPORT
Prepared for:
Saldanha Bay Municipality
Private Bag X12
Vredenburg
7380
Prepared by:
Guillaume Nel Environmental Consultants
P.O. Box 2632
Paarl
7620
Tel: 021 870 1874
Fax: 021 870 1873
Cell: 072 157 1321
E-Mail: [email protected]
8 October 2018
![Page 114: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/114.jpg)
Page | i
ABBREVIATIONS
DEA .............................................................................. Department of Environmental Affairs
DEA&DP ............................ Department of Environmental Affairs and Development Planning
DEAT ....................................................... Department of Environmental Affairs and Tourism
DWS ...................................................................Department of Water Affairs and Sanitation
EA .............................................................................................. Environmental Authorization
EAP ......................................................................... Environmental Assessment Practitioner
ECO ........................................................................................ Environmental Control Officer
EIA .................................................................................. Environmental Impact Assessment
EMP ....................................................................... Environmental Management Programme
DEO .................................................................................. Designated Environmental Officer
GNEC .................... .................................................Guillaume Nel Environmental Consulting
I&AP ..................................................................................... Interested and Affected Parties
RE…..………………………….………….……………………… ................ …Resident Engineer
INTRODUCTION
This FINAL CLOSURE report states the findings on the last site visit and may include
Environmental findings according to the Environmental Management Programme (EMP) that
still need to be addressed. This Final report is distributed to the Competent Authorities as well
as to the appointed Consulting Engineers and main Contractor in order to ensure continuous
improvement with regards to environmental related matters.
![Page 115: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/115.jpg)
Page | 1
ENVIRONMENTAL FINDINGS FOUND DURING THE SITE VISIT CONDUCTED ON
THE 2ND OF OCTOBER 2018.
Topsoil
The topsoil was spread over the pipeline route after the installation of the pipelines. Some of
the grasses have already started to grow.
Toilets
Two toilets were still present at the site camp. The contractor would remove the toilets as soon
as they remove the site camp.
Litter
All litter was removed from site.
Rubble
All rubble was removed from site.
Cement
All cement and concrete remains were removed from site.
![Page 116: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/116.jpg)
Page | 2
The construction activities have been completed successfully.
MAJOR AREAS OF CONCERN
No major areas of concern were found on site.
CONCLUSION
No environmental degradation was foreseen as a result of the construction activities and
GNEC has no objection to the contractor signing off the contract. The construction activities
during the duration of the contract were well managed. The general impression of the site was
orderly and tidy.
Compiled by:
Divan Opperman
for GNEC
![Page 117: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/117.jpg)
Page | 3
PRINCIPLES OF THE EMP WHICH WERE AUDITED
The EMP was compiled using the following concepts and implementation requirements so that
the higher principles of sustainable development are realised: The EMP can therefore be seen
as a flexible and responsive document.
Continuous improvement. The project proponent (or implementing organisation) must be
committed to review and to continually improve environmental management, with the
objective of improving overall environmental performance.
Broad level of commitment. A broad level of commitment will be required from all levels of
management as well as the workforce in order for the development and implementation of
this EMP to be successful and effective.
Flexible and responsive. The implementation of the EMP must be responsive to new and
changing circumstances, i.e. rapid short-term responses to problems or incidents. The EMP
is a dynamic “living” document and thus regular planned review and revision of the EMP
must be carried out.
Integration across operations. This EMP is integrated across existing line functions and
operational units such as health, safety, and environmental departments in a
company/project. This is done to change the redundant mindset of seeing environmental
management as a single domain unit.
Legislation. It is understood that any development project during its construction phase is
a dynamic activity within a dynamic environment. The Developer, Engineer, Contractor,
and sub-contractor must therefore be aware that certain activities conducted during
construction may require further licensing or environmental approval, e.g. river or stream
diversions, bulk fuel storage, waste disposal, etc. The Contractor must consult the RE,
EO and ECO on a regular basis in this regard
![Page 118: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/118.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 56 Reg. No: 2007/023691/07
ANNEXURE G – CONTRACTORS INDUCTION
![Page 119: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/119.jpg)
![Page 120: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/120.jpg)
![Page 121: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/121.jpg)
![Page 122: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/122.jpg)
![Page 123: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/123.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 57 Reg. No: 2007/023691/07
ANNEXURE H – DEADP CORRESPONDENCE
![Page 124: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/124.jpg)
Directorate: Development Management
Region 1
7th Floor, 1 Dorp Street, Cape Town, 8001 Private Bag X9086, Cape Town, 8000
Tel: +27 21 483 2742 Fax: +27 21 483 4372 www.westerncape.gov.za/eadp
REFERENCE NUMBER: 16/6/1/F4/17/Langebaan Phase 1
ENQUIRIES: Ms. N. Wookey
DATE: 08 SEPTEMBER 2020
The Municipal Manager
Saldanha Bay Municipality
℅ Bulk Water and Sanitation
Private Bag X2
VREDENBURG
7380
For Attention: Mr. G. Williams Tel: (022) 701 707
Fax: (022) 715 1304
Email: [email protected]
Dear Sir
COMMENTS ON THE ENVIRONMENTAL AUDIT REPORT SUBMITTED AS THE SECOND AUDIT REPORT FOR
THE LANGEBAAN AQUIFER GROUNDWATER INFRASTRUCTURE PROJECT WITH RESPECT TO THE SECTION
30A DIRECTIVE FOR THE PROVISION OF ADEQUATE WATER SUPPLY TO THE AREAS WITHIN THE
JURISDICTION OF THE SALDANHA BAY MUNICIPALITY.
1. The updated Water Supply Emergency Intervention Plan dated July 2018 and received by this
Directorate on 10 July 2018 (Ref. No. 16/6/F4/17/3140/17), this Directorate’s acknowledgement thereof
dated 17 July 208, the addendum to the updated Water Supply Emergency Intervention Plan dated 19
February 2020 and received by this Department on 05 March 2020, this Directorate’s acceptance
thereof dated 02 April 2020, the Environmental Audit Report dated and received by this Department via
electronic mail correspondence on 07 August 2020 and this Directorate’s acknowledgement thereof
dated 19 August 2020, refer.
2. Comments on the Audit Report (dated 07 August 2020) are as follows:
2.1. According to the Audit Report (dated 07 August 2020), a 77% compliance rating has been
achieved.
2.2. Reporting of compliance with the requirements of the Section 30A Directive (Ref. No.
16/6/F4/17/3140/17):
2.2.1. Although non-compliance with paragraph 6.3.1.2 of the Section 30A Directive (Ref. No.
16/6/F4/17/3140/17), in terms of the submission of the second audit report within three (3)
months of completion of the emergency measure or intervention, was noted by the auditor,
the submission of the Audit Report dated (07 August 2020) is in fulfillment of this requirement.
![Page 125: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/125.jpg)
REFERENCE NUMBER: 16/6/1/F4/17/Langebaan Phase 1 Page 2 of 3
2.2.2. The Audit Report (dated 07 August 2020) indicates that the Langebaan Phase 1 project has
contributed significantly to the water supply emergency situation and has improved the
water supply security in the area by 3 030 000m³ of water per annum.
2.2.3. The Section 30A Directive (Ref No. 16/6/F4/17/3140/17) requires that the Audit Report detail
how all the environmental impacts associated with each measure or intervention
implemented, have been mitigated. The Audit Report (dated 07 August 2020) does not
indicate the environmental impacts associated with the proposed development and does
not report on how each impact has been mitigated.
2.2.4. Proof of submission of the Audit Report (dated 07 August 2020) to the Department of Water
and Sanitation, Heritage Western Cape and the Department of Environmental Affairs:
Oceans and Coasts has not been provided.
2.3. Reporting of compliance with the Environmental Management Programme (“EMPr”)
2.3.1. Although the Audit Report (dated 07 August 2020) reports on compliance with the
performance specifications tables detailed in Section 6 of the EMPr (dated 14 December
2017), it is unclear as to whether the mitigation measures detailed in Section 7 of the EMPr
(dated 14 December 2017) were implemented during the planning, pre-construction and
construction phases of the proposed development.
2.3.2. Based on the fact that the ability of the EMPr to sufficiently provide for the avoidance,
management and mitigation of environmental impacts associated with the proposed
development was based on the assessment of compliance with Section 6 of the EMPr
(dated 14 December 2017), the outcome of the Audit Report (dated 07 August 2020) is
deemed to be premature. The ability of the EMPr to sufficiently provide for the avoidance,
management and mitigation of environmental impacts associated with the proposed
development must be based on the assessment of compliance with Section 7 of the EMPr
(dated 14 December 2017).
3. The Audit Report (dated 07 August 2020) must therefore be amended to include the following;
3.1. In terms of the reporting of compliance with the Section 30A Directive (Ref No. 16/6/F/17/3140/17),
the amended Audit Report must, inter alia:
3.1.1. Detail how all the environmental impacts associated with each measure or intervention
implemented have been mitigated; and
3.1.2. Include proof of the submission of a copy of the Audit Report to the Department of Water
and Sanitation, Heritage Western Cape and the Department of Environmental Affairs:
Oceans and Coasts.
3.2. In terms of the reporting of compliance with the EMPr, the amended Audit Report must, inter alia:
3.2.1. Report on compliance with Section 7 of the EMPr (dated 14 December 2017);
3.2.2. Report on the ability of the EMPr to sufficiently provide for the avoidance, management and
mitigation of environmental impacts associated with the proposed development must be
based on the assessment of compliance with Section 7 of the EMPr (dated 14 December
2017).
4. The amended Audit Report must be submitted to the Competent Authority for approval by no later than
30 November 2020.
5. You are advised that compliance site audits may be forthcoming and that you may be informed of such
site audits accordingly.
![Page 126: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/126.jpg)
REFERENCE NUMBER: 16/6/1/F4/17/Langebaan Phase 1 Page 3 of 3
The Department reserves the right to revise or withdraw comments or request further information based on
any information received.
Yours faithfully
__________________
MR. ZAAHIR TOEFY
DIRECTOR: DEVELOPMENT MANAGEMENT (REGION 1)
Copies to: (1) Dr. J. Mphepya (℅ Mr. Y. Peterson (DEA: Oceans and Coasts))
Email: [email protected] / [email protected] / [email protected]
Fax: (021) 819 8410
(2) Mr. M. Dlamuka (℅ Ms. W. Dhansay (Heritage Western Cape))
Email: [email protected] / [email protected]
Fax: (021) 483 9845
(3) Mr. R. Khan (Department of Water and Sanitation)
Email: [email protected]
Fax: (021) 941 6072
(4) Mr. G. Gerber /Ms. K. Rughoobeer (DEA&DP: Directorate Development Facilitation)
Email: [email protected] / [email protected]
Fax: (021) 483 8311
(5) Mr. M. Wheeler (CapeNature)
Email: [email protected]
Fax: (021) 866 1523
(6) Ms. M. Chauke (Department of Environmental Affairs)
Email: [email protected]
Fax: (012) 399 9081
![Page 127: Section 30(A) Directive External Audit Report](https://reader034.vdocuments.us/reader034/viewer/2022042201/62586e1803f2d313ee748177/html5/thumbnails/127.jpg)
NCC Environmental Services (Pty) Ltd External Compliance Audit - Langebaan Wellfield Water Augmentation Project – Oct 2020 Page 58 Reg. No: 2007/023691/07
ANNEXURE I – PROOF OF DISTRIBUTION TO RELEVANT AUTHORTIES