section 033000 - cast-in-place concrete part 1 - general · elevation, and position indicated,...

54
SECTION 033000 - CAST-IN-PLACE CONCRETE FACILITIES BUILDING POWER GENERATOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT # ECSU-2019-5 1 PART 1 - GENERAL 1.1 SUMMARY A. Section includes cast-in-place concrete, including formwork, reinforcement, concrete materials, mixture design, placement procedures, and finishes. 1.2 ACTION SUBMITTALS A. Product Data: For each type of product indicated. B. Design Mixtures: For each concrete mixture. C. Steel Reinforcement Shop Drawings: Placing drawings that detail fabrication, bending, and placement. 1.3 INFORMATIONAL SUBMITTALS A. Material certificates. B. Material test reports. 1.4 QUALITY ASSURANCE A. Manufacturer Qualifications: A firm experienced in manufacturing ready-mixed concrete products and that complies with ASTM C 94/C 94M requirements for production facilities and equipment. B. Testing Agency Qualifications: An independent agency, acceptable to authorities having jurisdiction, qualified according to ASTM C 1077 and ASTM E 329 for testing indicated. C. Welding Qualifications: Qualify procedures and personnel according to AWS D1.4/D 1.4M, "Structural Welding Code - Reinforcing Steel." D. ACI Publications: Comply with the following unless modified by requirements in the Contract Documents: 1. ACI 301, "Specifications for Structural Concrete," Sections 1 through 5. 2. ACI 117, "Specifications for Tolerances for Concrete Construction and Materials." E. Concrete Testing Service: The ECSU will engage a qualified independent testing agency to perform material evaluation tests and to design concrete mixtures. F. Preinstallation Conference: Conduct conference at Project site.

Upload: others

Post on 23-Mar-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 033000 - CAST-IN-PLACE CONCRETE

FACILITIES BUILDING POWER GENERATOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

# ECSU-2019-5

1

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes cast-in-place concrete, including formwork, reinforcement, concrete materials, mixture design, placement procedures, and finishes.

1.2 ACTION SUBMITTALS

A. Product Data: For each type of product indicated.

B. Design Mixtures: For each concrete mixture.

C. Steel Reinforcement Shop Drawings: Placing drawings that detail fabrication, bending, and placement.

1.3 INFORMATIONAL SUBMITTALS

A. Material certificates.

B. Material test reports.

1.4 QUALITY ASSURANCE

A. Manufacturer Qualifications: A firm experienced in manufacturing ready-mixed concrete products and that complies with ASTM C 94/C 94M requirements for production facilities and equipment.

B. Testing Agency Qualifications: An independent agency, acceptable to authorities having jurisdiction, qualified according to ASTM C 1077 and ASTM E 329 for testing indicated.

C. Welding Qualifications: Qualify procedures and personnel according to AWS D1.4/D 1.4M, "Structural Welding Code - Reinforcing Steel."

D. ACI Publications: Comply with the following unless modified by requirements in the Contract Documents:

1. ACI 301, "Specifications for Structural Concrete," Sections 1 through 5. 2. ACI 117, "Specifications for Tolerances for Concrete Construction and Materials."

E. Concrete Testing Service: The ECSU will engage a qualified independent testing agency to perform material evaluation tests and to design concrete mixtures.

F. Preinstallation Conference: Conduct conference at Project site.

Page 2: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 033000 - CAST-IN-PLACE CONCRETE

FACILITIES BUILDING POWER GENERATOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

# ECSU-2019-5

2

PART 2 - PRODUCTS

2.1 FORM-FACING MATERIALS

A. Smooth-Formed Finished Concrete: Form-facing panels that will provide continuous, true, and smooth concrete surfaces. Furnish in largest practicable sizes to minimize number of joints.

B. Rough-Formed Finished Concrete: Plywood, lumber, metal, or another approved material. Provide lumber dressed on at least two edges and one side for tight fit.

2.2 STEEL REINFORCEMENT

A. Reinforcing Bars: ASTM A 615/A 615M, Grade 60, deformed. 1. Epoxy-Coated Reinforcing Bars: ASTM A 775/A 775M, epoxy coated, with less than 2

percent damaged coating in each 12-inch bar length.

B. Plain-Steel Welded Wire Reinforcement: ASTM A 185/A 185M, plain, fabricated from as-drawn steel wire into flat sheets.

C. Deformed-Steel Welded Wire Reinforcement: ASTM A 497/A 497M, flat sheet.

D. Epoxy-Coated Welded Wire Reinforcement: ASTM A 884/A 884M, Class A coated, Type 1, deformed steel.

E. Bar Supports: Bolsters, chairs, spacers, and other devices for spacing, supporting, and fastening reinforcing bars and welded wire reinforcement in place. Manufacture bar supports from steel wire, plastic, or precast concrete according to CRSI's "Manual of Standard Practice.

2.3 CONCRETE MATERIALS

A. Cementitious Material: Use the following cementitious materials, of the same type, brand, and source, throughout Project:

1. Portland Cement: ASTM C 150, Type I or Type II, gray

B. Normal-Weight Aggregates: ASTM C 33, graded.

1. Maximum Coarse-Aggregate Size: 3/4 inch nominal. 2. Fine Aggregate: Free of materials with deleterious reactivity to alkali in cement.

C. Water: ASTM C 94/C 94M and potable.

2.4 ADMIXTURES

A. Air-Entraining Admixture: ASTM C 260.

B. Chemical Admixtures: Provide admixtures certified by manufacturer to be compatible with other admixtures and that will not contribute water-soluble chloride ions exceeding those

Page 3: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 033000 - CAST-IN-PLACE CONCRETE

FACILITIES BUILDING POWER GENERATOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

# ECSU-2019-5

3

permitted in hardened concrete. Do not use calcium chloride or admixtures containing calcium chloride.

2.5 VAPOR RETARDERS

A. Sheet Vapor Retarder: ASTM E 1745, Class B Include manufacturer's recommended adhesive or pressure-sensitive tape.

a. Stego Industries Stego Wrap ( 15 mil) or approved equal

2.6 CURING MATERIALS

A. Evaporation Retarder: Waterborne, monomolecular film forming, manufactured for application to fresh concrete.

B. Absorptive Cover: AASHTO M 182, Class 2, burlap cloth made from jute or kenaf, weighing approximately 9 oz./sq. yd. when dry.

C. Moisture-Retaining Cover: ASTM C 171, polyethylene film or white burlap-polyethylene sheet.

D. Water: Potable.

E. Clear, Waterborne, Membrane-Forming Curing Compound: ASTM C 309, Type 1, Class B, dissipating.

2.7 CONCRETE MIXTURES

A. Prepare design mixtures for each type and strength of concrete, proportioned on the basis of laboratory trial mixture or field test data, or both, according to ACI 301.

B. Admixtures: Use admixtures according to manufacturer's written instructions.

1. Use water-reducing or high-range water-reducing admixture in concrete, as required, for placement and workability.

2. Use water-reducing and retarding admixture when required by high temperatures, low humidity, or other adverse placement conditions.

C. Proportion normal-weight concrete mixture as follows:

1. Minimum Compressive Strength: 5000 psi 2. Maximum Water-Cementitious Materials Ratio: [0.50] [0.45] 3. Slump Limit: 4 inches for concrete with verified slump of 2 to 4 inches, plus or minus 1

inch. 4. Air Content: 6 percent, plus or minus 1.5 percent at point of delivery for 3/4-inch

nominal maximum aggregate size. 5. Air Content: Do not allow air content of trowel-finished slabs to exceed 3 percent.

Page 4: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 033000 - CAST-IN-PLACE CONCRETE

FACILITIES BUILDING POWER GENERATOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

# ECSU-2019-5

4

2.8 FABRICATING REINFORCEMENT

A. Fabricate steel reinforcement according to CRSI's "Manual of Standard Practice."

2.9 CONCRETE MIXING

A. Ready-Mixed Concrete: Measure, batch, mix, and deliver concrete according to ASTM C 94/C 94M, and furnish batch ticket information.

1. When air temperature is between 85 and 90 deg F, reduce mixing and delivery time from 1-1/2 hours to 75 minutes; when air temperature is above 90 deg F, reduce mixing and delivery time to 60 minutes.

PART 3 - EXECUTION

3.1 FORMWORK

A. Design, erect, shore, brace, and maintain formwork, according to ACI 301, to support vertical, lateral, static, and dynamic loads, and construction loads that might be applied, until structure can support such loads.

B. Construct formwork so concrete members and structures are of size, shape, alignment, elevation, and position indicated, within tolerance limits of ACI 117.

C. Chamfer exterior corners and edges of permanently exposed concrete.

3.2 EMBEDDED ITEMS

A. Place and secure anchorage devices and other embedded items required for adjoining work that is attached to or supported by cast-in-place concrete. Use setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded.

3.3 VAPOR RETARDERS

A. Sheet Vapor Retarders: Place, protect, and repair sheet vapor retarder according to ASTM E 1643 and manufacturer's written instructions.

1. Lap joints 6 inches and seal with manufacturer's recommended tape.

3.4 STEEL REINFORCEMENT

A. General: Comply with CRSI's "Manual of Standard Practice" for placing reinforcement.

1. Do not cut or puncture vapor retarder. Repair damage and reseal vapor retarder before placing concrete.

Page 5: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 033000 - CAST-IN-PLACE CONCRETE

FACILITIES BUILDING POWER GENERATOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

# ECSU-2019-5

5

3.5 CONCRETE PLACEMENT

A. Before placing concrete, verify that installation of formwork, reinforcement, and embedded items is complete and that required inspections have been performed.

B. Deposit concrete continuously in one layer or in horizontal layers of such thickness that no new concrete will be placed on concrete that has hardened enough to cause seams or planes of weakness. If a section cannot be placed continuously, provide construction joints as indicated. Deposit concrete to avoid segregation.

1. Consolidate placed concrete with mechanical vibrating equipment according to ACI 301.

C. Cold-Weather Placement: Comply with ACI 306.1.

D. Hot-Weather Placement: Comply with ACI 301.

3.6 FINISHING FORMED SURFACES

A. Smooth-Formed Finish: As-cast concrete texture imparted by form-facing material, arranged in an orderly and symmetrical manner with a minimum of seams. Repair and patch tie holes and defects. Remove fins and other projections that exceed specified limits on formed-surface irregularities.

1. Apply to concrete surfaces exposed to public view,.

2. Smooth-Rubbed Finish: Not later than one day after form removal, moisten concrete surfaces and rub with carborundum brick or another abrasive until producing a uniform color and texture. Do not apply cement grout other than that created by the rubbing process.

3.7 FINISHING SLABS

A. General: Comply with ACI 302.1R recommendations for screeding, restraightening, and finishing operations for concrete surfaces. Do not wet concrete surfaces.

B. Float Finish: Consolidate surface with power-driven floats or by hand floating if area is small or inaccessible to power driven floats. Restraighten, cut down high spots, and fill low spots. Repeat float passes and restraightening until surface is left with a uniform, smooth, granular texture.

1. Apply float finish to surfaces to receive trowel finish.

C. Trowel Finish: After applying float finish, apply first troweling and consolidate concrete by hand or power-driven trowel. Continue troweling passes and restraighten until surface is free of trowel marks and uniform in texture and appearance. Grind smooth any surface defects that would telegraph through applied coatings or floor coverings.

1. Apply a trowel finish to surfaces exposed to view.

Page 6: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 033000 - CAST-IN-PLACE CONCRETE

FACILITIES BUILDING POWER GENERATOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

# ECSU-2019-5

6

2. Finish and measure surface so gap at any point between concrete surface and an unleveled, freestanding, 10-ft.- long straightedge resting on two high spots and placed anywhere on the surface does not exceed 1/4 inch.

3.8 CONCRETE PROTECTING AND CURING

A. General: Protect freshly placed concrete from premature drying and excessive cold or hot temperatures. Comply with ACI 306.1 for cold-weather protection and ACI 301 for hot-weather protection during curing.

B. Evaporation Retarder: Apply evaporation retarder to unformed concrete surfaces if hot, dry, or windy conditions cause moisture loss approaching 0.2 lb/sq. ft. x h before and during finishing operations. Apply according to manufacturer's written instructions after placing, screeding, and bull floating or darbying concrete, but before float finishing.

C. Cure concrete according to ACI 308.1, by one or a combination of the following methods:

1. Moisture Curing: Keep surfaces continuously moist for not less than seven days. 2. Moisture-Retaining-Cover Curing: Cover concrete surfaces with moisture-retaining

cover for curing concrete, placed in widest practicable width, with sides and ends lapped at least 12 inches, and sealed by waterproof tape or adhesive. Cure for not less than seven days. Immediately repair any holes or tears during curing period using cover material and waterproof tape.

3. Curing Compound: Apply uniformly in continuous operation by power spray or roller according to manufacturer's written instructions. Recoat areas subjected to heavy rainfall within three hours after initial application. Maintain continuity of coating and repair damage during curing period.

4. Curing and Sealing Compound: Apply uniformly to slabs indicated in a continuous operation by power spray or roller according to manufacturer's written instructions. Recoat areas subjected to heavy rainfall within three hours after initial application. Repeat process 24 hours later and apply a second coat. Maintain continuity of coating and repair damage during curing period.

3.9 CONCRETE SURFACE REPAIRS

A. Defective Concrete: Repair and patch defective areas when approved by Engineer. Remove and replace concrete that cannot be repaired and patched to Engineer's approval.

3.10 FIELD QUALITY CONTROL

A. Testing and Inspecting: Owner will engage a qualified testing and inspecting agency to perform field tests and inspections and prepare test reports.

END OF SECTION 033000

Page 7: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 033000 - CAST-IN-PLACE CONCRETE

FACILITIES BUILDING POWER GENERATOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

# ECSU-2019-5

7

Page 8: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 078413 - PENETRATION FIRESTOPPING

FACILITIES BUILDING POWER GENERATOR ADDITION Proj#ECSU-2019-5 EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

1

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Penetrations in fire-resistance- rated walls.

1.2 ACTION SUBMITTALS

A. Product Data: For 2 hour rated penetration of the wall by the EMT conduits.

B. Product test reports.

1.3 QUALITY ASSURANCE

A. Fire-Test-Response Characteristics: Penetration firestopping shall comply with the following requirements:

1. Penetration firestopping tests are performed by UL, Intertek ETL SEMKO or FM Global 2. Penetration firestopping is identical to those tested per testing standard referenced in

"Penetration Firestopping" Article. Provide rated systems bearing marking of qualified testing and inspection agency.

3. 215 IBC

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following 1. Hilti, Inc. 2. RectorSeal Corporation. 3. 3M Fire Protection Products.

2.2 PENETRATION FIRESTOPPING

A. Provide penetration firestopping that is produced and installed to resist spread of fire according to requirements indicated, resist passage of smoke and other gases, and maintain original fire-resistance rating of construction penetrated. Penetration firestopping systems shall be compatible with one another, with the substrates forming openings, and with penetrating items if any.

Page 9: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 078413 - PENETRATION FIRESTOPPING

FACILITIES BUILDING POWER GENERATOR ADDITION Proj#ECSU-2019-5 EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

2

B. Penetrations in Fire-Resistance-Rated Walls: Ratings determined per ASTM E 814 or UL 1479, based on testing at a positive pressure differential of 0.01-inch wg.

1. F-Rating: Not less than the fire-resistance rating of constructions penetrated.

C. Penetrations in Smoke Barriers: Provide penetration firestopping with ratings determined per UL 1479.

1. L-Rating: Not exceeding 5.0 cfm/sq. ft. of penetration opening at 0.30-inch wg at both ambient and elevated temperatures.

D. Exposed Penetration Firestopping: Provide products with flame-spread and smoke-developed indexes of less than 25 and 450, respectively, as determined per ASTM E 84.

E. Accessories: Provide components for each penetration firestopping system that are needed to install fill materials and to maintain ratings required. Use only those components specified by penetration firestopping manufacturer and approved by qualified testing and inspecting agency for firestopping indicated.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Examine substrates and conditions, with Installer present, for compliance with requirements for opening configurations, penetrating items, substrates, and other conditions affecting performance of the Work.

B. Install penetration firestopping to comply with manufacturer's written installation instructions and published drawings for products and applications indicated.

C. Install forming materials and other accessories of types required to support fill materials during their application and in the position needed to produce cross-sectional shapes and depths required to achieve fire ratings indicated.

1. After installing fill materials and allowing them to fully cure, remove combustible forming materials and other accessories not indicated as permanent components of firestopping.

D. Install fill materials for firestopping by proven techniques to produce the following results:

1. Fill voids and cavities formed by openings, forming materials, accessories, and penetrating items as required to achieve fire-resistance ratings indicated.

2. Apply materials so they contact and adhere to substrates formed by openings and penetrating items.

3. For fill materials that will remain exposed after completing the Work, finish to produce smooth, uniform surfaces that are flush with adjoining finishes.

4.

Page 10: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 078413 - PENETRATION FIRESTOPPING

FACILITIES BUILDING POWER GENERATOR ADDITION Proj#ECSU-2019-5 EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

3

3.2 FIELD QUALITY CONTROL

A. Owner will engage a qualified testing agency to perform tests and inspections.

B. Where deficiencies are found or penetration firestopping is damaged or removed because of testing, repair or replace penetration firestopping to comply with requirements.

C. Proceed with enclosing penetration firestopping with other construction only after inspection reports are issued and installations comply with requirements.

END OF SECTION 078413

Page 11: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 260519 - LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

FACILITIES BUILDING POWER GENERATOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

# ECSU-2019-5

1

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Building wires and cables rated 600 V and less. 2. Connectors, splices, and terminations rated 600 V and less.

1.2 ACTION SUBMITTALS

A. Product Data: For each type of product.

1.3 INFORMATIONAL SUBMITTALS

A. Field quality-control reports.

PART 2 - PRODUCTS

2.1 CONDUCTORS AND CABLES

A. Copper Conductors: Comply with NEMA WC 70/ICEA S-95-658.

B. Conductor Insulation: Comply with NEMA WC 70/ICEA S-95-658 for Type THHN-2-THWN-2 .

C. Multiconductor Cable: Comply with NEMA WC 70/ICEA S-95-658 for armored cable, Type AC metal-clad cable, Type MC with ground wire.

2.2 CONNECTORS AND SPLICES

A. Description: Factory-fabricated connectors and splices of size, ampacity rating, material, type, and class for application and service indicated.

2.3 SYSTEM DESCRIPTION

A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in 2017 NFPA 70, by a qualified testing agency, and marked for intended location and application.

B. Comply with 2017 NFPA 70.

Page 12: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 260519 - LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

FACILITIES BUILDING POWER GENERATOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

# ECSU-2019-5

2

PART 3 - EXECUTION

3.1 CONDUCTOR MATERIAL APPLICATIONS

A. Feeders: Copper. Solid for No. 10 AWG and smaller; stranded for No. 8 AWG and larger.

B. Branch Circuits: Copper. Solid for No. 12 AWG and smaller; stranded for No. 10 AWG and larger.

3.2 CONDUCTOR INSULATION AND MULTICONDUCTOR CABLE APPLICATIONS AND WIRING METHODS

A. Service Entrance: Type THHN-2-THWN-2, single conductors in raceway.

B. Exposed Feeders: Type THHN-2-THWN-2, single conductors in raceway.

C. Feeders Concealed in Concrete, below Slabs-on-Grade, and Underground: Type THHN-2-THWN-2, single conductors in raceway.

3.3 INSTALLATION OF CONDUCTORS AND CABLES

A. Complete raceway installation between conductor and cable termination points according to Section 260533 "Raceways and Boxes for Electrical Systems" prior to pulling conductors and cables.

B. Use manufacturer-approved pulling compound or lubricant where necessary; compound used must not deteriorate conductor or insulation. Do not exceed manufacturer's recommended maximum pulling tensions and sidewall pressure values.

C. Use pulling means, including fish tape, cable, rope, and basket-weave wire/cable grips, that will not damage cables or raceway.

D. Install exposed cables parallel and perpendicular to surfaces of exposed structural members, and follow surface contours where possible.

E. Support cables according to Section 260529 "Hangers and Supports for Electrical Systems."

3.4 CONNECTIONS

A. Tighten electrical connectors and terminals according to manufacturer's published torque-tightening values. If manufacturer's torque values are not indicated, use those specified in UL 486A-486B.

B. Make splices, terminations, and taps that are compatible with conductor material and that possess equivalent or better mechanical strength and insulation ratings than unspliced conductors.

1. Use oxide inhibitor in each splice, termination, and tap for aluminum conductors.

Page 13: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 260519 - LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

FACILITIES BUILDING POWER GENERATOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

# ECSU-2019-5

3

C. Wiring at Outlets: Install conductor at each outlet, with at least 6 inches of slack.

3.5 IDENTIFICATION

A. Identify and color-code conductors and cables according to Section 260553 "Identification for Electrical Systems."

B. Identify each spare conductor at each end with identity number and location of other end of conductor, and identify as spare conductor.

3.6 SLEEVE AND SLEEVE-SEAL INSTALLATION FOR ELECTRICAL PENETRATIONS

A. Install sleeves and sleeve seals at penetrations of exterior wall assemblies.

3.7 FIRESTOPPING

A. Apply firestopping to electrical penetrations of fire-rated wall assemblies to restore original fire-resistance rating of assembly according to Section 078413 "Penetration Firestopping."

3.8 FIELD QUALITY CONTROL

A. Perform the following tests and inspections:

1. After installing conductors and cables and before electrical circuitry has been energized, test service entrance and feeder conductors for compliance with requirements.

2. Perform each visual and mechanical inspection and electrical test stated in NETA Acceptance Testing Specification. Certify compliance with test parameters.

B. Test and Inspection Reports: Prepare a written report to record the following:

1. Procedures used. 2. Results that comply with requirements. 3. Results that do not comply with requirements and corrective action taken to achieve

compliance with requirements.

C. Cables will be considered defective if they do not pass tests and inspections.

END OF SECTION 260519

Page 14: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 260526 - GROUNDING AND BONDING

FACILITIES BUILDING POWER GENERATOR ADDITION PROJ #ECSU-2019-5 EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT 1

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes grounding and bonding systems and equipment.

1.2 ACTION SUBMITTALS

A. Product Data: For each type of product indicated.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. Burndy; Part of Hubbell Electrical Systems. 2. Fushi Copperweld Inc. 3. ILSCO. 4. O-Z/Gedney; A Brand of the EGS Electrical Group. 5. Robbins Lightning, Inc. 6. Siemens Power Transmission & Distribution, Inc.

2.2 SYSTEM DESCRIPTION

A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in 2017 NFPA 70, by a qualified testing agency, and marked for intended location and application.

B. Comply with UL 467 for grounding and bonding materials and equipment.

2.3 CONDUCTORS

A. Insulated Conductors: Copper wire or cable insulated for 600 V unless otherwise required by applicable Code or authorities having jurisdiction.

B. Bare Copper Conductors:

1. Solid Conductors: ASTM B 3. 2. Stranded Conductors: ASTM B 8. 3. Tinned Conductors: ASTM B 33. 4. Bonding Cable: 28 kcmil, 14 strands of No. 17 AWG conductor, 1/4 inch in diameter. 5. Bonding Conductor: No. 4 or No. 6 AWG, stranded conductor.

Page 15: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 260526 - GROUNDING AND BONDING

FACILITIES BUILDING POWER GENERATOR ADDITION PROJ #ECSU-2019-5 EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT 2

6. Bonding Jumper: Copper tape, braided conductors terminated with copper ferrules; 1-5/8 inches wide and 1/16 inch thick.

7. Tinned Bonding Jumper: Tinned-copper tape, braided conductors terminated with copper ferrules; 1-5/8 inches wide and 1/16 inch thick.

2.4 CONNECTORS

A. Listed and labeled by an NRTL acceptable to authorities having jurisdiction for applications in which used and for specific types, sizes, and combinations of conductors and other items connected.

B. Bolted Connectors for Conductors and Pipes: Copper or copper alloy.

C. Welded Connectors: Exothermic-welding kits of types recommended by kit manufacturer for materials being joined and installation conditions.

D. Bus-Bar Connectors: Mechanical type, cast silicon bronze, solderless compression or exothermic-type wire terminals, and long-barrel, two-bolt connection to ground bus bar.

PART 3 - EXECUTION

3.1 APPLICATIONS

A. Conductors: Install solid conductor for No. 8 AWG and smaller, and stranded conductors for No. 6 AWG and larger unless otherwise indicated.

B. Conductor Terminations and Connections:

1. Equipment Grounding Conductor Terminations: Bolted connectors. 2. Connections to Structural Steel: Welded connectors.

3.2 GROUNDING AT THE SERVICE

A. Equipment grounding conductors shall be connected to the ground bus. Install a main bonding jumper between the neutral and ground buses.

3.3 EQUIPMENT GROUNDING

A. Install insulated equipment grounding conductors with all feeders and branch circuits.

B. Install insulated equipment grounding conductors with the following items, in addition to those required by 2017 NFPA 70:

1. Feeders and branch circuits.

Page 16: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 260526 - GROUNDING AND BONDING

FACILITIES BUILDING POWER GENERATOR ADDITION PROJ #ECSU-2019-5 EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT 3

3.4 INSTALLATION

A. Grounding Conductors: Route along shortest and straightest paths possible unless otherwise indicated or required by Code. Avoid obstructing access or placing conductors where they may be subjected to strain, impact, or damage.

B. Ground Bonding Common with Lightning Protection System: Comply with NFPA 780 and UL 96 when interconnecting with lightning protection system. Bond electrical power system ground directly to lightning protection system grounding conductor at closest point to electrical service grounding electrode. Use bonding conductor sized same as system grounding electrode conductor, and install in conduit.

C. Bonding Straps and Jumpers: Install in locations accessible for inspection and maintenance except where routed through short lengths of conduit.

1. Bonding to Structure: Bond straps directly to basic structure, taking care not to penetrate any adjacent parts.

2. Bonding to Equipment Mounted on Vibration Isolation Hangers and Supports: Install bonding so vibration is not transmitted to rigidly mounted equipment.

3. Use exothermic-welded connectors for outdoor locations; if a disconnect-type connection is required, use a bolted clamp.

3.5 FIELD QUALITY CONTROL

A. Perform tests and inspections. Inspect physical and mechanical condition. Verify tightness of accessible, bolted, electrical connections with a calibrated torque wrench according to manufacturer's written instructions.

END OF SECTION 16060

Page 17: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 260529 - HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

FACILITIES BUILDING POWER GENERATOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

1

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes:

1. Hangers and supports for electrical equipment and systems. 2. Construction requirements for concrete bases.

1.2 PERFORMANCE REQUIREMENTS

A. Design supports for multiple raceways capable of supporting combined weight of supported systems and its contents.

B. Design equipment supports capable of supporting combined operating weight of supported equipment and connected systems and components.

C. Rated Strength: Adequate in tension, shear, and pullout force to resist maximum loads calculated or imposed for this Project, with a minimum structural safety factor of five times the applied force.

1.3 ACTION SUBMITTALS

A. Product Data: For steel slotted support systems.

B. Shop Drawings: Show fabrication and installation details and include calculations for the following:

1. Trapeze hangers. Include Product Data for components. 2. Steel slotted channel systems. Include Product Data for components. 3. Equipment supports.

1.4 INFORMATIONAL SUBMITTALS

A. Welding certificates.

1.5 QUALITY ASSURANCE

A. Welding: Qualify procedures and personnel according to AWS D1.1/D1.1M, "Structural Welding Code - Steel."

B. Comply with 2017 NFPA 70.

Page 18: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 260529 - HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

FACILITIES BUILDING POWER GENERATOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

2

PART 2 - PRODUCTS

2.1 SUPPORT, ANCHORAGE, AND ATTACHMENT COMPONENTS

A. Steel Slotted Support Systems: Comply with MFMA-4, factory-fabricated components for field assembly. 1. Manufacturers: Subject to compliance with requirements, provide products by one of the

following:

a. Allied Tube & Conduit. b. Cooper B-Line, Inc.; a division of Cooper Industries. c. ERICO International Corporation. d. GS Metals Corp. e. Thomas & Betts Corporation. f. Unistrut; Tyco International, Ltd. g. Wesanco, Inc.

2. Metallic Coatings: Hot-dip galvanized after fabrication and applied according to MFMA-4.

3. Nonmetallic Coatings: Manufacturer's standard PVC, polyurethane, or polyester coating applied according to MFMA-4.

4. Painted Coatings: Manufacturer's standard painted coating applied according to MFMA-4.

5. Channel Dimensions: Selected for applicable load criteria.

B. Raceway and Cable Supports: As described in NECA 1 and NECA 101.

C. Conduit and Cable Support Devices: Steel hangers, clamps, and associated fittings, designed for types and sizes of raceway or cable to be supported.

D. Support for Conductors in Vertical Conduit: Factory-fabricated assembly consisting of threaded body and insulating wedging plug or plugs for non-armored electrical conductors or cables in riser conduits. Plugs shall have number, size, and shape of conductor gripping pieces as required to suit individual conductors or cables supported. Body shall be malleable iron.

E. Structural Steel for Fabricated Supports and Restraints: ASTM A 36/A 36M, steel plates, shapes, and bars; black and galvanized.

F. Mounting, Anchoring, and Attachment Components: Items for fastening electrical items or their supports to building surfaces include the following:

1. Powder-Actuated Fasteners: Threaded-steel stud, for use in hardened portland cement concrete, steel, or wood, with tension, shear, and pullout capacities appropriate for supported loads and building materials where used. a. Manufacturers: Subject to compliance with requirements, provide products by one

of the following:

1) Hilti Inc. 2) ITW Ramset/Red Head; a division of Illinois Tool Works, Inc. 3) MKT Fastening, LLC.

Page 19: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 260529 - HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

FACILITIES BUILDING POWER GENERATOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

3

4) Simpson Strong-Tie Co., Inc.; Masterset Fastening Systems Unit.

2. Mechanical-Expansion Anchors: Insert-wedge-type, zinc-coated steel, for use in hardened portland cement concrete with tension, shear, and pullout capacities appropriate for supported loads and building materials in which used. a. Manufacturers: Subject to compliance with requirements, provide products by one

of the following:

1) Cooper B-Line, Inc.; a division of Cooper Industries. 2) Empire Tool and Manufacturing Co., Inc. 3) Hilti Inc. 4) ITW Ramset/Red Head; a division of Illinois Tool Works, Inc. 5) MKT Fastening, LLC.

3. Concrete Inserts: Steel or malleable-iron, slotted support system units similar to MSS Type 18; complying with MFMA-4 or MSS SP-58.

4. Clamps for Attachment to Steel Structural Elements: MSS SP-58, type suitable for attached structural element.

5. Through Bolts: Structural type, hex head, and high strength. Comply with ASTM A 325.

6. Toggle Bolts: All-steel springhead type. 7. Hanger Rods: Threaded steel.

2.2 FABRICATED METAL EQUIPMENT SUPPORT ASSEMBLIES

A. Description: Welded or bolted, structural-steel shapes, shop or field fabricated to fit dimensions of supported equipment.

PART 3 - EXECUTION

3.1 APPLICATION

A. Comply with NECA 1 and NECA 101 for application of hangers and supports for electrical equipment and systems except if requirements in this Section are stricter.

B. Maximum Support Spacing and Minimum Hanger Rod Size for Raceway: Space supports for EMT, IMC, and RMC as required by 2017 NFPA 70. Minimum rod size shall be 1/4 inch in diameter.

C. Multiple Raceways: Install trapeze-type supports fabricated with steel slotted or other support system, sized so capacity can be increased by at least 25 percent in future without exceeding specified design load limits.

1. Secure raceways and cables to these supports with two-bolt conduit clamps.

Page 20: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 260529 - HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

FACILITIES BUILDING POWER GENERATOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

4

3.2 SUPPORT INSTALLATION

A. Comply with NECA 1 and NECA 101 for installation requirements except as specified in this Article.

B. Strength of Support Assemblies: Where not indicated, select sizes of components so strength will be adequate to carry present and future static loads within specified loading limits. Minimum static design load used for strength determination shall be weight of supported components plus 200 lb.

C. Mounting and Anchorage of Surface-Mounted Equipment and Components: Anchor and fasten electrical items and their supports to building structural elements by the following methods unless otherwise indicated by code:. 1. To New Concrete: Bolt to concrete inserts. 2. To Masonry: Approved toggle-type bolts on hollow masonry units and expansion anchor

fasteners on solid masonry units. 3. To Existing Concrete: Expansion anchor fasteners. 4. Instead of expansion anchors, powder-actuated driven threaded studs provided with lock

washers and nuts may be used in existing standard-weight concrete 4 inches thick or greater. Do not use for anchorage to lightweight-aggregate concrete less than 4 inches thick.

5. To Steel: Welded threaded studs complying with AWS D1.1/D1.1M, with lock washers and nuts.

6. To Light Steel: Sheet metal screws. 7. Items Mounted on Nonstructural Building Surfaces: Mount cabinets, panelboards,

disconnect switches, control enclosures, pull and junction boxes, and other devices on slotted-channel racks attached to substrate by means that meet seismic-restraint strength and anchorage requirements.

D. Drill holes for expansion anchors in concrete at locations and to depths that avoid reinforcing bars.

3.3 INSTALLATION OF FABRICATED METAL SUPPORTS

A. Cut, fit, and place miscellaneous metal supports accurately in location, alignment, and elevation to support and anchor electrical materials and equipment.

B. Field Welding: Comply with AWS D1.1/D1.1M.

3.4 CONCRETE BASES

A. Construct concrete bases of dimensions indicated but not less than 12 inches larger in both directions than supported unit (12 inches for generator), and so anchors will be a minimum of 10 bolt diameters from edge of the base.

B. Use 5000-psi, 28-day compressive-strength concrete. Concrete materials, reinforcement, and placement requirements are specified in Section 033000 "Cast-in-Place Concrete."

C. Anchor equipment to concrete base.

Page 21: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 260529 - HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

FACILITIES BUILDING POWER GENERATOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

5

1. Place and secure anchorage devices. Use supported equipment manufacturer's setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded.

2. Install anchor bolts to elevations required for proper attachment to supported equipment. 3. Install anchor bolts according to anchor-bolt manufacturer's written instructions.

3.5 PAINTING

A. Touchup: Clean field welds and abraded areas of shop paint. Paint exposed areas immediately after erecting hangers and supports. Use same materials as used for shop painting. Comply with SSPC-PA 1 requirements for touching up field-painted surfaces.

1. Apply paint by brush or spray to provide minimum dry film thickness of 2.0 mils.

B. Touchup: Comply with requirements in for cleaning and touchup painting of field welds, bolted connections, and abraded areas of shop paint on miscellaneous metal.

C. Galvanized Surfaces: Clean welds, bolted connections, and abraded areas and apply galvanizing-repair paint to comply with ASTM A 780.

END OF SECTION 260529

Page 22: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 260533 - RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS

FACILITIES BUILDING POWER GENERATOR ADDITION Proj# ECSU-2019-5 EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

1

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Metal conduits, tubing, and fittings. 2. Nonmetal conduits, tubing, and fittings. 3. Metal wireways and auxiliary gutters. 4. Boxes, enclosures, and cabinets.

1.3 DEFINITIONS

A. ARC: Aluminum rigid conduit.

B. GRC: Galvanized rigid steel conduit.

C. IMC: Intermediate metal conduit.

1.4 ACTION SUBMITTALS

A. Product Data: For surface raceways, wireways and fittings, floor boxes, hinged-cover enclosures, and cabinets.

B. Shop Drawings: For custom enclosures and cabinets. Include plans, elevations, sections, and attachment details.

1.5 INFORMATIONAL SUBMITTALS

A. Coordination Drawings: Conduit routing plans, drawn to scale, on which the following items are shown and coordinated with each other, using input from installers of items involved:

1. Structural members in paths of conduit groups with common supports.

B. Seismic Qualification Certificates: For enclosures, cabinets, and conduit racks and their mounting provisions, including those for internal components, from manufacturer.

1. Basis for Certification: Indicate whether withstand certification is based on actual test of assembled components or on calculation.

Page 23: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 260533 - RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS

FACILITIES BUILDING POWER GENERATOR ADDITION Proj# ECSU-2019-5 EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

2

2. Dimensioned Outline Drawings of Equipment Unit: Identify center of gravity and locate and describe mounting and anchorage provisions.

3. Detailed description of equipment anchorage devices on which the certification is based and their installation requirements.

4. Detailed description of conduit support devices and interconnections on which the certification is based and their installation requirements.

C. Source quality-control reports.

PART 2 - PRODUCTS

2.1 METAL CONDUITS, TUBING, AND FITTINGS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. AFC Cable Systems, Inc. 2. Allied Tube & Conduit. 3. O-Z/Gedney. 4. Southwire Company. 5. Thomas & Betts Corporation. 6. Western Tube and Conduit Corporation. 7. Wheatland Tube Company.

B. Listing and Labeling: Metal conduits, tubing, and fittings shall be listed and labeled as defined in 2017 NFPA 70, by a qualified testing agency, and marked for intended location and application.

C. GRC: Comply with ANSI C80.1 and UL 6.

D. IMC: Comply with ANSI C80.6 and UL 1242.

E. EMT: Comply with ANSI C80.3 and UL 797.

F. FMC: Comply with UL 1; zinc-coated steel or aluminum.

G. LFMC: Flexible steel conduit with PVC jacket and complying with UL 360.

H. Fittings for Metal Conduit: Comply with NEMA FB 1 and UL 514B.

1. Conduit Fittings for Hazardous (Classified) Locations: Comply with UL 886 and NFPA 70.

2. Fittings for EMT:

a. Material: Steel or die cast. b. Type: Setscrew or compression.

Page 24: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 260533 - RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS

FACILITIES BUILDING POWER GENERATOR ADDITION Proj# ECSU-2019-5 EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

3

3. Expansion Fittings: Steel to match conduit type, complying with UL 651, rated for environmental conditions where installed, and including flexible external bonding jumper.

4. Coating for Fittings for PVC-Coated Conduit: Minimum thickness of 0.040 inch, with overlapping sleeves protecting threaded joints.

I. Joint Compound for IMC, or GRC,: Approved, as defined in 2017 NFPA 70, by authorities having jurisdiction for use in conduit assemblies, and compounded for use to lubricate and protect threaded conduit joints from corrosion and to enhance their conductivity.

2.2 NONMETALLIC CONDUITS, TUBING, AND FITTINGS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. AFC Cable Systems, Inc. 2. Anamet Electrical, Inc. 3. Arnco Corporation. 4. CANTEX Inc. 5. CertainTeed Corporation. 6. Condux International, Inc. 7. Electri-Flex Company. 8. Lamson & Sessions; Carlon Electrical Products. 9. Niedax-Kleinhuis USA, Inc. 10. RACO; Hubbell. 11. Thomas & Betts Corporation.

B. Listing and Labeling: Nonmetallic conduits, tubing, and fittings shall be listed and labeled as defined in 2017 NFPA 70, by a qualified testing agency, and marked for intended location and application.

C. ENT: Comply with NEMA TC 13 and UL 1653.

D. RNC: Type EPC-40-PVC, complying with NEMA TC 2 and UL 651 unless otherwise indicated.

E. LFNC: Comply with UL 1660.

F. Rigid HDPE: Comply with UL 651A.

G. Continuous HDPE: Comply with UL 651B.

H. Coilable HDPE: Preassembled with conductors or cables, and complying with ASTM D 3485.

I. RTRC: Comply with UL 1684A and NEMA TC 14.

J. Fittings for ENT and RNC: Comply with NEMA TC 3; match to conduit or tubing type and material.

K. Fittings for LFNC: Comply with UL 514B.

Page 25: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 260533 - RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS

FACILITIES BUILDING POWER GENERATOR ADDITION Proj# ECSU-2019-5 EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

4

2.3 METAL WIREWAYS AND AUXILIARY GUTTERS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. Cooper B-Line, Inc. 2. Hoffman. 3. Mono-Systems, Inc. 4. Square D.

B. Description: Sheet metal, complying with UL 870 and NEMA 250, Type 1 or Type 3R unless otherwise indicated, and sized according to NFPA 70.

1. Metal wireways installed outdoors shall be listed and labeled as defined in 2017 NFPA 70, by a qualified testing agency, and marked for intended location and application.

C. Fittings and Accessories: Include covers, couplings, offsets, elbows, expansion joints, adapters, hold-down straps, end caps, and other fittings to match and mate with wireways as required for complete system.

D. Wireway Covers: Screw-cover type unless otherwise indicated.

E. Finish: Manufacturer's standard enamel finish.

2.4 BOXES, ENCLOSURES, AND CABINETS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. Cooper Technologies Company; Cooper Crouse-Hinds. 2. Hubbell Incorporated. 3. Milbank Manufacturing Co. 4. O-Z/Gedney. 5. RACO; Hubbell. 6. Thomas & Betts Corporation. 7. Wiremold / Legrand.

B. General Requirements for Boxes, Enclosures, and Cabinets: Boxes, enclosures, and cabinets installed in wet locations shall be listed for use in wet locations.

C. Sheet Metal Outlet and Device Boxes: Comply with NEMA OS 1 and UL 514A.

D. Cast-Metal Outlet and Device Boxes: Comply with NEMA FB 1, ferrous alloy or aluminum, Type FD, with gasketed cover.

E. Small Sheet Metal Pull and Junction Boxes: NEMA OS 1.

F. Cast-Metal Access, Pull, and Junction Boxes: Comply with NEMA FB 1 and UL 1773, cast aluminum or galvanized, cast iron with gasketed cover.

Page 26: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 260533 - RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS

FACILITIES BUILDING POWER GENERATOR ADDITION Proj# ECSU-2019-5 EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

5

G. Device Box Dimensions: 4 inches square by 2-1/8 inches deep.

H. Cabinets:

1. NEMA 250, Type 1, Type 3R galvanized-steel box with removable interior panel and removable front, finished inside and out with manufacturer's standard enamel.

2. Hinged door in front cover with flush latch and concealed hinge. 3. Key latch to match panelboards. 4. Metal barriers to separate wiring of different systems and voltage. 5. Accessory feet where required for freestanding equipment.

PART 3 - EXECUTION

3.1 RACEWAY APPLICATION

A. Outdoors: Apply raceway products as specified below unless otherwise indicated:

1. Exposed Conduit: GRC. 2. Connection to Vibrating Equipment or Motor-Driven Equipment): LFMC, LFNC. 3. Boxes and Enclosures, Aboveground: NEMA 250, ,Type 3R.

B. Indoors: Apply raceway products as specified below unless otherwise indicated:

1. Exposed, Not Subject to Physical Damage: EMT. 2. Exposed, Not Subject to Severe Physical Damage: EMT. 3. Exposed and Subject to Severe Physical Damage: GRC. Raceway locations include the

following: a. Repair shops areas.. b. Mechanical rooms.

4. Connection to Vibrating Equipment (Electric Solenoid, or Motor-Driven Equipment): FMC, except use LFMC in damp or wet locations.

5. Damp or Wet Locations: GRC. 6. Boxes and Enclosures: NEMA 250, Type 1.

C. Minimum Raceway Size: 3/4-inch trade size.

D. Raceway Fittings: Compatible with raceways and suitable for use and location.

1. Rigid and Intermediate Steel Conduit: Use threaded rigid steel conduit fittings unless otherwise indicated. Comply with NEMA FB 2.10.

2. EMT: Use setscrew or compression, steel or cast-metal fittings. Comply with NEMA FB 2.10.

3. Flexible Conduit: Use only fittings listed for use with flexible conduit. Comply with NEMA FB 2.20.

E. Do not install aluminum conduits, boxes, or fittings in contact with concrete or earth.

F. Do not install nonmetallic conduit where ambient temperature exceeds 120 deg F

Page 27: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 260533 - RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS

FACILITIES BUILDING POWER GENERATOR ADDITION Proj# ECSU-2019-5 EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

6

3.2 INSTALLATION

A. Comply with NECA 1 and NECA 101 for installation requirements except where requirements on Drawings or in this article are stricter. Comply with NECA 102 for aluminum conduits. Comply with NFPA 70 limitations for types of raceways allowed in specific occupancies.

B. Keep raceways at least 6 inches away from parallel runs of and hot-water pipes. Install horizontal raceway runs above water piping.

C. Complete raceway installation before starting conductor installation.

D. Comply with requirements in Section 260529 "Hangers and Supports for Electrical Systems" for hangers and supports.

E. Install conduits parallel or perpendicular to building lines.

F. Support conduit within 12 inches of enclosures to which attached.

G. Threaded Conduit Joints, Exposed to Wet, Damp, Corrosive, or Outdoor Conditions: Apply listed compound to threads of raceway and fittings before making up joints. Follow compound manufacturer's written instructions.

H. Raceway Terminations at Locations Subject to Moisture or Vibration: Use insulating bushings to protect conductors including conductors smaller than No. 4 AWG.

I. Terminate threaded conduits into threaded hubs or with locknuts on inside and outside of boxes or cabinets. Install bushings on conduits up to 1-1/4-inch trade size and insulated throat metal bushings on 1-1/2-inch trade size and larger conduits terminated with locknuts. Install insulated throat metal grounding bushings on service conduits.

J. Install raceways square to the enclosure and terminate at enclosures with locknuts. Install locknuts hand tight plus 1/4 turn more.

K. Do not rely on locknuts to penetrate nonconductive coatings on enclosures. Remove coatings in the locknut area prior to assembling conduit to enclosure to assure a continuous ground path.

L. Cut conduit perpendicular to the length. For conduits 2-inch trade size and larger, use roll cutter or a guide to make cut straight and perpendicular to the length.

M. Install pull wires in empty raceways. Use polypropylene or monofilament plastic line with not less than 200-lb tensile strength. Leave at least 12 inches of slack at each end of pull wire.

N. Install raceway sealing fittings at accessible locations according to 2017 NFPA 70 and fill them with listed sealing compound. Install raceway sealing fittings according to 2017 NFPA 70.

O. Install devices to seal raceway interiors at accessible locations. Locate seals so no fittings or boxes are between the seal and the following changes of environments. Seal the interior of all raceways at the following points:

1. Where conduits pass from warm to cold locations 2. Where otherwise required by 2017 NFPA 70.

Page 28: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 260533 - RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS

FACILITIES BUILDING POWER GENERATOR ADDITION Proj# ECSU-2019-5 EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

7

P. Comply with manufacturer's written instructions for solvent welding RNC and fittings.

Q. Expansion-Joint Fittings:

1. Install in each run of aboveground RNC that is located where environmental temperature change may exceed 30 deg F and that has straight-run length that exceeds 25 feet. Install in each run of aboveground RMC and EMT conduit that is located where environmental temperature change may exceed 100 deg F and that has straight-run length that exceeds 100 feet.

2. Install type and quantity of fittings that accommodate temperature change listed for each of the following locations: a. Outdoor Locations Exposed to Direct Sunlight: 155 deg F temperature change.

3. Install fitting(s) that provide expansion and contraction for at least 0.00041 inch per foot of length of straight run per deg F of temperature change for PVC conduits. Install fitting(s) that provide expansion and contraction for at least 0.000078 inch per foot of length of straight run per deg F of temperature change for metal conduits.

4. Install expansion fittings at all locations where conduits cross building or structure expansion joints.

5. Install each expansion-joint fitting with position, mounting, and piston setting selected according to manufacturer's written instructions for conditions at specific location at time of installation. Install conduit supports to allow for expansion movement.

R. Flexible Conduit Connections: Comply with NEMA RV 3. Use a maximum of 72 inches of flexible conduit for equipment subject to vibration, noise transmission, or movement.

1. Use LFMC in damp or wet locations subject to severe physical damage. 2. Use LFMC or LFNC in damp or wet locations not subject to severe physical damage.

S. Mount boxes at heights indicated on Drawings. If mounting heights of boxes are not individually indicated, give priority to ADA requirements. Install boxes with height measured to center of box unless otherwise indicated.

T. Locate boxes so that cover or plate will not span different building finishes.

U. Fasten junction and pull boxes to or support from building structure. Do not support boxes by conduits.

3.3 SLEEVE AND SLEEVE-SEAL INSTALLATION FOR ELECTRICAL PENETRATIONS

A. Install sleeves and sleeve seals at penetrations of exterior wall assemblies.

3.4 FIRESTOPPING

A. Install firestopping at penetrations of fire-rated wall assemblies. Comply with requirements in Section 078413 "Penetration Firestopping."

Page 29: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 260533 - RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS

FACILITIES BUILDING POWER GENERATOR ADDITION Proj# ECSU-2019-5 EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

8

3.5 PROTECTION

A. Protect coatings, finishes, and cabinets from damage and deterioration.

1. Repair damage to galvanized finishes with zinc-rich paint recommended by manufacturer.

END OF SECTION 260533

Page 30: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 260553 - IDENTIFICATION FOR ELECTRICAL SYSTEMS

FACILITIES BUILDING POWER GENERATOR ADDITION #ECSU-2019-5 EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

1

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Identification for raceways. 2. Warning labels and signs. 3. Instruction signs. 4. Equipment identification labels. 5. Miscellaneous identification products.

1.2 ACTION SUBMITTALS

A. Product Data: For each electrical identification product indicated.

1.3 QUALITY ASSURANCE

A. Comply with ANSI A13.1.

B. Comply with NFPA 70.

C. Comply with 29 CFR 1910.144 and 29 CFR 1910.145.

D. Comply with ANSI Z535.4 for safety signs and labels.

E. Adhesive-attached labeling materials, including label stocks, laminating adhesives, and inks used by label printers, shall comply with UL 969.

PART 2 - PRODUCTS

2.1 POWER RACEWAY IDENTIFICATION MATERIALS

A. Comply with ANSI A13.1 for minimum size of letters for legend and for minimum length of color field for each raceway size.

B. Colors for Raceways Carrying Circuits at 600 V or Less:

1. Black letters on an orange field. 2. Legend: Indicate voltage and system or service type.

C. Self-Adhesive Vinyl Labels for Raceways Carrying Circuits at 600 V or Less: Preprinted, flexible label laminated with a clear, weather- and chemical-resistant coating and matching wraparound adhesive tape for securing ends of legend label.

Page 31: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 260553 - IDENTIFICATION FOR ELECTRICAL SYSTEMS

FACILITIES BUILDING POWER GENERATOR ADDITION #ECSU-2019-5 EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

2

D. Snap-Around Labels for Raceways Carrying Circuits at 600 V or Less: Slit, pretensioned, flexible, preprinted, color-coded acrylic sleeve, with diameter sized to suit diameter of raceway or cable it identifies and to stay in place by gripping action.

E. Snap-Around, Color-Coding Bands for Raceways Carrying Circuits at 600 V or Less: Slit, pretensioned, flexible, solid-colored acrylic sleeve, 2 inches long, with diameter sized to suit diameter of raceway or cable it identifies and to stay in place by gripping action.

2.2 WARNING LABELS AND SIGNS

A. Comply with NFPA 70 and 29 CFR 1910.145.

B. Self-Adhesive Warning Labels: Factory-printed, multicolor, pressure-sensitive adhesive labels, configured for display on front cover, door, or other access to equipment unless otherwise indicated.

C. Baked-Enamel Warning Signs:

1. Preprinted aluminum signs, punched or drilled for fasteners, with colors, legend, and size required for application.

2. 1/4-inch grommets in corners for mounting. 3. Nominal size, 7 by 10 inches.

D. Warning label and sign shall include, but are not limited to, the following legends:

1. Multiple Power Source Warning: "DANGER - ELECTRICAL SHOCK HAZARD - EQUIPMENT HAS MULTIPLE POWER SOURCES."

2. Workspace Clearance Warning: "WARNING - OSHA REGULATION - AREA IN FRONT OF ELECTRICAL EQUIPMENT MUST BE KEPT CLEAR FOR 36 INCHES ."

2.3 INSTRUCTION SIGNS

A. Engraved, laminated acrylic or melamine plastic, minimum 1/16 inch thick for signs up to 20 sq. inches and 1/8 inch thick for larger sizes.

1. Engraved legend with black letters on white face. 2. Punched or drilled for mechanical fasteners. 3. Framed with mitered acrylic molding and arranged for attachment at applicable

equipment.

B. Adhesive Film Label: Machine printed, in black, by thermal transfer or equivalent process. Minimum letter height shall be 3/8 inch.

Page 32: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 260553 - IDENTIFICATION FOR ELECTRICAL SYSTEMS

FACILITIES BUILDING POWER GENERATOR ADDITION #ECSU-2019-5 EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

3

2.4 EQUIPMENT IDENTIFICATION LABELS

A. Adhesive Film Label with Clear Protective Overlay: Machine printed, in black, by thermal transfer or equivalent process. Minimum letter height shall be 3/8 inch. Overlay shall provide a weatherproof and UV-resistant seal for label.

B. Self-Adhesive, Engraved, Laminated Acrylic or Melamine Label: Adhesive backed, with white letters on a dark-gray background. Minimum letter height shall be 3/8 inch.

C. Stenciled Legend: In nonfading, waterproof, black ink or paint. Minimum letter height shall be 1 inch.

2.5 MISCELLANEOUS IDENTIFICATION PRODUCTS

A. Paint: Comply with requirements in painting Sections for paint materials and application requirements. Select paint system applicable for surface material and location (exterior or interior).

B. Fasteners for Labels and Signs: Self-tapping, stainless-steel screws or stainless-steel machine screws with nuts and flat and lock washers.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Location: Install identification materials and devices at locations for most convenient viewing without interference with operation and maintenance of equipment.

B. Apply identification devices to surfaces that require finish after completing finish work.

C. Self-Adhesive Identification Products: Clean surfaces before application, using materials and methods recommended by manufacturer of identification device.

D. Attach signs and plastic labels that are not self-adhesive type with mechanical fasteners appropriate to the location and substrate.

E. Painted Identification: Comply with requirements in painting Sections for surface preparation and paint application.

3.2 IDENTIFICATION SCHEDULE

A. Accessible Raceways and Metal-Clad Cables, 600 V or Less, for Service,or Feeder. More Than 30 A, and 120 V to ground: Install labels at 30-foot maximum intervals.

B. Accessible Raceways and Cables within Buildings: Identify the covers of each junction and pull box of the following systems with self-adhesive vinyl labels with the wiring system legend and system voltage. System legends shall be as follows:

Page 33: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 260553 - IDENTIFICATION FOR ELECTRICAL SYSTEMS

FACILITIES BUILDING POWER GENERATOR ADDITION #ECSU-2019-5 EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

4

1. Power.

C. Install instructional sign including the color-code for grounded and ungrounded conductors using adhesive-film-type labels.

D. Conductors to Be Extended in the Future: Attach write-on tags to conductors and list source.

E. Auxiliary Electrical Systems Conductor Identification: Identify field-installed alarm, control, and signal connections.

1. Identify conductors, cables, and terminals in enclosures and at junctions, terminals, and pull points. Identify by system and circuit designation.

2. Use system of marker tape designations that is uniform and consistent with system used by manufacturer for factory-installed connections.

3. Coordinate identification with Project Drawings, manufacturer's wiring diagrams, and the Operation and Maintenance Manual.

F. Workspace Indication: Install floor marking tape to show working clearances in the direction of access to live parts. Workspace shall be as required by NFPA 70 and 29 CFR 1926.403 unless otherwise indicated.

G. Warning Labels for Indoor Cabinets, Boxes, and Enclosures for Power: Self-adhesive warning labels.

1. Comply with 29 CFR 1910.145. 2. Identify system voltage with black letters on an orange background. 3. Apply to exterior of door, cover, or other access. 4. For equipment with multiple power or control sources, apply to door or cover of

equipment including, but not limited to, the following:

a. Power transfer switches.

H. Operating Instruction Signs: Install instruction signs to facilitate proper operation and maintenance of electrical systems and items to which they connect. Install instruction signs with approved legend where instructions are needed for system or equipment operation.

I. Emergency Operating Instruction Signs: Install instruction signs with white legend on a red background with minimum 3/8-inch- high letters for emergency instructions at equipment used for power transfer .

J. Equipment Identification Labels: On each unit of equipment, install unique designation label that is consistent with wiring diagrams, schedules, and the Operation and Maintenance Manual. Apply labels to disconnect switches and protection equipment, central or master units, control panels, control stations, terminal cabinets, and racks of each system. Systems include power, li control, communication, signal, monitoring, and alarm systems unless equipment is provided with its own identification.

1. Labeling Instructions:

a. Indoor Equipment: Adhesive film label with clear protective overlay or Self-adhesive, engraved, laminated acrylic or melamine label. Unless otherwise

Page 34: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 260553 - IDENTIFICATION FOR ELECTRICAL SYSTEMS

FACILITIES BUILDING POWER GENERATOR ADDITION #ECSU-2019-5 EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

5

indicated, provide a single line of text with 1/2-inch- high letters on 1-1/2-inch- high label; where two lines of text are required, use labels 2 inches high.

b. Outdoor Equipment: Stenciled legend 4 inches high. c. Elevated Components: Increase sizes of labels and letters to those appropriate for

viewing from the floor. d. Unless provided with self-adhesive means of attachment, fasten labels with

appropriate mechanical fasteners that do not change the NEMA or NRTL rating of the enclosure.

END OF SECTION 260553

Page 35: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 263213 - ENGINE GENERATORS

FACILITIES BUILDING POWER GENERATOR ADDITION Proj#ECSU-2019-5 EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

1

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes packaged engine-generator set for standby power supply, supplied by ECSU and installed by this contractor, with the following features:

1. Diesel engine. 2. Unit-mounted cooling system. 3. Unit-mounted control and monitoring. 4. Outdoor enclosure.

B. See Section 263600 "Transfer Switches" for transfer switches including sensors and relays to initiate automatic-starting and -stopping signals for engine-generator sets.

1.2 INFORMATIONAL SUBMITTALS

A. Source quality-control test reports.

B. Field quality-control test reports.

1.3 CLOSEOUT SUBMITTALS

A. Operation and maintenance data.

1.4 QUALITY ASSURANCE

A. Installer Qualifications: Manufacturer's authorized representative who is trained and approved for installation of units required for this Project.

B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in 2017 NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use.

C. Comply with ASME B15.1.

D. Comply with NFPA 37.

E. Comply with2017 NFPA 70.

F. Comply with NFPA 110 requirements for standby power supply system.

G. Comply with UL 2200.

Page 36: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 263213 - ENGINE GENERATORS

FACILITIES BUILDING POWER GENERATOR ADDITION Proj#ECSU-2019-5 EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

2

1.5 PROJECT CONDITIONS

A. Environmental Conditions: Engine-generator system shall withstand the following environmental conditions without mechanical or electrical damage or degradation of performance capability: 1. Altitude: Sea level to 1000 feet .

1.6 WARRANTY

A. Warranty: Manufacturer's standard form in which manufacturer agrees to repair or replace components of packaged engine generators and associated auxiliary components that fail in materials or workmanship within specified warranty period.

1. Warranty Period: 18 months (only for any new components) from date of Substantial Completion.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. The generator is existing and shall be supplied by the ECSU. This contractor scope of work includes installation and all work necessary to make the generator and the standby system operational.

B. The existing unit is manufactured by Onan/Cummins Power Generation; Model no. 250 DFBE. Serial no K 910436596

2.2 ENGINE-GENERATOR SET

A. Factory-assembled and -tested, engine-generator set.

B. Capacities and Characteristics:

1. Power Output Ratings: 250 kW 2. Output Connections: Three-phase, four wire.

2.3 ENGINE

A. Fuel: Fuel oil,

2.4 FUEL OIL STORAGE

A. Comply with NFPA 30.

B. Base-Mounted Fuel Oil Tank: Factory installed and piped, complying with UL 142 fuel oil tank. Features include the following:

Page 37: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 263213 - ENGINE GENERATORS

FACILITIES BUILDING POWER GENERATOR ADDITION Proj#ECSU-2019-5 EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

3

1. Tank level indicator. 2. Capacity: Fuel capacity existing. 3. Vandal-resistant fill cap. 4. Containment Provisions: Comply with requirements of authorities having jurisdiction.

2.5 CONTROL AND MONITORING

A. Automatic Starting System Sequence of Operation: When mode-selector switch on the control and monitoring panel is in the automatic position, remote-control contacts in one or more separate automatic transfer switches initiate starting and stopping of generator set. When mode-selector switch is switched to the on position, generator set starts. The off position of same switch initiates generator-set shutdown. When generator set is running, specified system or equipment failures or derangements automatically shut down generator set and initiate alarms.

B. Configuration: Operating and safety indications, protective devices, basic system controls, and engine gages shall be grouped in a common control and monitoring panel mounted on the generator set. Mounting method shall isolate the control panel from generator-set vibration.

C. Indicating and Protective Devices and Controls: As required by NFPA 110 for Level 2 system, and the following:

1. AC voltmeter. 2. AC ammeter. 3. AC frequency meter. 4. DC voltmeter (alternator battery charging). 5. Engine-coolant temperature gage. 6. Engine lubricating-oil pressure gage. 7. Running-time meter. 8. Ammeter-voltmeter, phase-selector switch(es). 9. Generator-voltage adjusting rheostat. 10. Fuel tank derangement alarm. 11. Fuel tank high-level shutdown of fuel supply alarm. 12. Generator overload.

D. Supporting Items: Include sensors, transducers, terminals, relays, and other devices and include wiring required to support specified items. Locate sensors and other supporting items on engine or generator, unless otherwise indicated.

2.6 VIBRATION ISOLATION DEVICES

A. Restrained Spring Isolators: Freestanding, steel, open-spring isolators with seismic restraint.

1. Housing: Steel with resilient vertical-limit stops to prevent spring extension due to wind loads or if weight is removed; factory-drilled baseplate bonded to 1/4-inch-thick, elastomeric isolator pad attached to baseplate underside; and adjustable equipment mounting and leveling bolt that acts as blocking during installation.

2. Outside Spring Diameter: Not less than 80 percent of compressed height of the spring at rated load.

3. Minimum Additional Travel: 50 percent of required deflection at rated load.

Page 38: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 263213 - ENGINE GENERATORS

FACILITIES BUILDING POWER GENERATOR ADDITION Proj#ECSU-2019-5 EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

4

4. Lateral Stiffness: More than 80 percent of rated vertical stiffness. 5. Overload Capacity: Support 200 percent of rated load, fully compressed, without

deformation or failure.

2.7 SOURCE QUALITY CONTROL

A. Prototype Testing: Factory test engine-generator set using same engine model, constructed of identical or equivalent components and equipped with identical or equivalent accessories.

1. Tests: Comply with NFPA 110, Level 1 Energy Converters and with IEEE 115. 2. Report factory test results within 10 days of completion of test.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Comply with packaged engine-generator manufacturers' written installation and alignment instructions and with NFPA 110.

B. Install packaged engine generator to provide access, without removing connections or accessories, for periodic maintenance.

C. Install packaged engine generator with restrained spring isolators having a minimum deflection of 1 inch on 4-inch- high concrete base. Secure sets to anchor bolts installed in concrete bases. Concrete base construction is specified in Section 033000.

D. Electrical Wiring: Install electrical devices furnished by equipment manufacturers but not specified to be factory mounted.

E. Piping installation requirements are specified in other Sections. Drawings indicate general arrangement of piping and specialties.

F. Connect fuel piping to engines with a gate valve and union and flexible connector.

G. Ground equipment according to Section 260526 "Grounding and Bonding for Electrical Systems."

H. Connect wiring according to Section 260519 "Low-Voltage Electrical Power Conductors and Cables."

I. Identify system components according to Section 260553 "Identification for Electrical Systems."

3.2 FIELD QUALITY CONTROL

A. Perform tests and inspections and prepare test reports.

B. Tests and Inspections:

Page 39: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 263213 - ENGINE GENERATORS

FACILITIES BUILDING POWER GENERATOR ADDITION Proj#ECSU-2019-5 EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

5

1. Perform tests recommended by manufacturer and each electrical test and visual and mechanical inspection[ (except those indicated to be optional)] for "AC Generators and for Emergency Systems" specified in NETA Acceptance Testing Specification. Certify compliance with test parameters.

2. NFPA 110 Acceptance Tests: Perform tests required by NFPA 110 that are additional to those specified here including, but not limited to, single-step full-load pickup test.

3. Battery Tests: Equalize charging of battery cells according to manufacturer's written instructions. Record individual cell voltages.

a. Measure charging voltage and voltages between available battery terminals for full-charging and float-charging conditions. Check electrolyte level and specific gravity under both conditions.

b. Test for contact integrity of all connectors. Perform an integrity load test and a capacity load test for the battery.

c. Verify acceptance of charge for each element of the battery after discharge. d. Verify that measurements are within manufacturer's specifications.

4. Battery-Charger Tests: Verify specified rates of charge for both equalizing and float-charging conditions.

5. System Integrity Tests: Methodically verify proper installation, connection, and integrity of each element of engine-generator system before and during system operation. Check for air, exhaust, and fluid leaks.

C. Coordinate tests with tests for transfer switches and run them concurrently.

D. Leak Test: After installation, charge system and test for leaks. Repair leaks and retest until no leaks exist.

E. Operational Test: After electrical circuitry has been energized, start units to confirm proper motor rotation and unit operation.

F. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and equipment.

G. Remove and replace malfunctioning units and retest as specified above.

H. Retest: Correct deficiencies identified by tests and observations and retest until specified requirements are met.

I. Report results of tests and inspections in writing. Record adjustable relay settings and measured insulation resistances, time delays, and other values and observations. Attach a label or tag to each tested component indicating satisfactory completion of tests.

3.3 DEMONSTRATION

A. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust, operate, and maintain packaged engine generators.

END OF SECTION 263213

Page 40: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 263600 - TRANSFER SWITCHES

FACILITIES BUILDING POWER GENERATOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

1

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes automatic transfer switches rated 600 V and less.

1.2 INFORMATIONAL SUBMITTALS

A. Field quality-control reports.

1.3 CLOSEOUT SUBMITTALS

A. Operation and maintenance data.

1.4 QUALITY ASSURANCE

A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in 2017 NFPA 70, by a qualified testing agency, and marked for intended location and application.

B. Comply with NEMA ICS 1.

C. Comply with 2017 NFPA 70.

D. Comply with NFPA 99.

E. Comply with NFPA 110.

F. Comply with UL 1008 unless requirements of these Specifications are stricter.

PART 2 - PRODUCTS

2.1 MANUFACTURED UNITS

A. Contactor Transfer Switches:

1. The ATS switch is EXISTING and will be supplied by ECSU. This contractor to move the unit to the site from the Communication Building. The installation shall be in the scope of work of this contractor. a. Manufacturer: Cummins Power Generation;. b. Model : OTPCD, Serial #B100098375

Page 41: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 263600 - TRANSFER SWITCHES

FACILITIES BUILDING POWER GENERATOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

2

2.2 GENERAL TRANSFER-SWITCH PRODUCT REQUIREMENTS

A. Indicated Current Ratings: Apply as defined in UL 1008 for continuous loading and total

2.3 AUTOMATIC TRANSFER SWITCHES

A. Comply with Level 1 equipment according to NFPA 110.

B. Switching Arrangement: Double-throw type, incapable of pauses or intermediate position stops during normal functioning, unless otherwise indicated.

C. Signal-Before-Transfer Contacts: A set of normally open/normally closed dry contacts operates in advance of retransfer to normal source. Interval is adjustable from 1 to 30 seconds.

D. In-Phase Monitor: Factory-wired, internal relay controls transfer so it occurs only when the two sources are synchronized in phase.

E. Motor Disconnect and Timing Relay: Controls designate starters so they disconnect motors before transfer and reconnect them selectively at an adjustable time interval after transfer. Time delay for reconnecting individual motor loads is adjustable between 1 and 60 seconds, and settings are as indicated.

F. Programmed Neutral Switch Position: Switch operator has a programmed neutral position arranged to provide a midpoint between the two working switch positions, with an intentional, time-controlled pause at midpoint during transfer.

G. Automatic Transfer (existing)-Switch Features:

1. Undervoltage Sensing for Each Phase of Normal Source: Sense low phase-to-ground voltage on each phase. Pickup voltage shall be adjustable from 85 to 100 percent of nominal, and dropout voltage is adjustable from 75 to 98 percent of pickup value. Factory set for pickup at 90 percent and dropout at 85 percent.

2. Adjustable Time Delay: For override of normal-source voltage sensing to delay transfer and engine start signals. Adjustable from zero to six seconds, and factory set for one second.

3. Voltage/Frequency Lockout Relay: Prevent premature transfer to generator. Pickup voltage shall be adjustable from 85 to 100 percent of nominal. Factory set for pickup at 90 percent. Pickup frequency shall be adjustable from 90 to 100 percent of nominal. Factory set for pickup at 95 percent.

4. Time Delay for Retransfer to Normal Source: Adjustable from 0 to 30 minutes, and factory set for 10 minutes to automatically defeat delay on loss of voltage or sustained undervoltage of emergency source, provided normal supply has been restored.

5. Test Switch: Simulate normal-source failure. 6. Switch-Position Pilot Lights: Indicate source to which load is connected. 7. Source-Available Indicating Lights: Supervise sources via transfer-switch normal- and

emergency-source sensing circuits.

a. Normal Power Supervision: Green light with nameplate engraved "Normal Source Available."

Page 42: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 263600 - TRANSFER SWITCHES

FACILITIES BUILDING POWER GENERATOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

3

b. Emergency Power Supervision: Red light with nameplate engraved "Emergency Source Available."

8. Unassigned Auxiliary Contacts: Two normally open, single-pole, double-throw contacts for each switch position, rated 10 A at 240-V ac.

9. Transfer Override Switch: Overrides automatic retransfer control so automatic transfer switch will remain connected to emergency power source regardless of condition of normal source. Pilot light indicates override status.

10. Engine Starting Contacts: One isolated and normally closed, and one isolated and normally open; rated 10 A at 32-V dc minimum.

11. Engine Shutdown Contacts: Instantaneous; shall initiate shutdown sequence at remote engine-generator controls after retransfer of load to normal source.

12. Engine Shutdown Contacts: Time delay adjustable from zero to five minutes, and factory set for five minutes. Contacts shall initiate shutdown at remote engine-generator controls after retransfer of load to normal source.

13. Engine-Generator Exerciser: Solid-state, programmable-time switch starts engine generator and transfers load to it from normal source for a preset time, then retransfers and shuts down engine after a preset cool-down period. Initiates exercise cycle at preset intervals adjustable from 7 to 30 days. Running periods are adjustable from 10 to 30 minutes. Factory settings are for 7-day exercise cycle, 20-minute running period, and 5-minute cool-down period. Exerciser features include the following:

a. Exerciser Transfer Selector Switch: Permits selection of exercise with and without load transfer.

b. Push-button programming control with digital display of settings. c. Integral battery operation of time switch when normal control power is not

available.

2.4 SOURCE QUALITY CONTROL

A. Factory test and inspect components, assembled switches, and associated equipment. Ensure proper operation. Check transfer time and voltage, frequency, and time-delay settings for compliance with specified requirements. Perform dielectric strength test complying with NEMA ICS 1.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Design each fastener and support to carry load indicated by seismic requirements.

B. Wall-Mounting Switch: Anchor to wall by bolting.

C. Identify components according to Section 260553 "Identification for Electrical Systems."

D. Set field-adjustable intervals and delays, relays, and engine exerciser clock.

Page 43: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 263600 - TRANSFER SWITCHES

FACILITIES BUILDING POWER GENERATOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

4

3.2 CONNECTIONS

A. Ground equipment according to Section 260526 "Grounding and Bonding for Electrical Systems."

B. Connect wiring according to Section 260519 "Low-Voltage Electrical Power Conductors and Cables."

C. Install control wiring between the generator and the ATS switch according to the manufacturer requirements.

3.3 FIELD QUALITY CONTROL

A. Perform the following tests and inspections

1. After installing equipment and after electrical circuitry has been energized, test for compliance with requirements.

2. Perform each visual and mechanical inspection and electrical test stated in NETA Acceptance Testing Specification. Certify compliance with test parameters.

3. Measure insulation resistance phase-to-phase and phase-to-ground with insulation-resistance tester. Use test voltages and procedure recommended by manufacturer. Comply with manufacturer's specified minimum resistance.

a. Check for electrical continuity of circuits and for short circuits. b. Inspect for physical damage, proper installation and connection, and integrity of

barriers, covers, and safety features. c. Verify that manual transfer warnings are properly placed. d. Perform manual transfer operation.

4. After energizing circuits, demonstrate interlocking sequence and operational function for each switch at least three times.

a. Simulate power failures of normal source to automatic transfer switches and of emergency source with normal source available.

b. Simulate loss of phase-to-ground voltage for each phase of normal source. c. Verify time-delay settings. d. Verify pickup and dropout voltages by data readout or inspection of control

settings. e. Verify proper sequence and correct timing of automatic engine starting, transfer

time delay, retransfer time delay on restoration of normal power, and engine cool-down and shutdown.

5. Ground-Fault Tests: Coordinate with testing of ground-fault protective devices for power delivery from both sources.

a. Verify grounding connections and locations and ratings of sensors.

B. Coordinate tests with tests of generator and run them concurrently.

Page 44: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 263600 - TRANSFER SWITCHES

FACILITIES BUILDING POWER GENERATOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

5

C. Report results of tests and inspections in writing. Record adjustable relay settings and measured insulation and contact resistances and time delays. Attach a label or tag to each tested component indicating satisfactory completion of tests.

D. Remove and replace malfunctioning units and retest as specified above.

E. Prepare test and inspection reports.

3.4 DEMONSTRATION

A. Train Owner's maintenance personnel to adjust, operate, and maintain transfer switches and related equipment as specified below.

B. Coordinate this training with that for generator equipment.

END OF SECTION 263600

Page 45: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 312000 - EARTH MOVING

FACILITIES BUILDING POWER GENERATOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

1

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Preparing subgrades for slabs-on-grade. 2. Excavating and backfilling for structures. 3. Drainage course for concrete slabs-on-grade. 4. Subbase course and base course for asphalt paving.

1.2 DEFINITIONS

A. Backfill: Soil material used to fill an excavation.

1. Initial Backfill: Backfill placed beside and over pipe in a trench, including haunches to support sides of pipe.

2. Final Backfill: Backfill placed over initial backfill to fill a trench.

B. Base Course: Aggregate layer placed between the subbase course and hot-mix asphalt paving.

C. Bedding Course: Aggregate layer placed over the excavated subgrade in a trench before laying pipe.

D. Borrow Soil: Satisfactory soil imported from off-site for use as fill or backfill.

E. Drainage Course: Aggregate layer supporting the slab-on-grade that also minimizes upward capillary flow of pore water.

F. Excavation: Removal of material encountered above subgrade elevations and to lines and dimensions indicated.

1. Authorized Additional Excavation: Excavation below subgrade elevations or beyond indicated lines and dimensions as directed by Engineer. Authorized additional excavation and replacement material will be paid for according to Contract provisions for changes in the Work.

2. Unauthorized Excavation: Excavation below subgrade elevations or beyond indicated lines and dimensions without direction by Engineer. Unauthorized excavation, as well as remedial work directed by Engineer, shall be without additional compensation.

G. Fill: Soil materials used to raise existing grades.

H. Structures: Buildings, footings, foundations, retaining walls, slabs, tanks, curbs, mechanical and electrical appurtenances, or other man-made stationary features constructed above or below the ground surface.

Page 46: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 312000 - EARTH MOVING

FACILITIES BUILDING POWER GENERATOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

2

I. Subbase Course: Aggregate layer placed between the subgrade and base course for hot-mix asphalt pavement, or aggregate layer placed between the subgrade and a cement concrete pavement or a cement concrete or hot-mix asphalt walk.

J. Subgrade: Uppermost surface of an excavation or the top surface of a fill or backfill immediately below subbase, drainage fill, drainage course, or topsoil materials.

K. Utilities: On-site underground pipes, conduits, ducts, and cables, as well as underground services within buildings.

1.3 QUALITY ASSURANCE

A. Preexcavation Conference: Conduct conference at Project site.

1.4 PROJECT CONDITIONS

A. Utility Locator Service: Notify utility locator service for area where Project is located before beginning earth moving operations.

PART 2 - PRODUCTS

2.1 SOIL MATERIALS

A. General: Provide borrow soil materials when sufficient satisfactory soil materials are not available from excavations.

B. Satisfactory Soils: Soil Classification Groups GW, GP, GM, SW, SP, and SM according to ASTM D 2487, or a combination of these groups; free of rock or gravel larger than 3 inches in any dimension, debris, waste, frozen materials, vegetation, and other deleterious matter.

C. Unsatisfactory Soils: Soil Classification Groups GC, SC, CL, ML, OL, CH, MH, OH, and PT according to ASTM D 2487, or a combination of these groups.

1. Unsatisfactory soils also include satisfactory soils not maintained within 2 percent of optimum moisture content at time of compaction.

D. Subbase Material: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D 2940; with at least 90 percent passing a 1-1/2-inch sieve and not more than 12 percent passing a No. 200 sieve.

E. Base Course: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D 2940; with at least 95 percent passing a 1-1/2-inch sieve and not more than 8 percent passing a No. 200 sieve.

F. Engineered Fill: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D 2940; with at least 90 percent passing a 1-1/2-inch sieve and not more than 12 percent passing a No. 200 sieve.

Page 47: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 312000 - EARTH MOVING

FACILITIES BUILDING POWER GENERATOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

3

G. Bedding Course: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D 2940; except with 100 percent passing a 1-inch sieve and not more than 8 percent passing a No. 200 sieve.

H. Drainage Course: Narrowly graded mixture of [washed ]crushed stone, or crushed or uncrushed gravel; ASTM D 448; coarse-aggregate grading Size 57; with 100 percent passing a 1-1/2-inch sieve and 0 to 5 percent passing a No. 8 sieve.

PART 3 - EXECUTION

3.1 PREPARATION

A. Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by earth moving operations.

B. Protect and maintain erosion and sedimentation controls during earth moving operations.

C. Protect subgrades and foundation soils from freezing temperatures and frost. Remove temporary protection before placing subsequent materials.

3.2 EXCAVATION, GENERAL

A. Unclassified Excavation: Excavate to subgrade elevations regardless of the character of surface and subsurface conditions encountered. Unclassified excavated materials may include rock, soil materials, and obstructions. No changes in the Contract Sum or the Contract Time will be authorized for rock excavation or removal of obstructions.

1. If excavated materials intended for fill and backfill include unsatisfactory soil materials and rock, replace with satisfactory soil materials.

3.3 EXCAVATION FOR STRUCTURES

A. Excavate to indicated elevations and dimensions within a tolerance of plus or minus 1 inch. If applicable, extend excavations a sufficient distance from structures for placing and removing concrete formwork, for installing services and other construction, and for inspections.

1. Excavations for Footings and Foundations: Do not disturb bottom of excavation. Excavate by hand to final grade just before placing concrete reinforcement. Trim bottoms to required lines and grades to leave solid base to receive other work.

3.4 EXCAVATION FOR PAVEMENTS

A. Excavate surfaces under pavements to indicated lines, cross sections, elevations, and subgrades.

Page 48: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 312000 - EARTH MOVING

FACILITIES BUILDING POWER GENERATOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

4

3.5 SUBGRADE INSPECTION

A. Proof-roll subgrade below the slabs and pavements with a pneumatic-tired dump truck to identify soft pockets and areas of excess yielding. Do not proof-roll wet or saturated subgrades.

B. Reconstruct subgrades damaged by freezing temperatures, frost, rain, accumulated water, or construction activities, as directed by Engineer, without additional compensation.

3.6 UNAUTHORIZED EXCAVATION

A. Fill unauthorized excavation under foundations or footings by extending bottom elevation of concrete foundation or footing to excavation bottom, without altering top elevation. Lean concrete fill, with 28-day compressive strength of 2500 psi, may be used when approved by Engineer.

1. Fill unauthorized excavations under other construction, pipe, or conduit as directed by Engineer.

3.7 STORAGE OF SOIL MATERIALS

A. Stockpile borrow soil materials and excavated satisfactory soil materials without intermixing. Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust.

1. Stockpile soil materials away from edge of excavations.

3.8 SOIL FILL

A. Plow, scarify, bench, or break up sloped surfaces steeper than 1 vertical to 4 horizontal so fill material will bond with existing material.

B. Place and compact fill material in layers to required elevations as follows: 1. Under pavements, use satisfactory soil material. 2. Under slabs, use engineered fill. 3. Under footings and foundations, use engineered fill.

3.9 SOIL MOISTURE CONTROL

A. Uniformly moisten or aerate subgrade and each subsequent fill or backfill soil layer before compaction to within 2 percent of optimum moisture content.

1. Do not place backfill or fill soil material on surfaces that are muddy, frozen, or contain frost or ice.

2. Remove and replace, or scarify and air dry, otherwise satisfactory soil material that exceeds optimum moisture content by 2 percent and is too wet to compact to specified dry unit weight.

Page 49: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 312000 - EARTH MOVING

FACILITIES BUILDING POWER GENERATOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

5

3.10 COMPACTION OF SOIL BACKFILLS AND FILLS

A. Place backfill and fill soil materials in layers not more than 8 inches in loose depth for material compacted by heavy compaction equipment, and not more than 4 inches in loose depth for material compacted by hand-operated tampers.

B. Place backfill and fill soil materials evenly on all sides of structures to required elevations, and uniformly along the full length of each structure.

C. Compact soil materials to not less than the following percentages of maximum dry unit weight according to ASTM D 1557:

1. Under structures, building slabs, steps, and pavements, scarify and recompact top 12 inches of existing subgrade and each layer of backfill or fill soil material at 95 percent.

3.11 GRADING

A. General: Uniformly grade areas to a smooth surface, free of irregular surface changes. Comply with compaction requirements and grade to cross sections, lines, and elevations indicated.

B. Site Rough Grading: Slope grades to direct water away from buildings and to prevent ponding. Finish subgrades to required elevations within the following tolerances:

1. Pavements: Plus or minus 1/2 inch.

3.12 SUBBASE AND BASE COURSES UNDER PAVEMENTS AND WALKS

A. Place subbase course and base course on subgrades free of mud, frost, snow, or ice.

B. On prepared subgrade, place subbase course and base course under pavements as follows:

1. Shape subbase course and base course to required crown elevations and cross-slope grades.

2. Place subbase course and base course that exceeds 6 inches in compacted thickness in layers of equal thickness, with no compacted layer more than 6 inches thick or less than 3 inches thick.

3. Compact subbase course and base course at optimum moisture content to required grades, lines, cross sections, and thickness to not less than 95 percent of maximum dry unit weight according to ASTM D 1557.

3.13 DRAINAGE COURSE UNDER CONCRETE SLABS-ON-GRADE

A. Place drainage course on subgrades free of mud, frost, snow, or ice.

B. On prepared subgrade, place and compact drainage course under cast-in-place concrete slabs-on-grade as follows:

Page 50: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 312000 - EARTH MOVING

FACILITIES BUILDING POWER GENERATOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC , CT

6

1. Place drainage course that exceeds 6 inches in compacted thickness in layers of equal thickness, with no compacted layer more than 6 inches thick or less than 3 inches thick.

2. Compact each layer of drainage course to required cross sections and thicknesses to not less than 95 percent of maximum dry unit weight according to ASTM D 698.

3.14 FIELD QUALITY CONTROL

A. Testing Agency: Owner will engage a qualified geotechnical engineering testing agency to perform tests and inspections.

B. Allow testing agency to inspect and test subgrades and each fill or backfill layer. Proceed with subsequent earth moving only after test results for previously completed work comply with requirements.

C. When testing agency reports that subgrades, fills, or backfills have not achieved degree of compaction specified, scarify and moisten or aerate, or remove and replace soil materials to depth required; recompact and retest until specified compaction is obtained.

3.15 PROTECTION

A. Protecting Graded Areas: Protect newly graded areas from traffic, freezing, and erosion. Keep free of trash and debris.

B. Repair and reestablish grades to specified tolerances where completed or partially completed surfaces become eroded, rutted, settled, or where they lose compaction due to subsequent construction operations or weather conditions.

C. Where settling occurs before Project correction period elapses, remove finished surfacing, backfill with additional soil material, compact, and reconstruct surfacing.

1. Restore appearance, quality, and condition of finished surfacing to match adjacent work, and eliminate evidence of restoration to greatest extent possible.

3.16 DISPOSAL OF SURPLUS AND WASTE MATERIALS

A. Remove surplus satisfactory soil and waste materials, including unsatisfactory soil, trash, and debris, and legally dispose of them off Owner's property.

END OF SECTION 312000

Page 51: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 321216 - ASPHALT PAVING

FACILITIES BUILDING POWER GENERATIOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC, CT

#ECSU-2019-5

1

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes: 1. Hot-mix asphalt paving (pavement replacement around the new generator pad).

B. Related Requirements:

1. Section 312000 "Earth Moving" for subgrade preparation, fill material, unbound-aggregate subbase and base courses, and aggregate pavement shoulders.

1.2 ACTION SUBMITTALS

A. Product Data: For each type of product.

1.3 INFORMATIONAL SUBMITTALS

A. Material Certificates: For each paving material. Include statement that mixes containing recycled materials will perform equal to mixes produced from all new materials.

1.4 QUALITY ASSURANCE

A. Manufacturer Qualifications: A paving-mix manufacturer registered with and approved by the DOT of the State of Connecticut..

B. Regulatory Requirements for asphalt paving work: Comply with materials, workmanship, and other applicable requirements with the following: 1. State of Connecticut Department of Transportation “Standard Specifications for Roads,

Bridges and Incidental Construction Form 816. 2. Standard Specifications for Highway Materials and Methods of Sampling and Testing,

American Association of State Highway and Transportation Officials (AASHTO).

PART 2 - PRODUCTS

2.1 AGGREGATES

A. Coarse Aggregate: ASTM D 692/D 692M, sound; angular crushed stone, crushed gravel, or cured, crushed blast-furnace slag.

Page 52: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 321216 - ASPHALT PAVING

FACILITIES BUILDING POWER GENERATIOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC, CT

#ECSU-2019-5

2

B. Fine Aggregate: AASHTO M 29, sharp-edged natural sand or sand prepared from stone, gravel, cured blast-furnace slag, or combinations thereof.

2.2 ASPHALT MATERIALS

A. Asphalt Binder: AASHTO M 320, PG 64-28 for Performance Grade.

B. Binder Course: Class 1, CT DOT Section M.04, Table M.04.01.

C. Top Course: Class 2, CT DOT Section M.04, Table M.04.01.

D. Tack Coat: ASTM D 977 emulsified asphalt.

2.3 AUXILIARY MATERIALS

A. Recycled Materials for Hot-Mix Asphalt Mixes: Reclaimed asphalt pavement; reclaimed, unbound-aggregate base material; and recycled tires, asphalt shingles, or glass from sources and gradations that have performed satisfactorily in previous installations, equal to performance of required hot-mix asphalt paving produced from all new materials.

2.4 MIXES

A. Hot-Mix Asphalt: Dense-graded, hot-laid, hot-mix asphalt plant mixes approved by CT DOT and complying with the following requirements:

1. Provide mixes with a history of satisfactory performance in geographical area where Project is located.

2. Base Course: CT DOT Class 1. 1 ½” thick 3. Surface Course: CT DOT Class 2. 1 ½” thick

PART 3 - EXECUTION

3.1 SURFACE PREPARATION

A. General: Immediately before placing asphalt materials, remove loose and deleterious material from substrate surfaces. Ensure that prepared subgrade is ready to receive paving.

B. Proof-roll subgrade below pavements with heavy pneumatic-tired equipment to identify soft pockets and areas of excess yielding. Do not proof-roll wet or saturated subgrades.

C. Tack Coat: Apply uniformly to surfaces of existing pavement at a rate of 0.05 to 0.15 gal./sq. yd.

1. Allow tack coat to cure undisturbed before applying hot-mix asphalt paving. 2. Avoid smearing or staining adjoining surfaces, appurtenances, and surroundings. Remove

spillages and clean affected surfaces.

Page 53: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 321216 - ASPHALT PAVING

FACILITIES BUILDING POWER GENERATIOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC, CT

#ECSU-2019-5

3

3.2 PLACING HOT-MIX ASPHALT

A. Machine place hot-mix asphalt on prepared surface, spread uniformly, and strike off. Place asphalt mix by hand in areas inaccessible to equipment in a manner that prevents segregation of mix. Place each course to required grade, cross section, and thickness when compacted.

1. Spread mix at a minimum temperature of 250 deg F. 2. Regulate paver machine speed to obtain smooth, continuous surface free of pulls and

tears in asphalt-paving mat.

B. Place paving in consecutive strips not less than 10 feet wide unless infill edge strips of a lesser width are required.

C. Promptly correct surface irregularities in paving course behind paver. Use suitable hand tools to remove excess material forming high spots. Fill depressions with hot-mix asphalt to prevent segregation of mix; use suitable hand tools to smooth surface.

3.3 JOINTS

A. Construct joints to ensure a continuous bond between adjoining paving sections. Construct joints free of depressions, with same texture and smoothness as other sections of hot-mix asphalt course.

1. Clean contact surfaces and apply tack coat to joints. 2. Offset longitudinal joints, in successive courses, a minimum of 6 inches. 3. Offset transverse joints, in successive courses, a minimum of 24 inches. 4. Construct transverse joints at each point where paver ends a day's work and resumes

work at a subsequent time. Construct these joints using either "bulkhead" or "papered" method according to AI MS-22, for both "Ending a Lane" and "Resumption of Paving Operations."

3.4 COMPACTION

A. General: Begin compaction as soon as placed hot-mix paving will bear roller weight without excessive displacement. Compact hot-mix paving with hot, hand tampers or with vibratory-plate compactors in areas inaccessible to rollers.

1. Complete compaction before mix temperature cools to 185 deg F.

B. Breakdown Rolling: Complete breakdown or initial rolling immediately after rolling joints and outside edge. Examine surface immediately after breakdown rolling for indicated crown, grade, and smoothness. Correct laydown and rolling operations to comply with requirements.

C. Intermediate Rolling: Begin intermediate rolling immediately after breakdown rolling while hot-mix asphalt is still hot enough to achieve specified density. Continue rolling until hot-mix asphalt course has been uniformly compacted to the following density:

Page 54: SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL · elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently

SECTION 321216 - ASPHALT PAVING

FACILITIES BUILDING POWER GENERATIOR ADDITION EASTERN CONNECTICUT STATE UNIVERSITY WILLIMANTIC, CT

#ECSU-2019-5

4

1. Average Density: 92 percent of reference maximum theoretical density according to ASTM D 2041, but not less than 90 percent or greater than 96 percent.

D. Finish Rolling: Finish roll paved surfaces to remove roller marks while hot-mix asphalt is still warm.

E. Edge Shaping: While surface is being compacted and finished, trim edges of pavement to proper alignment. Bevel edges while asphalt is still hot; compact thoroughly.

F. Protection: After final rolling, do not permit vehicular traffic on pavement until it has cooled and hardened.

G. Erect barricades to protect paving from traffic until mixture has cooled enough not to become marked.

3.5 INSTALLATION TOLERANCES

A. Pavement Thickness: Compact each course to produce the thickness indicated within the following tolerances:

1. Base Course: Plus or minus 1/2 inch. 2. Surface Course: Plus 1/4 inch, no minus.

B. Pavement Surface Smoothness: Compact each course to produce a surface smoothness within the following tolerances as determined by using a 10-foot straightedge applied transversely or longitudinally to paved areas:

1. Base Course: 1/4 inch. 2. Surface Course: 1/8 inch. 3. Crowned Surfaces: Test with crowned template centered and at right angle to crown.

Maximum allowable variance from template is 1/4 inch.

3.6 FIELD QUALITY CONTROL

A. Testing Agency: Owner will engage a qualified testing agency to perform tests and inspections.

B. Replace and compact hot-mix asphalt where core tests were taken.

C. Remove and replace or install additional hot-mix asphalt where test results or measurements indicate that it does not comply with specified requirements.

3.7 WASTE HANDLING

A. General: Handle asphalt-paving waste according to approved waste management plan and CT Federal and local regulations.

END OF SECTION 321216