secretariat programme of work and budget 2014 - 2016
DESCRIPTION
Secretariat Programme of Work and Budget 2014 - 2016. Johannes Jütting PARIS21 Board Meeting Paris, 3 April 2014. Programme of Work. Three year programme 2014-2016 Detailed activities for 2014 POW and Budget for 3 years, because… - PowerPoint PPT PresentationTRANSCRIPT
PARIS21Partnership in Statistics for
Development in the 21st Century
Secretariat Programme of Work and Budget 2014 - 2016
Johannes JüttingPARIS21 Board Meeting
Paris, 3 April 2014
2
Programme of Work
• Three year programme 2014-2016 Detailed activities for 2014 POW and Budget for 3 years, because…
o Need for multi-year planning given the specific nature of PARIS21
o Alignment with POW cycle of OECD
3
Programme of Work
Objectives• Continue to…
facilitate NSDS design and implementation promote advocacy and engagement in co-ordination as cross-
cutting activities• Act as…
a knowledge hub an incubator an independent and neutral organisation a focal point and convenor/facilitator
4
Strategy: Objectives
Support to countries in establishing national/regional partnerships on co-ordinating
statistics.
5
Strategy: Activities
Support for…• Countries embarking on an NSDS process for the
first time Anguilla, Haiti, Tonga
• Countries already engaged in the NSDS process 15 countries across all regions
• Regional Statistical Development Plans (RSDS)• National Statistical Systems
6
Strategy: Upcoming
Review and updating of Tonga Statistics Law, a priority need arising from NSDS Assessment Workshop
7
Access: Objectives
The tools and methodologies offered by
IHSN and ADP to the Partnership have been
instrumental in stimulating increased demand for and
better use of data.
8
Access: ActivitiesIHSN activities will include…
• Implementing jointly with the World Bank the recommendations for the evaluation
• Conducting assessments of survey methodologies and developing guidelines• Upgrading and maintaining the central survey catalog
ADP activities will include…• Making survey microdata more accessible• Increasing microdata use and strengthening the demand• Improving the quality of future surveys
9
Monitoring: Objectives
Monitor the implementation of the BAPS and facilitate co-
ordination
10
Monitoring: Activities
• Implementation and monitoring of BAPS• “Informing a Data Revolution” project• PRESS 2.0• Simplified CRESS questionnaire
First time for CRESS in Asia-Pacific• NSDS status updates in developing countries
11
Monitoring: Upcoming
Country Report on Support to Statistics (CRESS) for Philippines
12
Skills / Knowledge Sharing: Objectives
Development of skills and the
sharing of knowledge to adapt to an evolving data
and policy landscape.
13
Skills / Knowledge Sharing: Activities
• Regional workshops for new NSDS guidelines Translation of guidelines into Spanish
• User-producer dialogues, and regional dialogues• Assess the challenges of statistics development in small
island countries• Continue support to regional organisations• Work with Task Team on PARIS21 Beyond 2015 to
develop new strategy• Assist countries in producing advocacy materials to raise
the profile of statistics
14
Skills / Knowledge Sharing: Upcoming
User/Producer dialogues in Côte d’Ivoire, Ethiopia, Malawi, Tunisia, Zambia
15
PARIS21 2014-2016 Work Programme Budget (in Euros)
2014 2015 2016 TOTAL
S - STRATEGY 1,346,478 1,377,532 1,389,898 4,1 M €
A - ACCESS 2,091,242 2,137,696 2,149,773 6.4 M €
M - MONITORING 1,315,359 1,271,348 584,921 3.1 M €
S - SKILLS & KNOWLEDGE SHARING 979,384 934,089 949,822 2.9 M €
GRAND TOTAL 2014-2016 5,732,463 5,720,666 5,074,415 16.5 M €
Out of which
CORE/NSDS activities- S(a)MS 3,641,221 3,582,969 2,924,641 10.1 M €
ADP/IHSN activities - (s)A(ms) 2,091,242 2,137,696 2,149,773 6.4 M €
Indicative Budget 2014-16
16
Programme of work 2014 – some figures…
23%
36%
23%
17%
StrategyAccessMonitoringSkills & Knowledge sharing
37%
63%
Staff costs Non staff cost
17
Core/NSDS activitiesVCs/grants accepted (2)
Korea: 37,000 € / 2014 Canada: 25,000 CAD (= 16,283 €) / 2014
VCs/grants in the pipeline for acceptance (1) Belgium: 200,000 € / 2014
Discussions in progress (5) Australia: 900,000 AUD (= 585 K€) / 3-year grant Switzerland: 200,000 CHF / year in 2014, 2015 and 2016 (= 492 K€ in total) Qatar: contribution for a regional meeting in Doha (end of 2014) Eurostat: amount and timeframe to be confirmed World Bank – DGF grant for 2015: amount to be confirmed
ADP/IHSN activitiesVCs/grants accepted (2)
World Bank – ADP: 750,000 USD (= 548 K€) / 2014 World Bank – IHSN: 500,000 USD (= 366 K€) / 2014
Discussions in progress (1) World Bank – DGF grants for 2015: amounts to be confirmed
Income – 1st Quarter of 2014
18
PARIS21 CORE/NSDS ACTIVITIES- S(A)MS FUNDING GAP ANALYSIS 2014 - 2015 - 2016
2014 2015 2016 TOTAL
A Budgeted expenditure 3,641,221 3,582,969 2,924,641 10,148,831
B Income in hand 4,067,451 1,789,299 0 5,856,750
C Potential funding 654,640 437,744 397,744 1,490,127
VCs accepted - subject to Parliamentary approval
Norway 123,768 0 0 123,768
Finland 50,000 0 0 50,000
Discussions in progressBelgium - annual grant in 2014 200 000 0 0 200,000
Switzerland – annual grant in 2014, 2015 & 2016 (200,000 CHF/year) 164,000 164,000 164,000 492,000
Australia – 3 year grant (900,000 AUD) 116,872 233,744 233,744 584,359
Korea – Annual grant in 2015 40,000 40,000
Qatar – regional meeting in Doha tbc tbc
Eurostat tbc tbc
World Bank - DGF grant for 2015 tbc
B+C-A Current funding (gap)/surplus (annual) 1,080,870 (1,355,926) (2,526,897) (2,801,953)
B+C-A Current funding (gap)/surplus (cumulated) 1,080,870 (275,056) (2,801,953)
Estimated financial commitments for 2015 794,090
Estimated end/year funding (gap)/surplus 286,780
19
PARIS21 ADP/IHSN ACTIVITIES - (S)A(MS)FUNDING GAP ANALYSIS 2014 - 2015 - 2016
2014 2015 2016 TOTAL
A Budgeted expenditure 2,091,242 2,137,696 2,149,733 6,378,711
B Income in hand 2,091,242 0 0 2,091,242
C Potential funding 0 0 0 0
Other possible contributions
World Bank - DGF grants for 2015 (amount tbc) tbc
B+C-A Current funding (gap)/surplus (annual) 0 (2,137,696) (2,149,773) (4,287,469)
B+C-A Current funding (gap)/surplus (cumulated) 0 (2,137,696) (4,287,469)
Estimated financial commitments for 2014 323,350
Estimated end/year funding (gap)/surplus (323,350)
20
Thank you