secondary data pm&fa

Upload: kinjal-modha

Post on 07-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/6/2019 Secondary Data Pm&Fa

    1/41

    Secondary Data for the

    Portfolio Management and

    Fundamental Analysis of

    The Power Sector

    In Partial fulfilment for the requirement of

    Summer Internship Programme

    In the two year course of

    Master of Business Administration

    Programme.

    Gujarat Technological University

    Submitted to:

    Prof. Neha Patel

    Submitted by: Kinjal Modha (NR10052)

    Saloni Shah (NR10091)

  • 8/6/2019 Secondary Data Pm&Fa

    2/41

    INTRODUCTION TO INDIAN POWER SECTOR

    The process of electrification commenced in India almost with the developed world, in the

    1880s, with the establishment of a small hydroelectric power station in Darjeeling. However,

    commercial production and distribution started in 1889, in Calcutta (now Kolkata). In the

    year 1947, the country had a power generating capacity of 1,362 MW. Generation and

    distribution of electrical power was carried out primarily by private utility companies such as

    Calcutta Electric. Power was available only in a few urban centers; rural areas and villages

    did not have electricity. After 1947, all new power generation, transmission and distribution

    in the rural sector and the urban centers (which was not served by private utilities) came

    under the purview of State and Central government agencies. State Electricity Boards (SEBs)

    were formed in all the states.

    Legal provisions to support and regulate the sector were put in place through the Indian

    Electricity Act, 1910. Shortly after independence, a second Act -The Electricity (Supply) Act,

    1948 was formulated, paving the way for establishing Electricity Boards in the states of the

    Union.

    In 1960s and 70s, enormous impetus was given for the expansion of distribution of electricity

    in rural areas. It was thought by policy makers that as the private players were small and did

    not have required resources for the massive expansion drive, the production of power was

    reserved for the public sector in the Industrial Policy Resolution of 1956. Since then, almostall new investment in power generation, transmission and distribution has been made in the

    public sector. Most of the private players were bought out by state electricity boards.

    From the installed capacity of only 1,362mw in 1947, has increased to 97000 MW as on

    March 2000 which has since crossed 100,000 MW mark India has become sixth largest

    producer and consumer of electricity in the world equaling the capacities of UK and France

    combined. The number of consumers connected to the Indian power grid exceeds is 75

    million.

    India's power system today with its extensive regional grids maturing in to an integrated

    national grid, has millions of kilometers ofT & D lines criss-crossing diverse topography of

    the country.

    However, the achievements of India's power sector growth looks phony on the face of huge

    gaps in supply and demand on one side and antediluvian generation and distribution system

  • 8/6/2019 Secondary Data Pm&Fa

    3/41

    on the verge of collapse having plagued by inefficiencies, mismanagement, political

    interference and corruption for decades, on the other. Indian power sector is at the cross road

    today. A paradigm shift is in escapable- for better or may be for worse.

    EMERGENCE OF REGIONAL POWER SYSTEMS

    In order to optimally utilise the dispersed sources for power generation it was decided right at the

    beginning of the 1960s that the country would be divided into 5 regions and the planning process

    would aim at achieving regional self sufficiency. The planning was so far based on a region as a

    unit for planning and accordingly the power systems have been developed and operated on

    regional basis. Today, strong integrated grids exist in all the five regions of the country and the

    energy resources developed are widely utilised within the regional grids. Presently, the Eastern &

    North-Eastern Regions are operating in parallel. With the proposed inter-regional links being

    developed it is envisaged that it would be possible for power to flow anywhere in the country

    with the concept of National Grid becoming a reality during 12th Plan Period.

    GENERATION

    India has installed power generation capacity of 1,41,079.84 MW as on January 31, 2008, which

    is about 100 times the installed capacity of 1362 MW in the year 1947. Power generation has

    showcased a robust growth rate which is steadily improving year after year.

    There has been significant improvement in the growth in actual generation over the last few

    years. As compared to annual growth rate of about 3.1% at the end of 9th Plan and initial years of

    10th Plan, the growth in generation during 2006-07 and 2007-08 was of the order of 7.3% and

    6.33% respectively.

    The average shortage of electricity in India every year is approximately between 7-8%.

  • 8/6/2019 Secondary Data Pm&Fa

    4/41

    STRATEGIES

    The various strategies followed to achieve the goal in power sector are,

    Power Generation Strategy with focus on low cost generation, optimization of capacity

    utilization, controlling the input cost, optimization of fuel mix,T

    echnology up gradation andutilization of Nonconventional energy sources.

    Transmission Strategy with focus on development of National Grid including Interstate

    connections, Technology up gradation & optimization of transmission cost.

    Distribution strategy to achieve Distribution Reforms with focus on System up gradation, loss

    reduction, theft control, consumer service orientation, quality power supply commercialization,

    Decentralized distributed generation and supply for rural areas.

    Regulation Strategy aimed at protecting Consumer interests and making the sector commercially

    viable.

    Financing Strategy is to generate resources for required growth of the power sector.

    Conservation Strategy to optimize the utilization of electricity with focus on Demand Side

    management, Load management and Technology up gradation to provide energy efficient

    equipment gadgets.

    Communication Strategy for political consensus with media support to enhance the general

    public awareness.

    To achieve the above objectives National Electric Policy has been designed. To fulfill the

    objectives of the NEP, a capacity addition of 78,577 MW has been proposed for the 11th

    plan. This

    capacity addition is expected to provide a growth of 9.5 % to the power sector.

    The Tenth Plan for fiscal years 2002 to 2007 targeted a capacity addition of 41,110 MW, which

    was subsequently revised to 30,641 MW; however at the end of the Tenth Plan period, only

    21,180 MW of capacity was added. This shows that India is not upto the mark in achieving the

    targets of generation. Our planning is perfect but our path to achieve the target is not perfect.

  • 8/6/2019 Secondary Data Pm&Fa

    5/41

    TRANSMISSION

    Transmission of electricity is defined as bulk transfer of power over a long distance at high

    voltage, generally of 132 kV. In India bulk transmission has increased from 3708 ckm in 1950 to

    more than 256,000 ckm today.

    The Government of India has an ambitious mission ofPOWER FOR ALL BY 2012. This

    mission would require that our installed generation capacity should be at least 2, 00,000 MW by

    2012 from the present level of 1, 14,000 MW. To be able to reach this power to the entire country

    an expansion of the regional transmission network and inter regional capacity to transmit power

    would be essential. The latter is required because resources are unevenly distributed in the

    country and power needs to be carried great distances to areas where load centres exist.

    Ability of the power system to safely withstand a contingency without generation rescheduling or

    load-shedding was the main criteria for planning the transmission system. However, due tovarious reasons such as spatial development of load in the network, non-commissioning of load

    centre generating units originally planned and deficit in reactive compensation, certain pockets in

    the power system could not safely operate even under normal conditions. This had necessitated

    backing down of generation and operating at a lower load generation balance in the past.

    Transmission planning has therefore moved away from the earlier generation evacuation system

    planning to integrate system planning.

    While the predominant technology for electricity transmission and distribution has been

    Alternating Current (AC) technology, High Voltage Direct Current (HVDC) technology has also

    been used for interconnection of all regional grids across the country and for bulk transmission of

    power over long distances.

    Certain provisions in the Electricity Act 2003 such as open access to the transmission and

    distribution network, recognition of power trading as a distinct activity, the liberal definition of a

    captive generating plant and provision for supply in rural areas are expected to introduce and

    encourage competition in the electricity sector. It is expected that all the above measures on the

    generation, transmission and distribution front would result in formation of a robust electricity

    grid in the country.

  • 8/6/2019 Secondary Data Pm&Fa

    6/41

    FUTURE PLANS FOR POWER FOR ALL BY 2012

    The countrys transmission perspective plan for eleventh plan focuses on the strengthening of

    National Power Grid through addition of over 60,000 ckm ofTransmission Network by

    2012. Such an integrated grid shall carry 60% of the power generated in the country. The

    existing inter-regional power transfer capacity is 17,000 MW, which is to be further enhanced

    to 37,000 MW by 2012 through creation of Transmission Super Highways. Based on the

    expected generation capacity addition in XI plan, an investment of about 75,000 Crore is

    envisaged in Central Sector and Rs. 65,000 Crore is envisaged in the State Sector.

    POWERGRID is working towards achieving its mission of Establishment and Operation of

    Regional and National Power Grids to facilitate transfer of power within and across the

    regions with reliability, security and economy, on sound commercial principles".

    The exploitable energy resources in our country are unevenly distributed, like Coal resources

    are abundant in Bihar/Jharkhand, Orissa, West Bengal and Hydro Resources are mainly

    concentrated in Northern and North-Eastern Regions. As a result, some regions do not have

    adequate natural resources for setting power plants to meet their future requirements whereas

    others have abundant natural resources. Demand for power continues to grow unabated. This

    calls for optimal utilization of generating resources for sustainable development. Thus,

    formation of National Power Grid is an effective tool to achieve this as various countries

    have adopted the model of interconnecting power grid not only at national level but also at

    international level.

    Further, acquiring Right of Way (ROW) for constructing transmission lines is getting

    increasingly difficult, especially in eco-sensitive areas like North-Eastern Region, Chicken

    neck area, hilly areas in Jammu & Kashmir and Himachal Pradesh. At the same time, these

    areas are also endowed with major hydro potential of the country. This necessitates creation

    of Transmission Super Highways, so that in future, constraints in ROW do not cause

    bottleneck in harnessing generating resources. Inter-connection of these highways from

    different part of the country would ultimately lead to formation of a high capacity National

    Power Grid.

    Thus, developments in power sector emphasize the need for accelerated implementation of

    National Power Grid on priority to enable scheduled/unscheduled exchange of power as well

    as for providing open access to encourage competition in power market. Formation of such a

    National Power Grid has been envisaged in a phased manner.

  • 8/6/2019 Secondary Data Pm&Fa

    7/41

    Initially, considering wide variations in electrical parameters in the regional grids, primarily

    HVDC interconnections were established between the regions. This was completed in the

    year 2002, thereby achieving inter-regional power transfer capacity of 5000 MW.

    In the next phase, inter-regional connectivity is planned to be strengthened with hybrid

    system consisting of high capacity EHV/UHV AC and HVDC links. Such a National Power

    Grid is envisaged to disperse power not only from Mega sized generation projects but also to

    enable transfer of bulk power from one part of the country to another in different operational

    scenarios say, in varying climatic conditions across the country: Summer, Winter, Monsoon

    etc. Commissioning of links under this phase has already begun with the commissioning of

    2000 MW Talcher-II HVDC Bipole, Raipur Rourkela 400kV D/C AC transmission line

    having Series Compensation, augmentation of Gazuwaka HVDC (500MW) back to back link

    and Tala transmission system. The inter-regional transfer capacity of 16,200 MW is available

    as on date. Further strengthening of National Power Grid is envisaged through high capacity

    AC EHV lines, 765 kV UHV AC lines/ HVDC lines. This phase is planned to be

    implemented by 2012 when inter-regional power transfer capacity will be enhanced to about

    37,700 MW by the end of XI Plan, depending upon planned growth of generation capacity.

  • 8/6/2019 Secondary Data Pm&Fa

    8/41

    SEGMENTS IN POWER GENERATION

    1. THERMALCurrent installed capacity ofThermal Power as of February 28, 2011 is 111,324.48

    MW which is 64.75% of total installed capacity.

    Current installed base of Coal Based Thermal Power is92,418.38 MW whichcomes to 53.75% of total installed base.

    Current installed base of Gas Based Thermal Power is 17,706.35 MW which is10.3% of total installed capacity.

    Current installed base of Oil Based Thermal Power is 1,199.75 MW which is0.9% of total installed capacity.

    The state of Maharashtra is the largest producer of thermal power in the country.

    2. HYDRO POWERIndia is blessed with a rich hydro power potential. In the exploitable potential terms,

    India ranks fifth in the world. Less than 25% of the potential has been developed as of

    now. A large hydro has four main advantages.

    It is a source of green energy. It has low variable cost. It is grid friendly. It can also can sub serve other purposes by irrigation, flood control, etc.

    India has 3 major rivers: the Indus, the Brahmaputra, and the Ganga. It also has three

    major river systems? Central Indian, west flowing rivers of south India, and east

    flowing rivers of south India with a total of 48 river basins. The total potential from

    these river basins is 600TWh (Terawatt Hours) of electricity.

  • 8/6/2019 Secondary Data Pm&Fa

    9/41

    Hydroelectric projects can be classified on the basis of purpose, hydraulic features,

    capacity, head, constructional features, mode of operation, etc. The main types are

    1. ROR (Run of River) There are not large reservoirs; a part of water flow is diverted tothe plant which is adjacent to the river. After generation the flow is diverted back tothe main flow through the tail race. This type of hydro plants requires a diversion dam

    and has unregulated water flow.

    2. Dam Storage In these types of hydro plants, large reservoirs are created by theconstruction a sizeable dam across the river and the plants is situated at the toe of the

    dam. Here, water could be regulated to generate electricity depending upon the

    demand

    3. Pumped Storage These types of plants have two reservoirs, one at the upstream ofthe power plant and one at the downstream. When there is low peak demand, thewater from the reservoir situated downstream is pumped0020back to the upstream

    reservoir.

    Various initiatives for accelerated development have been taken up by the central

    government to harness the hydro potential in India. Some of these are

    Hydro Power Policy (1998) 50 000 MW initiative Preparation of viable models for private sector participation Ranking of projects R&M up gradation and life extension programmes Facilitation for trading and co-operation with other countries Execution of projects with interstate aspects by Central Public Sector Units

    SMALL HYDRO

    The word hydro comes from a Greek word meaning water. The energy from water has

    been harnessed to produce electricity since long. It is the first renewable energy source to

    be tapped essentially to produce electricity

    Hydro power currently suffices one fifth of the global electricity supply, also improving

    the electrical system reliability and stability throughout the world. It also substantially

    avoids the green house gas emissions, thus complimenting the measures taken towards

    the climate change issues.

  • 8/6/2019 Secondary Data Pm&Fa

    10/41

    Hydro projects below a specified capacity are known as small hydro. The definition of

    small hydro differs from country to country, depending on the resources available and the

    prevalent national perspective.The small hydro atlas shows that the largest of the projects

    (30 MW) is in US and Canada. Small hydro power has emerged as one of the least cost

    options of harnessing green energy amongst all the renewable energy technologies.

    According to the power generated, small hydro power is classified into small, mini/micro

    and Mico hydro.

    In India, it is being classified as follows. Small hydro - 2 MW - 30 MW Mini - 100 kW -

    2 MW Micro - 10 kW - 100 kW Mico hydro - 1 kW - 10 kW

    Indira Sagar Dam partially completed in 2008

    India was one of the pioneering countries in establishing hydro-electric power plants.

    The power plants at Darjeeling and Shimsha (Shivanasamudra) were established in

    1898 and 1902 respectively and are among the first in Asia.

    The installed capacity as of 28-2-2011 was approximately 37,367.4 MW. The public

    sector has a predominant share of 97% in this sector.

  • 8/6/2019 Secondary Data Pm&Fa

    11/41

    3. NUCLEAR POWER GENERATIONIn India, out of total installed capacity of 126993.97 MW (as on 31 August 2006); the

    share of nuclear power is 3% at 3900 MW. From the electricity generation point of

    view, nuclear power plants contributed 17 238.89 GWh out of total electricitygeneration of 6 17 510.44 GWh during April 2005 -March 2006, amounting to 2.79%

    of total generation. However, with exponential growth in energy demand coupled

    with a finite availability of coal, oil, and gas; there is a renewed emphasis on nuclear

    energy. Moreover, nuclear energy is considered to be an environmentally benign

    source of energy.

    Department of Atomic Energy is carrying out nuclear energy programme in India. The

    Indian Nuclear Power Programme has the following three stages.

    1. The first stage, already commercial now, comprised setting up of PHWRs (pressurisedheavy water reactors) and associated fuel cycle facilities. PHWRs use natural uranium

    as fuel and heavy water as moderator and coolant. The design, construction, and

    operation of these reactors is undertaken by public sector undertaking the NPCIL

    (Nuclear Power Corporation of India Ltd). The company operates 16 reactors (2

    Boiling Water Reactors and 14 PHWRs) with a total capacity of 3900 MWe.

    2. In the second stage, it was envisaged to set up FBRs (fast breeder reactors) along withreprocessing plants and plutonium-based fuel fabrication plants. Plutonium is

    produced by irradiation of Uranium-238. The Fast Breeder Programme is in the

    technology demonstration stage. Under this stage, the IGCAR (Indira Gandhi Centre

    for Atomic Research) has completed design of a 500 MWe PFBR (prototype fast

    breeder reactor) being implemented by BHAVINI (Bharatiya Nabhikiya Vidyut

    Nigam).

    3. The third stage of the Indian Nuclear Power Programme is based on the thorium-uranium-233 cycle. Uranium-233 is obtained by irradiation of thorium. Presently this

    stage is in technology development phase. The ongoing development of 300 MWe

    AHWR (advanced heavy water reactor) at BARC (Bhabha Atomic Research Centre)

    concerns thorium utilization and its demonstration.

  • 8/6/2019 Secondary Data Pm&Fa

    12/41

    Indian nuclear power plants

    Currently, twenty nuclear power reactors produce 4,780 MW

    Wind turbiness in Tamil Nadu

    4. SOLARIndia is endowed with rich solar energy resource. The average intensity of solar

    radiation received on India is 200 MW/km square (megawatt per kilometer square).

    With a geographical area of 3.287 million km square, this amounts to 657.4 million

    MW. However, 87.5% of the land is used for agriculture, forests, fallow lands, etc.,

    6.7% for housing, industry, etc., and 5.8% is either barren, snow bound, or generally

    inhabitable. Thus, only 12.5% of the land area amounting to 0.413 million km square

    can, in theory, be used for solar energy installations. Even if 10% of this area can beused, the available solar energy would be 8 million MW, which is equivalent to 5 909

    mtoe (million tons of oil equivalent) per year.

    However, solar energy is a dilute source. The energy collected by 1 m square of a

    solar collector in a day is approximately equal to that released by burning 1 kg of coal

    or 1/2 litre of kerosene. Thus, large areas are needed for collection. Besides, the

  • 8/6/2019 Secondary Data Pm&Fa

    13/41

    efficiency of conversion of solar energy to useful energy is low. Therefore, the energy

    actually available would be order of magnitude lower than the aforementioned

    estimates. Nonetheless, it is obvious that solar energy can be a good source of meeting

    energy demands.

    On the applications side, the range of solar energy is very large. While at the high end

    there are megawatt level solar thermal power plants, at the lower end there are

    domestic appliances such as solar cooker, solar water heater, and PV lanterns. Then,

    in between, there are applications such as industrial process heat, desalination,

    refrigeration and air-conditioning, drying, large scale cooking, water pumping,

    domestic power systems, and passive solar architecture. Solar energy can be

    harnessed to supply thermal as well as electrical energy. Those technologies that use

    solar energy resource to generate energy are known as solar energy technologies.

    Solar energy technologies consists of

    Solar thermal technologies, which utilize sun's thermal energy and Solar photovoltaic technology, which convert solar energy directly in to

    electricity.

    Solar energy resource: Since the accurate information about solar energy resource at

    a specific location is crucial for designing appropriate solar system. Solar energy

    resource assessment becomes an essential activity of any solar energy programme.

    The first Indian solar thermal power project (2X50MW) is in progress in Phalodi

    (Rajasthan), and is constructed by CORPORATE ISPAT ALLOY LTD. The solar

    thermal power plant has cost 4 times as much as the coal based steam thermal power

    plant, CIAL carried this 2x850 crore solar thermal project. It is the "pioneering of

    solar energy" in india. India is densely populated and has high solar insolation, an

    ideal combination for using solar power in India. Much of the country does not havean electrical grid, so one of the first applications of solar power has been for water

    pumping, to begin replacing India's four to five million diesel powered water pumps,

    each consuming about 3.5 kilowatts, and off-grid lighting. Some large projects have

    been proposed, and a 35,000 km area of the Thar Desert has been set aside for solar

    power projects, sufficient to generate 700 to 2,100 gigawatts.

  • 8/6/2019 Secondary Data Pm&Fa

    14/41

    The Indian Solar Loan Programme, supported by the United Nations Environment

    Programme has won the prestigious Energy Globe World award for Sustainability for

    helping to establish a consumer financing program for solar home power systems.

    Over the span of three years more than 16,000 solar home systems have been financed

    through 2,000 bank branches, particularly in rural areas of South India where the

    electricity grid does not yet extend.

    Launched in 2003, the Indian Solar Loan Programme was a four-year partnership

    between UNEP, the UNEP Risoe Centre, and two of India's largest banks, the Canara

    Bank and Syndicate Bank.

    Announced in November 2009, the Government of India proposed to launch its

    Jawaharlal Nehru National Solar Mission under the National Action Plan on Climate

    Change with plans to generate 1,000 MW of power by 2013 and up to 20,000 MW

    grid-based solar power, 2,000 MW of off-grid solar power and cover 20 million sq

    metres with collectors by the end of the final phase of the mission in 2020.

    5. WIND

    The suns energy falling on the earth produces large-scale motions of the atmosphere

    causing winds, which are also influenced by small scale flows caused by local

    conditions such as nature of terrain, buildings, water bodies, etc. Wind energy is

    extracted by turbines to convert the energy into electricity.

    A small-scale and large-scale wind industry exists globally. The small-scale wind

    industry caters for urban settings where a wind farm is not feasible and also where

    there is a need for household electricity generation. The large-scale industry is

    directed towards contributing to countrywide energy supply.

    The development ofwind power in India began in the 1990s, and has significantly

    increased in the last few years. Although a relative newcomer to the wind industry

    compared with Denmark or the US, a combination of domestic policy support for

    wind power and the rise of Suzlon have led India to become the country with the fifth

    largest installed wind power capacity in the world.

  • 8/6/2019 Secondary Data Pm&Fa

    15/41

    As of June 2010 the installed capacity of wind power in India was 12009.14 MW,

    mainly spread across Tamil Nadu (4132.72 MW), Maharashtra (1837.85 MW),

    Karnataka (1184.45 MW), Rajasthan (670.97 MW), Gujarat (1432.71 MW), Andhra

    Pradesh (122.45 MW), Madhya Pradesh (187.69 MW), Kerala (23.00 MW), West

    Bengal (1.10 MW), other states (3.20 MW). It is estimated that 6,000 MW of

    additional wind power capacity will be installed in India by 2012. Wind power

    accounts for 6% of India's total installed power capacity, and it generates 1.6% of the

    country's power.

    Strategies

    Power Generation Strategy with focus on low cost generation, optimization ofcapacity utilization, controlling the input cost, optimisation of fuel mix,

    Technology upgradation and utilization of Non Conventional energy sources

    Transmission Strategy with focus on development of National Grid includingInterstate connections, Technology upgradation & optimization of transmission

    cost.

    Distribution strategy to achieve Distribution Reforms with focus on Systemupgradation, loss reduction, theft control, consumer service orientation, quality

    power supply commercialization, Decentralized distributed generation and supply

    for rural areas.

    Regulation Strategy aimed at protecting Consumer interests and making the sectorcommercially viable.

    Financing Strategy to generate resources for required growth of the power sector. Conservation Strategy to optimise the utilization of electricity with focus on

    Demand Side management, Load management and Technology upgradation to

    provide energy efficient equipment / gadgets.

    Communication Strategy for political consensus with media support to enhancethe general public awareness.

    WIND RESOURCE IN INDIA

    The wind resource assessment in India estimates the total wind potential to be around

    45 000 MW (mega watt). This potential is distributed mainly in the states ofTamil

    Nadu, Andhra Pradesh, Karnataka, Gujarat, Maharashtra, and Rajasthan. The

  • 8/6/2019 Secondary Data Pm&Fa

    16/41

    technical potential that is based on the availability of infrastructure, for example the

    availability of grid, is estimated to be around 13 000 MW. In India, the wind

    resources fall in the low wind regime, the wind power density being in the range of

    250 -450 W/m2

    . It may be noted that this potential estimation is based on certain

    assumptions. With ongoing resource assessment efforts, extension of grid,

    improvement in the wind turbine technology, and sophisticated techniques for the

    wind farm designing, the gross as well as the technical potential would increase in the

    future.

    STATUS

    Wind power has become one of the prominent power generation technologies

    amongst the renewable energy technologies.

    TECHNOLOGY TRENDS

    Use of wind energy started long ago when it was used for grinding. The commercial

    use of wind energy for electrical power generation started in 1970s. Horizontal axis

    wind turbines are most commonly used for power generation, although some vertical

    axis wind turbine designs has been developed and tested. The vertical axis turbines

    have structural as well as aerodynamic limitations and, hence, are not commercially

    used.

    WIND POWER IN INDIA

    Wind turbines offered in India range from 250 kW to 2 MW capacities. As of 31

    March 2006, the total installed capacity in the country was 5340 MW, which is 46%

    of the total capacity of renewable resources based power generation. There are 7

    manufacturers of wind turbine generators in India.

  • 8/6/2019 Secondary Data Pm&Fa

    17/41

    Rural Electrification

    Jharkhand, Bihar, Uttar Pradesh, Orissa, Uttranchal, and Madhya Pradesh are some of

    the states where significant number (more than 10%) of villages are yet to be

    electrified.

    Number of Villages (1991 Census) - 593,732 Villages Electrified (30 May 2006) - 488,173 Village level Electrification % - 82.2%Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY)Ministry of Power (Government of India) has launched nation-wide scheme for

    development of rural and household electrification in 2005 towards the NationalCommon Minimum Programme goal of providing access to electricity to all. REC Ltd

    is the nodal agency for the mega-scheme. Under the scheme, 90% capital subsidy is

    provided by Government of India for overall cost of projects. Cumulatively till FY10,

    works in 190,858 villages have been completed and free connections to over 10

    million below poverty line (BPL) households have been released.

    Renewable Energy

    Renewable energy in India is a sector that is still undeveloped. India was the first

    country in the world to set up a ministry of non-conventional energy resources, in

    early 1980s. However its success has been very spotty. In recent years India has been

    lagging behind other nations in the use of renewable energy (RE). The share of RE in

    the energy sector is less than 8% of India's total energy needs. Renewable energy in

    India comes under the purview of the Ministry of New and Renewable Energy.

  • 8/6/2019 Secondary Data Pm&Fa

    18/41

    IMPACT OF POWER SECTOR

    LOCAL IMPACTS

    Large power sources can affect their surroundings through impacts such as airpollution, submergence of land and waste accumulation, excessive resource use and

    disruption of human activity.

    The impacts of coal-based thermal plants are particularly important in a study of

    India, as these plants currently provide the largest generating capacity in India, and

    about 80% of the actual generation. Electricity generation consumed 67% of Indias

    coal use, in 2002; further, Indias coal consumption is projected to grow 2.2%

    annually between 2002 and 2025 (EIA, 2005).

    Most of the existing thermal power plants in India use the traditional pulverized coal

    combustion technology. As a result, they have to contend with gaseous emissions

    including carbon dioxide, nitrogen oxides, carbon monoxide, sulphur dioxide,

    mercury and particulate matter. Coal-burning thermal power plants in India are

    responsible for about 40% of the countrys SO2 and 41% of its CO2 in 2000 (Shukla,

    Nag, & Biswas, 2003). Coal-plant emissions far outweigh those from other fossil-fuel

    plants contributing to acid rain, and air pollution and the consequent adverse effects

    on health.

    When based on locally mined coal, the associated problems of mining accidents and

    land degradation are serious. In some areas, the use of high ash coal results in disposal

    problems, although ash does have productive uses such as brick-making. However,

    with the alternative fossil-fuel options, oil-and gas-based plants, too, issues of waste

    disposal and possible drilling and pipeline accidents have to be considered. The water

    use by some thermal plants constitutes a more serious problem; Indian thermal power

    plants reportedly use 88% of the countrys industrial water supply (DTE, 2003).

    Temperature increases and pollution of receiving water bodies through inadequately

    treated effluents have also to be dealt with.

    Although based on a clean and renewable source, large hydroelectric plants are not

    impact-free. Large dams can cause submergence of human settlements and natural

  • 8/6/2019 Secondary Data Pm&Fa

    19/41

    forests, adversely affecting or even destroying peoples livelihoods, particularly

    traditional lifestyles, and also terrestrial ecosystems. However, the magnitude of these

    impacts varies with the location and the height of the dams constructed.

    With nuclear power plants, radiation hazards (not only through accidents), anddisposal of radioactive spent fuel must also be contended with. Thus far, no country is

    sure of safe and permanent waste disposal. And, while clean in terms of carbon-

    emissions, both ends of the nuclear fuel cycle uranium mining and nuclear waste

    have harmful environmental impacts, if not very carefully managed.

    However, environmental impact costs are not easily quantifiable. Pollution-induced

    health impacts are underestimated when economically disadvantaged people do not

    obtain medical treatment; similarly, disruption costs of displaced communities could

    be inestimable.

    REGIONAL IMPACTS

    Regional pollution issues, for example the issue of acid rain and sulphur deposition,

    have received attention in Northeast Asia. While the magnitude of coal-fired power

    plants' contribution may be disputed, particularly during winter and spring, when

    dominant high-pressure systems sweep accumulated pollutants off the landmass

    toward the eastern ocean-mass.

    To study and analyze the power sector better, the comparative and analytical study of

    the Top 5 listed firms of power sector in India is done. The firms are chosen based on

    their sales turnover. The below are the firms selected by us for the study,

    TOP 5 COMPANIES OF POWER SECTOR

    NTPC Energy Develop Tata Power Power Grid Torrent

  • 8/6/2019 Secondary Data Pm&Fa

    20/41

    1.NTPC Ltd.NTPC Limited is the largest power generating and Navratna status company of India;

    it was incorporated in the year 1975 as National Thermal Power Corporation Private

    Limited to accelerate power development in the country. As a wholly owned company

    of the Government of India, NTPC has emerged as a truly national power company,

    with power generating facilities in all the major regions of the country. NTPC's core

    business is engineering, construction and operation of power generating plants. NTPC

    as an integrated Power Major with presence in Hydro Power, Coal mining, Oil & Gas

    exploration, Power Distribution & Trading and also enter into Nuclear Power

    Development. It provides consultancy also in the area of power plant constructions

    and power generation to companies in India and abroad. It is providing power at the

    cheapest average tariff in the country. With its experience and expertise in the power

    sector, also NTPC is extending consultancy services to various organisations in the

    power business. The consulting Wing of NTPC is an ISO 9001:2000 accreditation. In

    the year of 1982, the company commissioned the first Singrauli unit.

    During the year 2002, the company incorporated three wholly owned subsidiary of the

    company viz. NTPC Electric Supply Company Limited, NTPC Hydro Limited and

    NTPC Vidyut Nigam Limited. Golden Peacock Award conferred to the company for

    Corporate Social Responsibility in14th November of the year 2003. Unit IV (500

    MW) of Talcher Super Thermal Power Project -Stage II (TSTPP-II) of THE

    COMPANY has been successfully synchronized on 6th February 2005. The 500 MW

    Unit at Ramagundam Super Thermal Power Station has commenced commercial

    operation on 25th March 2005. In May of the year 2005, NTPC and Defence

    Metallurgical Research Laboratory (DMRL) have signed an MOU. NTPC has bagged

    IPMA International Project Management Award 2005 for its Simhadri Thermal Power

    project on 15th November 2005.

    NTPC established the medium Term Note ('MT N') Programme in February of the

    year 2006 to facilitate the raising of funds on a regular basis from the international

    debt capital markets and also signed an MOU with Delhi Transco Ltd., (DTL) on 10th

    February 2006 for expansion of one of its stations namely National Capital Power

    Station Stage-II at Dadri (U. P.). During the March of the year 2006, NTPC Ltd has

    entered into a Memorandum of Understanding with Petronet LNG Limited for

  • 8/6/2019 Secondary Data Pm&Fa

    21/41

    arranging one MMTPA of LNG, which used to overcome shortage of gas at the

    existing gas power stations of NTPC. The Company had taken over the Badarpur

    Thermal Power Station with the capacity of 705MW in the year 2006 from Central

    Electricity Authority. The Company had signed a Memorandum of Understanding in

    11th March of the year 2006 with the Energy and Resources Institute (TERI) for

    implementation of distributed generation projects in villages in India. A 500 MW unit

    of Vindhyachal SuperThermal Power Project -Stage III of NTPC Limited located in

    the state of Madhya Pradesh has been successfully synchronized on 27th July 2006.

    NTPC Limited and Singareni Collieries Company Limited have signed a

    Memorandum of Understanding during August of the year 2006, for creation of a

    Joint Venture Company to undertake various activities in coal and power sectors

    including acquisition of coalmines, development and operation of integrated coal

    based plants and providing consultancy services. The Company has signed a

    Memorandum of Agreement (MOA) in September 21st of the year 2006 with the

    Government of Arunachal Pradesh for implementation of the following two

    hydroelectric power projects in the States of Arunachal Pradesh. NTPC had formed a

    joint venture Company under the name and style of 'Aravali Power Company Pvt Ltd'

    on December 21, 2006 with Haryana Power Generation Corporation Ltd (A

    Government of Haryana Undertaking). The Company has signed a MoU in February

    14th of the year 2007 with Bharat Earth Movers Limited (BEML) for collaborating

    and associating with NTPC for a long-term mutually beneficial business.

    A 500 MW unit of Vindhyachal Super Thermal Power Project, Stage III of NTPC

    Limited located in the state of Madhya Pradesh has been successfully (test)

    synchronized in the night of 8th March 2007. Signed a Memorandum of

    Understanding with Coal India Limited on 15.03.2007 for undertaking development,

    operation & maintenance of coal blocks and integrated coal based power plants.

    NTPC signed an agreement for a term loan of USD 100 million with KFW of

    Germany on March 23, 2007 at Frankfurt am Main.

    During the year 2007-08, the MOU was signed with ADB for establishment of power

    generation capacity of about 500 MW through Renewable Energy Sources. The JVA

    was signed between NTPC and BSEB for setting up 3x660 MW at Nabinagar, Bihar

    and also another one JVA was signed with UPRVUNL to set-up 2x660 MW power

  • 8/6/2019 Secondary Data Pm&Fa

    22/41

    project at Meja Tehsil in Allahabad, UP. The Joint Venture Company (Subsidiary of

    NTPC) under the name of 'Bhartiya Rail Bijlee Company Limited' incorporated with

    Railways for setting up 1000 MW coal based power plant at Nabinagar, Bihar.

    Business Collaboration and Share Holder's Agreement signed with Govt. of Kerala

    and TELK to acquire around 44.6% stake of TELK. The MOU was signed with

    Bharat Forge Limited for setting up a new facility to take up manufacture of Balance

    of Plant equipments, castings, forgings, fittings etc. JVA signed with BHEL for taking

    up activities related to carrying out EPC and manufacturing of equipments in the

    period of 2007-08. The 500 MW Unit-I at Sipat SuperThermal Power Project, Stage-

    II has commenced commercial operation in June of the year 2008. NTPC has signed a

    Memorandum of Understanding (MOU) with Secretary (Power), Government of India

    for generating 2.09 billion units of Electricity during the financial year 2008-09.

    Developing and operating world-class power stations is NTPC's core competence. Its

    scale of operation, financial strength and large experience serve to provide an

    advantage over competitors. To meet the objective of making available reliable and

    quality power at competitive prices, NTPC would continue to speedily implement

    projects and introduce state-of-art technologies.

    The growth of the capacity of NTPC

  • 8/6/2019 Secondary Data Pm&Fa

    23/41

    2.RELIANCE INFRASTRUCTURE LTDReliance Energy Limited (REL), with its corporate lineage going back to 1929. At the

    time of incorporation REL was called as Bombay Suburban Electric Supply Limited

    (BSES). The company has been in the field of power distribution for nearly eight

    decades and with its emphasis on continuous improvements. REL is a fully integrated

    utility engaged in the generation, transmission and distribution of electricity. It ranks

    among India's top listed private companies on all major financial parameters,

    including assets, sales, profits and market capitalization. A key constituent of the

    Reliance -Anil Dhirubhai Ambani Group, India's third largest business house.

    Reliance Energy has emerged as one of the leading players in India in the

    Engineering, Procurement and Construction (EPC) segment of the power sector.

    Reliance Energy company currently pursue several gas, coal, wind and hydro-based

    power generation projects in Maharashtra, Uttar Pradesh, Arunachal Pradesh and

    Uttaranchal with aggregate capacity of over 13,510 MW. Reliance Energy is also

    active in the trading and transmission of power sector and has forayed as an equity

    investor in to the infrastructure business, including in the prestigious Mumbai metro

    rail project and various road projects of the National Highways Authority of India.

    REL has also entered into the Internet service provider business in a big way by the

    name of powersurfer.net. REL (BSES) has several group companies -ST-BSES Coal

    Washery (Joint Venture), BSES Infrastructure Finance, Utility Powertech (Joint

    Venture), Ticapco, BSES Telecom, BSES Kerala Power, BSES Andhra Power and

    three new companies of Orissa. The company has a strategy of adding value by

    strategic alliances within the group.

    In March 2000 company has been operated "BSES Telecom" as an Internet service

    provider (ISP) in Mumbai and has a fiber optic network to support its last mile

    services and also exploring alliances for providing utility solutions. Dahanu Power

    Station achieved a plant load factor (PLF) of 82.68% during 2000-01. In 2001-02, the

    BSES Kerala Power Ltd had commissioned the power station in the Combined Cycle

    mode but due to various reasons the BKPL has suspended its operations from

    October, 2001. OFGW of 220 KW transmission line between Ghodbunder, Versova

    and Dahanu was successfully completed. RE L's Wind Energy has one of the highest

    PLF in the country in the wind farm segment. Contracts and EPC Division was

  • 8/6/2019 Secondary Data Pm&Fa

    24/41

    instrumental in construction and erection works of 5,000 mw in Indian and other

    industrial and infrastructure projects. BSES Infrastructure Finance has tied up funds

    for various projects to the tune of over Rs 1,500 crore. Utility Powertech is a JV with

    National Thermal Power Corporation (NTPC) has 250 operational sites.

    During the year 2002-2003, the company has successfully commissioned 210 MW

    Gas Based Combined Cycle power plants for BSES Andhra Power and 24 MW

    Bagasse fired Power Plant for Godavari Sugar Mills Ltd and 20 MW for Suryachakra

    Power Corporation Ltd. In April 2003 Andhra Power Ltd and Reliance Salgocar

    Power Company Ltd were amalgamated with the company. During the year 2003-

    2004, the Company was renamed to Reliance Energy Ltd from its old name BSES.

    Reliance energy continues to receive prestigious awards and recognitions for its

    outstanding performance in various fields and through various sources. The DahanuPower Station received the National Award for Excellence in Energy Management

    and National Award for Excellence in Water Management from the Confederation of

    Indian Industry and also company got the Maharashtra safety award-2004 from the

    Maharashtra Chapter of National Safety Council.

    Gold Shield for Meritorious Performance by the Central Electricity Authority (CEA)

    of the Government of India for its excellent performance amongst Indian thermal

    power plants in the year 2004-05, which was presented by the Honorable PrimeMinister of India. The power station also obtained OSHAS 18001 certification from

    BVQI during the year of 2005-06. During the year 2006-07, Reliance Energy had

    received many awards such as Golden Peacock Award for its pursuit of excellence in

    corporate governance, International Quality Crown Award London 2006 in Gold

    category, Srishti Good Green Governance (G-Cube) Award and participated in the

    prestigious Ramakrishna Bajaj National Quality Awards, the company was awarded a

    commendation certificate for the same. In April 2007 REL planned to set up a 1,400

    Mw gas-based power project in Delhi and also company has estimated that it wouldhave to invest Rs 60,000 crore in next five years to add a capacity of 15,000 MW of

    power. As on September 2007 REL considered to hive off its engineering,

    procurement and construction (EPC) division into a new company.

  • 8/6/2019 Secondary Data Pm&Fa

    25/41

    Reliance Energy distribute more than 28 billion units of electricity to cover 25 million

    consumers across different parts of the country including Mumbai and Delhi in an

    area that spans over 1,24,300 sq. kms. It generates 941 MW of electricity, through its

    power stations located in Maharashtra, Andhra Pradesh, Kerala, Karnataka and Goa.

    These projects are at various stages of development. Company wants to attain global

    best practices and become a world-class utility and to provide uninterrupted,

    affordable, quality, reliable and clean power to millions of customers. Future plan and

    action of the company is installation of third cooling tower cell to improve plant

    reliability and output. Energy savings by installation of energy efficient blades on

    cooling tower fans. ETP pump modification to reduce auxiliary power consumption.

    Auto -locking facility of energy meters at midnight to facilitate simultaneous logging

    of energy meter readings. The company has targeted to complete all activities under

    the six sigma project, ISO 27001 and OHSAS certifications during 2007-08, which

    will make Reliance Energy the first utility in the country to achieve these

    certifications. These initiatives are aimed to cater the market and at further promoting

    business excellence in all functional areas of the company. In 2008 company engaged

    in several mega projects under implementation and under consideration in different

    functional areas, in that the notable two big projects are engineering, procurement and

    construction (EPC) contract from Damodar Valley Corporation (DVC) to set up the 2

    x 600 MW coal based power station at Raghunathpur in West Bengal worth of Rs

    3,725 crore and Airport Metro Express Line, Delhi project on BOOT basis for a

    concession period of 30 years worth of Rs 2,500 crore.

    Production Capacity : 941 MW

  • 8/6/2019 Secondary Data Pm&Fa

    26/41

  • 8/6/2019 Secondary Data Pm&Fa

    27/41

    comprised 3 x 250 MVA, 220/110/33 KV autotransformers, space saving 245 KV gas

    insulated switchgear and supervisory control and data acquisition system.

    The modern 22 KV indoor SF6switchgear was installed at Salsette and also the 60

    MVAR new capacitor banks were installed during the year 1992 at Versova andMalad. Apart from these, replacement of 110 KV oil circuit breakers by modern SF6

    breakers at Kalyan, Ambernath, Vikhroli and Salsette receiving stations and extension

    of fibre optic communication network were also carried out during the same year. In

    1994, the Trombay Unit-7 steam turbine generator of the company was harmonized,

    which generated 650 MUS with PLF of 61.9%. During the year, the Company

    undertook the work of strengthening dams as per designs codes in respect of

    earthquakes.

    The Government of Maharashtra had accorded its permission for rebuilding a dam at

    Somwadi. A MoU was signed between TEC and the Tennesse Valley Authority of

    USA for renovation and modernisation of power plants. In the same year 1994, the

    Company issued 91,549 Global Depository Shares. The 150 MW Pumped storage unit

    was commissioned in the year 1995, based on the synchronous condenser mode and

    also the Company undertook the work of modernisation and renovation of old 12 MW

    hydro units at Bhivpuri and Khopoli Generating Stations. In the year 1996, the

    generating station five 25 MW units were refurbished by installation of new modernturbine runners of higher efficiency at Bhira. During same the year, the Company

    bagged the Multi-fuel based 80 MW power project from the Government of

    Karnataka. The thermal Units at Trombay operated by the company in the year 1997

    based on-line availability of about 74% and utilization of about 64.3%. TPC entered

    into a Joint Venture Agreement with Total Gas and Power India in the year 1998 for

    establishment of LNG Terminal at Trombay.

    During 1999, the company acquired a generating station consisting of 37.5 MW Unit

    at Wadi, Karnataka and also in the year the Power Purchase Agreement for 81.3 MW

    Diesel-based Power Plant at Belgaum, Karnataka was signed with Karnataka

    Electricity Board. Tata Power Company has obtained A' licence as Internet service

    provider that enables it to operate throughout the country in the year 2000. The

    Andhra Valley Power Supply Company Ltd and Tata Hydro Electric Supply

  • 8/6/2019 Secondary Data Pm&Fa

    28/41

    Company Ltd were merged with the company in the same year 2000. Tata Power

    Company Ltd on September of the year 2001, decided to sell its stake consisting of 45

    lakh shares in Tata Liebert Ltd (TLL) considering of Rs 170 per share to Emerson

    Electric (Mauritius) Ltd. The Company signed an agreement with Power Grid

    Corporation of India Ltd for 'Tala Transmission Line' in the year 2002. The 120 MW

    Unit 3 at the Jojobera Power Plant of the Company situated in Jamshedpur was

    commenced its commercial production. TPC has signed the share acquisition

    agreement with Gvt of National Capital Territory of Delhi to acquire the North North-

    West Delhi Distribution Co. Ltd. (Discom-III), a distribution company belonging to

    the Delhi Vidyut Board (DVB), which supplies power to north and northwestern

    Delhi. The company ties up with the UK-based energy major British Petroleum to

    jointly work on 2,184 mw Dabhol power project during the year 2003. During the

    same year 2003, TPC awarded the contract for supply and construction of 180 KM

    long 400 KV Double Circuit Transmission Line from Palandur to Chandrapur

    (Maharashtra) By Power Grid Corporation of India Ltd. Tata Power infuses Rs 352

    crore in the group's telecom businesses.

    Tata Power acquired 100% equity stake in Tata PowerTrading Co. Pvt Ltd in the year

    2004. The Christened Tata PowerTrading Company was incorporated in the year as a

    subsidiary of the company. TPC has signed a Development Agreement with GAIL

    India Ltd & BP to jointly participate in evaluating the Dabhol gas and power

    opportunity. A MoU was signed with National Power Company of Al-Zamil Group,

    Kingdom of Saudi Arabia. The company bagged the 2nd Wartsila -Mantosh Sondhi

    Award for outstanding contribution to the Indian Power Sector in 2004. Tata Power

    signed a generation pact with DVC on Maithon Project in the year 2005 and entered

    into an agreement for sale of shares in Tata Power Broadband. The company received

    CII EXIM Bank Award 2005 for 'Certificate for Strong Commitment to Excel'.

    During the period of 2006, the company joined hands with Siemens. The company

    signed a joint venture agreement with Tata Steel to set up a Captive Power plants in

    Chattisgarh, Orissa and Jharkhand. The company received seven licenses from the

    Gvt of India, Ministry of Commerce and Industry, Dept of Industrial Policy &

    Promotion for its Strategic Electronics Division (Tata Power SED).

    In the year 2007, TPC has signed a MoU with the Government of Chhattisgarh for the

  • 8/6/2019 Secondary Data Pm&Fa

    29/41

    setting up of a 1000 MW coal fired mega power plant in the State. The company has

    roped in Korea-based Doosan Heavy Industries and Construction Ltd for supercritical

    boilers for its Mundra ultra mega power project. The acquisition of Coastal Gujarat

    Power Ltd was med by the company and a Special Purpose Vehicle (SPV) formed for

    Mundra Ultra Mega Power Project (UMPP). TPC has signed an EPC contract for

    supply of five (5) 800 MW Steam Turbine Generators with Toshiba Corporation for

    the first 4000 MW Ultra Mega Power Project (UMPP) in India to be located at

    Mundra, Gujarat in August 2007.

    As on February 2008, The Tata Power Company Limited (Tata Power) and Damodar

    Valley Corporation (DVC) jointly completed its financing for the 1050 MW coal

    based thermal power project, being set up in Dhanbad District of Jharkhand State.

    Recognising the steady and stable performance in generating quality and reliableenergy, the Central Electricity Authority has awarded Tata Power's Bhira Hydro

    generation facility with the Silver Shield award for the meritorious performance in

    March 2008. April of the year 2008, Tata Power completes the Signing of Financial

    Agreements for 4000 MW Ultra Mega Power Project, coming up at Mundra, Gujarat.

    The cost of the project is estimated at INR 17000 crores (USD 4.2 billion). Tata

    Power announced in September of the year 2008, it would acquire a 11.4 per cent

    stake in Geodynamics Ltd, an Australian company specialising in geothermal energy,

    for Rs 165 crore.

    Tata Power is surging ahead, lighting up lives through its activities from its inception.

    The challenge of fulfilling the ever growing needs of power have been met by Tata

    Power through efficient generation, transmission, distribution and constant

    upgradation of its technology in every aspects.

  • 8/6/2019 Secondary Data Pm&Fa

    30/41

    4.POWER GRID CORPORATION OF INDIA LTDThe Company was incorporated in October 23rd of the year 1989 as the National

    Power Transmission Corporation Limited with the responsibility of planning,

    executing, owning, operating and maintaining the high voltage transmission systems

    in the country. Subsequently, the company name was changed to the present name

    Power Grid Corporation of India Limited (PGCIL) with effect from October 23rd of

    the year 1992. The company's operational area includes, Development of Inter-State

    transmission Systems and Grid Management. Development of Inter-State

    transmission Systems consists of Planning & Design, Construction, Quality

    Assurance & Inspection and Operation & Maintenance. Grid Management includes

    Establishment of modern Load Despatch Centres, Real-time Grid Operation,

    Optimum scheduling & despatch and Energy accounting including settlements. The

    Diversification consists of Broadband Telecom Services, Sub-transmission,

    Distribution and Rural Electrification. The company has certified as PAS 99:2006,

    which integrates the requirements of ISO 9001:2000 for quality, ISO 14001:2004 for

    environment management and OHSAS 18000:1999 for health and safety management

    systems.

    PGCIL has commenced the operations in the year 1992 as part of an initiative of the

    Government of India to consolidate all the interstate and inter-regional electric power

    transmission assets of the country in a single entity. In the year 1993 Tehri Hydro

    Development Corporation Limited's assets were transferred to PGCIL pursuant to a

    memorandum of understanding executed between the both. Since 1994, the GOI has

    progressively entrusted the company with the operation of the Regional Load

    Despatch Centres ('RLDCs') in each of the five regions into which India is divided for

    purposes of power transmission and regulation. From the year 1995, the consultancy

    division of the company has provided transmission-related consultancy services to

    domestic and international projects. In consultancy business, the company has also

    facilitate the implementation of various GOI-funded projects for the distribution of

    electricity to end-users, such as the Accelerated Power Development and Reform

    Programme ('APDRP') in urban and semi-urban areas and the Rajiv Gandhi Grameen

    Vidhyutikaran Yojana (the 'RGGVY') in rural areas. During the year 1995, the

    company took over the management of the Eastern Regional Load Despatch Centre

    and the North Eastern Load Despatch Centre. Again in 1996, the company captured

  • 8/6/2019 Secondary Data Pm&Fa

    31/41

    over the management of the remaining two regional load despatch centres, namely,

    the Northern Regional Load Despatch Centre and the Western Load Despatch Centre.

    In 1998, the Government of India formally notified the PGCIL as a Central

    Transmission Utility and also in same year PGCIL was declared as a Mini Ratna

    Category I public sector undertaking by the Government of India.

    Department of Telecommunications, Government of India has granted the

    Infrastructure Provider II license (IP II) to the company in the year of 2001, for pursue

    leasing of bandwidth capacity to various customers on its telecommunications

    network. During the year 2002, the company commissioned the unified load dispatch

    and communications schemes for the northern and southern regions. The Sasaram

    HVDC back to back transmission system developed by the PGCIL was commissioned

    leading to the completion of the first phase of the construction of the National Gridand also the 2,000 MW Talchar-Kolar bipolar HVDC link was commissioned, which

    also developed by the company.

    The Company had entered into a joint venture arrangement with Tata Power

    Company Limited during the period of 2003 for implementing a part of the entire

    transmission system associated with Tala Hydro-Electric Project which was the first

    public-private sector initiative in the transmission sector. PGCIL had developed the

    400 KV Raipur-Rourkela line transmission lines and it was commissioned. Also in thesame period of 2003, the Western region, Eastern Region and North-Eastern Region

    begin operating in a synchronised manner with a cumulative capacity of 50,000 MW.

    The Company secured its first international consultancy contract from Bhutan

    Telecommunications. The unified load dispatch and communications scheme for the

    eastern region was commissioned in the year of 2005. After a year, in 2006, the

    unified load dispatch and communications scheme for the western region was

    commissioned. In the same year 2006, PGCIL had entered into an agreement with

    Rural Electrification Corporation Limited and certain state governments and stateutilities for undertaking rural electrification works under the Rajiv Gandhi Grameen

    Vidyutkaran Yojana in nine states. Power Grid Corporation of India Ltd (PGCIL) has

    been selected for the Government's MoU Excellence Award for the year 2006-07.

  • 8/6/2019 Secondary Data Pm&Fa

    32/41

    PGCIL has signed a loan agreement with Asian Development Bank (ADB), Manila

    for US$ 400 million on March 28th 2008, as well as in the same date, same month

    and same year the company has signed a loan agreement with The World Bank for

    USD 600 Million. As on May 1st of the year 2008, the Government granted coveted

    'Navratna' status to Power Grid Corporation of India Ltd, giving the transmission

    major financial autonomy to take independent decision on investments up to Rs 1,000

    crore. The company is looking to tap the potential of its telecom business and

    consultancy; the electricity towers could be an ideal place to locate the cellular phone

    transmission towers in the future.

    5.TORRENT POWER LTD

    Torrent Power Limited (TPL) is an integrated power company engaged in the

    generation and distribution of electricity in the cities of Ahmedabad, Gandhinagar and

    Surat in the state of Gujarat and Bhiwandi Franchise in Maharashtra. TPL was

    incorporated in 29th April of the year 2004 as Torrent PowerTrading Private Limited.

    Torrent brought together three of its group companies during the year 2004-05,

    Torrent Power AEC Limited, Torrent Power SEC Limited and Torrent Power

    Generation Limited under a single, unified brand as Torrent Power. Government of

    India conferred Gold shield for best performance in power distribution for the years

    2004-05 and also for 2005-06. TPL and Siemens created a 50:50 JV to provide O&M

    services to its SUGEN 1147.5 MW CCPP in the year 2005-06. The Company had

    awarded EPC contract for its SUGEN 1147.5 MW CCPP to a consortium of Siemens

    AG and Siemens Ltd. India; commenced construction of its first power block. The

    Company had entered into a Joint Venture with Power Grid Corporation of India

    Limited (PGCIL) in the same year 2005-06 for setting up dedicated transmission lines

    of 440 KV for evacuation of power from 1100 MW SUGEN project to Ahmedabad

    distribution area and to the National Grid through connectivity with PGCIL at

    Dehgam and Loop In Loop Out of Gandhar-Vapi line. The name of the company was

    changed to Torrent Power Private Limited in 25th January of the year 2006.

    Consequent to the conversion of the company into a Public Limited Company in 8th

    February of the year 2006, the company came to be called as Torrent Power Limited.

  • 8/6/2019 Secondary Data Pm&Fa

    33/41

    As at 20th December 2006, the company had signed a distribution franchise

    agreement for a period of ten years for the Bhiwandi circle in Maharashtra with

    Maharashtra State Electricity Distribution Company Limited (MSEDCL). The

    Company had commenced Distribution Franchise Bhiwandi circle of catering to 1.4

    lakh customers with an unrestricted demand of about 700 MW in 26th January of the

    year 2007. TPL had signed a memorandum of understanding (MoU) with Gujarat

    Power Corporation in May of the year 2007 for setting up over 1000-MW coal based

    power project at Pipavav, dist. Amreli in Gujarat. TPL made tie up with Gujarat State

    Petronet Limited for the gas transportation in line with project requirement. The

    Company had enhanced power transformation capacity during the year 2007-08 about

    371 MVA by commissioned of two 220 kV substations at Surat and one 33 kV

    substation at Ahmedabad. CRISIL had assigned AA-& P1+ ratings to the company's

    bank facilities in March of the year 2008.

  • 8/6/2019 Secondary Data Pm&Fa

    34/41

    RATIO ANALYSIS

    Financial ratio analysis can reveal much about a company and its operations. However,

    there are several points to keep in mind about ratios. First, a ratio is a "flag" indicating

    areas of strength or weakness. One or even several ratios might be misleading, but when

    combined with other knowledge of a company's management and economic

    circumstances, financial analysis can tell much about a corporation. Second, there is no

    single correct value for a ratio. The observation that the value of a particular ratio is too

    high, too low, or just right depends on the perspective of the analyst and on the company's

    competitive strategy. Third, financial ratios are meaningful only when compared with

    some standard, such as an industry trend, ratio trend, a trend for the specific company

    being analyzed, or a stated management objective.

    Key Ratios

    1. Debt-to-equity ratio:A debt-to-equity ratio, which is the total debt of an entity divided by the total equity

    of that entity, is a measure of the use of leverage or a measure of risk. Leverage is the

    use of other people's money to make money. In its simplest form, it is borrowing

    money from someone at a stated interest rate (such as 8%) and then investing that

    money in a project that earns a greater return than this stated rate (such as a 12%

    return). Leverage results in great profitability--when it works--because an entity is

    earning profits without having to invest any of its own money to get that return. The

    greater an entity's debt-to equity ratio, the greater is the use of other people's money to

    make money. The greater an entity's debt-to-equity ratio, the greater is the opportunity

    for high returns for that entity. The debt-to-equity ratio is also a measure of risk since

    the more debt that is used, the greater the risk that the entity might be forced to

    liquidate and go out of business.

    2. Long Term Debt-to-equity Ratio:It is a capitalization ratio comparing long-term debt to shareholders' equity. Its a

    measure of a company's financial leverage calculated by dividing its total liabilities by

    stockholders' equity. It indicates what proportion of equity and debt the company is

    using to finance its assets. Sometimes only interest-bearing, long-term debt is used

  • 8/6/2019 Secondary Data Pm&Fa

    35/41

  • 8/6/2019 Secondary Data Pm&Fa

    36/41

    iii. Inventory turnover:Its a ratio showing how many times a company's inventory is sold and replaced

    over a period. This ratio measures the stock in relation to turnover in order to

    determine how often the stock turns over in the business. It indicates the

    efficiency of the firm in selling its product. It is calculated by dividing the cost of

    goods sold by the average inventory. Inventory represents one of the most

    important assets that most businesses possess, because the turnover of inventory

    represents one of the primary sources of revenue generation and subsequent

    earnings for the company's shareholders/owners. Possessing a high amount of

    inventory for long periods of time is not usually good for a business because of

    inventory storage and obsolescence costs. However, possessing too little inventory

    isn't good either, because the business runs the risk of losing out on potential sales

    and potential market share as well. The days in the period can then be divided by

    the inventory turnover formula to calculate the days it takes to sell the inventory

    on hand or "inventory turnover days".

    iv. Debtors Turnover Ratio:This ratio indicates the relation between net credit sales and average accounts

    receivables of the years. Its also known as debtors velocity. This ratio indicates

    the efficiency of the concern to collect the amount due from debtors. It determines

    the efficiency with which the trade debtors are managed. Higher the ratio, better it

    is as it proves that the debts are being collected very quickly.

    v. ROCE (Return on Capital Employed):ROCE is used in finance as a measure of the returns that a company is realizing

    from its capital employed. It is commonly used as a measure for comparing the

    performance between businesses and for assessing whether a business generates

    enough returns to pay for its cost of capital.

    vi. RONW (Return on Net Worth):RONW is the ratio of net income after taxes to total net worth at the end of the

    year. This ratio indicates the return on stockholder's total equity. Also known as

    Return on equity which measures a corporation's profitability by revealing how

    much profit a company generates with the money shareholders have invested.

  • 8/6/2019 Secondary Data Pm&Fa

    37/41

    FUNDAMENTAL ANALYSIS

    Fundamental analysis is the examination of the underlying forces that affect the well

    being of the economy, industry groups, and companies. As with most analysis, the

    goal is to derive a forecast and profit from future price movements. At the company

    level, fundamental analysis may involve examination of financial data, management,

    business concept and competition. At the industry level, there might be an

    examination of supply and demand forces for the products offered. For the national

    economy, fundamental analysis might focus on economic data to assess the present

    and future growth of the economy. To forecast future stock prices, fundamental

    analysis combines economic, industry, and company analysis to derive a stock's

    current fair value and forecast future value. If fair value is not equal to the current

    stock price, fundamental analysts believe that the stock is either over or under valued

    and the market price will ultimately gravitate towards fair value. Fundamentalists do

    not heed the advice of the random walkers and believe that markets are weak-form

    efficient. By believing that prices do not accurately reflect all available information,

    fundamental analysts look to capitalize on perceived price discrepancies.

    Strengths of Fundamental Analysis

    1.

    Long-term Trends

    Fundamental analysis is good for long-term investments based on long-term

    trends, very long-term. The ability to identify and predict long-term economic,

    demographic, technological or consumer trends can benefit patient investors who

    pick the right industry groups or companies.

    2. Value Spotting

    Sound fundamental analysis will help identify companies that represent a goodvalue. Some of the most legendary investors think long-term and value. Graham

    and Dodd, Warren Buffett and John Neff are seen as the champions of value

    investing. Fundamental analysis can help uncover companies with valuable assets,

    a strong balance sheet, stable earnings, and staying power.

  • 8/6/2019 Secondary Data Pm&Fa

    38/41

    3. Business AcumenOne of the most obvious, but less tangible, rewards of fundamental analysis is the

    development of a thorough understanding of the business. After such painstaking

    research and analysis, an investor will be familiar with the key revenue and profitdrivers behind a company. Earnings and earnings expectations can be potent

    drivers of equity prices. Even some technicians will agree to that. A good

    understanding can help investors avoid companies that are prone to shortfalls and

    identify those that continue to deliver. In addition to understanding the business,

    fundamental analysis allows investors to develop an understanding of the key

    value drivers and companies within an industry. A stock's price is heavily

    influenced by its industry group. By studying these groups, investors can better

    position themselves to identify opportunities that are high-risk (tech), low-risk(utilities), growth oriented (computer), value driven (oil), non-cyclical (consumer

    staples), cyclical (transportation) or income-oriented (high yield).

    4. Knowing Who's WhoStocks move as a group. By understanding a company's business, investors can

    better position themselves to categorize stocks within their relevant industry

    group. Business can change rapidly and with it the revenue mix of a company.

    This happened too many of the pure Internet retailers, which were not really

    Internet companies, but plain retailers. Knowing a company's business and being

    able to place it in a group can make a huge difference in relative valuations.

    Weaknesses of Fundamental Analysis

    1. Time ConstraintsFundamental analysis may offer excellent insights, but it can be extraordinarily

    time-consuming. Time-consuming models often produce valuations that are

    contradictory to the current price prevailing on Wall Street. When this happens,

    the analyst basically claims that the whole street has got it wrong. This is not to

    say that there are not misunderstood companies out there, but it is quite brash to

    imply that the market price, and hence Wall Street, is wrong.

  • 8/6/2019 Secondary Data Pm&Fa

    39/41

    2. Industry/Company SpecificValuation techniques vary depending on the industry group and specifics of each

    company. For this reason, a different technique and model is required for different

    industries and different companies.T

    his can get quite time-consuming, which canlimit the amount of research that can be performed. A subscription-based model

    may work great for an Internet Service Provider (ISP), but is not likely to be the

    best model to value an oil company.

  • 8/6/2019 Secondary Data Pm&Fa

    40/41

    PORTFOLIO MANAGEMENT

    Portfolio theory is an investment approach developed by University of Chicago

    economist Harry M. Markowitz (1927 - ), who won a Nobel Prize in economics in

    1990.

    Portfolio theory allows investors to estimate both the expected risks and returns,

    as measured statistically, for their investment portfolios.

    Markowitz described how to combine assets into efficiently diversified portfolios.

    It was his position that a portfolio's risk could be reduced and the expected rate of

    return could be improved if investments having dissimilar price movements were

    combined.

    In other words, Markowitz explained how to best assemble a diversified portfolio

    and proved that such a portfolio would likely do well.

    PORTFOLIO STRATEGY

    There are two types of Portfolio Strategies:

    A. Passive Portfolio Strategy:It is a strategy that involves minimal expectational input, and relies on

    diversification to match the performance of some market index. A passive

    strategy assumes that the marketplace will reflect all available information in

    the price paid for securities.

    B. Active Portfolio Strategy:

    It is a strategy that uses available information and forecasting techniques toseek a better performance than a portfolio that is simply diversified broadly.

  • 8/6/2019 Secondary Data Pm&Fa

    41/41

    Moreover, there are three more types of Portfolios:

    1. The Patient Portfolio:This type invests in well-known stocks. Most pay dividends and are candidates

    to buy and hold for long periods. The vast majority of the stocks in this

    portfolio represent classic growth companies, those that can be expected to

    deliver higher earnings on a regular basis regardless of economic conditions.

    2. The Aggressive Portfolio:This portfolio invests in "expensive stocks" (in terms of such measurements as

    price-earnings ratios) that offer big rewards but also carry big risks. This

    portfolio "collects" stocks of rapidly growing companies of all sizes, that overthe next few years are expected to deliver rapid annual earnings growth.

    Because many of these stocks are on the less-established side, this portfolio is

    the likeliest to experience big turnovers over time, as winners and losers

    become apparent.

    3. The Conservative Portfolio:They choose stocks with an eye on yield, as well as earnings growth and a

    steady dividend history.