second lhc splice review

19
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski, Z. Charifoulline, G. D’Angelo, M. Koratzinos, J. Steckert, H. Thiesen, A. Verweij

Upload: gil

Post on 24-Jan-2016

34 views

Category:

Documents


0 download

DESCRIPTION

Second LHC Splice Review. Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices. K. Brodzinski, Z. Charifoulline, G. D’Angelo, M. Koratzinos, J. Steckert, H. Thiesen, A. Verweij. H. Thiesen 28 November 2011. CSCM possible QC tool for consolidation splices. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Second LHC Splice Review

1

Second LHC Splice Review

Copper Stabilizer Continuity Measurementpossible QC tool for consolidated splices

H. Thiesen 28 November 2011

K. Brodzinski, Z. Charifoulline, G. D’Angelo, M. Koratzinos, J. Steckert,H. Thiesen, A. Verweij

Page 2: Second LHC Splice Review

2

CSCM possible QC tool for consolidation splices

Outline

• Project motivations and objectives• Tests description• Powering implementation• Circuit protection• Cryogenic issues• Main risks• Planning and impact• Conclusion

H. T

hie

sen

– 2

8 N

ove

mb

er 2

011

Page 3: Second LHC Splice Review

3

Project motivations and objectives

Recommendation:

(R9) Launch the Copper Stabilizer Continuity Measurements Project aimed at the measurement of all the copper stabilizer joints in all the LHC sectors during the technical stop at the end of 2011. On the basis of these measurements the safe 2012 operation beam energy can then be determined.

Conclusions of Steve Myers from Chamonix 2011: Recommendations of the 3rd MAC meeting:

• The CSCM project was launched after Chamonix 2011 to identify for each main circuits (MB and MQ) the maximum safe current.

• The main objective is a possible increase of energy in 2012.

H. T

hie

sen

– 2

8 N

ove

mb

er 2

011

Page 4: Second LHC Splice Review

t1 t2

500 A

4-6 kA

60 s

PC in voltage mode PC in current mode

Trip by mQPS th

T = 20 K

I_circuit, V_bus

t

• CSCM tests consist to reproduce similar conditions to those during a quench, but w/o energy stored in the magnets so that the thermal runaway can safely be stopped by an interlock process.

• This is achieved by doing the test at a temperature of about 20K, so that the magnets are no longer superconducting and the current passes through the bypass diodes connected to all main magnets.

Test descriptionH

. Th

iese

n –

28

No

vem

ber

201

1

Page 5: Second LHC Splice Review

5

• During the test the busbar segment voltages are measured to detect the runaway.

• Maximum safe current of the circuit can be calculated with the time delay and the current level.

0

50

100

150

200

250

300

350

0

1000

2000

3000

4000

5000

6000

7000

0 10 20 30 40 50 60

Peak

tem

pera

ture

[K]

Curr

ent [

A]

Time [s]

Current

Tpeak

0

40

80

120

160

200

0 10 20 30 40 50 60

Volt

age

[mV]

Time [s]

Vres

Vind

Vres+Vind

Test descriptionH

. Th

iese

n –

28

No

vem

ber

201

1

time delay

Board A

Page 6: Second LHC Splice Review

6

• The CSCM does not measure the quality of each splice. It can only identify the worst one.

Limitation of CSCM

Cool down

CSCM tests

Runaway

Warm up

repair

OK

no

yes

H. T

hie

sen

– 2

8 N

ove

mb

er 2

011 Warm-up and repair is only needed if the

current at which the machine will run is larger than the safe current deduced from the CSCM test.

Page 7: Second LHC Splice Review

What can the CSCM measure?

• The CSCM can also measure:

• All 13 kA current lead-busbar connections at the DFB

• All bypass diode paths

H. T

hie

sen

– 2

8 N

ove

mb

er 2

011

Page 8: Second LHC Splice Review

Test implementation

• LHC has been designed to operate the main dipole and quadrupole magnets with super fluid helium at 1.9K.

• CSCM requests to operate the main MB and MQ magnets with gaseous helium at 20 K.

• Special cryogenic control to maintain the arc at 20K

• Special powering configuration to inject 6kA in the circuits

• Special protection system to protect the circuits during the powering tests

• The new powering configuration and the circuit protection system have to be designed and commissioned as permanent systems

H. T

hie

sen

– 2

8 N

ove

mb

er 2

011

Page 9: Second LHC Splice Review

9

Powering configuration

RB circuit RQ circuits (in series)

Open circuit Short circuit Open circuit Short circuit

• The voltage delivered by RB (190V) and RQ (18V) power converters are not enough for the CSCM tests:

• 1.7 < Vdiode < 2 V at 20 K (assumption)

Þ Modification of actual RB power converter to obtain the requested voltage

H. T

hie

sen

– 2

8 N

ove

mb

er 2

011

Page 10: Second LHC Splice Review

10

Powering configuration

• Modification of RB power converter

Normal configuration CSCM configuration

U_out

I_out

Tests in P-Hall with 4 W load

U_bridge

U_out

L

L L

L

H. T

hie

sen

– 2

8 N

ove

mb

er 2

011

Same modified power converter (RB) for the both circuits (MB and MQs)

Page 11: Second LHC Splice Review

11

Powering configuration

• RB powering configuration

-1000

0

1000

2000

3000

4000

5000

6000

7000

0 0.05 0.1 0.15 0.2 0.25 0.3 0.35

2*EE

0*EE

time (s)

current (A)

< 350 ms

Vdiode = 0.7 VL = 5 mHVout Pc = 0V

RB 300 V300V

1x240mm2 1x240mm2

• RQ powering configuration

RQD

RQF

RB300V

H. T

hie

sen

– 2

8 N

ove

mb

er 2

011

0

1000

2000

3000

4000

5000

6000

7000

0 0.2 0.4 0.6 0.8 1 1.2

2*EE

1*EE

0*EE

0.25

0.36

0.85

time (s)

current (A)Vdiode = 0.7 VL = 10 mHVout PC = 0 V

• Main challenge = How to control the current in the “diode circuits” ?• 5 bars have to be maintained in the cryostat to have 400V insulation

voltage at 20K

Page 12: Second LHC Splice Review

12

CSCM protection system

• During the powering tests, the CSCM protection system have to protect:

• Busbar segments

• Current lead

• Magnets

PC

Current LeadsExisting DQQDC detector(3mV 100ms)

BB splice & diode BB -> mDQQBS board

Diode/MagnetDQQDS measures voltage over 4 magnets if difference is > threshold, current will be cut

Umag

Ures

Current LeadsExisting DQQDC detector(3mV 100ms)

Global BB detector (monitoring)EE system is bridged

PICInterlock Loop from QPS

EE system bridged

H. T

hie

sen

– 2

8 N

ove

mb

er 2

011

Page 13: Second LHC Splice Review

13

CSCM protection system

• Busbar protection system

H. T

hie

sen

– 2

8 N

ove

mb

er 2

011

Recorded mDQQBS buffer, stimulated with simulated signal for a bad splice

Usplice

dv/dt splice

dv/dt threshold

absolute thresholdramp

plateau

1000 boards are in production and will be delivered in December 2011

Page 14: Second LHC Splice Review

14

CSCM protection system

• Tests in SM18

H. T

hie

sen

– 2

8 N

ove

mb

er 2

011

T5

Conn

ecti

on

Conn

ecti

on

VT1

VT5 VT4

VT13

VT3

VT12VT6

VT7

VT8

VT9

VT10 VT2 VT11

T1

T2

T3

T4 T6

mBS

VT1-13L=11.4m

I2C/

SPI

mBS, board A

mBS, board B

IMAX=5.1kAdI/dt = 200A/sT = 14.5K

UBUS

dV/dt

The busbar segment protection system has been tested in SM18• 10 m of MQ busbar• 50 mm single-sided defect

Page 15: Second LHC Splice Review

Special cryogenic condition

0

5

10

15

20

25

2010

/12/

11 0

0:00

2010

/12/

11 0

3:32

2010

/12/

11 0

7:04

2010

/12/

11 1

0:36

2010

/12/

11 1

4:08

2010

/12/

11 1

7:40

2010

/12/

11 2

1:12

2010

/12/

12 0

0:44

2010

/12/

12 0

4:16

2010

/12/

12 0

7:48

2010

/12/

12 1

1:20

2010

/12/

12 1

4:52

2010

/12/

12 1

8:24

2010

/12/

12 2

1:56

2010

/12/

13 0

1:28

2010

/12/

13 0

5:00

2010

/12/

13 0

8:32

2010

/12/

13 1

2:04

2010

/12/

13 1

5:36

2010

/12/

13 1

9:08

2010

/12/

13 2

2:40

2010

/12/

14 0

2:12

2010

/12/

14 0

5:44

2010

/12/

14 0

9:16

2010

/12/

14 1

2:48

2010

/12/

14 1

6:20

2010

/12/

14 1

9:52

2010

/12/

14 2

3:24

2010

/12/

15 0

2:56

2010

/12/

15 0

6:28

2010

/12/

15 1

0:00

2010

/12/

15 1

3:32

2010

/12/

15 1

7:04

2010

/12/

15 2

0:36

Tem

pera

ture

[K]

C1109_11L4_TTAVG.POSST

C11L4_11L4_TTAVG.POSST

C13L4_13L4_TTAVG.POSST

C1513_15L4_TTAVG.POSST

C15L4_15L4_TTAVG.POSST

C17L4_17L4_TTAVG.POSST

C1917_19L4_TTAVG.POSST

C19L4_19L4_TTAVG.POSST

C21L4_21L4_TTAVG.POSST

C2321_23L4_TTAVG.POSST

C23L4_23L4_TTAVG.POSST

C25L4_25L4_TTAVG.POSST

C2725_27L4_TTAVG.POSST

C27L4_27L4_TTAVG.POSST

C29L4_29L4_TTAVG.POSST

C3129_31L4_TTAVG.POSST

C31L4_31L4_TTAVG.POSST

C33L4_33L4_TTAVG.POSST

conditioning

stabilization

RRR tests

Homogeneity over a sector length for RRR

• Requested cryogenic conditions can be provided with good stability and homogeneity over a sector length: ARC at 20 K and 5 bars, DFBs cooled with 20 K GHe to maintain the current lead at nominal condition (TT891A@50K)

• Proposed cooling of DFBs have to be analyzed in more in details

• Particularity of busbar interface between DFB/Q7 interface to be studied

• Recovery after each powering test is estimated at 5 hours

Page 16: Second LHC Splice Review

16

CSCM main risks

• CSCM tests

• During the CSCM tests the main risks (extremely small) are to damage a splice, a diode, a magnet or a DFBA (current leads or splice).

• Splice or diode are “easy” to repair (warm up, repair, cool down, CSCM tests)

• Magnet is “easy” to replace if spare is available (warm up, replace, etc…).

• DFBA is more complex to repair: must be transport to the surface.

H. T

hie

sen

– 2

8 N

ove

mb

er 2

011

• Recovery

• Important modification have to be done to realize the CSCM tests

• The main risk is to do a mistake during the recovery

• The risk can be mitigate to acceptable level by procedure for reconfiguration, test and (re)commissioning.

Page 17: Second LHC Splice Review

17

CSCM planning

• CSCM tests request time and resources

H. T

hie

sen

– 2

8 N

ove

mb

er 2

011

s1 s2

s3 s4

s5 s6

s7 s8

Brief estimation of time• 2 sectors in parallel• 2 weeks for preparation• 2 weeks for the tests• 2 weeks for the recovery and recommissioning

18 weeks (4.5 months) to tests the LHC

- Planning can be optimized to reduce the time at 3.5 or 2.5 months

- Preparation time can be done in parallel with the other LS1 activities

- But powering tests can be done only during the night- CSCM campaign requests resources: 8 to 10 tech. or

Eng.

Page 18: Second LHC Splice Review

18

CSCM planning

• If CSCM tests must be realized after the consolidation of the splices:

• The project have to be approved in March - April 2012

• Type test has to be realized in one sector at the beginning of the LS1 (6 weeks)

• CSCM campaign has to be integrated in the LS1

H. T

hie

sen

– 2

8 N

ove

mb

er 2

011

Page 19: Second LHC Splice Review

19

Conclusion

• CSCM tests can be used to qualify the LHC at 7 TeV after the splice consolidation: qualification of the splices, diode paths and current lead – busbar connections

• CSCM tests require to modify several critical systems as QPS, 13kA-EE, PIC and PC: full re-commissioning (IST and powering tests) is mandatory.

• Cryogenic conditions can be provided with good stability and homogeneity over a sector length but proposed cooling of the DFBs has to be analyzed in details.

• CSCM tests will interfere with other LS1 activities

• CSCM tests present some risks (extremely small): damage a splice or a DFB/CL can not be excluded

• CSCM tests require time (2.5-3.5 months) and resources (8-10 technicians-Engineers)

• Engineering challenges are being met and a test and simulation program is under way (validation of protection system, correlation between 20 K and 1.9 K, control of power converter)

• No show stoppers found so far but there are some open issue as PC current control.

H. T

hie

sen

– 2

8 N

ove

mb

er 2

011