    Center City ConnectorCity Council Transportation Committee BriefingJuly 9, 2013

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    2/36

    Presentation Overview

    Background Timeline

    Goals

    Public engagement

    Evaluation process and results Next steps

    2

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    3/36

    Background

    Transit Master Plan priority Increase transit capacity

    Enhance transit service

    quality and reliability

    Improve transit options for

    people traveling between

    and within Center City

    neighborhoods and

    attractions

    3

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    4/36

    Project Need

    4

    Significant population and employment growth downtown

    Growing demand for circulation trips and last-mile connections

    Special mobility needs of tourists, visitors, and casual users

    Affordable access to key social and human services

    Connections for low-income workers

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    5/36

    From Plan to Built Project

    Center CityConnector

    Transit Study

    5

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    6/36

    Study Timeline

    6

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    7/36

    Project Goals

    7

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    8/36

    Stakeholder Interviews

    8

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    9/36

    Public Engagement

    Open Houses

    9

    Media Outreach

    Stakeholder Interviews Community Meetings

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    10/36

    Study Evaluation Process

    10

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    11/36

    Study Evaluation Process

    11

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    12/36

    Initial Screening - Modes

    12

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    13/36

    Tier 1 Modes - Streetcar

    13

    Exclusive vs mixed

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    14/36

    Initial Screening - Alignments

    14

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    15/36

    Tier 1 Alignment Alternatives

    4th and 5th Avenue Couplet

    15

    1st Avenue

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    16/36

    1st Avenue

    16

    Exclusive & Mixed-Traffic Alternatives operate in center lane

    1st @

    Madiso

    n

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    17/36

    4th and 5th Avenue Couplet

    Exclusive Alternative has two transit-only lanes on 4th Avenue

    (below)

    17

    4th@M

    arion

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    18/36

    4th and 5th Avenue Couplet

    5th Avenue cross section is the same for Exclusive & Mixed-Traffic

    Exclusive transit lane only feasible Spring to Cherry

    18

    5th@

    Columb

    ia

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    19/36

    Tier 1 Analysis

    Purpose: To narrow

    alternatives for more

    detailed evaluation in

    Tier 2

    5 goals, 15 measures

    Scorecard approach

    Rated (Best, Good,

    Fair, Poor)

    19

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    20/36

    Key Findings from Tier 1 Analysis

    Ridership demand is comparablefor both alignments

    1st Avenue Exclusive alternativehas fastest travel time betweenWestlake and Jackson

    4th/5th alignments have moremodal conflicts and increasetravel time (vs. no build) for morenon-streetcar travelers

    1st

    Avenue provides greateropportunity to spurredevelopment, improve streetconditions, and support localbusiness districts

    20

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    21/36

    June Open House

    21

    0% 50% 100%

    1st Avenue

    4th/5th AvenuesExclusive

    Exclusive

    Mixed

    Mixed

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    22/36

    Open House - What Matters?

    22

    Connect

    Connect

    Enhance

    Thrive

    Thrive

    Sustain

    Develop

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    23/36

    What Matters to Agency Partners?

    Bus Operations Impacts

    23

    Additional Hours of Bus Passenger

    Delay (PM Peak Hour)

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    24/36

    What Matters to Key Stakeholders?

    24

    Modal integration bikes, auto traffic

    Support business districts, connect cultural/visitor attractions

    1st Avenue Supports More Visitor Activity

    4th/5th Avenues have more conflicts

    with local regional bus and planned

    bike facilities

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    25/36

    Alternatives Recommended to Advance to Tier 2

    25

    Considered with

    Ballard to Downtown

    Study Alignments

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    26/36

    Operating Plan Considerations

    26

    Options to interline Connector withSLU & First Hill

    Exclusive running alternatives will

    explore improvements to WestlakeSegment of SLU

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    27/36

    What happens next?

    Further define remaining alternatives

    Complete detailed analysis of

    alternatives

    Public Open House #3 Sept/Oct

    27

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    28/36

    28

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    29/36

    NELSON\NYGAARD CONSULTING ASSOCIATES 2013

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    30/36

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    31/36

    Stakeholder Interviews - Major Conclusions

    1st phase connect South Lake

    Union and First Hill

    Vast majority support 1stAvenue alignment

    Almost unanimous support forstreetcar vs. bus mode

    Most believe mixed-trafficoperations will be necessarygiven limited north-south rightsof way

    31

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    32/36

    Cumulative Result of Tier Evaluation Measures

    32

    0 5 10 15 20 25 30 35 40

    1st Exclusive

    1st Mixed

    4th/5th Exlusive

    4th/5th Mixed

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    33/36

    Delay to Bus Passengers

    33

    Additional Hours of Bus Passenger

    Delay (PM Peak Hour)

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    34/36

    Streetcar Travel Times

    34

    One-Way Streetcar Travel Times vs. Auto (No-Build)

    4th/5th Avenues 1st Avenue

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    35/36

    Access to Tourist and Visitor Destinations

    35

  • 7/27/2019 Seattle CC Transit Study COUNCIL July 9 FinalCC.pdf

    36/36

    Urban Form and Placemaking Opportunities