se-280 dr. mark l. hornick schedule planning & earned value

16
SE-280 Dr. Mark L. Hornick Schedule Planning & Earned Value

Upload: maria-cain

Post on 12-Jan-2016

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SE-280 Dr. Mark L. Hornick Schedule Planning & Earned Value

SE-280Dr. Mark L. Hornick

Schedule Planning &Earned Value

Page 2: SE-280 Dr. Mark L. Hornick Schedule Planning & Earned Value

SE-280Dr. Mark L. Hornick

2

So far, you have made project plans, which estimate the task time for project phases.

The work breakdown identifies the tasks necessary

for successful process completion.

Plan

Design

DLDR

Code

CR

Test

PM

A total time estimate is distributed across the tasks

(each task's effort is estimated)

Page 3: SE-280 Dr. Mark L. Hornick Schedule Planning & Earned Value

SE-280Dr. Mark L. Hornick

3

In addition to a project plan, you also often need a period plan (i.e. a calendar schedule)

A period plan links project tasks to specific dates, indicating the sequence of activities and projected milestones.

For non-trivial projects, both project and period plans are required, and they must be effectively

linked.

Page 4: SE-280 Dr. Mark L. Hornick Schedule Planning & Earned Value

SE-280Dr. Mark L. Hornick

4

To make a period plan, you must know the distribution of available "task hours".

Task hours represent the time spent on specific tasks in the project plan.

How many task hours should a team expect to have in a 40-45 hour week?

Total work time

Project Non-project

Task Non-task• Boolean• Necessary• Plannable• Worth planning

• Time logging• Team meetings• Brief consults• Brainstorming

• Other projects• Email• Training• Other meetings• Lunch

Page 5: SE-280 Dr. Mark L. Hornick Schedule Planning & Earned Value

SE-280Dr. Mark L. Hornick

5

Here is an example of making a period plan or schedule.

Task A: 10 hours

Task B: 8 hours

Task C: 7 hours

Task D: 3 hours

10

18

25

28

Week 1: 12 hours

Week 2: 5 hours

Week 3: 10 hours

Week 4: 9 hours

12

17

27

36Task E: 9 hours

37Week 5: 11 hours

47

Cumulative task time Cumulative schedule time

Page 6: SE-280 Dr. Mark L. Hornick Schedule Planning & Earned Value

SE-280Dr. Mark L. Hornick

6

Here is an example of making a period plan or schedule.

Task A: 10 hours

Task B: 8 hours

Task C: 7 hours

Task D: 3 hours

10

18

25

28

Week 1: 12 hours

Week 2: 5 hours

Week 3: 10 hours

Week 4: 9 hours

12

17

27

36Task E: 9 hours

37Week 5: 11 hours

47

Cumulative task time Cumulative schedule time

Page 7: SE-280 Dr. Mark L. Hornick Schedule Planning & Earned Value

SE-280Dr. Mark L. Hornick

7

From the schedule, we can identify task-completion milestones.

Task Scheduled task completion (week)

# 1 2 3 4 5

A 1 X

B 3 X

C 3 X

D 4 X

E 5 X

Page 8: SE-280 Dr. Mark L. Hornick Schedule Planning & Earned Value

SE-280Dr. Mark L. Hornick

8

The Planned Value (PV) of each task is the percentage it represents of the total planned project time.

TaskPlan hrs. PV%

Cum. hrs.

Cum. PV%

Plan wk.

A 10

B 8

C 7

D 3

E 9

Total 37

Cumulative PV by Week

0

10

20

30

40

50

60

70

80

90

100

0 1 2 3 4 5 6

WeekC

um

. P

V

27.0

21.6

18.9

8.1

24.3

100

10 27.0

18 48.6

25 67.6

28 75.7

37 100.0

1

3

3

4

5

Page 9: SE-280 Dr. Mark L. Hornick Schedule Planning & Earned Value

SE-280Dr. Mark L. Hornick

9

Earned value (EV) represents the cumulative planned value of completed tasks, even if they are not completed in the planned sequence.

Week Task PV% EV%Cum.

EV

1 A

D

2 B

3 --

4 C

5 --

6 E

Cumulative PV/EV by Week

0

10

20

30

40

50

60

70

80

90

100

0 1 2 3 4 5 6 7

Week

27.027

8.1

21.6 21.6

-- --

18.9 18.9

-- --

24.3 24.3

27

56.7

56.7

75.6

75.6

100.0

Page 10: SE-280 Dr. Mark L. Hornick Schedule Planning & Earned Value

SE-280Dr. Mark L. Hornick

10

This simplified example illustrates some possible planning problems.

The task granularity (size) is too large for meaningful planning, and some plan/actual weeks have no

completed tasks.

Generally, each team member should complete 1-2 tasks per week. This implies that tasks should normally be less than 10 hours,

depending on the task hours available.

Page 11: SE-280 Dr. Mark L. Hornick Schedule Planning & Earned Value

SE-280Dr. Mark L. Hornick

Process Dashboard supports task and schedule planning for individual engineers and teams

Page 12: SE-280 Dr. Mark L. Hornick Schedule Planning & Earned Value

SE-280Dr. Mark L. Hornick

12

Process Dashboard can generate earned value charts and forecasts.

Page 13: SE-280 Dr. Mark L. Hornick Schedule Planning & Earned Value

SE-280Dr. Mark L. Hornick

13

Experience with TSP teams indicates that engineers love to earn value!

Earned value can help motivate team members to:

Finish a "close to completion" task.

Push through a less desirable task.

Avoid distractions (tasks not in the plan).

Page 14: SE-280 Dr. Mark L. Hornick Schedule Planning & Earned Value

What is the appropriate time scale for project schedule planning?

When the environment and requirements change very slowly, it may be practical to plan for years at a time. (Not very common any more.)

Page 15: SE-280 Dr. Mark L. Hornick Schedule Planning & Earned Value

What is the appropriate time scale for project schedule planning?

When the environment and requirements change very slowly, it may be practical to plan for years at a time. (Not very common any more.)

Due to “learning”, it is difficult to make detailed plans for more than 10-13 weeks at a time.(High-level, less detailed project plans may still have a place for 12- to 24-month or even longer timeframes.)

Page 16: SE-280 Dr. Mark L. Hornick Schedule Planning & Earned Value

What is the appropriate time scale for project schedule planning?

When the environment and requirements change very slowly, it may be practical to plan for years at a time. (Not very common any more.)

Due to “learning”, it is difficult to make detailed plans for more than 10-13 weeks at a time.(High-level, less detailed project plans may still have a place for 12- to 24-month or even longer timeframes.)

All planning takes some time, so very short (< 4 weeks) intervals may result in excessive planning overhead. (Planning for subsequent cycles can often be done in less time than the initial cycle/project planning.)