scope of services - etenders.gov.za. part c3.2 sos... · scope of services ... compilation of the...
TRANSCRIPT
Document Title:
SCOPE OF SERVICES
Project Title:
PROFESSIONAL SERVICES FOR OWNERS TEAM TO
COLABORATE WITH TRANSNET PIPELINES IN THE
COMPILATION OF THE EPCM SCOPE OF WORK AS
WELL AS MANAGEMENT OF THE FEL 1 PHASE
(WITH AN OPTION TO EXTEND INTO OTHER
PHASES UNTIL CLOSE-OUT) OF THE PROJECT AS
PER TRANSNET PLP METHODOLOGY FOR THE
PIPELINE CONSTRUCTIONS AND FACILITIES
PROJECT
REVISION 07: FOR TENDER
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 2 of 34 Rev 7
CHANGE CONTROL DOCUMENT PREPARATION
Compiled by S. Shange Projects Manager
Reviewed by A. N. Thoolsiram Projects Manager
B. S. Panday Capital Projects Manager
C. A. Parsons MC&I Manager
D. B. Burger Electrical Manager
E. A. Fabricius Mechanical Manager
F. M. Beneke Pipeline Integrity Manager
E. v Blerk Project Liaison manager
M Pilime Operations Support Manager
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 3 of 34 Rev 7
1. GLOSSARY
AC - Acquisition Council
ALR - Alrode
APT - Airport
AVTUR - Aviation Turbine Fuel
BOQ - Bill of Quantities
BDAC - Board and Acquisition Council
CAPIC - Capital Investment Committee
CF2 - Clean Fuels Act 2
CP - Cathodic Protection
DJP - Durban Johannesburg Pipeline
EDS - Engineering Design Specification (document used for software development)
EPCM - Engineering, Procurement and Construction Management
ETC - Estimate to Complete
EXCO - Executive Committee
FEL - Front End Loading
FEED - Front End Engineering and Design
EIA - Environmental Impact Assessment
E&I - Electrical and Instrumentation
EPCM - Engineering, Procurement and Construction Management
FFP - Fitness for Purpose
GIS - Geographic Information System
HAZOP - Hazardous and Operability Study
H&S - Health and Services
ICT - Information and Communications Technology
ISO - International Standards Organisation
IVW - Coastal Terminal
JMP - Jameson Park Terminal
KEN - Kendal
KRO - Kroonstad
MC&I - Metering Control and Instrumentation
LSD - Low Sulphur Diesel
LLA - Langlaagte
MCC - Master Control Centre
NEC - Mew Engineering Contract
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 4 of 34 Rev 7
NOC - National Operating Centre
NKP - National Key Point
NMPP - New Multi Product Pipeline
OHS - Occupational Health and Safety
ORTIA - OR Tambo International Airport
P&ID - Process and Instrument Diagram
PEP - Project Execution Plan
PII - Pipeline Integrity International
PL - Pipeline
PLP - Project Lifecycle Process
PPM - Procurement Procedures Manual
RFP - Request for Proposal
SAT - Site Acceptance Test
SBG - Sasolburg
HSERQ - Safety, Health, Environmental, Risk & Quality
SANS - South African National Standards
SOC - State Owned Company
SIL - Safety Integrity Levels
TPL - Transnet Pipelines
ULSD - Ultra Low Sulphur Diesel
WAO - Waltloo
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 5 of 34 Rev 7
2. CONTENTS
1. GLOSSARY...................................................................................................... 3
2. CONTENTS ..................................................................................................... 5
3. TRANSNET PIPELINES BACKGROUND .............................................................. 7
4. PROJECT HISTORY AND BACKGROUND ........................................................... 7
5. PROJECT OBJECTIVE ...................................................................................... 9
6. PROJECT REQUIRMENTS ................................................................................. 9
7. TPL PROJECT EXECUTION STRATEGY ............................................................ 10
8. PROJECT CONTRACTING STRATEGY .............................................................. 11
9. SCOPE OF SERVICES ..................................................................................... 12
9.1 SCOPE OF SERVICE OVERVIEW ..................................................................... 13
9.2 LOCATION OF THE SITES AND ACCESS ......................................................... 14
9.3 GENERAL DESCRIPTION OF THE SERVICES .................................................... 14
9.4 DETAILED SCOPE OF THE PROJECT AS PER PLP PROCESSESS ........................ 16
9.4.1 FEL 1 – CONCEPT PHASE SCOPE .............................................................. 17
9.4.2 FEL 2 – PRE FEASIBILITY PHASE .............................................................. 20
9.4.3 FEL 3 –FEASIBILITY PHASE (BASIC ENGINEERING) ................................... 24
9.4.4 FEL 4–DETAILED ENGINERING ................................................................. 25
9.4.5 EXECUTION AND CLOSE OUT PHASE ........................................................ 26
9.4.6 REQUEST FOR PROPOSAL ........................................................................ 26
9.4.7 ROLE OF THE CONSULTANT WITHIN THE PROJECT CONTEXT ................... 27
9.4.8 PROCUREMENT ....................................................................................... 27
9.4.9 DATA TO BE SUPPLIED TO CONSULTANT ................................................. 27
9.4.10 COMPLIANCE WITH LAWS ..................................................................... 27
9.4.11 NON-ASSIGNMENT ............................................................................... 27
9.4.12 OWNERSHIP OF DOCUMENTS AND COPYRIGHT ..................................... 28
9.5 COMMUNICATIONS ....................................................................................... 29
9.6 DOCUMENTATION CONTROL ......................................................................... 30
9.7 INFORMATION AND COMMUNICATIONS TECHNOLOGY (ICT) ......................... 31
9.8 OFFICE SPACE .............................................................................................. 31
10. APPENDIX .................................................................................................... 32
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 6 of 34 Rev 7
10.1 APPENDIX A: MAP OF TRANSNET’S EXISTING PIPELINES’ NETWORK .............. 33
10.2 APPENDIX B: TRANSNET CAPITAL UNIVERSE ................................................. 34
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 7 of 34 Rev 7
3. TRANSNET PIPELINES BACKGROUND
Transnet Pipelines, a division of Transnet SOC Ltd, provides strategic pipeline infrastructure,
with associated world class pipeline logistics, for the petroleum and gas industries of South
Africa. This is done in partnership with our customers and stakeholders thereby assuring the
African sustainable development imperative. Established in 1965, Transnet Pipelines owns,
maintains and operates a network of some 3800km of high-pressure petroleum and gas
pipelines. Transnet Pipelines transports an average of 17 billion litres of fuel per annum. This
includes diesel, unleaded petrol, aviation turbine fuel and crude oil.
The pipeline network and the liquid fuels network depots traverses 5 provinces, KwaZulu-
Natal, Free State, Gauteng, North West and Mpumalanga. The intake stations are the two
refineries in Durban, the crude refinery at Coalbrook (Natref -Sasolburg) and the Synfuel
plants at Secunda (Sasol II and III). TPL transports petrochemical products through the
pipeline network comprising of underground steel pipelines, delivery depots and pump
stations as depicted in the attached map PPT 1604D. The pipeline is laid within a servitude,
which traverses through many properties (private, state owned, local authorities) with the
pump stations and delivery depots located in rural, industrial and suburban areas along the
pipeline routes.
The pipelines range from 6” (150mm) to 24” (600mm) in diameter. All the pipelines have
been constructed in accordance with the American Code ASME B31.4. Pressure in the
pipeline network is monitored 24 hours a day, 365 days a year in the current control centre in
Transnet Pipelines’ Head Office in Durban, with the future facility being at the NOC in Kirk
Road, Pinetown, KZN.
4. PROJECT HISTORY AND BACKGROUND
The Durban Johannesburg (DJP) petroleum products pipeline was the first pipeline to come
on stream at TPL and was commissioned in November 1965 for the then South African
Railways and Harbour Company, to transport petroleum products between Durban and
Johannesburg.
This 300mm (12”) diameter main line stretched over a distance of approximately 720km in
length and pump stations was located at Island View (later to be called Fuelflow), Hillcrest,
Howick, Ladysmith, Van Reenen, Bethlehem, Magdala (18km north of Kroonstad) and
Sasolburg, with take-off / delivery stations at Pietermaritzburg, Ladysmith, Bethlehem,
Kroonstad, Sasolburg, Alrode and Langlaagte.
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 8 of 34 Rev 7
In 1971 due to the construction of the Natref refinery at Sasolburg and the increased
demand for fuels in the interior additional pipeline extensions were commissioned. A 200mm
(8”) pipeline from Sasolburg via Potchefstroom to Klerksdorp was laid. A 300mm (12”)
extension from Alrode via Airport, Elardus Park and on to Waltloo in Pretoria was laid in
addition to a 200mm (8”) pipeline from Elardus Park to Pretoria West
In 2003 TPL began the process to construct the 24” multi product pipeline to replace the DJP
to what eventually became the New Multi-products Pipeline (NMPP).
To reduce the cash flow impact of the NMPP project on Transnet at that stage, the following
pipeline sections, namely;
Terminal 1 (IVW) to Terminal 2 (JMP), also known as PL1 (24” diameter)
JMP to Alrode (ALR) also known as PL2 (16” diameter)
ALR to Langlaagte (LLA) also known as PL3 (16” diameter)
And Kendal (KEN) to Waltloo (WAO) also known as PL4 (16” diameter)
were completed while other sections of the pipeline were deferred to phase 2 of the NMPP.
The deferred scope is:
Replacing the section of 12” DJP from Sasolburg to Kroonstad ( approx. 124km)
Replacing the section of 12” DJP from Alrode to Airport depot (and to Waltloo),
which is used as part of the coastal jet route. This is the alternate Jet fuel route to
the 6” Avtur line from SBG to O R Tambo Int. (via. Airport Depot). This replacement
plan was to provide new routing for the coastal jet from Jameson Park to the O R
Tambo International Airport (approx. 50km).
During the original study various alternatives were considered as part of the multi modal
logistics study with the most viable alternative being the construction of the respective
pipelines.
The DJP was commissioned in 1965 and although currently still in use, this pipeline will reach
the end of its technical and economic life and will be replaced by the new NMPP.
With NMPP Phase 1 not yet complete and only expected to be complete in 2017 and the
NMPP Phase 2 planning an uncertainty, there is a need to commence with planning for the
replacement of the pipelines from Sasolburg (SBG) to Kroonstad (KRO) and Alrode (ALR) to
Airport (APT) as there is the added risk of the DJP failing in service or TPL not being able to
sustain the integrity of the DJP.
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 9 of 34 Rev 7
Furthermore a report of the coastal jet study has indicated that while it is possible to
transport jet fuel in a common pipeline with ULSD, under Clean Fuels 2 (CF2) regulations, it
is not possible to deal with intermix within the typical pipeline operations i.e. refractionation
or blending, unless there is a high sulphur product in the transported product mix to use as
the ‘sacrificial’ product to blend into. Hence the need for a dedicated jet pipeline from
Jameson Park (JMP) to APT.
5. PROJECT OBJECTIVE
5.1 The project objective is to design, construct, commission and hand over:
An adequately sized and specified pipeline from TPL’s Jameson Park depot to
TPL’s Airport depot, an estimated distance of 50km,
And an adequately sized and specified pipeline from TPL’s Sasolburg depot to
TPL’s Kroonstad depot an estimated distance of 124km,
Upgrading of the associated facilities found on either ends of respective pipe
lines to cater for the relevant pipeline operational requirements,
by September 2022, within the allocated budget.
6. PROJECT REQUIRMENTS
6.1 The requirement is for the project to complete and handover the new legal, compliant
and adequately sized pipelines for TPL pipeline operations. This is to include the new
pipelines interfacing with the existing pipelines systems.
6.2 The pipeline is to align to TPL’s engineering standards and specifications in
conformance with ASME 31.4 code. The engineering is to include but not be limited
to the following requirements.
Operational and maintenance requirements (including Cathodic Protection (CP)
Process requirements
Civil requirements
Structural, mechanical, fire and piping requirements
Pipeline integrity requirements
Electrical requirements
Metering, control and instrument requirements
Business information systems requirements
6.3 The pipeline is to be designed and constructed in accordance with the regulatory and
compliance requirements as stipulated by the applicable legislation, including but not
be limited to the
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 10 of 34 Rev 7
Regulatory legislations
Environmental legislations
Health and Safety legislations
Construction legislation
6.4 The project is to be completed with little to no impact on TPL’s day to day operations.
6.5 Transnet’s policies and procedures are to be used throughout the project lifecycle and
should there be any deviation, the deviation is to be highlighted to the project
sponsor and or steering committee.
7. TPL PROJECT EXECUTION STRATEGY
All of the capital projects in the TPL capital projects portfolio are managed according to the
PLP methodology. The Project Lifecycle Process, referred to as the PLP, is the methodology
for the effective management of capital investment projects within Transnet to ensure that
all projects are managed with a consistent approach. The study phases, or Front End
Loading (FEL) phases, are crucial to the successful implementation of the execution and
finalization phases. The term Front End Loading is a term commonly used to illustrate the
value and opportunity that may be realized by doing upfront work in the early study phases
of the project lifecycle when there is still potential to influence the successful outcome of the
project. A gate review is conducted by an independent team at the end of each study phase
to determine whether the work in that phase has been done with sufficient thoroughness for
the project to proceed to the next phase. The PLP is broken up into 6 sequential phases
namely;
Front End Loading (FEL) 1 or concept Phase: where the project options are defined and
the engineering is completed up to 10%.
FEL2 or prefeasibility phase: where the optimum option is selected and detailed up to
30% of engineering.
FEL3 or feasibility phase: where the project is defined and the execution planning of
the project completed. The engineering of the project at the end of the FEL3 phase is
approximately 70% complete. The scopes of works are to be complete and approved
for tender stage.
FEL4 or detailed design phase: Where the designs are detailed to approved for
construction stage. (AFC) The engineering is complete up to 100%
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 11 of 34 Rev 7
And the execution phase: where the project is implemented. This includes all testing
and commissioning up to plant / equipment handover.
Close out phase: This is the final phase and includes commercial, financial and
technical closure of the project.
The picture below represents the various phases of the project life cycle planning process and is
intended to graphically illustrate the weighting of the commercial and technical stream as the
project progresses through the phases.
Picture 1: technical versus commercial streams
8. PROJECT CONTRACTING STRATEGY
During the various phases of the project the employer will split the services required in
distinct contracts or contract groups.
Contract Group 1 (Owners Team) – Contract(s) will be entered into with service
provider(s) who will provide hydrocarbon pipeline engineering consulting services to the
employer based on their specialist pipeline experience and knowledge. This service will
be rendered for the FEL 1 phase with an option to extend to other FEL Phases should
Transnet Pipelines choose to do so. It is anticipated that this will be a contract with a
single service provider but TPL reserves the right to award this work to more than one
service provider should it be required. TPL also reserves the right to discontinue or
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 12 of 34 Rev 7
terminate the services of the Specialist (Owners team) at or before the end of a phase
i.e. FEL 1, FEL2, FEL3, etc.
Contract Group 2 (Engineering, Procurement and Construction Management (EPCM) –
Contract(s) will be entered into with service provider(s) who will provide the services
from the concept design through to the approved for construction design based on their
experience, capability and capacity to undertake a project within the constrained
requirements. Their service is to also include the supervision during construction, the
commissioning support during commissioning; project handover and project close out.
It is anticipated that this will be a contract with a single service provider but TPL
reserves the right to award this work to more than one service provider.
Contract Group 3 (Supply Contracts) – For the supply of plant and material which is not
defined at this stage.
Contract Group 4 (Construction Contracts) – Construction contracts to complete the
supply, fabrication, manufacture, installation, and construction works as per the
approved designs which is also not defined at this stage.
This scope of service is restricted to the contract group 1 (owners team) for the specialist
consultant.
It is also important to note that if a service provider is awarded work in one contract group
then it precludes him / her from being awarded work in another contract group, to avoid
situations of conflict of interest.
9. SCOPE OF SERVICES
The service provider is to provide hydrocarbon pipeline engineering consulting services to
the employer, serving as part of the employer’s owner’s team on the Transnet Pipeline
PL5&PL6 project. This is to include the required commercial, engineering, regulatory and
compliance input to assist the employer in selecting the most viable solution, for project
development and to assist the employer throughout the development of the project.
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 13 of 34 Rev 7
These services are to be undertaken from the FEL 1 through to the close out phases of the
project lifecycle within the PLP process and will include the requirement for the service
provider to work with the employer in developing and producing all the required and agreed
gate review deliverables as well as partake in the gate review process together with the
EPCM.
During gate reviews the project may not be given authority to proceed onto the next FEL
phase due to various reasons, in which case, TPL reserves the right to discontinue the
services of the specialist consultant from one FEL phase to the next and will be included in
the contract as key dates (milestones), even though it may be (is) included in the contract.
The services are to be structured around the employer’s project objective of replacing the
section of 12” DJP pipeline from Sasolburg to Kroonstad (with PL5) and replacement of the
section of 12” DJP pipeline from Alrode to OR Tambo International Airport, which is used as
part of the coastal jet route (with PL6). This replacement route (PL6) is between Jameson
Park and Airport. It also includes the upgrade of the associated facilities found on either end
of respective pipelines to cater for the relevant pipeline operational requirements. This may
be expanded to other services at the discretion of the employer and or his agent.
9.1 SCOPE OF SERVICE OVERVIEW
The Employer intends to enter into a contract with a service provider to assist the employer
in the development of the project over the project lifecycle. The consultant will serve as a
specialist consultant on the project owner team and the service in brief is to include the
following:
Establish what the commercial, regulatory, engineering and financial requirements
are for the completion of the project on behalf of the employer.
Drafting a scope of service, compiling a tender in accordance with Transnet
Procurement requirements and deliverables, assisting the employer with the tender
briefing/s, evaluating the tender in lieu of awarding a contract to an EPCM service
provider.
Assist the employer in the review of deliverables during the optioneering phase of the
project (FEL 1 and 2)
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 14 of 34 Rev 7
Provide quality assurance, including design reviews and approvals during the design
phases (FEL 3 and 4)
Provide quality assurance during the execution phase of the project.(Provide
Construction Project Management services for the execution phase)
Assist the employer to ensure that the project is adequately closed out, including
technical, operational, administrative, financial and contractual close out
9.2 LOCATION OF THE SITES AND ACCESS
The services rendered will be largely office based, with the TPL engagement sessions
convened at TPL’s Head Office at 202 Anton Lembede Street, Durban but will include site
work on the TPL sites specifically TPL Sasolburg Depot and TPL Kroonstad Depot including
the linking route as well as the TPL Jameson Park Depot and TPL OR Tambo International
Airport Depot including the linking route. Attached map PPT 1604D illustrates the location of
these sites.
9.3 GENERAL DESCRIPTION OF THE SERVICES
The Consultant shall function within the Project Team as the Specialist Consultant led by
Transnet Pipelines Project Manager/s with the aim of supporting all the technical aspects of
the project towards achieving a successful implementation of all elements of the project. In
achieving this goal, the consultant shall:
Maintain communications with the Transnet Pipelines project manager along with
project EPCM. It should be noted that although direct lines of communication
between the Consultant and the project manager is required for discussion/resolution
of all Technical issues, all such proposals/agreements shall be made with the consent
of the Project Manager, who carries overall responsibility for Project Management.
Evaluate and interpret client requirements, preliminary investigation, where any of
these are required for determination of feasibility. Furthermore, the Consultant shall
be responsible for all user related issues relating to design, supply, installation and
commissioning of the various elements of the project.
Write functional descriptions and user requirement specifications as needed. This will
be included in the preparation of detailed Scopes of Work for the EPCM tender,
encompassing all mechanical, civil, structural, environmental, instrumentation and
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 15 of 34 Rev 7
electrical design and construction activities required to be performed during the
projects.
Assist the employer in the interpretation of functional specifications and ensure to
review, and make recommendations on the technical design documents as
developed by the EPCM. Review of the detailed scopes of work prepared by the
EPCM contractor.
Liaise with TPL operations and maintenance staff and advise on overall
implementation approach. Review and recommendation of the design of any process
or system or refinement of the preliminary process design, where such process
design is a prerequisite for the design of the Works
Review, familiarize and understand the proposed site including all constraints and
environmental factors.
Assist in the co-ordination and attend inspections such as factory acceptance testing
(FATS) and investigations with technical counterparts from TPL, the EPCM team,
contractors, etc.
Maintain in-depth technical knowledge of products utilised by Transnet Pipelines.
Interpret and perform valued input early within Transnet Pipelines’ decision making
process. Assistance with the evaluation of tenders received, and the submission of
recommendations. Review contractors including EPCM’s procedures, policies and
design documentation.
Co-ordinate and generally inspect the execution of the design works for compliance
with the EPCM Contract at such intervals as the Consultant may deem necessary.
Control and co-ordination of all quality assurance issues that may arise between the
Employer and other parties, ensuring full compliance with SANS/ISO procedures.
Assisting with resolving disputes or differences that may arise between the Client and
EPCM Contractor, excluding mediation, arbitration and litigation.
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 16 of 34 Rev 7
Assist in the attendance and witnessing of performance and acceptance tests if
required.
Assistance during commissioning periods, as and when required.
Verifying the monthly assessment for services rendered by the EPCM and or other
contractors, including assisting with re-measurement if required.
Prepare reports at the various stages of the projects to the project team and other
relevant stakeholders.
Undertake design review coordination with the employer’s team.
Undertake and be available to execute Squad checks at various stages as and when
required.
Manage the EPCM to ensure the planning and execution of all phases and aspects of
the project so as to ensure that the project is executed expeditiously and efficiently.
Assist the employer in the review of the EPCM’s methodology and program
Obtain prior approval from the employer and or his agent for the mobilisation of a
resource to serve on the project.
The supplier to demonstrate by means of resource schedule with timelines as to how
the resources will be deployed and utilised for different phases and deliverables of
the project.
Should there be a need to demobilise key resources as identified at tender and award
stage, the employer should be notified of such demobilisation. The employer is to
approve all suitability and mobilization key resources.
9.4 DETAILED SCOPE OF THE PROJECT AS PER PLP PROCESSESS
The following pertains to the scope, in terms of project activities and or deliverables
envisaged. The requirement for the specific deliverable is captured below and is intended to
be a guide. Even though the activities / deliverables are intended to be sequential, it is
dependent on the methodology of the EPCM service provider.
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 17 of 34 Rev 7
9.4.1 FEL 1 – CONCEPT PHASE SCOPE
9.4.1.1 Project Kick-off – Through engagement with the TPL owner’s team members confirm
the roles and responsibilities of the various role players in the project, amongst other
project kick off requirements.
9.4.1.2 Compilation of Owners Requirement Specifications (ORS) – Through engagement with
the TPL owner’s team members as well as engineering research to understand the
operational and technical requirements of the project to include and not limited to:
o The TPL operations philosophy
o The TPL operations capacity analysis
o The 30 year demand analysis
o Project sustainability objectives
o TPL pipeline routing criteria
o Pipeline routing hazards
o TPL environmental design criteria
o Project specific legal register
o Project specific compliance and regulatory universe
o Stakeholder identification
o Risk identification
The ORS is to be approved by the person with the correct delegated authority (within
Transnet / TPL) and be the guiding document for the project during the phase.
9.4.1.3 Compilation of Project Execution Plan (PEP) – On approval of the project ORS, develop
the project execution plan. The plan is to consider the following and not limited to:
o Stakeholder management plan
o Project risk management plan
o Procurement and contracting plan
o Engineering management plan
o Environmental management plan
o Health and Safety Management plan
o Cost, Time and Quality management plan
o Project resourcing or organisational plan
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 18 of 34 Rev 7
9.4.1.4 Compilation of EPCM scope of service –
o Compile a scope of service for the engineering, procurement and construction
management (EPCM) for the FEL 1 to Close out phase of the project.
o Compile other tender documents including schedule of quantities, technical
returnables, adjudication criteria and other necessary documents for the EPCM
tender.
o Attend site briefing, complete tender adjudication and recommendation
o Provide input to contract negotiation and award.
9.4.1.5 Review and recommend the concept (FEL1) design basis as compiled by the EPCM
including and not limited to:
o Engineering
Process design criteria
Draft civil design criteria
Draft structural, mechanical and piping design criteria
Draft fire System design criteria
Draft electrical design criteria
Control system philosophy
Draft functional design criteria for metering control and instrumentation
Draft sustainability design criteria and alternatives analysis
o Health Safety Environmental Risk and Quality (HSERQ)
Environmental authorisation requirements including permitting requirements
Environmental baseline data collection requirements
o Community Management and Social Risks
Stakeholder / landowner identification model
o Regulatory and compliance
Regulatory specifications and requirements
9.4.1.6 Review and advice on the end of phase deliverables (FEL1) compiled by the EPCM
including and not limited to:
o Engineering
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 19 of 34 Rev 7
Preliminary pipeline routing
Major civil property impacts of project
Identify geotechnical data
Preliminary site conditions
Digital Terrain model
Preliminary seismic data
Preliminary GIS
Preliminary structural concepts
Preliminary corrosion protection plans
Preliminary mechanical equipment list
Preliminary piping specifications
Preliminary piping material classes
Preliminary electrical equipment list
Completed electrical power supply survey
Preliminary hazardous area classification
Preliminary energy optimisation study
Final control system architecture
Preliminary instrument equipment list
Preliminary SIL analysis
Preliminary operational analysis and commissioning plan
o HSERQ
Preliminary quality management systems and procedures
End of phase risk review update for the FEL 2 phase
o Community Management and Social Risks
Stakeholder / Landowner engagement strategy
o Cost and Schedule
Class 2 capital cost estimate with cash flow for entire project
Class 4 capital estimate for the FEL 2 phase
Class 2 operating cost estimate
Estimate basis
Level 2 master schedule
Summary of schedule basis
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 20 of 34 Rev 7
9.4.1.7 Finalise end of phase reports including:
o Regulatory, Compliance
Draft regulatory submission for project construction licence (Project Intent)
o Commercial and Procurement
Draft work package list for entire project
Final work package list for FEL2
o Financial
Financial analysis and project viability
o Draft FEL 2 business case
9.4.1.8 Prepare for gate review (FEL1)
9.4.1.9 Participate in FEL 1 gate review
9.4.1.10 Resubmission of FEL 1 gate review documents if required.
9.4.1.11 Compilation and submission of business case for approval to TPL CAPIC, Transnet
CAPIC, Transnet EXCO, Transnet BDAC and the shareholder.
9.4.2 FEL 2 – PRE FEASIBILITY PHASE
9.4.2.1 Phase Kick-off – Through engagement with the project team members participate in
the review the roles and responsibilities of the various role players in the project,
amongst other phase kick off requirements.
9.4.2.2 Update of ORS – Through items identified in the FEL 1 phase of the project as well as
through research update the operational and technical requirements of the project to
include but not limited to:
o The updated TPL operations philosophy
o The updated TPL operations capacity analysis
o The 30 year demand analysis
o The updated project sustainability objectives
o The updated pipeline routing criteria
o The updated routing hazards
o The updated environmental design criteria
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 21 of 34 Rev 7
o The updated project specific legal register
o The updated project specific compliance and regulatory universe
The ORS is to be approved by the person with the correct delegated authority (within
Transnet/TPL) and be the guiding document for the project during the FEL 2 phase.
9.4.2.3 Update of Project Execution Plans – On approval of the project ORS, update the project
execution plan. The plan is to consider the following but not limited to:
o Stakeholder management plan
o Project risk management plan
o Procurement and contracting plan
o Engineering management plan
o Environmental management plan
o Health and Safety Management plan
o Cost, Time and Quality management plans
o Project resourcing and organisational plan
9.4.2.4 Motivate for the extension of the EPCM contract to the TPL acquisition council or
alternatively assist in the procurement of the required service through the open market
9.4.2.5 Review and advise on the updated pre-feasibility (FEL2) interim design review compiled
by the EPCM and a finalisation of the following design criteria but not limited to:
o Environmental design criteria
o Process design criteria
o Civil design criteria
o Structural, Mechanical and Piping design criteria
o Fire System design criteria
o Updated control philosophy
o Electrical design criteria
o Functional design criteria for metering control and instrumentation
o Sustainability design criteria
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 22 of 34 Rev 7
9.4.2.6 Finalise the regulatory submission for the project construction licence.
9.4.2.7 Review and advise on the end of phase pre-feasibility deliverables (FEL2) compiled by
the EPCM including but not limited to:
o Engineering
Frozen pipeline routing
Preliminary site plot plans
Preliminary layout design criteria
Preliminary facility layouts
Major and Minor civil property impacts of project
Detailed geotechnical data
Final site conditions
Final Digital Terrain model
Final seismic data
Final GIS
Final structural concepts
Final corrosion protection plans
Detailed mechanical equipment list
Preliminary P&ID
Final piping specifications
Final piping material classes
Detailed electrical equipment list
Final electrical power supply survey
Final hazardous area classification
Final energy optimisation study
Frozen control system architecture
Detailed instrument equipment list
Detailed SIL analysis
Updated operational analysis and commissioning plan
o HSERQ
Updated environmental management plan
Environmental baseline data completed
Environmental authorisation submission completed
Environmental permits application completed
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 23 of 34 Rev 7
Updated quality management systems procedures and plan
End of phase risk review update for FEL 3 phase
o Community Management and Social Risks
Updated stakeholder management plan for FEL 3
Land acquisition approvals initiated
o Cost and Schedule
Class 3 capital cost estimate with cash flow for entire project
Class 4 capital estimate for the FEL 3 phase
Class 3 operating cost estimate
Updated Estimate basis
Updated Level 2 master schedule
Updated summary of schedule basis
9.4.2.8 Finalise end of phase reports including:
o Regulatory, Compliance
Response to regulator and obtain approval for construction licence
o Commercial and Procurement
Updated work Package List for project
Final work package list for FEL3
o Financial
Updated financial analysis and project viability
o Draft FEL 3 business case
9.4.2.9 Prepare for gate review (FEL2):
9.4.2.10 Participate in FEL 2 gate review:
9.4.2.11 Resubmission FEL 2 gate review documents if required
9.4.2.12 Resubmission FEL 2 gate review documents if required
9.4.2.13 Submission of business case for approval to TPL CAPIC, Transnet CAPIC, Transnet
EXCO, Transnet BDAC and the shareholder.
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 24 of 34 Rev 7
9.4.3 FEL 3 –FEASIBILITY PHASE (BASIC ENGINEERING)
9.4.3.1 Phase Kick-off – Through engagement with the project team members participate in
the review the roles and responsibilities of the various role players in the project,
amongst other phase kick off requirements.
9.4.3.2 Review of Preliminary design documents for the FEL 3 phase in the following work
streams:
o Pipeline engineering and design
o Facility engineering and design
9.4.3.3 30% model reviews for designs
o Pipeline engineering and design
PL5 (124km)
PL6 (50km)
o Facility engineering and design
Sasolburg
Kroonstad
Airport
Jameson Park
9.4.3.4 70% model reviews for designs
o Pipeline engineering and design
PL5 (124km)
PL6 (50km)
o Facility engineering and design
Sasolburg Pump Station
Kroonstad Depot
Airport Depot
Jameson Park Terminal – TM2
9.4.3.5 Business Information Systems assessment
9.4.3.6 Finalise end of phase reports including:
o Regulatory, Compliance
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 25 of 34 Rev 7
Regulator updates and communication
o Commercial and Procurement
Review final work package list for FEL4 phase
o Financial
Updated financial analysis and project viability
o Updated FEL 4 business case
9.4.3.7 Prepare for gate review (FEL3)
9.4.3.8 Participate in FEL 3 gate review
9.4.3.9 Resubmission FEL 3 gate review documents if required
9.4.3.10 Submission of updated business case for approval to TPL CAPIC, Transnet CAPIC,
Transnet EXCO, Transnet BDAC and the shareholder.
9.4.4 FEL 4–DETAILED ENGINERING
9.4.4.1 Phase Kick-off – Through engagement with the project team members participate in
the review the roles and responsibilities of the various role players in the project,
amongst other phase kick off requirements.
9.4.4.2 Review of detailed design documents for the FEL 4 phase
9.4.4.3 Participate in the 90% model reviews of the EPCM`s designs
9.4.4.4 Finalise end of phase reports including:
o Regulatory, Compliance
Regulator updates and communication
o Commercial and Procurement
Participate in the tender briefing, technical evaluation and award of major
contracts
o Financial
Updated financial analysis and project viability
o Updated FEL 4 business case
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 26 of 34 Rev 7
9.4.4.5 Prepare for gate review (FEL4)
9.4.4.6 Participate in FEL 4 gate review
9.4.4.7 Resubmission FEL 4 gate review documents if required
9.4.4.8 Submission of updated business case for approval to TPL CAPIC, Transnet CAPIC,
Transnet EXCO, Transnet BDAC and the shareholder.
9.4.5 EXECUTION AND CLOSE OUT PHASE
9.4.5.1 Provide quality assurance during installation
9.4.5.2 Prepare for post implementation review
9.4.5.3 Assist employer with technical, financial, administrative and commercial close out of
project.
9.4.5.4 Prepare for post implementation review
9.4.6 REQUEST FOR PROPOSAL
A suitable Professional Services Contractor will be appointed though an NEC Professional
Services Option E contract (cost reimbursable contract). Tenderers are requested to submit
valid information in the form of a tender / bid based on their experience to deliver the
required services, to the employer. The employer will evaluate the tenderer’s proposal on
9.4.6.1 Company and staff experience, capability, and capacity to undertake this service
with a special focus on the hydrocarbon industry, consulting on the design and
management of hydrocarbon pipelines.
9.4.6.2 The tenderers understanding of the specific project requirements.
9.4.6.3 And the tenderers proximity to the TPL head office situated at 202 Anton Lembede
Street. It is the employer’s requirements to ensure logistical efficiencies are
assessed when resources assigned to the service are mobilised.
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 27 of 34 Rev 7
9.4.7 ROLE OF THE CONSULTANT WITHIN THE PROJECT CONTEXT
The consultant will provide specialist technical assistance to the employer within a pipeline
development context. The role is largely to provide specialist input during the development
of a typical hydrocarbon pipeline project and to perform technical quality assurance on the
project in the various pipeline specific disciplines and any other services in connection with
the carrying out of the project:
9.4.8 PROCUREMENT
The consultant is to assist the employer in the procurement of the contractors, including
specialised services and equipment. It is important to note that all contracts are to be
procured through TPL’s procurement department and all procurement activities will be
aligned to Transnet’s Procurement and Procedures manual (PPM). It is the responsibility of
the consultant to familiarise him/herself with the manual and its updates. The ruling of
National Treasury on procurement matters to be adhered to.
9.4.9 DATA TO BE SUPPLIED TO CONSULTANT
Transnet Pipelines will furnish, with all reasonable expedition, all available pertinent data and
information and give such assistance as may reasonably be required by the Consultant for
the carrying out of his duties under this agreement.
9.4.10 COMPLIANCE WITH LAWS
The Consultant shall comply with all laws or regulations applicable to or in connection with
the project, and with all applicable requirements of any government, provincial or any other
responsible governing or public authority.
9.4.11 NON-ASSIGNMENT
The Consultant may at any time take into partnership a partner or partners, and that he/she
or they shall thereafter be deemed to be included in the expression “the Consultant”, where
the context so allows or permits. The Consultant shall not re-assign or transfer his rights or
obligations or any part thereof under this agreement without the prior written approval of
Transnet Pipelines.
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 28 of 34 Rev 7
It may be a requirement for the consultant to mobilise other resources not in the employ of
the consultant to satisfy the requirements of the project on short assignments as and when
needed.
9.4.12 OWNERSHIP OF DOCUMENTS AND COPYRIGHT
9.4.12.1 The Consultant hereby grants to Transnet Pipelines a non-exclusive licence in
accordance with the provisions of section 22 of the Copyright Act 1978:
i. to copy any plan, diagram, drawing, specification, bill of quantities, design,
calculation, or similar document made, other than under the direction or control of
Transnet Pipelines, by the Consultant in connection with the Project;
ii. to make free and unrestricted use thereof for its own purposes.
iii. to provide copies thereof to other consultants to be used by them for the purposes of
the consultancy;
iv. to provide other parties with copies thereof for the purpose of tenders invited by it.
9.4.12.2 The Consultant, furthermore, shall engage any specialist and/or firm employed by him
for investigation or for design in connection with the project, to grant to Transnet
Pipelines a similar non-exclusive licence for the purposes set out herein. No separate or
extra payment shall be due by Transnet Pipelines in respect of any non-exclusive
licence granted in terms of this clause.
9.4.12.3 The source codes of computer programmes designed and developed for Transnet
Pipelines by the consultant shall be the sole property of Transnet Pipelines, and
Transnet Pipelines has the right to copy and alter code without obtaining permission of
the Consultant. No portion of the completed system shall be available as commercial
value for any party besides Transnet Pipelines. After completion of such software, and
prior to final payment the Consultant will forward a copy of the data code with all
documentation.
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 29 of 34 Rev 7
9.5 COMMUNICATIONS
9.5.1 The Consultant shall abide to all communication requirements imposed upon them by TPL.
Any communication received, produced or issued by the Consultant shall first be reviewed by
TPL before transferred onto another party. This covers but is not limited to; engagement with
market place, advertisements, communications with Transnet Clients, industry forums,
magazines, websites, blogs and any other social media.
9.5.2 All communication initiatives shall be approved by TPL.
9.5.3 The engagement, communication (timing and context) templates and formats shall be agreed
and signed off by the relevant Employers’ process owner before any deliverables are started.
Time spent correcting incomplete and incorrect documentation will be for the Consultant`s
own cost. All reports shall be cross-referenced against other disciplines and tools to ensure
accuracy and integration of information. All communications direct, indirect, 3rd party or other
shall be captured in the relevant document control system.
9.5.4 It is important that there be no communication between the Consultant and the contractor
without the approval of the EPCM and or TPL Employers Agent or Project Manager.
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 30 of 34 Rev 7
9.6 DOCUMENTATION CONTROL
9.6.1 The Consultant’s documentation shall comply with the Employer’s standards and
requirements. The Employer will issue all relevant documentation to the Consultant, but
control, maintenance and handling of these documents will be the Consultant’s sole
responsibility and at its expense, and managed with a suitable document control system. At
agreed periods throughout the development of the project the Consultant will be required to
transfer/migrate documentation to the TPL document management system. The format of
these documents shall be agreed up front and shall be fully usable and in native & PDF
format. All the relevant links and supporting documents shall be provided.
9.6.2 All documents issued to 3rd Party contractors and to the Employer must be submitted as per
the TPL’s Document policy. Any contractual communication between TPL and the
contractors shall be issued by the Consultant on behalf of TPL. These communications shall
be similarly recorded through the Consultant’s document control system and all
communication to be restricted to the communication protocol.
9.6.3 Upon completion of services ownership of Data, Designs and Documents: The Parties shall
agree that copyright in the data, design and documents shall, after payments by the
Employer of the services to the Consultant, lie with the Employer subject to the Employer’s
indemnification against any claim from any party that may arise as a result of the Employer’s
use of such a document due to the Consultant’s infringement of copyright.
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 31 of 34 Rev 7
9.7 INFORMATION AND COMMUNICATIONS TECHNOLOGY (ICT)
9.7.1 The Consultant shall provide and have available computing, server, back-up,
communications, software’s and licencing in order to successfully interface with Transnet’s
tools and systems.
9.7.2 Should the Consultant access Transnet’s Information Assets; they will use these in a
manner that will not harm or endanger Transnet as a company in line with the Transnet’s
Information Security Policy and any other related policies.
9.7.3 The Consultant shall sign the confidentiality agreement to adhere to Transnet’s Information
Security Policy and all other relevant Transnet’s Policies
9.7.4 The software used shall similarly be conversant with Transnet’s approved software in order
to meet the obligation of the document control process spelt out in this document.
9.7.5 The Consultant shall make available connectivity, internet access, ICT infrastructure and
applications access, document control access and any other systems used by the
consultant shall be made available to the Employer at any point in time during the project.
9.7.6 The Consultant shall ensure that all data stored on the workstations is backed up to the
secure server provided by the Consultant. It is the responsibility of user of the desktop,
laptop, handheld mobile devices to ensure that business information and data stored on
these devices is backed up.
9.8 OFFICE SPACE
9.8.1 The services are to be rendered from the consultants’ office. It is a requirement that the
consultant make provision for office space for the employer’s agent and at least one other
on and as and when required basis. This requirement is anticipated to change when the
project is in the construction phase and the
9.8.2 The office is to include a venue where meetings and other engagement sessions could be
held to accommodate the employers owners team.
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 32 of 34 Rev 7
10. APPENDIX
APPENDIX A: DRAWING LIST
APPENDIX B: TRANSNET CAPITAL UNIVERSE
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 33 of 34 Rev 7
10.1 APPENDIX A: MAP OF TRANSNET’S EXISTING PIPELINES’ NETWORK
________________________________________________________________________
TRANSNET PIPELINES
PROFESSIONAL SERVICES FOR THE OWNERS TEAM TO COLABORATE WITH TPL IN COMPILATION OF EPCM
SCOPE OF WORKS AND MANAGEMENT OF FEL PHASES
TECHNICAL PROJECTS
RFPS 091215 Page 34 of 34 Rev 7
10.2 APPENDIX B: TRANSNET CAPITAL UNIVERSE