Work Instruction MIGO_TR - JPN - Perform Stock Transfer Between Storage Location Purpose Stock Transfer can occur in one of following scenarios: 1. Stock Transfer between Storage Locations within a plant. 2. Transfer between stock types. All of the above scenarios are using the same MIGO_TR transaction with different movement types to process the transfer in the system. In this simulation, you will perform stock transfer between storage locations from using 1 step movement. Trigger Perform this transaction when you need to perform Stock Transfer between Storage Locations. Menu Path Use the following SAP Easy Access menu path(s) to begin this transaction: Logistics > Materials Management > Inventory Management > Goods Movement > MIGO_TR - Transfer Posting (MIGO) Transaction Code MIGO_TR Monday, June 08, 2009 SCM_MIGO_TR_UAPL_Perform Stock Transfer Between Storage Loca_JPN.udc 1/13

Upload: nguyencaohuy

Post on 28-Oct-2015

30 views

Category:

Documents


2 download

DESCRIPTION

scm temple

TRANSCRIPT

Page 1: SCM MIGO TR UAPL Perform Stock Transfer Between Storage Loca JPN

Work Instruction MIGO_TR - JPN - Perform Stock Transfer Between

Storage Location

Purpose

Stock Transfer can occur in one of following scenarios:

1. Stock Transfer between Storage Locations within a plant. 2. Transfer between stock types.

All of the above scenarios are using the same MIGO_TR transaction with different movement types to process the transfer in the system.

In this simulation, you will perform stock transfer between storage locations from using 1 step movement.

Trigger

Perform this transaction when you need to perform Stock Transfer between Storage Locations.

Menu Path

Use the following SAP Easy Access menu path(s) to begin this transaction:

Logistics > Materials Management > Inventory Management > Goods Movement > MIGO_TR - Transfer Posting (MIGO)

Transaction Code

MIGO_TR

Monday, June 08, 2009 SCM_MIGO_TR_UAPL_Perform Stock

Transfer Between Storage Loca_JPN.udc

1/12

Page 2: SCM MIGO TR UAPL Perform Stock Transfer Between Storage Loca JPN

Work Instruction MIGO_TR - JPN - Perform Stock Transfer Between

Storage Location

Screen Flow

Monday, June 08, 2009 SCM_MIGO_TR_UAPL_Perform Stock

Transfer Between Storage Loca_JPN.udc

2/12

Page 3: SCM MIGO TR UAPL Perform Stock Transfer Between Storage Loca JPN

Work Instruction MIGO_TR - JPN - Perform Stock Transfer Between

Storage Location

Procedure

1. In SAP, start the transaction using the menu path or transaction code.

SAP Easy Access

2. Double-click the Logistics node .

3. Double-click the Materials Management node .

4. Double-click the Inventory Management node .

5. Double-click the Goods Movement node .

Monday, June 08, 2009 SCM_MIGO_TR_UAPL_Perform Stock

Transfer Between Storage Loca_JPN.udc

3/12

Page 4: SCM MIGO TR UAPL Perform Stock Transfer Between Storage Loca JPN

Work Instruction MIGO_TR - JPN - Perform Stock Transfer Between

Storage Location

6. Double-click the MIGO_TR - Transfer Posting (MIGO) node .

Transfer Posting Other - Jewel Geno Jurlano

7. Click the Movement Type? edit field .

8. As required, complete/review the following fields:

Field R/O/C Description

Movement Type

R A classification key indicating the type of material movement (for example, goods receipt, goods issue, physical stock transfer). Example:

Monday, June 08, 2009 SCM_MIGO_TR_UAPL_Perform Stock

Transfer Between Storage Loca_JPN.udc

4/12

Page 5: SCM MIGO TR UAPL Perform Stock Transfer Between Storage Loca JPN

Work Instruction MIGO_TR - JPN - Perform Stock Transfer Between

Storage Location

311

Monday, June 08, 2009 SCM_MIGO_TR_UAPL_Perform Stock

Transfer Between Storage Loca_JPN.udc

5/12

Page 6: SCM MIGO TR UAPL Perform Stock Transfer Between Storage Loca JPN

Work Instruction MIGO_TR - JPN - Perform Stock Transfer Between

Storage Location

Depending on your business scenario, movement types can vary. Ensure that you have input the correct movement type.

Movement Type can also be checked in this tab.

9. Click the Enter button .

10.

Click the Material edit field .

11.

As required, complete/review the following fields:

Field R/O/C Description

Material R The goods that are the subject of business activity. The material can be traded, used in manufacture, consumed, or produced. Example: 62131199

For Japan:

Use the Material 31033078.

12.

Click the Plant edit field .

13.

As required, complete/review the following fields:

Field R/O/C Description

Plant R A plant is an organizational unit for dividing an enterprise according to production, procurement, maintenance, and materials planning. It is a place where materials are produced, or goods and services are provided. Example: 9000

For Japan: Use the Plant J101.

Monday, June 08, 2009 SCM_MIGO_TR_UAPL_Perform Stock

Transfer Between Storage Loca_JPN.udc

6/12

Page 7: SCM MIGO TR UAPL Perform Stock Transfer Between Storage Loca JPN

Work Instruction MIGO_TR - JPN - Perform Stock Transfer Between

Storage Location

14.

Click the Stor. Loc. edit field .

15.

As required, complete/review the following fields:

Monday, June 08, 2009 SCM_MIGO_TR_UAPL_Perform Stock

Transfer Between Storage Loca_JPN.udc

7/12

Page 8: SCM MIGO TR UAPL Perform Stock Transfer Between Storage Loca JPN

Work Instruction MIGO_TR - JPN - Perform Stock Transfer Between

Storage Location

Field R/O/C Description

Stor. Loc. R An organizational unit allowing differentiation between the various stocks of a material in a plant. Example: 9001

For Japan: Use the Stor. Loc. J001.

16.

Click the Stor. Loc. to edit field .

17.

As required, complete/review the following fields:

Field R/O/C Description

Stor. Loc. to

R Upper range value of storage location allowing differentiation between the various stocks of a material in a plant. Example: 9002

For Japan: Use the Stor. Loc. J001.

18.

Click the Unit of Entry edit field .

19.

As required, complete/review the following fields:

Field R/O/C Description

Unit of Entry

R Unit of measure in which a goods movement or physical inventory count is entered. Example: 40

20.

Click the Enter button .

Monday, June 08, 2009 SCM_MIGO_TR_UAPL_Perform Stock

Transfer Between Storage Loca_JPN.udc

8/12

Page 9: SCM MIGO TR UAPL Perform Stock Transfer Between Storage Loca JPN

Work Instruction MIGO_TR - JPN - Perform Stock Transfer Between

Storage Location

21.

Click the Batch edit field .

22.

As required, complete/review the following fields:

Monday, June 08, 2009 SCM_MIGO_TR_UAPL_Perform Stock

Transfer Between Storage Loca_JPN.udc

9/12

Page 10: SCM MIGO TR UAPL Perform Stock Transfer Between Storage Loca JPN

Work Instruction MIGO_TR - JPN - Perform Stock Transfer Between

Storage Location

Field R/O/C Description

Batch R A subset of the total quantity of a material in stock, managed separately from other subsets of the same material. Example: 00001

23.

Click the Batch to edit field .

24.

As required, complete/review the following fields:

Field R/O/C Description

Batch to R Upper range value of a subset of the total quantity of a material in stock, managed separately from other subsets of the same material. Example: 00001

25.

Click the Check button .

26.

Click the Post button .

27.

Click the Exit button .

A success message is displayed indicating that a Material document has been posted.

Monday, June 08, 2009 SCM_MIGO_TR_UAPL_Perform Stock

Transfer Between Storage Loca_JPN.udc

10/12

Page 11: SCM MIGO TR UAPL Perform Stock Transfer Between Storage Loca JPN

Work Instruction MIGO_TR - JPN - Perform Stock Transfer Between

Storage Location

Result

You have performed stock transfer in SAP ECC 6.0.

Monday, June 08, 2009 SCM_MIGO_TR_UAPL_Perform Stock

Transfer Between Storage Loca_JPN.udc

11/12

Page 12: SCM MIGO TR UAPL Perform Stock Transfer Between Storage Loca JPN

Work Instruction MIGO_TR - JPN - Perform Stock Transfer Between

Storage Location

Scenario

Situation

You want to perform stock transfer Instructions In this simulation you are required to:

Perform One Step Stock Transfer from RMS to SS in SAP ECC 6.0.

Required Data

This section provides the field data required to complete this exercise. Refer to this data sheet as necessary while performing the exercise.

Field Value

Movement type 311

Material 62131199

Plant 9000

Storage Location 9001 - 9002

Unity of entry / Qty 40

Batch from / Batch to 00001

Monday, June 08, 2009 SCM_MIGO_TR_UAPL_Perform Stock

Transfer Between Storage Loca_JPN.udc

12/12