sasol chemical operations: solvents division … · 6/13/2019 · this compliance audit report...
TRANSCRIPT
SASOL CHEMICAL OPERATIONS: SOLVENTS DIVISION
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT
14/3/L/A/SAS.EA - ETHYL ACETATE PLANT
13 JUNE 2019
CONFIDENTIAL
WSP Environmental (Pty) Ltd.
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT
14/3/L/A/SAS.EA - ETHYL ACETATE PLANT
SASOL CHEMICAL OPERATIONS:
SOLVENTS DIVISION
TYPE OF DOCUMENT (VERSION)
CONFIDENTIAL
PROJECT NO.: 41101534
DATE: JUNE 2019
WSP
BUILDING C
KNIGHTSBRIDGE, 33 SLOANE STREET
BRYANSTON, 2191
SOUTH AFRICA
T: +27 11 361 1392
F: +27 11 361 1381
WSP.COM
Q U A L I T Y M A N A G E M E N T
ISSUE/REVISION FIRST ISSUE REVISION 1 REVISION 2 REVISION 3
Remarks Draft for Review –
Compliance Audit
EA Ref:
14/3/L/A/SAS.EA
Final – Compliance
Audit
EA Ref:
14/3/L/A/SAS.EA
Date April 2019 June 2019
Prepared by Bronwyn Fisher Bronwyn Fisher
Signature -
Checked by Ashlea Strong Ashlea Strong
Signature
Authorised by Jenny Cope Jenny Cope
Signature
Project number 41101534 41101534
Report number 041 041
File reference file:///W:\000 NEW Projects\41101534 - Sasol EA and EMP Audits\42 ES\2-REPORTS\
S I G N A T U R E S
PREPARED BY
-
Bronwyn Fisher
Environmental Consultant
REVIEWED BY
Ashlea Strong
Principal Consultant
This Compliance Audit report (Report) has been prepared by WSP Environmental (Pty) Ltd (WSP) on behalf
and at the request of Sasol Synfuels: Secunda Operations (Client), to provide the Client with an understanding
of their compliance with the conditions included in the Environmental Authorisation.
Unless otherwise agreed by us in writing, we do not accept responsibility or legal liability to any person other
than the Client for the contents of, or any omissions from, this Report.
To prepare this Report, we have reviewed only the documents and information provided to us by the Client or
any third parties directed to provide information and documents to us by the Client. We have not reviewed any
other documents in relation to this Report, except where otherwise indicated in the Report.
P R O D U C T I O N T E A M
CLIENT
SHE: Environmental Compliance
Specialist
Broni van der Meer
Solvents Production Senior Manager,
Secunda Chemicals Operations
Alfie Naidoo
WSP
Associate Jenny Cope
Lead Auditor Anri Scheepers
Lead Auditor Ashlea Strong
Consultant Bronwyn Fisher
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL CHEMICAL OPERATIONS: SOLVENTS DIVISION
WSP June 2019
TABLE OF CONTENTS
1 INTRODUCTION ........................................ 1
1.1 Terms of Reference ................................................. 1
1.2 Ethyl Acetate Plant (SASOL CHEMICAL
OPERATIONS: SOLVENTS DIVISION)
(Authorisation Number: 14/3/L/A/SAS.EA) ........... 1
2 AUDIT SCOPE ........................................... 3
3 AUDIT METHODOLOGY ........................... 4
3.1 Audit Checklist ........................................................ 4
3.2 Site Inspection ......................................................... 4
3.3 Documentation Considered ................................... 4
3.4 Audit Compliance Assessment .............................. 5
3.5 Audit Team ............................................................... 5
3.6 Assumptions and Limitations ................................ 6
4 AUDIT FINDINGS ...................................... 7
5 SUMMARY OF THE AUDIT FINDINGS ... 17
5.1 Environmental Authorisation ............................... 17
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL CHEMICAL OPERATIONS: SOLVENTS DIVISION
WSP June 2019
TABLES
TABLE 1: COMPLIANCE LEVEL DEFINITION AND TARGET COMPLETION DATES .................. 5
TABLE 2: AUDIT FINDINGS – ENVIRONMENTAL AUTHORISATION ......................... 7
TABLE 3: SUMMARY OF EA COMPLIANCE AUDIT FINDINGS ........................ 17
FIGURES
FIGURE 1: LOCATION OF THE ETHYL ACETATE PLANT (SOURCE: GOOGLE EARTH, 2018) ............... 2
FIGURE 2: NUMBER/COUNT CONTRIBUTION OF FINDINGS MADE TO THE EA CONDITIONS PER SECTION ............................ 18
FIGURE 3: OVERALL COUNT FINDINGS ON COMPLIANCE TO THE EA CONDITIONS .............................. 18
FIGURE 4: PERCENTAGE CONTRIBUTION OF FINDINGS MADE TO THE EA CONDITIONS PER SECTION ..... 19
FIGURE 5: OVERALL PERCENTAGE FINDINGS ON COMPLIANCE TO THE EA CONDITIONS ................ 19
APPENDICES
A ENVIRONMENTAL AUTHORISATION
(14/3/L/A/SAS.E.A)
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL CHEMICAL OPERATIONS: SOLVENTS DIVISION
WSP June 2019
Page 1
1 INTRODUCTION
1.1 TERMS OF REFERENCE
Sasol South Africa (Pty) Limited operating through its Secunda Synfuels Operations (Sasol) appointed WSP
Environmental (Pty) Ltd (WSP) as an independent environmental consultant, to undertake a compliance audit
and compile an audit report according to the requirements of the National Environmental Management Act (No.
107 of 1998) as amended (NEMA). This report presents the findings of the compliance audit completed for the
Environmental Authorisation (EA) (Reference number: 14/3/L/A/SAS.EA issued on 14 January 2000) for the
period December 2014 to February 2019.
1.2 ETHYL ACETATE PLANT (SASOL CHEMICAL
OPERATIONS: SOLVENTS DIVISION)
(AUTHORISATION NUMBER: 14/3/L/A/SAS.EA)
The Ethyl Acetate Plant was constructed in 2001 for the production of 99.8% ethyl acetate. The plant is located
within the Solvents Operation Area (Figure 1). Feed (E95) is received in tank farm TK0145 from Unit 38 (U38)
and U238, the Alcohol Processing Units. The E95 (enthanol) is converted into ethyl acetate in a vapour phase
dehydrogenation reactor prior to being sent to a polishing reactor to remove some of the impurities in the final
product. The product is then sent the tank farm for distribution. By products produced through this process are:
— E93 which is sent U73 (high purity ethanol plant); and
— Hydrogen which is sent to unit 233 (cat- poly hydro treater).
An EA (Reference number: 14/3/L/A/SAS.EA) for the construction and operation of the Ethyl Acetate Plant
was issued on 14 January 2000.
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL CHEMICAL OPERATIONS: SOLVENTS DIVISION
WSP June 2019
Page 2
Figure 1: Location of the Ethyl Acetate Plant (Source: Google Earth, 2018)
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL CHEMICAL OPERATIONS: SOLVENTS DIVISION
WSP June 2019
Page 3
2 AUDIT SCOPE The 7 April 2017 amendment to the Environmental Impact Assessment (EIA) regulations introduced the
requirement for the auditing for all EAs and EMPrs in effect on 8 December 2014 and submission of audit
reports to the Department of Environmental Affairs (DEA) by 7 December 2019 and every five years thereafter.
This audit is designed to meet the requirements of Regulation 34 of the EIA Regulations, 2014.
The audit period runs from December 2014 to February 2019, therefore any construction related conditions that
would have been relevant pre-December 2014 are considered not applicable (outside audit period).
The objective of the audit was to:
— Assess the level of compliance with the conditions of the EAs;
— Identify and assess any new impacts and risks that result from undertaking the activity;
— Make recommendations in order to achieve compliance in terms of the EAs; and
— Ensure the commitments contained in Condition 9.02 of the EA are completed, more specifically:
— “Records relating to the compliance/non-compliance with the conditions of the authorization must be
kept in good order. Such records must be made available to this Department within seven (7) workdays
of the date of written request for such records”.
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL CHEMICAL OPERATIONS: SOLVENTS DIVISION
WSP June 2019
Page 4
3 AUDIT METHODOLOGY The International Organisation of Standardisation (ISO) 14010, ISO 14011 and ISO 14012 guideline documents
were utilised as a template during the compliance audit process. This methodology ensures that the compliance
audit was conducted in a systematic and independent manner that was documented and objectively evaluated to
determine compliance to the EA conditions.
The audit process comprised the following:
— Confirmation of the audit checklist;
— Site inspection (12 March 2019);
— Review of documentation relevant to the conditions of the EA (e.g. records, permits/certificates/maintenance
logs/monitoring results/previous reports etc.); and
— Compilation of an audit report.
3.1 AUDIT CHECKLIST
WSP compiled an audit checklist to assist with the EA compliance audit (Section 4).
3.2 SITE INSPECTION
Bronwyn Fisher conducted the site inspection on 12 March 2019. The findings and observations of the site visit
are recorded and summarised in Section 4 with evidence included in Table 2. Key personnel interviewed
included:
— Simon Malinga (Production Foreman).
3.3 DOCUMENTATION CONSIDERED
The following documentation was provided and considered:
— SCO DQS ISO 14001 2015;
— 2018 DQS 3rd Party Audit Report_Sasol Secunda Chemicals Operations;
— EA_EX Handover_SCO_Solvents_CWU_EA;
— 3.1 RE EA Condition information;
— 3.1 RE EA Condition information1;
— 3.1 Earthing andLight Protection_2006;
— 3.1 Elec design criteria_SP-60-56_2010-05-29;
— 3.1 Smoke detection_2019-01-15;
— SCO DQS BSOHSAS 18001 2007;
— EA_Illumination Survey;
— 3.05 EA SOP;
— 3.11 EA Emergency Procedure;
— Compliance_Air_Secunda Complex;
— AEL Sasol Solvents 0017-2015-F02 (2015) ;
— Copy of Environment Impact register_ New FY17;
— Environment Impact register_ New FY19_2019-02-18;
— IWWMP SIC 2015 Final_2018-05-15;
— Induction_Mod3_Environment;
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL CHEMICAL OPERATIONS: SOLVENTS DIVISION
WSP June 2019
Page 5
— Induction_Mod4_ProcessSafetyManagement;
— Induction_Mod5_WorkPlaceSafety;
— Induction_Mod6_EmergencyManagement;
— Environmental Complaints Register_2019-02-18; and
— Various email correspondence.
3.4 AUDIT COMPLIANCE ASSESSMENT
WSP utilised a pre-prepared audit checklist to assist with the audit execution (Table 2 ). The checklist included
the conditions and associated requirements as specified in the EA.
Each condition was verified, either by reviewing documentation, interviewing employees and/or visually
inspecting the facility. Each condition was rated in accordance with Table 1 below, and recommendations with
associated target completion dates included.
It should be noted that some of the EA conditions were apportioned according to the elements requiring
compliance assessment therein. Although some elements of the condition may have been compliant, if one of
the elements was determined to be non-compliant, the entire condition has been reported as such (and counted
as such during percentage compliance calculation). This apportionment further allowed for the development of
focussed recommendations and timeframes.
Table 1: Compliance Level Definition and Target Completion Dates
COMPLIANCE LEVEL DEFINITION
Compliant (C) Sasol could provide evidence for compliance with the commitment and condition and/or
relevant actions were implemented.
Non-compliant (NC) Specified commitments, conditions and documents were not in place or implemented
according to the requirements of the EA. Non-complaint conditions are given target
completion dates, as follows:
— Short term: 0 – 6 months.
— Medium term: 6 – 12 months.
— Long term: 12 – 18 months.
Not applicable (N/A) These are commitments are either not required yet or not applicable to Sasol.
— Conditions marked as “Noted” are considered information points only.
— Where conditions are considered “not auditable” within the scope of this assessment this
is stated and explained within the condition commentary.
Refer to Section 4 for the detailed audit findings (including evidence, recommendations and target completion
dates).
3.5 AUDIT TEAM
The auditor, Bronwyn Fisher, was hosted by Broni van der Meer and Simon Malinga to whom we express our
gratitude for his time and attention during our visit. A brief summary of the external auditors’ experience is
provided below.
— Auditor: Bronwyn Fisher
Bronwyn Fisher has 6 years of experience as an Environmental Consultant, undertaking Environmental
Impact Assessments (EIAs) and Basic Assessments. She has experience in developing Environmental
Management Programmes (EMPrs), undertaking site audits (ECO), Water Use Licence Applications and
undertaking Public Participation. Bronwyn’s project experience includes construction of pipelines, diesel
storage installations, waste disposal sites, water treatment facilities, oil refineries, tank farm installations,
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL CHEMICAL OPERATIONS: SOLVENTS DIVISION
WSP June 2019
Page 6
recycling facilities, mixed-use developments, industrial developments and renewable energy technology
projects.
— Lead Auditor and Quality Assurance: Ashlea Strong
Ashlea has 16 years’ experience and holds a Masters in Environmental Management; a BTech (Nature
Conservation), and a National Diploma (Nature Conservation); She is also a Certified Environmental
Assessment Practitioner of South Africa (CEAPSA). She currently provides technical and strategic
expertise on a diverse range of projects in the environmental management field, including environmental
scoping and impact assessment studies, environmental management plans, waste and water management, as
well as the provision of environmental management solutions and mitigation measures. She has been
involved in the management of a number of large EIAs within South Africa and has environmental auditing
and training experience and expertise. Ashlea has carried out over 50 compliance audits and is well versed
in the audit process.
— Project Manager and Quality Assurance: Jenny Cope
Jenny is an environmental due diligence specialist, with over 11 years’ experience in the Environmental
Sector. Jenny’s experience includes managing and completing projects and portfolios internationally;
undertaking both detailed and broad Environmental, Health & Safety compliance and audits of across a
range of sectors. Jenny’s recent experience includes completion and management of several pan-European
and global projects requiring reviews of extensive virtual data rooms, on a very rapid turnaround, and
providing clients with ‘red flag’ reports to give clear commercial advice. Jenny has worked both in
environmental consultancies and with a developer, giving context to understanding the practicalities of
implementing recommendations.
3.6 ASSUMPTIONS AND LIMITATIONS
This Report has been prepared by WSP on behalf and at the request of Sasol, to provide the Client an
understanding of the Relevant Documents.
Unless otherwise agreed by us in writing, we do not accept responsibility or legal liability to any person other
than the Client for the contents of, or any omissions from, this Report.
To prepare this Report, we have reviewed only the documents and information provided to us by the Client or
any third parties directed to provide information and documents to us by the Client. We have not reviewed any
other documents in relation to this Report and except where otherwise indicated in the Report.
The findings, recommendations and conclusions given in this report are based on the author’s best scientific and
professional knowledge, as well as available information. This report is based on survey and assessment
techniques which are limited by time and budgetary constraints relevant to the type and level of investigation
undertaken; WSP and its staff reserve the right to modify aspects of the report including the recommendations if
and when new information may become available from on-going research or further work in this field, or
pertaining to this investigation.
Although WSP exercises due care and diligence in rendering services and preparing documents, WSP accepts
no liability, and Sasol, by receiving this document, indemnifies WSP and its directors, managers, agents and
employees against all actions, claims, demands, losses, liabilities, costs, damages and expenses arising from or
in connection with the services rendered, directly or indirectly by the use of the information contained in this
document.
This report must not be altered or added to without the prior written consent of the author. This also refers to
electronic copies of this report which are supplied for the purposes of inclusion as part of other reports.
Similarly, any recommendations, statements or conclusions drawn from or based on this report must make
reference to this report. If this report is used as part of a main report, the report in its entirety must be included
as an appendix or separate section to the main report.
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL CHEMICAL OPERATIONS: SOLVENTS DIVISION
WSP June 2019
Page 7
4 AUDIT FINDINGS Table 2: Audit Findings – Environmental Authorisation
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
GENERAL CONDITIONS
1.01 This authorization refers only to the Ethyl Acetate Plant at
Sasol's Complex in Secunda, as specified above and
described in Record of Decision. Separate application/s must
be lodged for any other development and /or activity at or
near plant, which is covered by section 21 and 22 of the Act
and Government Notice R1182 and 1183 of 5 September
1997.
N/A Noted. Sasol have advised the auditor that they are aware of this
condition.
None.
1.02 Authorization is only granted in terms of Section 22 of the
Act, and does not exempt the holder from compliance with
any other relevant legislation.
N/A A full legal review does not form part of the scope of this Audit.
The site is operated under ISO14001:2015, which requires the
compilation of a legal register. Furthermore, WSP has been
provided with the 2018 ISO audit for review, which specifically
states “the development of the compliance risk management
protocol (CRMP) to assist the organization to reach a higher level
of legal compliance is commendable”.
Evidence:
— SCO DQS ISO 14001 2015;
— 2018 DQS 3rd Party Audit Report_Sasol Secunda Chemicals
Operations.
None
1.03 This Department may change and/or amend any of the
conditions in this authorization if, in the opinion of the
Department, it is environmentally justified.
N/A Noted. Sasol advised the auditor that to their knowledge the
Department has not changed, added or amended any of the
conditions within this EA.
None.
1.04 A copy of this authorization shall be available at the Sasol
Chemical Industries (Pty) Ltd Secunda, at all times and all C Copies of all authorisations and licences are sent to, and details
communicated with, relevant business units. Copies of these
None.
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL CHEMICAL OPERATIONS: SOLVENTS DIVISION
WSP June 2019
Page 8
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
staff, contractors and sub-contractors shall be acquainted
with the contents of the authorization.
documents are also available at the SHE: Environment department
and on SAP EC and SharePoint. Sasol provided the auditor with
the evidence that the responsible persons, Alfie Naidoo (Senior
Manager of Chemical Workup Units) and Willem Jacobs (legal
appointee of Solvents), were made aware of the EA in September /
October 2016.
Evidence:
— EA_EX Handover_SCO_Solvents_CWU_EA
ESTABLISHMENT OF THE ETHYL ACETATE PLANT
2.01 If changes need to be made to the plant and/or associated
structures other than that which has been agreed upon, this
Department must be informed thirty (30) days in advance, to
be able to decide whether the changes need authorization.
N/A Noted. Sasol have advised the auditor that no changes have been
made to the project description within the EA within the audit
period.
None.
2.02 The Ethyl Acetate Plant must operate according to
recognized environmental management standards. This
Department must receive a proposal towards the
environmental management system which management of
the specific plant proposes to implement in order for the
Department to approve or disapprove such a system.
C Sasol Chemical Operations are ISO 14001:2015 certified. The
auditor was provided with proof of certification. The certification
is valid from 12 October 2016 until 11 October 2019.
The submission of a proposal to the Department is deemed outside
of the audit period and therefore not applicable.
Evidence:
— SCO DQS ISO 14001 2015
None.
2.03 This Authorisation is repealed if the project is not
commenced within two (2) years from the date of
Authorization.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None.
CONSTRUCTION AND OPERATION
3.01 Standards laid down by the SABS and National Fire
Prevention Association (NFPA) regarding i) lightning C Sasol have developed Sasol specification SP-60-56 rev1_2010-05-
29 for Electrical Design Criteria and Earthing and Lightning
None.
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL CHEMICAL OPERATIONS: SOLVENTS DIVISION
WSP June 2019
Page 9
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
protection as we as ii) fire detection, protection and fighting
systems must be followed and adhered to.
Protection Guidelines DG60-06-02-001_2006-01-06. SP-60-56
makes reference to SANS 10313 (Protection against Lightning-
Physical damage to structures and life hazard). In addition Sasol
have a Earthing and Lightning Protection: General Guidelines
(DG60-06-02-001). Other codes which Sasol conform with are
NFPA code 780 standard for the installation of lightning protection
and API RP 545, Recommended Practice for Lightning Protection
of Above Ground Storage Tanks for Flammable or Combustible
Liquids.
Evidence:
— 3.1 RE EA Condition information
— 3.1 RE EA Condition information1
— 3.1 Earthing andLight Protection_2006
— 3.1 Elec design criteria_SP-60-56_2010-05-29
— 3.1 Smoke detection_2019-01-15
3.02 The Ethyl Acetate plant must be incorporated into Sasol's
existing Hearing Conservation Programme in order to
comply with the minimum requirements of Environmental
Regulations for workplaces in terms of the Occupational
Health and Safety Act, 1993 (Act 85 of 1993).
C Sasol Chemical Operations have a valid BS OHSAS 18001: 2007
certification. The auditor was provided with proof of the
certification. The certification is valid from 12 October 2016 to 11
October 2019.
Evidence:
— SCO DQS BSOHSAS 18001 2007
None.
3.03 Illumination of the plant must comply with the statutory
requirements of Environmental Regulations for Workplaces
in terms of the Occupational Health and Safety Act, 1993
(Act 85 of 1993).
NC The auditor was informed that Sasol undertake biennial
Illumination surveys at the Sasol Chemicals Operational area.
The auditor was provided with a copy of the original survey
undertaken by Daleen Locke (dated 2 February 2002). The survey
concluded that a number of areas were under illuminated. The
auditor was not provided evidence that the recommendations in
this report were actioned.
Evidence:
— EA_Illumination Survey
Ensure that illumination of
the plant meets the required
standards as outlined in this
condition.
Target Completion
Medium Term
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL CHEMICAL OPERATIONS: SOLVENTS DIVISION
WSP June 2019
Page 10
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
3.04 Care must be taken to comply with any other relevant section
of the Occupational Health and Safety Act, 1993 (Act 85 of
1993). This must be accomplished by incorporating the Ethyl
Acetate Plant into Sasol's NOSA Five (5) Star System.
C Sasol no longer use the NOSA 5 Star Safety System. Sasol are BS
OHSAS 18001: 2007 certified. The auditor was provided with
proof of the certification. The certification is valid from 12
October 2016 to 11 October 2019.
Evidence:
— SCO DQS BSOHSAS 18001 2007
None.
3.05 The design capacity of Ethyl Acetate produced at the Ethyl
Acetate plant may not be surpassed. C Sasol have advised the auditor that the plant is operated in
accordance with a Standard Operating Procedure, prohibiting
exceedance of the design capacity.
Evidence:
— 3.05 EA SOP
None.
3.06 No firewater, apart from firewater to be utilized for
firefighting/commissioning purpose, may be used during the
normal operation of the High Purity Ethanol Plant.
C During the site walk over, Sasol confirmed that no firewater, apart
from firewater to be utilized for firefighting/commissioning
purpose, is utilised during the normal operation of the High Purity
Ethanol Plant.
Evidence:
— Personal Communication
None.
3.07 No raw water/potable water may be utilized during the
normal operation of the Ethyl Acetate Plant. C During the site walk over, Sasol confirmed that no raw
water/potable water is utilized during the normal operation of the
Ethyl Acetate Plant.
Evidence:
— Personal Communication
None.
3.08 Burrow-pits utilized for the mining of dolerite must be
registered with the Department of Minerals and Energy
(DME). Operators of these burrow-pits must be in
possession of approved Environmental Management
Programmes (EMPRs), registration certificates and all
N/A Mining of dolerite is not associated with the operational activities
covered within the EA. This condition is considered not applicable.
OFI:
An amendment of the EA
could be sought to remove
this condition.
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL CHEMICAL OPERATIONS: SOLVENTS DIVISION
WSP June 2019
Page 11
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
requirements of the Minerals Act, 1991 (Act 50 of 1991),
must be adhered to.
3.09 All waste, off-spec products or spent catalysts, should be
recycled or re-routed into the process treated or disposed of
on a permitted waste disposal site according to the
classification of such waste.
C Sasol advised the auditor that all off-sec product is sent to a slop
tank and then sent back into the processing plant for reworking
until it meets the required specifications.
Evidence:
— Personal Communication
None.
3.10 Firewater and not raw water must be used for commissioning
of the Ethyl Acetate Plant. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None.
3.11 A plant specific Emergency Procedure must be developed as
part of the operation manuals of the Ethyl Acetate Plant. C Sasol have provided the auditor with the emergency response
procedure developed in August 2018 for the control room,
conference room and shutdown facility. The plan clearly identifies
the roles and responsibilities, procedures to be followed in case of
emergency scenarios such as:
— Fires on tank roofs;
— Building fires;
— Bomb threats; and
— Medical emergencies.
Evidence:
— 3.11 EA Emergency Procedure
None.
3.12 Commissioning of the site may not take place before receipt
of, and approval of the final design criteria for the Polishing
Reactor and Ethyl Acetate column reflux system.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None.
3.13 Commissioning of the site may not commence without this
Department receiving and approving the considerations
given in determining the final site location with regard to a
potential explosive buffer zone.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None.
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL CHEMICAL OPERATIONS: SOLVENTS DIVISION
WSP June 2019
Page 12
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
3.14 Sasol must conduct a quantitative risk assessment as soon as
more detailed process information becomes available. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None.
3.15 Emission limits and operating conditions issued in terms of
the Atmospheric Pollution Prevention Act, 1965 (Act 45 of
1965), must be adhered to.
C Sasol makes use of an integrated approach to air quality
management as governed by National Environmental
Management: Air Quality Act. Sasol works closely with the local
authority and operates units in line with the relevant AEL and
minimum legal emission requirements.
Sasol Solvents Chemical Operations have an Atmospheric
Emissions Licence (AEL) issued on 31 March 2015 (reference
number: 0017/2015/F02). Sasol undertake atmospheric emission
monitoring in accordance with the conditions of the requirements
of the AEL. The incidents registers for 2015- 2017 and 2017- 2019
do indicate any emission exceedances from the plant.
Evidence:
— Compliance_Air_Secunda Complex
— AEL Sasol Solvents 0017-2015-F02 (2015)
— Copy of Environment Impact register_ New FY17
— Environment Impact register_ New FY19_2019-02-18
None.
3.16 Detailed plans for the water removal unit must be forwarded
to this Department and the DWAF before the construction of
the plant may commence.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None.
3.17 Sasol must develop the contingency plans regarding storm
water quality and quantity. These plans must be approved by
the DWAF. Proof of approval must forwarded to this
Department.
C Sasol have developed an Integrated Water and Waste Management
Plan (IWWMP) which was submitted to the Department of Water
and Sanitation (DWA), formally known as DWAF. Sasol have
however Sasol have not provided evidence that the approval of the
IWWMP was submitted to the Provincial Department of
Agriculture, Rural Development, Land and Environmental Affairs
(DARDLEA), formally known as the Department of Agriculture,
Conservation and Environment.
None.
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL CHEMICAL OPERATIONS: SOLVENTS DIVISION
WSP June 2019
Page 13
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
The submission of the plans to the DWAF, and subsequent
approval, is considered outside of this audit period.
Evidence:
— IWWMP SIC 2015 Final_2018-05-15
AIR POLLUTION
4.01 Emission limits and operating conditions as stated in the
provisional registration certificates issued in terms of the
Atmospheric Pollution Prevention Act, 1965 (Act 45 of
1965), must be adhered to.
C Sasol makes use of an integrated approach to air quality
management as governed by National Environmental
Management: Air Quality Act. Sasol works closely with the local
authority and operates units in line with the relevant AEL and
minimum legal emission requirements.
Sasol Solvents Chemical Operations have an Atmospheric
Emissions Licence (AEL) issued on 31 March 2015 (reference
number: 0017/2015/F02). Sasol undertake atmospheric emission
monitoring in accordance with the conditions of the requirements
of the AEL. The incidents registers for 2015- 2017 and 2017- 2019
do indicate any emission exceedances from the plant.
Evidence:
— Compliance_Air_Secunda Complex
— Copy of Environment Impact register_ New FY17
— Environment Impact register_ New FY19_2019-02-18
— AEL Sasol Solvents 0017-2015-F02 (2015)
None.
RISK MANAGEMENT
5.01 All employees, contractors and sub-contractors employed by,
or delivering a service to Sasol with regard to the Ethyl
Acetate Plant must be acquainted with the characteristics and
dangers associated with such a plant. They must also be
familiarised with emergency procedures associated with the
C Every person entering the Sasol site is subject to a SHE induction
process to ensure that all persons are familiar with the Safety,
Health & Environmental aspects and requirements of that
site/plant.
In addition, there is specific induction training for entry into the
Sasol Solvents Operational areas. No person unaccompanied
None.
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL CHEMICAL OPERATIONS: SOLVENTS DIVISION
WSP June 2019
Page 14
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
Ethyl Acetate Plant and any other integrated structures that is
relevant to this project.
unauthorised person will be allowed access to the solvents area
without undertaking solvents induction training. Sasol have
advised the auditor that the training includes risks associated with
working in the solvents area, operational and emergency
procedures.
Evidence:
— Induction_Mod3_Environment
— Induction_Mod4_ProcessSafetyManagement
— Induction_Mod5_WorkPlaceSafety
— Induction_Mod6_EmergencyManagement
INSPECTION AND MONITORING
6.01 The Ethyl Acetate Plant and its associated infrastructure
should be regularly checked to prevent incidents from
occurring. Inspection time frames must be reviewed at pre-
determined time-intervals.
C During the site walkover Sasol advised the auditor that the Ethyl
Acetate Plant and its associated infrastructure is regularly
inspected to prevent incidents from occurring.
Evidence:
— Personal Communication
None.
DECOMMISSIONING
7.01 Decommissioning of the new Ethyl Acetate Plant may not
commence without the Department receiving, and approving
the formal rehabilitation plan for the plant six (6) months in
advance of the proposed decommissioning date.
N/A Noted. Sasol have advised the auditor that there are no plans to
decommission the plant in the foreseeable future. This condition is
therefore deemed not applicable.
None.
ENVIRONMENTAL AUDITING
8.01 External environmental audit: Six (6) months after
commissioning of the plant, this Department must be
supplied with the external audit report. The report must
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None.
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL CHEMICAL OPERATIONS: SOLVENTS DIVISION
WSP June 2019
Page 15
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
cover all environmental as well as operational aspects
associated with the plant.
8.02 Internal Environmental auditing: Sasol must conduct internal
environmental audits on a yearly basis. The results of these
internal audits must be forwarded to this Department for
monitoring purposes.
NC Sasol have not undertaken internal auditing of the EA on an annual
basis.
Sasol should undertake
annual internal audits going
forward.
Target Completion
Short term
REPORTING
9.01 The Department must be notified within 24 hours in the
event of non-compliance with any of the conditions of this
Authorization.
NC Sasol have not advised the Department regarding the non-
compliances identified in this audit.
Going forward Sasol must
notify the Department of
any non-compliances
against the conditions of
this EA.
Target Completion
Short Term
9.02 Records relating to the compliance/non-compliance with the
conditions of the authorization must be kept in good order.
Such records must be made available to this Department
within seven (7) workdays of the date of written request for
such records.
N/A This audit represents the first required audit for this Exemption.
Prior to the introduction of the 7 April 2017 amendment to the
Environmental Impact Assessment (EIA) regulations, no audit
against this Exemption was required.
None.
9.03 Non-compliance with, or any deviations from the conditions
as set out in the authorization and Environmental Scoping
Report, is regarded as an offence and, after reasonable
provision has been made for remedial action, will be dealt
with in terms of Section 29, 30 and 31A of the Act.
N/A Noted. Sasol has advised the auditor that they are aware of this
condition.
None.
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL CHEMICAL OPERATIONS: SOLVENTS DIVISION
WSP June 2019
Page 16
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
9.04 Any complaint regarding the said activity must be brought to
the attention of the Department within 24 hours after
receiving the complaint. A complaints register must be kept.
This register must contain up to date information by
members of this Department within seven (7) days, after
requesting such information.
C The auditor has reviewed the complaints register maintained by
Sasol. No complaints have been received in relation to the
operating of the Ethyl Acetate Plant for the audit period. Sasol
have advised that should a copy of the complaints register be
requested by the relevant Department, it will be made available.
Evidence:
— Environmental Complaints Register_2019-02-18
None.
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL CHEMICAL OPERATIONS: SOLVENTS DIVISION
WSP June 2019
Page 17
5 SUMMARY OF THE AUDIT FINDINGS
5.1 ENVIRONMENTAL AUTHORISATION
The audit findings have been summarised into the following categories: compliance, non-compliance and not
applicable. The overall audit findings concerning compliance to the EA conditions are as listed in Table 3
below.
Table 3: Summary of EA Compliance Audit Findings
SECTION OF THE EA
NO.
COMMITMENTS C NC N/A
GENERAL CONDITIONS 4 1 0 3
ESTABLISHMENT OF THE ETHYL ACETATE
PLANT
3 1 0 2
CONSTRUCTION AND OPERATION 17 10 1 6
AIR POLLUTION 1 1 0 0
RISK MANAGEMENT 1 1 0 0
INSPECTIONS AND MONITORING 1 1 0 0
DECOMMISSIONING 1 0 0 1
ENVIRONMENTAL AUDITING 2 0 1 1
REPORTING 4 1 2 1
Total Count 34 16 4 14
Total Percentage 47% 12% 41%
Percentage Compliance with Applicable Conditions 80%
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL CHEMICAL OPERATIONS: SOLVENTS DIVISION
WSP June 2019
Page 18
Figure 2 illustrates the number/count contribution of the findings of the EA per section while Figure 3 presents
the total proportion of compliance for the facility.
Figure 2: Number/Count contribution of findings made to the EA conditions per Section
Figure 3: Overall count findings on compliance to the EA conditions
02468
1012141618
Sectional Count Contribution
C
NC
N/A
16
4
14
Total Compliance
C
NC
N/A
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL CHEMICAL OPERATIONS: SOLVENTS DIVISION
WSP June 2019
Page 19
Figure 4 illustrates the percentage contribution of the findings of the EA conditions. Figure 5 presents the total
percentage compliance for the facility.
Figure 4: Percentage contribution of findings made to the EA conditions per Section
Figure 5: Overall percentage findings on compliance to the EA conditions
0102030405060708090
100
Sectional Percentage Contribution
C
NC
N/A
47%
12%
41%
Total Percentage Compliance
C
NC
N/A
APPENDIX
A ENVIRONMENTAL AUTHORISATION
(14/3/L/A/SAS.E.A)