  • OVER VIEW OF

    SAP PS Configuration

    Pack

    Published by Team of SAP

    Consultants at SAPTOPJOBS

    Visit us at www.sap-topjobs.com

    Copyright 2010-12@SAPTOPJOBS

    All rights reserved. No part of this publication may be reproduced, stored in

    a retrieval system, or transmitted in any form, or by any means electronic

    or mechanical including photocopying, recording or any information storage

    and retrieval system without permission in writingfrom

    SAPTOPJOBS

  • PS Configuration Overview

    1. PROJECT SYSTEM STRUCTURE 4

    1.1

    Define Special Characters for Projects

    8

    1.2

    Define Project Coding Mask

    11

    1.3

    Define Field selection for Work Breakdown Structures

    14

    1.4

    Define Validation

    19

    1.5

    Maintain Substitution

    24

    2. DEFINE TIME PROFILES 29

    2.1

    Define Profiles for Time Scales

    33

    2.2

    Define PRT Usage

    36

    3. ACTIVATE PROJECT MANAGEMENT IN CONTROLLING AREA 39

    3.1 Maintain Value categories 42

    3.2

    Unit Costing

    45

    3.3

    Create / Change Planning Profile

    49

    3.4

    Maintain Budget Profile

    54

    3.5

    Define Tolerance Limits

    57

    3.6

    Maintain Progress Version

    60

    4. SCHEDULING TYPES 63

    4.1

    Parameters for Network Scheduling

    66

    4.2

    Define Database Selection Profile

    69

  • Hello Everyone,

    A Ware Welcome To You All! We are really excited to offer the

    complete SAP PS configuration pack to the SAP community. This

    was a much- awaited pack and we are happy to present that to

    you As you are aware that our SAP FICO, PP/QM , SD, MM/WM

    HR, and PM have already achieved the best selling status and have

    received lots of accolades and really helped the consultants take

    their SAP knowledge and career to the next level I am very

    confident that PS configuration package will go a step forward and do

    much more than that.

    For those who have been on our list and who have bought from us

    earlier you all know that we have over-delivered on each of our

    configuration packs and we want to do the same thing with SAP PS

    config pack too For those who have visited our site for the first

    time I would like to welcome you to our site and promise you that

    we would do our best to ensure that your life at the clients place would

    be very comfortable

    What I have done here is given you a brief of around 69+ pages

    of content in PS pack so that you can have a feel of what it would be

    like in terms of structure. The whole pack is extremely voluminous,

    step by step guide this is just a feeler So I hope you enjoy this. So

    lets dive right in.

  • 1. Project System Structure

    Planning of all activities in detail is an essential process in any

    project irrespective of its size and volume. Right Project planning helps to ensure the completion of project at right

    time with right amount cost involved.

    It is also essential to know the amount of resource and funds

    required to execute the project and also the timings of its

    requirement. In an organization many tasks like construction,

    installation of large machinery etc.., are carried out as projects.

    Project organization is a prime and foremost step in project

    structuring. Project Organization in PS helps to

    Plan the project

    Monitor the project progress

    Control the project progress

    Projects can be structured based on

    Work Breakdown Structure (WBS) element Work package with activities

    From Finance point of view, each project is identified as

    Externally financed project Internally financed project

    Project System Organization: -

  • Project system has got the following parameters.

    Project definition

    WBS element

    Networks

    Activities

    The above discussed PS module elements are assigned to the

    existing organizational units. I.e. these are assigned to the

    existing controlling area, company code, business area, profit

    center and plant.

    In short we can say that there is no independent org structure

    for PS module like SD and MM. The PS parameters are

    assigned to the existing organizational units at different levels.

    Let us discuss the possible assignments of each PS elements

    with existing org. structure.

    Project Definition:

    Project Definition is the process of defining the project with its

    objective, Accounting information and logistic related

    information.

    Accounting information:-

    Controlling Area

    Company code Business Area

    Plant

    Location

    Profit center

    Currency

    Budget profile

    Interest calculation profile

    Planning profile

    Investment profile

    Result Analysis key

  • Logistic information

    Network profile

    WBS Scheduling profile

    Person responsible

    Start & End date

    Factory calendar

    Time unit

    WBS Element: -

    WBS element is a master data used for projects. The usage of

    WBS is

    Organizes the project task in an order Process planning, cost planning, capacity planning Costing and controlling To know the amount of work involved in a project

    WBS is created with reference to the project definition. The

    data maintained under project definitions are copied into WBS

    WBS Accounting information:-

    Currency Copied from projection profile. Can be changed only if company code

    currency is different from controlling

    area and there must NOT be any

    budget, commitments exist for the

    WBS element.

    Company code Business area Profit center Plant

  • Network: -

    Network represents flow of task in a project. Tasks performed

    with WBS such as planning, controlling etc. can be done with

    network also. The structure of the network is similar to that of

    production order and maintenance order.

    Network can be assigned to

    Project definition WBS Time sheet entry

    Activities: -

    Activities indicate the sequence of any process. Activities

    contains

    Duration

    Start and finish

    Requirement of resources

    Cost requirements

    Activities can be

    Internally processed

    Externally processed

    Service related

    General cost activities

    Now let us see what is there in the configuration for PS

    structure.

    The project definition contains various profiles from costing

    point of view. We shall start from WBS structure.

  • Define Special Characters for Projects

    BACKGROUND

    This configuration setting enables to define how the project

    number is coded for editing.

    Following parameters are controlled in this setting to edit the

    project number.

    Length of the key for project coding - Max. five Mandatory length of the project coding whether all five

    must be filled or not.

    Special characters allowed for entering WBS

    SCENARIO

    Define special character for projects.

    INSTRUCTION

    Follow the Menu Path: IMGProject System Structures Operative Structures Work Breakdown Structures (WBS) Project Coding Mask Define Special characters for Projects

    Click or

    use OPSK in the command field and press Enter.

  • Maintain fields as explained below

    Field Name Value and Description of field

    Length of key for coding of the project

    definition and WBS elements.

    Possible entries are

    E.g.5 indicates maximum

    It must be set carefully before creating any

    projects.

    We will proceed with 1 in our example.

    Key used to specify project coding and

    WBS element must of same length as it is

    defined here.

    E.g. Leave it blank not to restrict the length

    of project coding and WBS element.

    To help entering the WBS element in the

    work break down structure, this special

    key is defined.

    E.g. Enter ". To enter a new WBS element

    under WBS element, it is enough to enter "

    and new number. E.g. say new number is 30, then system will maintain the number

    with all prefixes and the number 30.

  • Special character used to limit the

    segments in the coding.

    E.g. / to limit with the character / between

    the segments.

    Check in this tick box will allow only the

    coded project numbers within the project

    system.

    E.g. tick the check box.

    This field is used for automatic number

    assignment.

    E.g. Leave it blank.

    Click

    Click

    Impact of this configuration in Master Data / Transaction

    Project numbering will be as per this project special character

    setting.

  • Define Project Coding Mask BACKGROUND

    This configuration setting enables to create masks for editing

    the project number.

    Project coding mask is helpful to simplify the complex project

    numbers. It is also used to indicate the position of the WBS

    element.

    SCENARIO

    Discuss the project coding mask. Ex: /000-XXX-000/XXXX

    INSTRUCTION

    Follow the Menu Path: IMGProject System Structures Operative Structures Work Breakdown Structures (WBS) Project Coding Mask Define Project Coding Mask

    Click

    Or Enter OK02 in the command field press Enter.

    Click

    Maintain fields as explained below

  • Field Name Value and Description of field

    Length of key for coding of the project

    Note:- Here the project id can be maximum

    of 1 digit as we have set up the PL field in

    the above setting as 1.

    Define the coding mask for project

    definition

    0 (zero) only numeric characters

    X alpha numeric characters

    Maintain description of coding mask

    Tick in this check box will not enable the

    new request for WBS element, project

    definition or appropriation request to be

    created with this masking code.

    Tick in this check box will not allow

    creating coding mask for standard project

    or WBS element.

    Click

    Click

    Impact of this configuration in Master Data / Transaction

    Project coding mask created here will be used while creation

    project definition, WBS element or appropriate request.

  • Define Field selection for Work Breakdown Structures

    BACKGROUND

    This configuration setting enables to define the WBS field

    selection.

    Through this configuration setting it is possible to make a field

    mandatory, optional, hide or view only.

    It is required to make certain field to make mandatory

    according to the business requirement.

    SCENARIO

    Make Project Description field as mandatory for company code

    3000

    INSTRUCTIONS

    Follow the Menu Path: IMGProject System Structures Operative Structures Work Breakdown Structures (WBS) User Interface Settings Define Field Selection for Work Breakdown Structures

    Click

  • Double click

    Double click on Description field

  • Click on

    Click

    Enter the company code as 1000

    select radio button

    Double Click to influence any of one fields

  • Click

    Double click

    Similarly as explained above, field selection can be done for

    WBS element also.

    Note:- the procedure is same for Network field selection as well.

    Impact of this configuration in Master Data / Transaction

  • When creating project definition CO area become mandatory

    entry

  • Define Validation

    BACKGROUND

    This configuration setting enables to define validation.

    Use validations to check values and value combinations that

    users enter in the Project System. Validation can be carried

    out at various points in time.

    Following are the steps to be carried-out:

    Enter a name for the validation.

    The application area is proposed by the system.

    Enter a call-up point when the validation should be

    carried out.

    Create a validation step or select an existing one.

    Select the field that you want to use for the validation.

    Enter a prerequisite and specify how the validation

    should be carried out.

    For each validation step enter a prerequisite, a check and

    a validation message. The message is issued when the

    prerequisite is met and when the value does not check. SCENARIO

    Discuss validation defining.

    INSTRUCTION

  • Follow the Menu Path: IMGProject System Structures Operative Structures Work Breakdown Structures (WBS) Maintain Validations

    Click

    Click the required object to create validation E.g.

    Click

    Enter validation name. e.g. ZLEGL02 and text as check profit center

    Click

  • Click to enter any prerequisite

    Double click

    Click

    Click

    Enter the project definition to which the check is to be

    applicable.

    Double Click

  • double click

    Click

    Click

    Enter the value which must be maintained as profit center for

    project definition with W

    Click

    Double Click

    Enter message type

    Enter message number.

    Message variable entered if the message contains any variable.

    Example: -

    Message:- "Acount $ is not allowed in company code $"

    Output field 1: BSEG-HKONT (=400000)

  • Output field 2: BSEG-BUKRS (=0001)

    Click

    Message appear at the bottom

  • Maintain Substitution

    BACKGROUND

    This configuration setting enables to define substitution.

    Use substitutions to replace values and value combinations in

    the Project System. In addition you can define several

    interdependent substitution statements for future use.

    Following are the steps to be carried-out:

    Enter a name for the Substitution.

    The application area is proposed by the system.

    Enter a call-up point when the substitution should be

    carried out.

    Create a substitution step or select an existing one.

    Select the field that you want to use for the substitution.

    Enter a prerequisite and specify how the substitution

    should be carried out.

    SCENARIO

    Discuss substitution defining.

    INSTRUCTION

    Follow the Menu Path: IMGProject System Structures Operative Structures Work Breakdown Structures (WBS) Maintain Substitution

  • Click

    Click on the object where the substitution is to be created. E.g.

    whether on project definition or on WBS element

    Click to create rule or click to create

    substitution

    Enter substitution key and text

    Click

  • Enter the step number and text

    Double click

    Double click

    Click

    Click

    Enter the finish date

    Click

  • Double click

    Click

    Select the field person responsible

    Click

    Select the appropriate radio button. E.g.

    Click

  • Enter the required value

    Click

  • 2. Define Time Profiles

    BACKGROUND

    This configuration setting enables to define the time profiles.

    Time profile is used to specify various working time periods

    used in the project planning board.

    Time profile contains the evaluation period and planning

    period.

    Evaluation period is the time frame for working with and

    displaying data in the project planning board. Beyond the

    evaluation period, it is not possible to work with and display

    the data in the planning board.

    Planning period is used to define the time frame for carrying

    out current planning in the project planning board.

    If the start date is beyond the current date, the planning period begins with the start date.

    If the start date is earlier than the current date, the

    planning period begins with the current date.

    SCENARIO

    Discuss the time profile.

    INSTRUCTION

    Follow the Menu Path: IMGProject System Structures Project Planning Board Define Time Profiles

    Click

  • Click

    Maintain fields as explained below

    Field Name Value and Description of field

    Key identifying the time profile. Enter key

    and description. E.g.

    Key indicates the type of entry to be made.

    I.e. Monthly, yearly. Select from available

    entries

  • for

    evaluation period

    E.g. L to indicate years

    Enter start date. E.g. 0. Indicates start

    from 0 years

    Start date is the date of the first day of the

    period to which the data required to be

    evaluated.

    System determines the first date with entry

    here along with entry type.

    E.g. today is 14.01.2005

    Type of entry: G

    Start: -10

    Finish : +20

    evaluation

    period.

    For

    This generates an evaluation period from

    04.01.2005 to the 03.02.2005.

    Enter finish date. E.g. 2 indicates

    evaluation allowed for next two years.

    Similarly maintain the entries as shown below for planning

    period.

  • Click

    Click

    Click

    Impact of this configuration in Master Data / Transaction

    Time profile defined here can be assigned to the project

    planning board in the subsequent settings.

  • Define Profiles for Time Scales

    BACKGROUND

    This configuration setting enables to define Time scale

    profile.

    Time scale profile defines the properties of all possible

    scales.

    The possible time scale headings are

    Yearly split Quarterly split Monthly split Weekly split Daily split Hourly split Minute split Shift split

    For each time scale heading maximum and minimum time

    scale must be maintained.

    SCENARIO

    Discuss the profile for time scale.

    INSTRUCTION

    Follow the Menu Path: IMGProject System Structures Project Planning Board Define Profiles for Time Scales

    Click

  • Click to create new entries.

    Note:- it is always suggested to copy from the existing

    standard entry.

    Select any standard row. E.g. second row

    Click

    Enter the new time scale profile. E.g. ZPS_PROAAA

  • As the standard setting is sufficient nothing much to

    change other than specifying the bar chart width in mm for

    minimum and maximum.

    Click

    Click

    Click

    Impact of this configuration in Master Data / Transaction

    Profile for time scale defined here will be used in the project

    planning board setting.

  • Define PRT Usage

    BACKGROUND

    This configuration setting enables to define the PRT usage.

    Production Resource Usage controls the usage of PRT in

    different task list and applications.

    It is possible to allow the usage of PRT only in networks.

    SCENARIO

    Discuss the PRT usage setting.

    INSTRUCTION

    Follow the Menu Path: IMGProject System Production Resource Tool General Data Define PRT Usage

    Click

  • Click to create new entries, SAP standard usage is

    sufficient to work with. Let us discuss the standard usage

    003.

    Select usage 003

    Double Click in the left side

  • Maintain the task list type under the usage.

    Click

    Click

    Click

    Impact of this configuration in Master Data / Transaction

    When creating the PRT, usage can be defined as per the

    settings here.

  • 3. Activate Project Management in Controlling Area

    BACKGROUND

    This configuration setting enables to activate project

    management in controlling area.

    This setting also enables to activate the commitment

    management for a controlling area.

    SCENARIO

    Discuss activation of project management in controlling area. INSTRUCTIONS

    Follow the Menu Path:- IMGProject System Costs Activate Project Management in Controlling Area

    Click

  • Available controlling areas are displayed at right side. Select

    the desired row

    To the desired controlling area activate the projects( )

    and commitments management ( )

  • Note:- There could be other settings related to CO module, like

    assigning the company code to controlling area etc.. but here

    the point of activating project management only explained.

    Click

  • Maintain Value categories

    BACKGROUND

    This configuration setting enables to define value categories.

    Value categories are required for

    Updating project information database

    Calculating interest on projects

    Defining reports

    Updating quantities in project info. SCENARIO

    Discuss maintenance of value categories. INSTRUCTIONS

    Follow the Menu Path:- IMGProject System Costs Value Categories Maintain Value categories

    Click

    Enter the controlling area

    Click

    Click

  • Enter the value category. E.g. Z01

    Enter the description for value category maintained.

    Select the relevant radio button as explained below.

    E.g. Cost radio button to the purpose of posting of costs or

    outgoing payments.

    Revenues to the purpose of posting revenues and incoming

    payments

    SKFw.Tt to the purpose of posting statistical key figure with

    total characteristic value

    SKF FVA to the purpose of posting statistical key figure with

    fixed value characteristic

  • Click

  • Unit Costing

    Unit costing will be where you have information on sources of

    supply, quantities, and prices. Plan overall or annual values

    for unit costing. Costing variant is to combine all the controlling parameters for

    costing. Costing variant represents the link between the

    application and customizing because all costing run must

    reference a costing variant as they are made and stored.

    The costing variant controls the following parameter.

    Costing variant contains the valuation variant and

    costing type.

    Valuation variant controls price to pickup for material,

    subcontracting and external processing.

    Valuation variant contains the costing sheet also (over

    head calculation)

    BACKGROUND

    This configuration setting enables to define the variants for

    Unit costing.

    SCENARIO

    Define / discuss costing to create variant.

    INSTRUCTIONS

    Follow the Menu Path:- IMGProject System Costs Manual cost planning in WBS Unit Costing Create Costing Variant.

    Or Enter OKKT in the command field press Enter.

  • Maintain the fields as explained below Field Description

    This field sets how the cost to

    be estimated based on the

    materials, Production orders

    with controlling, Internal

    orders and sales orders.

    Based on the type of business scenario costing variant is

    created.

    Click on new entries

  • In Control Tab maintain the field as explained below Field Description

    This field requires how the

    cost estimate to be used. Ex:

    unit cost est. for proj

    This field specifies the prices

    the system selects to valuate

    the quantity structure of a

    cost estimate with quantity

    structure or of the order, or to

    valuate the costing items of a

    unit cost estimate. Ex:

    Planned valuation orders.

    This field sets how the date

    control of a cost estimate is

    handled. Ex: Mod.std cost est.

    dates

  • Click on the assignment tab

    Click on to verify the variant. To verify the variant variant to be saved.

    Click Save .

    If the Variant is ok system will give message

    Impact of this configuration in Master Data / Transaction

    Based on the business scenario use the costing variant

  • Create / Change Planning Profile

    BACKGROUND

    This configuration setting enables to create / change planning

    profile. Planning profile is required to plan the cost methods.

    Following controls are available in the planning profile.

    Time frame can specify which values are the to planned and

    their fiscal years.

    Value display - to display the decimal places and decimal

    factor

    Detail planning values for cost element planning ,activity

    Input planning and cost planning.

    Planning profile is used

    For all WBS elements or only on planning elements ,

    Bottom-Up planning within hierarchical planning ,

    Automatic revenue planning. Based on the settings one can decide whether the system

    updates plan revenues on the corresponding billing elements.

    Profile can be Cost planning for investment programs or

    investment measures, and for appropriation requests.

    SCENARIO

    Define / Discuss Planning profile. INSTRUCTIONS

  • Follow the Menu Path:- IMGProject System Costs Planned Costs Manual cost planning in WBS Hierarchical Cost Planning Create / Change Planning Profile.

    Or Enter OPSB in the command field press Enter.

    Click on the new entries or copy the existing plan based on

    the business scenario.

    Maintain the fields as explained below

    Field Description

    This sets the control

    parameter for the planning.

    In the Manual Planning - when the Bottom up planning indicator is set, the system

    automatically carries out the

    total up function in structure

    planning for costs and

    revenues each time you save

    and check data. The structure

    plan value for the higher level

    WBS item is the total of all the

    plan values for the WBS

    elements directly below it.

    To ensure that the structure

    plan values for the whole

    project structure are uniform,

    must access the structure

    planning for the whole project

    and check and save the

    values.

  • This field sets cost planning is

    possible in only those WBS

    elements are defined as

    Planning elements. Can carry

    the cost planning in any WBS

    elements when the indicator is

    set.

    This field require the time

    frame in future means how

    far can far.

    Based on the scenario can

    mention Past and start time

    frames.

    This field sets the values

    required in total and annual

    years.

    This field sets whether any

    decimal places and its scaling

    factor required for the

    planning profile.

    This field sets the cost

    element group as primary

    costs where goods brought in

    externally like raw materials ,

    operating supplies ,

    services ,etc based on the

    chart of accounts. Ex:

    OAS_PRIM

    This field sets to summarize

    cost elements of the same

    types in reports. Ex:

    OAS_REVEN

    This field specifies the cost

    center group of sender

    for which activity types

    are planned. EX: H1400

    This field sets each activity

    type in this group can appear

  • as a sender activity type in

    activity input planning. EX:A1

    This field sets a group of

    stastical key figure used in

    reporting to process multiple

    key figures in a

    single transaction. EX:

    STAT_9000

    This field sets how the cost

    estimate is performed and

    valuated. EX: INV1

    This field sets the exchange

    rate in the system and value

    dates determines daily

    exchange rates applies

    For currency translation. EX:

    001

    This field sets the types of

    planning currency based on

    Controlling area currency /

    object currency / Translation

    currency. EX: Controlling area

    currency.

    This field sets how the

    revenue planning should

    happen automatically through

    quotation or sales order..

    This field requires to enter the

    type of revenue element for

    billing plan to WBS element.

  • Click Save .

    Impact of this configuration in Master Data / Transaction

    Based on the planning profile one can carry out Cost

    Planning by entering values in the cost plan column using

    CJ30 transaction code.

  • Maintain Budget Profile

    BACKGROUND

    This configuration setting enables to control the budget for the Project.

    SCENARIO

    Define / Discuss budget profile.

    INSTRUCTIONS

    Follow the Menu Path:- IMGProject System Costs Budget Maintain Budget Profiles.

    Or Enter OPS9 in the command field press Enter.

    Click on new entries or copy the existing profile based on the

    Business scenario.

    Maintain fields as explained below

    Field Description

    This field sets type profile type

    and description. Ex: 1000

    This field sets the time frames

    which can in past, future or

    start and enable total and

    annual values. Ex: enable in

    Future - 3

    This field sets WBS element

    using this budget profile can

  • only be budgeted if the WBS

    element or a WBS element

    above it in the hierarchy is

    assigned to a program

    position of an investment

    program with the correct

    program type. Ex: 1000.

    This field sets type of control

    that should be available while

    budgeting and how the

    activation type should be. i.e

    Automatic activation during

    budget allocation.

    EX : 1 means automatic

    allocation during budget

    activation.

    This field sets a WBS element

    using this budget profile can

    only be budgeted if the WBS

    element or a WBS element

    above it in the hierarchy is

    assigned to a program

    position of an investment

    program with the correct

    program type. Ex: 1000.

    Based on the type of business scenario use the control

    parameters for network scheduling

    Click Save .

    Impact of this configuration in Master Data / Transaction

    Based on the business scenario define and use the control

    parameters.

  • Define Tolerance Limits

    BACKGROUND

    This configuration setting enables to give tolerance limit for

    the budget profile.

    The Tolerance range /limits the budget if any project overruns

    the allocated cost / money. Activate availability control for a certain budget profile. Can

    specify one or more tolerance limits for each activity group for

    a budget profile. Selected actions (warning, warning with mail to person

    responsible for project, error message) are triggered when

    these limits are reached.

    Tolerance limit for all activity groups can be chosen as activity

    group ++ which make entry easier. Tolerance limit for all

    activity groups can be used if it is not required to define a

    separate tolerance limit for each activity group.

    It is possible to define a limit for a specific activity group in

    addition to a tolerance limit defined for all activity groups.

    This additional tolerance limit has priority over the generally

    valid tolerance limit. SCENARIO

    Define / Discuss Tolerance limits. INSTRUCTIONS

    Follow the Menu Path:- IMGProject System Costs Budget Define Tolerance Limits.

  • Click on new entries if the controlling area belong to the Controlling does not exists. If exists define the tolerance limits.

    Field Description

    This field tells about the

    controlling area. Ex: 2000

    This field sets the budget

    profile to the controlling area.

    Ex: 1000

    This field tells about target

    group of the activity type. Ex:

    ++ indicates that target group

    belongs to all activity types.

    This field sets activity type.

    Ex: 1 /2 / 3.

    This field sets how much the

    usage should be for the said

    budget profile.

    This field tells about difference

    between the assigned funds

    and the budget exceeds the

    absolute variance, availability

    control triggers the

    appropriate action.

    This field tells about the

    controlling area currency.

    Click Save .

  • Impact of this configuration in Master Data / Transaction

    Based on the business scenario define the budget tolerance

    limits.

  • Maintain Progress Version

    BACKGROUND

    This configuration setting enables to define the progress

    version. Progress version is required to create control data for

    calculating the % of completion and the earned value.

    Note:- This is to be done in discussion with CO team

    SCENARIO

    Discuss progress version .

    INSTRUCTIONS

    Follow the Menu Path:- IMGProject System Progress Progress Analysis Maintain Progress Version

    Click

    Click to create new entry

  • Maintain the fields as explained below Field Description Key identifying the controlling

    area. Enter controlling area Key identifying the progress

    version. Enter progress

    version and description Key identifying the plan

    version. Note:- the CO version

    must have exclusive use 03

    i.e. earned value analysis. Earned value is calculated by

    applying the % of completion

    of the cost amount. This

    defines which cost amount is

    to be used. Available entries

    are

  • Value used for weighting in

    the aggregation of the % of

    completion. Possible entries

    are

    Key identifying the type of

    planning to be used. Available

    entries are

    This key to determine whether

    either:

    the earliest date is set to

    the latest date of the

    activity or

    The latest date is set to the earliest date of the

    activity.

    Tick in this check box will

    enable the system to use the

    system uses an existing

    method if the method is not

    maintained.

    Click

  • 4. Scheduling Types

    BACKGROUND

    This configuration setting enables to define the scheduling

    types to the projects.

    Scheduling types governs the way scheduling is to be

    performed.

    SCENARIO

    Define / Discuss scheduling types.

    INSTRUCTIONS

    Follow the Menu Path:- IMGProject System Dates Scheduling Define scheduling types.

    Or Enter OPJN in the command field press Enter.

  • Field Description

    This indicator sets the

    scheduling type as Forward

    for orders and Networks

    means schedules from the

    start date.

    This indicator sets the

    scheduling type as backward

    for orders and Networks

    means schedules from the

    Finish date.

    This indicator sets the

    capacity requirements to

    calculate. Distributed across

    the periods based on the types

  • of dates.

    This indicator sets as todays

    date for scheduling.

    This indicator sets the time to

    enter the basic dates for the

    production orders.

    Based on the type of business scenario use the scheduling

    type.

    Click Save .

    Impact of this configuration in Transaction

    When performing the scheduling in the project, scheduling will

    be carried out as per the setting maintained here.

  • Parameters for Network Scheduling

    BACKGROUND

    This configuration setting enables to define parameter for

    network scheduling.

    Network scheduling contains settings for

    Dates adjustment Type scheduling to be performed Control to allow start day in the past Reduction type

    This setting is performed for the combination of Plant, order

    type and Production scheduler.

    SCENARIO

    Define / Discuss control parameters of scheduling.

    INSTRUCTIONS

    Follow the Menu Path:- IMGProject System Dates Scheduling Specify Parameters for Network scheduling.

    Or Enter OPU6 in the command field press Enter.

  • Field Description Key identifying the plant.

    E.g. 1000 Key identifying order type.

    E.g. PS05 Key identifying the production

    scheduler.

    E.g. * This control determination of basic

    dates to the element or to its

    dependant requirements during

    lead time scheduling. Type of scheduling to be applied to

    this order type or network type.

  • Indicates whether the past start

    date is allowed. If it is to be

    allowed, enter the number of days.

    E.g. Leave it blank.

    Tick in this check box

    automatically schedule the network

    on saving.

    Tick in this check box displays

    scheduling log automatically during

    each scheduling

    e.g. Leave it blank

    Tick in this check box considers the

    exact time of break during

    scheduling.

    e.g. Leave it blank

    Tick in this check box will not

    consider the partially confirmed

    operations.

    E.g. Leave it blank

    This tick mark to schedule the

    component on latest scheduled

    date.

    Indicates what reduction type is to

    be employed

    Number of reduction level to be

    applied.

    Click Save

    Impact of this configuration in Master Data / Transaction

    During network creation, scheduling will be done according to

    the settings maintained here.

  • Define Database Selection Profile

    BACKGROUND

    This configuration setting enables to define Database selection

    profile.

    This is the process of picking up the desired objects and fields

    from the database for information analysis purpose.

    Note: - Standard SAP setting will be sufficient in most of the

    cases. Let us discuss the standard setting and understand.

    SCENARIO

    Discuss the Database selection profile. INSTRUCTION

    Follow the Menu Path: IMGProject System Information system Selection Define Database Selection Profile

    Click

  • Field Name Value and Description of field

    Tick in this check box will enable only last

    person who made changes only to make

    further changes

    Tick in this check box will pickup its

    superior objects also. E.g. WBS elements

    are selected as objects, but it will pickup

    its project definition also.

    Changes can be made only through the

    configuration setting if this check box is

    ticked.

    Tick in this check box will pickup project

    definition from the database

    If not ticked, project can not be made as a

    selection criteria as project definition does

    not appear in the selection screen.

    Tick in this check box will pickup sales

    order and customer quotation for selection

  • Tick in this check box will pickup material

    component from Database.

    Tick in this check box will pickup WBS

    element

    Tick in this check box will pickup

    hierarchy of sub element of WBS.

    Tick in this check box will stipulate

    network and orders assigned to WBS.

    Tick in this check box will pickup network

    assigned to WBS element

    Tick in this check box will pickup the

    production order, process orders assigned

    to WBS

    Similarly all check boxes which are ticked are selected from

    the data base.

    Click Click

    Impact of this configuration in Master Data / Transaction

    Information system when displaying the objects, it will pickup

    data from database as per the configuration maintained here.

    Thats it then The entire PS configuration pack comes

    in 7 voluminous power packed CDS f u l l o f m e a t y c o n t e n t and

    each sub module in SAP PS is broken into Configuration, End

    user and Power point. There are tons of bonuses which you get

    along with this pack including complete Integration documents,

    PS Interview questions and answers and a boatload of step by

    step guides You can take advantage of the special offer by

    visiting the site at

    http://www.sap-topjobs.com/SpecialPP/sapps20071123.html

  • All our packs are shipped thru FedEx and reaches you in three days time. One more thing this configuration pack is compatible with version 4.7, version 5.0 and 6.0 So you really do have to worry about the version at all.. We have taken care of that Also all future version changes will be provided as free updates to you. So you can sit back relax and play the music .

    What I want from you now is to do yourself a favour by bringing

    the brains and wisdom of SAP PS Experts with more than

    12+yrs of implementation experience to your drawing room today.

    Do it right now my dear friend and take your SAP career to the

    next level. You will love it I promise you.