SF Transbay Terminal Roof City Park ProjectGreenleaf Construction Co.
Jessica Chase Thaisa FernandesElizabeth GarrityJorge Martínez
Greenleaf Construction Co.
Greenleaf Construction Co.
Greenleaf Construction CO. aims to be the leader of eco space planning design in San Francisco. Our goal is to design and build community and private outdoor areas in an environmentally sustainable and pet-friendly
Vision
Greenleaf Construction Co.
San Francisco Transbay Terminal
Conceptual Design and Detailed Design of the Transbay Terminal City Park which considering a green roof with sustainable design features and display gardens featuring climate-appropriate plants
Project Objectives
Greenleaf Construction Co.
● Landscape design featuring Mediterranean style/water wise plants● Lighting plan supported by solar energy● Automatic water system utilizing recycled water● Rain water collection system● Hardscape and design features such as statue● Public facilities (benches, public water access) ● IT connectivity by solar panels● Composting for garden maintenance● Compostable doggy bag dispenser ● Water dispenser for people and pets● Cellphone charger by solar energy
Project Scope
Greenleaf Construction Co.
● General Design Criteria and Specific Design Criterias● Architectural and Landscape Design● Layout and 3D Model● Technical Specifications for Eco-friendly (light, water, plants) ● Technical Specifications Public Safety Requirement● Piping Design (technical specifications, data sheets, P&ID, general arrangements, elevations,
isometrics, list, material take-off)● Electrical Design (technical specifications, data sheets, unilineal drawings, material take off,
calculations reports)● Civil Works (technical specifications, drawings, material take-off, calculations reports)● FInal Report
Project Services
Greenleaf Construction Co.
● Construction● Capital Cost Expenditure Estimation and Procurement● Electrical and Water supply● Environmental Impact Analysis, assessment and mitigation requirements due to it● All the lease and the contract requirement to develop the retail areas● Community relationships● Wireless access● Restrooms● Cafe shop design● Topography services● Any other facility does not include in the project scope
Exclusions
Greenleaf Construction Co.
● 38 weeks maximum time to develop the project● The Conceptual Design needs to be approved by the client and other stakeholders
before proceeding with detailed design● Since the roof is under construction, access to the facilities/work site may be
limited● Design based on previous conceptual designs by others
Constraints
Greenleaf Construction Co.
● Design under ISO 14020 and ISO 14024● Eco stamping according to “The United States Environmental Protection Agency” ● Environmentally Preferable Purchasing according to The United States
Environmental Protection Agency ● Recycled-content materials● Reduced or no pesticide use in the garden specification● Use of native plants
Assumptions
Greenleaf Construction Co.
Stakeholders Org Chart
Company Organizational Chart
Project Organizational Chart
Greenleaf Construction Co.
Phases of the Project
Phase 1: Conceptual DesignDeveloping conceptual design that allows the client to view the main features of the park, providing a list of materials for a CAPEX estimation (out of the scope) with an accuracy of +/- 40%
Phase 2: Detailed DesignThis phase builds on pre-approved conceptual design, aiming to further elaborate each aspect of the project through a complete description through solid modeling, drawings, as well as specifications
Work Breakdown Structure (WBS)
Work Breakdown Structure (WBS)
PhasesWBSProject Timeline
60 days116 days
WP Landscape
80 days
WP Garden and Plants
WP Mechanical/ Piping design
55 days
WP Electrical design
48 days
WP Civil work
WP Schedule
10 days48 days81 days
WP = Work Package
60 days
Detailed Design
121 days
Conceptual
Design
SF Transbay Terminal Roof City Park Project181 days (37 weeks)
● Approval of the conceptual design (13th Week)● Completion of Landscape Design Lay-out (19th Week)● Completion of Garden Lay-out (24th Week)● Construction Program (36th Week)● Final Report (37th Week)
Milestones
Greenleaf Construction Co.
PhasesGantt Chart
PhasesGantt Chart
PhasesGantt Chart
Critical Path Schedule
Critical Path Activities Phase 1
1. Conceptual Design Develop2. 3D Model Develop3. Conceptual Design Report
Critical Path Activities Phase 21. General Design Criteria General Work Package2. Landscape Design Criteria Landscape Work Package3. Landscape Design Lay-out Landscape Work Package4. Garden Lay-out (4 units) Garden and Plants Work Package 5. Piping General Arrangement Mechanical/Piping Work Package6. Elevation and Section Dwg Mechanical/Piping Work Package7. Civil/Structural Design Criteria Civil Work Package8. Concrete Specification Civil Work Package9. Structural Specification Civil Work Package
10. Paints Specification Civil Work Package11. Concrete Calculations Civil Work Package12. Structural Calculations Civil Work Package13. Concrete Lay out Civil Work Package14. Standard Steels Typical Details Railings Civil Work Package15. Construction Program Schedule Work Package16. Final Report General Work Package
Cost Estimate - Level off Efort WorkWork Package Landscape
● Work Package Duration: 80 days
● Resources ○ An Architect○ A Designer
● Work hours required: 878○ Architect: 231 work hours○ Designer: 647 work hours
Cost Estimate Work Package Landscape
Thank youThank you