8/12/2019 Sample Quote
1/14
New Double Garage
for
Mr Joe BloggsHappy Customer Lane
BostonLincolnshire
at:
Happy Customer LaneBoston
Lincolnshire
-
8/12/2019 Sample Quote
2/14
ST Portess & Son, Shorts Corner, Boston, Lincolnshire, PE22 7EA. Tel: 01205 750358, Fax: 01205 750358,VAT No: 310927971
Page 2
Mr Joe BloggsHappy Customer LaneBostonLincolnshire
Site address:Happy Customer LaneBostonLincolnshire
Wednesday, 15 July 2009
Dear Mr Joe Bloggs,
Subject: Garage
Thank you for your valued enquiry and instructions to quote for the above project.
We are pleased to attach the following estimate as requested. Should you have anyquestions regarding this estimate, please do not hesitate to contact us.
Considerations:
This estimate is based on the specification described herein. Any changes to drawingsor specification would be treated as a variation and may be subject to an agreed priceadjustment.
This estimate is valid for a period of 28 days from date of issue.
We trust that we have interpreted your requirements correctly as every effort has been
made to accurately estimate your project.
We look forward to hearing from you.
Yours sincerely
ST Portess & Son
-
8/12/2019 Sample Quote
3/14
ST Portess & Son, Shorts Corner, Boston, Lincolnshire, PE22 7EA. Tel: 01205 750358 or 07990887380, Fax:01205 750358, E-mail: [email protected], VAT No: 310927971
Page 3
Commencement
Preparation of site and commencement of all building works.
Plant
GarageSite Strip (Reduce dig)Removal of spoil from site 20 Tonne Tipper & Driver inc. Land Fill Tax 0.34 20
TonneDumper to assist with site clearance 3 Tonne Dumper 1 Week
Total Cost Excluding VAT 263.93
Foundations
Excavate for foundations using mechanical plant (if required) andcast foundations. Please note that the Building Control Officer willinspect the foundation prior to concreting and may require changesto the foundation depth and construction. Variations for additionalexcavation, trench support and concrete etc. will incur additionalcosts.
Material
GarageBrick and Block Cavity Wall (Brick and blockwalls)Structural concrete R'mix Concrete GEN 1 50 - 70mm slump 6m3 (Allowance 80) 0.81 m
Brick and Block Cavity Wall (Brick and blockwall, rear)Structural concrete R'mix Concrete GEN 1 50 - 70mm slump 6m3 (Allowance 80) 0.81 m
Brick and Block Cavity Wall (brick and blockwall, side)Structural concrete R'mix Concrete GEN 1 50 - 70mm slump 6m3 (Allowance 80) 1.6 m
Labour
GarageBrick and Block Cavity Wall (Brick and blockwalls)
Additional tasks to include Excavate trench,Remove spoil from site, Prepare bottom of trench,Lay structural concrete, Place cavity fill
Groundworker 3 Hours
Brick and Block Cavity Wall (Brick and blockwall, rear)
Additional tasks to include Excavate trench,Remove spoil from site, Prepare bottom of trench,Lay structural concrete, Place cavity fill
Groundworker 3 Hours
Brick and Block Cavity Wall (brick and blockwall, side)Excavate trench Groundworker 2 Hours
Prepare bottom of trench Groundworker 2 HoursPlace cavity fill Groundworker 1 Hours
Additional tasks to include Remove spoil from site,Lay structural concrete
Groundworker 2 Hours
-
8/12/2019 Sample Quote
4/14
ST Portess & Son, Shorts Corner, Boston, Lincolnshire, PE22 7EA. Tel: 01205 750358 or 07990887380, Fax:01205 750358, E-mail: [email protected], VAT No: 310927971
Page 4
Plant
GarageBrick and Block Cavity Wall (Brick and blockwalls)Plant to remove excavated spoil from site 20 Tonne Tipper & Driver inc. Land Fill Tax 0.34 20
Tonne
Brick and Block Cavity Wall (Brick and blockwall, rear)Plant to remove excavated spoil from site 20 Tonne Tipper & Driver inc. Land Fill Tax 0.34 20
Tonne
Brick and Block Cavity Wall (brick and blockwall, side)Plant for excavation of trench JCB 3CX Excavator & Driver (8hr. day) 0.39 DayPlant to remove excavated spoil from site 20 Tonne Tipper & Driver inc. Land Fill Tax 0.68 20
Tonne
Total Cost Excluding VAT 913.99
Footings
Construct brick and block footings off prepared foundations.
Material
GarageBrick and Block Cavity Wall (Brick and blockwalls)Cavity Fill R'mix Concrete GEN 1, 125mm slump 2-3 m3 (Allowance 85) 0.07 mTrench Blocks Trench Block 440 x 215 x 275mm 1.4 mBlockwork to Inner leaf below dpc Solid Dense Concrete Block 7N 440 x 215 x 100mm 2.7 mBlockwork to outer leaf below dpc Solid Dense Concrete Block 7N 440 x 215 x 100mm 1.4 mBricks below splash course Facing Bricks - Provisional (Allowance 0.40 each) 27 EachBricks for use in splash course Engineering Brick - Class A Blue 65mm 54 EachSand below dpc in brickwork Building Sand Bulk Bag 0.06 EachSand below dpc in blockwork Building Sand Bulk Bag 0.06 EachSand below dpc in trench blocks Building Sand Bulk Bag 0.04 EachCement below dpc in brickwork Blue Circle Mastercrete Original Cement 25kg Bag 0.66 EachCement below dpc in blockwork Blue Circle Mastercrete Original Cement 25kg Bag 0.63 EachCement below dpc in trench blocks Blue Circle Mastercrete Original Cement 25kg Bag 0.42 Each
Brick and Block Cavity Wall (Brick and blockwall, rear)Cavity Fill R'mix Concrete GEN 1, 125mm slump 2-3 m3 (Allowance 85) 0.07 m
Trench Blocks Trench Block 440 x 215 x 275mm 1.4 mBlockwork to Inner leaf below dpc Solid Dense Concrete Block 7N 440 x 215 x 100mm 2.7 mBlockwork to outer leaf below dpc Solid Dense Concrete Block 7N 440 x 215 x 100mm 1.4 mBricks below splash course Facing Bricks - Provisional (Allowance 0.40 each) 27 EachBricks for use in splash course Engineering Brick - Class A Blue 65mm 54 EachSand below dpc in brickwork Building Sand Bulk Bag 0.06 EachSand below dpc in blockwork Building Sand Bulk Bag 0.06 EachSand below dpc in trench blocks Building Sand Bulk Bag 0.04 EachCement below dpc in brickwork Blue Circle Mastercrete Original Cement 25kg Bag 0.66 EachCement below dpc in blockwork Blue Circle Mastercrete Original Cement 25kg Bag 0.63 EachCement below dpc in trench blocks Blue Circle Mastercrete Original Cement 25kg Bag 0.42 Each
Brick and Block Cavity Wall (brick and blockwall, side)Cavity Fill R'mix Concrete GEN 1, 125mm slump 2-3 m3 (Allowance 85) 0.14 mTrench Blocks Trench Block 440 x 215 x 275mm 2.7 mBlockwork to Inner leaf below dpc Solid Dense Concrete Block 7N 440 x 215 x 100mm 5.4 mBlockwork to outer leaf below dpc Solid Dense Concrete Block 7N 440 x 215 x 100mm 2.7 mBricks below splash course Facing Bricks - Provisional (Allowance 0.40 each) 54 EachBricks for use in splash course Engineering Brick - Class A Blue 65mm 108 EachSand below dpc in brickwork Building Sand Bulk Bag 0.11 EachSand below dpc in blockwork Building Sand Bulk Bag 0.11 Each
-
8/12/2019 Sample Quote
5/14
ST Portess & Son, Shorts Corner, Boston, Lincolnshire, PE22 7EA. Tel: 01205 750358 or 07990887380, Fax:01205 750358, E-mail: [email protected], VAT No: 310927971
Page 5
Sand below dpc in trench blocks Building Sand Bulk Bag 0.07 EachCement below dpc in brickwork Blue Circle Mastercrete Original Cement 25kg Bag 1.3 EachCement below dpc in blockwork Blue Circle Mastercrete Original Cement 25kg Bag 1.3 EachCement below dpc in trench blocks Blue Circle Mastercrete Original Cement 25kg Bag 0.84 Each
Labour
GarageBrick and Block Cavity Wall (Brick and blockwalls)Backfill trench Groundworker 2 HoursLay Trench Blocks 2 Bricklayers and Mate 1 HoursLay blockwork to inner leaf below dpc 2 Bricklayers and Mate 1 HoursLay blockwork to outer leaf below dpc 2 Bricklayers and Mate 1 HoursLay bricks for use in splash course 2 Bricklayers and Mate 1 Hours
Additional tasks to include Lay bricks below splashcourse
2 Bricklayers and Mate 1 Hours
Brick and Block Cavity Wall (Brick and blockwall, rear)Backfill trench Groundworker 2 HoursLay Trench Blocks 2 Bricklayers and Mate 1 HoursLay blockwork to inner leaf below dpc 2 Bricklayers and Mate 1 HoursLay blockwork to outer leaf below dpc 2 Bricklayers and Mate 1 HoursLay bricks for use in splash course 2 Bricklayers and Mate 1 Hours
Additional tasks to include Lay bricks below splash
course
2 Bricklayers and Mate 1 Hours
Brick and Block Cavity Wall (brick and blockwall, side)Backfill trench Groundworker 3 HoursLay Trench Blocks 2 Bricklayers and Mate 1 HoursLay blockwork to inner leaf below dpc 2 Bricklayers and Mate 2 HoursLay blockwork to outer leaf below dpc 2 Bricklayers and Mate 1 HoursLay bricks below splash course 2 Bricklayers and Mate 1 HoursLay bricks for use in splash course 2 Bricklayers and Mate 1 Hours
Total Cost Excluding VAT 1,246.43
Oversite and slabbing
Lay and compact subbase on reduced levels and form concreteslab.
Material
GarageGarage Slab (Floor slab)
Sub-base to concrete slab Sub Base MOT Type 1 Bulk Bag 10 EachSand blinding to slab Building Sand Bulk Bag 1.7 EachConcrete in slab R'mix Concrete RC 30, 50mm slump 6m3 (Allowance 75) 3.8 mDPM to concrete slab Polythene DPM Blue 300mu 4 x 25m PIFA (27.6kg) 0.42 Each
Labour
GarageGarage Slab (Floor slab)Place and compact sub-base to slab Groundworker and Labourer 3 HoursLay sand blinding Groundworker and Labourer 2 HoursLay DPM to slab Groundworker and Labourer 1 HoursPlace and compact concrete slab Groundworker and Labourer 3 HoursFloat finish to concrete slab Groundworker and Labourer 3 Hours
Plant
GarageGarage Slab (Floor slab)
-
8/12/2019 Sample Quote
6/14
ST Portess & Son, Shorts Corner, Boston, Lincolnshire, PE22 7EA. Tel: 01205 750358 or 07990887380, Fax:01205 750358, E-mail: [email protected], VAT No: 310927971
Page 6
Excavator for preparation of slab JCB 3CX Excavator & Driver (8hr. day) 0.5 DayPlant delivery and collection Delivery (10 to 15 Miles) 4 Each
Total Cost Excluding VAT 1,488.83
Erect Scaffold
Erect scaffolding on site to provide access for our contractors. Noallowance has been made to adapt the scaffolding for clients ortheir own contractors' requirements.
Subcontract Work
GarageScaffolding (Scaffold)Scaffold budget Scaffolding contractor 525 Unit
Subcontract Work
GarageScaffolding (Scaffold)
Allowance for sundry costs Sundry Costs 50 Each
Total Cost Excluding VAT 632.50
Brickwork Shell
Construct facing brick in sand/cement mortar, leaving all joints withrecessed finish. All openings around windows, doors etc. to beprovided with vertical damp proof courses where required. Internalleaf to be formed in blockwork.
Material
GarageDouble Garage Door (Vertical Slat Garage Door)
Garage Door Frame Softwood Garage Door Frame 4270 x 1981mm 1 EachExternal/Combination lintel Steel Lintel 100mm Cavity 4800mm (Garage) 1 Each
Garage Pedestrian DoorDoor frame External Softwood Door Frame 838 x 1981 Open in 1 EachExternal/Combination lintel Steel Lintel 50 Cavity x 1200mm 1 Each
Brick and Block Cavity Wall (Brick and blockwalls)Bricks above dpc less openings Facing Bricks - Provisional (Allowance 0.40 each) 353 EachBlocks above dpc less openings Insulation Block Standard 440 x 215 x 100mm 5.9 mBrick ties Brickwork Tie DD140 Type 4 225mm 26 EachDPC to brickwork Pitch Polymer DPC 100mm x 20m 0.3 EachDPC to blockwork Pitch Polymer DPC 100mm x 20m 0.3 EachSand above dpc in brickwork Building Sand Bulk Bag 0.26 EachSand above dpc in blockwork Building Sand Bulk Bag 0.08 EachCement above dpc in brickwork Blue Circle Mastercrete Original Cement 25kg Bag 1.5 EachCement above dpc in blockwork Blue Circle Mastercrete Original Cement 25kg Bag 0.49 Each
Brick and Block Cavity Wall (Brick and blockwall, rear)Bricks above dpc less openings Facing Bricks - Provisional (Allowance 0.40 each) 773 Each
-
8/12/2019 Sample Quote
7/14
ST Portess & Son, Shorts Corner, Boston, Lincolnshire, PE22 7EA. Tel: 01205 750358 or 07990887380, Fax:01205 750358, E-mail: [email protected], VAT No: 310927971
Page 7
Blocks above dpc less openings Insulation Block Standard 440 x 215 x 100mm 13 mBrick ties Brickwork Tie DD140 Type 4 225mm 47 EachDPC to brickwork Pitch Polymer DPC 100mm x 20m 0.3 EachDPC to blockwork Pitch Polymer DPC 100mm x 20m 0.3 EachSand above dpc in brickwork Building Sand Bulk Bag 0.58 EachSand above dpc in blockwork Building Sand Bulk Bag 0.19 EachCement above dpc in brickwork Blue Circle Mastercrete Original Cement 25kg Bag 3.3 EachCement above dpc in blockwork Blue Circle Mastercrete Original Cement 25kg Bag 1.1 Each
Brick and Block Cavity Wall (brick and blockwall, side)Bricks above dpc less openings Facing Bricks - Provisional (Allowance 0.40 each) 1800 EachBlocks above dpc less openings Insulation Block Standard 440 x 215 x 100mm 30 mBrick ties Brickwork Tie DD140 Type 4 225mm 106 EachDPC to brickwork Pitch Polymer DPC 100mm x 20m 0.6 EachDPC to blockwork Pitch Polymer DPC 100mm x 20m 0.6 EachSand above dpc in brickwork Building Sand Bulk Bag 1.4 EachSand above dpc in blockwork Building Sand Bulk Bag 0.43 EachCement above dpc in brickwork Blue Circle Mastercrete Original Cement 25kg Bag 7.7 EachCement above dpc in blockwork Blue Circle Mastercrete Original Cement 25kg Bag 2.5 Each
Labour
GarageDouble Garage Door (Vertical Slat Garage Door)Form opening Bricklayer 2 Hours
Fix external lintel 2 Bricklayers and Mate 1 HoursMake door frame Joiner 2 Hours
Additional tasks to include Fix preformed cavitytray
Bricklayer 1 Hours
Garage Pedestrian DoorForm opening Bricklayer 1 Hours
Additional tasks to include Fix external lintel Bricklayer 1 Hours
Brick and Block Cavity Wall (Brick and blockwalls)Lay bricks above dpc less openings 2 Bricklayers and Mate 3 HoursLay blocks above dpc less openings 2 Bricklayers and Mate 2 Hours
Brick and Block Cavity Wall (Brick and blockwall, rear)Lay bricks above dpc less openings 2 Bricklayers and Mate 7 HoursLay blocks above dpc less openings 2 Bricklayers and Mate 4 Hours
Brick and Block Cavity Wall (brick and blockwall, side)Lay bricks above dpc less openings 2 Bricklayers and Mate 15 HoursLay blocks above dpc less openings 2 Bricklayers and Mate 8 Hours
Total Cost Excluding VAT 5,274.43
-
8/12/2019 Sample Quote
8/14
ST Portess & Son, Shorts Corner, Boston, Lincolnshire, PE22 7EA. Tel: 01205 750358 or 07990887380, Fax:01205 750358, E-mail: [email protected], VAT No: 310927971
Page 8
Roof Structure
Form roof structure including any fascias and bargeboards andassociated guttering as described.
Material
GarageApex Truss Roof (Roof)Noggings between roof joists Sawn Softwood Kiln Dried Treated 47.0 x 50mm 33 Metre
Apex truss roof rafters To be defined 11 UnitTruss Clips Truss Clip 50mm 22 Each
Apex roof gable Ladder Rafters Sawn Dry Graded Structural Softwood Treated 47.0 x 125mm 36 MetreGable ladder noggings Sawn Softwood Kiln Dried Treated 47.0 x 50mm 11 MetreSoffit carriers Sawn Batten Treated 25.0 x 38mm 6 MetreWall plate Sawn Dry Graded Structural Softwood Treated 75.0 x 100mm 13 Metre
Diagonal bracing Sawn Dry Graded Structural Softwood Treated 25.0 x 100mm 20 MetreLongitudinal bracing Sawn Dry Graded Structural Softwood Treated 25.0 x 100mm 22 Metre
Apex bracing Sawn Dry Graded Structural Softwood Treated 25.0 x 100mm 5.5 MetreRoof structure fixings (allowance) Round Wire Nails Bright 100mm x 25kg 0.57 BoxEaves fascia White 175mm Square Fascia x 16mm x 5.0M 2.6 EachBargeboard White 175mm Square Fascia x 16mm x 5.0M 3.6 EachBargeboard fixings White plastic top Nail 40mm - 10G 0.89 EachWallplate straps Lateral Restraint Strap 30 x 5 x 1200mm bent at 150mmm 6 EachGable straps at joist level Lateral Restraint Strap 30 x 5 x 1200mm bent at 150mmm 4 EachGable straps at verge level Lateral Restraint Strap 30 x 5 x 1600mm bent at 100mmm 8 EachGable soffits (side 1) White 400mm PVC Board x 9mm x 5.0M 0.85 EachGable soffits (side 2) White 400mm PVC Board x 9mm x 5.0M 0.85 EachEaves soffitts (side 1) White 400mm PVC Board x 9mm x 5.0M 0.64 EachEaves soffitts (side 2) White 400mm PVC Board x 9mm x 5.0M 0.64 EachSoffit fixings White plastic top Nail 40mm - 10G 1.2 EachGutter Half Round Gutter 4m x 112mm 3.3 EachDown pipe Half Round Downpipe 4m x 68mm 1.3 EachStop ends Half Round Gutter Stop End External 112mm 4 Each
Gutter unions Half Round Gutter Union Bracket 112mm 4 EachGutter clips Half Round Gutter Support Bracket 112mm 14 EachGutter outlet Half Round Gutter Running Outlet 112mm 2 EachDown pipe unions Half Round Downpipe Connector 68mm 2 EachDown pipe clips Half Round Downpipe Saddle Bracket 68mm 6 EachSwan necks Half Round Downpipe Bend 67.5 deg 68mm 4 EachPrimer for bargeboard and fascia Undercoat White 5 Litre 0.15 EachPrimer for soffits Undercoat White 5 Litre 0.18 Each
Labour
GarageApex Truss Roof (Roof)Fix noggings between roof joists Joiner 5 HoursFix apex roof truss rafters Joiner + Mate 5 HoursFix apex roof gable ladder rafters Joiner + Mate 3 HoursFix gable ladder noggings Joiner 2 Hours
Fix soffit carriers Joiner 1 HoursFix wall plate Joiner 2 HoursFix diagonal bracing Joiner + Mate 2 HoursFix longitudinal bracing Joiner + Mate 2 HoursFix eaves fascia Joiner + Mate 2 HoursFix bargeboard Joiner + Mate 2 HoursFix wallplate straps Joiner 1 HoursFix gable straps at joist level Joiner 1 HoursFix gable straps at verge level Joiner 2 HoursFix gutter Joiner 3 HoursFix down Pipe Joiner 1 HoursFix gable soffits (side1 ) Joiner 2 HoursFix gable soffits (side 2) Joiner 2 HoursFix eaves soffitts (side 1) Joiner 1 HoursFix eaves soffitts (side 2) Joiner 1 HoursPrepare bargeboard and fascia for painting Joiner 2 HoursPrime bargeboard and fascia Joiner 2 HoursPrime soffits Joiner 2 Hours
Additional tasks to include Fix apex bracing Joiner + Mate 1 Hours
-
8/12/2019 Sample Quote
9/14
ST Portess & Son, Shorts Corner, Boston, Lincolnshire, PE22 7EA. Tel: 01205 750358 or 07990887380, Fax:01205 750358, E-mail: [email protected], VAT No: 310927971
Page 9
Total Cost Excluding VAT 2,135.12
Roof Tiling
Lay roof covering.
Material
GarageApex Truss Roof (Roof)Lathe Sawn Batten Treated 25.0 x 38mm 603 MetreLathe nails Round Wire Nails Galvanised 65mm x 25kg 0.42 BoxRoofing felt Breather Membrane 700 1.5 x 50 m 0.84 EachTiles Plain Clay Tile (60 per m2) (Allowance 0.70 each) 3412 EachTile Nails Round Wire Nails Galvanised 65mm x 25kg 0.09 BoxRidge tile Half Round Clay Ridge (300mm) (Allowance 12 each) 22 EachEaves tiles Clay Eaves Tile (Allowance 0.90) 87 EachTop tiles Clay Eaves Tile (Allowance 0.90) 87 EachVerge tiles Clay Tile & Half (Allowance 1.40 each) 87 EachTile undercloak 1 Cement Soffit Strip 2400 x 150 x 4.5mm 3.6 EachTile undercloak 2 Cement Soffit Strip 2400 x 150 x 4.5mm 3.6 EachSand pointing/bedding to ridge Building Sand Bulk Bag 0.07 EachSand pointing/bedding to verge Building Sand Bulk Bag 0.17 EachCement in pointing/bedding to ridge Blue Circle Mastercrete Original Cement 25kg Bag 0.75 EachCement pointing/bedding to verge Blue Circle Mastercrete Original Cement 25kg Bag 2 Each
Labour
GarageApex Truss Roof (Roof)Fix tiles, felt and lathe. 3 Roof tilers + mate 21 HoursFix top tiles Roof tiler 1 HoursFix verge tiles Roof tiler 1 HoursFix ridge tile Roof tiler + mate 1 Hours
Additional tasks to include Fix eaves tiles, Fix tileundercloak 1, Fix tile undercloak 2
Roof tiler 2 Hours
Total Cost Excluding VAT 5,385.95
Joinery 1st Fix
Form carcassing and first fix timbers.
Material
GarageDouble Garage Door (Vertical Slat Garage Door)Door frame fixings to sides Hammer in Fixing 8mm x 100mm (12 Bag) 0.5 PackDoor frame fixings to top and bottom Wood Screws Steel CSK Twin Thread 10 x 3 inch (100 box) 0.14 Box
Garage Pedestrian Door
Door frame fixings to sides Hammer in Fixing 8mm x 100mm (12 Bag) 0.5 Pack
-
8/12/2019 Sample Quote
10/14
ST Portess & Son, Shorts Corner, Boston, Lincolnshire, PE22 7EA. Tel: 01205 750358 or 07990887380, Fax:01205 750358, E-mail: [email protected], VAT No: 310927971
Page 10
Labour
GarageDouble Garage Door (Vertical Slat Garage Door)Fix door frame Joiner 2 Hours
Garage Pedestrian DoorAdditional tasks to include Fix door frame Joiner 1 Hours
Total Cost Excluding VAT 42.04
Internal Decoration
Apply decoration. (Note that a basic paint specification has beenused for the purposes of estimating the building works. However,colours and finishes may be changed by agreement in writing.)
Material
GarageDouble Garage Door (Vertical Slat Garage Door)Primer for door frame internally Undercoat White 5 Litre 0.04 EachUndercoat for door frame internally Undercoat White 5 Litre 0.04 EachPaint for door frame internally Gloss Brilliant White 5 Litre 0.04 Each
Garage Pedestrian DoorPrimer for door frame internally Undercoat White 5 Litre 0.03 EachUndercoat for door frame internally Undercoat White 5 Litre 0.03 EachPaint for door frame internally Gloss Brilliant White 5 Litre 0.03 EachPrimer for door internally Undercoat White 5 Litre 0.05 EachUndercoat for door internally Undercoat White 5 Litre 0.05 EachPaint for door internally Gloss Brilliant White 5 Litre 0.05 Each
Labour
GarageDouble Garage Door (Vertical Slat Garage Door)
Additional tasks to include Prepare interior of doorframe for decoration, Apply primer to door frameinternally, Apply undercoat to door frame internally,
Apply paint to door frame internally
Decorator 3 Hours
Garage Pedestrian DoorAdditional tasks to include Prepare interior of doorframe for decoration, Apply primer to door frameinternally, Apply undercoat to door frame internally,
Apply paint to door frame internally, Prepare int. ofdoor for primer or paint, Apply primer to interior ofdoor, Apply undercoat to interior of door, Applygloss to interior of door
Decorator 3 Hours
Total Cost Excluding VAT 89.50
External Decoration
Apply decoration. (Note that a basic paint specification has beenused for the purposes of estimating the building works. However,colours and finishes may be changed by agreement in writing.)
-
8/12/2019 Sample Quote
11/14
ST Portess & Son, Shorts Corner, Boston, Lincolnshire, PE22 7EA. Tel: 01205 750358 or 07990887380, Fax:01205 750358, E-mail: [email protected], VAT No: 310927971
Page 11
Material
GarageDouble Garage Door (Vertical Slat Garage Door)Sealant Silicone Sealant White 0.31 Litre 0.39 EachPrimer for door frame externally Undercoat White 5 Litre 0.04 EachUndercoat for door frame externally Undercoat White 5 Litre 0.04 EachPaint for door frame externally Gloss Brilliant White 5 Litre 0.04 EachUndercoat for door externally Undercoat White 5 Litre 0.27 EachPaint for door externally Gloss Brilliant White 5 Litre 0.27 Each
Garage Pedestrian DoorSealant Silicone Sealant White 0.31 Litre 0.18 EachPrimer for door frame externally Undercoat White 5 Litre 0.03 EachUndercoat for door frame externally Undercoat White 5 Litre 0.03 EachPaint for door frame externally Gloss Brilliant White 5 Litre 0.03 EachPrimer for door externally Undercoat White 5 Litre 0.05 EachUndercoat for door externally Undercoat White 5 Litre 0.05 EachPaint for door externally Gloss Brilliant White 5 Litre 0.05 EachPrimer for external cill Outdoor Varnish Clear Gloss 750ml 0.02 EachUndercoat/varnish for external cill Outdoor Varnish Clear Gloss 750ml 0.02 EachPaint/varnish for external cill Outdoor Varnish Clear Gloss 750ml 0.02 Each
Apex Truss Roof (Roof)Undercoat for bargeboard and fascia Undercoat White 5 Litre 0.15 Each
Paint for bargeboard and fascia Gloss Brilliant White 5 Litre 0.15 EachUndercoat for soffits Undercoat White 5 Litre 0.18 EachPaint for soffits Gloss Brilliant White 5 Litre 0.18 Each
Labour
GarageDouble Garage Door (Vertical Slat Garage Door)Prepare exterior of door for painting Decorator 2 Hours
Apply undercoat to exterior of door Decorator 2 HoursApply gloss to exterior of door Decorator 2 HoursAdditional tasks to include Apply sealant Joiner 1 HoursAdditional tasks to include Prepare exterior of doorframe for decoration, Apply primer to door frameexternally, Apply undercoat to door frameexternally, Apply paint to door frame externally
Decorator 3 Hours
Garage Pedestrian DoorAdditional tasks to include Apply sealant Joiner 1 HoursAdditional tasks to include Prepare exterior of doorframe for decoration, Apply primer to door frameexternally, Apply undercoat to door frameexternally, Apply paint to door frame externally,Prepare exterior of door for painting, Apply primerto exterior of door, Apply undercoat to exterior ofdoor, Apply gloss to exterior of door, Prepareexternal cill for decoration, Apply primer toexternal cill, Apply undercoat/varnish to externalcill, Apply paint/varnish to external cill
Decorator 3 Hours
Apex Truss Roof (Roof)Undercoat bargeboard and fascia Decorator 2 HoursPaint bargeboard and fascia Decorator 2 HoursPrepare soffits for painting Joiner 2 HoursUndercoat soffits Decorator 2 HoursPaint soffits Decorator 2 Hours
Total Cost Excluding VAT 362.82
Joinery 2nd Fix
Fix doors and windows, fixtures and fittings.
-
8/12/2019 Sample Quote
12/14
ST Portess & Son, Shorts Corner, Boston, Lincolnshire, PE22 7EA. Tel: 01205 750358 or 07990887380, Fax:01205 750358, E-mail: [email protected], VAT No: 310927971
Page 12
Material
GarageDouble Garage Door (Vertical Slat Garage Door)Garage Door Double Garage Door 4267 x 1981mm (Allowance 1350) 1 Each
Garage Pedestrian DoorDoor KXT Back Door Softwood 3 Panel 6 Pane D&G 838 x 1981mm 1 EachDoor furniture Georgian Brass 5 Lever BS Exterior Door Pack 1 EachHinges Butt Hinge Brassed 102mm 1.5 PairSafety Glass Toughened Sealed Units for KXT Door 1 Each
Labour
GarageDouble Garage Door (Vertical Slat Garage Door)Hang door Joiner 6 Hours
Garage Pedestrian DoorHang door Joiner 3 HoursFix door furniture Joiner 2 HoursFix glazing Joiner 1 Hours
Total Cost Excluding VAT 2,241.67
Completion
Completion of all building works.
Labour
GarageGarage Pedestrian DoorReturn to ease door Joiner 1 Hours
Total Cost Excluding VAT 18.70
Total Cost Excluding VAT 20,095.92Total VAT 3,014.39Total Cost Including VAT 23,110.31
-
8/12/2019 Sample Quote
13/14
ST Portess & Son, Shorts Corner, Boston, Lincolnshire, PE22 7EA. Tel: 01205 750358 or 07990887380, Fax:01205 750358, E-mail: [email protected], VAT No: 310927971
Page 13
Acceptance of Estimate/Variation
Reference: Garage (Estimate dated Wednesday, 15 July 2009)
Mr Joe Bloggs
Happy Customer LaneBostonLincolnshire
Site address:Happy Customer LaneBostonLincolnshire
Please carry out the building works itemised in the Estimate defined above, datedWednesday, 15 July 2009 to the value of:
Total Cost Excluding VAT 20,095.92Total VAT 3,014.39Total Cost Including VAT 23,110.31
Signed Mr Joe Bloggs .
Date //20..
Signed on behalf of ST Portess & Son .
Date //20..
-
8/12/2019 Sample Quote
14/14
ST Portess & Son, Shorts Corner, Boston, Lincolnshire, PE22 7EA. Tel: 01205 750358 or 07990887380, Fax:01205 750358, E-mail: [email protected], VAT No: 310927971
Page 14