ID Task Name 1 Project 2 Meeting with Customer 3 Acquire & Define Problem 4 Gather Requirements 5 Brief Q&A to Refine Problem Details 7 Present Problem (First Meeting) 8 Review Problem Details 9 Analyze Requirements 10 Determine Project Feasibility 11 Research Existing Solutions 12 Produce Research Documentation 13 Discussions (Second Meeting) 14 Discuss Existing Solutions 15 Discuss Possible Solutions 16 Construct Feasible Solution 17 Refine Technology Research 18 Refine Requirements 19 Project Preparations 20 Prepare Preliminary Design Plans 21 Construct Preliminary Architecture 22 Produce Top-Level Components 23 Construct Basic Design Modules 24 Organize Requirements & Specifications 25 Prepare Requirements Checklist 26 Incorporate Specs into Design Modules 27 Finalize Preliminary Design Plans 28 Communicate with Customer 11/5 11/5 11/5 1 4 7 10 13 16 19 22 25 28 ovember 2010 Dec Critical Critical Split Critical Progress Task Split Task Progress Baseline Baseline Split Baseline Milestone Milestone Summary Progress Summary Project Summary External Tasks External Milestone Deadline sample.mpp Page 1

Upload: biggiesmalls

Post on 11-Jun-2017

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Sample Project Plan

ID Task Name

1 Project

2 Meeting with Customer

3 Acquire & Define Problem

4 Gather Requirements

5 Brief Q&A to Refine Problem Details

7 Present Problem (First Meeting)

8 Review Problem Details

9 Analyze Requirements

10 Determine Project Feasibility

11 Research Existing Solutions

12 Produce Research Documentation

13 Discussions (Second Meeting)

14 Discuss Existing Solutions

15 Discuss Possible Solutions

16 Construct Feasible Solution

17 Refine Technology Research

18 Refine Requirements

19 Project Preparations

20 Prepare Preliminary Design Plans

21 Construct Preliminary Architecture

22 Produce Top-Level Components

23 Construct Basic Design Modules

24 Organize Requirements & Specifications

25 Prepare Requirements Checklist

26 Incorporate Specs into Design Modules

27 Finalize Preliminary Design Plans

28 Communicate with Customer

11/5

11/5

11/5

1 4 7 10 13 16 19 22 25 28

ovember 2010 Dec

Critical

Critical Split

Critical Progress

Task

Split

Task Progress

Baseline

Baseline Split

Baseline Milestone

Milestone

Summary Progress

Summary

Project Summary

External Tasks

External Milestone

Deadline

sample.mpp

Page 1

Page 2: Sample Project Plan

ID Task Name

29 Present Preliminary Plans

30 Confirm/Clarify Customer Expectations

31 Acquire Preliminary Design Approval

32 Team Meeting

33 Organize Design Teams

34 Assign Design Tasks

35 Design and Planning

36 Designing

37 Top-Level Designs

38 Specify Architecture Details

39 Construct Block Diagram

40 Add Data Flow Information

41 Define Major Modules:

42 Tag Module

43 Construct Tag Specifications

44 Elaborate Data Details

45 Analyze & Note Cost of Tags

46 Sensor Module

47 Construct Hardware Specification

48 Elaborate Data Details

49 Analyze & Note Cost of Sensors

50 Raw Data Interpreter Module

51 Construct Hardware Specifications

52 Elaborate Data Details

53 Analyze & Note Cost of Interpreter

54 Central Server Module

55 Produce Server Sub-Modules

1 4 7 10 13 16 19 22 25 28

ovember 2010 Dec

Critical

Critical Split

Critical Progress

Task

Split

Task Progress

Baseline

Baseline Split

Baseline Milestone

Milestone

Summary Progress

Summary

Project Summary

External Tasks

External Milestone

Deadline

sample.mpp

Page 2

Page 3: Sample Project Plan

ID Task Name

56 List Sub-Module Functionalities

57 Construct Hardware Specifications

58 List and Describe Data Contents

59 Analyze & Note Cost of Server

60 Terminal Module

61 Produce Client Sub-Modules

62 List Sub-Module Functionalities

63 List Hardware Requirements

64 List Data Contents

65 Analyze & Record Cost of Unit

66 Backup Unit Module

67 List Storage Unit Specifications

68 List Data Contents

69 Analyze & Record Cost of Unit

70 Low-Level Designs

71 Server Software Design

72 Specify Sub-Module Details

73 Database Design

74 Specify Database Structure

75 List Database Contents

76 Raw Data Augmenter Module

77 File Storage Module

78 Accessor Module

79 Determine Best Development Tool

80 Client Software Design

81 Specify Sub-Module Details

82 User Interface Module

1 4 7 10 13 16 19 22 25 28

ovember 2010 Dec

Critical

Critical Split

Critical Progress

Task

Split

Task Progress

Baseline

Baseline Split

Baseline Milestone

Milestone

Summary Progress

Summary

Project Summary

External Tasks

External Milestone

Deadline

sample.mpp

Page 3

Page 4: Sample Project Plan

ID Task Name

83 Input Analyzer

84 Interpreter

85 User Data

86 Access Module

87 Temporary Storage

88 Determine Best Development Tool

89 Analyze Risks, Constraints, and Unknowns

90 Construct Cross reference listing

91 Hardware Selection

92 Determine Equipment Requirements

93 Determine Test Equipment Requirements

94 Generate Budget Estimates

95 Retrieve and Organize Equipment Costs

96 Estimate Cost for Test Equipment

97 Estimate Labor Costs

98 Create SRS Draft

99 Project Plan Approval

100 Meeting with Customer

101 Present Software Requirements Specification

102 Gain Feedback

103 SRS Revision Based on Concerns

104 Present Finalized SRS for Approval

105 Production

106 Production Preparations

107 Purchase Test Equipment

108 Team Meeting

109 Organize Development Team

1 4 7 10 13 16 19 22 25 28

ovember 2010 Dec

Critical

Critical Split

Critical Progress

Task

Split

Task Progress

Baseline

Baseline Split

Baseline Milestone

Milestone

Summary Progress

Summary

Project Summary

External Tasks

External Milestone

Deadline

sample.mpp

Page 4

Page 5: Sample Project Plan

ID Task Name

110 Assign Coding Tasks

111 Software Development

112 Server Software

113 Database

114 Set Up Database Tables

115 Referencing Data

116 Session Data

117 Account Data

118 Activity Logs

119 Implement Access Scripts

120 Raw Data Augmenter

121 Code Based on Specified Designs

122 Integration and Testing

123 Integrate with Test Equipment

124 Integrate with Database

125 Test

126 File Storage

127 Set Up File System

128 Integrate into Test Equipment

129 Accessor

130 Code Based on Specified Designs

131 Integration and Testing

132 Integrate to Previous Test

133 Test

134 Client Software

135 Input Analyzer

136 Code Based on Specified Designs

1 4 7 10 13 16 19 22 25 28

ovember 2010 Dec

Critical

Critical Split

Critical Progress

Task

Split

Task Progress

Baseline

Baseline Split

Baseline Milestone

Milestone

Summary Progress

Summary

Project Summary

External Tasks

External Milestone

Deadline

sample.mpp

Page 5

Page 6: Sample Project Plan

ID Task Name

137 Integration and Testing

138 Integrate with Test Equipment

139 Test

140 Interpreter

141 Code Based on Specified Designs

142 Integration and Testing

143 Integrate with Test Equipment

144 Test

145 User Data

146 Code Based on Specified Designs

147 Integration and Testing

148 Integrate with Test Equipment

149 Test

150 Pre-Deployment Testing

151 Integrate Core Components

152 Test Integrated System

153 Confirm Success of Test

154 Meeting with Customer

155 Present Demonstration with Test Equipment

156 Pre-Deployment Preparation

158 Purchase Equipment

159 Tags and Sensors

160 Raw Data Interpreter

161 PC for Server

162 PC for Terminal

163 Cables, Wires, and Installation Tools

164 Network Equipment

1 4 7 10 13 16 19 22 25 28

ovember 2010 Dec

Critical

Critical Split

Critical Progress

Task

Split

Task Progress

Baseline

Baseline Split

Baseline Milestone

Milestone

Summary Progress

Summary

Project Summary

External Tasks

External Milestone

Deadline

sample.mpp

Page 6

Page 7: Sample Project Plan

ID Task Name

165 Prepare Equipment

166 Install Software

167 Install Necessary Software (OS, JVM, etc.)

168 Install Server Software onto Server PC

169 Install Client Software onto Client PC

170 Program & Label Sensor Equipment

171 Program Tags [Essential Tags Only]

172 Prepare Installation Layout

173 Prepare User Manual

174 Deployment

175 Bring Equipment to Facility

176 Install Equipment and Hardware

177 Configure System

178 Set Up Server Machine

179 Set Up Client PC

180 Install Optional Equipment [Upon Request]

181 Backup Unit

182 Uninterruptible Power Supply

183 Additional Terminal PC's

184 Run Extensive Test on Full System

185 Full System Demonstration for Customer

186 Customer Training

1 4 7 10 13 16 19 22 25 28

ovember 2010 Dec

Critical

Critical Split

Critical Progress

Task

Split

Task Progress

Baseline

Baseline Split

Baseline Milestone

Milestone

Summary Progress

Summary

Project Summary

External Tasks

External Milestone

Deadline

sample.mpp

Page 7

Page 8: Sample Project Plan

1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27

ecember 2010 January 2011

Critical

Critical Split

Critical Progress

Task

Split

Task Progress

Baseline

Baseline Split

Baseline Milestone

Milestone

Summary Progress

Summary

Project Summary

External Tasks

External Milestone

Deadline

sample.mpp

Page 8

Page 9: Sample Project Plan

1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27

ecember 2010 January 2011

Critical

Critical Split

Critical Progress

Task

Split

Task Progress

Baseline

Baseline Split

Baseline Milestone

Milestone

Summary Progress

Summary

Project Summary

External Tasks

External Milestone

Deadline

sample.mpp

Page 9

Page 10: Sample Project Plan

1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27

ecember 2010 January 2011

Critical

Critical Split

Critical Progress

Task

Split

Task Progress

Baseline

Baseline Split

Baseline Milestone

Milestone

Summary Progress

Summary

Project Summary

External Tasks

External Milestone

Deadline

sample.mpp

Page 10

Page 11: Sample Project Plan

1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27

ecember 2010 January 2011

Critical

Critical Split

Critical Progress

Task

Split

Task Progress

Baseline

Baseline Split

Baseline Milestone

Milestone

Summary Progress

Summary

Project Summary

External Tasks

External Milestone

Deadline

sample.mpp

Page 11

Page 12: Sample Project Plan

1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27

ecember 2010 January 2011

Critical

Critical Split

Critical Progress

Task

Split

Task Progress

Baseline

Baseline Split

Baseline Milestone

Milestone

Summary Progress

Summary

Project Summary

External Tasks

External Milestone

Deadline

sample.mpp

Page 12

Page 13: Sample Project Plan

1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27

ecember 2010 January 2011

Critical

Critical Split

Critical Progress

Task

Split

Task Progress

Baseline

Baseline Split

Baseline Milestone

Milestone

Summary Progress

Summary

Project Summary

External Tasks

External Milestone

Deadline

sample.mpp

Page 13

Page 14: Sample Project Plan

1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27

ecember 2010 January 2011

Critical

Critical Split

Critical Progress

Task

Split

Task Progress

Baseline

Baseline Split

Baseline Milestone

Milestone

Summary Progress

Summary

Project Summary

External Tasks

External Milestone

Deadline

sample.mpp

Page 14