sample project: collar joint stabilization · 3/4/2017 · “fight” the shell, and one of the...
TRANSCRIPT
C O N S U L T I N G E N G I N E E R S , I N C .
Sample Project:
Collar Joint Stabilization Grace Episcopal Church, New Bedford, MA
Owner: Grace Episcopal Church
Engineer: Structures North Consulting Engineers, Inc.
General Contractor: Aniceto, Inc.
Grouting Contractor: Special Breaks, LTD
C O N S U L T I N G E N G I N E E R S , I N C .
The Challenge: The Grace Episcopal Church in New
Bedford, MA (USA) was constructed
in late 19th century as a stone
masonry tower with massive brick
pilasters at each corner. These
shared load with the stone shaft of
the tower, and above transitioned to
brick piers that supported nearly all of
the weight of the combined brick and
stone spire.
As the tower acclimatized and aged,
the brick piers swelled, as materials
normally do, and attempted to
additionally lift the structure causing
the tower to contort.
C O N S U L T I N G E N G I N E E R S , I N C .
f
Field notes
describing
the masonry
contortions
f
As the brick pilasters grew, the
stone shell of the tower did not.
This caused the brick piers to
“fight” the shell, and one of the
piers to peel itself off.
Delaminating
and
Separating
Pilaster
C O N S U L T I N G E N G I N E E R S , I N C .
Delaminating and
Separating Pilaster
C O N S U L T I N G E N G I N E E R S , I N C .
The brick pilaster had
separated from the stone shell
by up to 4-inches
C O N S U L T I N G E N G I N E E R S , I N C .
The brick pilaster movement
caused a similar buckling effect
in the stonework below, and a
similar movement
C O N S U L T I N G E N G I N E E R S , I N C .
In its buckled state, the pilaster had a
fraction of its original strength, as 24-
inches of composite masonry became
8 to 12 inches of brick running past
12 to 16 inches of stone.
While one consider shoring and
reconstructing the separated brick,
the intensity of the structural load and
the precariousness of its support
precluded this. Additionally, simply
pinning the pilaster back to the stone
back-up would only have resulted in
two thin elements tied together, rather
than one thick element- the
perpendicular wall was made
discontinuous below the adjacent
roof by a beam supported opening.
A system would need to be selected,
or devised, that would compositely
bond the corner of the tower back
together.
Delaminated
and
Buckled
Pilaster
Massive
Structural
Load
C O N S U L T I N G E N G I N E E R S , I N C .
In-Place Stabilization Options:
• Injection Grouting Systems- no cross tie when used alone, and thus no way of
resisting internal grouting pressures without external bracing or tying.
• Resin-Based Anchor Systems with Screen Tubes- marginal ability to span
gaps, shear transfer only through dowel action.
• Mechanical Wedge Anchor Based Systems- no shear transfer
• Sock Anchor Systems- better but shear transfer dependent upon dowel action.
• Self-Grouting Port Anchor System- The only system that not only ties
both surfaces against further separation, but while provides a port through
separated cavities and can be cleaned, inject a compatible grout and
knitted back together.
C O N S U L T I N G E N G I N E E R S , I N C .
Port Anchor Design Parameters: Non-corroding all stainless steel construction.
Must provide a clear pathway for inspection and cleaning of void then injection of grout
while resisting at least two 3-foot lifts of grouting pressures.
Detail to suit loading, grouting conditions and injection pressures- grouted anchor socks
possible at either or both ends, with bearing plates available in lieu of or in addition to the
socks.
Removable threaded rods socket into outer ends of anchor in order to directly attach
dunnage to counter injection pressures- The port anchor doubles as the fastening system
for the dunnage, avoiding the need for external bracing.
Double ended anchors possible where dunnage needed on both faces of masonry.
Anchor shear capacity not reliant on dowel action but based upon shear friction “haunch”
theory, with the maximum tie capacity provided at the point of best grout compaction- At
the anchor. No shear lag, no bending or crushing, only direct fixation.
Hollow or open shank allows insertion of secondary rods for additional shear capacity, and
electric heating wands if needed for installation during cold weather conditions.
C O N S U L T I N G E N G I N E E R S , I N C .
Void Filling Grout Design Parameters
• Must be flowable and have ultra-low shrinkage.
• Must stiffen fast enough to safely support an unlimited number of successive 36-inch grout lifts
every 20-hours.
• Must be more breathable than Cement, more forgiving of building movements, and generally
more compatible with older structures that have lime mortars.
• Must cure without needing significant carbon from the atmosphere.
• Should have a proportionately high tensile strength and a low compressive strength with good
adhesion.
•Should meet the material requirements of ASTM C1713: Standard Specification of Mortars for the
Repair of Historic Masonry to serve as a fluid-applied historic mortar replacement
C O N S U L T I N G E N G I N E E R S , I N C .
C O N S U L T I N G E N G I N E E R S , I N C .
Anchor Installation
C O N S U L T I N G E N G I N E E R S , I N C .
Sock Inflation
C O N S U L T I N G E N G I N E E R S , I N C .
Grout Mixing
C O N S U L T I N G E N G I N E E R S , I N C .
Void Filling
C O N S U L T I N G E N G I N E E R S , I N C .
Port Removal
C O N S U L T I N G E N G I N E E R S , I N C .
Completed
Stabilization