sample project brief
DESCRIPTION
This my first major project since I came back home from abroad...TRANSCRIPT
04/09/23 1
2
Goals:
• To create proper and automated inventory management system for raw materials and finished products.
• Inter-branch synchronization.
• Allow top management to view and access the inventory management system over the World Wide Web.
3
Scope of Work:
• Job Orders• PO Requisition• Purchasing• Receiving• Material Requisition • WH Transfer• Production• Shipping
15
Hardware Requirements:
• 2 computers as servers
Specifications:
Processor : Intel Core 2 Duo
Memory : 2 Gigabytes (GB)
LAN : 1 GB network card
Storage : 40 GB (minimum)
16
• *Software Requirements:Operating System : Windows 2003 Server
• *Local Web Server and Programming Requirements : Apache web server PHP 5.0
• *Database Requirements: MS SQL Server 2005
• *User Manual and Training:
Legend * all items with asterisk are provided by Black
Code IT Solutions
17
Implementation
• Soft Launch :
60 days from April 24 (June 23, 2009)
• Full Scale Implementation :
90 days from April 24 (July 23, 2009)
18
After Sales Service/ Maintenance:
• One year free maintenance pertaining to the 33 point 3 IMS, hardware problems. This excludes the major modification of the IMS.
04/24/2009 19