sale of agricultural land for farm use (lck 114a, …...upgrading the road reserves abutting the...
TRANSCRIPT
TR5/GA/FIDM CA 1 of 18
SALE OF AGRICULTURAL LAND FOR FARM USE
(LCK 114A, LCK 114C AND LCK 114D)
CONDITIONS AND REQUIREMENTS OF RELEVANT AUTHORITIES / PUBLIC UTILITY
LICENSEES (FOR TENDERERS’ INFORMATION ONLY)
CONTENTS PAGE
1 DEFINITION 2
2 GENERAL CONDITIONS AND REQUIREMENTS 2
3 NATIONAL ENVIRONMENT AGENCY (NEA) 3
4 POWERGAS 6
5 SP POWERGRID (SPPG) 6
6 MINISTRY OF DEFENCE (MINDEF) 7
7 SINGAPORE CIVIL DEFENCE FORCE (SCDF) 8
8 LAND TRANSPORT AUTHORITY (LTA) 9
9 NATIONAL PARKS BOARD (NParks) 10
10 PUBLIC UTILITIES BOARD (PUB) 12
11 COMPLIANCE WITH TECHNICAL CONDITIONS OF RELEVANT AUTHORITIES 18
ANNEX A
ANNEX B
ANNEX C
ANNEX D
ANNEX E
ANNEX F
ANNEX G
ANNEX H
ANNEX I(i)
ANNEX I(ii)
ANNEX J
TR5/GA/FIDM CA 2 of 18
1.0 DEFINITION
1.1 The Singapore Food Agency (“SFA”), is inviting offers for the lease of Land Parcel(s)
LCK 114A, LCK 114C and LCK 114D at Lim Chu Kang. The lease of the Land Parcel(s)
is subject to the Conditions of Tender, the Technical Conditions of Tender and the
Lease for the Land Parcel(s) issued by SFA in the said Invitation to Tender.
2.0 GENERAL CONDITIONS AND REQUIREMENTS
2.1 The Successful Tenderer for the Land Parcel(s) is required under the said Conditions
of Tender to ascertain the exact and detailed conditions and requirements of all
relevant Competent Authorities/ Public Utility Licensees in respect of the proposed
development thereon and shall at his own cost and expense observe and comply with
the same.
2.2 Without affecting the generality of paragraph 2.1 above and without prejudice to the
obligations of the Successful Tenderer as set out therein, the contents herein are
provided for the information of the tenderers only. Whilst every care and attention has
been taken in the compilation and preparation hereof, SFA does not warrant that the
contents herein represent all the conditions and requirements of the relevant
Competent Authorities/ Public Utility Licensees in respect of the proposed
development on the Land Parcel(s) or that they are free from errors or omissions
whatsoever. The contents herein are subject to changes by the relevant Competent
Authorities/ Public Utility Licensees concerned.
2.3 A summary of the initial services requirements of the relevant Competent Authorities/
Public Utility Licensees is set out herein. It serves only as an indication of the possible
work involved with regards to services, and is by no means exhaustive or final.
2.4 The Successful Tenderer shall ensure that the following requirements are complied
with:
2.4.1 to consult and liaise directly with the relevant Competent Authorities/ Public
Utility Licensees regarding the actual locations of all service mains within the
Land Parcel(s) and on the requirements and conditions for services diversion
and provision prior to the commencement of site work. All necessary
precautions shall be taken by the Successful Tenderer to safeguard the service
mains before they are diverted.
2.4.2 to engage his own licensed Cable Detection Worker (CDW)/ licensed
Telecommunication Cable Detection Worker (TCDW) to carry out cable
detection and if necessary to carry out trial trenches to locate any manholes
and cable routes prior to the commencement of site work. The Successful
Tenderer shall bear the cost of any diversion work.
2.4.3 to ensure that all service mains that do not need to be diverted are identified
and provided with protection, if necessary, during the construction stage of the
proposed development. The cost of repairs to any damaged service main as a
TR5/GA/FIDM CA 3 of 18
result of work carried out by the Successful Tenderer shall be borne by the
Successful Tenderer.
2.4.4 to ensure that the relevant Competent Authorities/ Public Utility Licensees are
allowed free and unconditional access at all times to services that are required
to remain within the Land Parcel(s) for the purpose of installation, maintenance,
repair and improvement works and all other work and activities incidental
thereto.
2.4.5 to make his own arrangements with the relevant Competent Authorities/ Public
Utility Licensees and pay for the costs of any diversion and/ or "Capping off" of
existing services, provision of service mains and connection fees if any, in
connection with the proposed development.
2.4.6 to provide all the internal distribution for water, electricity, drainage and sanitary
discharge for the proposed development.
2.4.7 to liaise with all the relevant Competent Authorities/ Public Utility Licensees on
upgrading the road reserves abutting the Land parcel(s) to ensure that the
necessary roadside drains, sidetable, kerb, etc are carried out in accordance
with the latest Road Reserve requirements.
2.5 The Successful Tenderer shall note that there may be sub-structures e.g. footings,
piles, tree roots, etc. and other obstructions in the ground. The Successful Tenderer
shall at his own cost and expense carry out his own site verification of these sub-
structures and other obstructions, and ascertain its effect on the proposed
development.
2.6 In general, no structure shall be sited close to or over existing/ proposed services. The
Successful Tenderer shall comply with all the necessary requirements as stipulated by
the relevant Competent Authorities/ Public Utility Licensees.
2.7 The Successful Tenderer shall seek all relevant agencies’ approval on the layout plan.
3.0 NATIONAL ENVIRONMENT AGENCY (NEA)
3.1 The Successful Tenderer shall check with PUB whether the Land Parcel(s) is located
within a water catchment area, where rainwater and surface runoff are collected in the
downstream reservoir for treatment to produce drinking. The proposed development
shall not cause pollution directly or indirectly to our water resources. Activity that could
cause serious contamination problem to our water resources shall not be carried out.
Please also ensure that the requirements for developments in water catchment areas
at ANNEX A are duly complied with.
3.2 Sewage and used water from the proposed development shall be discharged into the
public sewer. If public sewer is not able to commission in time for the proposed
development, sewage and used water may be collected using a temporary holding
tank system. A licensed waste collector could then be engaged to transport the content
TR5/GA/FIDM CA 4 of 18
of the holding tank for treatment and disposal at an approved Water Reclamation Plant
operated by PUB. Details of the temporary holding tank system shall be submitted to
PUB for approval before implementation. Also, when public sewer serving the Land
Parcel(s) becomes available, the Successful Tenderer shall divert sewage and used
water to the public sewer and demolish the temporary holding tank.
3.3 Pollution control facilities shall be provided at the areas designated for unloading of
animals in cages and also washing/cleaning of empty cages as well as the vehicles
after unloading. All washing wastewater generated shall be collected and treated to
meet the discharge requirements before it is discharged into the public sewer.
3.4 As far as possible, all waste water (e.g. fish tank water, etc.) generated from the
proposed development shall be collected and treated for reuse in the farm. Any excess
wastewater that cannot be recycled and reuse, shall be discharged into the public
sewer in accordance with the conditions and requirements imposed by PUB. If public
sewer is not available, the Successful Tenderer shall submit his wastewater treatment
and disposal plan to NEA for approval.
3.5 If the proposed farming activities would include the use of pesticides, only pesticides
that are registered by the Singapore Food Agency shall be used. Approval from NEA
is required for chemicals including pesticides that are listed as hazardous substances
under the Environmental Protection and Management Act (EPMA). Only pesticides
registered with NEA shall be used against the five vectors (namely mosquitoes, flies,
cockroaches, rodents and rat fleas). All the pesticides and chemicals used for the
proposed farming activities shall be stored within buildings or covered sheds equipped
with leakage or spillage containment facilities. Their dosage will also have to be
controlled so that it will not cause any nuisance to people in the vicinity or
contamination problems to the surface run-off during rain events.
3.6 The emissions of air pollutants shall comply with the prevailing emission limits for air
impurities as stipulated in the Environmental Protection and Management (Air
Impurities) Regulations. For air impurities with no prescribed emission standards, the
best practical means shall be adopted to minimise air pollution and odour nuisance.
3.7 Off-road diesel engines used in the proposed development are to comply with the
emission and other requirements as stated in the Environmental Protection and
Management (Off-Road Diesel Engine Emissions) Regulations. Off-road diesel
engines are any equipment or machinery with diesel engines as the main or auxiliary
prime mover and not registered with the Land Transport Authority (LTA) for use on
public roads. Examples include construction equipment such as cranes, excavators,
forklifts and power generators.
3.8 The noise levels measured at the boundary of the proposed development shall comply
with the noise limits stipulated in the Environmental Protection and Management
(Boundary Noise Limits for Factory Premises) Regulations.
3.9 Refuse and solid wastes from the proposed development, including the sludge
generated from treatment of wastewater, shall be collected and kept in a proper holding
TR5/GA/FIDM CA 5 of 18
area before disposal by a licensed general waste collector. The Successful Tenderer
is reminded that refuse or solid wastes are not allowed to be disposed by throwing
them into any drain, burying them on-site or using open burning method.
3.10 If the proposed farm activities include holding, keeping, rearing, breeding or the use of
hoof animals (e.g. cattle, goat, etc.), the Successful Tenderer shall comply with the
public health requirements as stated in the Cattle Act and its regulations.
3.11 The proposed development shall comply with all the applicable requirements and
provisions of the Singapore Standard on Code of Practice for Pollution Control (i.e.
SS593:2013), the Code of Practice on Environmental Health, the Code of Practice for
the Control of Legionella Bacteria in Cooling Towers, the Guidelines on Boundary
Noise Limits for Air-Conditioning and Mechanical Ventilation Systems in Non-Industrial
Buildings, the Environmental Protection and Management Act, the Environmental
Public Health Act, the Cattle Act, the Energy Conservation Act, the Radiation
Protection Act and their Regulations.
3.12 Under the Environmental Protection and Management (Control of Noise at
Construction Sites) Regulations, construction sites within 150 m of residential estates
need to comply with more stringent noise limits at the construction stage especially
during night time hours. Hence, the appointed Qualified Person (“QP”) shall implement
noise control measures during the construction period to ensure that the noise
emission levels from the building and construction activities are within noise limits and
would not cause nuisance to any nearby residents. In addition, the proposed
development is not allowed to carry out construction activities from 10 pm on Saturday
and eve of public holiday to 7 am on the following Monday and the day after the public
holiday respectively.
3.13 The Land Parcel(s) is located in close proximity to the Tengah Airbase and hence has
a relative high ambient noise level attributed to the aircraft operations. If any uses or
activities in the proposed development are noise sensitive, the Successful Tenderer is
advised to assess the noise impact and incorporate mitigation measures in the
planning, design, building, construction, operation and maintenance of the proposed
development so as to mitigate the noise impact.
Additional Requirements for Farms with Slaughter House/Processing Facility
3.14 All dead animals, dung, offal (internal organs), blood, feathers, and other solid wastes
from the proposed slaughterhouse/processing facility shall be collected and stored in
an enclosed purpose-built building/shed designed with abatement measures to control
water pollution, smell/dust nuisance and pest infestation, pending the collection and
disposal by a licensed waste disposal company.
3.15 Technical details of the proposed air pollution control equipment, odour abatement
facility, fuel burning equipment (e.g. boilers, heaters and ovens, etc.) & chimney for
flue gas discharge and wastewater control system shall be submitted to NEA(CBPD)
for clearance before installation. Thereafter, the proposed equipment shall be duly
TR5/GA/FIDM CA 6 of 18
installed and ready for use before the proposed slaughtering/processing facility is
allowed to commence operations.
4.0 POWERGAS
4.1 There are no existing gas mains in the vicinity of the Land Parcel(s).
4.2 A report must also be made to SPPG (Gas Network Management), upon detecting any
gas pipelines of which we have no records in your vicinity at Tel No. 1800 7521800.
4.3 Enclosed is a copy of the “Requirement for Distribution Gas Mains Diversion Works”
(ANNEX B) and "Notes For Working Near PowerGas Gas Transmission Pipeline"
(ANNEX C) for your information.
4.4 Existing gas plan(s) can be purchased on request to:
Mapping & Earthworks Administration Section
Pasir Panjang District Office
25 Pasir Panjang Road
Singapore 117536
Tel No. 6916 5022
Email: [email protected]
5.0 SP POWERGRID (SPPG)
5.1 There are underground electricity cables in the vicinity of the Land Parcel(s). If the
Successful Tenderer shall carry out earthworks in the vicinity of the cables, their
contractors shall engage the services of licensed cable detection workers to carry out
the cable detection work prior to the commencement of earthworks. All necessary
precautionary measures must be taken to prevent damaging SPPG’s cables at the
work site.
5.2 The Successful Tenderer can contact Earthworks Surveillance and Protection
Section’s Mr Chen Jianhong, Senior Engineer at Tel No. 6916 5116 regarding cable
damage preventive measures. The Successful Tenderer shall submit notices to SP
PowerGrid at least 7 days prior to earthworks (including trial trenches) in the vicinity of
high voltage electricity cables under the provisions of the Electricity Act.
5.3 The Successful Tenderer is advised to acquire a set of drawings for the electricity
cables around the proposed work area. For further details on cable plan requests,
please contact Mr Ismail, Technical Officer of Mapping & Earthworks Administration
Section at Tel No. 6916 5022.
5.4 For proposed earthworks which are likely to affect the cables and need cable
diversion/protection/suspension etc, after the cable detection work is done, the
Successful Tenderer can request for diversion via our SP e-Business Portal located at
www.spgroup.com.sg, under the heading “Electricity & Gas” or contact the following
officers:
TR5/GA/FIDM CA 7 of 18
For 22kV and below cables, please contact Mr Vincent Wong Kum Fong, Principal
Engineer of Distribution Network North Section at Tel No. 69165735 or email:
For 66kV cables, please contact Mr Fu Yongyi Jimmy, Principal Engineer of
Regional Network West Section at Tel No. 69165225 or email:
For 230kV and above cables, please contact Mr Richard Ngo, Principal Engineer
of Extra High Voltage Network Section at Tel No. 69165490 or email:
[email protected] for 230kV and above cables
5.5 The Successful Tenderer shall notify SPPG 6 months before the commencement of
earthworks affecting distribution cables and 24 months if the work involves
transmission cables (66 kV and above). The cost of cable
diversion/protection/suspension incurred by SPPG shall be borne by the requesting
party. The Successful Tenderer shall not commence the proposed earthworks until the
affected cables are diverted/protected/suspended.
5.6 Please consult Mr Ooi Wenyao, Senior Engineer of Distribution Planning Section at
6916 8551 or email: [email protected] if you need information on substation
and connection requirement, etc. for your proposal. For matters on substations to make
way for redevelopment works, please contact Mr Bob Tan, Principal Engineer of
Distribution Planning Section at Tel No. 6916 8452 or email: [email protected].
5.7 If you need further clarification, please contact Mr Chen Jianhong, Senior Engineer of
Earthworks Surveillance & Patrolling Section at Tel No. 6916 5116 or email:
5.8 Based on information given by Singapore Food Agency (SFA) of Singapore, there are
400 A of power available from the 22 kV/LV electrical substation under construction by
SFA. The proposed ESS is expected to be completed and commissioned by 31 Dec
2019. The indicative completion date of 31 Dec 2019 is based on the assumption that
the proposed ESS works can be carried out and completed as scheduled without any
complications or delay. The State shall not be responsible for any delay in completion
of the proposed ESS works, whatsoever. If the farm operation requires more than 400
A of power, the Successful Tenderer shall construct their own 22 kV/LV ESS as part
of their farm development within their Land Parcel(s).
6.0 MINISTRY OF DEFENCE (MINDEF)
6.1 The Successful Tenderer shall ensure that all developments, structures and fixtures
on the Land Parcel(s) shall not exceed the maximum height of 100m AMSL. Such
developments, structures and fixtures include those on the roof tops, whether
permanent, temporary, transient or stationary (including but not limited to the building
superstructure, TV antennae, water tanks, lift motor rooms, cranes, maintenance
equipment, lightning conductors, moving objects, vegetation etc.) and all construction
equipment and temporary structures (including but not limited to cranes, piling rigs,
etc.) which shall all be subject to the same height limit(s). Republic of Singapore Air
TR5/GA/FIDM CA 8 of 18
Force’s (RSAF) clearance shall be sought for the use of construction equipment and
temporary structures above 75m AMSL (Email: [email protected]). For
civil aviation height and requirements, please consult the Civil Aviation Authority of
Singapore (“CAAS”). The more stringent height restriction(s) from the respective
agencies shall apply.
6.2 The lighting system and solar reflectance from materials (e.g. façade cladding) for the
proposed development must not affect aircraft in flight. The Successful Tenderer shall
ensure that any working/outdoor lightings and solar reflectance must be directed
downwards and/or shielded to prevent causing glare and confusion to pilots. The
Successful Tenderer shall undertake all necessary rectifications at its own cost and
expenses to the satisfaction of the RSAF if the lightings are assessed by the RSAF to
be a hazard to air navigation. The Successful Tenderer shall submit their detailed plans
on any glare-inducing installations to DSTA, CAAS and BCA for comments prior to
implementation.
6.3 The Successful Tenderer may wish to note that the Land Parcel(s) are in the vicinity of
Army training grounds. The proposed development must not encroach on MINDEF’s
land boundary or affect any of its facilities, infrastructure and services.
6.4 The proposed development must not impose any constraint on MINDEF or curtail its
existing and future developments, operations and activities in any way.
6.5 The access road(s) leading to MINDEF’s premises must not be obstructed at any point
in time, including during the construction period.
6.6 Under no circumstances shall MINDEF be responsible for any loss, damage, liability
or expense incurred or suffered that is claimed to have resulted from siting in proximity
to military training grounds.
6.7 The Successful Tenderer may wish to note that as the Land Parcel(s) are located in
proximity to Tengah Air Base and military training grounds, there may be noise, dust
and vibrations concerns regarding the proposed usage of the site, especially for noise
or vibration-sensitive operations. As such, these effects should be taken into account
in the proposed development, and in particular, in the design of the facilities and
operating equipment. For further information on noise issues, the Successful Tenderer
can consult NEA.
6.8 The Successful Tenderer shall consult DSTA through URA – Development Control
Group when the detailed development plans are available.
7.0 SINGAPORE CIVIL DEFENCE FORCE (SCDF)
7.1 For Fire Safety requirements, the Successful Tenderer shall comply with the Fire
Safety Act and Regulations (ANNEX D). If the Successful Tenderer has any
clarifications on Fire Safety requirements, the Successful Tenderer shall consult the
Fire Safety and Shelter Department (FSSD) located at SCDF Headquarters. The
Successful Tenderer shall ensure fulfilment of the necessary FSSD requirements.
TR5/GA/FIDM CA 9 of 18
7.2 Besides the fire safety requirements, the Successful Tenderer is encouraged to adopt
measures stated in the attached advisory (ANNEX E) from the Singapore Police Force.
8.0 LAND TRANSPORT AUTHORITY (LTA)
General requirements
8.1 All proposed street works, as well as proposed engineering/ construction works within
the road reserve shall be prepared/designed, submitted, supervised and constructed
in accordance with the Street Works (Private Street Works) Regulations and the
following prevailing standards and code of practice:
a. Street Work Proposals relating to Developmental Works
b. LTA Standard Details of Road Elements
c. Materials Workmanship Specifications for Civil and Structural Works
d. Code of Practice for Road Opening Works
e. Code of Practice for Traffic Control at Work Zone and,
f. Architectural Design Criteria and Civil Design Criteria
8.2 Prior approval from LTA is required for any deviation from the designated access points
as indicated in the Control Plans provided in the Technical Information Booklet.
8.3 The detailed plan for the said development, incorporating LTA’s requirements, shall be
submitted to LTA’s Development and Building Control Division at the relevant DC and
BP submission stages.
8.4 The proposed development is required to comply with the physical parking requirement
of the prevailing Parking Places (Provision of Parking Places and Parking Spaces)
Rules.
8.5 Specific requirements
a) There should be only one access for one development.
b) The access to access (including opposite access) has to be at least 30m apart.
c) The access has to be at least 50m away from bus stop, road junction and road
bend (measured from start/end of bend).
d) Proposed access must have sufficient line-of-sight as in accordance to LTA
guideline especially from the road bends (eg. intersection sight distance, stopping
sight distance and etc).
e) Turning radius of the access is in accordance to LTA standards.
f) Sufficient line of sight to be provided along the main road where the accesses are
located (ie. Stopping sight distance, etc.)
g) Proposed access to meet the Intersection Sight Distance guideline.
h) Access should not be located at road bend.
i) Ensure the boundary walls do not block the line-of-sight of vehicles exiting from
the development.
j) Sufficient parking space should be provided within the development.
TR5/GA/FIDM CA 10 of 18
k) Parking/waiting/ pick-up/drop-off activities should be done within the development,
no parking/waiting/pick-up/drop-off activities are allowed along the main road.
l) Any gantries provided within the development should be set back to at least 2 car
length into the development.
m) To include stop line and sign within the development access.
n) Pedestrian gate(s), if any, should be located near bus stops and/or nearby
crossing facilities if any.
o) The access points should not be blocked by any obstruction on the verge.
9.0 NATIONAL PARKS BOARD (NParks)
9.1 Pursuant to the Parks & Trees Act (Cap.216), any tree with a girth exceeding 1 m
measured 0.5 m from the ground, growing on the Land Parcel(s), any tree conservation
area or any vacant land shall not be cut or damaged.
9.2 The proposed development shall comply with requirements for green buffers and 2-
metre wide peripheral planting verges. The green buffers and peripheral planting
verges must be free from any encroachment above ground, and/or any structures or
services are to be recessed to at least 2-metre below ground level, and are not to
slope with gradients steeper than 1:2.5.
9.3 The Successful Tenderer shall consult NParks’ Greenery and Development Planning
(GDP) Branch early at the planning and design stage on the felling of any trees that
may be affected by the proposed development with a copy of recently surveyed plan
of the site (of less than 2 years) and its peripheral roads, at a scale of at least 1:500,
clearly indicating information on tree species, height and girth. Additional information
such as plans indicating the construction hoardings should also be submitted.
9.4 The Successful Tenderer shall ensure that roadside trees and green verge(s) abutting
the Land Parcel(s) are not to be affected, especially by vehicular ingress/egress,
acceleration/deceleration/storage/vehicular lanes, services access, bus stops, and any
structure required under statute to be erected to divert or reconstruct services or road
features/elements, etc. Similarly, the Successful Tenderer shall ensure that pick-
up/drop-off points, taxi lay-bys, loading/unloading bays and fire engine hard-standing
areas are to be located within the Land Parcel(s).
9.5 The Successful Tenderer shall replace the existing roadside green verge fronting the
Land Parcel(s) if it is affected by the proposed use. The width of the replacement green
verge should be in accordance to LTA’s standard road code for that category of road
or match the existing green verge along the road, whichever is wider.
9.6 Development works are to be confined within the Land Parcel(s) and working
boundaries. There must not be any illegal dumping or storing of construction materials
beyond the approved boundaries. The proposed development shall not encroach on
the road reserve line and affect any roadside table.
9.7 There must not be any change of soil level to the roadside planting verge without prior
approval from NParks.
TR5/GA/FIDM CA 11 of 18
9.8 There must not be any widening and/or raising of existing carriageways and
realignment of road kerbs and drains on abutting roads without prior approvals from
the relevant authorities.
9.9 The Successful Tenderer shall ensure that all necessary measures (i.e. installation of
appropriate barriers/nettings, regular inspections by authorities etc) are taken to
prevent disease transmission between farmed and wild animals. In undertaking any of
the above measures, all reasonable efforts should be made to ensure the welfare and
safety of the animals. The Successful Tenderer shall ensure that all farmed animals
are properly housed and managed to prevent any escape.
9.10 To minimise impact to the nearby Sungei Buloh Nature Reserve, the proposed
development shall comply with the list of best management practices for agricultural
developments attached at ANNEX A.
9.11 The Successful Tenderer shall comply with planting provision and aeration
requirements for open air parking at street level. More details can be viewed on
NParks’ website at https://www.nparks.gov.sg/-/media/nparks-real-content/partner-
us/developers-architects-and-engineers/guidelines-on-greenery-provision-and-tree-
conservation-for-developments_version-3.pdf. See Chapter 3 on “Planting Provision
for Open Air Parking Area at Street Level”.
9.12 The Successful Tenderer shall comply with any height restrictions imposed by URA on
the proposed development.
9.13 The Land Parcel(s) abut NParks’ proposed landscape nurseries. The Successful
Tenderer shall ensure that:
i. No animal waste to be discharged into public drains or neighbouring parcels
through groundwater migration.
ii. Where necessary, buffer areas for air borne chemicals (e.g.
pesticides/fertilizers) are to be provided within the Land Parcel(s).
iii. Electrical requirements for the proposed farms are to be factored in.
9.14 Future effluent and runoff from the farms have to meet NEA standards for discharge
into uncontrolled watercourse and sewerage system. The Successful Tenderer shall
conduct water monitoring at the approved discharge point to ensure compliance and
report the results to NEA.
9.15 Direct dumping of farm waste or wastewater into any water bodies/sewerage system
is strictly prohibited.
9.16 The Successful Tenderer shall comply with the list of best management practices.
Please note that the BMPs are applicable to all farms within and outside the water
catchment area.
TR5/GA/FIDM CA 12 of 18
9.17 SFA will jointly with relevant authorities conduct site checks where necessary to ensure
compliance of the farm’s waste water and waste management practices to prevailing
NEA standards.
10.0 PUBLIC UTILITIES BOARD (PUB)
10.1 DRAINAGE DESIGN AND STORMWATER MANAGEMENT
a) All structures and proposed works shall not encroach into the drainage reserves.
b) The existing drainage system shall not be altered or interfered with without the prior
approval of PUB.
c) The minimum platform level for the Land Parcel(s) shall not be lower than RL 104.50m
or 300mm above the existing adjacent road levels or ground levels, whichever is the
highest. No marine sand shall be used for backfill. Soil used must be of suitable
materials with chloride content less than 0.01%.
d) All runoff within a development site shall be discharged into a roadside drain or an
outlet drain and not into the adjacent premises.
e) The design and construction of the proposed development within the Land Parcel(s)
shall not cause or affect the structural integrity of the roadside drains or outlet drains.
f) Development sites greater than or equal to 0.2 hectares in size are required to control
the peak runoff discharged from the development sites. The maximum allowable peak
runoff to be discharged to the public drains will be calculated based on a runoff
coefficient of 0.55, and for design storms with a return period of 10 years and for
various storm durations of up to 4 hours (inclusive).
g) Effective erosion and sediment control measures shall be provided by the Successful
Tenderer and the appointed QP shall advise the Successful Tenderer to provide such
effective measures and facilities with inputs from Qualified Erosion Control
Professional (including site management system and perimeter cutoff drain, silt traps,
storage ponds, treatment plants, etc.) to ensure clean discharge that complies with the
statutory requirement. The proposed erosion and sediment control measures shall be
submitted by a Qualified Erosion Control Professional (QECP) to Public Utilities Board
before commencement of works. All affected watercourses shall be desilted and
cleared until completion of work.
h) The planning, design, construction activities and procedures for plan submission shall
comply fully with the requirements as stipulated in the current edition of the Code of
Practice on Surface Water Drainage and The Sewerage and Drainage (Surface Water
Drainage) Regulations 2007.
i) The Successful Tenderer shall not extract any groundwater for whatever uses and/or
activities.
TR5/GA/FIDM CA 13 of 18
j) PUB has in 2006 launched the Active, Beautiful and Clean Waters (ABC Waters)
Programme. As part of the Programme, PUB has launched ABC Waters design
guidelines which provide ideas on how natural runoff treatment systems termed ABC
Waters design features such as rain gardens, vegetated swales and bioretention
swales can be integrated within a development. These features detain/ slow down
stormwater runoff and improve water quality by using plants and soil. They also
enhance landscape and biodiversity of the development. Specific information on the
design of these features can be found at the website
http://www.pub.gov.sg/abcwaters/abcwatersdesignguidelines/pages/abcdesignguideli
nes.aspx.
k) PUB encourages the implementation of ABC Waters design features in the
development as well as the achievement of ABC Waters certification. Information
regarding ABC Waters Certification can be found via the link:
http://www.pub.gov.sg/abcwaters/ABCcertified/Pages/default.aspx.
If applicable, the design and construction supervision of ABC Waters design features
as well as drawing up the maintenance plan for these features shall be carried out by
an ABC Waters Professional.
10.2 PROTECTION OF WATER QUALITY IN WATERWAYS
a) General Requirements
i. Strict pollution control measures such as oil spillage preventive measures shall be
incorporated in the design and during the construction of the proposed
development.
ii. All pollution control measures stipulated in NEA’s Environmental Protection and
Management Act (EPMA) shall be fully complied with.
iii. All sewage and sullage water shall be discharged into a public sewer.
iv. The discharge from any agricultural sites (located at outside water catchment
area) into the drainage system shall comply with Allowable Limits for Trade
Effluent Discharge to Watercourse under EPMA (Trade Effluent) Regulations.
v. The Successful Tenderer shall ensure compliance with the list of best
management practices for agricultural developments appended at ANNEX F of
the “Conditions and Requirements of Relevant Authorities / Public Utilities
Licensees”.
10.3 USED WATER
a) PUB is implementing public sewers within the vicinity of the proposed Land Parcel(s).
These sewers will be ready to receive used water from the proposed development after
end 2020. The Successful Tenderer may liaise with PUB’s project officer, Mr Paul Puah
(email: [email protected]; Tel No. 68852487) or Wening (email:
TR5/GA/FIDM CA 14 of 18
[email protected]) on the details of the project schedule. The plans of the
proposed 250mm and 500mm diameter sewers along Neo Tiew Crescent are found in
ANNEX G.
b) Please note that NEA no longer allows the use of conventional STP and R2s. The
Successful Tenderer shall use only on-site sewerage systems approved by NEA
(holding tank, etc.), while the new public sewers are being constructed. Please refer to
items ANNEX H for the preliminary advice/requirements on the use of on-site
sewerage system. The Successful Tenderer shall seek approval from PUB on the
finalised details of the proposed on-site sewerage system before developing these
proposed sites.
c) When the new public sewers are completed, the Successful Tenderer shall divert the
flow from the on-site sewerage system to the completed estate sewer within 6 months
upon being notified by PUB. This includes engagement of plumbers/contractors for the
diversion of flows from the drainline to the existing sewer, and the subsequent
demolition of the on-site sewerage system at their own cost. PUB has proposed
advance sewer to facilitate connection from the Land Parcel(s). Sewer connection from
each Land Parcel should be connected to the proposed advance sewer. These
advance sewers’ location would be marked above ground with a steel plate. The
indicative location of the proposed advance sewer for each individual plot is attached
in ANNEX I(i) (for LCK114A) and ANNEX I(ii) (LCK114C, LCK114D).
d) Animal waste shall not be discharged to the sewerage system. The Successful
Tenderer shall comply with NEA requirements in accordance with SS 593: Code of
Practice for Pollution control for the disposal of animal waste.
e) PUB will maintain the approved holding tanks installed only if the Successful Tenderer
engages in conventional farming activities (e.g leafy vegetable farming). If, in addition
to conventional farming activities, the farm also conducts/organises activities that
would promote/attract big crowds/visitorship to the farm, resulting in the generation of
huge quantity of used water, the Successful Tenderer shall maintain the holding tanks
installed. Some examples of uses/activities are as follows:
o Farm Stay
o Education tours/activities
o Commercial cafes/cafeteria/eatery
o Cooking classes
o Marketing or selling of farm produce
o Exhibition/visitor centre
f) If a MBR-STP is installed, it shall be maintained by the Successful Tender, and NEA’s
prior approval is required.
g) Trade effluent discharge from the proposed development into the public sewerage
system shall comply with the requirements as stipulated in the Sewerage and Drainage
(Trade Effluent) Regulations. Pre-treatment plant/facilities shall be installed to ensure
the compliance of the trade effluent with the discharge requirements. The Successful
Tenderer shall be responsible for the provision, operation and maintenance of the pre-
treatment plant/ facilities. A summary of the discharge requirements for trade effluent
TR5/GA/FIDM CA 15 of 18
can be viewed from PUB website at:
https://www.pub.gov.sg/Documents/requirements_UW.pdf.
h) The Successful Tenderer shall obtain a Written Approval (WA) issued by PUB for the
discharge of trade effluent into public sewers. The application for WA can be done
online at https://licence1.business.gov.sg. For matters relating to trade effluent
discharge, please contact Mr Fang Sain Piaw or Mr Chee Kian Heng at Tel No. 6517
2223 from PUB (WRN).
i) For construction works near public sewers, the Successful Tenderer shall comply with
PUB’s Code of Practice on Sewerage and Sanitary Works and the guidelines on
‘Prevention of Damage to The Sewerage System’ which can be found in PUB website
at https://www.pub.gov.sg/Documents/WRN_AdvisoryNotes.pdf.
The Successful Tenderer shall check for the presence of public sewerage pipelines by
referring to the Sewer Information Plan (SIP) which can be purchased online through
PUB’s website at
https://www.pub.gov.sg/compliance/qualifiedpersonsportal/eservices/requestforservic
esplans. Please note that the sewerage information in SIPs is indicative and for
reference only. A thorough site investigation, including trial trenches, shall be carried
out to determine the exact position and levels of the existing sewers prior to
commencement of any works.
10.4 WATER SUPPLY
a) Water Supply Infrastructure/Land Use
i. Provisions shall be made by the Successful Tenderer for PUB to lay new
watermains if required, along public road reserves/sidetables to the Land
Parcel(s). The cost for the laying of new watermains and connecting pipes to
serve the Land Parcel(s) shall be borne by the Successful Tenderer. Please note
that PUB will only lay new watermains on LTA public road reserves. If the new
roads to be constructed are not LTA public road reserve, then PUB will not lay new
watermains in these privately owned roads. The Successful Tenderer will have to
lay their own water service pipes to the proposed development.
ii. PUB’s existing watermains are located in the vicinity of the some of the Land
Parcel(s) and may be affected by the proposed development. The Successful
Tenderer shall determine by means of trial holes the exact positions of all the
watermains and let PUB know which of these watermains will be affected so that
we can advise on whether diversion is required. If deemed necessary by PUB, the
affected watermains shall be diverted and the cost of diversion shall be borne by
the Successful Tenderer. The cost of diversion shall be finalised upon confirmation
on the length of watermains affected.
TR5/GA/FIDM CA 16 of 18
b) Marking of Watermains
i. The positions of all the watermains as shown are approximate only. Please
determine by means of trial holes the exact alignment and levels of all existing
watermains during the design stage and let PUB know whether they are affected
by the proposed works so that we can advise whether diversion is required. If
diversion is required for watermains of 300 mm diameter and below, consultation
must be made at least 6 months ahead and the cost of diversion of any watermain
shall be borne by the Successful Tenderer. Diversion of PUB’s existing
watermains of 500 mm and above, being PUB’s vital watermain should be avoided
unless absolutely necessary.
ii. No structure either permanent or temporary may be erected over or within 1 m
from PUB watermains. PUB’s buried watermains require a minimum cover of 1 m,
and the Successful Tenderer shall provide adequate protection for PUB’s
watermains should the cover be removed or reduced.
iii. No services shall overcross or be erected over any watermain. Where a cable,
pipe or drain undercrosses a watermain, a clearance of 1 m is required. No
manhole is allowed on top of any watermain. There must be a horizontal clearance
of 1 m between the manhole and watermains.
iv. The Successful Tenderer shall take all necessary precautions to safeguard and to
avoid damage to all watermains. The cost of repairs to any watermain damaged
as a result of work carried out shall be borne by the party who caused the damage.
The party will also be required to indemnify the PUB against all losses and claims
arising from damage to watermain. The party will also be billed for the estimated
quantities of water loss from the damaged main. Further information on prevention
of damage to PUB watermains can be found in ANNEX J attached for reference.
v. In general, care should be exercised to prevent any damages to PUB watermains
and appurtenances Section 57 of the Public Utilities Act stipulates a duty to
enquire on watermains before any person digs, bores, trenches, grades,
excavates, tunnels or breaks any ground with any mechanical equipment, tool or
explosive. Under Section 47A of the Public Utilities Act, any person who, whether
wilfully or otherwise, removes, destroys or damages or causes or permits to be
removed, destroyed or damaged, any watermains belonging to or under the
management or control of the Board, shall be guilty of an offence and shall be
liable on conviction to a fine not exceeding $40,000 or to imprisonment for a term
not exceeding 3 months or to both; or if the watermains is 300 mm or more in
diameter, to a fine not exceeding $200,000 or to imprisonment for a term not
exceeding 3 years or to both. For more information of the Public Utilities Act,
please refer to http://statutes.agc.gov.sg/
vi. PUB watermains and connections must be accessible for maintenance and repair
works at all times
vii. PUB watermain valve chambers and appurtenances shall not be covered over.
TR5/GA/FIDM CA 17 of 18
viii. PUB watermains shall not be subjected to more than 15 mm/s peak particle
velocity for any work to be carried out in the vicinity of PUB’s watermain and
appurtenances.
ix. Please inform PUB’s 24-hour Water Service & Operations Centre at 6521 6488
immediately in the event of damage to any watermain.
c) Submission of Plans
i. The design of the water reticulation system shall comply with the Public Utilities
(Water Supply) Regulations, Singapore Standard CP 48 – Code of Practice for
Water Services and all other relevant statutory requirements. The modes of water
supply to be adopted are as follows:
Height of Highest Fittings Method of Supply
i) Less than 125 mRL Direct.
ii) Above 125 mRL but below
*137 mRL
Indirect supply through high level
storage tanks.
iii) Above 137 mRL Indirect supply through low level
tank with pumping to high level
storage tanks.
(* Refers to height of inlet pipe to high level storage tanks.)
ii. Notwithstanding the above modes of supply, where water is essential for the
operations of the above premises, storage tanks of capacity equivalent to 1 day’s
water requirements shall be provided for the purpose of maintaining a continuous
supply of water in the event of supply interruption.
iii. Where pumping systems or storage tanks are required for the water services, a
Professional Engineer must submit the Notification of Water Service Work
together with a set of the drawings to Water Supply (Network) Department. If all
the fittings in the water service installation are receiving direct water supply from
PUB mains, then a licensed water service plumber shall be engaged to submit the
Notification of Water Service Work and a set of drawings to our Department prior
to commencement of the installation work.
iv. PUB is presently supplying NEWater for direct non-potable purposes such as for
cooling towers, industrial processes, general washing, landscaping, and other
non-potable purposes. All new non-domestic premises such as commercial and
industrial developments, etc, including those existing premises undergoing
addition/alteration works where it is applicable to use NEWater, are therefore
required to provide a dedicated NEWater pipe system now to facilitate the supply
NEWater when it becomes available in future. Provision shall also be made for a
TR5/GA/FIDM CA 18 of 18
NEWater storage tank to be installed within the premises with its inlet not higher
than 115 mRL and a capacity equivalent to the 1 day’s non-potable water
requirement. There shall be no cross connection between the PUB water and
NEWater supply pipelines. The Successful Tenderer may consult PUB during the
pre-planning stage on the detailed requirements.
v. Water pipes and fittings to be used in the above site shall comply with standards
stipulated by PUB.
vi. The detailed water requirement for the proposed development shall be submitted
to Water Supply (Network) Department if it is more than 1,000 m3/month.
vii. Water conservation measures as stipulated in the Public Utilities (Water Supply)
Regulations and SS CP 48 – Code of Practice for Water Services shall be adopted.
viii. Non-potable water should be used for non-potable purposes such as irrigation,
general washing, etc. whenever possible.
ix. Water should be recycled wherever possible.
Please contact Mr Ow Zhao Hui (email: [email protected]; Tel No. 6731 3934) if
you need any clarifications on the water supply requirements.
11.0 COMPLIANCE WITH TECHNICAL CONDITIONS OF RELEVANT AUTHORITIES
11.1 The Successful Tenderer shall consult and comply with all the technical conditions
imposed by the relevant authorities such as SFA, NEA, PUB, PowerGas, SP
PowerGrid, MINDEF, SCDF, LTA, NParks and the URA et cetera at farm development
plan, the detailed development control and building plan stages.
ANNEX A
POLLUTION CONTROL MEASURES
FOR PROPOSED DEVELOPMENT
WITHIN WATER CATCHMENT AREA
1 Storage of Toxic Chemicals
(a) No toxic or hazardous chemicals shall be stored or moved within the
premises.
(b) Storage of fuel may be allowed subject to provision of pollution control
measures as stipulated in the Singapore Standard on Code of Practice for
Pollution Control (i.e. SS593:2013).
2 Public Sewerage System
(a) Public sewerage system shall be extended to serve the proposed
developments.
(b) All sewage shall be collected and discharged into the public sewers.
3 Drainage System
Vertical steel gratings shall be installed at major outlet drains.
4 Refuse Management System
Storage and transfer of refuse shall be confined within buildings.
5 Pollution Control Measures
(a) The exterior walls of buildings shall, where practical, be constructed,
coated or clad with materials that do not require periodic painting.
(b) Boundary fence/wall shall, where practical, be built with materials that do
not require periodic painting.
(c) The developments shall be designed to ensure that all activities that
generate wastewater or spent oil are carried out within buildings. The
design may include the following:
All sanitary fittings including wash areas be provided within
buildings.
Kitchens be designed to have sufficient area to ensure that all food
preparation and washing facilities are confined to within the
premises.
Washing bays for vehicles be provided within buildings and
wastewater from the washing of vehicles be collected, treated and
reused or discharged into the sewers.
6 Pollution Control Measures at Construction Stage
(a) During construction stage, no sewage from the construction sites shall be
discharged into the open drains leading to the reservoir.
(b) All washings activities shall be carried out within the buildings and all
sewage and the wastewater shall be collected and discharged into the
public sewerage system or holdings tanks and tankered away for disposal
at a Water Reclamation Plant approved by PUB.
(c) No servicing and repairing of mechanical plants and equipment are
allowed within the construction sites.
(d) Fuel storage tanks, if any, shall be provided with containment facilities as
stipulated in the Singapore Standard on Code of Practice for Pollution
Control (i.e. SS593:2013).
(e) The requirements for the control of silt discharge from a construction site
as stipulated in the Code of Practice on Surface Water Drainage shall be
complied with.
--------------------------------------------------------------------------------------------------
SP PowerGrid Ltd GDP-24
(0110)
1
To all concerned parties
We act for PowerGas Ltd.
Requirements for Distribution Gas Mains Diversion Works
1. Prior to any excavation works, the project owner / contractor shall request for gas servicesreturns and acquire the gas plans.
2. A minimum clearance of 300mm shall be maintained between our gas pipes and all otherservices or structure.
3. Where any gas pipes are affected, the project owner / contractor shall liaise with GasDistribution Projects for diversion of pipes. As far as possible, no gas pipes shall be withinthe hoarding area of the work site.
4. The project owner / contractor shall provide a corridor to facilitate diversion.
5. Wherever possible, isolation valves shall be inserted to enable quick isolation of pipelinewithin the work site (eg. crossing of bored tunnels, cut-and-cover tunnels, etc.). Theseisolation valves should not be located inside the work site.
6. Where the cut-and-cover tunnel runs parallel to the existing gas mains, there shall be aminimum clearance of 5 metres from the diaphragm wall.
7. All vent shafts to the tunnels shall be at least 20 metres away from the existing gas mains.
8. All piles shall be at least 5 metres away from the existing gas mains, which shall bedetermined by trial holes.
9. All crossings over cut-and-cover tunnels shall be replaced temporarily with steel pipes forsuspension and subsequently replaced with the original pipe materials upon the completion ofthe construction work. The steel pipe supports shall be endorsed by a Professional Engineerand submit to SPPG Gas Operations for approval. The support system shall allow access tothe pipe for inspection and for fire-fighting purposes in the event of an emergency.
10. No Air intake / outlet shall be located nearby existing gas mains.
11. Depending on the extent and complexity of diversion, a long lead-time may be required.Hence, the project owner is advised to consult SPPG Gas Operations early.
12. The project owner / contractor shall coordinate all diversion activities.
13. Where required, the project owner / contractor shall peg the agreed corridor for the laying ofthe diversion pipeline.
ANNEX B
SP PowerGrid Ltd GDP-24
(0110)
2
14. The project owner / contractor shall be aware of all gas pipes within the work site, and shall ensure that all parties working within the site are also aware of the locations of the gas pipes. Where possible, prominent markers indicating the pipe route shall be displayed.
15. The project owner / contractor shall be responsible to inspect, protect and maintain the
integrity of gas pipes within the work site, and observe the following: 15.1. No building structure is allowed to be built over all existing gas mains.
15.2. No heavy machinery/equipment is allowed to be placed or constructed over all existing
gas mains.
15.3. No heavy machinery / vehicle movement over the existing gas mains.
15.4. .Leak survey along the pipe route within the work site shall be conducted regularly. 16. Wherever possible, no hot work is allowed in the vicinity of gas pipes. If hot work is
unavoidable, the project owner / contractor shall take all necessary measures, including but not limited to the following:
16.1. the site shall be certified gas-free by a qualified Safety Officer. 16.2. gas-free checks shall be conducted regularly before commencement of work and
throughout the work.
16.3. all necessary precautions to prevent damage to the existing gas mains shall be taken.
16.4. all possible occurrence of fire hazards shall be eliminated.
16.5. where possible, physically separate the gas pipe from the heat source.
16.6. where necessary, consult SPPG Gas Operations on other precautionary actions to be taken.
17. Valve chambers which are still located within the work site due to site constraints, shall be
raised 0.5metre above ground and kept visible and accessible at all times, to enable easy identification and operation in the event of an emergency.
18. The project owner / contractor shall notify SPPG Gas Operations of any works directly or
indirectly affecting the existing gas mains or the newly diverted gas mains. 19. The project owner / contractor shall monitor possible ground movements / soil subsidence in
the vicinity of their work sites and inform SPPG Gas Operations immediately if any such movements / subsidence is observed / detected and where gas pipes are present.
20. In the event that any gas leak is detected, all works shall cease immediately and SPPG Gas
Operations 24 hrs Gas Service Operation Centre shall be contacted at Tel: 1800-752-1800 for assistance.
page 1 of 5
SP PowerGrid Ltd Company Registration No. 200306959Z
TPOM-12 (0714)
To all concerned parties
We act for PowerGas Ltd.
NOTES FOR WORKING NEAR POWERGAS GAS TRANSMISSION PIPELINE
1. Introduction
1.1 The Gas Transmission Pipeline (GTP) is designed to carry gas at high pressures. It isburied underground with granite dust and earth backfill cover as required under LTA’sregulations. Warning markers are planted near the pipeline to indicate its existence andwarn third parties working in the area.
1.2 SPPG patrols the pipeline regularly to monitor works in the vicinity by third parties. Suchworks if done without knowing the existence and/or exact location of the pipeline canpotentially damage the pipeline and/or it’s coating. SPPG pays special attention to drilling,piling, blasting or any high impact works, excavation and tunneling works and constructionof structures near or over the pipeline.
1.3 Any party who intend to carry out any construction activities in the vicinity of the GTP shallnotify and collaborate with SPPG to implement measures to protect the pipeline from allpossible damages.
2. Statutory Requirement
2.1 Section 32 Carrying out earthworks within vicinity of gas plant or gas pipe of the Gas Act(Chapter 116A) requires anyone who wants to carry out earthworks in the vicinity of thegas plant or gas pipe to
(a) give the gas transporter (SPPG) not less than 7 days’ notice in writing of the date onwhich it is proposed to commence the earthworks;
(b) obtain from the gas transporter the necessary information on the location of the gasplant or gas pipe; and
(c) consult the gas transporter on the steps to be taken to prevent the gas plant or gaspipe from being damaged while the earthworks are being carried out.
2.2 Section 32 also requires the person carrying out the earthwork to comply with the requirements of the transporter, ensure precautionary measures are taken to prevent damage to the gas pipe or gas plant and provide access to the transporter for inspection or taking necessary protective measures.
2.3 Any person that contravenes this Section 32 is guilty of an offence and shall be liable to a fine not exceeding $100,000 or to imprisonment for a term not exceeding 5 years or both.
ANNEX C
page 2 of 5
SP PowerGrid Ltd Company Registration No. 200306959Z
TPOM-12 (0714)
3. Requirements on Third Parties working near the Gas Transmission Pipeline
3.1 Pre-work Consultation with SPPG a) The works owner and contractor shall inform SPPG in advance of their intention to work in
the vicinity of the GTP and submit NCE accordingly. Such works include excavation, piling, earthwork leveling, bore logging, trial holes, blasting, tunneling or any earth works. The proposed work with construction drawings and method of statements shall be given to SPPG to evaluate the impact of the works on the pipeline. This enables SPPG to advise on appropriate precautionary measures to be taken.
b) The works owner and contractor shall obtain the as-built drawings of GTP from SPPG.
They are required to incorporate the pipeline alignment co-ordinates into their construction drawings. Please note that the information in the as-built drawings should be treated as confidential. Do not disclose or forward them to others.
c) No works in the vicinity of GTP shall be carried out without prior consultation and written clearance from SPPG.
d) SPPG shall be kept informed of any changes to the proposed works. e) No permanent structures shall be designed and constructed above the GTP. However,
surface road over the pipeline without reducing the pipeline cover may be acceptable, subject to SPPG's concurrence.
3.2 Precautionary Measures during Works a) The works owner and contractor shall take all necessary precautions to prevent any
damages to the GTP during the construction stage. They shall inform SPPG before carrying out any excavation works near the pipeline and report all damages to the pipeline and its coating to SPPG. Repair shall be done immediately to prevent corrosion aggravation to the pipeline at the damage location and thus becoming a potential hazard.
b) If any earthwork is within 5m of the pipeline (or more when required), a competent
surveyor shall be engaged to peg the pipeline alignment and interpret the pipeline depth from the pipeline drawings. Pegging and marking shall be clear and prominent and remain as such for the duration of works. Trial holes to prove the location of the GTP shall be carried out and all trial holes shall only be done in the presence of SPPG officer. The contractor's competent personnel shall supervise the earthwork, monitoring closely the pipeline depth based on the surveyor's interpretation.
c) Only manual excavation is allowed within 1m of the pipeline and only hand excavation is allowed within 0.5m of the pipeline.
d) Under no circumstance shall the GTP be exposed without written consent of SPPG. GTP
shall only be exposed in the presence of SPPG Officer. If a GTP is exposed, the owner/contractor shall take the necessary measures to protect the pipe from any physical impact that may cause damage to the pipe and/or its coatings to the satisfaction of SPPG.
e) Do not shift or remove warning markers indicating the existence of the GTP at site without
SPPG’s approval. The contractor shall protect them from being damaged or tempered. In the event the warning markers are damaged, they shall be reported to SPPG and replaced immediately. Where necessary, additional temporary warning markers shall be installed to warn others of the presence of gas pipeline.
page 3 of 5
SP PowerGrid Ltd Company Registration No. 200306959Z
TPOM-12 (0714)
f) For blasting works, piling or any works that cause ground vibration, the peak particle
velocity (PPV) of ground shock generated by the blast shall be limited to 15mm/s measured at the pipeline. The PPV shall be monitored in real time. SPPG shall be notified once the PPV reaches 10mm/s.
g) For tunneling, shaft excavation and piling works, ground consolidation could occur due
to ground water losses resulting in surface settlement. This settlement can potentially induce excessive stress on the pipeline. The contractor shall conduct a risk assessment to assess the impact of tunneling on the surrounding area. To monitor the surface settlement, surface monitoring points shall be installed along the pipeline alignment at every 10m intervals for at least 100m pipe length from the tunnel or shaft. The settlement shall be regularly monitored while excavation or tunneling works are being carried out. A differential settlement of 20mm will require all parties involved to assess the ground consolidation and evaluate the need to implement measure to arrest the consolidation. A thorough stress analysis of the pipeline shall be done by competent persons recognised by SPPG if the differential settlement reaches 60mm. Depending on the findings of the analysis, measures shall be taken to relieve the pipeline from the stress.
h) For crossing and parallel laying of services to GTP, Table 1 shows the required
separation distance between the GTP and other services or structures. It should be noted that other authorities may have stricter or additional requirements on minimum separation distance between proposed building / structure and the pipeline than what is stated here. Services crossing the pipeline shall not be at the previous boring pit locations of the pipeline, the locations are to be advised by SPPG.
i) For major works that span over a long period of time, the owner and contractor shall hold
monthly meetings to update SPPG on the progress and any changes to their works. j) For any new development surrounding the GTP, the developer shall inform the property
owner on the location of the pipeline within their premises and draw up measures to prevent any possible damage to it. Pipeline within a fenced compound shall be accessible to SPPG for patrolling and any maintenance works as and when required.
3.3 Repair of Damage Pipe/Coating
In the event the pipe and/or its coating are damaged by the third party works, SPPG will undertake the necessary repair works. All costs of such repairs shall be borne by the third party responsible for the damage.
3.4 Emergency Works
When emergency works have to be done near the pipeline in the interest of public or private safety, the owner and contractor shall call SPPG at the 24-hour hotline at 1800 752 1800 or 6595 5003. SPPG officers will respond to site to advise on the prevention of pipeline damage. The Principal shall submit a written notice to EMCP within 24 hours after the work has commenced.
page 4 of 5
SP PowerGrid Ltd Company Registration No. 200306959Z
TPOM-12 (0714)
4. Enquiries
The above requirements are only stated in general. The concerned party shall consult SPPG on all works near the GTP. SPPG reserves the right to alter any stated requirements or impose additional requirements that are necessary depending on site conditions and type of work. Refer all enquiries and correspondences on works near the GTP to:
Postal address
Transmission Pipelines Operations and Maintenance (TPOM) Section SP PowerGrid Ltd (Gas Operation) National Gas Control Centre 24A Senoko Ave Singapore 758314 Fax: 6304 8851 Email: [email protected] Telephone numbers
Transmission Pipelines Operations and Maintenance (TPOM) Section : 6595 5093 / 6595 5901 24-hour System Control Centre: 6595 5003 24-hour Customer Service Centre: 1800 752 1800
HEAD OF SECTION (TPOM) GAS TRANSMISSION MANAGEMENT BRANCH GAS OPERATION SP POWERGRID LTD As agent for and on behalf of PowerGas Ltd
page 5 of 5
SP PowerGrid Ltd Company Registration No. 200306959Z
TPOM-12 (0714)
Table 1: Minimum Separation Distance Between GTP And Other Services / Structures
S/N Service / Structure Minimum separation distance
1. Bore / sheet piling 2.0m
2. 200x200 Concrete Piles 2.0m
3. Tunneling Clearance distance 2.0m or more. Depending on size and depth, it may require monitoring of soil movement and settlement and risk assessment.
4. Directional Drilling 2.0m plus radius of final tunnel size
5. Formed Drain / Earth Drain 1.2m / 1.5m
6. Minor Drain 0.5m
7. Control Blasting 10m and PPV not more than 15mm/s.
8. Water/Sewer Pipe: less than 700mm dia.
0.5m
9. Water/Sewer Pipe: 700mm dia.or larger
1.5m or more depending on size of pipe and construction method.
10. Electric Cables: less than 22 KV 0.5m
11. Electric Cables: 22KV and above 1.2m
12. Telecom cables 0.5m
13. Low pressure gas pipe 0.5m
14. Shrubs 1.2m
15. Trees 2.0m
16. Posts / foundations for light, signs etc 1.5m
17. Road Pavement 1.5m
18. Off-Road Crossing for heavy vehicles 1.5m or more with 25mm steel plating on surface.
19. Earthing Rods 5.0m
FIRE SAFETY REQUIREMENTS, SINGAPORE CIVIL DEFENCE FORCE (SCDF)
The developer and building owner/management/user (named as the Proposer) are required to comply with the Fire Safety Act and Regulations, the prevailing "Code of Practice for Fire Safety Precautions in Buildings" (Fire Code), the relevant Codes of Practices & Guidelines, and SCDF Circulars. These general fire safety requirements are also applicable to any proposed temporary usage or installation. In addition, the following conditions will apply where applicable:
(a) To consult SCDF on the specific design requirements if the premises is tostore, handle, use, transport or import of hazardous materials, including petrolstation or CNG station which may have impact within the premises or on thesurrounding existing or new developments. SCDF may impose theQuantitative Risk Assessment study (QRA) and/or additional Fire Safetyrequirements, or disapprove such proposal if there is possible impact withinthe premises or on the surrounding developments.
(b) To consult SCDF on any specific developments or structures havingimpact on SCDF operations e.g. deep basement works (which are more than4 storey or more than 24 metres in depth), tunnel or any other specialdevelopments, etc. SCDF may impose additional Fire Safety requirements.
(c) The Proposer shall ensure that their proposal will not affect existing othersurrounding developments (neighbouring) such as their exit provision,sidelane / backlane, window openings [the unprotected openingsrequirements, i.e. the Proposer and their Qualified Person (QP) shall strictlyobserve these existing conditions and provide more setback if necessary toprevent fire spread] and fire engine accessway etc. The Proposer and theirQP shall consult FSSD (SCDF) directly for those new proposed buildingstructures to be sited near to common boundary line, as additional Fire Safetyrequirements may be imposed.
(d) The Proposer shall ensure that no building structures be located within25m buffer zone from any petrol station, either be a existing or going-to-buildpetrol station.
(e) For existing premises, the Proposer may wish to note that the FSSD’sPlan Approval and Fire Safety Certificate (FSC) will have to be obtained ifthere is any change in use or involving any alteration / addition works. TheProposer shall ensure that the existing premises, including existing layoutsand usages, have obtained the necessary Approvals from FSSD/SCDF.
(f) For lease extension, the Proposer is urged to engage their own QP inassisting them to obtain the FSSD’s Plan Approval and Fire Safety Certificate(basing on the prevailing Fire Code) if it is not done so for the entirebuildings/premises. The fire safety provisions and mitigation measures areessential for all buildings; it is particularly true for religious premises wherecongregation of general public is possible, and for premises with similar usageas Nursing Home & Childcare Centre where the occupants are vulnerable toemergency situations. (The premises/building owner, such as HDB, SLA and
ANNEX D
JTC etc shall engage the operator and see how to address the shared concerns before considering granting their lease extension application). (g) For applications of non-exclusive and limited religious use, the Proposer shall liaise directly with the building owner/management to ensure their proposed usage and number of occupants for that particular room /floor does not exceed the limit as originally designed & approved for. The Proposer shall also provide the full details to the building owner/management so that the Emergency Response Plan (ERP) can be updated accordingly. (h) For new road development (including road widening, realignment, road expunction & interim measures etc), it shall not affect or encroach upon any part of existing development compounds. For public fire hydrant, do liaise with PUB directly for any proposed relocation or erection of new fire hydrant. (i) For drainage system development (including widening, realignment, extension & interim measures etc), it shall not affect or encroach upon any part of existing development compounds.
2. Before making any commitment (purchase/occupation or rental/lease etc) or commencement of any proposal, the Proposer shall engage Qualified Person (QP) to carry out a feasibility study to ensure the entire premises and new proposals are able to comply with all the Fire Safety requirements (the current Fire Code & other relevant standards/guidelines/circulars). The feasibility study shall also ensure those existing fire safety provisions of surrounding developments are not affected. The QP will then assist them to obtain the FSSD's Plan Approval and the Fire Safety Certificate (FSC). If the Proposer has any doubts or queries regarding the fire safety requirements or plan approval procedures, he shall visit the FSSD at SCDF
Headquarters, 91 Ubi Ave 4, for a walk-in consultation.
3. For special projects including but are not limited to Chemical Plants, Petroleum Refineries and Buildings/Structures used for handling & storage of Highly Combustible Substances etc (e.g. for petrol station or CNG station, the 25m buffer zone shall be observed strictly), the Proposer and their QP shall provide the overall layout details to FSSD at SCDF Headquarters at 91 Ubi Ave 4, for further comments, as additional fire safety provisions and mitigation measures will be imposed. The Proposer and their QP may wish to consult LTC Han Fook Kuang (Email: [email protected] ) from the Fire Safety and Shelter Department (FSSD/ SCDF) for a consultation session.
GENERAL POLICE ADVISORIES
The proposer is encouraged to adopt the following measures where applicable as part of crime prevention;
Uses Recommended Measures
Farming activities e.g. urban
farming, ornamental fish
breeding, plant nursery, etc.
• The perimeter is to be adequately fencedup to prevent unauthorised access.
• CCTV surveillance cameras and alarmsto be installed at the entry/exit points andalong the perimeter fencing to detercrime.
• Adequate lightings and regular grasstrimmings to illuminate the compound andfacilitate surveillance.
ANNEX E
FINAL
TECHNICAL REQUIREMENTS FOR AGRICULTURAL DEVELOPMENTS WITHIN WATER CATCHMENT AREAS
1.0 GENERAL REQUIREMENTS
1.1 These general requirements are applicable to all types of agricultural developments indicated in Section 2.
1.2 If the development site abuts a watercourse (reservoir or storm drain), the developer/owner shall provide and maintain a vegetated buffer strip of minimum 2m width along the length of the boundary abutting the watercourse, within the farm development. The buffer strip can be part of the planting verge set by the National Parks Board (NParks).
1.3 There shall be no agricultural activities within the buffer strip.
1.4 Water pollution control requirements as stipulated in Environmental Protection and Management Act (EPMA) shall be fully complied with. The discharge from any agricultural sites into the drainage system shall comply with Allowable Limits for Trade Effluent Discharge to Controlled Watercourses under the EPMA (Trade Effluent) Regulations and PUB’s discharge water quality requirements of Total Nitrogen ≤ 10 mg/L; Total Phosphorus ≤ 0.65 mg/L and Total Suspended Solids ≤ 30 mg/L for water catchment areas.
1.5 The drains within the development site shall be regularly de-silted and maintained.
2.0 SPECIFIC REQUIREMENTS FOR VARIOUS AGRICULTURAL DEVELOPMENTS
2.1 Vegetable Farms
a. Best management practice (BMP) is to be adopted to prevent the discharge of nutrient-richwater into the watercourse/reservoir. Such BMP could be in the form of a cut-off drain beconstructed along the boundary of farming areas to channel all runoff with high nutrient(Nitrogen and Phosphorus) to a treatment pond (as illustrated in Diagram 1) which isdesigned to treat the pond water to meet the discharge water quality shown in Section 1.4.Alternative proposals designed and endorsed by a Qualified Person (QP) to meet thedischarge water quality requirements can be submitted for PUB’s approval.
b. A typical design of a treatment pond to treat the pond water before discharge into thestorm drain is shown in Diagram 2 for reference. The design of the treatment pond withsufficient size shall be endorsed by a QP. Some suggested wetland plants that can be usedat the treatment pond are shown in Table 1. Details on the construction of wetlands andvegetated swale can be found in the ABC Waters Design Guidelines athttps//www.pub.gov.sg/abcwaters/designguidelines.
c. Ponds shall be regularly de-sludged and the sludge shall be disposed off-site.
d. No raw animal waste shall be allowed for use as fertilizer in vegetable farming activities.
ANNEX F
e. All compost shall be fully composted before use and composting activities (if any) shall be carried out using proper composting facilities in roofed and curbed areas with impervious flooring such as concrete flooring to prevent feedstocks from leaching into the ground and entering the storm drain. All feedstocks for composting shall be stored in roofed and curbed areas with impervious flooring.
f. Only pesticides (including herbicides) registered with AVA are allowed to be used in the agricultural activities. Approved pesticides can be found in the AVA website, i.e. http://www.ava.gov.sg/explore-by-sections/plants/agricultural-pesticides/guidelines-for-pesticide-registration.
g. All pesticides (including herbicides) shall be used in accordance with the manufacturers' recommendations and guidelines.
h. No fertilizers, soil amendments and pesticides (including herbicides) shall be applied within 2m of storm drain or reservoir.
i. Proper storage and disposal measures shall be taken to prevent any fertilizers, soil amendments, pesticides (including herbicides), and plant waste from entering storm drain. They are to be stored in roofed/properly covered areas.
2.2 Animal Farms (except poultry and birds)
a. No hoofed animals are allowed in water catchment areas, as stipulated in the Cattle Act.
b. All animals shall be housed in roofed sheds.
c. All washing activities shall be carried out in covered/roofed areas with concrete flooring
and perimeter curbs to contain all used water which shall be discharged into a used water collection system.
d. All animal excreta (urine and feces) shall be promptly collected, removed and disposed off-site or treated according to an approved method by the authorities. If wastes are to be temporary stored within the farms awaiting disposal, they shall be stored under roof within a shed which is curbed up to contain the wastes.
e. On-site burial for animal carcasses is not allowed in the farm within water catchment areas, unless approved by the relevant authorities.
f. Frog tanks/ponds shall be properly and adequately designed to ensure no leakage into the storm drain.
g. Proper storage and disposal measures shall be taken to prevent any frog waste, dead frog and sludge, from entering the storm drain and reservoir.
2.3 Fish and Aquatic Plant Farms a. Fish ponds shall be properly and adequately designed to ensure no overflow and leakage
into the storm drain.
b. If seawater is used in the fish farming, no seawater shall be discharged into the public sewer and storm drain. All used seawater shall be properly collected and disposed off-site.
c. Proper storage and disposal measures shall be taken to prevent any fish waste, dead fish, and plant waste and sludge, from entering the storm drain and reservoir.
DIAGRAM 1
DIAGRAM 2
A TYPICAL CUT-OFF DRAIN AND TREATMENT POND FOR AGRICULTURAL RUNOFF MANAGEMENT
Plant species Water-treatment function
Papyrus reed / Egyptian Paper Plant
(Cyperus papyrus)
Reduces nitrogen and phosphorus and able
to accumulate copper, zinc and lead
Cattail (Typha angustifolia) Reduces nitrogen and phosphorus,
accumulates a range of heavy metals and
serves as habitat for a variety of animals
Blue Rush / Tube Sedge (Lepironia
articulata)
Reduces nitrogen and phosphorus and
accumulates lead
Dwarf Papyrus (Cyperus haspan var.
viviparus)
Able to absorb nitrogen and phosphorus
rapidly
Water Canna / Alligator Flag (Thalia
dealbata / Thalia geniculata)
Reduces nitrogen and phosphorus
Fragrant Pandan (Pandanus amaryllifolius) Reduces nitrogen and phosphorus
Pickerelweed (Pontederia cordata L.) Reduces nitrogen and phosphorus
Ricefield bulrush (Scirpus mucronatus) Reduces nitrogen and phosphorus
SEALED & RETURN TO OWNER ON SEP 2011
25P
25P STP
20P
50P MAINTAINED
BY WRN
MAINTAINED BY OWNER10P
5PWRN TAKEN OVER FOR MAINTAIN ON 20 JUN 2012
10PWRN TAKEN OVER FOR MAINTAIN ON 17 JUL 2012
MAINTAINED BY WRN
10P
20P STP
3226134
3226135
3226137
3371550
3371552
3371554
3371556
3371558
3371560
3371562
3371564
3371604
3371606
3371608
3226136
3226138
3226140
3371551
3371553
3371555
3371557
3371559
3371561
3371563
3371565
3371605
3371607
3371609
250
106
25092
500100
50035
500
34
500
121
500 63
500
120
500
120
50035
25083
25090
25069
BJ 817
STP (BJ828) - 54
STP (BJ832) - 25
STP (BJ844) - 33
STP - 117
STP - 145
STP - 111
STP - 148
STP (BJ799) - 45
HT - 27
MK12
-0178
0T
MK12-01776P
MK12-017
75V
MK12-01154A
MK12-01223V
MK12-01089W
MK12-01653M
MK12-01241PMK12-
01324M
MK12
-0157
6L
MK12-00912X
MK12-0
1651L
MK12
-0119
4M
MK12-00915MMK12-01216L
MK12-00913L
MK12-00914C
MK12-0
1314T
MK12-01083K
MK12-01217C MK12-01333K
MK12-01704N
MK12
-0104
0X
MK12-01777T
MK12-00917V MK12-00868XMK12-01589X
260
260
240
301
240
301
260
240
240
240
291
90
240
291
291
291
291
291
291
240
301
240
291
291
291
260
260
291
240
240
240
240
240240
240
260
301
260
291
291
291
291
291
291
291
240
291
291
291
291
240
240
260
260
60
321
321
321321
321
281281
321 321
301
321
281
281
301
281
321
321
321321
301
281
281
281
261
NEO TIEW CRESCENT
SCALESEWERAGE INTERPRETATION PLANTHE INFORMATION GIVEN ON THIS SEWERAGE INTERPRETATION PLAN FORMS THE BEST INFORMATION AVAILABLE ON THE DATE PRINTED AND IS LIABLE TO CHANGE WITHOUT NOTICEWHILST EVERY ENDEAVOR IS MADE TO ENSURE THAT THE INFORMATION PROVIDED IS CORRECT, THE PUBLIC UTILITIES BOARD DISCLAIMS ANY LIABILITY FOR ANY DAMAGE OR LOSSTHAT MAY BE CAUSED TO ANY PERSON DIRECTLY OR INDIRECTLY AS A RESULT OF ANY ERROR OR OMISSION.Caution:The information given is indicative only. The Applicant is advised to verify the information at the site.
LEGEND :(in A1 Size)
1:1,500EXISTING SEWERUNSURVEYED SEWERUNCOMMISSIONED SEWERDECOMMISSIONED SEWERPROPOSED SEWER
REHABILITATED SEWERABANDONED SEWERSEWER TO BE ABANDONED
EXISTING DRAINLINEPROPOSED DRAINLINE
NO CONNECTION TO THISSEWER IS ALLOWED
REXISTING PUMPING MAINDECOMMISSIONED PUMPING MAINPROPOSED PUMPING MAINABANDONED PUMPING MAINPUMPING MAIN TO BE ABANDONED
123456123456
EXISTING SLUDGE MAINABANDONED SLUDGE PUMPING MAINPROPOSED DTSS TUNNELEXISTING DTSS TUNNELIMMEDIATE DOWNSTREAM SEWER GIS IDMANHOLE GIS ID
Prepared By: ZAHIRUDINDate: 18/04/2018
ANNEX G
GENERAL REQUIREMENTS ON THE USE OF ON-SITE SEWERAGE SYSTEM
1. The Successful Tenderer/operator/owner shall provide the following details in his
submission for the proposed on-site sewerage system:
i. The exact type and details of activities that would be carried out at the
development site;
ii. The highest number of people expected to be at the site; and
iii. The volume, peak and average rate of used water discharge expected to be
received by the proposed holding tank/MBR-STP.
2. The Successful Tenderer/operator/owner shall ensure that the new on-site sewerage
system is designed and constructed with sufficient capacity to handle the used water
generated at the site. The Successful Tenderer/operator/owner shall undertake
expansion of the new on-site sewerage system if the existing capacity is found
inadequate, or as and when required by PUB.
3. The proposed on-site sewerage system shall be constructed next to the lot boundary
abutting the public road to enable flow diversion to the sewer when it is available in
future.
4. The holding tank/MBR-STP shall be installed with high water level alarms and beacon
light to provide warning in the case of high levels of used water and significant risk of
overflow. The high water level alarm shall be set at a level which allows a minimum of
two hours of reaction time for the senior staff of the company to take preventive actions.
5. The alarm system shall also be programmed to alert, via SMS, at least two senior
management level officers appointed by the Successful Tenderer/operator/owner to
take immediate preventive actions. The Successful Tenderer/operator/owner shall
provide the names/mobile phone numbers of the two senior staff responsible for
receiving the SMS notification to PUB before the sewerage system is operational.
6. The Successful Tenderer/operator/owner shall divert the used water discharge from
the site to the public sewer when this is made available near the site. The Successful
Tenderer/operator/owner shall bear the cost of the flow diversion, including the
construction of internal drain lines, sewer and other sewerage facilities necessary to
effect the diversion of flow. The Successful Tenderer/operator/owner shall also
demolish all the disused on-site sewerage systems and sewerage facilities after the
flow diversion.
7. All sewerage infrastructure provided by the Successful Tenderer/operator/owner shall
be demolished when they no longer serve any purpose. However, the Successful
Tenderer/operator/owner shall consult PUB on the extent of sewerage infrastructure
that would have to be demolished before proceeding with the demolition works. The
Successful Tenderer/operator/owner shall inform PUB upon completion of the
demolition works.
ANNEX H
8. In accordance with Clause 11.2.8 of the Singapore Standard SS 593:2013- Code of
Practice on Pollution Control (administered by NEA), animal wastes and sludge
generated from wastewater treatment shall be stabilised, dewatered and disposed of
as solid waste. Therefore, animal wastes/horse wastes/chicken wastes shall not be
discharged to the on-site sewerage system.
9. In accordance with Clause 11.2.7 of the Singapore Standard SS 593:2013- Code of
Practice on Pollution Control (administered by NEA), sludge (if it is an aquaculture
farm), if generated, shall be stabilized, dewatered and disposed of as solid waste.
10. Used water from the washing of premises shall be free of plant/fish waste/matter or
other materials before it is allowed to be discharged into the on-site sewerage system.
11. Surface runoff or rainwater shall not be allowed to be discharged into the on-site
sewerage system.
12. The Successful Tenderer/operator/owner shall inform PUB of any intention to change
the type of activities that may lead to higher used water discharge, resulting in the need
to upgrade or expand the on-site sewerage system, prior to undertaking it.
13. The Successful Tenderer/operator/owner shall construct and demolish the approved
on-site sewerage system in compliance with the standard requirements.
ADDITIONAL REQUIREMENTS IF HOLDING TANK IS USED
a) The Successful Tenderer/operator/owner shall ensure that the holding tank is
designed/installed and constructed with an adequate capacity to store used water
generated on-site at all times.
b) The Successful Tenderer/operator/owner shall provide proper vehicular access for
tankers to get near/next to the holding tanks so that used water could be pumped to
the tankers.
c) The holding tank shall have a capacity to hold the used water from the development
site for at least 1 week;
d) The Successful Tenderer/operator/owner/operator shall expand the capacity, when
required by PUB, to meet the above requirement if the discharge from the development
is found higher than it was estimated or designed for.
ADDITIONAL REQUIREMENTS IF MBR-STP IS USED
a) The effluent discharge from the MBR-STP shall comply with the following requirements: i. The Biochemical Oxygen Demand (BOD) shall not exceed 20 milligrams per litre. ii. The Total Suspended Soils (TSS) shall not exceed 30 milligrams per litre.
iii. C&W’s and/or NEA’s requirements. The successful tender/operator/developer is advised to consult these two agencies for requirements before making his tender submission.
b) The MBR-STP shall be designed to serve the intended use of the proposed development.
The Successful Tenderer/operator/owner shall be responsible for upgrading the capacity
of the MBR-STP if there are plans to expand the development and/or change the intended
use of the proposed development that the MBR-STP is designed for.
c) The MBR-STP shall be designed with sufficient capacity buffer to be able to treat the
influent at 2 times the average flow rate to cope with unforeseeably high sewage/trade
effluent discharge during peak flow periods. The design of the MBR-STP shall be
submitted to PUB for approval prior to implementation.
d) PUB will carry out regular effluent sampling for the MBR-STP. The Successful
Tenderer/operator/owner/operator shall be responsible for the upgrade/expansion of the
MBR-STP when directed by PUB if the effluent discharge quality does not comply with the
standards specified by PUB or NEA.
e) The Successful Tenderer/operator/owner shall allow unimpeded access to PUB officers
into the proposed development site for sampling of the MBR-STP.
f) The MBR-STP shall be equipped with sensors, alarms and instruments to alert the
operator and maintenance team of the plant’s performance.
g) The proposed MBR-STP should be sited as far away as possible from
dormitory/residences. The proposed MBR-STP should also be shielded from
view. Vehicular access to the proposed MBR-STP should be provided to facilitate the
clearing of sludge from the plant.
h) Where treated trade effluent has to be discharged to the on-site sewerage system (which
is meant for treating domestic used water), the MBR-STP shall be designed and
constructed so that it is capable of producing effluent quality that complies with the
discharge requirements stipulated by NEA and PUB.
i) If NEA approves the use of MBR-STP, it may require the effluent to be disinfected among
other requirements.
j) The owner shall engage only NEA-licensed wastewater collector to regularly maintain/de-
sludge the MBR-STP and ensure that it produces treated effluent of compliant quality at
all times. The owner shall keep the MBR-STP maintenance records and produce them for
checking as and when required by PUB. In addition, the clearing of the sludge and
maintenance of the plant should be carried out only at times likely to cause the least
nuisance and inconvenience.
k) The owner shall engage an accredited laboratory to collect and analyse the MBR-STP’s treated effluent monthly. The owner shall maintain the sampling results for PUB’s inspection as and when required.
)
)
)
))
)
)
)
)
)
(
(
(
(
A
A
A
AA
(
(
(
e
e
e
e
3226134
3371556
3371558
3371560
3371562
3371564
3371604
3371606
3371608
3226136
3371557
3371559
3371561
3371563
3371565
3371605
3371607
3371609
50
063
50
012
0
500
120
500
35
25
0
83
25
0
90
25069
STP - 145
STP - 148
STP - 117
STP (BJ799) - 45
STP (BJ832) - 25
MK12-01154A
MK12-01776P
MK
12
-01
24
1P
MK12-01653M
MK
12
-01
78
0T
MK
12-0
1194M
MK
12-0
1775V
MK12-01651L
MK12-0
1223V
MK12-01576L
MK
12
-0132
4M
MK12-00913L
Plot No.
POINT OF
CONNECTION TO
MANHOLE (ID)
LCK 114A 3371558
LCK 114B 3371606
LCK 114A
LCK 114B
ANNEX I(i)
)
)
)
))
)
)
)
)
)
))
))
)
)
)
)
(
(
(
(
A
A
A
AA
(
(
(
e
e
e
3371556
3371558
3371560
3371562
3371564
3371604
3371606
3371608
3371557
3371559
3371561
3371563
3371565
3371605
3371607
3371609
50
063
50
012
0
500
120
500
35
25
0
83
25
0
90
25069
STP - 145
STP - 148
STP - 117
STP (BJ799) - 45
STP (BJ832) - 25
MK12-01154A
MK12-01776P
MK
12
-01
78
0T
MK12
-017
75V
MK
12
-01
241P
MK
12-0
1194M
MK12-01653M
MK12-01651L
MK
12
-013
24M
MK12-01223V
MK12-01576L
Plot No.
POINT OF
CONNECTION TO
MANHOLE (ID)
LCK 114C 3371560
LCK 114D 3371564
LCK 114C
LCK 114D
ANNEX I(ii)
40 Scotts Road #10-01 Environment Building Singapore 228231. Republic of Singapore Website: www.pub.gov.sg
PREVENTION OF DAMAGE TO PUB WATERMAIN
General
1. We would like to draw your attention to Section 57 of the Public Utilities Act whichstipulates a duty to enquire on water mains if any person wishes to carry out any work inthe vicinity of watermains. We wish to highlight that under Section 47A of the PublicUtilities Act, any person who, whether wilfully or otherwise, removes, destroys or damagesor causes or permits to be removed, destroyed or damaged, any watermains belonging toor under the management or control of the Board, shall be guilty of an offence and shall beliable on conviction to a fine not exceeding $40,000 or to imprisonment for a term notexceeding 3 months or to both; or if the watermains is 300mm or more in diameter, to afine not exceeding $200,000 or to imprisonment for a term not exceeding 3 years or toboth. For more information of the Public Utilities Act, please refer tohttp://statutes.agc.gov.sg/.
2. Before commencing any works in the vicinity of PUB watermains, the QP shallobtain Water Service Plan (WSP) which indicates the approximate position of thewatermains (i.e.potable water, NEWater, industrial water and raw water mains) in thevicinity of the development. Smaller submains and connection pipes (<100 mm diameter)to customers' premises/properties may not be included in the WSP. The QP is to determineand indicate the exact alignments and depths of the watermains, submains and connections,on site by means of trial holes using manual excavation especially near watermains beforecommencement of any work. The position and alignment of the watermains shall beindicated on the survey plan, and shown at site to allow easy identification of thewatermains in future after completion.
3. The QP shall design both the temporary and permanent works in such a way to ensurethat ground movements are kept to an absolute minimum. The employment of proven
techniques and good workmanship are important to minimize ground loss and in turnground movements.
4. The QP shall select and ensure the operation of construction equipment shall be in amanner such that vibration induced damage to the watermains is prevented.
5. The QP shall establish and inform PUB of the procedures and methods for allexcavation and other construction works within 10 meters radius of watermains to preventdamage to the watermains during the work.
6. Before commencement of works, the QP shall submit the detailed method statementand drawings for the construction works, details of the machinery/equipment used withanalyses / assessment to demonstrate that the construction method proposed is non-invasiveand will not cause any impact or damage to the watermains.
7. Equipment Vibrations - Construction activities such as piling, excavation, soilimprovement, diaphragm wall and retaining wall construction etc and the use of constructionequipment such as piling/boring machine etc shall not subject the watermains to a peak particle velocity (PPV) exceeding 15mm/s at any frequency. The QP shall provide a detailed impact assessment that clearly demonstrates the vibration attenuation for each of the equipment
ANNEX J
40 Scotts Road #10-01 Environment Building Singapore 228231. Republic of Singapore Website: www.pub.gov.sg
proposed to be used at the development site and in similar ground conditions to show that this vibration limit would not be exceeded on the existing watermains. 8. Ground Displacements - Ground displacements caused by construction or other activities shall be “zero”. If the QP's analysis shows that the ground displacement due to the construction or other activities exceeds “zero”, a further design check shall be undertaken to ensure that the construction or other activities will not induce any damage to the watermains. 9. Groundwater Drawdown - The groundwater drawdown shall not exceed 10 kPa in the vicinity of the watermains. 10. No heavy machinery or vehicles shall be located or driven over watermains. 11. Construction Impact Assessment Report (CIAR) - The QP shall carry out a construction impact assessment of the construction effects of the works on the watermains in the vicinity of the works and submit the report to PUB for records. The report shall include the following details:
(i) The ground conditions, geotechnical profiles and relevant borehole logs.
(ii) The proposed construction equipment and methods, and sequencing of construction.
(iii) Assessments on the use of the proposed construction equipment /methodology on
the existing watermains, vibrations, ground displacements and groundwater draw downs and how the impacts would be mitigated to meet requirements.
(iv) Vibration characteristics and attenuation for major construction
equipment/methodology.
(v) Instrumentation and monitoring proposals.
(vi) The damage potential and risks to the watermains.
(vii) Preventative and precautionary measures to protect the watermains from damage and remedial measures to be taken in the event of damage/incidents.
12. The QP shall advise PUB on the assessed probable risk and level of damage to the watermains and his/her proposed mitigating measures for preventing the watermains and watermains’ structures from damage to the satisfaction of PUB. 13. No heavy machinery or vehicles shall be located or driven over watermains.
40 Scotts Road #10-01 Environment Building Singapore 228231. Republic of Singapore Website: www.pub.gov.sg
Instrumentation and Monitoring Programme
14. The QP shall carry out an instrumentation and monitoring programme to monitor the surface and subsurface ground movements, vibrations, the variation of ground water table and pore pressures, and the displacement and distortion of watermains. 15. The QP shall include in the monitoring plan all watermains that in his/her view are likely to be affected by the works. 16. The QP shall submit full details of the proposed monitoring procedures and instrumentation to PUB for concurrence before commencing the works. 17. The QP’s method statement shall include the proposed monitoring intervals and all requirements imposed by PUB. 18. The QP shall review the safe limits of ground movements, vibration levels or other changes for ensuring the structural integrity and proper functioning of all watermains. The QP is to provide PUB with the new alert level and stop work level for each of the monitoring instrumentations that will be deployed at site. He/she shall provide comprehensive basis for the proposed safe limits. 19. The QP shall provide a recharge well at site to maintain existing ground water table so as to prevent ground subsidence. The QP is to provide the proposal for the recharge well, with the technical drawing and calculation, to PUB for approval. 20. The QP shall verify and certify by monitoring that construction works have not resulted in displacements or vibration levels that have or will cause damage to any watermains. As a minimum, the following are required to be carried out and the relevant details are to be submitted to PUB:
(i) Monitoring of the displacements or vibration levels of watermains or the adjacent ground from the construction works. (ii) Preparation of action plans for remedial action in the event that displacements or vibration levels exceed the design limitations or cause damage.
21. It shall be clearly understood that the submissions of the instrumentation monitoring results and reports to PUB are only for PUB’s information. The QP shall be fully responsible for the analysis and interpretation of all the readings and measurements and for taking all remedial measures where necessary. When abnormal readings or measurements are obtained, QP shall immediately investigate the causes of the abnormalities and take all necessary remedial measures. QP shall promptly inform PUB should such abnormalities be likely to affect the structural integrity of the watermains 22. Instrumentation monitoring regime consists of inclinometers, ground settlement markers, vibration meters, piezometers, strain gauges, rod extensometers, etc. shall be carried out by QP to check whether ground movements & vibration impacts are within allowable limits during the construction works. Records of the instrumentation monitoring regime shall be endorsed by the QP and properly maintained at the site, submitted to PUB or made available for inspection by PUB upon request.
40 Scotts Road #10-01 Environment Building Singapore 228231. Republic of Singapore Website: www.pub.gov.sg
23. QP shall monitor and review the instrumentation monitoring results twice daily during the construction work on each day. QP shall look out particularly for excessive ground movements that may cause damage to the watermains. The QP shall submit the instrumentation monitoring records to PUB at a frequency stipulated by PUB. QP shall highlight in his submission if there are any excessive ground movements monitored or any other abnormalities. 24. QP shall stop the works immediately if the instrumentation monitoring results exceed the allowable limits and inform PUB immediately before investigating whether the works have any impacts on the watermains. The QP shall submit his/her assessment of the impacts of the works on the watermains, including his proposed mitigating measures to address the excessive ground movement or any other abnormalities, to PUB for approval, before resuming the works. 25. It shall be clearly understood that the submissions of the instrumentation monitoring results and reports to PUB are only for PUB’s information. The QP shall be fully responsible for the analysis and interpretation of all the readings and measurements and for taking all remedial measures where necessary. When abnormal readings or measurements are obtained, QP shall immediately investigate the causes of the abnormalities and take all necessary remedial measures. QP shall promptly inform PUB should such abnormalities be likely to affect the structural integrity of the watermains Surveillance Cameras above Large Diameter Watermains (≥ 300mm Diameter)
26. Contractor shall provide web-based IP surveillance cameras to continuously monitor construction activities in the vicinity of the large diameter (≥ 300mm) watermains. The number of cameras to be provided shall be approved by PUB and shall be sufficient to cover at least 6 meters from the watermains. 27. The surveillance cameras must be able to capture still pictures and perform continuous video recording. 28. The contractor shall provide PUB with the Internet website address for centralized viewing of the still pictures and video recordings of the construction activities above PUB watermains captured by the surveillance cameras. 29. For any enquiries, please consult Mr Lau Khai Keong/Shahrudin/ Kua Cheng Chuan/Tay Eng Pin at DID: 68852542/ 68852473/ 63809893/ 63809804 or Email: [email protected]/[email protected]/ [email protected]/ [email protected] .