saimm pta branch 8 september 2011.ppt · phase 3 – implementation phase • project execution...
TRANSCRIPT
SAIMM Pretoria Branch 8 September 2011Implementation of an Alternative Matte Level Measurement Solution at Lonmin Marikana Smelter Division for Improved Process Monitoring
8 Sept 2011
Presentation :Trevor GoffSenior process Engineer – Hot SectionProcess Division - SmelterLonmin
Presentation overview
√ Introduction√ History√ Burning Platform√ Current type of controls√ Alternative matte level solution phases√ Trial results√ Conclusions√ Current status and results
2
Introduction
• Hatch design
• Three electrodes 27.5MW circular furnace with waffle (copper) coolers
• Dried filter cake fed to the furnace
• Electrical energy supplied to furnace to melt the concentrate
• As concentrate melts, slag and matte phase is formed
• PGM reports with Base Metal sulphides to furnace matte phase
• Settles to bottom of furnace via gravity separation, with the slag on top (lower density)
• Black top condition (unreacted concentrate material)
• Matte, slag and concentrate levels measured using mechanized sounding bar
Mechanized sounding bar
CONTROL
PANEL
RAISE
BUTTON
LOWER
BUTTON
EMERGENC
Y STOP
BUTTON
ELECTRIC
MOTOR AND
CABLE REEL
STEEL
CABLE
SOUNDING
BAR
Burning Platform
5
• Furnace design 170mm • Copper - watercooling elements and superheated matte• Accuracy method• Incidents – ICAM identified seek alternative
What was our situation?
“If you know what the matte level is,
you can CONTROL it”
History
• 2004 Dip tests conducted using magnetic sensor technology
• Results were encouraging, but further development was necessary
• Not much development after 2004
• 2008 Google search engine and came across Agellis
• Started teleconferences, meetings and e-mails
Current Type of Controls/measurement
• Manual sounding • following procedure• skill of the operators• interpretation
Hence, the need for an alternative sounding measurement method
• Matte Level Predictor (MLP)
• Slagging
Alternative matte level solution phase
Agellis 2008
Different options
Decide on one
Phase 2Conceptualization
Phase 1Initial improvement
Phase 3Implementation/Trial
Phase 4Concept Operation
Paint
Al wire
MLP
Enhancements to system
More case studies
Hand over to Operations
Trial date was set
Set up success criteria
Installation of equipment
9
Who is Agellis?• Swedish Company Agellis Group – measurement solutions
• ELIM 3 – molten measurement systems, foaming systems
• Double probe - Temperature, bottom build-up, metal (150 systems)
• Electromagnetic sensor – detects conductivity
• Interested new technology Agellis EMLI ELP
• Principle of measurement is the effect of the presence of conductive materials on an electromagnetic field
• By applying an electromagnetic signal of a particular frequency to a sensor coil embedded in a protected lance probe, it is possible to monitor the effect that occurs when it reaches the highly metallic matte in a furnace
• Sensor optimized to detect only very metal rich materials
Phase 2 – Concept/ Options available
• Dual lance carriage system
• Temperature, build-up, sampling of matte/slag ●●●● Complex and cost●●●● New technology – not proven yet in Sulphide smelting
Option 1
• Lance completed with a sensor probe
• Draw wire - part of the measurement system ●●●● ELP has its own winch and furnace access port●●●● Only matte detection●●●● Length of lance – same as manual sounding lance●●●● Electromagnetic sensor installed in lance tip●●●● High temperature cable connected the EM sensor ●●●● Winch capable of a steady 15m/min. ●●●● In all other respects, the lance was operated in the same way as a traditional sounding bar.
Phase 2 – Concept Phase
Option 2
Decided on Option 2
● 3 day plant trial to be conducted
• No safety incidents or injuries
• No operational downtime
• Clear conductivity changes between slag and matte
• 10 (ten) consecutive measurements (dips)
• A correlation of all sensor measurements
vs manual sounding measurement
Phase 3 – Implementation Phase
Success criteria
☑☑☑☑
☑☑☑☑
☑☑☑☑
☑☑☑☑
☑☑☑☑
☑☑☑☑
Phase 3 – Implementation Phase
• Project execution phase
• meetings between different engineering disciplines and interaction
• Mechanical - type of material, size of motor, placement of motor and all auxiliaries, where to fit the draw wire, etc
• Electrical - do we need to pull extra cables, MCC capacity, size and speed of motor (Volts), lead time, where to put management box, cables for new pushbuttons, etc
• Instrumentation - hardware requirements, installation of UTP cables, view computer, etc
• Other requirements - hole in roof and in upper floor, correct drawings, etc
Safety was the biggest vehicle
Phase 3 – Final installation
Phase 3 – Final installationWinch Floor Roof floor
Phase 3 – Final installation
Phase 3 – Final installation
Phase 3 – ImplementationWhat did the sensor see?
detection threshold of 101% was used – 1%Rule
19
What was the matte level?
Phase 3 – Day 1 trial
Dip 2
Total of 12 dips conducted- repeatability and precision
Matte level variance within reasonable limits ±10mm
Levelmatte = Depthvirtual + Furnace0 - Entrymatte
Phase 3 – Day 2 Case study
Dip no Time matte level Comments
mm
09:00 250 manual sounding
14 09:05 332
15 09:13 321
16 09:46 301 Matte tap @ 9H31
17 09:48 304 Matte tap @ 10H03
11:00 240 Matte tap @ 11H03
18 12:14 283
19 12:20 283 Matte tap @ 12H38
13H00 250 manual sounding
20 13:09 260
21 13:22 254
How does the matte level varies with changes in Process conditions?
Phase 3 – Day 2 Case study
Agellis showed variances as per process changes (more sensitive)
Manual sounding measurements did not change
Measured Matte Levels
200
220
240
260
280
300
320
340
08:00 09:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00
Time
Matt
e L
ev
el (m
m)
2010-10-13 Matte tap
Phase 3 – Day 3 Power off● Total of 5 dips conducted with Power off
● No effect on measurement accuracy
● Measurements were consistent with the sounding bar measurements
●●●● Agellis ELP showed variances with process changes
Phase 3 - Key learning's from trial
23
Negatives●●●● Slag cracking – lance too light●●●● No build-up detection - bottom readings are unreliable●●●● Rate of descend of winch – fixed speed and thermal exposure of sensor
Positives●●●● Good matte signal●●●● Teamwork constituted to the success (Eng/Elect/Instr)●●●● Customer requirement (no effect on operations)●●●● Better understanding of matte production over time
To sum up
24
●●●● The measurement results attained during the trial period were consistent, reliableand accurate●●●● The Agellis trial was deemed successful as all criteria for the trial have been met●●●● Agellis ELP – can be used as an alternative for matte level measurement
Phase 4 – R/D to Operational
25
• Matte level output required for process monitoring – software acquired
Enhancements to system
More dips during training of shifts
Date time matte level comments
mm
10-Aug 15H00 240 manual sounding
16H46 232 agellis
17H00 250 manual sounding
246 agellis
17H38 tapped and slagged
12-Aug 13h00 270 manual sounding
283 agellis
13H33 matte tapped
260 agellis
270 manual sounding
16-Aug 11H00 210 manual sounding
226 agellis
slagging whole morning
Handing over to Operations - End of November 2011
Thank You!
Smelting is an ancient art but is becoming a recent science