saganding, norhanie water hya-crafts for environmental justice
TRANSCRIPT
Template
WATER HYA-CRAFTS WATER HYA-CRAFTS FOR ENVIRONMENTAL FOR ENVIRONMENTAL JUSTICEJUSTICE
NORHANIE M. SAGANDING
Template
INTRODUCTIONINTRODUCTION
Project Title: WATER HYA-CRAFTS FOR ENVIRONMENTAL JUSTICE
Problem Statement:
Aside from being one of the conflict-affected areas in the municipality of Aleosan,Barangay Dungguan is also located near the marsh and the water hyacinth clogs the water which makes it more prone to flooding that affects the suitability of the soil for planting crops like corn and rice. These lead them to engage themselves in “kaingin” as one of the source of their income.
Community Needs:
• Alternative source of income instead of “kaingin”.
Objectives: • To promote environmental awareness among the residents of Barangay Dungguan and these would lead them to understand environmental justice.
• To involve youth, and the adults(farmers,women)in promoting environmental justice.
• To assist the residents in providing an alternative source of income instead of “kaingin”.This will became a new way to increase and develop their economic status.
Template
Solution statement The water hyacinth from the marsh will be harvested so that it won’t clog the water. The harvested water hyacinth will be used as raw materials for making handicrafts that would eventually lead them to stop the “kaingin” system
Output The residents will undergo a training, and their will be weekly and monthly checking of the project.
Outcome The environmental awareness of the residents of the said Barangay will be raised as well as their economic status.
Template
LESSONSLESSONS
Learned from: Prof. Kendall Thu’s lecture on Environmental Justice
Specifically about? Sustainability and Environmental justice
How applied in your project?
Using water hyacinth as raw materials for handicrafts is intended for the economic development as well as well as to sustain their daily needs in terms of finances.
How innovative is your project?
Removing the water hyacinth from the marsh is not only for avoiding the clogging but also to ensure the economic development of the residents of the said Barangay.
TemplatePRE-PROGRAM ACTION PLANPRE-PROGRAM ACTION PLAN
Tasks Lead Person Support Persons When When (Deadline)
Coordinating/Meeting with the partner organization
Norhanie Saganding
Bai Saganding May 18,2014 May 18,2014
Lobbying/Presentation of the project proposal to the community(may include some important lectures about environmental justice)
Norhanie Saganding
MYPEACE Members
May 20,2014 May 20,2014
Coordinating with the resource person.
Norhanie Saganding
Bai Saganding 3rd week of May,2014
May 26,2014
Planning for the activities on the actual day of implementation
Norhanie Saganding
Bai Saganding,
MYPEACE
May 22,2014 May 22,2014
TemplatePROGRAM ACTION PLANPROGRAM ACTION PLAN
Tasks Lead Person Support Persons When When (Deadline)
Lobbying/Presentation of the project proposal to the community(includes some important lectures about environmental justice)
Norhanie Saganding MYPEACE Members May 20,2014 May 21,2014
Removing/harvesting of the water hyacinth from the marsh
Norhanie Saganding MYPEACE Members
May 28,2014 May 29,2014
Training for making the handicrafts(actual day of program)
Norhanie Saganding
Resource person
MYPEACE Members June 06-07,2014 June 06-07,2014
Weekly checking of the project(for the first month,monthly cheking for the following months)
Norhanie Saganding Mypeace Dunguan From June 14,2014 Continuos
Final evaluation Norhanie Saganding Bai Saganding
MYPEACE
August 02,2014 August 03,2014
TemplateACTUAL DAY(June 06-07,2014)ACTUAL DAY(June 06-07,2014)
Activities Time Lead PersonSupport Persons
Arrive Brgy. Dungguan 8:30-9:00 AM
Welcome 9:00-9:15 AM Brgy.Chairman
Program introduction and overview/statement of purpose
9:15-9:30 AM
Introduction of the resource person
9:30 AM Norhanie Saganding
Actual training 9:40 AM
Lunch 12 – 1 PM
Continuation of the training 1-3:00 PM
*continuation of the training(June 07,2014)
Template
POST-PROGRAM ACTION PLANPOST-PROGRAM ACTION PLAN
Tasks Lead Person Support Persons When When (Deadline)
Maintainance of the project(weekly, for the first month, monthly checking for the following months)
Norhanie Saganding
MYPEACE DUNGGUAN
From June 1 continous
Final evaluation
Norhanie Saganding
Bai Saganding
MYPEACE Members
August 02,2014 August 03,2014
BUDGETBUDGETItem Cost/ Unit
Number of Persons
Subtotal
Certificates 5 30 Php150.00
Token 100 1 Php100.00
Refund for fare 50 8 Php400.00
Total: Php650.00
Template
How do you ensure How do you ensure sustainability?sustainability?
Using the water hyacinth as the raw materials for making handicrafts would ensure the sustainability of the project. First, it would promote economic development; and it would also promote environmental awareness which leads to environmental justice.