Saffo Contractors. Clinton Overpasses Clinton, NC 2007. Project Overview. This project called for abrasive blasting and painting of the steel beams supporting the overpasses on 7 stretches of US Highway 421 outside of Clinton. . Services Performed. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Saffo Contractors](https://reader036.vdocuments.us/reader036/viewer/2022062305/5681668e550346895dda6103/html5/thumbnails/1.jpg)
Saffo Contractors
Clinton OverpassesClinton, NC
2007
![Page 2: Saffo Contractors](https://reader036.vdocuments.us/reader036/viewer/2022062305/5681668e550346895dda6103/html5/thumbnails/2.jpg)
![Page 3: Saffo Contractors](https://reader036.vdocuments.us/reader036/viewer/2022062305/5681668e550346895dda6103/html5/thumbnails/3.jpg)
Project Overview
This project called for abrasive blasting and painting of the steel beams supporting the overpasses on 7 stretches of US Highway 421 outside of Clinton.
![Page 4: Saffo Contractors](https://reader036.vdocuments.us/reader036/viewer/2022062305/5681668e550346895dda6103/html5/thumbnails/4.jpg)
For this project, all steel beams on the overpasses in the area around Clinton, NC were abrasive blasted using a grit recycling system and painted. Saffo was responsible for adhering to all DOT specifications for traffic control and monitoring. During two phases of the project, traffic had to be diverted from the main intersection of the town for the duration of the weekend in order to complete all work.
Services Performed
![Page 5: Saffo Contractors](https://reader036.vdocuments.us/reader036/viewer/2022062305/5681668e550346895dda6103/html5/thumbnails/5.jpg)
ARS Recycling machine, Saffo Box Truck, & IR Dust Collector positioned next to contained overpass
Equipment Placement
![Page 6: Saffo Contractors](https://reader036.vdocuments.us/reader036/viewer/2022062305/5681668e550346895dda6103/html5/thumbnails/6.jpg)
Saffo was responsible for setting up lane closures, detours, and signal trucks to reroute traffic while work was being completed.
Traffic Control
![Page 7: Saffo Contractors](https://reader036.vdocuments.us/reader036/viewer/2022062305/5681668e550346895dda6103/html5/thumbnails/7.jpg)
The main intersection of Clinton has two overpasses that required blasting and painting work. The work was done in two consecutive weekends, and in a manner
so that traffic was still permitted to pass through under a lane closure.
Phase One of Intersection Work
![Page 8: Saffo Contractors](https://reader036.vdocuments.us/reader036/viewer/2022062305/5681668e550346895dda6103/html5/thumbnails/8.jpg)
Intersection Phase One containment from an alternate angle, with traffic uninhibited.
Containment
![Page 9: Saffo Contractors](https://reader036.vdocuments.us/reader036/viewer/2022062305/5681668e550346895dda6103/html5/thumbnails/9.jpg)
Much of the blast work was done by night so as to maintain proper temperature conditions for painting.
Overpass Two Containment
![Page 10: Saffo Contractors](https://reader036.vdocuments.us/reader036/viewer/2022062305/5681668e550346895dda6103/html5/thumbnails/10.jpg)
ARS Dust Collector in place on overpass three.Containment Three
![Page 11: Saffo Contractors](https://reader036.vdocuments.us/reader036/viewer/2022062305/5681668e550346895dda6103/html5/thumbnails/11.jpg)
Saffo Contractors