safe work method statement - clifford...

13
SAFE WORK METHOD STATEMENT Clifford Constructions P/L Phone: 02 9482 7288 SWMS No.________ 8/35 Leighton Place Fax: 02 9482 7037 Hornsby NSW 2077 Email: [email protected] Revision: 1 SWI011.01 Approval Date:04/06/2014 Page 1 of 13 ORGANISATION DETAILS Organisation Name: Clifford Constructions P/L Contact Name: ACN/ABN 96 054 514 859 Contact Position: Address: 8/35 Leighton Place, Hornsby NSW 2077 Contact Phone No: PROJECT DETAILS: Project: Address: Activity: This SWMS has been developed in consultation with:________________________Date:____________ This SWMS has been approved by:_______________________________________Date:____________ Resources/Trades Involved: Plant & Equipment Used: Frequency of Testing: Materials Used: Hazardous Substances Used: Method of Consultation & Communication: This SWMS is read and signed by all workers involved with this procedure. If changes occur, they will be noted on the amendments page (last page). The changes be conveyed to the workers and they will sign off that they have read and understood those changes. Process & frequency of reviews: This SWMS must be reviewed on a job by job basis, or before, if any changes to work environment occur.

Upload: hoangliem

Post on 10-Mar-2018

282 views

Category:

Documents


15 download

TRANSCRIPT

Page 1: SAFE WORK METHOD STATEMENT - Clifford Constructionscliffordconstructions.com.au/wp-content/uploads/2013/07/SWI011.01... · works: SAFE WORK METHOD STATEMENT ... permanent disability

SAFE WORK METHOD STATEMENT

Clifford Constructions P/L Phone: 02 9482 7288 SWMS No.________

8/35 Leighton Place Fax: 02 9482 7037

Hornsby NSW 2077 Email: [email protected]

Revision: 1

SWI011.01

Approval Date:04/06/2014 Page 1 of 13

ORGANISATION DETAILS

Organisation Name: Clifford Constructions P/L Contact Name:

ACN/ABN 96 054 514 859 Contact Position:

Address: 8/35 Leighton Place, Hornsby NSW 2077 Contact Phone No:

PROJECT DETAILS:

Project: Address:

Activity:

This SWMS has been developed in consultation with:________________________Date:____________

This SWMS has been approved by:_______________________________________Date:____________

Resources/Trades Involved:

Plant & Equipment Used:

Frequency of Testing:

Materials Used:

Hazardous Substances Used:

Method of Consultation &

Communication:

This SWMS is read and signed by all workers involved with this procedure. If changes occur, they will be noted on the amendments page (last

page). The changes be conveyed to the workers and they will sign off that they have read and understood those changes.

Process & frequency of

reviews: This SWMS must be reviewed on a job by job basis, or before, if any changes to work environment occur.

Page 2: SAFE WORK METHOD STATEMENT - Clifford Constructionscliffordconstructions.com.au/wp-content/uploads/2013/07/SWI011.01... · works: SAFE WORK METHOD STATEMENT ... permanent disability

SAFE WORK METHOD STATEMENT

Clifford Constructions P/L Phone: 02 9482 7288 SWMS No.________

8/35 Leighton Place Fax: 02 9482 7037

Hornsby NSW 2077 Email: [email protected]

Revision: 1

SWI011.01

Approval Date:04/06/2014 Page 2 of 13

PPE required:

WHS Legislation: WHS Act 2011

WHS Regulations 2011

Codes and/or Standards applicable to the

works:

Page 3: SAFE WORK METHOD STATEMENT - Clifford Constructionscliffordconstructions.com.au/wp-content/uploads/2013/07/SWI011.01... · works: SAFE WORK METHOD STATEMENT ... permanent disability

SAFE WORK METHOD STATEMENT

Clifford Constructions P/L Phone: 02 9482 7288 SWMS No.________

8/35 Leighton Place Fax: 02 9482 7037

Hornsby NSW 2077 Email: [email protected]

Revision: 1

SWI011.01

Approval Date:04/06/2014 Page 3 of 13

RISK MATRIX

Level Description of Consequence or Impact Consequence

Likelihood/Probability

L

Likely

M

Moderate

U

Unlikely

H (1)

(High Level of Harm)

Potential death, permanent disability or major structural failure/damage.

Off-site environmental discharge/release not contained and significant

long-term environmental harm.

H (1)

High 1 1 2

M (2)

(Medium Level of Harm)

Potential temporary disability or minor structural failure/damage. On-site

environmental discharge/release contained, minor remediation required,

short-term environmental harm.

M (2)

(Medium) 1 2 3

L (3)

(Low Level of Harm)

Incident that has the potential to cause persons to require first aid On-site

environmental discharge/release immediately contained, minor level clean

up with no short-term environmental harm.

L (3)

(Low) 2 3 3

LEVEL LIKELIHOOD/PROBABILITY

Likely Could happen frequently

Moderate Could happen occasionally

Unlikely May occur only in exceptional circumstances

CONTROLS CONSIDERED TO MANAGE RISKS

Elimination Substituting Isolating Engineering Administration PPE

Page 4: SAFE WORK METHOD STATEMENT - Clifford Constructionscliffordconstructions.com.au/wp-content/uploads/2013/07/SWI011.01... · works: SAFE WORK METHOD STATEMENT ... permanent disability

SAFE WORK METHOD STATEMENT

Clifford Constructions P/L Phone: 02 9482 7288 SWMS No.________

8/35 Leighton Place Fax: 02 9482 7037

Hornsby NSW 2077 Email: [email protected]

Revision: 1

SWI011.01

Approval Date:04/06/2014 Page 4 of 13

Item Job Steps Hazards Risk Rate

Before Controls

Risk Rate

After Person Responsible

Page 5: SAFE WORK METHOD STATEMENT - Clifford Constructionscliffordconstructions.com.au/wp-content/uploads/2013/07/SWI011.01... · works: SAFE WORK METHOD STATEMENT ... permanent disability

SAFE WORK METHOD STATEMENT

Clifford Constructions P/L Phone: 02 9482 7288 SWMS No.________

8/35 Leighton Place Fax: 02 9482 7037

Hornsby NSW 2077 Email: [email protected]

Revision: 1

SWI011.01

Approval Date:04/06/2014 Page 5 of 13

Item Job Steps Hazards Risk Rate

Before Controls

Risk Rate

After Person Responsible

Page 6: SAFE WORK METHOD STATEMENT - Clifford Constructionscliffordconstructions.com.au/wp-content/uploads/2013/07/SWI011.01... · works: SAFE WORK METHOD STATEMENT ... permanent disability

SAFE WORK METHOD STATEMENT

Clifford Constructions P/L Phone: 02 9482 7288 SWMS No.________

8/35 Leighton Place Fax: 02 9482 7037

Hornsby NSW 2077 Email: [email protected]

Revision: 1

SWI011.01

Approval Date:04/06/2014 Page 6 of 13

Item Job Steps Hazards Risk Rate

Before Controls

Risk Rate

After Person Responsible

Page 7: SAFE WORK METHOD STATEMENT - Clifford Constructionscliffordconstructions.com.au/wp-content/uploads/2013/07/SWI011.01... · works: SAFE WORK METHOD STATEMENT ... permanent disability

SAFE WORK METHOD STATEMENT

Clifford Constructions P/L Phone: 02 9482 7288 SWMS No.________

8/35 Leighton Place Fax: 02 9482 7037

Hornsby NSW 2077 Email: [email protected]

Revision: 1

SWI011.01

Approval Date:04/06/2014 Page 7 of 13

Item Job Steps Hazards Risk Rate

Before Controls

Risk Rate

After Person Responsible

Page 8: SAFE WORK METHOD STATEMENT - Clifford Constructionscliffordconstructions.com.au/wp-content/uploads/2013/07/SWI011.01... · works: SAFE WORK METHOD STATEMENT ... permanent disability

SAFE WORK METHOD STATEMENT

Clifford Constructions P/L Phone: 02 9482 7288 SWMS No.________

8/35 Leighton Place Fax: 02 9482 7037

Hornsby NSW 2077 Email: [email protected]

Revision: 1

SWI011.01

Approval Date:04/06/2014 Page 8 of 13

PERSONNEL ON SITE QUALIFICATIOINS &/OR LICENCE NUMBERS ADDITIONAL TRAINING REQUIRED TO COMPLETE WORK

All personnel must be site inducted before commencing work on this site

1st Supervisor

2nd Supervisor

ENGINEERING DETAILS/CERTIFICATES/WORKCOVER APPROVALS ETC

Page 9: SAFE WORK METHOD STATEMENT - Clifford Constructionscliffordconstructions.com.au/wp-content/uploads/2013/07/SWI011.01... · works: SAFE WORK METHOD STATEMENT ... permanent disability

SAFE WORK METHOD STATEMENT

Clifford Constructions P/L Phone: 02 9482 7288 SWMS No.________

8/35 Leighton Place Fax: 02 9482 7037

Hornsby NSW 2077 Email: [email protected]

Revision: 1

SWI011.01

Approval Date:04/06/2014 Page 9 of 13

THIS SWMS HAS BEEN DEVELOPED THROUGH CONSULTATION WITH OUR EMPLOYEES AND HAS BEEN READ, UNDERSTOOD AND SIGNED BY ALL EMPLOYEES UNDERTAKING

THE WORKS

NAME SIGNATURE DATE

Page 10: SAFE WORK METHOD STATEMENT - Clifford Constructionscliffordconstructions.com.au/wp-content/uploads/2013/07/SWI011.01... · works: SAFE WORK METHOD STATEMENT ... permanent disability

SAFE WORK METHOD STATEMENT

Clifford Constructions P/L Phone: 02 9482 7288 SWMS No.________

8/35 Leighton Place Fax: 02 9482 7037

Hornsby NSW 2077 Email: [email protected]

Revision: 1

SWI011.01

Approval Date:04/06/2014 Page 10 of 13

AMENDMENTS TO ORIGINAL SWMS

Item Job Steps Hazards Risk Rate

Before Controls

Risk Rate

After Person Responsible

Page 11: SAFE WORK METHOD STATEMENT - Clifford Constructionscliffordconstructions.com.au/wp-content/uploads/2013/07/SWI011.01... · works: SAFE WORK METHOD STATEMENT ... permanent disability

SAFE WORK METHOD STATEMENT

Clifford Constructions P/L Phone: 02 9482 7288 SWMS No.________

8/35 Leighton Place Fax: 02 9482 7037

Hornsby NSW 2077 Email: [email protected]

Revision: 1

SWI011.01

Approval Date:04/06/2014 Page 11 of 13

THESE AMENDMENTS HAVE BEEN READ, UNDERSTOOD AND SIGNED BY ALL EMPLOYEES UNDERTAKING THE WORKS

NAME SIGNATURE DATE

Review 1 2 3 4 5 6

Initial

Page 12: SAFE WORK METHOD STATEMENT - Clifford Constructionscliffordconstructions.com.au/wp-content/uploads/2013/07/SWI011.01... · works: SAFE WORK METHOD STATEMENT ... permanent disability

SAFE WORK METHOD STATEMENT

Clifford Constructions P/L Phone: 02 9482 7288 SWMS No.________

8/35 Leighton Place Fax: 02 9482 7037

Hornsby NSW 2077 Email: [email protected]

Revision: 1

SWI011.01

Approval Date:04/06/2014 Page 12 of 13

Plant ID Register

The plant listed below will be brought onto site and operated by Clifford Constructions P/L. None of the listed mobile plant will be operated or static plant used,

until appropriate plant inspection and maintenance records have been provided to the head contractor. All inspection and maintenance records will, as a minimum standard, comply with the manufacturers recommendations or relevant Australian Standard where appropriate

The following static (e.g. scaffold) or mobile (e.g. Manitou) plant will be used on site:

Type Static (s)/ Mobile (m)

Date Registration Purpose (use on site)

Inspection Frequency

Inspected by whom (qualified person)

Page 13: SAFE WORK METHOD STATEMENT - Clifford Constructionscliffordconstructions.com.au/wp-content/uploads/2013/07/SWI011.01... · works: SAFE WORK METHOD STATEMENT ... permanent disability

SAFE WORK METHOD STATEMENT

Clifford Constructions P/L Phone: 02 9482 7288 SWMS No.________

8/35 Leighton Place Fax: 02 9482 7037

Hornsby NSW 2077 Email: [email protected]

Revision: 1

SWI011.01

Approval Date:04/06/2014 Page 13 of 13

HAZARDOUS SUBSTANCES USED ON THIS SITE

Name of Hazardous Substance MSDS Provided