s20_lrsp project successes & challenges_ltc2013
TRANSCRIPT
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
1/44
LRSP PROJECT SUCCESSES
& CHALLENGES
2013 LA TRANSPORTATION
CONFERENCE
Nick Verret, P.E.
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
2/44
PROJECTS TO BE
DISCUSSED
St. Tammany Trace Warning Signs
New Iberia Sidewalks &
City of Central Radar Speed Signs
Caddo Parish Guard Rail Installation
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
3/44
ST. TAMMANY TRACE
Advance warning
system, including
motion detection,installed at 7 local
road crossings of 31-
mile bicycle,
pedestrian, &equestrian trail utilized
by over 10,000 people
monthly
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
4/44
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
5/44
PRE-PROJECT VIEW
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
6/44
PRE-PROJECT VIEWAT S CURVE LOCATION
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
7/44
After Early Warning System Installation Monitor Road
North of intersection facing south West of intersection facing east
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
8/44
After Advance Early Warning System Installation S. Tranquility Road
West of intersection facing east Southeast of intersection facing west
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
9/44
SPECIAL PROJECT
FEATURES
Motion detection [50 from road crossing]
Powered by solar panels
Total project cost of $155,650
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
10/44
TESTIMONIAL FROM
SHERIFF JACK STRAIN Several near-misses prior to project
Since completion of project, no cyclist or
pedestrian crashes
Motorists have slowed down considerably
Thank you for your assistance . . . I want
you to know what a difference these Early
Warning Systems have made.
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
11/44
SPECIAL THANKS TO . . .
Sue Rountree, Grants Manager
Eddie Williams, Engineering Director
Lisa Maddox
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
12/44
LRSP PROJECTS IN
NEW IBERIA
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
13/44
JEFFERSON TERRACE
Traffic Study of
rapidly-developing
corridor that includeda high school,
rehabilitation hospital,
numerous doctors
offices, & businessesincluding Wal-Mart
88 crashes since 2005
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
14/44
RESULT OF TRAFFIC STUDY
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
15/44
A SECOND PROJECT ON
JEFFERSON TERRACE
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
16/44
CITY OF NEW IBERIA
HAS RECEIVED . . .
3 LRSP projects, including a second Traffic
Study [Lewis Street]
Total of $291,591
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
17/44
MAYOR HILDA CURRY:
LRSP has been a great benefit to the City
of New Iberia.
Through LRSP, municipalities have the
opportunity to apply for [funding] that is
essential for safe communities.
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
18/44
SPECIAL THANKS TO:
Elmire Elledge, City Clerk
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
19/44
LRSP PROJECTS INCITY OF CENTRAL
MR. DAVID BARROW,
CHIEF ADMINISTRATIVE
OFFICER
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
20/44
City of Central BackgroundCity of Central Background
Incorporated in 2005 and officiallyIncorporated in 2005 and officiallyseparated from EBR Parish government inseparated from EBR Parish government in
March 2008March 2008
Approx. 27,000 residents (2010 census)Approx. 27,000 residents (2010 census)Approx. 66 sq. milesApprox. 66 sq. miles
Annual budget: Approx. $6 million.Annual budget: Approx. $6 million.
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
21/44
City of Central LRSP Projects
First project submitted to Local Road Safety Program
(LRSP) in October 2008 for safety improvements in curves
on four local roadways.
Plans call for centerline rumble strips, thermoplastic
striping, raised pavement markers, and chevron signs
Estimated project cost: $88,000 for construction and
$31,000 for engineering.
City of Central puts up 10% local match.
Bids and engineering handled through state DOTD.
Maximum funding of $500,000 per project.
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
22/44
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
23/44
Project Description
Identify and describe
the problem
Symptoms Provide a detailed
description of the
project you propose to
solve the problem.
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
24/44
Supporting Documentation
Data Analysis
Crash reports from the last
1-3 years (provided by
LRSP engineers)
Road Safety Audit
Traffic Study
Emergency ResponsePersonnel, Law
Enforcement
Citizens
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
25/44
Sample Crash Data
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
26/44
Supporting Documentation 2
What other
countermeasures have
been attempted? How successful were
they?
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
27/44
Supporting Documentation 3
Project Limits Map
Traffic Counts/Volume
Type of traffic on theroadway
Time of Day
Special events in the area
# of lanes; speed limit How will your project
reduce crashes?
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
28/44
Detailed Cost Estimate
Materials to be
purchased
Engineering costs Right of Way
acquisition
Utility relocations
Construction costs
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
29/44
Approval Process
3 copies of application sent to Local Road Safety
Program office for evaluation in October 2008
Selected applicants notified within 3 months(January 2009)
Contracts and funding approval (FHWA): approx.
one year (March 2010)
Engineering and design selection: approx. one
year (May 2011)
Engineering design completion: December 2011
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
30/44
Approval Process
Scheduled for bid letting: March 14, 2012
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
31/44
2nd ProjectRadar Signs
Submitted application in October 2007 for
two permanent radar display signs on a
local residential road in which speeding wasa problem, and accidents were occurring
due to speeding vehicles
Did study: 85th percentile was 44 mph andspeed limit was 30 mph in a residential
neighborhood
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
32/44
2nd project Radar Signs
Submitted application in October 2007 for $12,350 to
purchase two permanent radar display signs
Approval granted in January 2008.
Contract signed January 2010.
Notice to proceed issued July 2010.
Material purchase only
100% reimburseable. No local match required.
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
33/44
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
34/44
TESTIMONIAL FROM
RESIDENT I have lived on Durmast Drive for the past
15 years and have seen the high rate of
speed in the past. Since the signs have beeninstalled, I have noticed a significant
decrease in the speed . . . They have
certainly been very beneficial in helpingcontrol the speed on the street.
Lester Strange
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
35/44
3rd Project: Curve Signs
Submitted request for $3,000 in funding in
October 2011 for advanced curve signs and
chevron signs in curves on rural local roads Request approved in January 2012.
Awaiting contract documents.
10% local match in the form of crew labor.
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
36/44
CADDO PARISH
GUARDRAIL PROJECT Installed guardrails on
multiple bridges
Total cost of $348,154
Local Match of 10%
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
37/44
TESTIMONIAL FROM KEN WARD,
CADDO P.W./ENGR. PROJECT MGR. The program is great to assist local
governments in making the needed
upgrades to provide citizens the safestconditions possible. The application
process is easy and the award and
construction process was efficient. TheParish of Caddo would use the program
again in the future.
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
38/44
LRSP CHALLENGES
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
39/44
Despite widespread promotional efforts,
many local agencies are still unaware that
the program exists.Some juridictions do not have technical staff to
research various funding sources
Turnover in elected officials
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
40/44
Some local agencies are unable to
participate in the program because they are
unable to contribute the 10% local match.Other funding sources can be sought for the
match, including grants or State Capital Outlay
Remember, this is NOT a grant program!
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
41/44
Admittedly, it can be a long and
cumbersome process for obtaining a
relatively small amount of funding[
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
42/44
Project management by Local Public
Agencies is sometimes ineffective and
results in delays in project delivery and lackof timely completion.
This is being addressed by new DOTD
Qualification training program for LPAs
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
43/44
BUT, IN SPITE OF THE
CHALLENGES . . . LRSP remains a viable means for providing
local agencies with the funding for making
a variety of needed safety improvements onthe local road system, to meet the end goal
of --
Reducing crashesReducing injuries and fatalities
-
7/29/2019 S20_LRSP Project Successes & Challenges_LTC2013
44/44
THATS ALL FOLKS!
Thanks for your kind attention!