s17_o-cell capacity determination for driven piles_ltc2013

39
www.fugro.com www.loadtest.com Bi-Directional Static Load Testing of Driven Piles Paul J. Bullock, PhD Fugro Consultants Inc. Loadtest

Upload: walaywan

Post on 03-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 1/39

www.fugro.comwww.loadtest.com

Bi-Directional

Static Load

Testing of Driven Piles

Paul J. Bullock, PhD

Fugro Consultants Inc.

Loadtest

Page 2: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 2/39

www.fugro.comwww.loadtest.com

Bi-Directional Osterberg Cell Testing

• Specialized jack in pile uses

bearing to mobilize side shear 

• Developed by

Dr. Jorj Osterberg and AEFC

LOADTEST Inc. founded 1991(purchased by Fugro in 2008)

• First “O-cell” tests on driven

steel pipe piles 1987

• >2000 O-cell tests to date,mostly drilled shafts (300+/yr)

• ~ 30 driven piles since 1987

(12”-66”, 52 tons – 1,480 tons)

Page 3: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 3/39

www.fugro.comwww.loadtest.com

P = F+Q

Conventional Test

F

Q

F

F1 

Q

F2

Q

Osterberg Cell Test

O = F = Q = P/2 O = F1 = (F2+Q)

O

O

Pile Provides Reaction

Reaction System

Page 4: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 4/39

www.fugro.comwww.loadtest.com

Driven Pile O-cell Installation

O-cell cast into or welded

to pile before driving

O-cell grouted into pile

after driving

66” Cylinder Pile, Harrison County, MS 30” PSC Pile, Morgan City, LA 

Page 5: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 5/39

www.fugro.comwww.loadtest.com

O-cell Features

Robust for installation• Aligned with pile axis

• Special seal for eccentricity

•Water used for hydraulic fluid

• Rated at 10,000 psi

• Calibrated by AEFC

(NIST Traceability)

• Linear & Repeatable

• Strain gauges

also confirm load

24” PHC Korea 

Page 6: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 6/39

www.fugro.comwww.loadtest.com

O-cell Instrumentation

O-cell Pressure monitoredby gauge and transducer 

• Pile Top Movement

• O-cell Expansion

Transducers

• O-cell Top Telltales

• Pile Bottom Telltales

• Embedded Strain Gauges

• Embedded Pile

Compression Transducers

Page 7: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 7/39www.fugro.comwww.loadtest.com

O-cell Test Setup

• ASTM D1143

Quick Test (newstandard coming)

• 20 Loads to failure

• 8 min load intervals

(identify creep limit)

• All instruments

monitored by

datalogger 

• Real-time load

vs. deflection plot

• Reference beams

replaced by

electronic levels

Page 8: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 8/39www.fugro.comwww.loadtest.com

O-cell Sizes

O-cell Size Rated Capacity Max. Test Load

6” 100 tons 200 tons

9” 225 tons 450 tons

13” 438 tons 875 tons

16” 700 tons 1400 tons

20” 1125 tons 2250 tons

24” 1550 tons 3100 tons

26” 1950 tons 3900 tons

34” 3000 tons 6000 tons

• Cells typically welded to load plates

• Cells can be grouped together 

•6” stroke standard, 9” stroke available 

Page 9: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 9/39www.fugro.comwww.loadtest.com

Special Features of Driven Pile O-cells

• AEFC welds plates to O-cell that fit pile

form (or pile ID)

• O-cell welded shut for safe pile handling

• O-cell placed at pile bottom

• O-cell skirt / enclosure

provided (if driven)

• Rebar anchors cell to pile

• Vent pipe to minimizedisturbance at cell opening

• Instrumentation cables

and hoses coiled at top of pile

Page 10: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 10/39www.fugro.comwww.loadtest.com

Example: 18” Steel Pipe Piles, MA 

Saugus River Bridge Pines River Bridge

• DelmagD62-22

• Refusal

10 blows /0.5” 

• 142 tons

O-cell Load

• 0.28 tsf Side

Resistance

Failure (0.3”) 

• 80 tsf 

End Bearing(not failed)

• 284 tons

Capacity

• DelmagD36-13

• Refusal

10 blows /0.5” 

• 215 tons

O-cell Load

• 0.39 tsf Side

Resistance

Failure (0.3”) 

• 122 tsf 

End Bearing(not failed)

• 430 tons

Capacity

Page 11: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 11/39www.fugro.comwww.loadtest.com

FL Research Pile Setup

•Five 18” PSC Piles 

• PDA Tests

• Long-term, staged

static tests (25)

• Osterberg Cell in tip

• Strain Gages

• Telltales

• Piezometers

• DMT Stress Cells Osterberg Cell

Cast Into Pile,

with XXS Pressure Pipe

to Top

Pile

Side

Shear 

Pile End Bearing

O-cell® Top

Telltales Inside PVC

Pipe

O-cell® Bottom Telltale (through center of 

pressure pipe)

Friction Collar 

for Gage SupportO-cell® 

Tee

(not to scale)

Dilatometer Cell (L)

& VW Piezometer (R)

on Pile Face

VW Strain Gage(in pairs, tied to prestress

strands)

Hydraulic Pump

with Gage

& Piezometer 

Wireline & Scale

Page 12: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 12/39www.fugro.comwww.loadtest.com

FL Research Pile Setup: O-cell

Page 13: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 13/39www.fugro.comwww.loadtest.com

0 50 100 150 200 250 3000

500

1000

1500

2000

2500

Aucilla, Static TestAucilla, Dynamic Test

1 min

15 min60 min

1727 days

Elapsed Time, t (days)

PileSideShearQS

(kN)

Bullock et al. (1995) in FL

18” PSC, O-cell at bottom

FL Research Pile Setup – Arithmetic Plot 

= 225 tons

Page 14: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 14/39www.fugro.comwww.loadtest.com

0.001 0.01 0.1 1 10 100 10000

500

1000

1500

2000

2500

Aucilla, Static TestAucilla, Dynamic Test

1 min

15 min

60 min

QS0 =1021 kN (at t0 = 1day )

mS = 293.4 kN

Elapsed Time, t (days)

PileSideShear

QS

(kN)

Bullock et al. (1995) in FL18” PSC, O-cell at bottom

(EOID Capacity plotted at 1 min)

FL Research Pile Setup – Log-linear Plot 

= 225 tons

Page 15: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 15/39www.fugro.comwww.loadtest.com

0.001 0.01 0.1 1 10 100 1000

0.0

0.2

0.4

0.6

0.8

1.0

1.2

1.4

1.6

1.8

2.0

2.2

Aucilla, Dynamic Test

Aucilla, Static Test

A = (mS / QS0) = 0.30

R2

= 0.99

1 min

15 min

60 min

Elapsed Time Ratio, ( t / t0 ) with t0 = 1 day

Pile

SideShearRa

tio,(Qs/Qs0)

Bullock et al. (1995) in FL

18” PSC, O-cell at bottom

+30%

+30%

+30%

Σ = +90% in 1 day

(or 9X 1 min capacity)

1-3d

+14 %

1-7d

+25%

1-28d +43% or about half of 

EOD-1d change

FL Research Pile Setup – Non-dimensional Plot

Page 16: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 16/39www.fugro.comwww.loadtest.com

Example: Morgan City, LA - 30” PSC 

• HPSI 2500, 300 bpf 

• 30” PSC, 18” Void, 143 ft long

• Pile Setup Clay/Sand

• 950 ton O-cell

369 tons

at 1wk

416 tons

at 3 wks

464 tons

at 5 wksMax. O-cell Load 493 tons

Buoyant Pile Weight 29 tons

Page 17: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 17/39www.fugro.comwww.loadtest.com

Example: Busan, Korea - 24” PHC 

• Prestressed Spun High Strength Conc.

• 24” OD, 16” ID, 103 ft long, 46 ft sections• Sand / Clay / Sand

• 875 ton O-cell, 7 Strain Levels, Grouted

Buoyant Pile Weight 16 tons

Max. Side Shear 456 tons

Unit Side Shear 0.14 to 1.98 tsf 

Max. O-cell Load 472 (944 ton test)

Max. End Bearing 155 tsf 

Page 18: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 18/39www.fugro.comwww.loadtest.com

Example: Harrison County, MS - 66” Cylinder  

• Conmaco 300, 128 bpf EOID

• 66” OD, 54” ID, 108 ft long

• Silt / Sand / Dense Sand

• 3000 ton O-cell, 4 Strain Levels

Buoyant Pile Weight 114 tons

Max. Side Shear 626 tons

Unit Side Shear 0.23 to 4.10 tsf 

Max. End Bearing 45 tsf 

Max. O-cell Load 740 tons (1480 ton test)

Page 19: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 19/39

www.fugro.comwww.loadtest.com

Efficient O-cell Test Applications

End bearing

side resistance (use ultimate!)• Restricted site access (remote location, existing

structures, environmentally sensitive, water)

• Prove capacity distribution (end bearing vs. side

resistance, unit side resistance)• Accelerated construction schedule

• Large test loads required

• Site safety restrictions (personnel & equipment)

• Repeated tests (setup)

• Multiple test piles (but only one test frame)

• Compare with total cost of conventional testing

Page 20: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 20/39

www.fugro.comwww.loadtest.com

Pile preselected for testing• Maximum load limited by the weaker of the

end bearing or side shear (add top load?)

• Top of pile not structurally tested

• Subtract buoyant weight of pile above O-cellto calculate side resistance

• Must construct equivalent top load

movement curve

• use the sum of measured behavior • use the sum of modeled behavior 

• use finite element or t-z approach

O-cell Test Limitations

Page 21: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 21/39

www.fugro.comwww.loadtest.com

Typical O-cell Test Result

(1 MN = 112.4 tons)

2,700 tons

Page 22: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 22/39

www.fugro.comwww.loadtest.com

Equivalent Top-Load Curve

Page 23: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 23/39

www.fugro.comwww.loadtest.com

Equiv. Top-Load + Elastic Shortening

Page 24: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 24/39

www.fugro.comwww.loadtest.com

• RIM-cell pressurizes pile cross-section

• Full-scale static bi-directional load test• Install a RIM-cell in any pile

• Economical testing

• QA/QC device eliminates uncertainty

• End-bearing engaged during test,

stiffens shaft response under load

RIM-CELL

60” RIM-cell

Page 25: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 25/39

www.fugro.comwww.loadtest.com

Cross-section of a RIM-cell installed at the shaft toe.

RIM-CELL 

TESTING

Page 26: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 26/39

www.fugro.comwww.loadtest.com

The RIM-cell confines the fluid pressure, creating a hydraulic

cylinder at the shaft toe capable of applying high static loads.

RIM-CELL 

TESTING

Page 27: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 27/39

www.fugro.comwww.loadtest.com

Fluid grout is pumped through the hydraulic hoses creating a

fracture across the shaft, pressurized within the RIM-cell.

RIM-CELL 

TESTING

Page 28: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 28/39

www.fugro.comwww.loadtest.com

As the internal grout sets, more grout is pumped into

external pipes to fill the annular fracture around the RIM-cell.

RIM-CELL 

TESTING

Page 29: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 29/39

www.fugro.comwww.loadtest.com

USING THE RIM-CELL 

• PROOF TEST

•Install in every pile

• Load shafts to design load or higher (2000 – 5000 psi)

• Eliminate uncertainty of sitevariability

• Use higher LRFD factors• Detect / remediate a “soft toe” 

• POST-STRESSING 

• Consolidate loose material atshaft toe

• Engage end bearing withoutlosing side shear 

• Limit settlement at service load

Page 30: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 30/39

www.fugro.comwww.loadtest.com

RIM-CELL ASSEMBLYDesigned for drilled shaft construction.

RIM-cell fits inside reinforcing cage.

Hydraulic hoses and instrumentation pipe

installed on the cage. Add strain gages, etc.

to isolate and analyze different soil strata.

RIM-cell welded to frame

below O-cell assembly for amulti-level test shaft.

24” RIM-cell installed with

8 levels of strain gages

60” RIM-cell

Page 31: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 31/39

www.fugro.comwww.loadtest.com

After shaft excavated and approved, hang

cage with RIM-cell at the desired elevation.

Large center opening allows tremie pipe to

pass during concrete placement. Low

cross-sectional area does not inhibit

concrete flow or trap loose materials.

RIM-CELL INSTALLATION 

60” RIM-cell installed into

78” rock socket 24” RIM-cell at toe of 

an O-cell test shaft20” RIM-cell installed

at the toe of 30” shaft 

Page 32: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 32/39

www.fugro.comwww.loadtest.com

Perform test after concrete obtains strength. Cement grout

is mixed and pumped through the hydraulic hoses into theRIM-cell. Measured pressure is converted to load using

calibration factor of the RIM-cell. Load is increased to 1.2

to 1.5 times design load. Shaft movement is measured and

recorded. Grout will set up to restore integrity to the shaft.RIM-cell Load-Displacement

-1.5

-1.3

-1.1

-0.9

-0.7

-0.5

-0.3

-0.1

0.1

0.3

0.5

0.7

0.9

0 100 200 300 400 500 600

RIM-cell Load ( kips )

Displaceme

nt(in)

Upward Top of RIM-cell

Downward Base of RIM-cell

24” RIM-cell Test Curve 36” RIM-cell Test Curve

RIM-CELL TESTING

Page 33: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 33/39

www.fugro.comwww.loadtest.com

The RIM-cell report similar to O-cell

test report. Load-Displacement plot

generated in real time during test.

Electronic preliminary results available

the same day as the test.

RIM-CELL REPORTING

60” RIM-cell

Schematic

section of 

RIM-cell

shaft

Equivalent Top Load Plot

Page 34: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 34/39

www.fugro.comwww.loadtest.com

RIM-CELL LIMITATIONS

Internal friction unknown (but small)• Preselect shaft

(install in every shaft, test as required)

• Reduced pressure vs. O-cell(but large area)

• Typically will not test to failure

• Grouting required to restore shaft integrity

• Maximum load limited by the weaker of theend bearing or side shear (add top load?)

• Top of pile not structurally tested

Page 35: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 35/39

www.fugro.comwww.loadtest.com

MISSOURI RESEARCHPROJECT

• 24” bi-directional test piles ontwo different sites

• Two piles on each site weretested using RIM-cells

• 24” RIM-cells in 36” piles 

• 20-30 feet deep shafts in

unweathered and weatheredshale

• Side by side comparison toO-cell tests

24” RIM-CELL TESTS

Page 36: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 36/39

www.fugro.comwww.loadtest.com

24” RIM-CELL TESTS

Similar piles on same site. O-cell test (red) taken to ultimate capacity. RIM-celltest (blue) taken to design load. Plots show similar deformations at design load.

Page 37: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 37/39

www.fugro.comwww.loadtest.com

RIM-CELL Tests to Date

RIM-cell

Size

Shaft DiameterMax

Pressure

Max Cell

Load

Test Result

14" 24" 2500 psi 350 kips Side Shear Failure

14" 24" 1780 psi 250 kips End Bearing Failure

20" 30" 1530 psi 450 kips Side Shear Failure

20" 30" 1360 psi 400 kips Side Shear Failure

24" 36" 2560 psi 1100 kips RIM-cell Capacity Maxed Out

24" 36" 1980 psi 850 kips RIM-cell Capacity Maxed Out

24" 36" 640 psi 275 kips End Bearing Failure

24" 36" 1170 psi 500 kips End Bearing Failure

24" 30" 940 psi 400 kips Test stopped at 1" Expansion

36" 54" 475 psi 450 kips Side Shear Failure

60"

96"

(76"rock socket) 4950 psi 13,000 kips Test stopped at 1/2" Expansion

Page 38: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 38/39

www.fugro.comwww.loadtest.com

Summary

• O-cell test proven for driven piles

• Compare overall cost and quality of testresults for conventional top-down testingwith O-cell testing

• RIM-CELL tests to verify production pilecapacity (QA/QC)

• Coming Attractions:

• New ASTM Standard

•Bigger piles, higher loads

• Mid-pile O-cell placement for splicedconcrete piles

• Mid-pile placement for steel pipe piles

Page 39: S17_O-Cell Capacity Determination for Driven Piles_LTC2013

7/29/2019 S17_O-Cell Capacity Determination for Driven Piles_LTC2013

http://slidepdf.com/reader/full/s17o-cell-capacity-determination-for-driven-pilesltc2013 39/39

Thank You

www.loadtest.com

www.fugro.com