rrmj0366 · table of contents 1.0 introduction 1 1.1 project background 1 1.2 general scope of...
TRANSCRIPT
LAW ENVIRONMENTAL INC.112 TOWNPARK DRIVEKENNESAVi! GEORGIA 30144-5599404-421-3400
; April 23, 19871
Scovill Inc.• %0gletree, Deakins, Nashr Smoak & Stewart
First Atlanta Tower, Suite 3920Two Peachtree Street, N.W.
! Atlanta, Georgia 30303
ATTENTION: Mr. Charles A. Perry
' SUBJECT: Report of Building Surface Sampling and AnalysesMontross Plant
; Montross, Virginia{ LE Job NO. HC-5283
Gentlemen:
This report presents results of the building surface sampling andanalyses performed for the subject site as a result of the "walk-through" inspection conducted on 17 February 1987.
The sampling and analyses were performed in accordance with Mr.Stewart Hudnut's authorization. Sampling was conducted at thesite from 23 February to 27 February 1987.
Please let us know if there are questions or if you wish todiscuss the report.
We appreciate the opportunity of performing this work forScovill.
Very truly yours,
LAW ENVIRONMENTAL, INC.
Kathleen A. McNelisStaff Chemical Engineer
_L. CTavid Wheeless, P.E.Senior Geotechnical Engineer
KAM/LDW:cfenc.
RRMJ0366
REPORT OF
BUILDING SURFACE SAMPLING AND ANALYSES
for
SCOVILL INC.
MONTROSS PLANT
MONTROSS, VIRGINIA
APRIL 1987
TABLE OF CONTENTS
1.0 INTRODUCTION 1
1.1 Project Background 11.2 General Scope of Phase I Abatement 31.3 Phase II Plan 31.4 "Walk-Through" Inspection 3
2.0 OBJECTIVE OF SAMPLING
3.0 FIELD SAMPLING 6
3.1 Building Surfaces 63.2 Buffing Area 73.3 Sump Discovered on Dip Tank Line 73.4 Debris 83.5 Deteriorated Concrete 8
4.0 LABORATORY ANALYSES 9
4.1 Building Surfaces 94.2 Buffing Area 104.3 Sump Discovered on Dip Tank Line 104.4 Deteriorated Concrete 11
5.0 RESULTS 12
5.1 Building Surfaces 125.2 Buffing Area 175.3 Sump Discovered on Dip Tank Line 175.4 Deteriorated Concrete 18
TABLES
1. Concentrations of Contaminants on Building Surfaces2. Analyses of Soil Samples from Sump Discovered on Dip
Tank Line3. Mean and Standard Deviation of Contaminant Concen-
trations in Building Areas4. 95 Percent Confidence Limit, Contaminant Concen-
trations in Building Areas.5. Lead Contamination on Building Surfaces6. Silver Contamination on Building Surfaces7. Cadmium Contamination on Building Surfaces8. Chromium Contamination on Building Surfaces
TABLE OF CONTENTS (Cont.)
9. Copper Contamination on Building Surfaces10. Nickel Contamination on Building Surfaces11. Zinc Contamination on Building Surfaces12. Cyanide Contamination on Building Surfaces13. Summary of Comparison, Contaminants on Types of
Surfaces, All Building Areas Combined
FIGURES
1. Building Surface Sample Locations. 2. Sample Locations: Dip Tank Line
^369
1.0 INTRODUCTION
1.1 Project Background
Scovill Incorporated is conducting environmental assessment and
abatement activities at the site of a former metal plating
operation located on Route 3, Montross, Virginia. The work is
being performed for Scovill by Law Environmental, Inc. (LEI),
Marietta, Georgia.
The site (property) is roughly square, about 1100 x 1100 feet in
plan. The on-site manufacturing plant building is one story,
about 350 x 400 feet in plan.
Metal plating operations were conducted at the site from 1966 to
1979. Cosmetic assembly and wiring harness manufacturing
operations are presently conducted in portions of the building
not occupied by the abandoned plating facilities. Wastes from
previous metal plating and cosmetic assembly operations were in
containers (such as drums and tanks) and floor sumps in the
building and in drums stored outside the building.
Tnere are six impoundments involved in the environmental work.
These consist of one settling pond and five sludge beds. During
plating operations, the impoundments received discharge from the
plant's waste treatment system. The settling pond is about 275 x
200 feet in plan. Plan dimensions of each sludge bed are about
120 x 80 feet. Design drawings for the facility indicate the
impoundments are ten feet deep, measured from the top of the
earth dikes to impoundment bottom.
A small stream drains northward from the north side of the
impoundments. Near the impoundments, the stream has been
observed to be about 12 inches wide and less than 6 inches deep.
Assessment work on the site began in June 1985 and has progressed
in phases toward abatement of environmental conditions. LEI
prepared a Phase I Abatement Plan dated 12 September 1986 for the
site. The plan divided the anticipated site abatement work into
two phases. The work phases were selected to prioritize the
areas and types of contamination at the facility to accomplish
abatement of the areas and types of contamination in order of
decreasing levels of release or threat of release of hazardous
waste. Phase I involved removal of those wastes that were in and
around the building in process tanks and containers, storage
containers (such as tanks, drums and buckets), equipment and
subfloor sumps. Phase II involves soils at the outside drum
storage areas, surface water and sediment (sludge) in the
settling pond and sludge beds.
The Consent Order (effective date 3 July 1986) for the site uses
the same Phase I and Phase II definitions as the Draft Remedial
Action Plan in describing required abatement work. Paragraph 33
of the Consent Order requires submittal of a plan for accomplish-
ing Phase II.
1.2 General Scope of Phase I Abatement
The initial Phase I abatement was completed by LEI in February
1987. This consisted of "immediate removal" activities to remove
hazardous wastes in and around the building. The "immediate
removal" removed to treatment or disposal at approved
treatment/disposal facilities those wastes located in:
1) Process tanks and containers
2) Drums, buckets and other storage containers
3) Equipment (such as degreasers and stripper)
4) Piles of waste solids on the building floor
5) Contaminated wood flooring
6) Crushed drums, buckets and storage containersemptied in Item 2.
1.3 Phase II Plan
In compliance with paragraph 33 of the Consent Order, LEI
prepared a plan dated 29 August 1986 to address the Phase II
characterization and treatment/disposal alternatives. This plan
described sampling and analyses required to design abatement
measures for the soil, lagoon waters, and lagoon sludges. In
September of 1986 Law Environmental began execution of the work
described in the Phase II Plan.
1.4 "Walk Through* Inspection
On 17 February 1987, personnel from EPA, Scovill and LEI met at
the Montross site at EPA's request to determine what work would
be performed in the building beyond the scope of the Phase I
plan. The following items were agreed to be added:
1) Sampling
a) Sample building surfaces and analyze for appropriate
parameters to determine whether decontamination of
building surfaces is required.
b) Sample soils taken adjacent to sump discovered during
Phase I on the Bright Dip Line and analyze for pH,
cyanide and metals.
c) Sample deteriorated concrete on dip tank line to
determine if removal is required.
d) Sample buffing rooms and analyze for asbestos fibers.
2) Pressure Wash
a) Exterior of kolene caustic stripper
b) Sumps under kolene caustic stripper
c) Concrete floor and sumps in anodizing, plating and waste
treatment areas
d) Exteriors of tanks in plating and waste treatment areas
e) "Septic" sump in anodizing area
3) Remove and Transport to Hazardous Waste Disposal
a) Debris in plating and waste treatment areas
b) Piping in plating and waste treatment troughs and sumps
c) Any remaining wood flooring in the plating, anodizing
and waste treatment areas.
d) Plating tank Nos. 413, 449 and 456 due to broken liners
This report summarizes the result of the required sampling.
2.0 OBJECTIVE OF SAMPLING
The sampling program was planned to:
1) Determine contaminant concentrations on building surfaces so
that EPA and Scovill could decide the extent of building
decontamination and decontamination criteria.
2) Determine extent of contamination around the sump discovered
on the dip tank line to decide further action.
. 3) Collect samples of debris to be removed for submission with
Waste Material Profile Sheets to an approved disposal
facility, as required to obtain waste acceptance agreements
with a facility.
4) Collect samples of deteriorated concrete in troughs along
dip tank line to evaluate the need for removal.
5) Collect lint sample from buffing-rooms to determine whether
lint contains asbestos fibers.
3.0 FIELD SAMPLING
3.1 Building Surfaces
The building was divided into eight areas for purposes of sample
collection and data evaluation. These eight areas are shown on
Figure 1. The table below lists the numbers and types of samples
collected and the number of samples analyzed for specified
contaminants:
_______________Number of Samples__________________Building ____Cyanide____ _____Metals____ Trichloroethylene
Area Collected Analyzed Collected Analyzed Collected Analyzed
Kolene 18 9 18 9
Degreaser &hand buffing 36 9 36 9 36 9
SolventStill I I 1 8 9 1 8 9 6 2
Buffing & dustcollection 18 9 18 9
Paint Room 18 9 18 9
Plating Room 18 9 18 9
Anodizing 18 9 18 9
Waste treat-ment 18 9 18 9
Total 162 72 162 72 42 11
All of the 162 samples for cyanide were collected by wiping a 100
cm^ area with gauze dipped in one percent sodium hydroxide
solution. Samples were stored in 8-oz plastic or glass
containers and delivered to Law Environmental National
Laboratories (LEND for analyses.
The 162 samples for metals were collected by scraping
accumulations of dust from selected surfaces using a dedicated
wooden tongue depressor for each sample. Samples were stored in
8-oz plastic or glass containers and delivered to LENL for
analyses.
The 42 samples for trichloroethylene were collected by scraping
dust accumulations into VOA vials with a dedicated wooden tongue
depressor for each sample. Samples were shipped to LENL.
Approximate locations of samples which were analyzed for cyanide,
metals and trichloroethylene are shown on -Figure 1. Descriptions
of each sample location are listed with the laboratory results in
Table 1.
3.2 Buffing Area
One composite sample was made from lint collected from the four
buffing rooms and the dust collector room. This sample was
stored in an 8-oz plastic bottle and shipped to Micro Analytical
Laboratories for asbestos analyses.
3.3 Sump Discovered on Dip Tank Line
Four samples were taken in a boring made into the soil adjacent
to the sump at the location shown on Figure 2. Samples were
taken at depths to correspond to: 1) the top of the sump (0-6"
sample); 2) middle of sump (15-20" sample); 3) bottom of sump
(33-39" sample); and 4) two feet below the bottom of the sump
(57-63" sample).
Samples were taken by hand auger using procedures described by
ASTM D-1452-80. Samples were collected in 8-oz glass jars and
delivered to LENL for analyses.
3.4 Debris
Samples of the debris to be removed from the plating and waste
treatment areas were collected and shipped with completed Profile
Sheets to Chemical Waste Management in Emelle, Alabama for their
acceptance.
3.5 Deteriorated Concrete
A composite was made from samples collected at locations shown on
Figure 2 of the deteriorated concrete in the dip tank line
troughs. Samples were stored in 8-oz glass bottles and delivered
to LENL for analyses.
4.0 LABORATORY ANALYSES
4.1 Building Surfaces
The following test methods were used for analyses of building
surface samples:
Test Parameter Method Number
Trichloroethylene EPA 8010
Total lead EPA 7420
Total silver EPA 7760
Total cadmium EPA 200.7
Total chromium EPA 200.7
Total copper EPA 200.7
Total nickel EPA 200.7
Total zinc EPA 200.7
Total cyanide EPA 9010
The results of these analyses are listed according to building
area in Table 1. Concentrations of metals shown on Table 1 are
total metals. Results of the metals and trichloroethylene
analyses are shown as concentration of total metal in each dust
sample. Results of the cyanide analyses are shown as weight of
cyanide (micrograms, extracted from the gauze pad which was wiped
over a 100 cm2 area) per cm2.
Laboratory reports from LENL are included as Appendix A.
HM80378
4.2 Buffing Arfea ^
The results of the transmission electron microscopy asbestos
analyses performed on the buffing room composite sample was below
the detection limit of 2254 asbestos structures/mg.
The laboratory report from Micro Analytical Laboratories is
included as Appendix B.
4.3 Sump Discovered on Dip Tank Line
Soil samples collected adjacent to the Dip Tank Line sump were
analyzed for:
Test Parameter Method Number
pH • EPA 150.1
Cyanide, Total EPA 9010
Total lead' EPA 7420
Total silver EPA 7760
Total cadmium EPA 200.7
Total chromium EPA 200.7
Total copper EPA 200.7
Total nickel EPA 200.7
Total zinc EPA 200.7
The results of these analyses are presented as Table 2. The
laboratory reports from LENL are included as Appendix C.
10 AR408379
4.4 Deteriorated Concrete
Test methods and results of analyses performed on the
deteriorated concrete sample composited from two locations on the
dip tank line troughs are listed below:
ConcentrationTest Parameter Method Number in Sample
pH EPA 150.1 1.1 (units)
Total Cyanide EPA 9010 82 mg/kg
Total lead EPA 7420 35 mg/kg
Total silver EPA 7760 26 mg/kg
Total cadmium EPA 200.7 <2 mg/kg
Total chromium EPA 200.7 1000 mg/kg
Total copper EPA 200.7 2300 mg/kg
Total nickel EPA 200.7 610 mg/kg
Total zinc EPA 200.7 230 mg/kg
The laboratory report on the deteriorated concrete sample is
included as Appendix D.
11
5.0 RESULTS
5.1 Building Surface
In evaluating the measured concentrations of each contaminant in
dust in each building area to decide the necessity of
decontamination, it is desirable to consider the mean
concentration, rather than the maximum concentration measured,
since the mean value is more representative of prevailing
conditions. However, where individual measured concentrations
vary widely, the true mean can be determined only by collecting
and analyzing all the dust.
Statistical analyses can be used to characterize the variation of
measured concentrations by expressing the mean, standard
deviation and confidence limit of each set of values. The mean
describes the central tendency of the set of measured
concentrations. The standard deviation measures the extent to
which individual sample concentrations are dispersed around the
mean. The confidence limits describe the confidence interval, or
range of concentrations, within which the true mean lies for a
selected probability. These analyses are based on the assumption
that the individual concentrations exhibit a normal (bell-shaped)
frequency distribution.
In calculating the mean or average value of each measured
contaminant concentration in each building area, a value must be
assigned to those measurements which resulted in BDL (Below
Detection Limit). The actual values of such measurements are
12
known only to the extent that they could range from zero to the
detection limit. Therefore, the average of each set of values is
reported for 2 cases: A) with BDL concentrations being
considered as being equal to zero, and B) with BDL
concentrations being considered as equal to the method detection
limit.
Table 3 presents the mean and standard deviation values for each
contaminant in each building area. Of the metals listed in Table
3, lead, silver, cadmium, and chromium are included in 40 CFR
261.24 as contaminants for determining the characteristic of EP
toxicity. EP toxicity tests were not run on the dust samples.
The dust samples had weights typically of one to two grams, and
EP toxicity test procedures require a minimum sample size of 100
grams.
Upper confidence limits were calculated using the Student's t
test. The building surface sample data in Table 1 was evaluated
for each building area using a one-tailed Student's t value
corresponding to a 95 percent upper confidence limit (UCL).
There is a 95 percent probability that the true mean
concentrations are below the calculated values for the upper
confidence limit. The concentrations calculated for the 95
percent UCL are in all cases higher than the mean values. This
is because in the 95 percent UCL analyses, a value is calculated
from the standard deviation and added to the mean to account for
the variations of individual data. These are reported on Table
4. As previously described for the calculations of mean and
13 AR.fcQ8.3S2
standard deviation, two cases are reported: A) setting BDL » 0,
and B) setting BDL = detection limit. An example of the
calculations used is included as Appendix E.
UCL's of mean lead range from 32 ppm in the buffing and dust
collector areas (Method A) to 3,807 ppm in the kolene area (both
methods) UCL's of silver range from 0 ppm in the buffing and
dust collector area (Method A) to 86 ppm in the plating area
(Method B). Cadmium UCL's ranged from 17 ppm in the buffing and
dust collector area (Method A) to 260 ppm in the solvent still II
area (both methods). Chromium UCL's range from 0 ppm in the
buffing and dust collector area (Method A) to 14,178 ppm in the
plating room (both methods).
UCL's of mean copper concentrations range from 1,916 ppm in the
Kolene area (both methods) to 121,734 ppm in the paint room area
(Method B). UCL's of mean nickel concentrations range from 101
ppm (Method B) in the buffing and dust collector areas to 6,407
ppm (both methods) in the plating room. Zinc concentrations
range from 3,311 ppm (both methods) in the buffing and dust
collector rooms to 246,650 ppm (both methods) in the solvent
still II area. Cyanide concentrations range from 0.004 ug/cm^
(Method A) in the buffing and dust collector rooms to 0.767
ug/cm2 (both methods) in the plating room area.
Trichloroethyiene was sampled only in the degreaser and hand
butfing area and solvent still II area. The results were 38 ppm
and 47 ppm respectively.
14
Average concentrations (calculated with BDL = detection limit)
were further compared as functions of the surface sampled. The
following types of surfaces were evaluated:
1) Light fixtures
2) I beams
3) Air ducts, air conditioners and blowers
4) Overhead pipes and electrical conduits
5) Miscellaneous wooden surfaces: building overhangs,
speaker boxes, wooden storage racks, inside roofs
6) Miscellaneous metal surfaces: buffing machinery, blow-
out doors, fans, cabinets, breaker boxes
Walls were not included in this comparison because of the
relatively small number of walls sampled.
The comparison was done by the following method of computation
for each of the metals and cyanide:
1) Each type of surface was individually considered as the
surface of interest.
2) In each building area, the average concentration of
those samples taken rrom the surface of interest was
calculated.
3) In each building area, the average concentration of
those samples from all surfaces other than the surface
of interest was calculated.
15
4) The difference between the two averages calculated in
Steps 2 and 3 was expressed as a percentage of the sum
of the two average concentrations.
Results of the comparison by building area are shown on a
separate table for each contaminant, Tables 5 through 12. A
negative percent difference indicates the particular surface of
interest has an average concentration smaller than that on the
other types of surfaces. A positive percent difference indicates
the particular surface of interest has an average concentration
larger than that on the other types of surfaces.
With a few possible exceptions, the concentrations of
contaminants in samples do not appear to be functions of the
surfaces sampled. In Table 5, for example, the concentrations of
lead are consistently higher in samples collected from
miscellaneous metal surfaces than on other surfaces sampled.
Similarly, the concentrations of lead are consistently lower on
duct work than on other surfaces sampled. In general, there is
no consistent trend of relative contaminant concentrations on
surfaces of interest in different building areas.
Overall averages were compared for each surface of interest to
examine the trends over the building as one unit, without respect
to building area. Table 13 summarizes the magnitude of the
percent differences between contaminant levels on the surface of
interest and all other surfaces.
16
The values on this table were calculated by the following steps
for each of the metals and cyanide:
1) Each type of surface was individually considered as the
surface of interest.
2) The average concentrations on the surface of interest in
all building areas in which the surface of interest was
sampled were averaged to yield one value for each
contaminant.
3) The average concentrations on surfaces other than the
surface of interest in the same building areas as
considered in Step 2 were averaged to one value for each
contaminant.
4) The difference between the two averages calculated in
Steps 2 and 3 was expressed as a percentage of the sum
of the tv/o average concentrations.
5.2 Buffing Area
Asbestos was not detected in the composite sample of lint from
the buffing and degreaser rooms.
5.3 Sump Discovered on Dip Tank Line
The results of the analyses of soils beside the sump indicates
that cyanide is present in all four of the samples and does not
appear to decrease with increasing depth. In the deepest sample
(57-63") cyanide is present at 46 ppm. The soil pH increases
with depth ranging from 1.8 in the 0-6" sample to 2.3 in the 47-
63" sample. In general, the concentrations of metals decrease
with increasing depth. At 57-63", the only metal present in
detectable concentrations is copper (73 ppm).
5.4 Deteriorated Concrete
The results of the analyses on the deteriorated concrete in the
troughs of the dip tank line (data listed in Section 4.4 of
report) indicates that cyanide is present at 82 ppm at a pH of
1.1.
TABLE 1
CONCENTRATIONS OF CONTAMINANTS ON BUILDING SURFACES Page 1 of 4
A) KOLENE AREA
Sample Location ______Concentration in mg/kg______ CNNumber Description Pb Ag Cd Cr Cu Ni Zn (ug/cm2)
K-l Light fixture 270 42 40 <50 1300 270 3300 0.019K-2 I beam over
caustic stripper 1900 20 280 430 1300 400 9300 0.029K-3 I beam over
caustic stripper 10000 30 320 <50 1500 600 9100 0.049K-5 Top of air duct 2400 40 180 630 830 90 67000 0.30K-6 I beam 740 20 80 220 1900 390 23000 0.20K-7 Top of exhaust
duct from stripper 870 20 390 150 1300 180 94000 0.021K-13 Top of duct 70 <15 40 140 500 90 10000 0.12K-16 Wooden supply racks 80 <15 50 180 640 150 10000 0.020K-18 Light fixutre
& I beam 260 20 50 130 3300 260 9400 0.039
B) DE6REASER AND HAND BUFFING AREA.
Sample Location ______Concentration in mg/kg____________ CNNumber Description Pb _Ag_ Cd Cr . Cu Ni_ Zn TCE (ug/cm2)
D-2 Light fixture 500 20 60 90 17000 780 8900 19 0.020D-6 Light fixture over
degreaser I 850 60 90 150 20000 310 8700 16 0.020D-8 Light fixture over
Degreaser II 1000 70 60 190 19000 270 12000 72 0.015D-9 Top of Solvent
Still I 1100 20 220 250 11000 440 85000 20 0.008D-12 Top of Blower
between degreasers 930 <15 60 170 6100 450 8200 21 0.026HB-1 Floor drain 490 <15 60 170 7100 710 4300 NT 0.036HB-2 Light fixture NT NT NT NT NT NT NT 24 NTHB-5 Top of air duct <50 <15 <10 <50 23000 <50 7600 15 0.018HB-6 Top of air cond. 160 20 <10 200 8100 600 4400 33 0.008HB-9 Top of pipe 100 40 <10 50 32000 190 69000 21 <0.005
NT: Not tested
TABLE 1
CONCENTRATIONS OF CONTAMINANTS ON BUILDING SURFACES Page 2 of 41
C) BUFFING ROOMS AND DUST COLLECTOR AREA
Sample . Location ______Concentration in mg/kg______ CNNumber Description Pb Ag Cd Cr Cu Ni Zn (ug/cm2)
BR-1 Duct <50 <15 <10 <50 7000 60 2200 0.008BR-4 Buffing machine <50 <15 <10 <50 2300 <50 490 <0.005BR-5 Duct <50 <15 <10 <50 6400 90 1700 0.006BR-8 Buffing machine <50 <15 <10 <50 2100 80 490 <0.005BR-10 Duct <50 <15 30 <50 9800 90 4700 <0.005BR-11 Frame of buffing
machine 100 <15 30 <50 5900 140 2900 0.006BR-12 Light fixture <50 <15 <10 <50 10000 60 3000 <0.005BR-16 Wall <50 <15 <10 <50 18000 90 3300 <0.005BR-17 Light fixutre <50 <15 20 <50 18000 100 3300 <0.005
D) SOLVENT STILL II AREA
Sample Location ______Concentration in mg/kg____________ CNNumber Description Pb Ag Cd Cr Cu Ni Zn TCE (ug/cm2)
S-l Light fixtureover SS II 560 70 100 120 50000 320 25000 22 0.023
S-2 Top of duct 210 30 40 50 19000 120 6200 13 0.034S-4 Light over
conveyor rack 240 60 80 80 42000 190 17000 NT 0.017S-9 Top of building
overhang 520 30 80 190 25000 370 24000 NT 0.13S-10 Light over
conveyor rack 180 20 60 70 50000 160 17000 NT 0.066S-13 Supply rack out-
side buffing 2200 90 670 90 4800 70 740000 NT 0.37S-14 Speaker box 200 50 62 70 50000 160 19000 NT 0.006S-16 Light fixture 350 30 40 100 8200 290 8000 NT 0.015S-17 Top of supply racks <50 <15 80 200 4100 730 18000 NT 0.20
AR400390
TABLE 1
CONCENTRATIONS OF CONTAMINANTS ON BUILDING SURFACES Page 3 of 4
E) FAINT ROOM AREA
Sample Location ______Concentration in mg/kg_______ CNNumber Description Pb Ag Cd Cr Cu Ni Zn (ug/cm2)
PR-1 Light .fixture 120 20 140 60 210000 190 37000 0.048PR-2 Light fixture 100 20 130 50 220000 150 41000 0.040PR-3 Light fixture 360 20 70 110 33000 250 10000 0.024PR-5 Light fixture 280 20 90 90 63000 210 13000 0.026PR-6 Wall - discolored
area <50 <15 <10 <50 60 <50 80 <0.005PR-8 Wall - discolored
area <50 <15 <10 <50 <25 <50 90 <0.005PR-10 Light fixture 150 <15 270 60 54000 190 15000 0.008PR-12 Blow-out door 4400 <15 60 330 6100 880 5600 <0.005PR-18 Light & Sprinkler
pipe 50 <15 60 <50 29000 120 8900 <0.005
F) PLATING ROOM AREA
Sample Location ______Concentration in mg/kg_______ CNNumber Description Pb Ag Cd Cr Cu Ni Zn (ug/em2)
PL-4 Top of pipe 320 20 80 360 8200 520 3300 0.81PL-6 Top of pipe 910 30 30 290 9900 240 4600 0.87PL-7 Duct near dip
tank line 400 30 40 550 9300 490 5000 0.15PL-10 I beam crossing
plating line 340 20 60 1100 13000 350 7100 0.30PL-11 I beam crossing
plating line 300 <15 60 1400 28000 230 14000 0.69PL-15 I beam crossing
dip tank line 350 <15 50 1500 7500 720 4400 0.03PL-16 I beam crossing
dip tank line 260 90 60 710 3800 1100 2100 0.0222PL-17 Ducts over pre-
cious metals line 190 90 60 43000 8100 19000 4100 0.95PL-18 Pipe at end of pre-
cious metals line 360 170 50 50 14000 630 5300 0.89
TABLE 1
CONCENTRATIONS OF CONTAMINANTS ON BUILDING SURFACES Page 4 of 4'
G) ANODIZING AREA
Sample Location ______Concentration in mg/kg_______ CNNumber Description Pb Ag Cd Cr Cu Ni Zn (ug/cm2)
A-l Wooden supply rack 540 40 40 280 4900 520 3100 0.089A-2 Wooden supply rack 230 150 50 320 3700 240 2700 0.042A-3 Wooden supply rack 100 90 20 530 2100 120 1700 0.093A-6 Quality Control
lab roof 360 30 30 160 470 160 7700 0.15A-7 Supply room roof 250 <15 20 160 640 180 620 0.36A-10 I beam 860 40 70 340 7500 760 3500 0.80A-ll I beam 630 20 40 190 5100 510 1900 0.33A-l3 I beam 870 30 <10 160 14000 140 5100 0.11A-17 Speaker box 200 20 100 200 9800 430 47000 0.23
H) WASTE TREATMENT
Sample Location ______Concentration in mg/kg_______ CNNumber Description Pb Ag Cd Cr Cu Ni Zn (ug/cm2)
W-l Top of pipe 300 40 20 130 5900 220 2400 <0.005W-3 Top of pipe over
caustic tank 50 40 100 290 5100 670 30000 <0.005W-4 Light over copper
bright dip sump <50 60 40 200 8000 680 970 0.76W-5 I beam over
mixing tank 70 90 <10 220 7400 540 1600 <0.005W-6 Light over acid neu-
tralization tank 630 50 <10 190 2700 760 660 <0.005W-7 Cabinet top 60 20 50 180 5400 730 1100 <0.005W-ll I beam 380 40 <10 220 2000 830 650 <0.005W-13 Light over flash
nuetralization sump 70 15 50 250 3000 810 4200 0.62W-l7 Fan 7900 70 40 260 2200 510 4600 0.36
TABLE 2
ANALYSES OF SOIL SAMPLES FROM SUMP DISCOVERED ON DIP TANK LINE
_________Sample Depth_____Test_ Parameter 0-6" 15-20" 33-39" 47-63"
pH (units) 1.8 1.7 2.0 2.3Total cyanide (mg/kg) 15 10 47 46Total lead (mg/kg) 13 14 13 <5Total silver (mg/kg) 5 35 5 <3Total cadmium (mg/kg) 4 <2.0 <2.0 <2.0Total chromium (mg/kg) 52 30 20 <10.0Total copper (mg/kg) 2300 1500 990 73Total nickel (mg/kg) 36 30 20 <10.0Total zinc (mg/kg) 200 300 150 10
£5Cz
BSoH
§js
15*1 O
w
S §
a 1M
I
1
131
c
*Ba3oo•H4JCO
£0)uB0
4JCCDC•HECO
O
^
"H'Oot3
I
8E-t
c
00 •-*o*
IX
CO
IX
M
IX
ON00oo
11
11
ONr-«ONI-Hen
CMCM
NOCM
• H•z
w
IX
ONl4
or~
3
w
IX
coS
ON
••*
uU
CO
IX
oCM
CNo
sw
IX
COenrH
ONm1-H
<
.OCU
w m
IX
00
IX
rHCM
^
2en
en<fCO1-4
1-1Oops*
r-lOo
CO1-1
fCM
inCOoen
CMCMenCM
eninCM
pi— 1
COsCO
CM
2
^
i—l•T
CO
rtNO
NOCM
<OCM
CO^
Oin
enOOoCMOOO
11
11
-3-COen
eninCM
COen
c*P*.
NOCOin
en03
o
S
ON
O
o
enen
rHi— 1
CMr-l
O
N0CNOo
NO
COr-t
p-.in
CM
enenr*-ON
ONo**i—t
CONOCM
en£-1oCM
CM
CM
in
CO
CM
men1-4
COCM
CM"*
CM
NO
NOCN•*
r-tOO
NOOO
11
11
rtCMai—t
ON
in*"
CMNOCM
r-lCMCM
O2sin
S
o
CO
3
i-iO
i— (
O
CO
5,_4^ovO
CMONenO
^CMino
i1
II
<fin<•en
-3-•3-inm
rHNO1— tNO
r-.COmCM
CMONNO
1— 1
rH
CNO-3-
O
m
S
.g.in
>0m
om
coS
_icoen
.3.CM
O
in•3-CM0
11
11
coPX•9
r-•3-co
^CMCM
Oen
in••?•*
inin
<N
O
s1-1*3"
N0<•
px"<r
COCM
ON<?•"*
"-1O
eni-io
ii
Ii
CM
•a-ON
rtenin
1-4CNr-l
CNen
•a1CMe-j
en•*
•*
NO
S
enen
^CM
p
"
P
inCM
r4mrH
o a <* o t-t 4-1II a l E M O r M (D || B X Q O H S C f i
0 ) S l D t H B B . O J B D r ^ B B r o e o
Socc
C OJ <« -rt « 0) 4J -H -rl3 iH H > J 3 1 M 3 ? ' E 4 - I T !
'a "om10^ " O C O I - I B* CQ ^ ( 2 e Q O O C u C u < ;
•Hfi
|
84J£uQ
g^
^
_
1O.x-/
Co•HCOLt
cCil
cofjt
4_)cc«HBCO4Jco
qusc32O
UCJEl
cN
• rlZ
3O
W
"OCJ
e£<
£1Cu
00
IX
CO
IX
w
IX
w
IX
CO
IX
w
IX
CO
IX
00
IX
00
IX
BO<ea
*ur4
3
«
O
COoo
11
11
ON
ON
en
CMeMNOCM
ON
r-t
OP-~CM
coenCO
ONen
i— iON
OCMCM
COenr-l
CNm1—1
0
inCM
p~NOrHen
enCO1-H
<ac0)rHO^
BaX
0)uCO>JocQ
C7NOOO
OO
COrH
r~CM
incooenCM
enCM
en-3-CM
CMCM-3-
COCM
CO
CMCMO"iini-i
Q\
r-<rT—— 4
in
^NO
rHCM
rHen
O•a-
<oPm
eoCUHUHS03
rHOoo
§oo
11
11
.enrH
inCM
^
^CO
NO
coin
enCO
o
oin
ON
NO
o
in*"*
r*.r-l
NOin
i£ 04J
K OB 01O rH
O00C 4J•rt WUH 3•g QCO
rHCMrH
O
oo
vO
COrH
(S.
r-4rH
CM
enr~ON
ON
rH
CONOCM
enCM
OCM
CMrH
CM
enin
COO1-H
CMOCM
inr- 1
inCM
f
"*
COinNO
^Qin
M
H•H4J
4JC9!>rH0to
ps.rHOoCO
oo
11
11
_,CO•3-
rH
i?• '
CMCM
CMenCM
^
0CO
inenNO
rHON
•3-
OCO
en*
fl
fs
rtCMCM<•rH
COrHNO
g
OE£4-1C•H0)CM
CMONenO
-3-
ino
iI
iI
^s?en
•3-
In
^*-4\o
(sCOinCM
CM-31
NO
rHcn^
^o
o-3-in
<r1-4
,3.
in
enin
enin
COoCM
^coen
§
e£B•H4-)COr-lCu
in•* oCM en0 0
inCM CM0 0
I iI i
I ii i
CO CM
r^ 5•3" CJN
•» enco in
•3- rH
CM rH
O CJ>•S' encn NO
in -3-in m•3- CM• CM
in encn NO
en coCM <rrH
O NONO r-tCM CM
CO ONCM CM
CM pv
"""
-T CM
CO f.
co <rCO P~CM m
CM
ON r-v<r m"31 O
rt
4JB14Jctl
C IH
N•H as-O uo w>£ -B,^S
TABLE 4
95 PERCENT CONFIDENCE LIMITS
CONTAMINANT CONCENTRATIONS IN BUILDING AREAS
A) ASSIGNING BELOW DETECTION LIMITS = 0
_____________95% Upper Confidence Limit______Concentration in mg/kg___________ CN
Building Area Pb Ag Cd Cr Cu Ni Zn TCE (ug/cml)
Kolene 3807 31 245 335 1916 375 45949 — 0.151Degreaser & hand buffing 829 42 103 190 21272 573 42277 38 0.024Buffing & dust collector 32 0 17 0 12477 102 3311 — 0.004Solvent Still II 906 59 260 141 40598 391 246650 47 0.17Paint room 1492 15 143 141 121733 384 23708 — 0.028Plating room 510 85 63 14178 15615 6407 7686 — 0.767Anodizing 628 75 60 336 8119 479 17272 — 0.39Waste treatment 2649 62 54 245 . 6031 758 10985 — 0.38
B) ASSIGNING BELOW DETECTION LIMIT = DETECTION LIMIT
Kolene 3807 31 245 338 1916 375 45949 — 0.151Degreaser & hand buffing 830 44 105 190 21272 573 42277 38 0.023Buffing & dust collector 66 15 21 50 12477 101 3311 — 0.006Solvent Still II 909 60 260 141 40598 391 246650 47 0.17Paint room 1500 19 143 151 121734 389 23708 — 0.028Plating room 510 86 63 14178 15615 6407 7686 — 0.767Anodizing 628 76 60 336 8119 479 17272 — 0.39Waste treatment 2652 62 55 245 6031 758 10985 — 0.39
mCd
I
I
•H
I
OS4-1O
O
I0£•HrJ I
i cr> m in CN i i cr>I cn rH m CTI i i oo
m f-» m o i i orH vO CM O I I COO rH Sf ONrH rH <T Cn
tn I lot I oo iON I I CM I 1 - 3 - 1I I I
01 i o i i o ioo i I vo i i co icn cs
I -* I I I r-» I vo1 ' ' ' '
I o t I I o I mi o i i i cn i r--rH in rH
— iCO
ilcn in ON •* I vo i i Mcn f» i -a- i »-4 i i s ^I I I I vo pq tio§ r g"
rJ 4-1c n m o o i i n i i PQ i" °rH O U-| rH | O> I I jC O 3rH rH CM CM H M Q
cn I i I i NO co oI-. | | | I rH -a- IV.+ I + I fcj 03
cdcucn i i i i co iv. m Pg "frH | | | | rH CO CM W Mcs cn r-» CM j>
O\ in r>« rH CN) | |r^ CM i cn CJN. i iI + I I
I
oc•rf
in cn O cn f-. I I o r4vo co in cn f-- i i mcs r-~ cn r-i CM
i vo o cn o\ i i cnI CO rH | | | |
I +030)U .CO 03I co in cn in I I in m rn
I rH rH in rH | | st ^ y3 CO03 >4-ib
>-> 301 wr- I I vo I I cs i j2cs i i i i i cn i 4-1 MI + o v
£3 "il -o o
t I O I I CO I O OI I -a- I I m I
I cn i i t vo i o
cn I I I i in o in
+ +
I
< U r 4 « H > C 4 - > * O 4 J Cd CD M 14-1 > c 4->OO U-4 r -l -H" - - •
4-> TJ -Mcrj O to. . — . -. , -i • •o a) 3 o « ,-4, c
•w acfl or< -H•M 4Jc a(1) r4
I rH | | | CM | rH C C+ + i o £o cjc §CO CJrCI o i I I cn I o *J ci •? i i i r*. i sr «fc rCat 4j4-1cd u<a caM <a
O VO O rH | CO I | OOrHcn CN I + I iI I 4 J 4 Jto u
0) <1)r4 i-l(U (Um co m o I o i i 4-1 4J
CN! rH rH cn I VO | | C £3•H -H
o o•*• I I I I CS CS rH 0) Q)I I I I I cn cn cs cj cj1 1 + t o m
r* IJ3 303 W
CM i i i i cn cn vo a ao oc co o•H -r)
H -ucn + + i i i ac u c o c o
B C C•H 0) CU
CJ CJc c c1 CO I I CM O O Or rH | | <• -rt CJ CJ
4-1CO 03 03r4 QJ CU4-14-14-1
M 1-H C Cd CdM 4-1 M 4-1 (U CJ O
g C O -H -H
r-< e B r H s a o'a'e•1-1 0 4 - i - H O 4 - I O H H• i ^ E O c d 4 J @ o c dr4 OO O Di OO 0) M L O O C e S O O l U ......<D O C M 0) 0 C M 0 0 + 1
Q c d p n C t v i Q ) c d c c C M < !C <1> -H 0) 4J -H -rl <U C 01 -H S 4J -rl -H -'
cdOli-tV
I vO CO O vO I II m + rv cn I I+ + I
cuO rv m O I I in SIsT rH (v. vO I I •*rH CO
in I I rv i i <f im I I co I I + l
T3OO
O I I rH | | CO I 3m i i r-. l i -a- i
I vo I I I CS I COI fv I I I I I CO W TJI + M <dU oi
Q
fr«
I o i i i m i oI rH | | | in I VO
co co rv i \o i irv. + m I I I i' '
(8 O cj _ co O rv o I O I I «< H 3 od o rH rH <r l m l l SIUH)
03
CO
I4H•H
10 Q4J fr«
I
I
I
4-1 rJ Z 4-1y .- «T> o tv p l o I l » O y
O r H r H < r l i n lcs H H o
os l l i i in <r cn «cs i i i i + i vo HI 8cd
I
a> _. a)rQ S J3I rv i | i i oo O O 9 |-'• — CM | | | | in «* r-l ^
CS
cs vo vo m vo i l rvvo + i -a- co i i i1 1 + 0 3
4JrCoc a.
•rl -Hr J _ i n o i n o r v | i c o >J
I I*- O O in I I rHI cs cs vo i i +
I o o m o I I o
OI(-I'»-I>C4JTI4J Cdr H O O H H r H ' H c d O C O Q)O O S O c d r H B c d r4
t-l OOWHr-l'H CdO 03
co0)u .cd 0314H (U
rH m -a- m i i cs 3 «CN rH CO CS to itll1-1
14 3O U3
I CO I I CJ\ I rGI rH I I + I 4J H+ O (U
O OC Co i I o I i m I o ooo I I co I I rv i .H
rH rH CS 4-1 Ccd ot-l -H4J 4-1B cd<U M
I CM I I I •*• I CM CJ 4JI m I i I ON. i i B ci i o Su uBa ocd u
i o i i i cn i o 4J aI in I I I CO I rH CO
CS CS rl rC0) 4-14J0) 0301 ub 0)rv cyi o o i cn i ics I co l CT> I i
iv, m o o i m i i -u
03 M0) 01!-l r401 CU
o cs m in l rv i i E E^ , CO rH rv -H -H<\ rH
Xj tu *Ho o
«a- l l l l rv CTI rH 01 oj+ I I I I rv i + y ol m cdr4 r43 303 to
CO I I I I CO O Oco l l l I rv co cs BECS rH CS CS O O
i-HB BO O•H -H
64-14-1O O O O c O i n l l r H O u C f l C d-a- rH VO I I I O« Ll r4
' ' ' B C B•H 0) 01
CJ UE B B
O C O O C O O I I C O O O Ots I I co
CS 4-1CO 03 03t-i O 0)4-1 4-1 4J
rH M B Cfl CflM *J M 4J Q) CJ CJ
B B CJ -rl -rlrH OI tH (U B TJ "Or H S S l - l S S O B E• H O 4 J - H O 4 J O M H4 - i S q c d 4J E O cd
M C / 3 O I — O O O I l-i CO O OS 00 0) ......cu o e 1-4 o> o n M oo + lW 00 4-1 pi 00 T) H w 00 4J ci oo -H E-4 >
O I C d E B E N O I C d E E B N « CE 01 -rl CO 4-1 -H -rl 0) B OJ -H 01 -M -rl -H Q)
I
cH!
o
5 u3
pa -5 u<
&i
I
oc•rTrJ
&«
I
o o rv os l l cs•* m rv co i l rHI I I I I
O co O O I I Ol m co in o j I ol m -a- -a- rH coco cn -a- vo co
o i i o i i cs i-a- i i rH i i -a- il + l
o i 101 i cs i< f l 1 0 1 l o tvo m vocn
101 l l o l ol o i i i o l o
rH VO O rH | VO I ICO I CM I rH I II I I
rv in CO O I O I Iin rv cjv co
CTl I I I I VT CS rH+ 1 I I I rH <• ++ +
NO i i | i m rv o
O O I 3 O C d r H E C f l
I
I
l o vo rv m l l <sI rH + CS vO I I I
03
U .(0 0314H (!)
I in O O O I I O rl yl -a- cn o co i i cs 3 ca•>f •* co vo to IIH
0) WrH I I rH I I vO I -CCO | I I I I CS | 4J HI I O CD
B-gO O
o i l m l l in l o om i l vo i i rv i -HrH CS CS 4-1 Ccd o
CO rl•P 4-1E Cd0) rlI I I rv i cs y
I CO I I I I I rH TJ+ + W cfl
8 £< rl
01$I
_co I I I rv | cs BEI I I o 0 1u u
rCl o t l l co i m 4J Ei cn i i i vo i -a- a•a- <•o rv m .*cs o m U 01 4JCO rH Z 4J
M oj wM Q) to
rl 0)
I
ml l l i P~ vo or-l O CO rv
•if CO CO Cn O\ I I rHcn + vt cs co i I I
ocO r- O o o i l rv -Ho NO o in o i i NO rJcn vo o in m mCS CO -if rv rH -cr
rH r-l CO O
00 rH -a* tH I Cn I I OOrH-4- rH I <!• | CO | |1 1 1 + «ta to,01
01 0)o in o o l m l l 4J 4-1CM cs co cs i <r i i BErH CO rH rv -H -rl
CJ\HH I4HO O
vo i i i i m vo m (DO)-a" i i i i rv cs + o cj+ l + cd cdM M3 3
Ico i l i l o o m
I
0! M IIH > e 4JrH OOU-4tH'H
4J T3 4-1CO O 03
U) 03
vO | I | | O tv CO BEvt* vo *a* vo o oE EO O•H -Ha 4-> 4JrHcocncjiini i m O H C O C O
I rH I I VO I I 1-H CU rl rl+ I + -U 4JB E E
•H Q) 01CJ CJ
B E Ei n c o o o m i i o o o ov o m c o - a - c o i i m - H O OCM <• CS rH fv 4-1cd 03 ta
rl 0) 0)4-1 4-1 4-1
M M E (fl CdM 4-1 M 4-1 01 CJ O
E E O -H -HrH O) r-f QJ B TJ TJ
• H O 4 J -H O 4)J U M M4 J 3 o c d 4 - i a o c dM C/3 O p ^ ) f-i cy3 O f"**t 00 c .. .» ••01 O B t-i 0) O C rl 00 + I
O i c O E B B N 0) rt C C C 'N <E Ol -H 0) *-> «rl -rl 0) B 0) >r( O 4J -H -H O)O I » - l < 4 H r > C 4 - l T 3 4 J C O - . . - . . .- • - 01 T*"l ww ** T~n *n \w %rff wj
O d ) 3 0 c d i H E C dW QrQWtuCj<3
ftRJ*G0398
cd4-10>s
II
I co cn cs oo i i <fI vt co cn m i l co+ 1 + 1 l
I O CO O O I I OI O cn o O I I invO CM o vO 00VO rH O\ in CS-a- rv
•oto01
I
I
co i i cn l i o i-a- i l vo l i m li i +
O I I O I I O01 t o I l rvO m <fO
I NO i | I N£) | CDI m I l I rH i rv
i o i i i o i oi o l t l o l o-a- CM<• \oocn
8«S
co co rv cn I cs i i
a >| o o oo cs mrv \o cs vo -a-
•HWaCfl 6-8
1 I I I rH O OI l i i cs m rv+ 1 1
ri o i i i i o o mM Ofl O I I I I O O CS
•HtQ Q4-1
rv vo o rH co i l inNO m CM co m l I mI I + I + I
4-1 fr-e
I O cn -a- rv | i inI 1-1 I rv vo i ii
il
I
0)Arl<ll
VO VO rH CO I rH | | PQ r- -n+ I + I I CM £ Q
* 8 »SO 4J M 2 4-1_ y o o r v o i o i i J O y- — 3 od o o vo o i m l I « w 3
UH
Icd 8-S
co i i i i m
4-1
ec oc•H o rv o o rv i i cn -Hcn co rH rv co cnvo cn co vo o rH
rH CS
vo
cdr - I O O U - i r H ' H C d O t a 0)O O l S O C d r H B O ) r4
ai u UH > E 4-1 -ar - I O O U H i H - H c f l O t O
wa>urv m in m I l co co 01rH o oo O i I oo UH 01O O CN O rH ri y.... . 3 cdO O O O O ta UH
CO
<U 03\o i I 1-4 i i m- ivO I I CM I I -a- I 4-1 rli l l 0 ( U
c:go oO CO C BCN I I vO I I vO I O OO I I O I I i-l I -rl
BoCS rH t-l -H
4J 4JB tdOJ r4
I CS I I I rH I VO y 4Ji m i l i <r l cn c EI + 1 O Q )y y
B ocd ym m AI O I I I vo | o 4-i El o I I I oo i o• • • r< -CO O O tt> 4J
cd ta01 03M 01
-T O C7l O I CO I I OOrHVt rH + in I + I I+ 1 1 4 - 1 4 - 1
U 030> 0>M H
CO vO <• 0) 01m rH o cn I m I I 4-14-1rH O O O I in I I BE
o o o o om H o oco i l l l rv -a- vo o> 01+ i l i i -a- -a- o> y yi + i to 03
U-4 U-lrl3 303 03
VO rH O C Gcs <r o o oco cn m rHCO vO CO rH
000 E B.3.3a 4J 4J
CUrlI + I + + 4J 4J
E B B•H 01 O>y y<TI oo m m EBB
C S r H O C O C S I I v O O O Oo o o o o i i - a - - r - i y yooooo o t d t a t a
rl 0) 014-14-14-1
M M E cfl cdM 4-1 rH 4J Q) y yC E y -H -HrH 0) r-l Ol B -O T3r H S S r-l 0 0 O E C•H O 4-1 i H O 4 - I C J M M4-J S O CO 4J B O 0)r4 co 5 a; oo a) IH oo o PS oo 01 ......
O J O E r l O I O B r l O O + lW 00 -P Oi CO-H fH M 00 4-i Pi 00-H E-i >
O l t O E E B N O J C d E B B N <B 0) -H 0) 4J -rt -H 0) B Ot -rl 0) 4J -rl -H 01
TABLE 13
SUMMARY OF COMPARISON
CONTAMINANTS ON TYPES OF SURFACES
ALL BUILDING AREAS COMBINED
____Percent Difference in Concentration____________________Contaminant________________
Surface Pb Ag Cd _Cr_ Cu Ni Zn CN
Light fixtures -67 +10 -21 -26 +53 -11 -61 +25I beams +35 -12 +12 -67 +18 -41 -36 -23Air ducts, con-ditioners & blowers -38 -8 -16 +89 -14 +72 -35 +3
Overhead pipes& electrical conduits -48 +11 -13 -89 +22 -62 +53 +16
Misc. wood surfaces -65 +6 -38 +3 +8 -19 -56 -42Misc. metal surfaces +79 -5 +38 +26 -73 +24 +74 +26
+: Indicates average concentration of contaminant is larger onthe surface of interest than on other surfaces.
-: Indicates average concentrations of contaminant is smaller onthe surface of interest than on other types of surfaces.
TlOc708!
f
UNSCANNED ITEM(S)
ONE OR MORE OF THE FOLLOWING ITEMS MAY BE ASSOCIATEDWITH THIS DOCUMENT:
PHOTOGRAPHSDRAWINGS
OVERSIZED MAPSROLLED MAPS
PLEASE CONTACT THE CERCLA RECORDS CENTER TO VIEW THEITEM(S)
1 CEI-
s8«S§"I**xo§I"5ock
i •
nu:
uJ^
S:QU)
O
a g(L5 O<m
-!_1 «-" W
0 V K-£ z S
<
i I