rp sp19 999 6300 007 2 steel piping fabrication

47
To: Project Engineering Manager, SP19 A4 A3 A2 A1 A0 1 PI * 2 PI * 3 PI * Date: 08-May-2010 Contract No.: POGC 655-89-35 DESCRIPTION / TITLE AFD RP-SP19-999-1300-030 2 RP-SP19-999-1300-007 CC: DOCUMENT / DRAWING TRANSMITTAL 2 24 REV. DOCUMENT / DRAWING No. STATUS HARD COPY SET 1 AFD 2 SH./VOL. No. CLASS RP-SP19-999-1300-004 Petro Pars Iran Company No. 9, Maaref St., Farhang Blv., Saadat Abad, Tehran/Iran, Zip Code: 1997743881 Tel: +98(21)22096701-4 - Fax: +98(21)22096538 Mr. M.Hosseinkhani SIZE ELEC. SET 2 Attention: Mr. A.Nassori 3 2 AFD 3 Transmittal No: SP19-SNT/PPI-T-02388 2 1 3 6 1 Piping Design Job Specification DISC. 21 Engineering Design Specification for Piping Supports Pneumatic Testing of Above Ground Piping Systems Job Specification PPI NATIONAL IRANIAN OIL COMPANY SOUTH PARS GAS FIELD DEVELOPMENT PHASE 19, TOMBAK-IRAN ONSHORE FACILITIES 4 PI * 5 PI * 6 PI * 7 PI * 8 PI * 9 PI * 10 PI * 11 PI * Class 1: For Approval IFA: Issued for Approval AFD: Approved for Design 2: For Review IFR: Issued for Review AFC: Approved for Construction 3: For Information IFI: Issued for Information IFP: Issued for PO Authorized by: Recipient Signature: Signature: Date: Fabrication of Seamless Pipes for Pipelines (sour effluents) Fabrication of Longitudinally Submerged Arc Welded Pipes for Pipelines (Sour Effluents) Internal Cleaning of Piping and Vessels Job Specification Erection of Glass Reinforced Plastic Piping Job Specification 3D Electronic Models Job Specification Model Review Check List Installation Rulers for Jacketing Piping-Job Specification Spring Hangers and Supports Job Specification 3 1 AFD 3 2 2 1 3 AFD 3 2 7 RP-SP19-999-1300-062 Please return above mentioned documents with Comments/Approved by: 2 17 1 AFD 3 2 2 RP-SP19-999-1300-074 2 AFD 2 AFD 2 2 3 RP-SP19-999-1300-031 2 7 1 1 6 7 6 3 2 1 AFD 3 2 1 AFD 11 AFD 1 Remarks: 10 RP-SP19-999-1300-032 2 RP-SP19-999-1300-043 2 RP-SP19-999-1300-075 RP-SP19-999-1300-042 2 RP-SP19-999-1300-071 Status Page 1 of 2

Upload: eghashangzadeh

Post on 16-Dec-2015

83 views

Category:

Documents


7 download

TRANSCRIPT

  • To:

    Project Engineering Manager, SP19

    A4 A3 A2 A1 A0

    1 PI *

    2 PI *

    3 PI *

    Date:08-May-2010

    Contract No.: POGC 655-89-35

    DESCRIPTION / TITLE

    AFDRP-SP19-999-1300-030 2

    RP-SP19-999-1300-007

    CC:

    DOCUMENT / DRAWING TRANSMITTAL

    2 24

    REV

    .

    DOCUMENT / DRAWING No. STATUS HARD COPYSET

    1 AFD2

    SH./VOL.No. CLASS

    RP-SP19-999-1300-004

    Petro Pars Iran CompanyNo. 9, Maaref St., Farhang Blv., Saadat Abad, Tehran/Iran, Zip Code: 1997743881Tel: +98(21)22096701-4 - Fax: +98(21)22096538

    Mr. M.Hosseinkhani

    SIZEELEC.SET

    2

    Attention:

    Mr. A.Nassori

    3 2

    AFD 3

    Transmittal No: SP19-SNT/PPI-T-02388

    21

    3

    6 1

    Piping Design Job Specification

    DISC.

    21

    Engineering Design Specification for Piping Supports

    Pneumatic Testing of Above Ground Piping Systems Job Specification

    PPI

    NATIONAL IRANIAN OIL COMPANYSOUTH PARS GAS FIELD DEVELOPMENT

    PHASE 19, TOMBAK-IRANONSHORE FACILITIES

    4 PI *

    5 PI *

    6 PI *

    7 PI *

    8 PI *

    9 PI *

    10 PI *

    11 PI *

    Class1: For Approval IFA: Issued for Approval AFD: Approved for Design2: For Review IFR: Issued for Review AFC: Approved for Construction3: For Information IFI: Issued for Information IFP: Issued for PO

    Authorized by: Recipient Signature:Signature: Date:

    Fabrication of Seamless Pipes for Pipelines (sour effluents)

    Fabrication of Longitudinally Submerged Arc Welded Pipes for Pipelines (Sour Effluents)

    Internal Cleaning of Piping and Vessels Job Specification

    Erection of Glass Reinforced Plastic Piping Job Specification

    3D Electronic Models Job Specification

    Model Review Check List

    Installation Rulers for Jacketing Piping-Job Specification

    Spring Hangers and Supports Job Specification

    3

    1

    AFD

    3

    2

    2

    1

    3

    AFD

    32 7RP-SP19-999-1300-062

    Please return above mentioned documents with Comments/Approved by:

    2 17 1

    AFD 3 2

    2

    RP-SP19-999-1300-074 2

    AFD

    2AFD

    2

    2

    3

    RP-SP19-999-1300-031 2 7

    1

    1

    6

    7

    6

    3 2

    1 AFD 3 2

    1 AFD

    11

    AFD

    1

    Remarks:

    10

    RP-SP19-999-1300-032 2

    RP-SP19-999-1300-043 2

    RP-SP19-999-1300-075

    RP-SP19-999-1300-042 2

    RP-SP19-999-1300-071

    Status

    Page 1 of 2

    g.shirmohammadiStamp

  • Date:08-May-2010

    Contract No.: POGC 655-89-35

    Transmittal No: SP19-SNT/PPI-T-02388

    PPI

    NATIONAL IRANIAN OIL COMPANYSOUTH PARS GAS FIELD DEVELOPMENT

    PHASE 19, TOMBAK-IRANONSHORE FACILITIES

    A4 A3 A2 A1 A0

    12 PI *

    13 PI *

    14 PI *

    15 PI *

    16 PI *

    17 PI *

    18 PI *

    19 PI *

    20 PI *

    2

    3

    2

    3

    AFD

    AFD 3

    3

    3AFDRP-SP19-999-6600-002 2 8 1

    RP-SP19-999-6300-006

    AFD

    RP-SP19-999-1300-077

    2

    AFD

    14RP-SP19-999-6600-001

    HARD COPYSET

    STATUS

    3

    1

    3AFD

    2AFD

    AFD

    AFDSite Welding of Carbon Steel for Pipe Lines to API 1104 (Sour Effluents)

    Site Welding of Carbon Steel Pipelines to API 1104 (Sweet Effluent)

    2

    23

    Steel Piping Fabrication

    Shop & Field Painting Specification

    Internal Lining Job Specification

    1

    1

    1

    SH./VOL.

    1

    11

    1

    11 1

    2RP-SP19-999-6300-001

    No.

    3

    2

    SIZEELEC.SETCLASSDESCRIPTION / TITLEDOCUMENT / DRAWING No. R

    EV.

    7

    2 5

    2

    242

    19

    1

    2

    2

    RP-SP19-999-6300-007 2 11

    RP-SP19-999-6300-008 2

    RP-SP19-999-6300-005

    RP-SP19-999-6300-009 2

    2

    DISC.

    Material and Fabrication of Hot Formed Elbows and Hot Pressed Elbows for Pipelines (Sour Effluents)

    Welding of Pressure Containing Piping and Equipment

    Welding of UNS 31254 Alloy

    Specification for Fabrication and Welding of Piping Systems in Cupronickel and Associated Materials

    Page 2 of 2

  • NATIONAL IRANIAN OIL COMPANY SOUTH PARS GAS FIELD DEVELOPMENT

    PHASE 19 ONSHORE FACILITIES

    DOCUMENT TITLE: STEEL PIPING FABRICATION Class: 1

    DOCUMENT NUMBER: RP-SP19-999-6300-007 Rev. No.: 2

    Page 1 of 11

    PPL/IOEC/PPI CONSORTIUM

    NIOC Pars Oil & Gas Company

    PPI

    This

    doc

    umen

    t is t

    he p

    rope

    rty o

    f N.I.

    O.C

    .. A

    ny u

    naut

    horiz

    ed a

    ttem

    pt to

    repr

    oduc

    e it,

    in a

    ny fo

    rm, i

    s stri

    ctly

    pro

    hibi

    ted.

    NATIONAL IRANIAN OIL COMPANY

    SOUTH PARS GAS FIELD DEVELOPMENT

    PHASE 19 ONSHORE FACILITIES

    DOCUMENT TITLE

    STEEL PIPING FABRICATION

    DOCUMENT NUMBER

    RP-SP19-999-6300-007

    2 02-May-2011 Sh.Doorfard A.Sheykhi R.Maleki A.Nassori XXXXX Approved For Design

    1 25-Dec-2010 H.Stiri J.Masoumi R.Maleki A.Nassori XXXXX Approved For Design

    0 03.Nov-2010 H.Stiri J.Masoumi R.Maleki A.Nassori XXXXX Issued For Approval

    REV DATE ISSUE

    PREPARED CHECKED AUTH PPI POGC

    PURPOSE OF ISSUE APPROVED

    a.ahmadiText BoxSh.D

    a.ahmadiText BoxA.Sh

    a.ahmadiText BoxR.M

  • NATIONAL IRANIAN OIL COMPANY SOUTH PARS GAS FIELD DEVELOPMENT

    PHASE 19 ONSHORE FACILITIES

    DOCUMENT TITLE: STEEL PIPING FABRICATION Class: 1

    DOCUMENT NUMBER: RP-SP19-999-6300-007 Rev. No.: 2

    Page 2 of 11

    PPL/IOEC/PPI CONSORTIUM

    NIOC Pars Oil & Gas Company

    PPI

    This

    doc

    umen

    t is t

    he p

    rope

    rty o

    f N.I.

    O.C

    .. A

    ny u

    naut

    horiz

    ed a

    ttem

    pt to

    repr

    oduc

    e it,

    in a

    ny fo

    rm, i

    s stri

    ctly

    pro

    hibi

    ted.

    TABULATION OF REVISED PAGES

    Page Rev-0 Rev-1 Rev-2 Rev-3 Rev-4 Page Rev-0 Rev-1 Rev-2 Rev-3 Rev-4 1 x 36 2 x 37 3 x 38 4 x 39 5 x x 40 6 x x 41 7 x x 42 8 x 43 9 x x 44 10 x 45 11 x x 46 12 47 13 48 14 49 15 50 16 51 17 52 18 53 19 54 20 55 21 56 22 57 23 58 24 59 25 60 26 61 27 62 28 63 29 64 30 65 31 66 32 67 33 68 34 69 35 70

  • NATIONAL IRANIAN OIL COMPANY SOUTH PARS GAS FIELD DEVELOPMENT

    PHASE 19 ONSHORE FACILITIES

    DOCUMENT TITLE: STEEL PIPING FABRICATION Class: 1

    DOCUMENT NUMBER: RP-SP19-999-6300-007 Rev. No.: 2

    Page 3 of 11

    PPL/IOEC/PPI CONSORTIUM

    NIOC Pars Oil & Gas Company

    PPI

    This

    doc

    umen

    t is t

    he p

    rope

    rty o

    f N.I.

    O.C

    .. A

    ny u

    naut

    horiz

    ed a

    ttem

    pt to

    repr

    oduc

    e it,

    in a

    ny fo

    rm, i

    s stri

    ctly

    pro

    hibi

    ted.

    TABLE OF CONTENT

    1. GENERAL STATEMENT ........................................................................ 4 2. ADDENDUM .......................................................................................... 5 - TEP GENERAL SPESIFICATION NO: SP-TCS-171 REV. 6

  • NATIONAL IRANIAN OIL COMPANY SOUTH PARS GAS FIELD DEVELOPMENT

    PHASE 19 ONSHORE FACILITIES

    DOCUMENT TITLE: STEEL PIPING FABRICATION Class: 1

    DOCUMENT NUMBER: RP-SP19-999-6300-007 Rev. No.: 2

    Page 4 of 11

    PPL/IOEC/PPI CONSORTIUM

    NIOC Pars Oil & Gas Company

    PPI

    This

    doc

    umen

    t is t

    he p

    rope

    rty o

    f N.I.

    O.C

    .. A

    ny u

    naut

    horiz

    ed a

    ttem

    pt to

    repr

    oduc

    e it,

    in a

    ny fo

    rm, i

    s stri

    ctly

    pro

    hibi

    ted.

    GENERAL STATEMENT

    The attached TOTAL EXPLORATION PRODUCTION (TEP) General Specification No. : SP-TCS-171 Rev. 6 is confirmed as the Project Specification, except as amended herein and renumbered/reissued as Specification No. : RP-SP19-999-6300-007 for SOUTH PARS GAS FIELD DEVELOPMENT, Phase 19 Project.

  • NATIONAL IRANIAN OIL COMPANY SOUTH PARS GAS FIELD DEVELOPMENT

    PHASE 19 ONSHORE FACILITIES

    DOCUMENT TITLE: STEEL PIPING FABRICATION Class: 1

    DOCUMENT NUMBER: RP-SP19-999-6300-007 Rev. No.: 2

    Page 5 of 11

    PPL/IOEC/PPI CONSORTIUM

    NIOC Pars Oil & Gas Company

    PPI

    This

    doc

    umen

    t is t

    he p

    rope

    rty o

    f N.I.

    O.C

    .. A

    ny u

    naut

    horiz

    ed a

    ttem

    pt to

    repr

    oduc

    e it,

    in a

    ny fo

    rm, i

    s stri

    ctly

    pro

    hibi

    ted.

    ADDENDUM

    The following items refer to the attached TEP General Specification No. SP-TCS-171 REV. 6. The clauses set out below modify or replace the existing clauses in the original specification as noted.

    GENERAL COMMENTS

    The following items which are used in this general job specification are deleted or replaced by:

    COMPANY: In this project COMPANY shall mean National Iranian Oil Company/Pars Oil & Gas Company (N.I.O.C-P.O.G.C), which it means the legal owner of what is built. CONTRACTOR: Consortium of PPL, IOEC and PPI shall be read as CONTRACTOR or his nominated representative, which signs the contracts and orders on behalf of the company. ENGINEERING SUB-CONTRACTOR BY CONTRACTOR: Consortium of Sazeh, Nargan & Technimont shall be read as ENGINEERING SUB-CONTRACTOR, which it means the party which has entered under a Contract Agreement with CONTRACTOR for the design and engineering of the Onshore Facilities regarding the South Pars Gas Field Development, Phase19 Project. Manufacturer: shall mean any person, firm or company which manufacture or supply equipment or services for the performance of any item of the work. Work: shall mean works and/or services entrusted by ENGINEERING SUB-CONTRACTOR under the contract with CONTRACTOR.

    INSPECTION AGENCY: This term designates the Inspection Bodies as a third party which will be nominated by CONTRACTOR and approved by COMPANY.

    PARTICULAR COMMENTS ON FOLLOWING PARAGRAPHS: 3. TOTAL CONTRACTUAL REFERENCE DOCUMENTS

    b) Total general specifications

    2

  • NATIONAL IRANIAN OIL COMPANY SOUTH PARS GAS FIELD DEVELOPMENT

    PHASE 19 ONSHORE FACILITIES

    DOCUMENT TITLE: STEEL PIPING FABRICATION Class: 1

    DOCUMENT NUMBER: RP-SP19-999-6300-007 Rev. No.: 2

    Page 6 of 11

    PPL/IOEC/PPI CONSORTIUM

    NIOC Pars Oil & Gas Company

    PPI

    This

    doc

    umen

    t is t

    he p

    rope

    rty o

    f N.I.

    O.C

    .. A

    ny u

    naut

    horiz

    ed a

    ttem

    pt to

    repr

    oduc

    e it,

    in a

    ny fo

    rm, i

    s stri

    ctly

    pro

    hibi

    ted.

    Substitute:

    SP TCS 112 by : RP-SP19-999-1300-001 SP TCS 173 by : RP-SP19-999-1300-030 SP TCS 175 by : RP-SP19-999-1300-031 SP TCS 611 by : RP-SP19-999-6300-001 SP TCS 612 by : RP-SP19-999-6300-002 SP TCS 615 by : RP-SP19-999-6300-005 SP TCS 620 by : RP-SP19-999-6300-006 SP TCS 622 by : RP-SP19-999-6300-003

    4. INFORMATION SOURCES 4.1 PIPING MATERIAL CLASSES

    Substitute: SP TCS 112 by: RP-SP19-999-1300-001

    4.3 LINE LIST

    The paragraph shall be replaced by following paragraph; Mechanical data section of line list shows Line Identification (Service or Fluid Code, Serial No., Nominal Diameter, Piping Class, Insulation type and thickness), Painting System, Piping Routing (Termination to/of the line), Reference P&ID No., Operating and Design conditions (Pressure and Temperature), Testing Requirements, Density, Tracing inf. (If Any), Stress Analysis grades, NDT Class, Heat treatment and other requirements, for each project according to the projects need. Additional information such as wall thickness is available in the relevant piping material classes.

    6. MATERIALS 6.1 SUPPLY

    Article a in this section (Materials furnished by TOTAL free issue) shall be deleted completely.

    b) Materials supplied by CONTRACTOR

    The first sentence shall be replaced by following:

    2

    2

  • NATIONAL IRANIAN OIL COMPANY SOUTH PARS GAS FIELD DEVELOPMENT

    PHASE 19 ONSHORE FACILITIES

    DOCUMENT TITLE: STEEL PIPING FABRICATION Class: 1

    DOCUMENT NUMBER: RP-SP19-999-6300-007 Rev. No.: 2

    Page 7 of 11

    PPL/IOEC/PPI CONSORTIUM

    NIOC Pars Oil & Gas Company

    PPI

    This

    doc

    umen

    t is t

    he p

    rope

    rty o

    f N.I.

    O.C

    .. A

    ny u

    naut

    horiz

    ed a

    ttem

    pt to

    repr

    oduc

    e it,

    in a

    ny fo

    rm, i

    s stri

    ctly

    pro

    hibi

    ted.

    The CONTRACTOR shall furnish all materials necessary to perform the work.

    6.3 STORAGE Following sentence in the paragraph:

    Their plug shall be maintained in the open position at all time Shall be replaced by: Their Ball shall be maintained in the open position at all time

    7. FABRICATION 7.1 GENERAL

    In the first paragraph, The CONTRACTOR shall submit for TOTAL approval Shall be replaced by: The CONTRACTOR shall submit for INSPECTION AGENCY and COMPANY approval

    7.2 EXECUTION OF THE WORK

    - In the last paragraph, The CONTRACTOR shall notify the INSPECTION AGENCY immediately. Shall be replaced by: The CONTRACTOR shall notify the INSPECTION AGENCY and COMPANY immediately. - The following paragraph shall be added to this article: The prefabrication shop for Stainless Steel and Nickel Alloys should be separate from the fabrication shop which is used for Carbon and Alloy Steels.

    7.5 THREADING - Replace ASME Code B1.20 by ASME Code B1.20.1

    2

  • NATIONAL IRANIAN OIL COMPANY SOUTH PARS GAS FIELD DEVELOPMENT

    PHASE 19 ONSHORE FACILITIES

    DOCUMENT TITLE: STEEL PIPING FABRICATION Class: 1

    DOCUMENT NUMBER: RP-SP19-999-6300-007 Rev. No.: 2

    Page 8 of 11

    PPL/IOEC/PPI CONSORTIUM

    NIOC Pars Oil & Gas Company

    PPI

    This

    doc

    umen

    t is t

    he p

    rope

    rty o

    f N.I.

    O.C

    .. A

    ny u

    naut

    horiz

    ed a

    ttem

    pt to

    repr

    oduc

    e it,

    in a

    ny fo

    rm, i

    s stri

    ctly

    pro

    hibi

    ted.

    - In the last paragraph, Seal welds are prohibited on threaded assemblies, except where specifically required by the Engineering Company. shall be replaced by: Seal welds are prohibited on threaded assemblies, except where specifically required by ENGINEERING COPMANY / CONTRACTOR Engineering Department and approved by COMPANY.

    8. WELDING

    Substitute: SP TCS 611 by : RP-SP19-999-6300-001 SP TCS 612 by : RP-SP19-999-6300-002 SP TCS 615 by : RP-SP19-999-6300-005 SP TCS 620 by : RP-SP19-999-6300-006 SP TCS 622 by : RP-SP19-999-6300-003

    8.1 WELDING PROCEDURE SPECIFICATION (WPS) Add: A weld summary shall provide a list of the piping classes with the applicable WPS identification numbers, qualified thickness ranges, heat treatment condition, material grades, minimum and maximum design temperature, and service conditions.

    8.3 WELDERS AND WELDING OPERATORS QUALIFICATION

    Fifth sentence, delete and replace entirely this sentence and substitute by: Welding and welding operators qualification tests shall be in accordance with ASME IX. Sixth sentence, replace the following sentence: Only welders and welding operators successful in non-destructive and destructive tests By: At the discretion of the COMPANY, only welders and welding operators successful in non-destructive inspection and/or destructive tests

  • NATIONAL IRANIAN OIL COMPANY SOUTH PARS GAS FIELD DEVELOPMENT

    PHASE 19 ONSHORE FACILITIES

    DOCUMENT TITLE: STEEL PIPING FABRICATION Class: 1

    DOCUMENT NUMBER: RP-SP19-999-6300-007 Rev. No.: 2

    Page 9 of 11

    PPL/IOEC/PPI CONSORTIUM

    NIOC Pars Oil & Gas Company

    PPI

    This

    doc

    umen

    t is t

    he p

    rope

    rty o

    f N.I.

    O.C

    .. A

    ny u

    naut

    horiz

    ed a

    ttem

    pt to

    repr

    oduc

    e it,

    in a

    ny fo

    rm, i

    s stri

    ctly

    pro

    hibi

    ted.

    9. ASSEMBLY 9.1 ASSEMBLY OF FLANGED PIPING

    In the 7th paragraph the following sentence: if specified by the ENGINEERING COMPANY Shall be replaced by: if specified by the ENGINEERING COMPANY / CONTRACTOR and approved by COMPANY.

    10.2 EXTEND OF INSPECTION Table 1: NDT Requirements

    For Service conditions: Hydrocarbons (liquid or gas), pressure class 300 , girth welds add the following general note: For fluid of category M, minimum extent of radiography shall be 20% For Service conditions Hydrocarbons (liquid or gas), pressure class 300 and 600, girth welds delete: E and F (magnetic or dye penetrate examination).

    10.2.3-Aditional non-destructive inspections In this paragraph, after INSPECTION AGENCY and/or COMPANY shall be added.

    10.3 TYPES AND METHODES OF EXAMINATION 10.3.2-Radiogeraphic Inspection

    d) Spot examination In the first sentence of the last paragraph, INSPECTION AGENCY shall be replaced by COMPANY e) Socket welds Include this paragraph in the Table 1: NDT requirements 10.3.5-Ultrasonic Testing (UT): Add:

    2

  • NATIONAL IRANIAN OIL COMPANY SOUTH PARS GAS FIELD DEVELOPMENT

    PHASE 19 ONSHORE FACILITIES

    DOCUMENT TITLE: STEEL PIPING FABRICATION Class: 1

    DOCUMENT NUMBER: RP-SP19-999-6300-007 Rev. No.: 2

    Page 10 of 11

    PPL/IOEC/PPI CONSORTIUM

    NIOC Pars Oil & Gas Company

    PPI

    This

    doc

    umen

    t is t

    he p

    rope

    rty o

    f N.I.

    O.C

    .. A

    ny u

    naut

    horiz

    ed a

    ttem

    pt to

    repr

    oduc

    e it,

    in a

    ny fo

    rm, i

    s stri

    ctly

    pro

    hibi

    ted.

    For P. N 1 through P. N 5 material, piping of thickness 40 mm and above 100% ultrasonic examination shall be required on butt welds in addition to the specified radiography examination. Ultrasonic examination shall be regarded as a complementary examination to the radiography for the detection of Planar Flaws. Acceptance criteria shall be in accordance with ASME B31.3.

    10.4 STANDARDS OF ACCEPTANCE

    In the 4th paragraph, after INSPECTION AGENCY and COMPANY shall be added.

    10.5 PRODUCTION HARDNESS TESTING:

    Add a new paragraph 10.5.

    Production hardness test is mandatory after heat treatment and shall be performed on 10% of welds in each furnace heat treated batch and 100% of those which are locally heat treated. Unless otherwise required hardness results shall not exceed 225 HB for P. No. 1, P. No. 3 and P. No. 4 materials and 241 HB for P. No. 5 material after post weld heat treatment (PWHT). For sour service hardness test on P1 material shall be limited to 200HB. A hardness test shall consist of at least one reading on the deposited weld metal and one reading on HAZ as close as practicable to the edge of the weld. Personnel performing hardness testing shall be familiar with all hardness testing procedures and test methods. Procedures and test methods used for portable hardness testing shall be in accordance with ASTM A833 or ASTM E110 as applicable and submitted to COMPANY for agreement. Hardness testing results shall be expressed in Brinell numbers. The hardness report shall indicate actual hardness reading for the test method used, type of hardness tester, personnel conducting hardness tests, type of material, and calibration.

    12. TESTING 12.1 GENERAL

  • NATIONAL IRANIAN OIL COMPANY SOUTH PARS GAS FIELD DEVELOPMENT

    PHASE 19 ONSHORE FACILITIES

    DOCUMENT TITLE: STEEL PIPING FABRICATION Class: 1

    DOCUMENT NUMBER: RP-SP19-999-6300-007 Rev. No.: 2

    Page 11 of 11

    PPL/IOEC/PPI CONSORTIUM

    NIOC Pars Oil & Gas Company

    PPI

    This

    doc

    umen

    t is t

    he p

    rope

    rty o

    f N.I.

    O.C

    .. A

    ny u

    naut

    horiz

    ed a

    ttem

    pt to

    repr

    oduc

    e it,

    in a

    ny fo

    rm, i

    s stri

    ctly

    pro

    hibi

    ted.

    - Substitute: SP TCS 173 by : RP-SP19-999-1300-030 SP TCS 175 by : RP-SP19-999-1300-031

    - In the 4th paragraph, the first sentence shall be replaced by: The CONTRACTOR shall submit all testing procedure for INSPECTION AGENCY and COMPANY approval

    15. CARE AND MAINTENANCE 15.1 EQUIPMENT

    In the first paragraph, supplied by the Engineering Company Shall be replaced by: supplied by the ENGINEERING COMPANY / CONTRACTOR and approved by COMPANY.

    2

  • 6

    5

    4

    3

    Rev. n

    TOTAL

    TOTAL EXPLORATION PRODUCTION

    GENERAL SPECIFICATION

    PIPING - VESSELS - WELDING

    SP- TCS -171

    STEEL PIPING FABRICATION

    Revision paragraphs 3, 4.1, 4.2.1, 4.3, 5.3, 5.4, 6.1,

    March 98 6.3, 7.3, 7.5, 7.9 (new), 7.10, 7.11, 7.12, 8, 8.3, 8.4, 8.5, 9.1, 9.2, 10.1, 10.2, 10.2.1, 10.2.2, 10.2.3, 10.3.2, 10.4, 12.1, 12.3 and Appendix A

    June 91 Revision paragraph 7.9

    February 91 New issue

    November 87 Up dating

    Date Subject of the revision

    This document is the property of TOTAL. it must not be reproduced or transmitted to others without written authorization from the company.

  • TOTAL TEPIDO

    I -SCOPE

    STEEL PIPI='iG FABRICATI0;-.1

    co:--;T:-ns

    2- DEFINITION OF CONTRACTING PARTIES

    3 -CONTRACTUAL REFERENCE DOCUMENTS

    4- INFORMATION SOURCES

    4. I - Piping material classes 4.2 -Drawings 4.3 -Lines list 4.4- Isometric index

    5- EXTENT OF SHOP FABRICATED PIPEWORK

    5.1 - Carbon steel 5.2- Alloy 5.3 -Branches 5.4 - Attachments 5.5- Field runs

    6 - MATERIALS

    6.1 -Supply 6.2 - Identification 6.3 - Storage

    7 - FABRICATION

    7.1 -General 7.2- Execution of the work 7.3 - Fabrication tolerances 7.4 - Cutting 7.5 - Threading 7.6- Alignment of components to be assembled 7.7- Requirements for location of welds 7.8 - Socket welds 7.9- Threaded joints 7.10- Bends 7.11 - Elbows 7.12- Branch connections 7.13- Oritice runs 7. 14 - Galvanized piping

    SP- TCS- 171

    Page 2 nf 3-t

    Date: .Janua., 1998

    Page

    5

    5

    6

    7

    7 7 8 8

    9

    9 9 9 9 10

    10

    10 II II

    II

    II 12 12 13 13 14 14 14 15 15 16 \6 17 17

  • TOTAL TEP/DO

    7.15- Flange bolt holes 7.16- Cleaning

    STEEL PIPI:'IG FABRIC.-\ TIOl'l

    7. 17- Extra length for site adjustment

    8- WELDING

    8.1 -Welding procedure specifications (W.P.S.) 8.2- Welding procedure qualifications (P.Q.R.) 8.3- Welders and welding operators qualifications 8.4 - Welded connections 8.5- Post Weld Heat Treatment (PWHT) 8.6- Field weld location

    9 -ASSEMBLY

    9.1 -Assembly of flanged piping 9.2- Assembly of piping to equipment

    10- WELDING INSPECTION

    I 0.1 - General I 0.2 - Extent of inspection I 0.3 -Types and methods of examination I 0.4 - Standards of acceptance

    II - CONTRACTOR's DOCUMENTS

    12- TESTING

    12.1 - General 12.2- Material, equipment and test fluid 12.3 - Pressure testing 12.4 - Drying after testing

    13 - PAINTING

    14- MARKING

    14.1 - During pre-fabrication 14.2- Spool pieces for installation (hook-up)

    15 -CARE AND MAINTENANCE

    15.1 - Equipment 15.2- Valve operators 15.3- Temporary supports 15.4 - Protection of piping spools and piping materials

    SP-TCS-171

    Page 3 of 34

    Date : .Januarv 199S

    17 17 17

    18

    18 18 19 19 20 20

    21

    21 22

    22

    22 23 25 26

    28

    29

    29 30 30 30

    31

    31

    31 31

    32

    32 32 32 32

  • SP- TCS- 171

    TOTAL STEEL PIPI:\G FABRICATIO:"i Page -1 of 3-1 TEPIDO Date : .Janua., 199R

    16 - PRIORITY LISTS " 00

    17- REPORTING 33

    APPENDIX A- Dimensional Tolerances 34

  • TOTAL TEP/DO

    I - SCOPE

    STEEL PIPI'\G FABRIC.HIO'\

    SP- TCS- 171

    PagC' 5 of 3-t

    Date : .Januarv 199S

    This Specification applies to above ground process and utility piping lines. and those lines extending below ground in the same service using the same materials.

    Requirements herein shall govern shop and field fabrication. Additional requirements. such as coating and wrapping. are not covered in this document.

    2 - DEFINITION OF CONTRACTING PARTIES

    OWNER The legal Owner of what is built.

    COMPANY The party which signs the contracts and orders on behalf of the OWNER.

    TOTAL TOTAL acts as the COMPANY Representative and performs the role of MANAGER.

    ENGINEERING COMPANY This term designates the engineering companies which work under the supervision of TOTAL and assume the function of ENGINEER.

    CONTRACTOR

    INSPECTION AGENCY

    In all cases a contract exists between the COMPANY and the ENGINEERING COMPANY specifying the missions entrusted to the latter.

    In some cases, TOTAL may also act as the ENGINEERING COMPANY.

    The Company responsible for fabrication and installation of piping (either in its facilities or on site).

    This term designates the inspection bodies which work under the supervision of TOTAL. In some cases, TOTAL may also act as the INSPECTION AGENCY.

  • TOTAL TEP/DO

    STEEL PIPI:\G F.-\BRICATIO:\

    3 - CO'iTRACTt:AL REFERE'iCE DOCUi\IE:\'TS

    SP- TCS- 171

    Page 6 of 3-.1-

    Datt : .January 199S

    Lnless otherwise specifically indicated in \\riting, the CONTRACTOR shall \\Orkin accordance with the requirements of this specification and those of the latest editions at the time of call for tender of the documents listed hereafter :

    a) ASME (American Society of Mechanical Engineers) : - ASME B 31.3

    - ASME B 1.20.1

    - ASME B 16.25

    - ASME Section I

    : 11 Process Piping~~.

    : "Pipe Threads. General Purpose (Inch)" : "Buttwelding Ends"

    : "Power Boilers". (For parts of piping systems associated with boilers and steam generating equipment, where that code applies : such parts will be

    indicated on drawings as boiler code piping). - ASME Section V : "Non-Destructive Examination"

    - ASME Section VIII : "Pressure Vessels" (where applicable) - ASME Section IX : "Welding and Brazing Qualifications"

    b) TOTAL General Specifications : - SP-TCS-1 I 2 : Piping material classes.

    - SP-TCS-173 : Pneumatic testing of above-ground piping systems (where applicable). - SP-TCS-175 : Internal cleaning of piping and vessels.

    - SP-TCS-61 I :Welding of pressure containing piping and equipment.

    - SP-TCS-612 :Metallurgical requirements for carbon steels in sour wet service (piping and equipment subject to SSCC & HI C) (where applicable).

    - SP-TCS-614 :Welding of duplex stainless steel (where applicable). - SP-TCS-615 : Welding of UNS 31254 alloy (where applicable). - SP-TCS-616 :Welding of titanium pipes and fittings (where applicable). - SP-TCS-617 :Welding of 3 y, nickel steel (impact tested at minus l0! 0 C} (where

    applicable). - SP-TCS-618 :Fabrication of alloy UNS 06625 Grade I materials (where applicable). - SP-TCS-620 : Specification for fabrication and welding of piping systems in

    cupronic:,el and associated materials (where applicable). - SP-TCS-622 : Metallurgical requirements for carbon steels in sour wet service (piping

    and equipment subject to SSCC only) (where applicable).

  • TOTAL TEP/00

    c) Other documents :

    STEEL PIPI:\G FABRIC\ TIO:\

    - Project Specifications. requisitions. and purchase order. - Information sources mentioned in section 4 hereafter.

    SP- TCS- 171

    Page 7 of 3-l

    Date : .January 1998

    - In addition to the above mentioned codes and their sub-references. other codes, such as National Codes, may govern some part of the piping. Drawings will indicate the applicable codes in such cases.

    Construction Codes or Government regulations which may be listed m the Project Specifications, in the Requisition or in the Purchase Order, if any, shall have precedence except where this Specification is more stringent.

    Any divergence between any of the Contractual Reference Documents or between this specification and any other Contractual Reference Document, should be reported to TOTAL for decision. In such a case, and unless otherwise agreed or decided by TOTAL, it is understood that the more stringent requirement shall apply.

    4 - INFORMATION SOURCES

    4.1 - Piping material classes

    The Piping material classes Specification SP TCS 112 shows the pipes, valves, flanges, fittings, branch connection, design details for vents, drains and instrument connections, and other specific material requirements for piping services. The specification includes the individual ptpmg material classes and branch reinforcement requirements.

    4.2 - Drawings

    4.2.1 - Design Drawings

    a) General arrangement drawings Complete design of the piping systems including description, sizes, dimensions, relative location of the various parts or components is generally shown on Piping General Arrangement drawings.

  • TOTAL TEP/DO

    STEEL PIPI~G FABRIC-\TIO"i

    SP-TCS-171

    Page 8 of 3-l

    Date : .JanuarY 199S

    b) Isometric drawings Complete and detailed information such as description. sizes. e:-.:act location. dimensions. joint details. are given in the isometric drawings. They shall clearly indicate the parts and/or components scheduled for assembly on the tield. Welds and connections to be performed in the field shall be positioned in a manner requiring the least amount of lield work and/or in order to facilitate field installation. A material take-otr attached to the isometric drawing shall show details of all components of the isometric (list of materials. thickness. ratings, quantities, etc.).

    4.2.2- Fabrication Drawings

    Shop drawings or sketches shall be prepared by the CONTRACTOR to facilitate the fabrication of parts or components of the Piping Systems. These drawings are intended to provide full information and instructions including typical shop details, weld preparation and procedures, etc., needed for that purpose. They must show the spool number, materials, dimensions, fabrication details, and the applicable code and procedures. Drawings must identify all equipment, lines or spools connecting to that spooL The General Arrangement or isometric drawing used as a reference shall be indicated. Spool pieces shall be identified by numbers indicating the isometric line number followed by suffix letters : A, B, C, etc.

    Approval or revtew of shop drawings by TOTAL does not relieve the CONTRACTOR of his responsibility to complete the work in accordance with the contract, the approved fabrication drawings and the Contractual Reference Documents.

    4.3 - Lines list

    Mechanical data section of the lines list shows lines design pressures and temperatures as well as testing and insulation requirements. Additional information such as wall thickness is available in the relevant piping material classes.

    4.4 - Isometric index

    This document is a list of all isometric drawings with their issue dates.

  • TOTAL TEPIDO

    STEEL PIPI:-iG FABRICA TIO:S

    5 - EXTENT OF SHOP FABRICATED PIPEWORK

    5.1 - Carbon steel

    SP- TCS- 171

    Pa~e 9 of 3-1

    Date :.January 1998

    Carbon steel of sizes 2 inches and larger shall be shop fabricated except for straight runs in pipe racks which are normally field run. I y, inch sizes and smaller are normally field run, except if heat treatment is required.

    5.2- Alloy

    All alloy piping using butt-welded fittings shall be shop fabricated except for long straight runs in pipe racks which shall be field fabricated.

    5.3 - Branches

    Branch connections on shop fabricated piping shall include appropriate couplings, tittings, or group of fittings, (i.e. flanges thermowell connections), or stubs for small field-fabricated branch connections. I 1/2 in. and smaller stubs shall not extend more than 300 mm from the outside of the header. 2 inches and larger stubs and branches shall extend to the first flange or field weld point as indicated on the drawings or as required for reasonable piece size.

    Reinforcement pads for field welded branches shall be fabricated and tack welded to the stub-in pipe by fabricator, and shall include vent and tell-tale hole.

    5.4 - Attachments

    Attachments, such as supports, braces, lugs, and T -bars may normally be installed in the field. They shall be attached to the matching piece of pipe or fitting by means of an intermediate pad in order to avoid direct welding of the piping component to its support. Fabricated pipe requiring preheat or post weld heat treatment shall have shop welded pads or stubs, to which field welds can be made where attachments are required. In such a case, the pads or stubs welds to the pipe shall receive the required heat treatment in the shop.

  • TOTAL TEPffiO

    STEEL P1PI:\G FABRIC.\ TIO:\

    SP- TCS- 171

    Page Ill of 3~

    Date : .Januar~ I ')')R

    5.5- Field runs

    Field runs are designated on piping drawings.

    6 - MATERIALS

    6.1 - Supply

    All piping materials (pipes, fittings. valves, accessories, supports, ... ) shall conform to the relevant piping material class and to all the other related documents. Materials for non pressure parts which are directly welded to pressure parts shall be of the same type and quality as the pressure parts.

    a) Materials furnished by TOTAL "free issue"

    Materials eventually furnished by TOTAL shall be as listed in the Contract documents. The CONTRACTOR shall be provided with a copy of Mill Certificates including chemical and physical properties for the materials furnished by TOTAL.

    The CONTRACTOR shall inspect all the materials (pipes, fittings, etc.) internally and externally. He shall agree or disagree with their condition at the time of delivery on site. A confirmatory inspection shall also be made by the INSPECTION AGENCY.

    The CONTRACTOR shall declare all unacceptable defects and damages which are found on materials furnished by TOTAL. Damaged material or materials found to have injurious defects shall not be used in the fabrication. The INSPECTION AGENCY shall decide if such materials may be repaired or must be replaced. Repairable defects or damages may be repaired by the CONTRACTOR on a cost plus basis to TOTAL. Before a repair is made, it must be submitted to TOTAL for approval. Non-repairable materials shall be replaced by TOTAL.

    The CONTRACTOR shall be considered responsible for defects or damages which will be detected after delivery on site. Repair or replacement of such defective materials shall be at the CONTRACTOR's expense.

    The CONTRACTOR. on accepting the responsibility of the materials, shall keep a record on all related activities including date of inspection, designation and number of materials accepted or to be repaired or replaced, and any other pertinent information detailing material defects or damages. This record shall be signed by the CONTRACTOR and the INSPECTION AGENCY.

  • SP- TCS- 171

    TOTAL STEEL PIPI'iG FABRIC\ TIO'i Page It of 34 TEP/DO Date: .Janna!'\ I

  • TOTAL TEP/DO

    STEEL PIPI'iG FABRICATIO'i

    7.2- Execution of the work

    SP- TCS- 171

    Page 12 of 3-l

    Date : .January 1998

    The CONTRACTOR shall furnish qualified personnel and all ~quipment. tools. instruments. etc. necessary to carry out qualification of welding procedures and welders. handling. fabrication. welding. welding inspection. installation. testing. cleaning and painting of the piping components according to this Specitication and the Contractual Reference Documents.

    The furnished equipment shall be in first class operating condition and adequate replacement parts shall be available.

    The CONTRACTOR shall have available on the fabrication site suitable ovens for drying and conservation of low-hydrogen electrodes and suitable equipment for preheating, post-heating and stress relieving where and when required. (This equipment is subject to approval by the INSPECTION AGENCY).

    The CONTRACTOR shall execute the work in a continuous and workmanlike manner, taking all necessary precautions to ensure that good work will result and that the approved completion schedule will be met.

    The CONTRACTOR. at his own expense, shall provide the necessary weather protection to ensure that all work continues always as specified.

    When conditions are or become unsafe to start or continue the work, the CONTRACTOR shall notify the INSPECTION AGENCY immediately.

    7.3- Fabrication tolerances

    CONTRACTOR is responsible for ensuring that fabricated piping conforms to applicable codes, specifications, drawings and purchase order requirements. He is responsible for fabricated dimensions that agree with piping drawings. Where not otherwise specified. dimensional tolerances shall conform to those shown in Appendix A.

    All angular dimensions of bends and branches shall be maintained within I degree.

  • TOTAL TEPffiO

    7.-t- Cutting

    STF:EL PIPI:\G FABRIC\ TIO:\

    SP- TCS- 171

    Page 13 of 3~

    Date : .l~tnu~uy I 99S

    Cutting may be performed by machining. sawing. or by gas or plasma cutting guided torches. Any other process shall be submitted to the INSPECTION AGENCY for approval prior to use. Gas cutting is only accepted on non-galvanized carbon steel materials. In gas cutting. the cutting !lame shall be so adjusted and manipulated as to avoid cutting beyond the prescribed lines. The roughness of gas cut surfaces and occasional notches on edges shall be removed by machining or grinding ; cut surfaces and edges shall be left free of slag.

    Cutting shall be performed perpendicularly to the piping component centerline unless otherwise indicated on the drawings. Cutting shall be made with suitable allowance taken into account for shape of connections and shrinkage due to cutting and welding.

    After cutting, suitable identification markings, including at least grade of steel and heat number, shall be reproduced on each of the cut part of materials.

    Special care shall be taken to remove internal burrs resulting from cutting, especially on pipes equal to or less than 2 inches in diameter.

    7.5 - Threading

    Screwed connections shall only be used where permitted in the relevant piping material class.

    Unless otherwise indicated on drawings, all threads shall be "taper" to NPT and concentric to the outside of the pipe, in accordance with the ASME Code 8.1.20 Normally, all threading shall be carried out after bending, forging, or heat treatment, but when this IS not possible, suitable thread protection must be provided.

    Screwed threads shall be clean cut with no burrs, no stripping. Ends shall be reamed to remove burrs. Threaded parts shall be fitted by progressive and tight screwing :

    a) by inserting an appropriate PTFE tape for design temperatures up to 140C (except where seal-welding is required),

    b) without inserting any foreign material above this temperature, unless suitable sealant product has been specially selected.

    Excessive wrench marking on pipes or fittings shall be cause for rejection.

  • TOTAL TEP/DO

    STEEL 1'11'1:\G FABRIC A T!O:\

    SP-TCS-171

    Page 1-4 of 3-t

    Date : .Januan !91)S

    Seal welds are prohibited on threaded assemblies. e~cept "here 'pcciticall: required by the E"iGI?-iEERI'.;G CONIPA]\;Y. In that case. seal \\elds shall cover all exposed threads and shall be done with electrodes not in e:

  • TOTAL TEP/DO

    STEEL PIPI:\G FABRlC.\ TIO:\

    SP-TCS-171

    Pat!e 15 of 3""

    i. 9 - Threaded ,joints

    7.9.1 -Tightening of threaded connections

    In piping systems employing threaded connections. all joints shall be tightened using a suitable wrench. For connections 2" and larger, joints shall be tightened using a "RJDGID" Compound Leverage Pipe Wrench. or equivalent.

    7.9.2- Seal welding of threaded connections

    a) Hydrocarbon service : Threaded plugs on hydrostatic vents not provided with a valve shall be seal welded after testing has been carried out. Valved vents, drains, and sample connections discharging to an open system shall only be seal welded upstream the first block valve. Caps shall not be seal welded. Threaded needle valves at sample connections shall not be seal welded. Galvanized piping shall not be seal welded.

    b) Other services: all threaded connections shall be sealed as follows : - 204 C and below : PTFE thread tape (i.e. no seal-welding) - Above 204 oc : seal weld wherever possible, otherwise use pipe jointing compound

    to manufacturer's standard.

    c) Where seal welding of threaded joints is intended to be used, all following conditions shall be met :

    - The materials shall be weldable. - The joints shall be made up clean and without the use of any tape or compound. - The weld shall cover all exposed threads. - The welding procedure shall not cause damage to the threaded fitting, e.g. valve soft

    seats. - Welding shall only be carried out by qualified welders. - No other satisfactory means of jointing are available.

    7.10 -Bends

    Bending shall only be used if permitted in the relevant piping class. Bending is neither permitted on stainless steel materials nor on impact tested carbon steels.

    Bending and forming shall comply with the procedure requirements detined 10 ASME B 31.3 Code and the following requirements :

    a) Unless noted otherwise. the centerline radius of bends shall be live (5) nominal pipe diameter. Welds in bends are not permitted.

  • TOTAL TEP/DO

    STEEL 1'11'1:\C FABR1CA TIO:\

    SP- TCS- 171

    Page 16 of 3~

    Date: .JanuarY 19'JS

    b) Bends shall be produced onl: in seamless pipe. Cold bends shall he limited r,l diameters of l 'o inches and smaller. unless otherwise apprcwed b\ TOT.-\L. Elongation of outer la,er shall not e~ceed 15 0.

    c) Bending shall be made using suitable tools and procedures in order to obtain uniform arc surfaces free of cracks and buckles. without excessi\e out of roundness or thinning of the pipe material.

    d) The pipe wall thickness at the thinnest point after bending. less corrosion allowance, shall not be less than the calculated thickness required for pressure. Flattening of bends shall comply with the tolerances specified under clause 7.3 of this Specification. Weld repairs of defects in pipe bends are not acceptable.

    e) Galvanized pipes shall not be bent unless galvanizing is made a tier bending.

    t) Bent pipes shall be subject to heat treatment in accordance with the requirements applying to each material and the recommendations defined by the code ASMEB 31.3.

    7.11 -Elbows

    Elbows shall be long radius ( 1.5 diameter radius, as specified in the relevant piping material class) unless otherwise noted on drawings.

    Mitered elbows are not allowed, except on lines open to the atmosphere such as safety valves open discharge or turbines exhaust lines.

    7.12 -Branch connections

    Branch connections shall comply with the requirements of ASME B 31.3 Code for Process Piping.

    Branch connections shall be made by fabricated stub-in connections, couplings, outlet fittings (weldolets. etc.) or tees, as indicated on the piping material classes, and according to the material list of the relevant isometric drawings.

    All welded branch connections shall be joined to the header with full penetration welds.

    All instrument air. fuel gas. and steam connections shall be from the top of the header.

  • TOTAL TEP/DO

    i .13- Orifice runs

    STEFL PIPI:\G FABRICATIO:\

    SP-TCS-171

    Pa!_!c I 1 nf 34

    Date : .Januan I 998

    Orifice runs shall not contain welds except at the tlanges. Pipe ends at oriticc tlanges shall be machine-cut and perpendicular to the pipe axis.

    Welds at the oritice tlanges shall be ground smooth inside. Pipe-tap connections shall be drilled through the pipe wall and be smooth inside. Drawings will show the orientation of orifice !lange taps and location of pipe taps. Oritice tlanges shall be drilled and tapped for jack screws.

    Pipe in orifice meter runs shall be in accordance with Instrument Specitications applicable to the Project.

    7.14 -Galvanized piping

    Galvanized piping shall not be bent or welded. Piping required to be bent or welded shall be re-galvanized after fabrication and after having removed damaged galvanizing.

    7.15 -Flange bolt holes

    Where not shown otherwise. flange bolt holes shall straddle the vertical centerline of the pipe where the flange is installed vertically, and the north- south line where the flange is installed horizontally.

    7.16 -Cleaning

    Fabricated pipe spools shall be cleaned free from weld spatter, scale, grease and dirt.

    7.17 -Extra length for site adjustment

    Where the drawings indicate a "Field Weld" in the pipe, the relevant sections shall be supplied 200 mm longer with the ends left plain.

  • TOTAL TEP/00

    S - WELDI:\'G

    STEEL PIPI~C FABRIC\. TIO\;

    SP- TCS- 171

    Pa!!;c 18 of 34

    Date: .Januar~ 199S

    Welding shall be in accordance with the \\'elding Specitlcation SP TCS 611 "hich is fully applicable. together with one or se\eral of the following additional specitlcations. as applicable: SP TCS 612. SP TCS 614. SP TCS 615. SP TCS 616. SP TCS 617. SP TCS 620. and SP TCS 622. and the following additional requirements :

    8.1- Welding procedure specifications (W.P.S.)

    The approved welding procedure specifications shall be made available on site for the whole duration of the fabrication.

    8.2- Welding procedure qualifications (P.Q.R.)

    - Welding procedure qualification tests carried out on small diameter pipe may require execution of two welds if one does not permit all prescribed test specimens to be taken.

    - Welding procedure qualification for welded branch connections (especially angular), or welds of special configurations, may include special requirements and testing. In that case, qualification tests shall be as directed by the INSPECTION AGENCY.

    - For carbon steel materials, welding procedure qualification tests shall include those prescribed in ASME Code Section IX and the additional requirements here after :

    Non-destructive examinations

    Visual and radiographic or ultrasonic examinations shall be carried out according to this Specification prior to sampling the test specimens.

    Macrosections

    A specimen shall be extracted from the completed joint at 2 opposite locations (12 and 6 o'clock locations for the 5G position). The specimens shall be examined to ensure a good weld profile and freedom from unacceptable weld defects.

  • TOTAL TEP/DO

    STEEL PIP!'iG FABRIC\ T!O'i

    8.3- Welders and welding operators qualifications

    SP- TCS- 171

    Page 19 of 3-'

    Datl' : .Ltnuary 1 99S

    - Welders qualit\cation shall be made on pipe either in the positions 2G 7 5G. or in the 6G position. Welders qualitled in the 2G + 5G or 6G positions shall be considered as qualified for all positions.

    - Welders and welding operators shall be qualified on the same P number material as for the work to be done.

    - Welder qualification for welded branch connections (especially angular) or for welds of special configurations shall include special requirements and testing as directed by the INSPECTION AGENCY. Only welders qualified for groove welds in the 6G (inclined. fixed) position may be submitted to particular qualification for welded branch connections.

    - Welders qualifications documents shall be stamped by re~ognized authorities such as: LLOYD's. D.N.V., T.U.V., BUREAU VERITAS, lNSTITUT DE SOUDURE, APA VE.

    - Welders and welding operators qualification tests based only on radiographic examination are not acceptable : qualification shall be based mechanical tests. Qualification test welds shall be subject to non-destructive inspection (visual+ radiographic, and eventually ultrasonic) before any mechanical test specimen is removed from the test plate.

    - Only welders and welding operators successful in non-destructive inspection and destructive tests shall be permitted to perform any welding on the project in accordance with their qualification. However, at the discretion of the INSPECTION AGENCY, welders and welding operators are subject to re-qualification when the quality of their work, during fabrication, appears to be below the requirements of this Specification.

    - A record of the results of each test weld shall be jointly signed by the CONTRACTOR and the INSPECTION AGENCY. The record shall indicate the symbol or number given to the welder for identification of his work.

    8.4 - Welded connections

    All butt welds shall be full penetration welds made using at least two passes.

    No pass shall be commenced until the preceding pass has been completed.

    Weld passes shall not start or stop at the same point.

  • TOTAL TEP/DO

    STF:EL PIPI:\"G FABR!C..\TH):\"

    SP-TCS-171

    Page 20 of 3-1.

    Date: .Jauuan 199S

    Welding shall not be stopped before the second pass is completed. anJ umil the thickness of the weld is at least equal to one third of the pipe wall thickness.

    Where possible. butt welds may be made from both sides. in accordance with approved welding procedures. In that case. the back side of the root pass shall be ground or gouged-out to sound metal before welding on that side.

    Welds joining components of different material thickness shall be made in such a manner that the slope through the transition zone does not exceed I /4.

    8.5- Post Weld Heat Treatment (PWHT)

    PWHT, when required, may be carried out by either of the following means:

    - enclosed furnace - in-situ furnace - local electric induction or resistance.

    The PWHT procedure shall be submitted to TOTAL for review and approval.

    The surfaces of the pipe in the heat treatment zone shall be clean of all foreign matter.

    The thermocouples shall be mechanically attached to the parts being heat treated, and within 40 mm from the outside surface of the weld metal.

    When welds are locally heat treated, the pipes shall be adequately supported and the ends blanked off.

    8.6 - Field weld location

    Piping drawings shall show limits of field run piping and locations of field welds required between spool pieces.

  • TOTAL TEP!DO

    9 - ASSE~IBL Y

    SlTEL PIPI:XG FABRIC\ TIO:X

    9.1- Assembly of flanged piping

    SP-TCS-171

    Pagl' 21 of 3..1.

    DatL': .Ltnuarv llJl)S

    All flanged joints shall be properly assembled. Unusual measures such as the building-up of imperfect tlanges by welding. re-facing of distorted tlanges and heating and bending of pipe for proper alignment is not permitted.

    Foreign material and protective grease shall be removed from flange faces prior to assembly. After cleaning. flange faces shall be inspected for pits and defects in the gasket contact face. Imperfections may not be repaired except by re-machining the flange facing on a lathe. RTJ flange grooves may be satisfactorily trued by hand lapping with an ORJ gasket.

    After cleaning the flanges for make-up, dry gaskets shall be inserted. Flat gaskets shall be centered by the flange bolts. Centering rings of spiral wound type gaskets shall be properly centered.

    All studs and nuts shall be thoroughly cleaned before assembling joints. Studs shall be long enough to show one and one-half threads after proper tightening.

    When flanges are in alignment, both horizontally and vertically, and faces are parallel, studs shall be installed with the exception of one or two, and nuts hand tightened. In one of the holes left open, a pin wrench may be inserted to raise or lower either flange as required to ensure proper alignment. One stud shall then be tightened sufficiently to keep the gasket seated. The pin wrench shall then be removed and remaining stud tightened by gradually working around the flange until all studs are tight with equal tension on each stud.

    For spiral wound type gasket joints, the bolting sequence shall consist of a series of uniform loading starting with the flange bolt in the 12 o'clock position, then transferring successively to the 6 o'clock, 9 o'clock, 3 o'clock, etc. bolt positions, increasing the load uniformly each time until the sequence is completed. Bolts shall be tightened until the flanges are uniformly seated on the gasket centering ring.

    When flanges are in alignment but require a cold pull up to take care of expansion during operation, and if specified by the ENGINEERING COMPANY, bolting up shall be accomplished by use of special bolts or chain blocks. Special bolts shall be of a length great enough to engage the two flanges plus the cold pull. Use at least two bolts to provide equal tension on each side of the flange and by tightening up these bolts alternately, bring the tlanges together. The correct length of studs shall be substituted for the special bolts.

    In using chain blocks. the blocks shall be lashed to the pipe and the two tlanges brought together and bolted up as prescribed previously.

  • TOTAL TEP/DO

    STf.EL P1P1:\G FABRIC A TIO:\

    SP-TCS-171

    Pagt. 22 of 3-t.

    Date: .JanuarY !99S

    Paint damaged during bolt-up procedures shall be repaireJ in acc,;rdancc "ith the Project paint specitications.

    9.2 - Assemblv of piping to equipment

    Piping shall be erected and supported in a manner that will not put undue strain on pumps. compressors. tanks. vessels or other equipment. Adjustment of piping by local heating is prohibited.

    The procedure for connection of piping to equipment shall be as follows :

    a) After the equipment has been set. the pipe shall be connected to the equipment without making any tight connections to flanges.

    b) Full face gaskets shall be used on piping connecting to equipment with t1at face flanges.

    c) Flanges shall be checked to assure that no strain is induced on the equipment. If pipe is not in correct alignment, it shall be removed and corrected. The correction in alignment shall not be made while the pipe is connected to the equipment.

    d) Scratched flange faces shall be repaired by re-machining in a workshop or shall be replaced.

    e) After alignment is found correct, the flanges shall be carefully "bolted up" with the stud bolt centered in the flanges and the nuts having equal threads showing.

    10- WELDING INSPECTION

    10.1 -General

    Welding inspection shall be made in accordance with ASME B 31.3 Code and the additional requirements defined herein.

    Inspection personnel and equipment shall be subject to prior approval by the INSPECTION AGENCY.

    All fabrication shall be subject to inspection by the CONTRACTOR under the INSPECTION AGENCY's supervision and approval. All weld preparation. fit-up. and weld assemblies shall be visually inspected during all phases of fabrication. Where necessary. corrections shall be made in the weld preparation to assure that sound welds can be achieved by the welding process used. Cracks and undercuts or any evidence of poor workmanship shall be cause for rejection. Special care shall be taken in the inspection of branch welds.

  • Sl'- TCS- 171

    STEEL 1'11'1:\G F.-\BRIC.\ TIO:\ TOTAL Page 13 of 34 TEP/DO Date : .January I'!IJS

    The COI\TRACTOR shall pro\ ide s i tc: access and reasonable cud w the INSPECTION AGENCY as required for the performance. of their dut:. The CONTRACTOR shall supply and operate at his own expense all equipment and materials necessary to inspect the ''e\ds according to this specitication.

    F ina\ inspection of welds shall be made after Post Weld Heat Treatment where such heat treatment is performed. The INSPECTION AGENCY shall have the right to select the welds to be inspected.

    10.2 -Extent of ins~ection a) Visual inspection

    A 100% visual inspection of all welds shall be done after cleaning and prior to any subsequent NOT.

    b) Other NOT requirements The extent of NOT requirements other than visual inspection is defined in the table I hereafter :

    TABLE I : NDT REQUIREMENTS

    Service conditions Utilities lines Hydrocarbons Cryogenic Severe Cyclic -...--- (liquid or gas) Service Conditions

    Pressure class ~ 600 ~ 900 ~ 300 ~ 600 ~!50 ~ 300 ~!50

    Longitudinal welds c c c c c c c

    Girth welds A CE B(I)E CF B(t) E CF CF .,

    .

    Socket welds None E E F E F (See note 2)

    Pressure-containing fillet welds such as pipe-to-pipe branch connections (including reinforcing pads) and 0 E E F E F F btanches made with "0-\et" tittings. slip-on flange welds. pipe couplings. etc.

    Non pressure-containing fillet welds (attachments welds to None D 0 E 0 E F pressure-containing parts).

    (I) I 00% RT for lines subject to pneumatic tests (2) Socket welds are not permitted on severe cyclic conditions

  • TOTAL TEPIDO

    STFTL P1P1:\G FABRIC.-\ TIO:\

    SP- TCS- 171

    Date: .Januan }l)')S

    I 0.2.1 - General notes for Table I :

    A= :VIinimum 5% of random radiographic testing (RT). If the \\eld reject ratio per welder or welding operator e>Cceeds 5o. RT shall be increased to 100% and shall stay at I 00% until the reject rate per welder or vvelding operator drops below 5% and stays there for five consecutive working days.

    B =Minimum !0% of random RT. If the weld reject ratio per welder or welding operator exceeds 5%. RT shall be increased to I 00% and shall stay at !00% until the reject rate per welder or welding operator drops below 5% and stays there for five consecutive working days.

    C = 100% RT.

    D = 5% Magnetic particle (MP1) or dye penetrant (DPI) inspection. E = 10% Magnetic particle (MPI) or dye penetrant (DPI) inspection. F = I 00% Magnetic particle (MPI) or dye penetrant (DPI) inspection.

    I 0.2.2 - Particular case of welds of piping supports

    a) All welds : I 00 %visual inspection b) Fillet welds:

    - Welds between supports and main or secondary steel structure to which they are attached shall be subject to 100% MPI or DPI if they are supporting at least one line ofNPS 10 inches or larger.

    - Welds between supports and main or secondary steel structure to which they are attached shall be subject to 10 % MPI or DPI if they are supporting lines ofNPS less than 10 inches.

    - Other welds shall be subject to MPI or DPI of one weld every 20 welds made by each welder or welder operator.

    c) Butt welds : Radiographic examination of one weld every 10 welds made by each welder or welder operator.

    I 0.2.3 - Additional non-destructive inspections

    Non-destructive inspection in addition to radiographic examination (ultrasonic. magnetic particle, liquid penetrant .... ) may be required at the discretion of the INSPECTION AGENCY as additional inspection, or in the case of special weld configuration. or depending on the welding process used by the CONTRACTOR.

  • l TOTAL TEP/DO

    STEEL PIPI'iG FABRIC.-\ TIO'i

    SP-TCS-171

    Pagl' 25 of 3-t

    Date: .lannary 199S

    I 0.3 -Types and methods of examination

    I 0.3.1 -Visual examination

    This shall be carried out before. during and atier fabrication in accordance with ASME Y article 9 and ASME B 31.3.

    Visual examination shall apply to all welds and shall include : Joint preparation and cleanliness Fit-up and internal alignment prior to welding Preheating Welding position, welding products and all other parameters defined in the

    applicable welding procedures Condition of the root pass after cleaning (external, and internal where

    accessible) Slag removal and weld condition between passes Appearance of the finished weld.

    I 0.3.2- Radiographic inspection

    a) Applicable code Radiographic examination shall be in accordance with the code ASME B 31.3

    b) Film quality Only ultra fine grain films of a quality equal or finer than AGFA GEVAERT "04", or KODAK "M", shall be used for radiographic inspection of piping welds.

    c) Film size Films size shall generally be I 0 x 40 em. Smaller width films for welds without intersections may be used provided a minimum width of ISmm of base metal appears on each side of the weld on the radiograph.

    d) Spot examination When radiography is specified as a percentage (e.g., 10 %), radiographic examination shall be carried out on the complete circumference (e.g .. I in 10) of each size of piping butt welds.

    As a minimum, at least one radiograph shall be taken on work performed in early stages of fabrication by each welder or welding operator.

  • TOTAL TEP/DO

    SP- TCS- 171

    STEEL PIPI:\G FABRIC.\ TIO:\ Page 26 of 34

    Date: .Januan 1998

    The IC\SPECTIO:\ .\GE:\CY may require radiographic inspection ell a k\el abo\e the percentage detlned. In such a case. additional radiographs shall be at the CO:VIPA:\Y's e~pense if the welds are sound and at the CONTRACTOR's e~pense if they are unacceptable.

    e) Socket welds I 0 percent of socket welds shall be radiographed in order to check the gap between the male and female parts of the assembly. In no case this inspection is meant to be a weld imperfection (soundness) check.

    I 0.3.3 -Magnetic particle inspection

    When this method of examination is specified or required by the INSPECTION AGENCY. it shall be carried out in accordance with ASME V article 7. It is the preferred method of surface crack detection for carbon steel materials.

    I 0.3.4- Liquid penetrant

    When this method of examination is specified or required by the INSPECTION AGENCY, it shall be carried out in accordance with ASME V article 6.

    I 0.3.5 -Ultrasonic Testing (U.T.)

    Ultrasonic testing may be used at the discretion of the INSPECTION AGENCY as additional inspection, or in the case of special weld configuration, or depending on the welding process used by the CONTRACTOR. In such a case, U.T. shall be carried out in accordance with ASME V article 5.

    10.4 -Standards of acceptance

    The following standards of acceptance shall be used for the visual and radiographic inspection for welding procedure qualification test welds, welder qualification and production welds. where applicable.

    Standards of acceptance shall comply as a minimum with the limitations on defects detined in ASME B 31.3 Code for normal fluid service. and with the additional requirements shown on the Table II hsreafter.

  • SP- TCS- 171

    STEEL PIPI:\G FABRIC-\ TIO:\ TOTAL Page 1:"'" of 3-t. TEP/DO Date: .Ltnuan: 1 l}l)~

    The dimensional limitations oi tlcms subject to rejection specitied in this clause are intended to ensure good quality welding. The etlect ot' \\eld tla\\s on the seC\ ice performance of a joint are intluenced by their location and disposition. those located in the body of the weld being in general less serious than those in the root. This should be taken into account when considering the rejection oi joints that appear to be border-line in quality as assessed by the limitations of tlaws specitied in this clause.

    The INSPECTION AGENCY shall be the sole judge for the acceptability of welds and their decisions are final.

    TABLE II: STAl'IDARDS OF ACCEPTANCE

    TYPE OF DEFECT LIMITATION

    Lack of penetration No lack of penetration is permitted on process lines.

    Cracks Any form of crack or suspected crack ("linear indication") shall be considered as unacceptable ..

    Weld reinforcement shall be uniform. It shall merge smoothly with the parent material.

    Weld Reinforcement Limitations of the ASME B 31.3 code on weld reinforcement shall apply to internal surfaces as well as to external. No chipping of the weld reinforcement shall be permitted.

    The root bead shall fuse to both inside surfaces of joined materials. The depth of any root

    Concave root surface concavity shall not exceed 1.2 mm, but at no point shall the weld be thinner than the thickness of the thinner of the welded components.

    The summation of all imperfections in a length Summation of all lengths of of 300 mm of weld shall not exceed 50 mm. A imperfections summation of discontinuities having a total

    length of more than 8 percent of the total weld length shall be considered as unacceptable.

  • TOTAL STEEL PIPI'IG FABRIC A TIO'i SP- TCS- 171

    Page 2X of 3-t

    TEP!DO Date: .Januar: l'J'JS

    II- CO"TRACTOR's DOCDIE:'\TS

    The CONTRACTOR shall prepare and keep up-to-date documents g1' 1ng detailed technical information on welding operations.

    These documents shall include. but not be limited to. the following information:

    a) Welding procedures specitlcations (WPS)

    b) Welding procedures qualitlcation test results (PQR)

    c) Welders qualitlcation tests results

    d) Approved fabrication and shop drawings

    e) Sequence in assembling piping components

    t) Weld-logbook, giving for each part or component under fabrication : item number of the piping section containing the weld, weld number, welder identitlcation, date of welding, welding procedure used, type and date of non-destructive tests, inspection results, radiographic films (if weld was radiographed), date of heat treatment (if applicable), records of heat treatment parameters and heat treatment charts (if applicable), repairs.

    Radiograph locations shall be carefully indicated on the isometric drawings.

    These documents shall be jointly signed by the CONTRACTOR and the INSPECTION AGENCY.

    TOTAL shall be provided with these documents when the work is completed.

  • TOTAL TEP/00

    12- TESTI:\G

    12.1 -General

    SP-TCS-171

    STEEL PIPI:-;G FABRIC A TIO'i Page 19 of 3-t

    D~ltl': .lanuary 199S

    The CONTRACTOR shall perform the work necessary to successti.dly hydrostatically. or pneumatically and leak test the piping.

    Shop and field tests shall be performed in accordance with ASME B 31.3 e:-ccept that pneumatic testing shall be subject to TOTAL prior approval.

    Pneumatic testing shall cc .. 1ply with the TOTAL specification no SP TCS 173.

    The CONTRACTOR shall submit all testing procedures for approval. All piping systems shall be tested, including those designed at I bar gage or less. regardless of design temperature. Shop hydrostatic test is required for piping on which field welding is not required.

    All joints, including welds, are to be left un-insulated and unpainted for examination during testing. Vents, drains and relief valves shall be utilized to prevent damage to the piping system due to thermal expansion or other hazardous conditions during the test period.

    Any test shall include a preliminary cleaning of the piping after fabrication, to be performed externally and internally, in order to remove all loose scale, weld spatter, sand and other foreign material. The cleaning shall be performed according to the TOTAL specification n SP-TCS-175. Any test shall include a preliminary check at no more than 2 bars (g) to locate any major leak. Hydrostatic pressure testing shall only be carried-out on perfectly dry surfaces to allow for proper visual check for leaks.

    All lines shall be hydrostatically or pneumatically tested. The line list shall indicate the type of test and pressure to use on each line. The maximum operating pressure of each piece of equipment, including instruments, shall be checked against the test pressure of the piping system in which the piece of equipment is included. If the test pressure of the piping system is greater than the maximum operating pressure of the equipment, the equipment shall be blanked-off and tested separately.

    The CONTRACTOR shall assign and designate a separate crew with suitable equipment for the testing operations. These shall be conducted diligently, thoroughly and in a safe and workmanlike manner in accordance with accepted piping testing practices.

    No test shall be performed without witness of TOTAL and/or INSPECTION AGENCY's representative(s).

  • TOTAL TEP!DO

    STEEL 1'\PL\C. FABRIC\TIO\

    12.2 - :\laterial, equipment and test tluid

    SP-TCS- Pi

    Datl': .Iannan !l) 1),"!

    The CO'\TRACTOR shall suppl: all necessary testing equ1pmcnt !pumps. compressors. pressure indicators and recorders ... ) and testing tluids. The CONTRACTOR shall assume full responsibility for the disposal of testing tluids.

    As water is normally used for pressure testing of process lines. special precautions shall be taken for draining and drying the lines. Test water shall be clean and free from minerals and suspended matter. Only water having a chloride content of I 5 PPM or less shall be used in contact with stainless steel. Sea water shall never be used.

    If required. rust inhibitor and other chemical additives as oxygen scavenger, passivating agents shall be injected with the test water by the CONTRACTOR. Air for pneumatic testing shall be dried and filtered before use as a testing tluid.

    12.3 -Pressure testing

    The minimum hydrostatic test pressure shall be 7 bars (g).

    The pressure shall be maintained for an adequate time (not less than 30 minutes) to detect small seepage leaks and to permit a thorough inspection.

    All piping which is pneumatically tested, such as process piping, instrument air, plant air and other low pressure piping, shall be tested at a pressure of II 0 percent of the maximum operating pressure.

    Attention is drawn to the fact that some pneumatic tests, where high test pressures or large volumes, or both are involved, would introduce considerable hazard due to possible release of stored energy in the system. It is the CONTRACTOR's responsibility to select these cases and to propose alternative tests in line with ASME B 31.3 Code, for TOTAL approval.

    12.4- Drving after testing

    All piping shall be completely drained of all testing tluid. Special precautions should be talcn to ensure the draining of all pockets where the testing tluid may be trapped.

  • l TOTAL TEP/DO

    STHL PIPI\"G FABRICATIO\"

    SP-TCS-171

    Date : .lanu~~n I 998

    .All piping tested with water. in which water would be detrimental w the process operation. shall be thorough!: dried. This piping shall be blown-do" n "ith air. and air circulated through the piping until it has been determined that there are no trapped pockets of water and that the piping is dry. This in particular shall apply to all stainless steel piping.

    13- PAINTING

    Painting shall be in accordance with Project Painting and Color Coding Specifications.

    14- MARKING

    14.1- During pre-fabrication

    Fabricated parts requiring trial shop assembly shall be match-marked with paint to facilitate onshore erection.

    Each piece shall be plainly marked with the piece number, using paint. After application of the primer, or rust preventor on carbon steel piping, permanent markings shall be stamped with steel stamps having rounded or U-shaped cross section.

    On carbon steel ptpmg for low temperature and on stainless steel ptpmg, no stamping is permitted and permanent marking (if required) shall be etched with an electric pencil.

    On each element. the flow direction shall be marked so that there are no mistakes during the module assemblies for check valves, flow meters, flow orifices, or globe valves.

    14.2 -Spool pieces for installation (hook-up)

    Each spool piece to be installed shall be marked with an identifying number relating to the line number and position in the line.

    Flanges indicated on the drawings as supplied loose for site welding shall be supplied either lightly tack-welded to the pipe or wired on.

  • TOTAL TEP!DO

    STEEL P1PI'iG FABRIC\ TIO'i

    15- CARE A:-ID :\IAI:-ITE:-IA:-ICE

    15.1- Equipment

    SP-TCS-171

    Page 32 of 3-l

    Date: .Januan l'l9S

    The CONTRACTOR shall be responsible for the care and maintenance of all equipment or material delivered on his site (installed. erected or stored). This care and maintenance must be done according to the vendor specifications supplied by the ENGINEERING COMPANY. and must ensure the good working conditions of all materials until the start up time.

    It must be clearly understood that all extra work which would occur during hook up or start up phases due to CONTRACTOR's lack of care shall be back-charged to him.

    15.2- Valve operators

    Valves handles, wrenches, etc. are to be issued from warehouse with valves and shall be fastened on the line as close as possible to the valve, as soon as the valve is erected. Fastening must be done using steel bands.

    Valves supplied with packaged equipment are also subject to the above rules.

    15.3-Temporary supports

    It may be necessary to provide temporary supports for protecting the piping against shocks, vibrations, stresses, due to on-shore or off-shore handling until the final erection.

    Temporary supports are particularly necessary for hanger supports and for large diameter piping.

    15.4- Protection of piping spools and piping materials

    Openings in piping spools shall be securely closed and flange faces and threaded connections shall be protected with suitable plugs, flange covers, and thread protectors. Small branches and flimsy parts shall be adequately braced or otherwise protected to prevent damage during handling and storage.

    Flange gasket contact faces protection which becomes defective either after fabrication. handling or during storage must be re-protected immediately.

  • TOTAL TEPIDO

    16- PRIORITYLISTS

    STEEL PIPI:\G FABRICATIO:\

    SP-TCS-171

    Page 33 of 3-1.

    Date : .JanuaJ> !99S

    The ENGINEERING COMPANY may supply the CONTRACTOR with lists of line numbers .,howin~ the required fabrication priorities. These priorities would be based for the main part on expected equipment deliveries to site. When [ate, or out-of-sequence equipment deliveries occur, the ENGINEERING COMPANY's coordinator shall revise and up-date the priority list to reflect these changes.

    17- REPORTING The CONTRACTOR shall be responsible for the preparation and distribution of all status reports, schedules, etc .. pertaining to spools and materials as follows :

    a) Spool fabrication record b) Weekly fabrication status report c) Material summary report

  • TOTAL TEP!DO

    STEEL PIPI:\G FABRIC A TIO:\

    .-\PPE:\DIX .-\

    DIMENSIONAL TOLER.\NCES

    c '-------"----.j : _J : __j

    SP-TCS-171

    Page 3-l of 3-l

    Date : .January 1998

    -------------: ----------- _--: :~ ---J- ---------------L \._.

    '

    I ; -+----t-'-.._---1

    I '

    ~~--~------------------+---- ----+-

    0

    ([) ([) CD CD

    '

    '

    ' t

    0 ' 0

    . - .!-. ' '

    '

    '

    '

    -~~~~ I

    CD 3 mm max. from indicated dimensions for face to face, center to face, location of branches, attachments, etc.