1.0 INTRODUCTION
Since Mei 2007, the issue of building defects is keep on reporting in the
media, particularly about the condition of government buildings andinfrastructures. It is about that time the issue of building maintenance, building
defects and its related terms has come into existence, and it is deliberated up to
the parliament level. The former Public Work Minister (Datuk Seri S Samy Vellu)
had announced that the Building Surveyors should be in the field together with all
the building industry players as to uphold the maintenance management of the
buildings. Behind the scene, the question post; what is going on actually in our
building industry with regards to building maintenance management?
One of the key points that answering this phenomenon is the inspection.
Sad but true, we do not properly inspect our building. We do not treat our building
like our car. Similarly, we do not care about our building as importance as caring
about our health. This has contributed to a lot of building-related problems that
we are facing now. In relation to the dynamic and complexity of the building
industry, the inspection work needs to be carried out by an expert. Thus, the
expert must be call in for the purpose of building inspection. In other words, the
professional has to undertake the building inspection work and responsible for
the building survey reports. There are various level of inspection and testing
involved during the course of survey; and there are a number of possible formats
for the report (Glover, 2001).
-
8/3/2019 Role&Method Inspection
2/20
PERANAN DAN KAEDAH PEMERIKSAAN KECACATAN BANGUNAN
2
This paper will cover the fundamental aspect of building inspection and
not intended to cover the whole spectrum as outlined by Glover (2001). It
highlights the importance of performing the inspection in view of building
maintenance management practices as well as the method of building defects
identification during the course of building inspection work. Also, some of the
common defects are shown as to establish their occurrences in the building.
2.0 WHY INSPECTION?
Building defects can only be determined when inspection was carried out
by the competent person. This person should be qualified both academically and
by practically experience to a high standard (Glover, 2001). Otherwise, the
inspection is just a waste of time and resources, since the result of the inspection
can be questioned and seems to be unrealistic. The inspection is the start before
any recommendation can be put forward pertaining to the condition of the
building/infrastructure. If it is not important, then we can just pick anybody from
the roadside for the purpose of carrying out the inspection. To stress again, the
inspection is a high priority in defects identification and all related works alike.
In the broadest sense, the inspection is a general surface examination of
those parts of the property which are accessible: in other words, visible and
readily available for examination from ground and floor levels, without risk of
causing damage to the property or injury to the surveyor. The inspection should
be carry out by a competent person to make sure the building is fully check and
gives true information about the physical condition of the building. This is
important because if the inspection was carry out by the incompetent person, the
report to be prepared may lack of information and unclear. In most cases, there
are building which physically looks in good condition but truly there are
many hiding problems such as timber decay of structured above ceiling or
water penetration from lower floor.
-
8/3/2019 Role&Method Inspection
3/20
PERANAN DAN KAEDAH PEMERIKSAAN KECACATAN BANGUNAN
3
The important of carrying out building defects inspection is to provide
enough information to be used in maintenance planning and how to remedy the
defects. This is to prevent emergency breakdown of any element or system in the
building because building failure normally shows their symptoms before getting
worst (Hollis and Gibson, 2000). Sometimes the inspection data is not only used
for repair or maintenance purpose; it is also can be used by expert witness as the
fact in court. Besides, there are few reasons why we need the data that resulting
from the inspection:
1. To get the true picture of building physical condition especially the fabric
and the structure and knowing current building performance;
2. To determine how large the damages or defective area and planning
preventive maintenance based on priority;
3. To predict the strengthens of the old element or structure and provide
basic data for repair or extend works in existing building;
4. To provide estimate cost for the repair works and giving the value of the
building after considered all the defects; and
5. Providing basic and design information for the future.
3.0 BASIC INSPECTION SKILL AND MEDIUM
The basic skill in carrying out the inspection is on how to look and how to
see. This is important as to differentiate between competent person and ordinary
people because anyone can claim they can perform an inspection. The skill can
be our good reason to show our competency and capability in performing the
inspection.
-
8/3/2019 Role&Method Inspection
4/20
PERANAN DAN KAEDAH PEMERIKSAAN KECACATAN BANGUNAN
4
3.1 Looking vs Seeing
As explained by Hollis and Gibson (2000), looking is a skill which has
been examined by some professions, for example, the conjurer. Here is a person
who practices deceit, makes people fooling via believing that they have seen
magic where part of the action was to divert the eye. In our case, if the eye can
be diverted, there is a chance that defect may not be noticed. How to read an
image? Do you, as with book, start at the top right (or left) and run your eye down
the building? There is case where a training surveyor told to view a room
clockwise, return to the door and then view it again anticlockwise, the opposite
view often revealing that which was missed on the first circuit.
Seeing is difference with looking. Seeing is the result of the mind
interpreting the observed element or composite. To see one must first
understand. When read, it takes us to go further. Familiarity means that we do
not see the letters of each word but see their combined meaning as a word. If we
are familiar with the language, then there will be no difficulty. Many common
defects within a building are a short cut to their cause. The familiarity may
conceal the real cause of failure because we have not looked. We have seen
first, and maybe not looked at all.
To see one must first look, and then recognize. Recognition is the
gateway to seeing, because it is impossible to see without understanding,
otherwise it would be just looking. Looking is innocent and seeing is revealing
and understanding. The recollection of images enables the surveyor to place
labels on what they look at; but to understand, reliably the image; they must learn
to look, to observe and to challenge before accepting the meaning of what they
see.
-
8/3/2019 Role&Method Inspection
5/20
-
8/3/2019 Role&Method Inspection
6/20
PERANAN DAN KAEDAH PEMERIKSAAN KECACATAN BANGUNAN
6
4.0 METHOD OF BUILDING DEFECTS INSPECTION
Method of inspection particularly deals with the on-site work inspection i.e.
how do we inspect the building. It should be understand that it is different with the
type of survey/inspection, or in other words the purpose of the survey that is
going to be carried out, either for the purpose of selling/leasing, maintenance
budget, pre-construction and dilapidation. Thus, the type of survey and method of
survey (inspection) is totally two different topics. But they are closely related i.e.
inspection is compulsory in any type of survey. Moreover, the on-site inspection
is the most important and demanding activities involved with a survey. Basically
there are a number of inspection methods, in almost cases depends very much
on the preference of the surveyor, meaning that there is no such a question
whether it is right or wrong, as long as the procedural framework of inspection
follows its logical sequence (Hoxley, 2002).
4.1 Commencement of Inspection The 3Fs and Internal or External
To start with, Hoxley (2002) and Ramly (2004) suggested the essential
element of the preliminary part of a survey is to become familiar with the building.
Then the 3Fs (Hoxley, 2002) approach is apply i.e. focus, familiarity and
freedom. Focus deals with the attention given to the building to be inspected. In
many cases, the existence of owner or occupier during the inspection could
distract the process of the inspection. It is important for the surveyor to be single-
minded in carrying out the inspection.
Meanwhile familiarity deals with the experience of the surveyor in carrying
out the inspection i.e. preliminary inspection once arrived at the site will get the
surveyor familiarize with the type and layout of the building. Glover (2001)
mentioned that the surveyor should be qualified both academically and by
practical experience; but there is at present no statutory requirement for this to
-
8/3/2019 Role&Method Inspection
7/20
PERANAN DAN KAEDAH PEMERIKSAAN KECACATAN BANGUNAN
7
be so, as our country is concerned. Anyone may set their self up as a surveyor
and accept instruction from the general public to undertake such surveys.
Without the statutory to govern this, there is no obvious prospect of the
situation changing in the foreseeable future, although an unqualified surveyor
without a professional indemnity insurance policy is taking a very high risk
(Glover, 2001). As this matter is concern, the familiarity about the type and layout
of the building in the first thought (which normally suggest the condition of the
building as a whole either bad, moderate or good) is quite difficult to be
achieved.
Furthermore, the freedom means the sequence of carrying out the
inspection. Hoxley (2002) stated that scholars differ on the question of whether it
is better to commence the full inspection internally or externally. The bottom line
is it has to be in logical order. As to recommend, commencing with external
inspection sounds more logic, which also follows the usual way of reporting the
inspection work, as suggested by Hollis and Gibson (2000) and Hoxley (2002).
This is due to the reason of:
i) If anything is missed during the initial inspection of the exterior, it is
an easy task to re-inspect part of the exterior again; and
ii) It may not be easy to re-inspect the interior again, if problem is
suggested by the external inspection.
As example, heavy rain always gives effects to the outer part of the
building and in many cases, it also penetrate into the internal part of the building.
With the external inspection come first, it would suggest the bubble effect of wall
paper finishes is due to the dampness resulting from the heavy rain. If we start
from the interior, perhaps its difficult to justify whether the bubbling effect is the
result of heavy rain or something else; and this will definitely difficult once the
internal inspection had been completed.
-
8/3/2019 Role&Method Inspection
8/20
PERANAN DAN KAEDAH PEMERIKSAAN KECACATAN BANGUNAN
8
The other reason is, as our climate is concern, the weathering effect
become the main sources of building defects; and the defects manifest itself at
the external element of the building, particularly if painting become the exterior
finishes. In many respect, the order of inspection is a matter of the personal
preference of the surveyor, but what is most important is that the inspection
carried out in a logical sequence with which the surveyor is familiar (Hoxley,
2002).
4.2 External and Internal Inspection
It is usually best to follow the principle of starting at the top and working
down as the sequence of inspection (Hoxley, 2002). What to be recorded during
inspection is not discussed in detail in this paper. If the building to be inspected is
big (either multi-storey or shopping complex), then it will take more than one day
to cover the whole external part i.e. external wall, drainage, site and boundaries.
As stated by Dickinson and Thornton (2006), a straightforward procedure is
seldom possible. The process typically involves repeated inspections, tests and
data recording.
The internal inspection follows after completing the external part. In this
case, try not to break-up the sequence i.e. take a rest for few days before
continuing with the internal. This may disrupt the flow of inspection and there is
also a tendency to forget in finding out any correlation between external and
internal condition. If the inspection is carried out by a number of team, then the
internal and external inspection can go parallel. The senior surveyor will normally
supervise both inspections as to synchronize the on-site work as well as
monitoring the condition survey report later on.
Very often more than one cause may be responsible for the defect (and
there may of course be more than one defect), but in all cases it is necessary to
identify the primary cause (Dickinson and Thornton, 2006). This normally happen
-
8/3/2019 Role&Method Inspection
9/20
PERANAN DAN KAEDAH PEMERIKSAAN KECACATAN BANGUNAN
9
if the defects do not attended over a period of time. For example, the fine crack in
the concrete flat roof will allow the ficus to growth. If nothing is done, the root will
find itself in penetrating deeper inside the concrete slab. Eventually there will be
a spot of dampness at the ceiling underneath. If this is notice during inspection,
one might predict there is a serious defect occurred at the roof top. Base from
this illustration, the primary cause of the defect is the fine crack at the roof top.
As for further explanation about crack inspection, refer to Table 1 below.
Table 1: Classification of visible damage to walls with particular reference to easeof repair of plaster and brickwork masonry (Dickinson and Thornton, 2006)
For the internal, it is recommended to start from the roof space. As
mentioned by Hoxley (2002), there are 3 reasons why the inspection should be
start from this point. The first of these is that it continues the logical sequence of
starting at the top and working down. Another is that it is possible to discover
Notes: 1. It must be emphasised that in assessing the degree of damage account must be taken of the location in the building or structure
where it occurs, and also of the function of the building or structure.
2. Crack width is one factor in assessing the category of damage and should not be used on its own as direct measure of it.
3. Local deviation of slope, from the horizontal or vertical, of more than 1/100 will normally be clearly visible.
Overall deviations in excess of 1/150 are undesirable
Copyright Building Research Establishment (BRE) from BRE Digest 251.
BRE material reproduced by permission of Building Research Establishment Ltd.
Category
of
Damage
Degree(1)
of damage
Description of typical damageEase of repair in italic type Approximatecrack width mm
0 Negligible Hairline cracks of less than about 0.1mm width are classed asnegligible.
Up to 0.1(2)
1 Very slight Fine cracks which can easily be treated during normal
decoration. Perhaps isolated slight fracturing in building. Cracksrarely visible in external brickwork.
Up to 1(2)
2 Slight Cracks easily filled. Redecoration probably required. Recurrentcracks can masked by suitable linings. Cracks not necessarily
visible externally; some external repointing may be required toensure weathertightness. Doors and windows may stick slightly.
Up to 5(2)
3 Moderate The cracks require some opening up and can be patched by amason. Repointing of external brickwork and possibly a small
amount of brickwork to be replaced. Doors and windowssticking. Service pipes may fracture. Weathertightness oftenimpaired.
5 to 15(2) (or anumber of cracks
up to 3)
4 Severe Extensive repair work involving breaking-out and replacing
sections of walls, especially over doors and windows. Windowand door frames distorted, floor sloping noticeably(3). Wallsleaning(3) or bulging noticeably, some loss of bearing in beams.Service pipes disrupted.
15 to 25(2) but also
depends on numberof cracks
5 Very severe This requires a major repair job involving partial or completerebuilding. Beams lose bearing, walls lean badly and requireshoring. Windows broken with distortion, danger of instability.
Usually greaterthan 25(2) butdepends on numberof cracks
-
8/3/2019 Role&Method Inspection
10/20
PERANAN DAN KAEDAH PEMERIKSAAN KECACATAN BANGUNAN
10
more about the quality of construction in the roof space, where the builder would
have made no attempt to disguise any shortcomings, than anywhere else in a
building i.e. the tradesemen left the discarded newspaper read during their lunch-
break. Finally, a relatively high number of defects or matters requiring
improvement are often identified in the roof space.
Since this is an area of where the owners or occupiers never venture and
they are very often not aware of some of the defects revealed by a survey
(Hoxley, 2002), it sounds very reasonable to adapt this sequence. Moreover, to
start with roof seems to be mandatory if the roof garden is part of the element
that needs to be inspected. The roof inspection should cover all the mechanical
and electrical room, together with water tank, chiller and any form of structure
above it (unless excluded in the letter of instruction). Bear in mind that the
surveyors just carry out the general inspection of all these mechanical and
electrical equipments. In this sense, the boundary of inspection work should be
clear-cut between the surveyor and the equipment specialist. Any visible defect
must be noted and pass on to the specialist for their consideration and further
investigation (should they need to perform it).
Once the roof space is inspected, each room and/or space (including
circulation areas such as staircase) should be inspected in detail. Again a logical
sequence should be followed, such as inspecting in turn (Hoxley, 2002):
i) Ceiling;
ii) Each wall (usually four);
iii) Window(s);
iv) Door(s);
v) Air-conditioning and/or heater;
vi) Electrical fittings; and
vii) Floor.
-
8/3/2019 Role&Method Inspection
11/20
PERANAN DAN KAEDAH PEMERIKSAAN KECACATAN BANGUNAN
11
Again the philosophy of the working downwards from the top has been
followed in each room and it is likely that the upper floors would be inspected
before the ground floor and basement (if any). The surveyor will already be
located at upper floor level after inspecting the roof space and this seems to be
called as logical sequence (Hoxley, 2002), as mentioned earlier in this paper.
4.2 Recording the Information
During the course of inspection, all the defects identified need to be
properly record, otherwise it will create difficulties in the next stage of building
survey i.e. the preparation of report. Normally the information to be recorded on
site, as stated by Hoxley (2002) are (i) design and construction; (ii) condition; (iii)
cause of any defects (or recommendation for further investigation); and (iv)
remedial work required. But in practice, this seems to be quite time consuming
(not mean that hurry is permitted for building inspection work). Therefore the
least to be recorded, as to suggest, the condition of the building elements,
including assigning related rating for the particular defects i.e. good, moderate
and poor (as for easy analysis later on).
But this is not recommended for inexperience surveyor, as well as when
inspecting the building than the surveyor might not be familiar with i.e. pre-war
building, castle, mansion and alike. Again, it does go to the surveyor familiarity
and preference. This is because obviously each surveyor will develop his own
style of note-taking and may well abbreviate frequently used terms (Hoxley,
2002). As to ensure error-free inspection, the information recorded (the what)
and the method of recording on-site information (the how) play the vital role.
According to Hoxley (2002), there are 6 methods of recording on-site information,
which outlined below.
-
8/3/2019 Role&Method Inspection
12/20
PERANAN DAN KAEDAH PEMERIKSAAN KECACATAN BANGUNAN
12
i) Long-hand
This is the most time consuming method, whereby it seems like writing
whatever that have been encountered during the inspection. The
advantage is that there is a clear and comprehensive record that are
available later on should this is necessary.
ii) Tape-recorder
This is the easiest way on-site, but the transcription process after that will
be very time consuming. This is to be so since most people can talk seven
times faster that they can write (Hoxley, 2002). The surveyor must be
careful enough during the recording process on-site. Failure to do so is
going to be terrible experience as to dictate the surveyors voice as well as
unnecessary sound together with it. The video recorder can also be used,
but with the help of assistance on-site. Handling the video recorder alone
would be very troublesome.
iii) Site-prepared sketches
This should be preferred by most perhaps, since it is easily locate the
defect in the sketches for one particular area. It is also simple and
practical since the location of the defects can be depicted in a most
meaningful manner. This method is most recommended if the as-built
drawing of the building is in-hand during the inspection (but be sure the
as-built is the most updated one, or else it will create another problem on-
site). As stated by Hoxley (2002), this method is strongly advocated by
one leading authority i.e. Hollis for the residential inspection.
iv) Pre-printed form/checklist
This is straightforward method of recording and might ease the work on-
site. The survey pro forma normally outlined the type of information that is
going to be recorded. But the preparation should be made before the day
of inspection. More often than not, even though the checklist is in the
-
8/3/2019 Role&Method Inspection
13/20
PERANAN DAN KAEDAH PEMERIKSAAN KECACATAN BANGUNAN
13
hand, the surveyor tends not to strictly adhere to it, and still the sketches
will do. This found to be true if the most common defects are noticed
several time during the inspection, as well as the defects suggest some
trend in their occurrences. For residential inspection, this method is
regarded by Hoxley (2002) as one to best suit the inexperience surveyor.
v) On-site computer
This is the quickest method of recording, either by the secretary or speech
recognition software. Whatever defects identified is directly transcribe on-
site during the inspection. It means that the surveyor does not need to
return to the office for typing the report. All is done during the period of
inspection. Its sound quite technological in advance but the absence of
any site notes leaves the surveyor open to a claim of negligence when
adopting this method (Hoxley, 2002). In this respect, it is recommended to
perform the minimum sketches as to supplement the report should this
method applied.
vi) Hand-held device (i.e. PDA)
The function of Personal Digital Assistance (PDA) nowadays is superb.
The high specification can do voice and video recording, either separate
or concurrent usage. It combining the feature of voice recorder, video
camera and digital camera, and any another features that available to
date. With RFID (radio frequency identification) technology that most
convenience as compared to barcode, this method is very much
recommended for performing the stock condition survey.
5.0 BUILDING DEFECTS AN EXAMPLE
It is compulsory to record the defects identified in the form of photograph.
As logical sequence, the sketches depicted the defects location and the
-
8/3/2019 Role&Method Inspection
14/20
PERANAN DAN KAEDAH PEMERIKSAAN KECACATAN BANGUNAN
14
photograph shows the defect itself (there is a case where the photograph
becomes an evidence of the surveyor on-site, particularly during the inspection).
With the use of imaging technology, the photograph can be enhanced later on to
focus on the defects i.e. crop and focus on the defected area. In showing how the
defect manifest itself, the use of simple hand illustration/sketch is sufficient
enough. As to ensure no defects is missing to be recorded, the image of each
defects identified must be captured. It is a best practice to put the note on each
photos within 7 days after the inspection completed (the earliest possible is most
recommended), since our memory be inclined to forget what have been captured
of more than 7 days time. This section portray some of the common defects
together with it notes that normally be encountered during the course of
inspection in our Malaysian climatic condition, as well as typical humidity causes
in building as suggested by Kottas (2007).
Roof
Growth of mould and algae due to water
ponding and continuous dampnessWater ponding due to blockage of outlet to
rainwater downpipe (due to small outlet)
its very hot during the course of inspection
-
8/3/2019 Role&Method Inspection
15/20
PERANAN DAN KAEDAH PEMERIKSAAN KECACATAN BANGUNAN
15
Ceiling
Ficus (plant) growth below roof covering due
to dampness and present of debris
Dent of roof edge due to hard wind impact
(perhaps also by vandalism it is noticed that
somebody loafed on the roof)
Water mark on the ceiling surface due to
water penetration from leaking roof (the
brown color suggest it dripped via timber
trusses, perhaps the trusses need structural
inspection)
Stalactite effect due to water proofing failure
at upstairs toilet
-
8/3/2019 Role&Method Inspection
16/20
PERANAN DAN KAEDAH PEMERIKSAAN KECACATAN BANGUNAN
16
Wall
Floor
Paint coating efflorescence and flaking due to
failure to prepare adequate dry surface
before painting works and used of low quality
paint (which not durable)
Flaking of plaster surface due to hard
impaction during moving activity
Peeling of tiles due to insufficient adhesive
Tiles finishes has been lifted due to
dampness from drain
Drop of floor surface due to settlement
-
8/3/2019 Role&Method Inspection
17/20
PERANAN DAN KAEDAH PEMERIKSAAN KECACATAN BANGUNAN
17
External and Services
Concrete manholes cover damaged and
affected floor near to it due to insufficient
support and/or overload
Gap at gutter jointing due to poor
workmanship very lucky to carry out
inspection during rainy days
Corrosion of water pipe due to leakage of
jointing
-
8/3/2019 Role&Method Inspection
18/20
PERANAN DAN KAEDAH PEMERIKSAAN KECACATAN BANGUNAN
18
Figure 1: Typical causes of humidity in buildings (Kottas, 2007)
Penetration by water
1. No waterproofing beneath the coping tiles on the parapet
2. Faulty chimney hood
3. Faulty chimney flashing
4. Tiles, loose or broken
5. Faulty flashing of the roof valley
6. No weather strip above the window head
-
8/3/2019 Role&Method Inspection
19/20
PERANAN DAN KAEDAH PEMERIKSAAN KECACATAN BANGUNAN
19
7. Faulty painting of the window frames
8. Cracks in the rendering of the walls
9. Cracks in the window sill
10. Asphaltic sheet on walls is insufficient
11. Cracks in the asphaltic insulation on a flat roof
12. Drainage, broken or blocked
13. No drip or weather molding to shed stormwater
14. Faulty plastering of the joints of a hollow wall
Rising damp
15. Uninsulated retaining walls
16. No insulation under the floor or over the foundation walls
17. The surrounding grade is higher than waterproof layer
18. Faulty insulation under the floor
Condensation
19. Unventilated air space under the roof
20. No ventilating brick in the flue
21. Damp walls inside unventilated cupboards
22. Flat roofs with no vapour barrier
23. Condensation on the inside of a solid concrete lintel
6.0 Conclusion
We do not want a structural survey. If you can just have a quick look at the
house to make sure that it is structurally sound, that will be fine. Extract from
clients letter of instruction. (Glover, 2001. pp. 15).
Based from the quotation above, it shows the importance of having the
general building defects inspection. To some people, it sounds easy rather than
not, as most of them not following the real practice of building inspection. The
basic skill i.e. looking versus seeing is mean to justify this truly mechanistic task.
-
8/3/2019 Role&Method Inspection
20/20
PERANAN DAN KAEDAH PEMERIKSAAN KECACATAN BANGUNAN
20
Above all, the method of inspection depends very much on the preference of the
surveyor. The bottom line is it must follow the logical sequence. During the
inspection, the surveyor must cover what to be recorded and how it is
recorded. The condition of the defects and accompanied by the sketches will do
in almost any form of inspection that the surveyor familiar with.
A point to ponder, do we need specialist to carry out those inspection i.e.
general inspection, as more or less the outcome will be in the form of
photographs illustrated above?Definitely its seems to be just waste of time and
resources. Somebody has to come first for this kind of inspection, and definitely
specialist will be put on standby mode (ready to come only when required). In
simple analogy, dont go to specialist if you just have the fever, headache, flu and
alike. The specialist will double charge you for taking their precious time for
undertaking general inspection to your health; and same goes to our building
inspection. As the living environment is become more and more complex and
dynamic nowadays, anybody is no longer can be anybody without sufficient
academic and professional competency background, which also had mentioned
by several leading authority in this discipline i.e. Hollis and Gibson (2000), Glover
(2001), Wordsworth (2001) and Ramly (2004).
References
Dickinson, P. R.; Thornton, N. (2006). Cracking and Building Movement.Reprinted. First Published in 2004. Coventry: RICS Books Imprint.
Glover, P. (2001). Building Surveys. 4th Edition. Oxford: Butterworth-Heinemann.Hollis, M.; Gibson, C. (2000). Surveying Buildings. 4th Edition. Coventry: RICS
Books Imprint.Hoxley, M. (2002). Condition Inspections of Residential Property: A Procedural
Framework. Journal of Structural Survey. Volume 20 Number 1. pp. 31-35.
MCB University Press Limited.Kottas, D. (2007). The Architects Handbook. Singapore: Page One Publishing
Private Limited.Ramly, A. (2004). Panduan Kerja-Kerja Pemeriksaan Kecacatan Bangunan
(Guideline for Building Defects Inspection Work). Selangor: Hizi Print Sdn.Bhd.
Wordsworth, P. (2001). Lees Building Maintenance Management. 4th Edition.Oxford: Blackwell Science Ltd.