role of account management at ercot prr 672 collaborative analysis presentation to rms november 8,...
TRANSCRIPT
Role of Account Management at ERCOT
PRR 672 Collaborative Analysis
Presentation to RMS
November 8, 2006
DRAFT ONLY
DRAFT ONLY2
Background of PRR672
• PRR written as a result of changes from Terms and Conditions.
• PRR requested timing changes for ERCOT processing of
transactions – TCTF noted in original PRR:
– A group needs to review CR and TDSP transaction timing requirements related to Terms and Conditions project to be addressed in a separate PRR.
• Group shared that ERCOT timing was first priority. TDSPs and CRs are reviewing timing changes.
– Due to the mandatory nature of the rulemaking, TCTF would also ask that ERCOT consider and present other options that may be less expensive to implement in the event that the changes proposed in this PRR would be cost prohibitive or would not allow implementation by the dates required by the rulemaking.
DRAFT ONLY3
Background of PRR672
• PRR puts ERCOT transaction timings into four categories based on their priority in the marketplace:– Level 1 Transactions: Including transaction pairs (inbound and outbound)
relating to 814_16 priority move-ins and 814_20 creates (adds), which should be processed within 1 Retail Business Hour (any hour within a Retail Business Day as defined in Section 2 of Protocols).
– Level 2 Transactions: Including transaction pairs relating to standard move-ins, move-outs, Off cycle Drops to AREP and Off cycle switches, which should be processed within 2 Retail Business Hours.
– Level 3 Transactions: Including transaction pairs relating to historical usage transactions, and 814_20 changes, which should be processed within 4 Retail Business Hours.
– Level 4 Transactions: Including pairs relating to On-cycle Switches, On-cycle Drops, 814_26 Ad Hoc Usage Request, Establishing/Deleting CSA within 1 Retail Business Day.
DRAFT ONLY4
PRS recommendation 7/20/06
• On 07/20/06, PRS voted to recommend approval of PRR672 as submitted by the Retail Market Subcommittee (RMS). Revised language will be grey-boxed until system implementation. ERCOT will be directed to implement priority move-ins within two (2) Retail Business Hours with the TX SET 3.0 implementation. Remaining grey-boxed language will be implemented with future system functionality. ERCOT and Market Participants will have a collaborative analysis of Retail Business Processes (RBP) associated with PRR672 transaction timing changes. Results of the analysis will be presented to RMS no later than the November 2006 RMS meeting.
• Rank and priority: – Two (2) Retail Business Hours processing and sorting of priority move-in
to be included with TX SET 3.0.– All other changes for PRR672 will be included in Project 60008_01
(priority 1.1; rank 10) • The motion passed with one (1) abstention from the Municipal segment.
All Market Segments were present for the vote.
DRAFT ONLY5
TAC recommendation to BOD 8/3/06
• On 08/03/06, TAC voted to recommend approval of PRR672 with
Phase 2 and Phase 3 language to be grey-boxed and assigned a
high priority to Phase 1.
• Priorities for Phase 2 and Phase 3 will be considered after
system and impact analyses have been completed and issues
have been further vetted.
• TAC will present Phase 1 and its associated costs to the ERCOT
Board for approval at this time.
• Phase 2 and Phase 3 costs will be further defined upon
completion of analysis.
• The motion passed with two oppositions from the Consumer
segment. All Market Segments were present for the vote.
DRAFT ONLY6
BOD action 8/15/06
• The Board voted unanimously to approve PRR672 as
recommended by TAC.
DRAFT ONLY7
Collaborative Analysis – Level 1 Recap
• Level 1 Transactions: Including transaction pairs (inbound and outbound) relating to 814_16 priority move-ins and 814_20 creates (adds), which should be processed within 1 Retail Business Hour (any hour within a Retail Business Day as defined in Section 2 of Protocols).
• Findings support timing changes for:– 814_16 Priority Move-Ins
• Approach - Two (2) Retail Business Hours processing and sorting of priority move-in to be included with TX SET 3.0.
• Approach – additional system changes (going from 2hr to 1hr) to be managed in PR60008 – Market decision to re-rank
• Findings by ERCOT support alternative to changing transaction timing for:
– 814_20 Creates (adds)• ERCOT recommends near term approach – changing transaction flow process for
814_20s (Two SIRs to be in Feb 2007 release)– Automate the 814_20s throttling capabilities within current processing pipe (all 814s) – Building a separate processing pipe for 814_20/814_21 processing
• ERCOT requests the market to review the production results from the near-term before adding system changes to PR60008 for the 814_20s
DRAFT ONLY8
Findings from Analysis – Level 1 transactions
• Priority Move-Ins
– TDSP needs to receive by 5pm or the order is considered received the next business day.
– CRs may need to review their batch times
– CRs may need to review their call center scripts to ensure that customer expectations are set appropriately
Tim
e re
ceiv
ed b
y E
RC
OT
To
tal
Mo
ve-i
ns
Rec
eive
d
Ou
t b
y 5p
m
No
t o
ut
by
5pm
% D
id n
ot
Get
Ou
t
12 a.m. 150 150 - 0% 1 a.m. 130 130 - 0% 2 a.m. 159 159 - 0% 3 a.m. 102 102 - 0% 4 a.m. 100 100 - 0% 5 a.m. 100 100 - 0% 6 a.m. 808 808 - 0% 7 a.m. 5,020 5,020 - 0% 8 a.m. 6,494 6,494 - 0% 9 a.m. 4,916 4,916 - 0% 10 a.m. 7,272 7,271 1 0% 11 a.m. 7,139 7,138 1 0% 12 p.m. 11,000 10,490 510 5% 1 p.m. 11,633 9,497 2,136 18% 2 p.m. 8,898 3,659 5,239 59% 3 p.m. 8,176 566 7,610 93% 4 p.m. 10,281 440 9,841 96%
DRAFT ONLY9
Collaborative Analysis – Level 2 recap
• Level 2 Transactions: Including transaction pairs relating to standard move-ins, move-outs, Off cycle Drops to AREP and Off cycle switches, which should be processed within 2 Retail Business Hours
• Findings support timing changes for:– Standard Move-ins– Move outs
• Approach – additional system changes (going to 2 hr) to be managed in PR60008 – Market decision to re-rank
• ERCOT does not believe that the analysis support the timing changes for the following:
– Off-cycle Switches – Off-cycle Drop to AREP
• ERCOT plans to file another PRR to move these to Level 4• Market participants did not agree with the moving from Level 2 to Level 4
DRAFT ONLY10
Findings from Analysis – Level 2 transactions
• Standard Move-Ins
– Standard move ins need to be received 2 business days prior to the requested date. TDSP needs to receive by 5pm or the order is considered received the next business day.
– CRs may need to review their batch times
– CRs may need to review their call center scripts to ensure that customer expectations are set appropriately
Tim
e re
ceiv
ed b
y E
RC
OT
To
tal
Mo
ve-i
ns
Rec
eive
d
Ou
t b
y 5p
m
No
t o
ut
by
5pm
% D
id n
ot
Get
Ou
t
12 a.m. 150 150 - 0% 1 a.m. 130 130 - 0% 2 a.m. 159 159 - 0% 3 a.m. 102 102 - 0% 4 a.m. 100 100 - 0% 5 a.m. 100 100 - 0% 6 a.m. 808 808 - 0% 7 a.m. 5,020 5,020 - 0% 8 a.m. 6,494 6,494 - 0% 9 a.m. 4,916 4,916 - 0% 10 a.m. 7,272 7,271 1 0% 11 a.m. 7,139 7,138 1 0% 12 p.m. 11,000 10,490 510 5% 1 p.m. 11,633 9,497 2,136 18% 2 p.m. 8,898 3,659 5,239 59% 3 p.m. 8,176 566 7,610 93% 4 p.m. 10,281 440 9,841 96%
DRAFT ONLY11
Findings from Analysis – Level 2 transactions
• Move-outs
–85% are submitted 2 or more days ahead–These are Move Outs, Move Out to CSA – does not include force off–Move Outs need to be received 2 business days prior to the requested date. TDSP needs to receive by 5pm or the order is considered received the next business day.
Transaction Submitted CountPercent of
Total
Submitted 3 or More Days Ahead 32,911 71%Submitted 2 Days Ahead 6,674 14%Submitted for Next Day 1,407 3%Submitted for Same Day 4,684 10%Backdated 1 Day 440 1%Backdated 2 or More Days 246
Total Move Out Transactions 46,362
DRAFT ONLY12
Findings from Analysis – Off Cycle Switches
Switches with a Special Switch Date
-
200
400
600
800
1,000
1,200
Days submitted ahead
Nu
mb
er
of
Tra
nsacti
on
s
ERCOT does not believe the analysis supports the timing changes for the following:
Off-cycle Switches •Market behavior of sending >15 days from date requested – changing the timing does not change the result for the end use customer•Protocol language for First Available Switch Date (FASD)
DRAFT ONLY13
Excerpt from Protocol 15.1.1
The FASD for a Switch Request where notification has not been waived is calculated as follows:
FASD = EPD + 3BD (Mailing to notify Customer of the pending Switch Request)+ 7CD (Customer Rescission Period)+ 3BD (Processing time to allow for potential cancellation by Customer)
In the event that Customer notification has been waived, the CR will indicate such a waiver in the 814_01 transaction. For additional information concerning which Customer class and /or events would qualify for a waiver of Customer notification, CRs should refer to the PUCT rules.
The FASD is calculated as follows for a waiver of notification:FASD = EPD + 3BD (Processing time)
Where:EPD = ERCOT Processed DateBD = Business Day (Does not include TDSP holidays.)CD = Calendar Day
DRAFT ONLY14
Findings from Analysis – Off Cycle Drop to AREP
ERCOT does not believe the analysis supports the timing changes for the following:
Off-cycle Drop to AREP•Market behavior of sending at least 8 days from date requested – changing the timing does not change the result for the end use customer•Protocol language for First Available Switch Date (FASD)
Drop to AREP Days Submitted Prior to Scheduled
0
50
100
150
200
250
300
8 10 12 14 16 18 20 22 24 27 29 31 33 35 37 39
Days
Nu
mb
er o
f T
ran
sact
ion
s
DRAFT ONLY15
Findings from Analysis – Off Cycle Drop to AREP
ERCOT does not believe the analysis supports the timing changes for the following:
Off-cycle Drop to AREP
•Protocol language for First Available Switch Date (FASD) – excerpt from 15.1.2.1
The FASD for a Drop to AREP Request is calculated starting with the date that ERCOT processes the 814_10 sent by the CR. The FASD is calculated as follows:
FASD = EPD + 6BD (Processing time)
Where:EPD = ERCOT Processed DateBD = Business Day (Does not include TDSP holidays.)
DRAFT ONLY16
Collaborative Analysis – Level 3 recap
• Level 3 Transactions: Including transaction pairs relating to historical usage transactions and 814_20 changes (i.e. maintains), which should be processed within 4 Retail Business Hours
• Findings by ERCOT support alternative to changing transaction timing for:
– 814_20 changes (i.e. maintains)• ERCOT recommends near term approach – changing transaction flow process
for 814_20s (Two SIRs to be in Feb 2007 release)– Automate the 814_20s throttling capabilities within current
processing pipe (all 814s) – Building a separate processing pipe for 814_20/814_21 processing
• ERCOT requests the market to review the production results from the near-term before adding system changes to PR60008 for the 814_20s
• Findings indicate that ERCOT already meets the 4 hour turn for historical usage (867_02).
DRAFT ONLY17
Collaborative Analysis – Level 4 recap
• Level 4 Transactions: Including pairs relating to On-cycle
Switches, On-cycle Drops, 814_26 Ad Hoc Usage Request,
Establishing/Deleting CSA within 1 Retail Business Day.
– Does not change current protocol timing. – No analysis requested by Market.– ERCOT will recommend adding additional transactions to this
category based upon the analysis shared with the market.
DRAFT ONLY18
Collaborative Analysis Recommendations
Recommendations:
1. TX SET 3.0 – priority Move ins w/in 2 hours – in progress
2. Ask ERCOT to move forward with near-term recommendations for 814_20 processing changes to be implemented prior to PR60008.
Automate the 814_20s throttling capabilities within current processing pipe (all 814s)
Building a separate processing pipe for 814_20/814_21 processing
3. Re-rank and initiate project PR60008 (remainder of grey box)– Intent of PR60008 is to implement remainder of grey box changes to
address timing of transactions – Intent of PR60008 also to include changes from a PRR that ERCOT will
draft for prioritization of all transactions (as set by analysis from this group) and recommend moving off-cycle switches and drops to AREP to level 4 transactions (not everyone participating agreed)
– Once re-ranked, ERCOT would provide IA and CBA for system changes (using information from collaborative analysis)
DRAFT ONLY19
Collaborative Analysis Closure
• PRR 672
– Phase 1 – already underway for TX SET 3.0
– Phase 2 & 3 – Collaborative Analysis / Future system release (PR60008 – Terms & Conditions)
• This report back to RMS at Nov 06 Meeting• RMS to report to TAC in Dec 06• TAC to report to BOD in Jan 07
– Near term – ERCOT to begin work on near term recommendations
– Long term – Market make decision to reprioritize PR60008 for 2007 Project list
• Market may file PRR on CR / TDSP timing changes that are needed
• ERCOT will draft PRR for prioritization of all transactions (as set by
analysis from this group) and recommend moving off-cycle switches
and drops to AREP to level 4 transactions
DRAFT ONLY20
Collaborative Analysis Closure
814_20 processing - Until near-term recommendations are
implemented – ERCOT encourages TDSPs to continue to
communicate to ERCOT any large volumes of 814_20s to be
managed through current market processes (bundles and
manual intervention by ERCOT and TDSPs).
Long Term analysis continues at TX SET
This concludes the Collaboration effort for PRR672. Thank you
for your support.