rock drop structure...profile rock drop structure notes: 1. a rock drop structure is a series of two...

2
FLOW A X1 - ROCK DROP STRUCTURE INVERT CONTROL POINT ELEVATION, TYPICAL (SEE NOTE 2) CONNECTING BOULDER, TYPICAL (SEE NOTE 9) SCOUR POOL, TYPICAL FLOODPLAIN SILL, TYPICAL X2 - LEFT VANE ARM INTERCEPT CONTROL POINT ELEVATION, TYPICAL (SEE NOTE 2) X3 - RIGHT VANE ARM INTERCEPT CONTROL POINT ELEVATION, TYPICAL (SEE NOTE 2) 1/3 X4 X8 X7 X6 X9 X4 COARSE BACKFILL (SEE NOTE 8) A' TOP OF BANK, TYPICAL X16 FLOW X3 - RIGHT VANE ARM INTERCEPT CONTROL POINT ELEVATION FILTER FABRIC (SEE NOTE 7) X1 - ROCK DROP STRUCTURE INVERT CONTROL POINT ELEVATION X2 - LEFT VANE ARM INTERCEPT CONTROL POINT ELEVATION HEADER BOULDER, TYPICAL (SEE NOTE 6) FOOTER BOULDER, TYPICAL (SEE NOTE 6) X8 X10 X4 1/3 X4 TOP OF BANK X12 X16 X17 1 ROCK DROP STRUCTURE NOT TO SCALE REV. # REV. DATE DRAFT - NOT TO BE USED FOR CONSTRUCTION 1 OF 2 SHEET NUMBER PLAN VIEW CROSS SECTION A - A' PHOTO: ROCK DROP STRUCTURE AT PIPE OUTLET THIS FIGURE IS ONLY MEANT TO DEFINE THE MINIMUM INFORMATION REQUIRED BY THE CITY OF CHARLOTTE TO BE INCLUDED IN A DETAIL FOR THIS TYPE OF TECHNIQUE. THIS FIGURE IS NOT MEANT TO REPRESENT A STANDARD DESIGN METHOD FOR THIS TYPE OF TECHNIQUE AND SHALL NOT BE USED AS SUCH.

Upload: others

Post on 17-Oct-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ROCK DROP STRUCTURE...profile rock drop structure notes: 1. a rock drop structure is a series of two or more interconnected in-stream, grade control structures that direct stream flow

FLO

W

A

X1 - ROCK DROP STRUCTURE INVERT CONTROL POINT ELEVATION, TYPICAL (SEE NOTE 2)

CONNECTING BOULDER, TYPICAL(SEE NOTE 9)

SCOUR POOL, TYPICAL

FLOODPLAIN SILL,TYPICAL

X2 - LEFT VANE ARM INTERCEPT CONTROL POINT ELEVATION, TYPICAL (SEE NOTE 2)

X3 - RIGHT VANE ARM INTERCEPTCONTROL POINT ELEVATION,

TYPICAL (SEE NOTE 2)

1/3 X4

X8

X7

X6

X9

X4

COARSE BACKFILL(SEE NOTE 8)

A'

TOP OF BANK, TYPICAL

X16

FLO

W

X3 - RIGHT VANE ARM INTERCEPTCONTROL POINT ELEVATION

FILTER FABRIC(SEE NOTE 7)

X1 - ROCK DROP STRUCTURE INVERTCONTROL POINT ELEVATION

X2 - LEFT VANE ARM INTERCEPT CONTROL POINT ELEVATION

HEADER BOULDER, TYPICAL (SEE NOTE 6)

FOOTER BOULDER, TYPICAL (SEE NOTE 6)

X8

X10

X4

1/3 X4

TOP OF BANK

X12

X16

X171

ROCK DROP STRUCTURE

NOT TO SCALE

REV. #REV. DATE

DRAFT - NOT TO BE USED FOR CONSTRUCTION

1 OF 2SHEET NUMBER

PLAN VIEWCROSS SECTION A - A'

PHOTO: ROCK DROP STRUCTURE AT PIPE OUTLET

THIS FIGURE IS ONLY MEANT TO DEFINE THE MINIMUM INFORMATION REQUIRED BY THE CITY OF CHARLOTTE TO BE INCLUDED IN A DETAIL FOR THIS TYPE OF TECHNIQUE.THIS FIGURE IS NOT MEANT TO REPRESENT A STANDARD DESIGN METHOD FOR THIS TYPE OF TECHNIQUE AND SHALL NOT BE USED AS SUCH.

Page 2: ROCK DROP STRUCTURE...profile rock drop structure notes: 1. a rock drop structure is a series of two or more interconnected in-stream, grade control structures that direct stream flow

FLOW

FOOTER BOULDER,TYPICAL

X1 - ROCK DROP STRUCTUREINVERT CONTROL POINT

ELEVATION, TYPICAL(SEE NOTE 2)

TOP OF BANK

HEADER BOULDER,TYPICAL

X7

X11

X10

FILTER FABRIC

NOT TO SCALE

REV. #REV. DATE

2 OF 2SHEET NUMBER

DRAFT - NOT TO BE USED FOR CONSTRUCTION

PROFILE

ROCK DROP STRUCTURE

NOTES:

1. A ROCK DROP STRUCTURE IS A SERIES OF TWO OR MORE INTERCONNECTED IN-STREAM, GRADECONTROL STRUCTURES THAT DIRECT STREAM FLOW AWAY FROM THE STREAM BANKS AND IN TOWARDTHE CENTER OF THE CHANNEL. THESE STRUCTURES SHALL TYPICALLY BE USED TO TIE-IN STORMDRAINAGE PIPES AND CHANNELS TO STREAMS ON STEEP SLOPES. FISH PASSAGE IS NOT A CONCERN.IF FISH PASSAGE IS A CONCERN HOWEVER, THE DROPS BETWEEN EACH STRUCTURE SHALL BE LIMITEDAS SPECIFIED BY THE DESIGNER.

2. ELEVATION CONTROL POINTS SHALL BE DESIGNATED THE UPSTREAM INVERT OF EACH GRADECONTROL STRUCTURE TO ESTABLISH PART OF THE PROFILE. SURVEY OF CONTROL POINTS SHALL BEREQUIRED TO ESTABLISH ACCURATE ROCK DROP STRUCTURE INSTALLATION WITHIN THE TOLERANCESPECIFIED BY THE DESIGNER.

3. EACH VANE ARM SHALL RISE FROM THE INVERT TO INTERCEPT THE STREAM BANK AT A HEIGHT EQUALTO BETWEEN ½ BANKFULL STAGE AND BANKFULL STAGE. ELEVATION CONTROL POINTS MAY BEESTABLISHED AT THE LEFT AND RIGHT STREAM BANK/VANE ARM INTERCEPT POINTS. BANKFULL IS NOTNECESSARILY THE TOP OF THE STREAM BANK SLOPE.

4. A TABLE OF ALL STATION LOCATIONS AND CONTROL POINT ELEVATIONS OF THE ROCK DROPSTRUCTURE SHALL BE PROVIDED IN THIS DETAIL.

5. A TYPICAL CROSS SECTION SHALL BE PROVIDED ELSEWHERE IN THE PLANS TO ESTABLISH THEDIMENSIONS OF THE CHANNEL GRADING INTO WHICH THE ROCK DROP STRUCTURE IS TO BEINSTALLED.

6. THE ROCK DROP STRUCTURES SHALL BE CONSTRUCTED WITH FLAT-SIDED BOULDERS OF A SIZE(LENGTH, WIDTH, AND DEPTH) AS SPECIFIED BY THE DESIGNER.

7. FILTER FABRIC OF A TYPE AND SIZE SPECIFIED BY THE DESIGNER SHALL BE USED TO SEAL THE GAPSBETWEEN THE BOULDERS AND UNDER THE COARSE BACKFILL MATERIAL.

8. COARSE BACKFILL OF THE ROCK DROP STRUCTURE SHALL BE OF A TYPE, SIZE, AND GRADATION ASSPECIFIED BY THE DESIGNER. COARSE BACKFILL SHALL BE PLACED IN EACH GRADE CONTROLSTRUCTURE TO A THICKNESS EQUAL TO THE DEPTH OF THE HEADER AND FOOTER BOULDERS ANDSHALL ALSO EXTEND OUT FROM THE VANE ARMS TO THE STREAM BANK.

9. THE INVERT (CENTER) OF EACH GRADE CONTROL STRUCTURE SHALL BE CONSTRUCTED FIRST,FOLLOWED BY ONE VANE ARM AND THEN THE OTHER VANE ARM. BOULDERS CONNECTING THEINDIVIDUAL GRADE CONTROL STRUCTURES SHALL THEN BE INSTALLED. THE FLOODPLAIN SILLS SHALLBE CONSTRUCTED LAST AND ARE REQUIRED ON AT LEAST THE FIRST AND LAST OF THEINTERCONNECTED GRADE CONTROL STRUCTURES.

10. ROCK DROP STRUCTURES SHALL BE BUILT TYPICALLY AS FOLLOWS:

A. BEGIN WITH THE DOWNSTREAM-MOST (LOWEST) GRADE CONTROL STRUCTURE.B. OVER-EXCAVATE STREAM BED TO A DEPTH EQUAL TO THE TOTAL THICKNESS OF THE HEADER

AND FOOTER BOULDERS.C. PLACE FOOTER BOULDERS. THERE SHALL BE NO GAPS BETWEEN BOULDERS.D. INSTALL FILTER FABRIC.E. PLACE COURSE BACKFILL BEHIND THE FOOTER BOULDERS.F. INSTALL HEADER BOULDERS ON TOP OF AND SET SLIGHTLY BACK FROM THE FOOTER

BOULDERS (SUCH THAT PART OF THE HEADER BOULDER IS RESTING ON THE COARSEBACKFILL). HEADER BOULDERS SHALL SPAN THE SEAMS OF THE FOOTER BOULDERS. THERESHALL BE NO GAPS BETWEEN BOULDERS.

G. PLACE COARSE BACKFILL BEHIND HEADER BOULDERS ENSURING THAT ANY VOIDS BETWEENTHE BOULDERS ARE FILLED.

11. IF ANY EROSION CONTROL MATTING IS SPECIFIED FOR USE IN THE VICINITY OF THE VANE ARMINTERCEPT POINTS AND FLOODPLAIN SILLS ALL MATTING EDGES SHALL BE NEATLY SECURED AROUNDTHE BOULDERS.

THIS FIGURE IS ONLY MEANT TO DEFINE THE MINIMUM INFORMATION REQUIRED BY THE CITY OF CHARLOTTE TO BE INCLUDED IN A DETAIL FOR THIS TYPE OF TECHNIQUE.THIS FIGURE IS NOT MEANT TO REPRESENT A STANDARD DESIGN METHOD FOR THIS TYPE OF TECHNIQUE AND SHALL NOT BE USED AS SUCH.

DIMENSIONS (VALUES TO BE PROVIDED BY DESIGNER)

VARIABLE VALUES TYPICAL UNIT DESCRIPTION

X1 FT. (NAVD) INVERT CONTROL POINT ELEVATION

X2 FT. (NAVD) LEFT INTERCEPT CONTROL POINT ELEVATION

X3 FT. (NAVD) RIGHT INTERCEPT CONTROL POINT ELEVATION

X4 FT. BANKFULL WIDTH

X5 IN. OR FT. D50 OF COARSE BACKFILL

X6 FT. VANE ARM LENGTH

X7 FT. LENGTH OF INDIVIDUAL GRADE CONTROL STRUCTURE

X8 FT. LENGTH OF FLOODPLAIN SILL

X9 DEGREES VANE ARM ANGLE WITH TOP OF BANK

X10 IN. OR FT.DIFFERENCE BETWEEN TOP OF BANK AND VANE ARM INTERCEPTPOINT

X11 IN. OR FT. DROP BETWEEN INVERTS

X12 PERCENT VANE ARM SLOPE

X13 IN. OR FT. BOULDER LENGTH

X14 IN. OR FT. BOULDER WIDTH

X15 IN. OR FT. BOULDER THICKNESS

X16 FT. CHANNEL WIDTH

X17 NONE BANK SLOPE RATIO (HORIZONTAL COMPONENT)