Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU funded Projects” Road Infrastructure Agency REPUBLIC OF BULGARIA MINISTRY OF REGIONAL DEVELOPMENT AND PUBLIC WORKS

Upload: gerard-scott

Post on 04-Jan-2016

212 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU

Road infrastructure in Bulgaria

1

Slovene – Bulgarian Business Forum, 12th May 2010

Vasilka KostadinovaDirector of Directorate “Implementation of EU funded Projects”Road Infrastructure Agency

REPUBLIC OF BULGARIA MINISTRY OF REGIONAL DEVELOPMENT AND PUBLIC WORKS

Page 2: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU

European transport corridors

2

Page 3: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU

3

European transport corridors in Bulgaria

Page 4: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU

Road Junctions – 268 km Motorways – 418 km

I Class roads – 2975 km

II Class roads – 4027 km

• Territory of Bulgaria: 110 900 km²• Total length of national roads: 19 436 km• Density of national roads: 0.18 km/km²

4

Page 5: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU

• State budget;• Pre-accession programmes PHARE and ISPA;• Operational programmes Transport and Regional

development 2007-2013(EU financing); • State investment loans

Sources of financing:

5

Page 6: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU

Operational Programme Transport 2007 – 2013

• Total budget of 990 Million Euro for construction of 213 km motorways and 69 km I class roads, part of the TEN-T network.

• Road Infrastructure Agency is the only beneficiary on Priority Axis II “Development of road infrastructure along the major national and Pan-European transport axes”.

6

Page 7: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU

Projects in Operational Programme Transport

1. Trakia MW (from Sofia to Burgas) – 115 km – 350 Million Euro

2. Mariza MW (from BG to TR) – 67 km – 208 Million Euro

3. Struma MW (from BG to GR) – 132 km – 250 Million Euro

4. Kardshali – Podkova (from BG to GR) – 28 km – 32 Million Euro

5. Hemus MW (from Sofia to Varna) – 8.5 km – 32 Million Euro

6. Е-79, Vraza – Botevgrad (north of Sofia) – 31 km – 85 Million Euro

7. Е-79, Vidin – Montana (from RO to BG) – 20 km – 32 Million Euro

7

Σ 990 Million Euro

Page 8: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU

8

2

34

5

6

7

1

Projects on Operational Programme Transport

2007 - 2013

Page 9: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU

Sections of Trakiya MW in exploitation

Projected sections of Trakiya MW

9

“Trakia” MW, Lot 2

Stara Zagora – Nova

Zagora from km 210+100

to km 241+900

Length – 31.800 km

•The tender procedure for construction is completed. Signature of construction contract: 23 April 2010 Investment cost: 70.5 Million Euro.

•The tender procedure for supervision was announced on 22 February 2010. Signature of contract: expected in May 2010

•End of construction: Summer 2012

Page 10: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU

“Trakia” MW, Lot 3Nova Zagora – Yambol from km 241+900 to

km 276+200Length – 35.697 km

Sections of Trakiya MW in exploitation

Projected sections of Trakiya MW

10

• Start of the tender procedure for construction: 26 February 2010. Signature of contract: expected in July 2010.

• Start of the tender procedure for supervision: 23 April 2010. Signature of contract: expected in July 2010

• End of construction: Summer 2012• Tentative investment cost: 108 Million Euro

Page 11: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU

“Trakia”, Lot 4Yambol - Karnobat from

km 276+200 to km 325+280

Length – 49.080 km

Sections of Trakiya MW in exploitation

Projected sections of Trakiya MW

11

• Start of the tender procedure for construction: 07 April 2010. Signature of contract: expected in August 2010.

• Start of the tender procedure for supervision: expected 14 May 2010. • Signature of contract: expected in August 2010 • End of construction: Autumn 2012• Tentative investment cost: 146 Million Euro

Page 12: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU

12

“Maritza” MW,Orizovo – Harmanli(connection Trakia

MW – Turkish border)

from km 5+000 to km 71 + 011

Length – 66,011 km

•Tender procedures for construction and supervision: Preparation of tender documentation is forthcoming. Start of tender procedures - second half of 2010 expected.

•Possible division of the project implementation – in 2 lots.•Tentative investment cost: 209 Million Euro

Page 13: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU

Corridor No IV, Sofia to Greek border

Lot 1 Dolna Dikania – Dupnitza from km 305+220 to km 322+000

Lot 2 Dupnitza-Blagoevrad from km 322+000 to km 356+000

Lot 4 Sandanski-Kulata from km 423+500 to km 438+500

Lot 3 will be constructed in the next programming period 2014-2020

Total length of Lot 1, Lot 2 and Lot 4: 65.78 km. Indicative cost: 250 Million Euro.

Tender procedures for construction and supervision of Lot 1 and Lot 4: first half of 2011.

Lot 2 – Tender procedure for design: forthcoming

13

Struma Motorway

Page 14: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU

„Hemus” Motorway Section : „Sofia Ring Road –

“Yana” road junction” from km 0 to km 8+460.

14

• Start of the tender procedure for construction and supervision: expected in June 2011• Selection of Contractor and Consultant: expected in October 2011• Tentative investment cost: 32 Million Euro

Page 15: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU

Road I-5 Kardzhali – Podkova

Corridor No IX, road to the Greek borderThe project includes rehabilitation of 8 km of the existing road and 24 km new construction from Kardzhali to Podkova.

15

• Start of the tender procedure for construction and supervision: expected in December 2010

• Selection of Contractor and consultant: expected in April 2011

• Tentative investment cost: 32 Million Euro

Page 16: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU

Operational Programme Regional Development 2007 - 2013

OPRD Phase 1, 302 km14 Lots, ongoing tender procedures for construction and supervision.Expected beginning of the construction – July 2010.Budget – 110, 6 mil. Euro

OPRD Phase 2, 311 km15 Lots, tender documents are approved.Expected start of tender procedures –second half of 2010. Budget – 135,5 mil. Euro

OPRD Phase 3Indicative list of projects, ready to be included in the programme.

16

Page 17: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU

ІI. Road infrastructure projects for design 2010 – 2013 under Operational Programme

Transport

Construction 2014 – 2020

17

Page 18: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU

Operational Programme Transport

OPT – 2007-2013 PROGRAMME PERIOD

OPT – 2014-2020 PROGRAMME PERIOD

18

Page 19: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU

Struma Motorway Lot 3 /Blagoevgrad -

Sandanski/

Total length: 67.5 km

3 major sections:

• 3.1 - Blagoevgrad – Krupnik from km

356+000 to km 380+000

• 3.2 – Krupnik – Kresna (Kresna defile)

from km 380+000 to km 400+600

• 3.3 - Kresna – Sandanski from km

400+600 to km 423+500

Preparation of Application form for funding

the design of Lot 3 by Technical

Assistance of Operational Programme

"Transport“ is ongoing.

Start of tender procedures for design –

Autumn 2010.19

Page 20: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU

Trakia MW Lot 6 (Black Sea Motorway)

The project is part of the Pan-European Transport Corridor No. VIII and connects the two biggest ports of the Republic of Bulgaria – Varna and Burgas

Length:100 kmIndicative cost: 350 Million Euro

20

Page 21: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU

Length: 50 kmIndicative cost: 150 Million

Euro

“Sofia – Kalotina (border to Serbia)” MW

21

Page 22: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU

Length: 85 km Indicative cost: 260 Million Euro

“Sofia – Gyueshevo (border to Macedonia)” MW

22

Page 23: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU

“Shipka” Tunnel

The total length is approx.: 3.2 km

23

Page 24: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU

Thank you for the attention!