Road infrastructure in Bulgaria
1
Slovene – Bulgarian Business Forum, 12th May 2010
Vasilka KostadinovaDirector of Directorate “Implementation of EU funded Projects”Road Infrastructure Agency
REPUBLIC OF BULGARIA MINISTRY OF REGIONAL DEVELOPMENT AND PUBLIC WORKS
![Page 2: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU](https://reader033.vdocuments.us/reader033/viewer/2022051820/56649f1c5503460f94c31d5a/html5/thumbnails/2.jpg)
European transport corridors
2
![Page 3: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU](https://reader033.vdocuments.us/reader033/viewer/2022051820/56649f1c5503460f94c31d5a/html5/thumbnails/3.jpg)
3
European transport corridors in Bulgaria
![Page 4: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU](https://reader033.vdocuments.us/reader033/viewer/2022051820/56649f1c5503460f94c31d5a/html5/thumbnails/4.jpg)
Road Junctions – 268 km Motorways – 418 km
I Class roads – 2975 km
II Class roads – 4027 km
• Territory of Bulgaria: 110 900 km²• Total length of national roads: 19 436 km• Density of national roads: 0.18 km/km²
4
![Page 5: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU](https://reader033.vdocuments.us/reader033/viewer/2022051820/56649f1c5503460f94c31d5a/html5/thumbnails/5.jpg)
• State budget;• Pre-accession programmes PHARE and ISPA;• Operational programmes Transport and Regional
development 2007-2013(EU financing); • State investment loans
Sources of financing:
5
![Page 6: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU](https://reader033.vdocuments.us/reader033/viewer/2022051820/56649f1c5503460f94c31d5a/html5/thumbnails/6.jpg)
Operational Programme Transport 2007 – 2013
• Total budget of 990 Million Euro for construction of 213 km motorways and 69 km I class roads, part of the TEN-T network.
• Road Infrastructure Agency is the only beneficiary on Priority Axis II “Development of road infrastructure along the major national and Pan-European transport axes”.
6
![Page 7: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU](https://reader033.vdocuments.us/reader033/viewer/2022051820/56649f1c5503460f94c31d5a/html5/thumbnails/7.jpg)
Projects in Operational Programme Transport
1. Trakia MW (from Sofia to Burgas) – 115 km – 350 Million Euro
2. Mariza MW (from BG to TR) – 67 km – 208 Million Euro
3. Struma MW (from BG to GR) – 132 km – 250 Million Euro
4. Kardshali – Podkova (from BG to GR) – 28 km – 32 Million Euro
5. Hemus MW (from Sofia to Varna) – 8.5 km – 32 Million Euro
6. Е-79, Vraza – Botevgrad (north of Sofia) – 31 km – 85 Million Euro
7. Е-79, Vidin – Montana (from RO to BG) – 20 km – 32 Million Euro
7
Σ 990 Million Euro
![Page 8: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU](https://reader033.vdocuments.us/reader033/viewer/2022051820/56649f1c5503460f94c31d5a/html5/thumbnails/8.jpg)
8
2
34
5
6
7
1
Projects on Operational Programme Transport
2007 - 2013
![Page 9: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU](https://reader033.vdocuments.us/reader033/viewer/2022051820/56649f1c5503460f94c31d5a/html5/thumbnails/9.jpg)
Sections of Trakiya MW in exploitation
Projected sections of Trakiya MW
9
“Trakia” MW, Lot 2
Stara Zagora – Nova
Zagora from km 210+100
to km 241+900
Length – 31.800 km
•The tender procedure for construction is completed. Signature of construction contract: 23 April 2010 Investment cost: 70.5 Million Euro.
•The tender procedure for supervision was announced on 22 February 2010. Signature of contract: expected in May 2010
•End of construction: Summer 2012
![Page 10: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU](https://reader033.vdocuments.us/reader033/viewer/2022051820/56649f1c5503460f94c31d5a/html5/thumbnails/10.jpg)
“Trakia” MW, Lot 3Nova Zagora – Yambol from km 241+900 to
km 276+200Length – 35.697 km
Sections of Trakiya MW in exploitation
Projected sections of Trakiya MW
10
• Start of the tender procedure for construction: 26 February 2010. Signature of contract: expected in July 2010.
• Start of the tender procedure for supervision: 23 April 2010. Signature of contract: expected in July 2010
• End of construction: Summer 2012• Tentative investment cost: 108 Million Euro
![Page 11: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU](https://reader033.vdocuments.us/reader033/viewer/2022051820/56649f1c5503460f94c31d5a/html5/thumbnails/11.jpg)
“Trakia”, Lot 4Yambol - Karnobat from
km 276+200 to km 325+280
Length – 49.080 km
Sections of Trakiya MW in exploitation
Projected sections of Trakiya MW
11
• Start of the tender procedure for construction: 07 April 2010. Signature of contract: expected in August 2010.
• Start of the tender procedure for supervision: expected 14 May 2010. • Signature of contract: expected in August 2010 • End of construction: Autumn 2012• Tentative investment cost: 146 Million Euro
![Page 12: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU](https://reader033.vdocuments.us/reader033/viewer/2022051820/56649f1c5503460f94c31d5a/html5/thumbnails/12.jpg)
12
“Maritza” MW,Orizovo – Harmanli(connection Trakia
MW – Turkish border)
from km 5+000 to km 71 + 011
Length – 66,011 km
•Tender procedures for construction and supervision: Preparation of tender documentation is forthcoming. Start of tender procedures - second half of 2010 expected.
•Possible division of the project implementation – in 2 lots.•Tentative investment cost: 209 Million Euro
![Page 13: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU](https://reader033.vdocuments.us/reader033/viewer/2022051820/56649f1c5503460f94c31d5a/html5/thumbnails/13.jpg)
Corridor No IV, Sofia to Greek border
Lot 1 Dolna Dikania – Dupnitza from km 305+220 to km 322+000
Lot 2 Dupnitza-Blagoevrad from km 322+000 to km 356+000
Lot 4 Sandanski-Kulata from km 423+500 to km 438+500
Lot 3 will be constructed in the next programming period 2014-2020
Total length of Lot 1, Lot 2 and Lot 4: 65.78 km. Indicative cost: 250 Million Euro.
Tender procedures for construction and supervision of Lot 1 and Lot 4: first half of 2011.
Lot 2 – Tender procedure for design: forthcoming
13
Struma Motorway
![Page 14: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU](https://reader033.vdocuments.us/reader033/viewer/2022051820/56649f1c5503460f94c31d5a/html5/thumbnails/14.jpg)
„Hemus” Motorway Section : „Sofia Ring Road –
“Yana” road junction” from km 0 to km 8+460.
14
• Start of the tender procedure for construction and supervision: expected in June 2011• Selection of Contractor and Consultant: expected in October 2011• Tentative investment cost: 32 Million Euro
![Page 15: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU](https://reader033.vdocuments.us/reader033/viewer/2022051820/56649f1c5503460f94c31d5a/html5/thumbnails/15.jpg)
Road I-5 Kardzhali – Podkova
Corridor No IX, road to the Greek borderThe project includes rehabilitation of 8 km of the existing road and 24 km new construction from Kardzhali to Podkova.
15
• Start of the tender procedure for construction and supervision: expected in December 2010
• Selection of Contractor and consultant: expected in April 2011
• Tentative investment cost: 32 Million Euro
![Page 16: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU](https://reader033.vdocuments.us/reader033/viewer/2022051820/56649f1c5503460f94c31d5a/html5/thumbnails/16.jpg)
Operational Programme Regional Development 2007 - 2013
OPRD Phase 1, 302 km14 Lots, ongoing tender procedures for construction and supervision.Expected beginning of the construction – July 2010.Budget – 110, 6 mil. Euro
OPRD Phase 2, 311 km15 Lots, tender documents are approved.Expected start of tender procedures –second half of 2010. Budget – 135,5 mil. Euro
OPRD Phase 3Indicative list of projects, ready to be included in the programme.
16
![Page 17: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU](https://reader033.vdocuments.us/reader033/viewer/2022051820/56649f1c5503460f94c31d5a/html5/thumbnails/17.jpg)
ІI. Road infrastructure projects for design 2010 – 2013 under Operational Programme
Transport
Construction 2014 – 2020
17
![Page 18: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU](https://reader033.vdocuments.us/reader033/viewer/2022051820/56649f1c5503460f94c31d5a/html5/thumbnails/18.jpg)
Operational Programme Transport
OPT – 2007-2013 PROGRAMME PERIOD
OPT – 2014-2020 PROGRAMME PERIOD
18
![Page 19: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU](https://reader033.vdocuments.us/reader033/viewer/2022051820/56649f1c5503460f94c31d5a/html5/thumbnails/19.jpg)
Struma Motorway Lot 3 /Blagoevgrad -
Sandanski/
Total length: 67.5 km
3 major sections:
• 3.1 - Blagoevgrad – Krupnik from km
356+000 to km 380+000
• 3.2 – Krupnik – Kresna (Kresna defile)
from km 380+000 to km 400+600
• 3.3 - Kresna – Sandanski from km
400+600 to km 423+500
Preparation of Application form for funding
the design of Lot 3 by Technical
Assistance of Operational Programme
"Transport“ is ongoing.
Start of tender procedures for design –
Autumn 2010.19
![Page 20: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU](https://reader033.vdocuments.us/reader033/viewer/2022051820/56649f1c5503460f94c31d5a/html5/thumbnails/20.jpg)
Trakia MW Lot 6 (Black Sea Motorway)
The project is part of the Pan-European Transport Corridor No. VIII and connects the two biggest ports of the Republic of Bulgaria – Varna and Burgas
Length:100 kmIndicative cost: 350 Million Euro
20
![Page 21: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU](https://reader033.vdocuments.us/reader033/viewer/2022051820/56649f1c5503460f94c31d5a/html5/thumbnails/21.jpg)
Length: 50 kmIndicative cost: 150 Million
Euro
“Sofia – Kalotina (border to Serbia)” MW
21
![Page 22: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU](https://reader033.vdocuments.us/reader033/viewer/2022051820/56649f1c5503460f94c31d5a/html5/thumbnails/22.jpg)
Length: 85 km Indicative cost: 260 Million Euro
“Sofia – Gyueshevo (border to Macedonia)” MW
22
![Page 23: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU](https://reader033.vdocuments.us/reader033/viewer/2022051820/56649f1c5503460f94c31d5a/html5/thumbnails/23.jpg)
“Shipka” Tunnel
The total length is approx.: 3.2 km
23
![Page 24: Road infrastructure in Bulgaria 1 Slovene – Bulgarian Business Forum, 12 th May 2010 Vasilka Kostadinova Director of Directorate “Implementation of EU](https://reader033.vdocuments.us/reader033/viewer/2022051820/56649f1c5503460f94c31d5a/html5/thumbnails/24.jpg)
Thank you for the attention!
24