risk management · bassam mahmoud ibrahim al-tahtamouni, parsons brinckerhoff created date:...

16
Better Practice Operational Tools and Techniques for Effective Construction Procurement Risk Management Ahmad Ali Al Ansari 20 January 2020

Upload: others

Post on 24-May-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Risk Management · Bassam Mahmoud Ibrahim Al-Tahtamouni, Parsons Brinckerhoff Created Date: 1/20/2020 6:26:11 PM

Better Practice Operational Tools and Techniques for Effective Construction Procurement

Risk Management

Ahmad Ali Al Ansari 20 January 2020

Page 2: Risk Management · Bassam Mahmoud Ibrahim Al-Tahtamouni, Parsons Brinckerhoff Created Date: 1/20/2020 6:26:11 PM

The Big Question

Are we getting Value for Money out of our

Construction Projects?

Page 3: Risk Management · Bassam Mahmoud Ibrahim Al-Tahtamouni, Parsons Brinckerhoff Created Date: 1/20/2020 6:26:11 PM

The Problem

• Cost Overrun

• Time Overrun

• Quality Degradation

Page 4: Risk Management · Bassam Mahmoud Ibrahim Al-Tahtamouni, Parsons Brinckerhoff Created Date: 1/20/2020 6:26:11 PM

Procurement

Procurement involves the following 4 parts:

• Organisation Method:

structure, level of authority & delegation, decision making process, etc.

• Payment System:

lump sum, measured, cost reimbursement, etc.

• Tender Procedure:

documentation, open or selective, single or two envelops, cost

estimation, etc.

• Conditions of Contract

Page 5: Risk Management · Bassam Mahmoud Ibrahim Al-Tahtamouni, Parsons Brinckerhoff Created Date: 1/20/2020 6:26:11 PM

PWA Common Procurement Methods

•Design – Bid – Build (DBB)

•Design & Build (DB)

Page 6: Risk Management · Bassam Mahmoud Ibrahim Al-Tahtamouni, Parsons Brinckerhoff Created Date: 1/20/2020 6:26:11 PM

Risk Management

Statement:

The selection of procurement method decides the level

of risk in construction projects

Page 7: Risk Management · Bassam Mahmoud Ibrahim Al-Tahtamouni, Parsons Brinckerhoff Created Date: 1/20/2020 6:26:11 PM

Areas of Risk – Internal Factors

Resources & Project Organisation

Data & Information

Process & Operation

Finance & Estimation

Procurement & Contractual Aspects

Contract Administration

Page 8: Risk Management · Bassam Mahmoud Ibrahim Al-Tahtamouni, Parsons Brinckerhoff Created Date: 1/20/2020 6:26:11 PM

Areas of Risk – External Factors

1. External Stakeholders

2. Environmental

3. Market Conditions, Resources &

Logistics

4. Budget & Financial

Approvals5. Legal

6. Political

7. Etc.

Page 9: Risk Management · Bassam Mahmoud Ibrahim Al-Tahtamouni, Parsons Brinckerhoff Created Date: 1/20/2020 6:26:11 PM

Question?

What is the level of

Consideration given to managing & mitigating

risks generated from

those areas in building up

our Construction Procurement Strategies and

selection of most appropriate methods?

Page 10: Risk Management · Bassam Mahmoud Ibrahim Al-Tahtamouni, Parsons Brinckerhoff Created Date: 1/20/2020 6:26:11 PM

Risk Management & Procurement Process

There are two main linkages between risk management and the procurement process:

Cost Management

Contract Strategy

Page 11: Risk Management · Bassam Mahmoud Ibrahim Al-Tahtamouni, Parsons Brinckerhoff Created Date: 1/20/2020 6:26:11 PM

Cost Management

“Effective risk management provides a better and

more realistic approach to defining risk allowance,

in terms of calculating contingencies and

tolerances*. If risk can be quantified in financial

terms, then it is possible to provide a more

effective approach to cost management.”

* Thomson and Perry (1992)

Page 12: Risk Management · Bassam Mahmoud Ibrahim Al-Tahtamouni, Parsons Brinckerhoff Created Date: 1/20/2020 6:26:11 PM

Contingency Management

The risk impact can be minimized through providing

a contingency allowance to mitigate the effects.

• The common practice is very subjective in contingency

allocation.

• A global percentage value is applied – a subjective

estimate.

• Need: accurate appraisal of contingency sums helps in

greater cost certainty.

Page 13: Risk Management · Bassam Mahmoud Ibrahim Al-Tahtamouni, Parsons Brinckerhoff Created Date: 1/20/2020 6:26:11 PM

Example

Inter-relationship between Cost, Risk and Design Management

Page 14: Risk Management · Bassam Mahmoud Ibrahim Al-Tahtamouni, Parsons Brinckerhoff Created Date: 1/20/2020 6:26:11 PM

Management & Practice (Teamwork)

Management action

Verify risks through clarifying the nature of risk, identify other concerns and mitigate the effects – Risk Register.

Analyze the significance of risk impact.

Prioritize risks in terms of probability of occurrence and magnitude of impact –

Identify project specific risks through workshops & brainstorming sessions.

Page 15: Risk Management · Bassam Mahmoud Ibrahim Al-Tahtamouni, Parsons Brinckerhoff Created Date: 1/20/2020 6:26:11 PM

Procurement & Contract Strategies

Risk management helps in establishing ……

• Project Priorities

• Number & Type of Work Packages

• Roles & Division of Responsibilities

• Terms of Payment

• Basis for Contractor selection

• Degree of Client Control & Involvement

• Most Appropriate Allocation of Risk

Page 16: Risk Management · Bassam Mahmoud Ibrahim Al-Tahtamouni, Parsons Brinckerhoff Created Date: 1/20/2020 6:26:11 PM

Thank [email protected]

Tel: 44951135