Page 1: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported

1

Risk Prep

Darryl Townsend, PMP

January 20, 2016

Page 2: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported

2

Safe Harbor

• The statements made in this technical presentation are

based on our current knowledge of the tools.

• Our statements should not be construed to be an official

“Vendor perspective”, but are intended to be the sharing of

technical and user knowledge gained as we explore new

paths and technologies, usually in advance of our clients.

• You need to make your own judgments as to the application

of our shared ideas in your own, unique environment.

Page 3: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported

3 3

• Authorized Oracle Primavera, Asta Powerproject and PMWeb Software Sales

• Experienced Industry Implementation Specialists & Consultants

• P6, Contract Management, Unifier, Asta Powerproject, and PMWeb

• Custom Integration, Analytics, Dashboards, Risk and Role-based User Access

• Program and Project System Support Services and Partnering

• Mentored and Supported Project Staffing Resources

• Cloud Based, Global Managed Hosting Services

• P6 and Asta Cloud Team Deployments Reduce the Risk of Critical Data Loss

• Project Status, Java-free Risk and Collaboration Using P6 Web Services

• Contract Management Interface (CMI) – Extend Your PCM Deployment

Products and Services

Page 4: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported

4

Tool Matrix

Business Process

Portfolio Management P6, Unifier Portfolios

Planning & Budgeting Unifier Powerproject Planning

Estimating BidCon Estimating

CPM Scheduling P6 Powerproject Scheduling

Cost Management & Reporting P6, Unifier Powerproject Cost Management

Document Management Unifier Doc. Management

Change Management Unifier Workflows

BIM/Engineering Forms Unifier Asta BIM Engineering Forms

Risk Analysis Risk Analysis Asta Risk Risk Register

Facility Management/Work Orders Unifier Facility

Management

Claims Support & Analysis P6 Powerproject Scheduling

Doc. Management

Page 5: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported

5

Agenda

• Risk Definitions, Reasons, Methodology

• Workshop Preparation - Process

– Schedule Review

– Metric runs

• Telling metrics for schedule health

• Corrections/improvements to schedule

– My typical Metric list

Risk Analysis Preparation

Page 6: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported

6

Risk Assessments

• Risk: An uncertain event or condition that, if it occurs, has a positive

(opportunity) or negative (threat) effect on a project’s objectives.

Understanding these risks helps to better evaluate and reduce risk exposure,

increase confidence, identify areas of potential acceleration of schedule and

help establish reasonable contingency

• Threat – situation or condition that is unfavorable to project

– Negative circumstance

– Risk with negative impact

• Opportunity – situation or condition that is favorable to project

– Positive circumstance

– Risk with positive impact

Risk Analysis Definitions

Page 7: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported

7

Risk Assessments

• Uncertainty – lack of knowledge about an event

that reduces

confidence in conclusions drawn from the data.

– Cost

– Time

– Work effort

– Quality requirements

Risk Analysis Definitions (Con’t.)

Page 8: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported

8

Risk Assessments

Why

• Identify/Quantify potential events causing delay/cost increase to Project

– Incomplete design

– Inadequate site investigation

– Unrealistic schedule/budget

– Permit requirements

– Weather

– Supplier’s/contractor’s ability to deliver

– Public relations

– Unforeseen conditions…

• Optimize Project Performance, identify Critical activities, create Transparency, predictability, minimize surprises-early warning

Risk Analysis Workshop – Why/When do it…

Page 9: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported

9

Risk Assessments

When• Before entering into a Funding gate

• Before/during Engineering Phase

• Before starting Construction – evaluating competing bids for equipment for example

• As often as it feels necessary to capture/evaluate/mitigate/eliminate risk affecting ultimate project goal – Completing project– Some groups review Portfolio quarterly

– Some review yearly (ex. LRP cycle)

– Partner review initiated

Many times it is seen as a one time event but in these large scale projects spanning several years, risk assessments should be done frequently, if nothing else, to update the risk register and adjust for risk past and for new risks surfacing.

Risk Analysis Workshop – Why/When do it…

Page 10: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported

10

Risk Assessments

• Review of CPM schedule for duration and logic integrity

(Schedule Quality)

– Use of Acumen Fuse for identifying issues

– Schedule quality key to driving valuable Risk outcomes

– Gameplan on addressing issues

• Modify existing file

• Start over with Risk file?

Without a good schedule, expecting a good risk assessment and

outcome are wishful thinking

Risk Analysis Preparation - Process

Page 11: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported

11

Risk Assessment Preparation

• Develop checklist of key areas of focus for quality

• Review key metrics for validating schedule (will expand over next few slides)

– Lag (negative/positive)

– Open ends

– Out of sequence updates (broken logic)

– Critical ratio

– Constraints

– Calendar count

– Float

• Schedule Cleanse (Acumen Fuse tool) options/do’s-don’ts

Schedule Review

Page 12: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported

12

Risk Assessment Prep

• Minimal lags/leads (+/-)

– Best if there are none

– Lags are fixed duration

– When applying duration uncertainty (min/ml/max), tool cannot apply

uncertainty to lags

– If no way around a lag, best to convert a lag duration to activity

– Lags on critical path or between activities with different calendars

exaggerate problem

Risk Model Metrics

Page 13: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported

13

Risk Assessment Prep

• Relationships

– Ideal to have only finish to start relationships

– Open ends - Best if there are none

– Open ended activities could be critical or near critical and impacting

project completion but not impactful when left open

– Ideally, one start and one finish. If not, possible to have multiple ends.

Special care to model each ending separately. Shorter paths will not

show as critical

– Start-to-finish links (reverse logic)

– External links (to other projects not in model)

Risk Model Metrics

Page 14: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported

14

Risk Assessment Prep

• Tasks

– Self-explanatory descriptions and not reliant on summary level descriptions (WBS or Coding)

– Summary Level titles should be avoided

– Calendars – with some risk tools, having many calendars can be problematic

– Some circles prefer smaller numbers of tasks to model (many believe the risks become diluted if applied to many activities) – Easier to manage model with fewer activities

– Seen several groups create separate files for risking (management/owner schedule)

– Links to/from summary tasks

Risk Model Metrics

Page 15: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported

15

Risk Assessment Prep

• Critical

– Watch for Critical ratio (critical to non-critical count)

• Too many critical could be indicator of redundant logic

• Too few could indicate high # of open ends

– Don’t ignore the non-critical, could be near and be a swing factor

– Does the critical list make sense

• Project where the rain gutters were on critical path for a compressor

shelter – probably not critical to start-up

• Close-out documents

Risk Model Metrics

Page 16: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported

16

Risk Assessment Prep

• Constraints

– Hard constraints defeat logic purpose and may drive more critical than

realistic

– Comment in Notes tab those critical dates

• Option – add a duplicate activity not in logic string to compare changes of

removing constraint

– Change constraint to Soft for Risk purposes

Risk Model Metrics

Page 17: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported

17

Risk Assessment Prep

• Calendar count

– In PRA, mixing of multiple calendars can affect duration calculations

– If multiple schedulers have worked file, opportunity to have several

equal calendars (slightly different names), especially if imported file

from another database

– Multiple calendars could be something simple as having different

holidays or no holidays identified

Risk Model Metrics

Page 18: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported

18

Risk Assessment Prep

• Float

– Watch for excessive float, large number-sometimes lack of logic

– Large float activities typically pose low risk exposure to project

– Low float activities could become critical with little warning

– Real float paths are good candidates for adding concurrent work for

acceleration

Risk Model Metrics

Page 19: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported

19

Risk Assessment Tool

• Schedule Cleanse (Acumen) – eliminate the below characteristics (any or all-user choice)– Redundant Logic

– Hard constraints

– Soft Constraints

– Remaining Leads/Lags

– Links on summaries

• Best to do in phases and not all at once– Step changes

– Save scenarios so you can go back if not satisfied with results

• Identifies each and lets you modify all or individually, user choice

Risk Model Metrics - tool

Page 20: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported

20

Risk Assessment Prep ToolRisk Model Cleanse - Acumen

Ava

ila

ble

ca

teg

ori

es

to m

od

ify

List of hard constraints

Page 21: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported

21

Risk Assessment Prep ToolRisk Model Diagnostics – Acumen Fuse – My typical metrics

Timeline Metrics

Page 22: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported

22

Risk Assessment Prep Tool

• Normal – count of activities (duration greater than 0)

• Milestones – count of milestones (looking at ratio normal/milestones)

• Average float – average float across entire schedule model

• Critical <=20 – float value less than or equal 20, helps to gather info on the near critical activities

• Missing Pred/Succ – Open ended activities

• FS Predecessors – should be majority of schedule

• SF Predecessors – should be none, issues when risking (successor happens before predecessor)

• Negative/Positive Lag – hidden detail (lack of tasks)

Risk Model Diagnostics – Acumen Fuse – My typical metrics

Page 23: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported

23

Risk Assessment Prep Tool

• Hard/soft constraints – Must start/finish, force critical logic

• Resources – simple check to see if any activities (normal

and/or summary) have resources applied

• Invalid dates – planned work in the past or actual work in

future. Easier in MSProject but could indicate lack of F9

progressing

• Critical <=0 – float value less than or equal 0, this helps some

schedules where critical has been redefined by user

• Missing WBS – activities not built using WBS, hopefully codes

are being used to organize. Helps to understand when I can’t

use WBS to organize

Risk Model Diagnostics – Acumen Fuse – My typical metrics

Page 24: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported

24

Risk Assessment Prep Tool

• Calendar count – understand how many calendars may be

included in schedule

• >30d float – activities seemingly off the critical path, they

missing logic?

• >30d lag – long duration lag, not good practice, especially for

a risk model, suggest changing to an activity

• Excessive lag – identifying lag that is equal to or greater than

the duration of the predecessor activity (hidden activity)

Risk Model Diagnostics – Acumen Fuse – My typical metrics

Page 25: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported

25

Risk Assessment Prep Tool

• Tools for running reports on the discussed issues

– Acumen Fuse

• Diagnostics tab

– Primavera P6

• Claim Digger (P6 Professional)

• Check Schedule (P6 EPPM)

• F9 Report

– Schedule Analyzer Enterprise

• Baseline Checker

Risk Model efforts

Page 26: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported

26

Risk Assessment Preparation

Risk Assessment Preparation Conclusion

Whatever changes are made to the model prior to rolling the dice, will help drive the results/outcome. Many times, these Risk results are major contributors in decision-making for proceeding through the project gate or for management providing additional funding for continuing. These changes need to be well thought out and documented. Management does not make decisions based on “gut-feel” and wants as much quantifiable information to aid in the right business decision, even if that answer says call time-out to reevaluate or STOP.

Ultimately, the best time to know these guidelines is before the schedule is ever built thereby eliminating most of this effort. Cleaning up a schedule worthy of using for Risking purposes can require a lot of effort that would seem easier to just have done right the first time. Many of these expectations shared are best practice which takes us down another path of discussing the very basics of this discipline which is another discussion for another day.

Page 27: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported

27

Questions & Comments

• All questions are gathered into a master sheet, answered

and distributed to all registrants as well as posted on our

website.

• Answers are based on our own experiences using the

various software products covered in this webinar.

Thank you for participating

Contact - [email protected]

Page 28: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported

28

Upcoming EventsWe highly recommend the following technical education and relationship events

aace-northeast-total-cost-management-symposium/http://www.westernwinterworkshop.com/http://www.constructioncpm.com/

Valley Forge, PA

Page 29: Risk Assessment Prep - Jan 2016 Webinardrmcnatty.com/.../Risk-Assessment-Prep-Jan-2016-Webinar.pdf• Program and Project System Support Services and Partnering • Mentored and Supported