risf pro

Upload: shyamanup

Post on 04-Jun-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/13/2019 Risf pro

    1/2

    PC vs. Traditional ApproachEPC has emerged as the deliverymethod of choice for executingsystem projects in all market

    sectors. The acronym EPC is shortfor Engineer-Procure-Construct,which implies that a single entity hascomplete responsibility for a project

    from start to finish. Oddly, the keyfunction that assumes this overallresponsibility, namely project

    management, is not in the name.

    Traditional Project ApproachHistorically, utility, industrial

    and large commercial entities, includ-ing governmental and institutionalfacilities, employed sufficientresources to perform projectmanagement, engineering designand procurement, and in some cases,construction. However, right sizingto meet competitive and economicconstraints has greatly trimmed thein-house capabilities of many

    firms, sometimes down to asingle individual.

    To compensate, project work wasprimarily outsourced to consultantsand contractors. Consultants devel-oped the design and bid packages,while the successful contractor was

    responsible for equipment andmaterial procurement, installationand start-up. The figure below depictsthe relationships in this traditional

    project approach.

    The customer has at least twomajor contracts to administer andmultiple lines of communication tooversee. Generally, the customer isassuming the business risk associatedwith the project and when problemsarise, they often result from mis-communications between the majorparties. Consequently, fingerpointing ensues.

    When viewed from a time-lineperspective, the traditional projectapproach has two distinct drawbacks.First, the two major functions,engineering and construction, areperformed at different times. Second,the total project schedule is longerbecause of multiple bidding phases.

    Consider the following observations:

    Not all major parties are known at

    the beginning of the project.The total cost is not always known

    at the start of a project. Manywork from a best estimate.

    The overall schedule has not been

    defined at the start of the project.The two major third parties, the

    consultant and the contractor,are not in sync, i.e. by the timethe contractor is on board, theconsultant has already completed

    as much as 95% of the engineeringdesign. This means most of theconsultants resources have beenredeployed with few left to satisfythe remainder of the contract,particularly when it comes toresolving problems encounteredby the contractor, unless a seriesof change orders are issuedalong with a correspondingschedule commitment.

    The return on investment

    is delayed due to the prolongedproject schedule.

    Fast-tracking is sometimes used

    to accelerate the project schedule, butthis usually increases the overall costand risk.

    Engineer-Procure-Construct(EPC) Approach

    In the EPC approach, the EPCfirm assumes overall responsibilityfor the project, thereby relieving the

    EPC-Lower Risk, Shorten

    Construction Cycle and

    Reduce Costs

    Risk Management

    by Rich Marking-Camuto, Systems Integration and Packaging

    ustomer

    Consultant Contractor

    EquipmentSupplier Subcontractor(s)

  • 8/13/2019 Risf pro

    2/2

    Bu l l e t in N u mb e r 03031 2003 Co o p e r I n d u s t r i e s , I n c . M I 7 /03

    customer of this burden and risk.The customer deals with a single-pointcontact the EPC project manager thus simplifying the lines of

    communication as illustrated inthe diagram below.

    With an EPC approach, the partiesinvolved, the project budget and theproject schedule are known BEFOREthe project begins. Communication

    between engineering design,procurement, and construction beginsimmediately, which makes accelerat-ing the project schedule possiblewithout imposing greater risk.Customers skeptical of using an EPCapproach for projects are generallyconcerned with the perception thatEPC projects

    command a premium price. This is nottrue. EPC can be more cost-effectivewhen the value of the risk assumed bythe EPC firm is considered, along withthe early revenue generating benefit ofthe accelerated project schedule.

    The following diagram comparesthe project schedule of a traditionalproject versus an EPC project. Notethe durations of each major task are

    the same, yet the project can bedelivered more efficiently. This clearlyshows the projects expected returnon investment (ROI) will be realizedsooner, which may make thedifference between doing theproject or not.

    No Risk EPCGuarantee

    Cooper Power Systems offersan exclusive guarantee that if

    we perform an EPC project, the

    solution will perform as expected.Projects include distribution and

    pad-mounted substations,capacitor banks and harmonic

    filters, regulator stations, relaycontrol houses and retrofits,

    distribution automation systemsand advanced protection systems.

    CUSTOMER

    BENEFITS Only One Contract To

    Administer

    Less Technical AndFinancial Risk

    Accelerated Project Schedule

    Investment ReturnRealized Sooner

    An Innovative Cooper Solution

    CPS Performance Guarantee

    For more information, see our

    ad on the back cover of this issue,

    visit our Web site atwww.cooperpower.com/guaranteed, or, contact

    Rich Marking-Camuto, P.E. at

    1-414-768-8304 [email protected] LINE

    Customer's ProjectManager

    CPS as EPCProject Manager

    CPS PM Support

    CPS SystemsEngineering ContractedPartnersCPSProcurement CPS Techervices

    Estimating Sc e u e & Document ControContact Administration & LegalAccounting & Finance

    Conceptual DesignSystem Modeling,

    Simulations & StudiesSystem IntegrationEquipment SpecsDesign Validation/QC

    - Equipment ProcurementMultiple Factory Order

    CoordinationExpeditingTransportation

    Coordination

    CommissioningTechnical DirectionTrainingSite ManagementWarranty Administration

    Civi Structua Des i nSurveying & Soil

    TestingConstruction Labor &

    SupervisionConstruction Equipment,

    Tools & MaterialsPermitting & Bonding

    Task Descripti on Duration-2Y -1Y

    Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1-14M -13M -12M -11M -10M -9M -8M -7M -6M -5M -4M -3M -2M -1M 0M 1M

    Traditional Project(non-fast track) 2400h

    Develop RFP for Engineering Services 2w

    Bid Engineering 3w

    Review Engineering Bids 1w

    Engineering Phase 20w

    Bid Construction 3w

    Review Construction Bids 2w

    Order Equipment 1w

    Recieve Equipment 2w

    Construction Phase 22w

    Commission 2w

    Negotiate Contract 4w

    Engineering Phase 20w

    Order Equipment 1w

    Recieve Equipment 2w

    Construction Phase 22w

    Commission

    Engineer-Procure-Construct 1600h