risf pro
TRANSCRIPT
-
8/13/2019 Risf pro
1/2
PC vs. Traditional ApproachEPC has emerged as the deliverymethod of choice for executingsystem projects in all market
sectors. The acronym EPC is shortfor Engineer-Procure-Construct,which implies that a single entity hascomplete responsibility for a project
from start to finish. Oddly, the keyfunction that assumes this overallresponsibility, namely project
management, is not in the name.
Traditional Project ApproachHistorically, utility, industrial
and large commercial entities, includ-ing governmental and institutionalfacilities, employed sufficientresources to perform projectmanagement, engineering designand procurement, and in some cases,construction. However, right sizingto meet competitive and economicconstraints has greatly trimmed thein-house capabilities of many
firms, sometimes down to asingle individual.
To compensate, project work wasprimarily outsourced to consultantsand contractors. Consultants devel-oped the design and bid packages,while the successful contractor was
responsible for equipment andmaterial procurement, installationand start-up. The figure below depictsthe relationships in this traditional
project approach.
The customer has at least twomajor contracts to administer andmultiple lines of communication tooversee. Generally, the customer isassuming the business risk associatedwith the project and when problemsarise, they often result from mis-communications between the majorparties. Consequently, fingerpointing ensues.
When viewed from a time-lineperspective, the traditional projectapproach has two distinct drawbacks.First, the two major functions,engineering and construction, areperformed at different times. Second,the total project schedule is longerbecause of multiple bidding phases.
Consider the following observations:
Not all major parties are known at
the beginning of the project.The total cost is not always known
at the start of a project. Manywork from a best estimate.
The overall schedule has not been
defined at the start of the project.The two major third parties, the
consultant and the contractor,are not in sync, i.e. by the timethe contractor is on board, theconsultant has already completed
as much as 95% of the engineeringdesign. This means most of theconsultants resources have beenredeployed with few left to satisfythe remainder of the contract,particularly when it comes toresolving problems encounteredby the contractor, unless a seriesof change orders are issuedalong with a correspondingschedule commitment.
The return on investment
is delayed due to the prolongedproject schedule.
Fast-tracking is sometimes used
to accelerate the project schedule, butthis usually increases the overall costand risk.
Engineer-Procure-Construct(EPC) Approach
In the EPC approach, the EPCfirm assumes overall responsibilityfor the project, thereby relieving the
EPC-Lower Risk, Shorten
Construction Cycle and
Reduce Costs
Risk Management
by Rich Marking-Camuto, Systems Integration and Packaging
ustomer
Consultant Contractor
EquipmentSupplier Subcontractor(s)
-
8/13/2019 Risf pro
2/2
Bu l l e t in N u mb e r 03031 2003 Co o p e r I n d u s t r i e s , I n c . M I 7 /03
customer of this burden and risk.The customer deals with a single-pointcontact the EPC project manager thus simplifying the lines of
communication as illustrated inthe diagram below.
With an EPC approach, the partiesinvolved, the project budget and theproject schedule are known BEFOREthe project begins. Communication
between engineering design,procurement, and construction beginsimmediately, which makes accelerat-ing the project schedule possiblewithout imposing greater risk.Customers skeptical of using an EPCapproach for projects are generallyconcerned with the perception thatEPC projects
command a premium price. This is nottrue. EPC can be more cost-effectivewhen the value of the risk assumed bythe EPC firm is considered, along withthe early revenue generating benefit ofthe accelerated project schedule.
The following diagram comparesthe project schedule of a traditionalproject versus an EPC project. Notethe durations of each major task are
the same, yet the project can bedelivered more efficiently. This clearlyshows the projects expected returnon investment (ROI) will be realizedsooner, which may make thedifference between doing theproject or not.
No Risk EPCGuarantee
Cooper Power Systems offersan exclusive guarantee that if
we perform an EPC project, the
solution will perform as expected.Projects include distribution and
pad-mounted substations,capacitor banks and harmonic
filters, regulator stations, relaycontrol houses and retrofits,
distribution automation systemsand advanced protection systems.
CUSTOMER
BENEFITS Only One Contract To
Administer
Less Technical AndFinancial Risk
Accelerated Project Schedule
Investment ReturnRealized Sooner
An Innovative Cooper Solution
CPS Performance Guarantee
For more information, see our
ad on the back cover of this issue,
visit our Web site atwww.cooperpower.com/guaranteed, or, contact
Rich Marking-Camuto, P.E. at
1-414-768-8304 [email protected] LINE
Customer's ProjectManager
CPS as EPCProject Manager
CPS PM Support
CPS SystemsEngineering ContractedPartnersCPSProcurement CPS Techervices
Estimating Sc e u e & Document ControContact Administration & LegalAccounting & Finance
Conceptual DesignSystem Modeling,
Simulations & StudiesSystem IntegrationEquipment SpecsDesign Validation/QC
- Equipment ProcurementMultiple Factory Order
CoordinationExpeditingTransportation
Coordination
CommissioningTechnical DirectionTrainingSite ManagementWarranty Administration
Civi Structua Des i nSurveying & Soil
TestingConstruction Labor &
SupervisionConstruction Equipment,
Tools & MaterialsPermitting & Bonding
Task Descripti on Duration-2Y -1Y
Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1-14M -13M -12M -11M -10M -9M -8M -7M -6M -5M -4M -3M -2M -1M 0M 1M
Traditional Project(non-fast track) 2400h
Develop RFP for Engineering Services 2w
Bid Engineering 3w
Review Engineering Bids 1w
Engineering Phase 20w
Bid Construction 3w
Review Construction Bids 2w
Order Equipment 1w
Recieve Equipment 2w
Construction Phase 22w
Commission 2w
Negotiate Contract 4w
Engineering Phase 20w
Order Equipment 1w
Recieve Equipment 2w
Construction Phase 22w
Commission
Engineer-Procure-Construct 1600h