rig repair
DESCRIPTION
An interruption in planned operations caused by a breakdown of the drilling rig equipment.TRANSCRIPT
2003
1
Rig Repair
• Unscheduled Rig Repair
2003
2
Rig Repair
• An interruption in planned operations caused by a breakdown of the drilling rig equipment.
• Running the rig equipment to failure is not cost effective for the Drilling Contractor, Operator or Wellbore.
2003
3
Rig Repair
THE IMPACT OF UNSCHEDULED RIG REPAIR
The Drilling Contractor
• Financial penalties
• Cost of emergency repairs
• Possible personnel injury
• Extensive equipment damage
• Loss of future contracts
2003
4
Rig Repair
THE IMPACT OF UNSCHEDULED RIG REPAIR
The Wellbore
• A high risk of more unscheduled events
• Extended exposure time
• Loss of a hole section
• Loss of the well
2003
5
Rig Repair
THE IMPACT OF UNSCHEDULED RIG REPAIR
The Operator
• Increased well cost
• Delayed production
• Loss of production
2003
6
Rig Repair
PRIMARY DRILLING CONTRACTOR
AND
OPERATOR
OBJECTIVES
2003
7
Rig Repair
Drilling Contractor
• No personnel injury• No well control incident• Optimise equipment life• Minimise rig repair• Control equipment cost• Long term drilling
contract
Operator
• No personnel injury• No well control incident• Optimise drilling
operation• Minimise unscheduled
events• Control final well cost• Cost effective
performance
2003
8
Rig Repair
2003
9
Rig Repair
Preventive Maintenance Program (PMP)
• A program designed to schedule regular inspection, maintenance and/or repair of drilling equipment prior to failure.
• The historical life expectancy of rig equipment is based on the frequency of maintenance.
2003
10
Rig Repair
THE FOUR COMPONANTS OF A PREVENTIVE MAINTENANCE PROGRAMME
CLOSED LOOP
CREW FEEDBACK
RECORD KEEPING
AUDITING
Management to rig
Refining and tailoring of the
system
Equipment history
Through inspection
Rig to management
Equipment trends
Well designed checklists
Roles defined Equipment maintenance
Follow-up plans and reports
Clear guidelines
2003
11
Rig Repair
COMPREHENSIVE PMP EQUIPMENT LIST• MAIN ENGINES• GENERATORS/SCR SYSTEM• BOP & ACCUMULATOR CONTROL SYSTEM• HOIST EQUIPMENT• TOP DRIVE SYSTEM• ROTARY SYSTEM• HP MANIFOLD/VALVES/HOSES• HYDRAULIC OPERATING SYSTEM• RIG MOVE EQUIPMENT
2003
12
Rig Repair
TOP DRIVE
SYSTEM
2003
13
Rig Repair
COMPREHENSIVE PMP EQUIPMENT LIST• COMPRESSED AIR SYSTEM• CRANES• PIPE HANDLING SYSTEM• CIRCULATION SYSTEM• MUD PUMPS• BULK SYSTEM• MIXING SYSTEM• SOLIDS CONTROL SYSTEM• RIG COMPUTER SYSTEM
2003
14
Rig Repair
PMP FREQUENCY SCHEDULEHOURLY BI-MONTHLY EVERY TWO
YEARS
DAILY QUARTERLY EVERY THREE YEARS
WEEKLY EVERY FOUR MONTHS
EVERY FOUR YEARS
BI-WEEKLY SEMI-ANNUALLY
EVERY FIVE YEARS
MONTHLY ANNUALLY EVERY EIGHT YEARS
2003
15
Rig Repair
BENEFITS OF A SUCCESSFUL PMP PROGRAM• ENSURE EQUIPMENT LIFE EXPECTANCY• REDUCE DOWNTIME FOR UNSCHEDULED RIG
REPAIR• LOWER WELL COST• REDUCE SEVERITY OF DAMAGE TO EQUIPMENT• MAINTENANCE COST LESS THAN EMERGENCY
REPAIR• LESS CHANCE OF PERSONNEL INJURY• INCREASE IN DRILLING CONTRACTOR PROFITS
2003
16
Rig Repair
BENEFITS OF A SUCCESSFUL PMP PROGRAM
• REDUCED RISK OF STUCK-PIPE, WELL CONTROL OR OTHER UNSCHEDULED EVENTS
• COMPONENT FAILURE FREQUENCY RECORDS DEFINES RIG AND OFFICE SPARE PARTS INVENTORY
• INCREASE OPERATOR AWARENESS OF DRILLING CONTRACTOR NEEDS
• AN OPPURTUNITY FOR THE DRILLING CONTRACTOR TO INPUT AND HAVE INVOLVEMENT IN THE WELL PLANNING PROCESS
2003
17
Rig Repair
EVALUATE RIG REPAIR FAILURE SEVERITY
• WHO SHOULD BE NOTIFIED?
• WHAT IMMEDIATE ACTION IS REQUIRED?
• CAN NORMAL OPERATIONS CONTINUE?
• CAN PARTIAL OPERATIONS CONTINUE?
• IS OPERATIONAL SHUT-DOWN REQUIRED?
2003
18
Rig Repair
EVALUATE RIG REPAIR FAILURE SEVERITY
• ARE PERSONNEL OR THE RIG IN DANGER?• IS THE WELLBORE IN DANGER?• WHAT SAFETY PRECAUTIONS ARE
REQUIRED?• CAN THE FAILURE BE REPAIRED AT THE
RIG SITE?• WHAT IS THE PREVENTIVE ACTION PLAN?
2003
19
Rig Repair
DRILLING SYSTEM EMERGENCY BREAKDOWN PROCEDURES
IF RIG EUIPMENT FAILURE SHUTS-DOWN A MAJOR DRILLING SYSTEM, IMMEDIATE
ACTION MUST BE TAKEN TO PROTECT THE PERSONNEL, RIG, AND THE WELLBORE
FROM ASSOCIATED EVENTS
2003
20
Rig RepairDRILLING SYSTEM EMERGENCY BREAKDOWN PROCEDURES
DRILLING SYSTEM
BREAKDOWN
INITIAL RESULT SECONDARY RESULT
ACTION PLAN
POSITIONING 1. RIG MOVES OFF LOCATION
2. DRILLSTRING SHEARED-OFF
1. STUCK-PIPE
2. BOP DAMAGE
3. DRILLSTRING DAMAGE
4. SURFACE EQUIPMENT DAMAGE
1. STOP ROTARY & CIRCULATION
2. POSTION T.J. ABOVE HANG-OFF RAMS
3. CLOSE RAMS & HANG-OFF
4. INITIATE EMERGENCY PROCEDURES
2003
21
Rig Repair
DRILLING SYSTEM EMERGENCY BREAKDOWN PROCEDURES
DRILLING SYSTEM
BREAKDOWN
INITIAL RESULT
SECONDARY RESULT
ACTION PLAN
TOTAL LOSS OF POWER
1. LOSS OF HOISTING
2. LOSS OF CIRCULATION
3. LOSS OF ROTATION
1. STUCK-PIPE
2. WELL CONTROL
3. SURFACE EQUIPMENT DAMAGE AND/OR FAILURE
1. START EMERGENCY GENERATOR
2. CIRCULATE WITH THE CEMENT UNIT
3. MONITOR THE WELL FOR FLOW
2003
22
Rig Repair
DRILLING SYSTEM EMERGENCY BREAKDOWN PROCEDURES
DRILLING SYSTEM
BREAKDOWN
INITIAL RESULT
SECONDARY RESULT
ACTION PLAN
TOTAL DRILLING POWER
1. LOSS OF HOISTING
2. LOSS OF CIRCULATION
3. LOSS OF ROTARY
1. STUCK-PIPE
2. WELL CONTROL
1. START EMERGENCY GENERATOR
2. CIRCULATE WITH THE CEMENT UNIT
3. MONITOR THE WELL FOR FLOW
2003
23
Rig RepairDRILLING SYSTEM EMERGENCY BREAKDOWN
PROCEDURES
DRILLING SYSTEM
BREAKDOWN
INITIAL RESULT
SECONDARY RESULT
ACTION PLAN
TOP DRIVE SYSTEM
(TDS)
1. LOSS OF HOISTING
2. LOSS OF CIRCULATION
3. LOSS OF ROTARY
1. STUCK-PIPE
2. WELL CONTROL
1. TRIP TO THE SHOE FOR REPAIR
2. ROTATE THE PIPE IN THE SLIPS
3. RIG-UP TO CIRCULATE
4. MONITOR THE WELL FOR FLOW
2003
24
Rig Repair
DRILLING SYSTEM EMERGENCY BREAKDOWN PROCEDURES
DRILLING SYSTEM
BREAKDOWN
INITIAL RESULT
SECONDARY RESULT
ACTION PLAN
HOISTING SYSTEM
1. CANNOT RAISE DRILLSTRING
1. STUCK-PIPE 1. CONTINUE CIRCULATION AND ROTATION
2003
25
Rig Repair
DRILLING SYSTEM EMERGENCY BREAKDOWN PROCEDURES
DRILLING SYSTEM
BREAKDOWN
INITIAL RESULT
SECONDARY RESULT
ACTION PLAN
ROTARY SYSTEM
1. CANNOT ROTATE THE DRILLSTRING
1. STUCK-PIPE 1. RECIPROCATE THE DRILLSTRING
2. TRIP TO THE SHOE FOR REPAIR
3. MAINTAIN FULL CIRCULATION
2003
26
Rig RepairDRILLING SYSTEM EMERGENCY BREAKDOWN PROCEDURES
DRILLING SYSTEM
BREAKDOWN
INITIAL RESULT
SECONDARY RESULT
ACTION PLAN
CIRCULATNG SYSTEM
1. CANNOT CIRCULATE THE WELL
1. STUCK-PIPE
2. WELL CONTROL
1. TRIP TO THE SHOE FOR REPAIR
2. ROTATE AND RECIPROCATE THE DRILLSTRING IF REPAIRS ARE MADE IN OPEN HOLE
2003
27
Rig RepairDRILLING SYSTEM EMERGENCY BREAKDOWN
PROCEDURES
DRILLING SYSTEM
BREAKDOWN
INITIAL RESULT
SECONDARY RESULT
ACTION PLAN
WELL CONTROL SYSTEM
1. CANNOT SHUT-IN THE WELL ON A KICK
2. BLOWOUT
1. EQUIPMENT DAMAGE
2. PERSONNEL INJURY
3. LOSS OF THE WELL
4. ENVIRONMENTAL DAMAGE
1. NON – EMERGENCY, SECURE THE WELL TO MAKE REPAIRS
2. INITIATE EVACUALTION PROCEDURES
2003
28
TeamsDrilling Problems
2003
29
Rig Repair
INTEGRATED PREVENTIVE MAINTENANCE PROGRAMME (IPMP)
RIG EQUIPMENT MAINTENANCE LIST
1. SERVICE MAIN ENGINE 8. SERVICE CENT. PUMPS 15. SERVICE VECHILES 22.
2. SERVICE GENERATORS 9. 4,5,6 16. SERVICE CENT. PUMPS 23.
3. SERVICE AIR COMPRESSOR 10. SERVICE D/WORKS BRAKES 17. SERVICE FLOOR WINCHES 24.
4. SLIP/CUT DRILL LINE 11. SERVICE TDS 18. SERVICE WATER COOLER 25.
5. SERVICE CRANE 12. SERVICE DIVERTER 19. SERVICE PUMP MANIFOLD 26.
6. LIFTING EQUIPMENT INSPECT 13. SERVICE SOLIDS CONTROL 20. SERVICE ST/PIPE MANIFOLD 27.
7. SERVICE BOP ACCUMULATOR 14. CHANGE SWIVEL PACKING 21. TEST PUMP 28.
LEGEND
PLANNED MAINTENANCE
LOW RISK MAINTENANCE
HIGH RISK MAINTENANCE
SERVICE COMPANY MAINTENANCE LIST
CEMENT UNIT LOGGING UNIT MUD LOGGING UNIT
OTHER
1. SERVICE TRANS #1 6. SERVICE P/TANK VALVES
11. SERVICE ENGINE 16. SERVICE COMPUTER
2. SERVICE ENGINE #1 7. SERVICE PUMP #1 12. SERVICE TRANS 17. INSPECT SENSORS
3. SERVICE TRANS #2 8. 13. SERVICE OP. CHAIR 18. RESUPPLY UNIT
4. SERVICE ENGINE #2 9. 14. REPLACE WIRE REEL
19. SERVICE OP. CHAIR
5. SERVICE PUMP #1 10. 15. 20. SERVICE LIGHTING
2003
30
Rig Repair
SERVICE IPMP 4-5-6-10-12 #2 12 9-22-23 16 13
RIG IPMP 1-2-4-5-6-10-12-29 15 11
19 17-16-20 18 10
DAYS FROM SPUD 0-----5-----10-----15-----20-----25------30------35------40------45------50------55------60------65------70
WELL PLAN 26” HOLE 20” CASING
W.OC.
CASING----------DEPTH 17½” HOLE 13⅜” CASING
RUN CASING
30” 1284 FT W.O.C.
12¼” HOLE 9⅝” CASING
20” 2600 FT RUN CASING
W.O.C.
13⅜” 5080 FT 8½” HOLE 7” LINER
RUN CSG
9⅝” 12,250 FT WOC
7” 14,540 FT