rig hse case guideline (modu)...this guideline is structured in accordance with the iadc hse case...
TRANSCRIPT
Wells HSE
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG HSE GUIDELINE/2015/ Rev. 1
March 2015
© 2015 PETROLIAM NASIONAL BERHAD (PETRONAS)
All rights reserved. No part of this document may be reproduced,
stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or
otherwise) without the permission of the copyright owner.
PETRONAS makes no representation or warranty, whether
expressed or implied, as to the accuracy or completeness of the
facts presented. PETRONAS disclaims responsibility from any liability arising out of reliance on the contents of this presentation.
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 2 of 41
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 3 of 41
Document Holder
No. Title
1 Stephen Oliver
Note:
1. A Document Holder is responsible to communicate and ensure compliance with the
requirements of this document.
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 4 of 41
Document Development Team Members
No. Name Designation Department
1 Stephen Oliver Technical Safety Specialist Wells HSE
2 Ad Theuns Senior Safety Specialist Wells HSE
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 5 of 41
Amendment Summary
The table below must be completed in detail for each revision. To indicate amendments from the
previous version, vertical lines in the left hand margin shall be added at the amended section.
Rev Page Description Approved By Approval Date
1
All
Approved Final Document
Datuk George
Ling Kien Sing
03-04-15
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 6 of 41
Table of Contents
1.0 INTRODUCTION .................................................................................................... 7
1.1 OBJECTIVE ........................................................................................................................................................... 7 1.2 SCOPE ................................................................................................................................................................... 7 1.3 STRUCTURE ......................................................................................................................................................... 7 1.4 ABBREVIATIONS ................................................................................................................................................ 7 1.5 GLOSSARY ........................................................................................................................................................... 8
2.0 Drilling Rig HSE Case ............................................................................................ 9
2.1 HSE CASE CONTENTS ....................................................................................................................................... 9
3.0 Section Content Guidance ................................................................................... 10
PART 1 INTRODUCTION .............................................................................................................................................. 10 PART 2 DRILLING CONTRACTORS MANAGEMENT SYSTEM ................................................................................. 11 PART 3 RIG DESCRIPTION AND SUPPORTING INFORMATION ........................................................................... 11 PART 4 RISK MANAGEMENT ...................................................................................................................................... 11 SAFETY CRITICAL ELEMENTS (BARRIERS) ............................................................................................................. 14 FIGURE 1 SCE ANALYSIS APPROACH ..................................................................................................................... 19 BOWTIE METHODOLOGY ............................................................................................................................................. 20 SAFETY (HSE) CRITICAL TASKS .............................................................................................................................. 21 PERFORMANCE STANDARDS ....................................................................................................................................... 22 DEVELOPING PERFORMANCE STANDARDS .............................................................................................................. 23 PERFORMANCE STANDARD PROCESS ....................................................................................................................... 25 PERFORMANCE STANDARD FORMAT ......................................................................................................................... 27 PERFORMANCE STANDARDS REVIEW ....................................................................................................................... 27 SWISS CHEESE MODEL ................................................................................................................................................ 28 PART 5 RIG EMERGENCY RESPONSE ........................................................................................................................ 29 PART 6 PERFORMANCE MONITORING...................................................................................................................... 29
4.0 Remedial Action Plan .......................................................................................... 31
5.0 Rig HSE Case Review ........................................................................................... 31
6.0 PETRONAS CARIGALI HSE Case Assessment Process .......................................... 31
7.0 Operationalization of the Rig HSE Case ............................................................... 33
EXAMPLE OF SAFETY CRITICAL LISTINGS .............................................................................................................. 34
8.0 Barrier Monitoring ............................................................................................... 35
9.0 Visual & Practicable Use...................................................................................... 36
10.0 Incident Investigation ..................................................................................... 36
11.0 Bridging Document .......................................................................................... 37
12.0 Simultaneous Operations ................................................................................. 37
13.0 Rig HSE Case Review Check List ....................................................................... 37
14.0 Appendix 1 - Typical SCE Barrier Diagram ........................................................ 40
15.0 References ....................................................................................................... 41
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 7 of 41
1.0 INTRODUCTION
1.1 Objective
The objective of this guideline is to give guidance to all Drilling Contractors on the
development, content and operationalization of the Rig HSE Case and assist PETRONAS
CARIGALI personnel to effectively review, verify and formally accept the Case for the
intended Operation.
In line with PETRONAS CARIGALI Operations requirement UHSE Technical Standard for HSE
Case EP-HSE Case-02-12 (rev 1) all drilling units shall have in place an HSE Case developed
in accordance with the latest IADC Guideline for HSE Case for Mobile Offshore Drilling Units
(MODU)
This Rig HSE Case Guideline is intended to give further guidance on PETRONAS CARIGALI
requirements in addition to IADC and give direction on effective development and
implementation of the Rig HSE Case specifically in relation to Major Accident Hazard (MAH)
prevention through Safety Critical Element (SCE) identification & setting, monitoring and
verification of the associated performance standard.
It shall also give guidance to Drilling Contractors on the submittal, approval and verification
process for formal acceptance of the HSE Case by PETRONAS CARIGALI.
It is the responsibility of each Drilling Contractor to ensure that any further revisions issued
by IADC to the HSE Case Guidelines for MODU are reviewed and implemented as required.
1.2 Scope
This guideline shall be applicable throughout PETRONAS CARIGALI global operations. For
international operations if operating in a country subject to regulatory HSE Case
requirements then the drilling contractor shall also adhere to the regulatory requirements
of the country of operation.
1.3 Structure
This Guideline is structured in accordance with the IADC HSE Case Guideline for MODU
(Jan 2015) in that further guidance and required PETRONAS CARIGALI Rig HSE case
content is outlined through HSE Case parts 1-6 in Section 3 of this Guideline, with
additional guidance as required.
1.4 Abbreviations
(1) For the purpose of this guideline, the abbreviations and acronyms used in this
document shall have the following meanings
No. Abbreviations Description
1 ESD Emergency Shutdown Device
2 F&G Fire and Gas
3 HSE Health Safety Environment
4 IADC International Association of Drilling Contractors
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 8 of 41
No. Abbreviations Description
5 MAH Major Accident Hazard
6 MOC Management Of Change
7 MODU Mobile Offshore Drilling Unit
8 OIM Offshore Installation Manager
9 PS Performance Standard
10 RAM Risk Assessment Matrix
11 SCE Safety Critical Element
12 TOR Terms of Reference
13 TR Temporary Refugee
1.5 Glossary
No. Term Description
1 Assurance Represents the activities performed to ensure SCE’s meet Performance Standards
2 Competence The ability to perform a particular job or task in compliance with the Performance Standard
3 Major Accident (MA)
An occurrence (including in particular, a major emission, fire or explosion) resulting from uncontrolled developments in the course of the operation of any establishment and leading to serious danger
to human health or the environment, immediate or delayed, inside or outside the establishment, and involving one or more dangerous substances.
4 Performance Standard
A statement that can be expressed in qualitative or quantitative terms of the performance required of a system, item of equipment,
person or procedure of which is used as the basis for managing the hazard.
5 Risk Matrix A Tool for ranking and displaying risks by defining ranges for consequence and likelihood.
6 Risk
Management
Coordinated activities to direct and control an organization with
regard to risk.
7 SCE Such Parts of an Installation, including computer programs, or any part there of:
The failure of which could cause or contribute substantially to ; or
A purpose of which is to prevent or limit the effect of a major
accident.
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 9 of 41
No. Term Description
8 Tolerability Tolerability refers to the willingness to operate with a risk to secure
certain benefits and in the confidence that it is being properly controlled.
9 Verification Represents the activities in addition to Assurance carried out by Independent Competent Person appointed by Duty Holder to confirm whether the SCE’s will be, are and remain suitable.
2.0 Drilling Rig HSE Case
As stated the drilling contractor shall have in place an HSE Case developed in accordance
with the latest revision of the IADC Guidelines.
The HSE Case shall:
Demonstrate that there is an effective HSE Management System in place to
manage major hazards, other work place hazards and environmental hazards.
Identify all potential hazards, including major accident events.
Identify, assess and manage the risks associated with the hazards and
demonstrate that all residual risks have been reduced to tolerable levels.
Identify those personnel with HSE Critical Tasks to maintain Safety Critical
Barriers.
2.1 HSE Case Contents
The rig HSE Case (as per IADC Guidelines) shall contain the following as minimum:
Introduction/Expectations
Drilling Contractors Management description, describes the drilling contractor’s
management system and presents HSE management objectives that must be met
to demonstrate assurance that HSE risks are reduced to tolerable levels.
MODU/Installation description and supporting information, describes the equipment
and systems necessary to meet the HSE management objectives and to fulfil the
requirements of the Drilling Contractors scope of operations.
Risk Management, describes the Risk Management Process for assuring that the
risks associated with a Drilling Contractor’s Scope of Operations are reduced to a
level of risk that is tolerable to the Drilling Contractor and PETRONAS. The Risk
Management Process must consider the HSE management objectives described in
Part 2 and the systems and equipment described in Part 3. Any gaps related to the
HSE Management Objectives in Parts 2 and 3 that are identified in Part 4 must be
addressed in the Drilling Contractor’s management system.
Emergency Response describes the HSE management objectives for
Emergency response of incidents - to mitigate the consequences (severity)
identified in Part 4 and the measures to recover.
Performance Monitoring, describes arrangements for monitoring to ensure that the
risk management measures identified in Part 4 are implemented, maintained and
effective at the workplace. (See section 6.0 on Performance Standards Framework)
Remedial Action Plan (PETRONAS CARIGALI requirement), is a compilation of
recommendations identified during HSE Case assessments. All recommendations
shall be reviewed and accepted by the HSE Case Custodian. The recommendations
shall be tracked to closure via a formal action tracking system (e.g. HSE Online,
iHSE etc.) to ensure it is properly monitored.
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 10 of 41
All Drilling Contractors shall refer to the latest revision of the IADC HSE Guidelines for
detailed guidance on the structure and content of each section.
3.0 Section Content Guidance The following section is structured in accordance with the IADC HSE Case Guidelines, the
intention is to give further guidance as required to ensure the Rig HSE Case meets the
requirements of both IADC & PETRONAS CARIGALI.
Part 1 Introduction
All Drilling Contractors shall refer to IADC Guidelines for development of Part 1 of the HSE
Case. Part one shall include as minimum:
Purpose of the Rig HSE Case
Senior Management Demonstration against the expectations identified in the IADC
Guidelines
HSE Case Scope and arrangements
Drilling Contractor Overview
HSE Case responsibilities, It is critical to demonstrate in this section who is
identified as the responsible person/position to ensure the HSE case is
implemented effectively and complied with
HSE Case Review and Updates
Continuous Improvement to include statement of contractors commitment to
continuous improvement and how they demonstrate this
Action Plan/Recommendations to demonstrate how the Drilling Contractor
addresses Identified HSE performance gaps
In addition to the above IADC requirements PETRONAS CARIGALI require this section to
also include a statement/demonstration of how bridging requirements will be addressed
for campaign specific risks.
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 11 of 41
Part 2 Drilling Contractors Management System
This section shall describe in detail the Drilling Contractors Management System and
layout the HSE Management objectives. The IADC Guidelines are quite prescriptive in
this section requirements thus PETRONAS CARIGALI shall review this section in line with
the IADC Guidelines and no further guidance is required.
Part 3 Rig Description and Supporting Information
The purpose of section 3 is to detail the rig layout and describe the equipment and
systems on the rig. It shall describe the equipment and systems onboard to meet HSE
Management objectives outlined in sections 2 & 5. This shall include but not limited to:
MODU Details
Certification, Classification and Registration
MODU Layout
Modifications or Upgrades
Selection of HSE Critical Equipment & Systems (See following Section for
Guidance)
Operating Limits
Structural Integrity
Stability Systems
Ballast & Bilge Systems (Semi, Drill ships)
Towing Arrangements
Mooring & Station Keeping (If required)
Drilling, Completion & Well Control Systems
Helideck Arrangements
Emergency Lighting
Fire & Explosion Protection
Detection Systems
ESD Systems
Passive Fire Protection
Temporary Refugee Arrangements
Evacuation & Escape Arrangements
Well Testing Arrangements
Other Third Party Equipment
Accommodation Arrangements
Within section 3 as per IADC HSE Case Guidelines for MODU Section 3.1.5 it shall describe
how the drilling contractor selects equipment/systems that are determined to be HSE
Critical (Safety Critical Elements SCE)
The IADC Guidelines do not outline a defined process for determining those equipment &
systems that are Safety Critical thus further guidance is described in Part 4 within this
Guideline.
Part 4 Risk Management
The objective of Part 4 of the Rig HSE Case is to demonstrate the effectiveness of the
Drilling Contractors risk management process and critically how it is applied by the rig
personnel at the worksite.
The IADC Guidelines calls for a consistent approach in identifying and managing risk thus
this section shall demonstrate the Risk Management Process for assuring that risks
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 12 of 41
associated with the Rig operations are reduced to a level that is tolerable both for the
Drilling Contractor and PETRONAS CARIGALI
The HSE Case is the principal document that is used to identify the Major Accident Hazards
and consequently establish the barriers that are in place that prevent or mitigate the
consequences of the MAH.
The Risk Assessment Process Shall address the key 3 steps as outlined in the Structured
Hazard Identification and Control (SHIDAC) Process:
Step 1 Identify Hazards
Step 2 Evaluate Risk
Step 3 Identify Risk Reduction measures (control, defense, and recovery measures
and set performance requirements)
Detailed guidance on the content of each step is outlined in the IADC Guidelines. Although
it should be highlighted that workplace hazards that have been assessed as high risk the
following shall be applied:
For each cause (potential to release hazards) identify the barriers (SCE) expected to
prevent the release of the hazard
For every potential release of hazard identify the barriers to reduce the consequences
or assist in the recovery from the consequences
For each (barrier) SCE Identified
Identify the critical tasks/activities required to ensure barriers are in place,
working effectively and integrity maintained
Identify the resources & competencies required for the barrier to be implemented
and effective
Identify where the barrier is referenced in the Management System
Identify any factors that prevent such barriers from being defeated, removed
from service or any reduction or elimination of their effectiveness and;
Identify any compensatory barriers and the associated activities, resources,
competencies and management system references to address such factors.
As per IADC Guidelines In order to provide a consistent and systematic estimation of risk,
the recommended approach is to apply a Risk Assessment Matrix (RAM) in a qualitative
manner. A RAM provides a convenient structure to apply the Drilling Contractor’s
screening criteria (values, targets or performance standards) to evaluate or compare
the significance of an identified hazard, event or associated risk to determine the
tolerability.
The IADC HSE Case Guidelines do not prescribe which RAM should be adopted and each
Rig Contractor may have different matrices, but the RAM is fundamental in the risk
management process for determining MAH.
The following RAM is a typical Risk Assessment Matrix taken from the IADC Guidelines and
the Specific RAM utilized by PETRONAS CARIGALI for determining risk.
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 13 of 41
PETRONAS CARIGALI RAM The classification of hazards as MAH is determined by risk
ranking, Major Accident Hazards are represented by risks ranked as Red – VERY HIGH
(E4, E5, D5), Orange – HIGH (B5, C5, D4, E3)
Whichever RAM has been applied when determing the classification of Hazards the
relevant Rig HSE Case shall reference:
A description of the process used to systematically evaluate and select the barriers
that will be applied to reduce the risk of each identified hazard and source
The completed Rig Contractors Hazard/Risk Register listing all the hazards and
sources, the estimates of the associated risks, the significance of these and the
references to the associated barriers selected to reduce the associated risks
Describe the critical activities, resources and competencies etc. needed to ensure
these are all established and maintained
References to the decisions made by the review team to document their
justifications for rejected or potential barriers
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 14 of 41
Details of where relevant good practice and judgement based on sound engineering
and ergonomic principles have been taken into account in determining which risks
are tolerable
A list of all the barriers that have been selected to reduce the risks, also
highlighting which barriers are already in place and those to be put in place.
A prioritized Remedial Action Plan to fully establish the remaining selected barriers
including identifying the required/responsible personnel for implementation.
PETRONAS CARIGALI shall use TOLERABILITY as it’s reference for determing risk.
Tolerability means a willingness to operate with some risk in order secure certain
benefits and in the confidence that the risk is being correctly controlled. The risks are
considered Tolerable where:
The Drilling Contractor is willing to accept the risk in order to gain the benefits
from the activity (with the understanding that the risk is being properly managed
and with the belief that the risk is worth taking); And
The risk has been reduced to a level where the effort, cost and practicality of
further reduction measures become disappropriate to the additional amount of risk
reduction that could be gained this condition is sometimes reffered to As Low As
Reasonably Practiable (ALARP)
Tolerability is considered to be achieved when the risk is reduced to a level at which the
cost and effort of further risk reduction is largely disproptionate to the achieved reduction
of risk, as illustrated in diagram below, although to ‘Tolerate” risk does not necessarly
mean it is regarded as negligible or the risk can now be ignored but rather a risk that
must be kept under review and reduced further if and when it can be.
Safety Critical Elements (Barriers)
Safety Critical Elements are any structure, plant, equipment, system (including computer
software) or component part whose failure could cause or substantially contribute to a
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 15 of 41
major accident, or are any which are intended to prevent or limit the effect of a major
accident.
The Safety Critical Element not only includes the specified equipment, but also any other
SCE required for the equipment to perform its specified safety function, including electric
and hydraulic power supplies and connections.
Each SCE shall be selected based on the following criteria:
Consequences of failure of the item
Elements that contribute substantially to preventing or reducing, risks from Major
Accident Hazards (MAH)
Elements that contribute substantially to controlling or mitigating the effects of a
MAH.
For PETRONAS CARIGALI requirements each SCE identified shall be grouped into the
relevant barrier which will prevent or limit the consequence of a Major Accident Hazard or
Event.
The Rig HSE Case (as minimum) should ensure that each SCE is identified/grouped using
the generic barrier groups: (See Section 3.0 Swiss Cheese Model)
1. Structural Integrity
2. Process Containment
3. Ignition Control
4. Detection Systems
5. Protection Systems
6. Shutdown Systems
7. Emergency Response
8. Life Saving
Each Major Accident Hazard (MAH) is established through Hazard Identification Study
(HAZID) each MAH shall be analyzed to identify the required means to manage the
associated risks. The HAZID process used by each Drilling Contractor to identify the MAH,
associated risks and SCE shall be demonstrated or referenced as part of the Rig HSE Case.
Typical Examples of SCEs and relevant associated equipment (sometimes referred to as
sub-elements) include but are not limited to:
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 16 of 41
Structural Integrity (SI)
Critical structures whose failure could lead to a multiple fatality accident, e.g.
offshore jackets, accommodation unit topside support structures
Structures supporting equipment where loss of integrity could result in an escape
of hazardous material with the potential to cause fatality and/or damage the
environment
Structures designed to protect other structures or equipment from the full force of
an impact which otherwise has the potential to cause major accidents e.g. boat
fenders / riser guards
Lifting equipment and systems, jacking systems whose failure could lead to or
contribute to a major accident
Ballast System
Heavy Lift Cranes
Drilling System
Mooring System
Subsea Foundation Structures
Topsides &/ Surface
Bridge Connections to support vessel
Station Keeping / Propulsion / Dynamic Positioning / Thrusters
Process Containment (PC)
Equipment, piping and pipelines where loss of integrity could result in an escape of
fluid under pressure or hazardous material with the potential to cause harm to
people and /or the environment
Integrity protection systems such as relief valves, instrumented protective
systems, and bursting discs that protect the plant from loss of containment as a
result of exceeding design conditions.
Fired Heaters
Gas Tight Floor Wall
Heat Exchanger
Helicopter Refuel
Oil Produced Water Control
Pipeline System
Piping System
Pressure Vessel
Rotating Equipment
Tank
Tanker Loading
Well Containment
Wire Line Equipment
Relief System
Moveable and Temporary Equipment
Ignition Control (IC)
Area classification systems and procedures designed to prevent ignition in case of
an escape of flammable material. This also includes ventilation systems that may
be necessary to maintain the correct area classification.
Miscellaneous ignition control components such as flame arrestors, spark arrestors,
etc.
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 17 of 41
Hazardous. Area Ventilation
Non- Hazardous. Area Ventilation
Certified Electrical Equipment
Earth Bonding
Cargo Tank Inert Gas System
Flare Tip Ignition
Fuel Gas Purge System
Miscellaneous Ignition Control
Chemical Tank Inert System
Detection Systems (DS)
Detection equipment and systems designed to alert the operators of an escape of
hazardous material and possibly to initiate various control actions.
Portable gas monitoring and gas testing equipment, used either to supplement, or
to complement fixed equipment and systems, or for certifying safe conditions of
work, e.g. prior to undertaking hot work or confined space entry under Permit to
Work (PTW).
Fire and Gas Detection System
H2O in Condensate
Protection Systems (PS)
Fire and explosion suppression equipment and systems where people could
otherwise be at risk
Firefighting equipment and systems
Incident control equipment such as water sprays, foam systems
Equipment and systems designed to mitigate the consequences of fire and
explosion such as fire walls, blast walls and passive fire protection
Other equipment and systems, which play a significant role in preventing major
accidents, such as navigational aids.
Chemical Injection System
Collision Avoidance
Deluge System
Fire/Explosion Protection
Navigational Aids
Power Management System
Sand Filter
Firewater Pumps
Firewater Ring main
PFP
Gaseous PFP
FWS System
Sprinkler System
Fixed Foam Sys
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 18 of 41
Shutdown Systems (SS)
Release control equipment and systems such as emergency shutdown, non-return
valves, and blowdown, which are designed to limit the quantity of hazardous
material involved in an incident.
Well isolation equipment such as the SCSSSV, SSV, etc.
Drilling well control equipment such as Blowout Preventer, Mud weight control, etc.
De-pressurization System
Drilling Well Control
ESD
HIPPS
SSIV
Well Isolation
Pipeline Isolation Valves
ESDVs
Emergency Response (ER)
Emergency power equipment and systems (emergency generators, switch gear,
Uninterruptable Power Supplies (UPS), etc.
Communications equipment and systems that alert people that an incident has
occurred and which can be used to provide instruction
Equipment and systems that allow communication between emergency response
teams and the emergency control centre
Equipment and systems that expedite the removal of people to a place of safety
such as emergency lighting, escape routes, offshore platform evacuation systems
and standby vessels.
Equipment and systems that allow communication with external agencies that can
provide assistance in dealing with the incident.
Secondary containment equipment and systems designed to restrict hazardous
materials spreading from a spillage location into other areas.
Weighing and measuring equipment and systems whose failure could lead to or
contribute to a major accident such as gas meters, pressure/ temperature/level
gauges, weighbridges.
Communication System
Emergency Power
Emergency/ Escape Lighting
Escape & Evacuation Routes
Helicopter Facilities
Temporary Refuge
UPS
Manual Fire Fighting Equipment
Open Hazardous Drain
Open Non Hazardous Drain
Oil Spill Contingency (Oil Booms and Dispersants)
Life Saving (LS)
Personnel protective equipment for general use in an emergency such as life
jackets, breathing apparatus, and search and rescue equipment, etc.
Evacuation facilities such as life boats, TEMPSC, life rafts, knotted ropes, scramble
nets, boat landing etc.
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 19 of 41
PPE
Lifeboats/ TEMPSC
Rescue Facilities
Tertiary Means of Escape
Life Jackets and Life Buoys
The IADC MODU HSE Case Guidelines do not give prescriptive list or overview of what
predefines Technical SCE and on which detail level they shall be identified although they
can be divided into two main categories – those that do and those that do not alter shape
state or condition in order to perform a barrier function. The former is commonly referred
to as active or functional barrier elements, while the latter is often called passive or
structural barriers.
Active barriers can be characterized by being dependent on actions of an operator, a
control system and/or some energy sources to perform their functions. Passive barriers
refer to measures integrated into the design of the platform or vessel, and do not
require operator actions, energy sources or control systems to perform their functions.
Examples Include:
Active / functional: Fire and gas detectors, fire dampers, sprinklers, emergency
shutdown valves, PA, communication equipment, BOP, choke and kill system, etc.
Passive / structural: Fire and explosion walls, casing, cements, 500m safety zone,
passive fire protection, drains, escape routes, temporary refuge etc.
Figure 1 SCE Analysis Approach
The below diagram gives a basic structured approach to the identification of SCE, Setting
of the Performance Standards and the verification of the Performance.
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 20 of 41
The main output objectives from the above process are to identify:
What is classed as Safety Critical? (SCE)
What does it have to do? (Functional Requirement)
What do we need to do to ensure its reliability? (Performance Standards)
Monitoring and Routine Inspection (Maintenance, inspection and Testing)
Auditing & Inspection (Assurance)
Bowtie Methodology
In order to better understand and be aware of the rigs Safety Critical Elements and their
functions a systematic approach shall be demonstrated. In order for the rig to manage
each SCE they must first know what they are and what they do.
Each SCE/Barrier for each identified MAH shall be presented in the “Bowtie” This picture
format links all the SCE/Barriers for a given MAH which in turn allows the rig to adopt a
systematic approach to the management of the SCE/Barriers.
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 21 of 41
Safety (HSE) Critical Tasks
HSE Critical Tasks or activities are essential for maintaining the effectiveness of each
identified safety critical element.
Personnel contribute to major accident risk both in positive and negative ways. Positively,
they detect and correct failures in technical systems through e.g. testing and
maintenance, they diagnose and respond to system upsets and abnormalities in ways
which computers are incapable of, and they perform other tasks which cannot be replaced
by machinery and automation. Negatively, as with technical systems, personnel are prone
to error under certain circumstances, such as working under stress, lacking proper
training or operating with misleading procedures. This contribution happens through what
is called HSE critical tasks, which in many ways can be considered the operational, or
human, equivalent to SCEs.
Operational elements are considered safety critical because they represent operator tasks
which play a direct role in realizing preventive or mitigating barrier functions. For
example, tasks required to ensure correct mud density and volume can be identified as an
HSE Critical task part of the barrier function “prevent well kick”.
The Drilling Contractor shall identify the competent staff designated to maintain the
Safety Critical Element/Barrier. Each task maybe a combination of:
Inspection and Maintenance – To ensure the equipment/hardware maintains its
integrity and reliability
Operational- To ensure that the equipment is used within the defined limits of the
controls provided
Administrative – To provide the necessary training and awareness to ensure people
perform to the required competency level and provide the necessary equipment
and support for them to adequately perform the task.
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 22 of 41
IADC does not define Competence but for PETRONAS CARIGALI requirements it shall
include having the necessary theoretical and practical knowledge and actual experience
of the type of rig or facility to conduct the necessary inspections and maintenance and
thus identify any defects or potential weaknesses.
The Drilling Contractor shall have a system of documented competence assurance with
a traceable means of assessment which clearly states the competence criteria and
method of assessing the designated person with the HSE Critical Task.
The Competence scheme shall contain the minimum following elements:
Competency criteria by engineering discipline or SCE Specific
Detailed criteria to define competence – a combination of technical knowledge
Frequency of review and assessment
Definition of which lifecycle phase the person is considered competent for
It may also be linked to the competence program to demonstrate how the level of
competence is increased.
The Rig HSE Case shall contain or make reference to:
List of the HSE Critical Activities/Tasks & Equipment/Systems
Details of the arrangements for verification of effectiveness for all HSE critical
activities/tasks and equipment/systems against the established performance
standards
Details for the arrangements for tracking actions arising from verification to
completion.
Further guidance on awareness and training into HSE Critical Tasks is outlined in
section 7.0 On Operationalization of The HSE Case.
Performance Standards
Performance standards shall be prepared for all Safety Critical Elements. The performance
standards are the parameters that are measured or assessed so that the suitability and
effectiveness of each SCE can be assured and verified.
Through the development of Performance Standards the drilling contractor shall
demonstrate a competent understanding of the MAH controls in place based on
measureable evidence. In that through the development of the performance standards
within the HSE Case they can demonstrate:
They fully understand what the performance criteria is for each MAH Control and;
That the maintenance and testing is fully implemented to demonstrate that these
performance standards can be met.
So in basic principle “This is what the control is designed to do” and “This is how we
demonstrate through testing/maintenance etc. It actual does it”
The performance standard process and associated standard shall be developed for each
identified Safety Critical Element (SCE)
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 23 of 41
Developing Performance Standards
When developing the performance standards the following criteria shall be met:
Functionality, what the control measure must do and the criteria it must achieve.
Reliability, assuring its functional capability.
Survivability, will it continue to function, if required after a hazardous event has
occurred.
Dependency, what other control measures are required to maintain/allow its
functional capability.
And then how the above criteria is or will be assured e.g. Design/Technical review,
QA/QC, maintenance, inspection & testing or audits etc.
The following shall be observed in the setting of Performance Standards:
Each criteria, including minimum acceptance criteria shall be justified
It should be encouraged to use and reference design standards and codes where this
is relevant. For example, the Code used to design the SCE, or that governs the
testing frequency e.g. API RP 520 for sizing of relief valves, EEMUA 188 for
establishing operating periods of relief valves. This may be relevant throughout the
asset lifecycle.
HSE Case supporting studies such as Fire and Explosion Risk Assessment (FERA) and
Quantitative Risk Assessment (QRA) should be reflected in the Performance
Standard criteria, e.g. FERA shall provide information for the required fire water
demand in respect to the largest potential scenario.
Clearly measurable criteria, which can be confirmed during routine operations,
maintenance, testing or inspection is needed. Where acceptance criteria are obscure
or ambiguous they cannot practicably be assured. This can lead to confusion and
loss of confidence in the SCE management process
Lifecycle phases shall be separately considered, but shall be combined into a single
Performance Standard document. This is to provide traceability across the entire
lifecycle of the SCE.
The specific performance standard shall ensure for all Safety Critical Elements that they:
Are suitable and fully effective for the type hazards identified,
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 24 of 41
Have sufficient capacity for the duration of the hazard or the required time to provide
evacuation of the installation,
Have sufficient availability to match the frequency of the initiating event,
Have adequate response time to fulfil its role,
Are suitable for all operating conditions”.
The following demonstrates the performance requirement for active fire water System:
Performance Criteria shows what the system requirements are, Basis is what the
Performance Criteria is developed against i.e. Design, Regulations, rules etc. Performance
Verification is how each function is verified and how it is assured.
The performance verification should also contain the relevant links to the Procedure or
Maintenance Task or Schedule.
Function 2 To Supply the Fire water at the required pressures and flow rate:
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 25 of 41
Performance Standard Process
Performance Standards need to be defined in a consistent and logical manner. It is likely
that more than one parameter will be needed to detail the required performance of the SCE
as a barrier. The codes, standards and specifications used in the original design of SCEs
should be identifiable from the Performance Standards so that suitability can be maintained
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 26 of 41
throughout the asset’s life. Any other related key documents should also be referenced
in the Performance Standard.
Performance Standards Criteria:
Functionality
Functionality defines the key duties that the SCE is required to perform. The minimum level
at which that function is achieved must also be defined. Criteria is considered measurable
where it is possible for a person carrying out an assurance task or activity to clearly
understand what the critical requirement is and thus be able to measure or observe that
the criteria is being met.
Reliability
How likely is it to perform on demand? Those SCE’s for which it is required to measure
reliability during operations shall be identified at the design stage. Reliability targets are
set during the design phase based upon the safety studies carried out in support of the
Rig Safety Case. When in the operation phase the ability to meet this criteria is
demonstrated by functional testing at appropriate intervals, From these functional tests
Survivability
Will it continue to function, if required after a hazardous event has occurred.
The performance criteria for survivability must be defined if the SCE is required to operate
in the event of a Major Accident, it shall also state how long the system should continue to
operate for. Each SCE shall be considered against the defined MAH in the Rig HSE Case.
Dependency/Interactions
What other control measures are required to maintain/allow its functional capability.
It shall also be defined what other SCE’s are required to function in order for the one in
question to operate effectively.
Systems of SCE’s are often dependent upon each other in order that the MAH is mitigated.
As example:
• Structural elements rely on Passive Fire Protection Systems to ensure they meet
Survivability criteria
• Fire & Gas systems rely on Emergency Power (UPS) to ensure they provide
protection during power outage or ESD
• Electrical ignition prevention is a system relied upon by others to ensure that safe
operation is continued in potential flammable atmospheres.
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 27 of 41
Performance Standard Format
When reviewing the performance standards as part of the HSE Case acceptance process
PETRONAS CARIGALI does not dictate which format the performance standards are to be
presented in but it shall be demonstrated that each of the above criteria have been
addressed through a systematic process.
The following example demonstrates a template for a performance standard for operations
phase, the template shows suggested layout not content.
Performance Standards Review
Review of performance standards shall be periodically carried out. The purpose to:
Incorporate new learnings from the Drilling Contractors organization and other
industry developments
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 28 of 41
Consider if they are still suitable as required by operator or the regulations, if
bound by country of operations regulatory requirements.
To ensure the effectiveness of the reviews mixed teams of Offshore & Onshore personnel
should be used.
The Performance Standards shall also be reviewed when operating parameters on the
installation change, e.g. additional wells bringing more hydrocarbons or sour gas or
modifications as in additional POB through further accommodation etc. Further Guidance
on review is detailed in Section 6.
Swiss Cheese Model
As outlined in the Risk Management Section of this guideline PETRONAS CARIGALI refer
within their Risk Management Process to the Swiss Cheese Model the Swiss Cheese
Model is one of the most acknowledged barrier models. The model builds on the
principles of “defenses in depth” with a set of successive protection layers (barriers)
preventing hazards from being realized and causing accidents to happen.
The Swiss Cheese Model illustrates an event sequence in which barriers are presented in
cheese slices the holes in each slice represent weakened barriers either caused by active
or latent failures:
Active Failures are caused by people (unsafe actions) or technology and have a
direct influence on the accident causation, examples can be failure to operate a
BOP in case of a well kick or a fire damper that fails to close when activated
Latent Failures are defects or flaws in the system which indirectly allows an
accident scenario’s to develop. One example could be incorrect line-up of valves
e.g. a maintenance task which at a later stage may cause flow of hydrocarbons to
undesired locations.
Throughout the lifetime of a rig, holes in this model are expected to constantly move and
change sizes depending on the type operation, asset management, external
environments etc. For a major accident to happen, holes in the Swiss Cheese Model need
to align allowing for an “accident trajectory.” The strength of the Swiss Cheese Model is
how it exemplifies and promotes the following strategy for management;
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 29 of 41
Each barrier should either prevent hazards from being realized or escalation of the
event
If one barrier fails, the subsequent barrier comes into play
Barriers should, as far as possible, be independent of each other
Barriers should be in place to reduce the risk to tolerable levels
No single failure should be able to cause a major accident
“Holes” i.e. degradation in barrier performance should be as small and few as
possible
For this strategy to be successful, barrier needs to be managed in a way which ensures
that they perform as intended at all times. This includes a comprehensive and common
understanding from design and throughout operations of what constitutes barriers to
hazards, and how barriers are verified, monitored and maintained.
Part 5 Rig Emergency Response
The objective of Section 5 is to demonstrate that emergency response arrangements for
the rig have been systematically assessed and suitable arrangements in place to respond
to all credible emergency situations to cover the following criteria:
Emergency Response Management
Command & Communication
Training/Drills for emergencies
Muster Station/Temporary Refuge (TR) arrangements
Details of evacuation and escape equipment, including details of Escape Routes and
Escape Times
Means of Recovery to Place of Safety.
PETRONAS CARIGALI shall review this section against the IADC Guidelines although the
Drilling Contractor shall ensure that this section is further developed into a rig specific
Emergency Response Plan to ensure alignment with current operations.
The Training, Exercise & Drills Plan shall be reviewed and further developed to ensure all
current credible emergency scenarios are covered and addressed in the plan.
PETRONAS CARIGALI shall ensure that Client and Third Party roles, responsibilities and
expectations are clearly defined in the Bridging Document. (See section 11.0 Bridging
Requirements)
Part 6 Performance Monitoring
Section 6 of the Rig HSE Case shall describe the systems and procedures in place to
ensure that all the Safety Critical Elements identified in section 4 are effectively
implemented and the effectiveness and integrity of those elements are maintained for the
life span of the rig.
AS per the IADC Guideline monitoring shall address the following:
Periodic Monitoring
Audit & Compliance
Verification of HSE Critical Activities/Tasks and Equipment/Systems
Periodic Monitoring:
The Rig HSE Case shall demonstrate that arrangements are in place for monitoring the
HSE management of major and other workplace hazards on a daily basis.
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 30 of 41
It shall clearly detail:
Roles and Responsibilities for monitoring compliance with daily procedures and
standards
References to the program of daily work place inspections including the Behavioral
Based Safety Observation Program in use on the rig.
Further development and document the performance standards related to HSE
Critical Activities/Tasks and Equipment/Systems
Proactive performance measures related to other workplace hazards i.e. Hazard
Hunts, Stop Work Drills etc.
Reactive performance measures, incident investigation and management reviews
(See section 10.0 Incident Investigation)
How performance monitoring is measured to ensure trends are captured and
improvements made,
When reviewing this section against the IADC Guidelines PETRONAS CARIGALI shall
ensure that the following is clearly addressed and documented:
Each line manager and supervisor responsibility for monitoring the compliance with
HSE Procedures & Standards
Details of all workplace inspection schemes
Details of the Leading HSE Performance indicators
Details of how the analysis of HSE Performance is documented
Details on the arrangements for discussing, communicating and reviewing the HSE
Performance at each level of the contractor’s organization.
Audit & Compliance
It shall be demonstrated that arrangements are in place for auditing of the HSE
Management Systems Policies and Procedures that address major hazards and other
workplace hazards.
PETRONAS CARIGALI requires the following to be detailed within this section:
A documented audit program covering all areas of the rig and operation
Details of the responsible persons identified for auditing the HSE Management
Systems, Policies and Procedures
Details of the arrangements in place for follow up of findings and the close out of
actions.
Details of how audit findings are communicated to senior management and to
those audited.
Verification of HSE Critical Activities/Tasks and Equipment/Systems
It shall be demonstrated the arrangements in place for verifying HSE Critical
Activities/Tasks and Equipment/Systems developed as per Section 4
It shall ensure that:
All HSE Critical Activities/Tasks and Equipment/Systems have been identified
That suitable arrangements are in place for verifying the effectiveness HSE Critical
Activities/Tasks and Equipment/Systems against the established Performance
Standards (See Section 4 Risk Management)
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 31 of 41
That Details of the verification process for assessment of the effectiveness of all
HSE Critical Activities/Tasks and Equipment/Systems against the established
Performance Standards (Third Party)
PETRONAS CARIGALI shall review this section against the IADC Guidelines, depending on
the scope of the rig contract an HSE Critical Activities/Tasks and Equipment/Systems
verification audit against the documented Bowtie diagrams shall be performed either prior
to commencement of operations or as soon as possible following commencement. This
may be performed internally with PETRONAS CARIGALI HSE Technical personnel or
through the use of Third Party Consultants.
4.0 Remedial Action Plan
As detailed in section 4.7 of the IADC HSE Case Guidelines it may be necessary to develop
a Remedial Action Plan to document and track actions arising from Risk Management
process, allocation of resources and nominated persons to ensure all barriers are
established prior to the potential of the MAH Risk at the rig.
PETRONAS CARIGALI requires the Remedial Action Plan to be documented as an additional
section 7 or additional appendix to the Rig HSE Case to allow a complete assessment
of the Rig HSE Case to be performed.
Once the Rig HSE Case has been accepted as suitable by PETRONAS CARIGALI the
Remedial Action Plan shall remain a live document to ensure all actions are tracked to
closure and any additional issues arising through operational requirements, major
design change or through result of incident investigation are included for tracking and
closure.
5.0 Rig HSE Case Review
Once the Rig HSE Case has been accepted by PETRONAS CARIGALI it shall be subject to
the criteria and arrangements for review and update.
PETRONAS CARIGALI require the HSE Case review to be performed for:
Changes in operation that significantly change the overall risk
Significant changes to manning levels or organizational structure
Significant Changes to the Drilling Contractors management System referenced in
the case
Significant lessons learned from incidents
If operating in a country subject to HSE Case regulatory requirements, any
changes in legislation/regulatory requirements
Expiry of specified Drilling Contractor specified review intervals
5 years has passed without formal review of the HSE case.
6.0 PETRONAS CARIGALI HSE Case Assessment Process
The following section outlines the review and acceptance process performed by
PETRONAS CARIGALI in order to accept the Rig HSE Case as suitable for the intended
operations.
As per the PETRONAS CARIGALI Rig Acceptance Procedure (If not submitted as part of
Tendering Process) the Rig HSE Case shall be submitted to PETRONAS CARIGALI a
minimum of 3 weeks prior to commencing operations to allow the HSE Case to go
through the 4 stages of review and acceptance.
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 32 of 41
Stage 1:
Submittal by the Drilling Contractor of the Rig HSE Case and official notification of
receipt by PETRONAS CARIGALI.
Stage 2:
Initial screening of the Rig HSE Case by PETRONAS CARIGALI Upstream HSE Operations,
this screening is an initial reading of the case not an assessment, to ascertain if the HSE
Case is generally fit for purpose and meets the IADC & PETRONAS CARIGALI
requirements and contains sufficient information to allow a full assessment to be
performed.
Where there is obvious insufficient information the Rig HSE Case will be returned to the
Drilling Contractor with the opportunity to make required improvements and resubmit.
Stage 2 will normally be completed within 5 days of receipt.
A Rig HSE Case that does not meet the basic requirements of IADC requirements shall
not progress to stage 3.
Stage 3:
A detailed technical assessment of the Rig HSE Case is undertaken by a designated
assessment team or individual. This assessment will involve a number of discussions and
areas for clarification with the Rig Contractor and requests for information until such time
that the assessment team or person are confident the HSE Case is acceptable.
The objectives of stage 3 are to:
Identify, clarify and prioritize issues which need to be clarified or resolved
Discuss and resolve the above issues with Rig Contractor
Reach formal agreement on required improvements
Reach a decision on whether to accept the HSE case or not
Where an HSE Case is rejected provide reasons of justification.
The assessment of the Rig HSE Case shall be done in accordance with the latest
revision of the IADC HSE Case Guideline and additional PETRONAS CARIGALI
requirements as outlined in this guide. Stage 3 assessment shall normally be completed
within 10 – 15 days.
Stage 4:
Formal acceptance of the Rig HSE Case as acceptable for the continued operation. This
may also include any gaps or outstanding items required for tracking and closure.
Any actions required to be closed will be included in the Remedial Action Plan (See Section
4) of the HSE Case with assigned targets and action parties for closure.
It is essential that the Rig HSE Case is maintained as a live document and kept
up to date to ensure that the information and risks of exposure are current.
The HSE case should form part of any consultation before any major
modifications are undertaken and form part of any incident review process to
ensure barriers referenced remain effective.
Management of Change (MOC) is one of the most important elements supporting
major accident prevention throughout the lifecycle of the rigs activities. Poor
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 33 of 41
identification of the hazards and risks exposed by change leads to improper
management of change and leads to the potential for major incidents.
7.0 Operationalization of the Rig HSE Case
Once the Rig HSE Case has been accepted as suitable by PETRONAS CARIGALI the Drilling
Contractor (If not already demonstrated) shall produce a documented implementation
plan to effectively roll out and communicate the HSE Case at the rig site.
The operationalization of the Rig HSE Case should be focused on operation requirements
as in what is required to be done now to manage all MAH rather than what has been done
previously.
The implementation plan shall as minimum cover the following areas:
Roll out and communication of the Rig HSE Case to all personnel at site.
Two levels of training on the HSE case, basic familiarization for all personnel and
technical training for management, supervisors and those with HSE Critical tasks.
Visibility and use of the Rig HSE Case.
Verification of the controls/barriers documented in the Bowtie’s
Sustainability on how the implementation and use will be sustained for the duration
of the rigs operation.
PETRONAS CARIGALI shall ensure that all PETRONAS CARIGALI Rig Management and
Supervisors, as well as relevant Third Party Rig Contractors attend the appropriate level of
training and familiarization into the Rig HSE case.
The Rig Drilling Supervisor in consultation with the Rig OIM shall track the progress of
the implementation plan and highlight any areas of concern to the Drilling
Superintendent for follow up with the Drilling Contractor.
Each Drilling Contactor shall ensure a systematic process is implemented to assess and
verify all documented barriers and SCE within each MAH Bowtie the purpose being to
ensure each barrier is actually in place, each SCE has the detailed performance
standard and HSE Critical Tasks/Activities have been assigned to maintain each barrier.
All personnel shall be made aware of their HSE critical tasks and activities. This should be
in the form of training and works shops as well as publication of associated safety critical
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 34 of 41
tasks lists and booklets for ease of use covering all levels of the rig organization including
third party the following stages should be addressed:
To ensure all personnel fully understand their HSE Critical Tasks, Frequency of task and
the performance standard it should be put in a simplified tabled format and distributed to
each relevant personnel in documented or booklet format.
Example of Safety Critical Listings
Rig Superintendent
Safety Critical Task Threat / Consequence Control Process Sirius
Reference H-01.02.01 Shallow Gas / Hydrocarbon gas release
Bridging document – Maersk involved in planning
T: Failure by well planners to act on survey information
WCM 12.02.09
Competency & training of personnel C: Cratering below spud cans
Competency & training of personnel C: Ignited release without conductor
Competency & training of personnel in diverting procedures
C: Ignited release with conductor
Consultation with Client Well Construction team
T: Failure by well planners to act on survey information
WCM 3.01
Drilling location moved T: Lack of precaution for identified shallow gas
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 35 of 41
Pre spud meeting will ensure the problem is communicated
T: Failure to communicate the information WCM 3.01
Required by Well Control Manual Procedures
T: Failure to carry out seismic survey / Failure to identify presence of shallow gas
WCM 7.02.1
Well program is approved and distributed
T: Failure to communicate the information WCM 3.01
H-01.02.02 Hydrocarbons in Formation during Drilling / Blowout at drill floor
Full redundancy in accordance with API RP53 requirements
T: BOP failure / Well control system failure WCM
Originals parts manufacturer or approved vendors
T: BOP failure / Well control system failure Models: Maintenance and repair
Trained & competent personnel T: Well control procedure failed whilst drilling with BOP
Training matrix: Trained & competent personnel + OJT
T: BOP failure / Well control system failure
H-01.02.03 Hydrocarbons in Formation during Coiled Tubing Work / Hydrocarbon release / blowout
Effective well planning process T: Well control procedure failure
Trained & competent personnel T: Well control procedure failure
Well program is accepted as per the bridging document
T: Inappropriate well plan WCM 12
Mud Logger
Safety Critical Task Threat / Consequence Control Process Sirius
Reference H-01.02.02 Hydrocarbons in Formation during Drilling / Blowout at drill floor
Kick identification procedures T: Well control procedure failure whilst drilling with BOP
WCM 5
Mud monitored – calibrated balance T: Incorrect hydrostatic pressure / Well control procedure failure whilst drilling with BOP
WCM 9
Monitoring of flow and pit volumes and drilling parameters
T: Unforeseen abnormal formation pressures / Well control procedure failure whilst drilling with BOP
WCM 9
H-01.02.03 Hydrocarbons in Formation during Coiled Tubing Work / Hydrocarbon release / blowout
Kick identification procedures T: Well control procedure failure with BOP WCM 5
Mud monitored – calibrated balance T: Incorrect hydrostatic pressure / Well control procedure failure
WCM 9
Monitoring of flow and pit volumes and drilling parameters
T: Unforeseen abnormal formation pressures / Well control procedure failure
WCM 9
Mud loggers sampling means T: Unexpected H2S encountered – not identified as present in drilling program / Release of H2S gas during drilling operations
Maintenance & calibration of logging equipment records maintained on rig
T: Mud loggers equipment failure or error/ Release of H2S gas during drilling operations
(Example Courtesy of Maersk Convincer)
8.0 Barrier Monitoring
It is crucial in managing major accident risk to capture early warnings of deterioration of
the barriers and the effectiveness of other systems in place. These warning signs can be
used to implement measures to improve the barriers or to adjust the activity level and
operations in accordance with the deteriorated barrier performance.
With reference to section 3.0 (Swiss Cheese Model) this early warning means to identify
the condition or the status of the barrier; where the holes are and how big they are. When
identified the holes can be fixed or the activity level can be adjusted so the hazard does
not penetrate a hole.
To ensure that barrier effectiveness is monitored the Drilling Contactor shall ensure that:
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 36 of 41
Information relevant for assessing the status of a barrier is identified
A process to evaluate and communicate the status is in place
Purpose and use of information about barrier status is identified related to
planning, operating and maintaining the MODU.
When establishing a monitoring system, a recommended approach is to map already
available information in existing reporting monitoring system(s) and evaluate how this can
be utilized directly or be made available with a minimum of modifications.
9.0 Visual & Practicable Use
It is critical that all levels of Company & Rig personnel understand the purpose and use of
the Rig HSE Case this is achieved by visibility of use at inductions, meetings and daily
planning.
If implemented effectively the Rig HSE Case is an indispensable tool for communicating
hazards and making all personnel aware of their interactions with the critical equipment
that manages them.
A basic introduction into the purpose and use of the Rig HSE Case shall be included in
the rig induction process for all personnel arriving at rig site this shall ensure that all
personnel arriving on the rig are aware of:
What are the MAH on the rig
Where the MAH may occur
The key management provisions/barriers they should be aware of
Each relevant Bowtie and associated HSE Critical Tasks shall be adapted for ease of use
and understanding by the rig crew. This should include visual display of the Bowtie’s at
the relevant work areas or listing of the critical barriers for verification and documented
listing of HSE Critical Tasks to be performed on a daily, weekly or monthly basis
depending on the phase of operation.
The Rig HSE Case shall be utilized when performing any High Level Risk Assessment
process to ensure no barriers are being compromised or if so then sufficient mitigation has
been implemented to ensure the risk remains at tolerable levels.
Any modifications or deviations from the Rig HSE Case shall be managed through the
Management of Change process with the appropriate level of management approvals.
To ensure the HSE Case remains a live document any required changes through
verification or actual use of the HSE Case shall be managed through the Remedial
Action Plan (See Section 4) and all required changes or modifications shall have an
assigned action party, closure date and justification for the change.
10.0 Incident Investigation
Following any High Potential Incident or Major Event the HSE Case shall form part of the
Terms of Reference for the resulting incident investigation the aim being to:
Review the barriers and controls in place
Ascertain if the barriers and controls where actually in place
Ascertain if the barriers and controls where maintained and in good state of repair
Ascertain if any barriers or controls where compromised
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 37 of 41
Ascertain if additional barriers or controls are required.
Following the incident investigation any recommended actions or revisions to the Rig HSE
Case shall be communicated to the appropriate level of management for change and
tracked to closure through the remedial action plan. Although any required immediate
preventative actions out with the HSE case requirements shall be implemented
immediately through the MOC Process.
11.0 Bridging Document
It is understood that not all specific aspects and associated risks of a project or operation
envelope can be effectively controlled and managed through the Rig HSE Case. Thus it is
imperative that the Bridging document is prepared and accepted by all Parties to align and
coordinate the response of both PETRONAS CARIGALI and the Drilling Contractor with
particular attention to alignment of emergency response procedures and responsibilities.
The Bridging Document is similarly a live document as is the Rig HSE Case and shall be
effectively put into operation and use as per section 9.0 of this document to ensure all
personnel are fully aware of their accountability and responsibilities.
Any identified additional MAH and Barriers due to further operations not already
assessed as part of the Rig HSE Case shall be subject to assessment using the RAM as
prescribed in section 4.0
12.0 Simultaneous Operations
When introducing further hazards not already assessed as part of the Rig HSE Case,
through required Simultaneous Operations PETRONAS CARIGALI shall ensure a hazard
assessment/risk assessment is performed to address any additional hazards not already
addressed as part of the rig HSE Case. This shall be further developed into the specific
Simultaneous Operations Procedure (SISO) this procedure shall:
Identify Management System Interfaces including responsibilities
Clarify the procedures to be followed and interface arrangements
Define the Boundaries of responsibility
The Drilling Contractor should be included in the risk assessment process and consultation
on development of the SISO Procedure/Document.
13.0 Rig HSE Case Review Check List
The following is a brief self-checklist to review the Rig HSE Case against to ensure it
meets the basic IADC Rig HSE Case requirements prior to submitting to PETRONAS
CARIGALI for acceptance or for use during periodic reviews.
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 38 of 41
Full Rig HSE Case with constituent and cross referenced sections:
Section Description Interrelationship
Part 1: Introduction
Provision of overview of both rig and Company along with agreed ownership for the HSE Case. Further summarizes the management inputs and requirements for the HSE Case along with continuous improvement. Provides statement for of justification for continued operations.
Provides introduction for all HSE Case Sections and sets out main purpose, goals and objectives.
Part 2:
HSE Management Systems
Describes the Company HSE management
system and sets out the expectations and its delivery through structure, responsibilities, training, competence, plans, systems, standards, procedures and safe work systems. Provides detail on assurance and verification
through measures, audit and compliance.
This section interacts with
parts 4, 5 and 6. Information is shared with regard to competencies, responsibilities, procedures, standards, SCA/SCE barriers
and overall hazard and contingency management aspects.
Part 3:
Rig Description
Describes the layout, equipment, and control systems of the rig, in particular those systems
that are critical to safety and the prevention, identification, control or mitigation of major hazards and risks.
Interacts with sections 4 and 5 with regard to layouts,
SCE’s and rig functions and section 2 with lifesaving and firefighting layouts.
Part 4:
Risk
Management
Describes the overall risk management arrangements in place that have been
identified, assessed through the relevant RAM
process demonstrating a high level or hazard management and TOLERABLE Risk standing for the rig.
Provides input to sections 2 and 5 with regard to the
hazard profile, its
management and emergency response function requirements. Provides input to section 3 with regard to SCE functionality, layout
considerations and design / change hazard management
Part 5: Emergency Response
Describes the arrangements for emergency response management, including plans, training, and arrangements for communication, and how these are tested during drills and
exercises.
Provides input to sections 2 and 4 on emergency functions during possible MAH events and recovery to
ALARP status. Provides input into section 3
with regard to EER functions, layout and equipment
Part 6:
Performance Monitoring
Describes the arrangements for monitoring key
risk management measures to ensure they are implemented, maintained, and remain effective. Key performance monitoring activities include active and reactive monitoring.
Provides input to all sections
with regard to continuous improvement and assurance processes in place to maintain justification for continued operation maintain all risks to TOLERABLE
levels.
Part 7 or Appendix: Remedial
Action Plan (PETRONAS
CARIGALI requirement)
Provides detail on any actions arising from the development of the HSE Case process for remedial work or aimed towards future
continuous improvement.
Provides an active process of closure and improvement for the HSE Case as a whole
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 39 of 41
The Completed Cycle of the Rig HSE Case:
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 40 of 41
14.0 Appendix 1 - Typical SCE Barrier Diagram
Rig HSE Case Guideline (MODU)
WELLS/WHSE/MNL/RIG
HSE GUIDELINES/2015/REV 1
March 2015
Page 41 of 41
15.0 References
No. Reference
1 Health Safety & Environmental Case Guidelines for Mobile Offshore Drilling Units, IADC January 2015
2 Assurance & Verification Practitioners Guide, Step Change in Safety
3 UK HSE Guide To The Offshore Installations (Safety Case) Regulations 2005
4 IADC Appendix 1 to Health, Safety and Environment Case Guidelines for
Offshore Drilling Contractors
5 IADC Drilling Manual
6 Aqua Marine Driller HSE Case Manual 2013 (Vantage Drilling Company)
7 Maersk Convincer Rig HSE Case 2013 (Maersk Drilling Company)
8 Effective Management Of Safety Critical Elements, Stena Drilling Practical Lessons
9 UK HSE Assessment Principles for Offshore Safety Cases (APOSC) 2006
10 Technical Standards for HSE Case EP-HSE-02-12 (Rev 1)