Revised Shasta Temperature Management Plan Overview June 2015

Upload: others

Post on 25-Sep-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Revised Shasta Temperature Management Plan Overvie...shasta dam 1045' upper gates 1000' tcd side gates 720' tcd wt 5643 cfs spp wu o cfs spillway & outlets a 68-70 66-68 a 64-66 062-64

Revised Shasta Temperature Management Plan Overview

June 2015

Page 2: Revised Shasta Temperature Management Plan Overvie...shasta dam 1045' upper gates 1000' tcd side gates 720' tcd wt 5643 cfs spp wu o cfs spillway & outlets a 68-70 66-68 a 64-66 062-64

1.46 maf

Page 3: Revised Shasta Temperature Management Plan Overvie...shasta dam 1045' upper gates 1000' tcd side gates 720' tcd wt 5643 cfs spp wu o cfs spillway & outlets a 68-70 66-68 a 64-66 062-64
Page 4: Revised Shasta Temperature Management Plan Overvie...shasta dam 1045' upper gates 1000' tcd side gates 720' tcd wt 5643 cfs spp wu o cfs spillway & outlets a 68-70 66-68 a 64-66 062-64
Page 5: Revised Shasta Temperature Management Plan Overvie...shasta dam 1045' upper gates 1000' tcd side gates 720' tcd wt 5643 cfs spp wu o cfs spillway & outlets a 68-70 66-68 a 64-66 062-64

Shasta Temperature Control Device

Page 6: Revised Shasta Temperature Management Plan Overvie...shasta dam 1045' upper gates 1000' tcd side gates 720' tcd wt 5643 cfs spp wu o cfs spillway & outlets a 68-70 66-68 a 64-66 062-64

Beta Version Shasta TCD Dashboard

Page 7: Revised Shasta Temperature Management Plan Overvie...shasta dam 1045' upper gates 1000' tcd side gates 720' tcd wt 5643 cfs spp wu o cfs spillway & outlets a 68-70 66-68 a 64-66 062-64

Shasta TCD Configuration 2015 vs. 2015

Page 8: Revised Shasta Temperature Management Plan Overvie...shasta dam 1045' upper gates 1000' tcd side gates 720' tcd wt 5643 cfs spp wu o cfs spillway & outlets a 68-70 66-68 a 64-66 062-64

Temperature Gage Locations

KWK SAC

CCR

Page 9: Revised Shasta Temperature Management Plan Overvie...shasta dam 1045' upper gates 1000' tcd side gates 720' tcd wt 5643 cfs spp wu o cfs spillway & outlets a 68-70 66-68 a 64-66 062-64

Revised Plan Elements • Target as close to 57°F as possible at CCR • Closely monitor real-time temperatures near the

Highway 44 bridge (SAC) • Allowing short-term exceedances above 58°F at

CCR to conserve cold water • Set base flow at 7,250 cfs for June & July • Delay full side-gate operation as long as possible • Establish a Real-time Operations Team

Page 10: Revised Shasta Temperature Management Plan Overvie...shasta dam 1045' upper gates 1000' tcd side gates 720' tcd wt 5643 cfs spp wu o cfs spillway & outlets a 68-70 66-68 a 64-66 062-64

Revised Plan Elements Base Keswick Flows

2015 Flow (cfs) June 7,250 July 7,250 August 7,250 September 6,500 October 5,000

Flows subject to adjustment by the Real-Time Operations Team based on plan performance in June and July.

Page 11: Revised Shasta Temperature Management Plan Overvie...shasta dam 1045' upper gates 1000' tcd side gates 720' tcd wt 5643 cfs spp wu o cfs spillway & outlets a 68-70 66-68 a 64-66 062-64

3 Month Temperature Outlook Shasta Dam

Page 12: Revised Shasta Temperature Management Plan Overvie...shasta dam 1045' upper gates 1000' tcd side gates 720' tcd wt 5643 cfs spp wu o cfs spillway & outlets a 68-70 66-68 a 64-66 062-64

Generic Temperature Trace Sacramento River 10% L3MTO

Full Side Gate

Page 13: Revised Shasta Temperature Management Plan Overvie...shasta dam 1045' upper gates 1000' tcd side gates 720' tcd wt 5643 cfs spp wu o cfs spillway & outlets a 68-70 66-68 a 64-66 062-64

Additional Actions • New temperature gage site (SAC) • Deploy additional temperature sensors • Increased redds and river monitoring • Tracking report of temperature exposure • More intense real-time decision making • Increased capacity at LSNF Hatchery to

accommodate up to 400 adults • Model review effort for future refinements