revised project report_group11
TRANSCRIPT
8/8/2019 Revised Project Report_Group11
http://slidepdf.com/reader/full/revised-project-reportgroup11 1/23
Industrial Energy Systems
Linköping Universitet,
SE-581 85 Linköping, Sweden
24th
May, 2010
Steel Drawing Mill Energy Audit
GROUP MEMBERS:
Mesfin Taye
Wisdom Kanda
S jit V G k j
8/8/2019 Revised Project Report_Group11
http://slidepdf.com/reader/full/revised-project-reportgroup11 2/23
Table of Contents
1.0
Introduction ................................................................................................................................
1
1.1 Company description .............................................................................................................. 1
1.2 Objective ................................................................................................................................. 1
1.3 Limitation ................................................................................................................................ 2
2.0
Method .......................................................................................................................................
2
3.0 Results ......................................................................................................................................... 2
3.1 Energy Survey .......................................................................................................................... 2
3.2 Energy Savings......................................................................................................................... 5
3.2.1 Energy saving potential in various unit processes. ......................................................... 5
4.0 Discussions and Conclusion ........................................................................................................ 8
5.0 References .................................................................................................................................. 9
6.0 Appendix....................................................................................................................................9
8/8/2019 Revised Project Report_Group11
http://slidepdf.com/reader/full/revised-project-reportgroup11 3/23
Summary The steel and iron industry is a very important part of the national development and structure.
It has been in existence for aver 2000 years and has evolved to become a high-quality steel
producer through several challenges such as energy intensive consumption.
In addition the consumption of energy does not come lone in the form of direct cost but also
has some added issues relating to the environment such as CO2 emissions. Energy cost make
up for a sizable amount of the running cost of the steel industry. This cost can be controlled
through energy audits to identify and implement possible energy saving measures.
This project presents the energy audit at cold drawn steel mill located in Linköping. It has an
annual steel production of about 50000 ton. The products of this company are delivered
primarily to the Swedish engineering industry whiles other exports go to Nordic countries,
Germany, the UK and the Benelux.
After performing the energy analysis with the help of ENSAM it was clear to identify the
various unit processes and the amount of energy they consumed. This depicted areas of the
processes with high consumption and as targets for energy consumption reduction.
The results show that from an initial annual energy consumption of 3800MWh/y of electricity
with a corresponding cost of 660650€/y it is possible to reduce the consumption and cost.
Energy efficiency measures such as changing of mercury lamps to T5’s and the shutting
down completely on production machines on idle can save several amounts of energy.
The energy savings as can be seen for electricity is 546MWh/y and with the cost of
electricity at 0.063 €/kWh (Europe's Energy portal) there is the potential saving of about
35000 €/year. Looking at other options there in some energy content in the exhaust air which
can be recovered to further reduce the annual oil demand for space heating.With the
employment of a heat excahnger with an efficiency of 75% the oil saving potential is
688MWh/y with an annual cost savings of about 31000€/year with the oil cost of 44€/MWh
provided in the invoice.
The total potential energy savings is 1234MWh/y which represents about 21% reduction. In
terms of cost the total cost savings is about 66000€/year which represent about 9%
8/8/2019 Revised Project Report_Group11
http://slidepdf.com/reader/full/revised-project-reportgroup11 4/23
1.0 Introduction History has it that steel and iron making in Sweden dates back over two thousand years. Iron
and steel making has been interwoven into the lives of the people to such an extent that it
played a key role in the country’s development. Huge amounts of natural resource reserves
coupled with the forest fuel supply have been very favourable for this Industry in the early
era which played a key role in the development of the country.
Yet the steel manufacturing sector has been faced by challenges in the past which threatened
its existence. In 1976 it was hit hardly by the energy crises. As a consequence of the energy
crises, the ship industry which was a major customer of the steel sector also went down in
production which had a rippling effect on their supply networks. Measures were implemented
to counter these challenges; finally by 1998 the industry was again well known
internationally as a high quality steel producer.
1.1 Company description The company under study is a cold drawn steel mill located in Linköping. It has an annual
steel production of about 50000 ton. The products of this company are delivered primarily to
the Swedish engineering industry whiles other exports go to Nordic countries, Germany, the
UK and the Benelux. The employees are 80 in number. The company production is organised
in campaigns of three weeks with production during 16 days. The production is closed during
midsummer and Christmas as well as during a four week holiday in summer. Office hours for
employees in 9 hours a day while production runs for 16 hours per day from Monday to
Friday1.
Many processes are needed to produce the final product. The raw material is first treated in
the drawing benches where it is pushed and drawn. In then goes into the straightening
machine after which it is ready for profile cutting. In the end it is cut to the specified length
and end machining is done.
As can be understood from the above description the different processes needed to run this
industry are energy intensive. In addition the related energy cost associated with this
processes form a significant part of the company cost. This cost is liable to minimization
through effective energy measures which can only be pointed out through energy audits.
8/8/2019 Revised Project Report_Group11
http://slidepdf.com/reader/full/revised-project-reportgroup11 5/23
1.3 Limitation The analysis is based on measured data provided as the starting point and further informationis also sourced from the energy manager which is supplemented by some assumptions to
make the process complete.
2.0 Method The method is to adopt a top-down approach in which the unit process concept is also
incorporated. The processes at the steel mill were categorised as either production or support
and then the available data is then apportioned as to the respective process consumption.
The software for energy audit ENSAM was used to determine the possible energy savings
after quantification of unit process consumption.
3.0 Results 3.1 Energy Survey Table 1.0 Steel drawing mill in numbers
Steel drawing mill
Number of employees 80
Production days 255 days/y (3 weeks each of 16 days and closed
for 4 weeks and during Christmas break)
Office hours 9 hours/day from Monday‐Friday* = 2295h/y
Production hours 16 hours/day from Mon‐Fri*=4080h/y
Annual Production(output) 50000ton
Electricity Use 3800 MWh/yr
Oil use 2128 MWh/y
*Energy manager Information
The only sources of energy employed in this company are electricity and oil. The annual cost
8/8/2019 Revised Project Report_Group11
http://slidepdf.com/reader/full/revised-project-reportgroup11 6/23
The energy distribution among the various unit processes is displayed in Figure 1.0 below.
Make reference to the appendix for a detailed presentation of calculation.
EI
Oil
Micsellaneous
Support
Processes
Production
Processes
LIghting
Ventilation
Compressed air
Space heating
Moulding
3800
2128
521
213
494
20
2128
1720
1248
1720
832
8/8/2019 Revised Project Report_Group11
http://slidepdf.com/reader/full/revised-project-reportgroup11 7/23
From the Figure 1.0 above it can clearly be seen that lighting consumes the largest portion of electricity in the support processes (521MWh/year). There exists numerous numbers of lamps
in the mill with no specified mode of control or dimming to reduce energy consumption.
According to information provided by the energy manager most of these lamps in the
production and storage area are mercury lamps thus this unit process holds a high potential
for energy savings.
The case for compressed air usage is no different it consumes 40% (Figure 2.0) of theelectricity supplied. This is not so surprising because from the data provided by the energy
audit it is on power throughout the period of measurement.
Ventilation also runs 24 hours and for 7days a week through the year but it consumes quite a
low percentage of electrical energy due to its low power demand.
Though the production processes are few they have higher electricity consumption than thesupport processes. This may be attributed to the higher energy consumption per unit.
8/8/2019 Revised Project Report_Group11
http://slidepdf.com/reader/full/revised-project-reportgroup11 8/23
3.2 Energy Savings Energy consumption forms a major part of the operating cost of a steel manufacturingprocess. From the view of profits making minimised energy consumptions means savings
cost and also raising annual income. We have identified some salient processes where energy
savings can be done.
3.2.1 Energy saving potential in various unit processes. Lighting
The source of lighting employed in the production and storage rooms consumed so muchpower (400W) . Reasonable measures are to change the lamp types to energy saving lamps
such as T5. Sensors could also be installed to detect the presence of employees and thus deem
or shut off the light source accordingly. With this change the annual electricity use for
lighting reduced from 521MWh/y to 369MWh/y with similar values for light intensity in the
storage, production and office rooms.
Measure Decreaseddemand(kW) Decreased time (h/y) Energysavings(MWh/y)
25 5997 152
Ventilation
In the case of the ventilation system there is no heat exchanger to take advantage of the hot
exhaust air temperature. If the exhaust air temperature is used there could be considerable
savings in oil cost for space heating. Use ventilation system only during production or office
hours and natural ventilation at night instead of running the system all the time. The potential
saving by this time reduction (20%) could save 43MWh/y (EnSAM).
Compressed air
The measures to save energy from compressor are reducing the load and discharge pressure
to reduce the air leakages, performing effective maintenance to the components, using less
compressed air for the unit processes and controlling the operating time as well as running
the equipment under lower pressure conditions. If possible, replace the compressed air driven
tools with electrical ones. The annual electricity demand for the compressor will be decreased
from 494 to MWh/year.
8/8/2019 Revised Project Report_Group11
http://slidepdf.com/reader/full/revised-project-reportgroup11 9/23
Space heating
Decreasing the heat loss by transmission and ventilation through the building envelope would
be useful. The exhaust air also has some energy content which could be heat exchanged for
space heating. The heat lost through ventilation is 890MWh/y. With the idea to employ to
employ a heat exchanger with 75% efficiency there is a savings potential of 668MWh/y to
save replace some demands for oil.
Production unit processes and others
Improved performance of equipments and energy efficiency can save some amount of energy
in the production processes. Controlling the operating time could be very important herebecause shutting down machines completely instead of leaving them on standby or idle could
save huge amounts of energy. The combined potential of shutting down completely all this
machines is about 87MWh/y of energy (Refer to appendix for detail calculations).
Measure Unit Energy
Savings(MWh/y)
Shut off machine
During non
production hours
Drawing bench 43
Triple straightening
machine
1.2
Levelling machine 10.6
Bulk Throwing
machine
32.4
Total 87
8/8/2019 Revised Project Report_Group11
http://slidepdf.com/reader/full/revised-project-reportgroup11 10/23
Table 3.0 Energy consumption before and after energy savings improvements
Energy demand
(MWh/y) Energy
demand
(MWh/y)*
Support
processes
Electricity Oil Electricity Oil
Lighting 521 369
Ventilation 213 170
Compressed
air
494 230
Space heating 20 2128 20 1440
sum 1248 2128 789 1440
Production
Processes
Drawing
bench
655 612
Triple
straightening
machine
355 354
Levelling
machine
163 152
Bulk
Throwing
machine
54754
547
515
Sum
1720 1633 1440
Others 832 0 832 0
8/8/2019 Revised Project Report_Group11
http://slidepdf.com/reader/full/revised-project-reportgroup11 11/23
4.0 Discussions and Conclusion The
steel
industry
is
an
energy
intensive
sector
with
energy
cost
contributing
a high
percentage
of total company cost. In addition to this direct cost, there are also other hidden costs such as
for pollution caused by the intensive use of energy. Therefore energy consumption should be
given particular attention and measures employed to reduce the amount consumed.
In order for a possible reduction in energy consumption to be done there is the need to identify
the various unit processes and their corresponding energy consumption. Then the power
consumption over
time
gives
energy
which
then
can
be
analysed
to
see
possible
means
to
achieve some savings. As a measure to improve accuracy it is advisable that the one doing the
measurements continues to carry on with the energy audit or analysis. When one is presented
with only the data without a direct involvement in how the data was obtained makes it difficult
for the analysis to go on smoothly and leads to several assumptions which could be erroneous.
Obvious conclusions we can draw from this energy audit is that the company does not really
have monitor
on
their
production
equipment
typically
in
instances
of
running
idle
whiles
consuming energy. Having a strict schedule to shut down completely all machines operating on
idle could save amounts of energy as already discussed in the energy saving measures for
production processes. Other simple aids such as the use of sensors and also a consideration of
load management could be useful. The energy source used for space heating could be costly
looking at the current oil prices. This could be changed to bio fuels which are renewable with
reduced environmental impacts.
The energy savings as can be seen for electricity is 546MWh/y and with the cost of electricity at
0.063 €/kWh (Europe's Energy portal) there is the potential saving of about 35000 €/year.
Looking at other options there in some energy content in the exhaust air which can be
recovered to further reduce the annual oil demand for space heating.With the employment of a
heat excahnger with an efficiency of 75% the oil saving potential is 688MWh/y with an annual
cost
savings
of
about
31000€/year
with
the
oil
cost
of
44€/MWh
provided
in
the
invoice.
The total potential energy savings is 1234MWh/y which represents about 21% reduction. In
terms of cost the total cost savings is about 66000€/year which represent about 9% percentage
reduction.
8/8/2019 Revised Project Report_Group11
http://slidepdf.com/reader/full/revised-project-reportgroup11 12/23
5.0 References 1. Aktiebolaget Svenska Teknologföreningens Förlag. Iron and Steel in Sweden. 2004.
http://runeberg.org/steelswe/. access April 17th, 2010
2. http://www.energy.eu/#industrial access April 29th,2010‐04‐29
3. Table of U‐values. Conservation of fuel and power.
http://www.officecomfort.co.uk/AppendixA_UValues.pdf. access April 26th2009
8/8/2019 Revised Project Report_Group11
http://slidepdf.com/reader/full/revised-project-reportgroup11 13/23
10
Support processes 6.0 Appendix
Lighting
Facility Number of
lamps
Actual
Power
(W)use/lamp
Operative
hours(h/yr)
Energy
demand(MWh/yr)
Storage 108 425 * 6120*** 281
Production 90 425 6120
24×255**
234
Office 20 140 2295 6
Total 521
*According to extra information provided by the energy manager the storage and production use mercury lamps while the office uses normal fluorescent
lamps. And from factors used in ENSAM the actual power demand for a mercury and fluorescent lamp are 425W and 70W respectively.
** The production is organized in campaigns of three weeks with production during 16 days. The production is closed during Midsummer and Christmas as
well during a four‐week holiday in summer [(52/3×16)‐((4×5) +2)] = 255days.
***Light is
on
throughout
the
day
during
production
days.
8/8/2019 Revised Project Report_Group11
http://slidepdf.com/reader/full/revised-project-reportgroup11 14/23
11
Ventilation
Production and
Storage
Electrical
power
demand
(kW)
Operating
hours(h/y)
Energy
demand(MWh/y)
Supply fan 6.5 8760*** 57
Exhaust fan 4.5 8760 39
Office fan
5.6*
8760
49
Total Energy =
145
AIR CURTAIN
AIR CURTAIN 1 AIR CURTAIN 2
Electrical
power(kW)
Operative
hours(h/y)
Energy
demand(MWh/y)
Electrical
power(kW)
Operative
hours(h/y)
Energy
demand(MWh/y)
Total Energy
demand(MWh/y)
Production 31.97 624.24 19.95 Production 32.42 1458.80 47.61
Off 0 8135.76 0 Off 0 7301.2 0
19.95 47.61
8/8/2019 Revised Project Report_Group11
http://slidepdf.com/reader/full/revised-project-reportgroup11 15/23
12
Assumption***: Ventilation
is
on
throughout
the
year.
*Average power consumption for office fan from energy survey data.
Compressed air
*Operative time
is
the
number
of
hours
the
machine
is
on
within
255
production
days
(16h/day×255days/year).
Compressor
is
on
throughout
production
hours.
3 All total energy consumption values have been rounded to the nearest integer.
Total Energy 683
Compressor power use(kW) Operation time(h/y) Energy demand(MWh/y)
Production 56.33477 4080* 230
Non Production
56.33477
4680
264
Total Energy consumption 494
8/8/2019 Revised Project Report_Group11
http://slidepdf.com/reader/full/revised-project-reportgroup11 16/23
13
SPACE HEATING
Storage
and
Production
Unit U-
value(W/m2K)*
A (m2) UA(W/K)
Wall 0.245 6238.98 1528.55
Floor 2.7 11852.78 32002.53
Window 2.7 750** 2025
Roof 1.067 11852.78 12646.93
∑=48203.01
Tin 18.88**
T*out(oC) TJan = -
2.9
TFeb= -
3.0
TMar= -
0.1
TApril =
5.3
TMay=
11.0
TJune=
15.4
TJuly=
17.7
TAug=
16.4
TSep=
12.2
TOct=
7.1
TNov=
2.7
TDec=
0
Q=UA(Tin-
Tout)
(Watts)
1.049 1.054 0.911 0.654 0.379 0.167 0.057 0.119 0.320 0.568 0.779 0.910
Degree
hours
107459
Energy UA × Degree hours 5180MWh
*From table of U-values
**Energy Manager Information
8/8/2019 Revised Project Report_Group11
http://slidepdf.com/reader/full/revised-project-reportgroup11 17/23
14
Unit U-
value(W/m2K)
*
A (m2) UA
Wall 0.245 244.96 60.0150
Floor 2.7 1488.21 4018.17
Window 2.7 27.22* 130.656
Roof 1.067 1488.21 1587.920
∑=5796.76
Tin(°C) 22**
T*out(°C) TJan = -2.9 TFeb= -
3.0
TMar= -
0.1
TApril =
5.3
TMay=
11.0
TJune=
15.4
TJuly=
17.7
TAug=
16.4
TSep=
12.2
TOct=
7.1
TNov=
2.7
TDec=
0
Q=UA(Tin-Tout)(Watts)
0.1443 0.1449 0.1280 0.0970 0.064 0.038 0.025 0.032 0.057 0.086 0.112 0.127
Degree
hours
107840
Demand
*Average monthly temperature for Linköping
Office
8/8/2019 Revised Project Report_Group11
http://slidepdf.com/reader/full/revised-project-reportgroup11 18/23
15
Energy
Demand
UA × Degree hours 625MWh
Aero tempers [Electricity]
Number Power (W) Operative hours (h/y) Energy demand (MWh)
8 200×8 3480* 6
Pump
in
heating
system
[electricity]
*According to the measurement data provided for the year 2005, there is no heating in the months of May till September. So we have taken out the
total number of week days between May till September (which is equal to 110 days) from the total working day over the year (i.e., 255 days) and
multiplied it with 24 hours. [((255‐110)*24) =3480]
Pump power demand(kW) Operation time(h/y) Energy demand(MWh/y)
4 3480 * 14
*Average monthly temperature for Linköping
** Asumption
8/8/2019 Revised Project Report_Group11
http://slidepdf.com/reader/full/revised-project-reportgroup11 19/23
16
Q ventilation
Q ventilation = air flow rate (m
3
/s) ×density of air (kg/m3) × specific heat capacity of air (kJ/kg.K) × (Troom -Toutside) (K)
Density of air at room temperature (20°C) =1.205 and the specific heat capacity = 1.005 (kJ/kg.K) (The engineering toolbox, 2010)
Toutdoor is the average outdoor temperature for Linkoping
Air flow of supply fans = 5+4.3=9.3(m
3
/s)
Storage and Production
Air flow
rate(m3/s)
9.3
Density of
air(kg/m3)
1.205
Specific heat
capacity of air
(kJ/kg.K)
1.005
Troom 18.88
Toutdoor4 TJan = - TFeb= - TMar= - TApril = TMay= TJune= TJuly= TAug= TSep= TOct= TNov= TDec=
4 Average outdoor temperature for Linkoping was sourced from tutorial material for Building Energy systems
8/8/2019 Revised Project Report_Group11
http://slidepdf.com/reader/full/revised-project-reportgroup11 20/23
17
2.9 3.0 0.1 5.3 11.0 15.4 17.7 16.4 12.2 7.1 2.7 0
Qventilation(kW) 179.97 178.85 211.51 152.95 88.74 39.19 13.29 27.93 75.23 132.67 182.23 212.64
Hours 744 672 744 720 744 720 744 744 720 744 720 744
Energy Supplied 133.89 120.19 157.36 110.12 0 0 0 0 0 78.71 131.21 158.20
Total Energy 890MWh
Total energy suppled
for space heating Oil
(MWh/y)
Total electricity
supplied for space
heating by electricity
(MWh/y)
2128* 20
*Energy audit information
8/8/2019 Revised Project Report_Group11
http://slidepdf.com/reader/full/revised-project-reportgroup11 21/23
18
Production processes
Moulding
DRAWING BENCHES
DRAWING BENCH 1 DRAWING BENCH 2
Electrical
power(kW)
Operative
hours(h/y)
Energy
demand(MWh/y)
Electrical
power(kW)
Operative
hours(h/y)
Energy
demand(MWh/y)
Total Energy
demand(MWh/y)
Production 48.1899 5220.36 251.57 Production 156.0695 2313.36 361.04
Idle 5.28 899.64 4.75 Idle 10.70 3531.24 37.78
Off 0 2640 0 Off 0 2915.4 0
256.32 398.82
Total Energy 655
8/8/2019 Revised Project Report_Group11
http://slidepdf.com/reader/full/revised-project-reportgroup11 22/23
19
TRIPLE STRAIGHTENING MACHINE
Electrical power(kW) Operative hours(h/y) Energy demand(MWh/y)
Production 133.33 2656.08 354.14
Idle 4.59 281.94 1.20
Off 0 5821.98 0
Total Energy 355
LEVELING BENCH
Electrical power (kW) Operating hours(h/y) Energy demand(MWh/y)
Production 75.50 2019.60 152.49
Idle 2.65 3837.24 10.16
Off 0 2903.16 0
Total Energy 163