revised 1/2012 alabama department of transportation … › conweb › pdf › road › c-25.pdf ·...
TRANSCRIPT
![Page 1: Revised 1/2012 ALABAMA DEPARTMENT OF TRANSPORTATION … › conweb › pdf › Road › C-25.pdf · Project Number: Sun Mon Tue Wed Thu Fri Sat Day Week Ending (Sat): Date ... deficiency](https://reader036.vdocuments.us/reader036/viewer/2022081611/5f0d83e87e708231d43abdd2/html5/thumbnails/1.jpg)
Form C-25 Revised 1/2012 ALABAMA DEPARTMENT OF TRANSPORTATION Sheet ___ of ___ DAILY INSPECTION OF TRAFFIC CONTROL DEVICES
Project Number: Sun Mon Tue Wed Thu Fri Sat Day Week Ending (Sat):
Date
County: Time Contractor:
if Night Insp
TRAFFIC CONTROL DEVICE(S) and LOCATION
TCD CONDITION “” denotes device properly maintained.
“X” denotes devices NOT properly maintained. REMARKS
Must be completed for “X” condition to describe type of deficiency (sheeting damaged, light not working, etc.).
DATE CORRECTED
Project Traffic Control Inspector Reviewed by: Project Manager
![Page 2: Revised 1/2012 ALABAMA DEPARTMENT OF TRANSPORTATION … › conweb › pdf › Road › C-25.pdf · Project Number: Sun Mon Tue Wed Thu Fri Sat Day Week Ending (Sat): Date ... deficiency](https://reader036.vdocuments.us/reader036/viewer/2022081611/5f0d83e87e708231d43abdd2/html5/thumbnails/2.jpg)
Form C-25 Revised 1/2012 ALABAMA DEPARTMENT OF TRANSPORTATION Sheet ___ of ___ DAILY INSPECTION OF TRAFFIC CONTROL DEVICES (Continuation)
Project Number: Sun Mon Tue Wed Thu Fri Sat Day Week Ending (Sat):
Date
County: Time Contractor:
if Night Insp
TRAFFIC CONTROL DEVICE(S) and LOCATION
TCD CONDITION “” denotes device properly maintained.
“X” denotes devices NOT properly maintained. REMARKS
Must be completed for “X” condition to describe type of deficiency (sheeting damaged, light not working, etc.).
DATE CORRECTED
![Page 3: Revised 1/2012 ALABAMA DEPARTMENT OF TRANSPORTATION … › conweb › pdf › Road › C-25.pdf · Project Number: Sun Mon Tue Wed Thu Fri Sat Day Week Ending (Sat): Date ... deficiency](https://reader036.vdocuments.us/reader036/viewer/2022081611/5f0d83e87e708231d43abdd2/html5/thumbnails/3.jpg)
Form C-25 Revised 1/2012 ALABAMA DEPARTMENT OF TRANSPORTATION Sheet ___ of ___ DAILY INSPECTION OF TRAFFIC CONTROL DEVICES (Continuation)
Project Number: Sun Mon Tue Wed Thu Fri Sat Day Week Ending (Sat):
Date
County: Time Contractor:
if Night Insp
TRAFFIC CONTROL DEVICE(S) and LOCATION
TCD CONDITION “” denotes device properly maintained.
“X” denotes devices NOT properly maintained. REMARKS
Must be completed for “X” condition to describe type of deficiency (sheeting damaged, light not working, etc.).
DATE CORRECTED
![Page 4: Revised 1/2012 ALABAMA DEPARTMENT OF TRANSPORTATION … › conweb › pdf › Road › C-25.pdf · Project Number: Sun Mon Tue Wed Thu Fri Sat Day Week Ending (Sat): Date ... deficiency](https://reader036.vdocuments.us/reader036/viewer/2022081611/5f0d83e87e708231d43abdd2/html5/thumbnails/4.jpg)
Form C-25 Revised 1/2012 ALABAMA DEPARTMENT OF TRANSPORTATION Sheet ___ of ___ DAILY INSPECTION OF TRAFFIC CONTROL DEVICES (Continuation)
Project Number: Sun Mon Tue Wed Thu Fri Sat Day Week Ending (Sat):
Date
County: Time Contractor:
if Night Insp
TRAFFIC CONTROL DEVICE(S) and LOCATION
TCD CONDITION “” denotes device properly maintained.
“X” denotes devices NOT properly maintained. REMARKS
Must be completed for “X” condition to describe type of deficiency (sheeting damaged, light not working, etc.).
DATE CORRECTED
![Page 5: Revised 1/2012 ALABAMA DEPARTMENT OF TRANSPORTATION … › conweb › pdf › Road › C-25.pdf · Project Number: Sun Mon Tue Wed Thu Fri Sat Day Week Ending (Sat): Date ... deficiency](https://reader036.vdocuments.us/reader036/viewer/2022081611/5f0d83e87e708231d43abdd2/html5/thumbnails/5.jpg)
Form C-25 Revised 1/2012 ALABAMA DEPARTMENT OF TRANSPORTATION Sheet ___ of ___ DAILY INSPECTION OF TRAFFIC CONTROL DEVICES (Continuation)
Project Number: Sun Mon Tue Wed Thu Fri Sat Day Week Ending (Sat):
Date
County: Time Contractor:
if Night Insp
TRAFFIC CONTROL DEVICE(S) and LOCATION
TCD CONDITION “” denotes device properly maintained.
“X” denotes devices NOT properly maintained. REMARKS
Must be completed for “X” condition to describe type of deficiency (sheeting damaged, light not working, etc.).
DATE CORRECTED
![Page 6: Revised 1/2012 ALABAMA DEPARTMENT OF TRANSPORTATION … › conweb › pdf › Road › C-25.pdf · Project Number: Sun Mon Tue Wed Thu Fri Sat Day Week Ending (Sat): Date ... deficiency](https://reader036.vdocuments.us/reader036/viewer/2022081611/5f0d83e87e708231d43abdd2/html5/thumbnails/6.jpg)
Form C-25 Revised 1/2012 ALABAMA DEPARTMENT OF TRANSPORTATION Sheet ___ of ___ DAILY INSPECTION OF TRAFFIC CONTROL DEVICES (Continuation)
Project Number: Sun Mon Tue Wed Thu Fri Sat Day Week Ending (Sat):
Date
County: Time Contractor:
if Night Insp
TRAFFIC CONTROL DEVICE(S) and LOCATION
TCD CONDITION “” denotes device properly maintained.
“X” denotes devices NOT properly maintained. REMARKS
Must be completed for “X” condition to describe type of deficiency (sheeting damaged, light not working, etc.).
DATE CORRECTED