reverse flow project on the trans balkan corridor...reverse flow project on the trans balkan...

16
Reverse Flow Project on the Trans Balkan Corridor Implementation of the Reverse Flow Project on the Trans Balkan corridor CESEC – 8 October 2019, Bruxelles

Upload: others

Post on 16-Jul-2020

22 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Reverse Flow Project on the Trans Balkan Corridor...Reverse Flow Project on the Trans Balkan Corridor Implementation of the Reverse Flow Project on the Trans Balkan corridor CESEC

Reverse Flow Project on theTrans Balkan Corridor

Implementation of the Reverse Flow Project on the Trans Balkancorridor

CESEC – 8 October 2019, Bruxelles

Page 2: Reverse Flow Project on the Trans Balkan Corridor...Reverse Flow Project on the Trans Balkan Corridor Implementation of the Reverse Flow Project on the Trans Balkan corridor CESEC

2

Trans Balkan Corridor – Greek section

Reference document: Concept paper on ensuring bidirectional flows on the Trans Balkan Corridor;

Scope: Offering the firm capacity of 46.535.000 kWh/day (1,5 bcm/y / 4,1 mil. cm./day) on the Transbalkan

pipeline until the end of 2019 (Option 1 of the Concept Paper);

Status on the Greek-Bulgarian border: firm capacity of 46.535.000 kWh/d (or 4,1 mil. Nm3/d) is already available at the I.P. Kulata/Sidirokastro in the

direction from GR to BG. In the period Jan-Aug 2019, delivery of 352.151.314 Nm3 (0,35 bcm) was made at the above IP from GR to

BG, out of which 4.121.380 Nm3 (0,004 bcm) in physical reverse flow.

Page 3: Reverse Flow Project on the Trans Balkan Corridor...Reverse Flow Project on the Trans Balkan Corridor Implementation of the Reverse Flow Project on the Trans Balkan corridor CESEC

Bulgartransgaz EAD Trans Balkan reverse flow project

State of play

08 October 2019 / Brussels, BelgiumCESEC Gas Plenary

Page 4: Reverse Flow Project on the Trans Balkan Corridor...Reverse Flow Project on the Trans Balkan Corridor Implementation of the Reverse Flow Project on the Trans Balkan corridor CESEC

Progress of Trans-Balkan Pipeline reverse flow

Signed Interconnection Agreementfor IP Kulata/Sidirocastro

4,100 mcm/d firm capacity at IPKulata/Sidirocastro (entry) from01.04.2019

0,500 mcm/d additional interruptiblecapacity from 01.04.2019

IP Kulata/Sidirokastro

AIMED RESULT: COST-EFFICIENT AND EXPEDIENT FULL UTILIZATION OF BI-DIRECTIONAL CAPACITY

Page 5: Reverse Flow Project on the Trans Balkan Corridor...Reverse Flow Project on the Trans Balkan Corridor Implementation of the Reverse Flow Project on the Trans Balkan corridor CESEC

Progress of Trans-Balkan Pipeline reverse flow

Amendment 4 of existing IA for IP Negru Voda 1/Kardamfinalized in May 2019

Technical improvements at GMS Negru Voda 1 by Transgazare required to sign Amendment 4

4,100 mcm/d firm capacity at IP Negru Voda 1/Kardam (exit)after completion of technical improvements

Public consultation on the Business rules to the draft IA forIP Negru Voda 2,3/Kardam was held in the period11.06.2019 - 11.07.2019

Conclusion of the IA for Negru Voda 2,3/ Kardam isforthcoming in the near future

IP Negru Voda/Kardam

AIMED RESULT: COST-EFFICIENT AND EXPEDIENT FULL UTILIZATION OF BI-

DIRECTIONAL CAPACITY

Page 6: Reverse Flow Project on the Trans Balkan Corridor...Reverse Flow Project on the Trans Balkan Corridor Implementation of the Reverse Flow Project on the Trans Balkan corridor CESEC

Thank you for your attention!

Yasen Ivanov, Head of Analysis and International Activities Division

[email protected]

[email protected]

Page 7: Reverse Flow Project on the Trans Balkan Corridor...Reverse Flow Project on the Trans Balkan Corridor Implementation of the Reverse Flow Project on the Trans Balkan corridor CESEC

Reverse Flow Project on theTrans Balkan Corridor

Implementation of the Reverse Flow Project on the Trans Balkancorridor

CESEC – 8 October 2019, Bruxelles

Page 8: Reverse Flow Project on the Trans Balkan Corridor...Reverse Flow Project on the Trans Balkan Corridor Implementation of the Reverse Flow Project on the Trans Balkan corridor CESEC

8

Trans Balkan corridor T1 – Romanian section

Implementation of the Reverse Flow Project on the Trans Balkan Corridor

Page 9: Reverse Flow Project on the Trans Balkan Corridor...Reverse Flow Project on the Trans Balkan Corridor Implementation of the Reverse Flow Project on the Trans Balkan corridor CESEC

9

Trans Balkan Corridor T1 – Romanian section

Implementation of the Reverse Flow Project on the Trans Balkan Corridor

Reference document: Concept paper on ensuring bidirectional flows on the Trans Balkan Corridor;

Scope: Offering the firm capacity of 46.535.000 kWh/day (1,5 bcm/y / 4,1 mil. cm./day) on the T1 pipeline until the end of 2019 (Option 1 of the Concept Paper);

Status of the negotiations of the Interconnection Agreements (IA) with adjacent TSOs: JSC Ukrtransgaz:

Delivery pressure (RO-UA) in IP Isaccea 1 was agreed as follows: Minimum: 35 barg; Maximum: 45 barg;

Transgaz completed the works necessary for bi-directional gas metering in the RO-UA direction in the current GMS Isaccea 1; Upgrading GMS Isaccea 1: it is estimated that the execution contract will be signed until the half of October 2019, the completion deadline is

30.09.2020; Addendum no. 9 to IA for IP Isaccea 1 is being agreed upon:

Technical aspects to be discussed: Selection of the commercial gas metering station for metering gas quantity and quality until the upgrading of GMS Isaccea 1 is

completed; Gas quality requirements in case of deliveries from Romania to Ukraine;

Setting the technical capacity of IP Isaccea 1 Exit: all the technical parameters of the IA in the RO-UA direction have to be agreed;

Page 10: Reverse Flow Project on the Trans Balkan Corridor...Reverse Flow Project on the Trans Balkan Corridor Implementation of the Reverse Flow Project on the Trans Balkan corridor CESEC

10

Trans Balkan Corridor T1 – Romanian section

Implementation of the Reverse Flow Project on the Trans Balkan Corridor

Bulgartransgaz EAD: Delivery pressure (BG-RO) in IP Negru Vodă 1/Kardam was agreed as follows:

Minimum: 46 barg; Maximum: 48 barg;

Transgaz completed the works necessary for bi-directional gas metering in the BG-RO direction in the current GMS Negru Vodă 1; Addendum no. 4 to IA for IP Negru Vodă 1/Kardam was signed by Transgaz and sent to Bulgartransgaz to be signed; Setting the technical capacity of IP Negru Vodă 1/Kardam Entry: by the Joint Method for the Calculation of the technical capacity of IP NegruVodă 1/Kardam, which is being amended;

Capacity allocation: Bidirectional capacity allocation at the IP in the South – North direction will be possible as soon as the national regulatory framework has been amended

by the introduction of the capacity allocation mechanism related to reverse flow, as follows: At IP Negru Vodă 1/Kardam Entry: RBP auction; At IP Isaccea 1 Exit: implicitly at the level of the maximum capacity of 1.5 bcm/year, from the capacity allocated at IP Negru Vodă 1/Kardam Entry;

Applicable tariffs: The tariffs are approved by ANRE Order no. 64/2019 and are available at: http://www.transgaz.ro/en/transmission-tariffs-2019-2020;

Page 11: Reverse Flow Project on the Trans Balkan Corridor...Reverse Flow Project on the Trans Balkan Corridor Implementation of the Reverse Flow Project on the Trans Balkan corridor CESEC

11

Trans Balkan Corridor T2,3 – Romanian section

Implementation of the Reverse Flow Project on the Trans Balkan Corridor

Reference document: Concept paper on ensuring bidirectional flows on the Trans Balkan Corridor

Purpose: Ensuring the complete physical bidirectional flow on T1 and T2,3 (Option 3);

Scope: Information on the possibility to ensure bidirectional gas flow on T2,3:

Transgaz is currently analyzing the technical solutions to ensure bidirectional gas transmission

In addition to ensuring the technical conditions for bidirectional gas flow it is also compulsory for the following prerequisite to be fulfilled:

Conclusion of Interconnection Agreements with adjacent TSOs; Amendment of the legacy contract for gas transmission, related to the T3 pipeline, concluded with Gazprom Export;

Page 12: Reverse Flow Project on the Trans Balkan Corridor...Reverse Flow Project on the Trans Balkan Corridor Implementation of the Reverse Flow Project on the Trans Balkan corridor CESEC

www.transgaz.ro

Page 13: Reverse Flow Project on the Trans Balkan Corridor...Reverse Flow Project on the Trans Balkan Corridor Implementation of the Reverse Flow Project on the Trans Balkan corridor CESEC

Trans-Balkan reverse flowinitiative implementation.State-of-play

Page 14: Reverse Flow Project on the Trans Balkan Corridor...Reverse Flow Project on the Trans Balkan Corridor Implementation of the Reverse Flow Project on the Trans Balkan corridor CESEC

Actions doneUnbundling ongoing – to be finished by 1 Jan 2020

Ukrainian government approved on 18 Sep 2019 the Resolution determining the final model of unbundling and the procedures to be finished by EOY. Action plan withclear steps and deadlines for all participants of UA natural gas market was approved. Most importantly for implementation of the EU business rules – the companyresponsible for submission of certification request and the party of interconnection agreements is determined – TSO LLC

Interconnection Agreements prepared – to be signed

Amendment for Interconnection Agreement between Ukrainian and Romanian TSOs prepared but not yet signed.The first draft of Interconnection Agreement between Ukrainian and Moldavian TSOs for IP Oleksiivka is prepared and is currently discussed by the TSOs.

Reconstructions on UA and MD facilities

Ukrainian TSO will finalize the reconstructions to enable reverse flow metering on GMS Grebenyky by end of October 2019.Moldavian TSO is also expected to finalize the reconstruction of GMS Kaushany by EOY.

Capacity allocation

In accordance with Ukrainian Network code, quarterly and monthly capacities of interconnection points, in particular new interconnection import point from Romania,are allocated in December 2019 – 30 calendar days before the beginning of the period for which capacity is allocated.

Page 15: Reverse Flow Project on the Trans Balkan Corridor...Reverse Flow Project on the Trans Balkan Corridor Implementation of the Reverse Flow Project on the Trans Balkan corridor CESEC

Pending issues and problems to be urgently solvedReconstruction of GMS Isaccea-1

Amendment to Interconnection Agreement between Ukrainian and Romanian TSOs are not yet signed. Moreover, there is no update from Romanian side about theongoing process and no information about commissioning date of new ultrasonic GMS Isaccea-1, which hinders the initiative as such.To our best knowledge, Romanian TSO started reconstruction of existing GMS, but we are not officially informed thereon.

Determination of the commercial metering station for IPs Orlovka-Isaccea 2-3 and IP Tekovo

For continued transportation of natural gas between Ukraine and Romania for all interconnection points it is necessary to sign Interconnection Agreements betweenUkrainian and Romanian TSOs. The main remaining unsolved issue is determination of commercial gas metering stations to be used from 1 January 2020. This alsothreatens the reverse flows on IPs Orlovka-Isaccea 2-3.

Capacity auctions from RO side for reverse flows

Romanian TSO did not auction annual capacity of IP Isaccea-1 in July 2019. On 4 November 2019 quarterly capacities shall be allocated. Moreover, the RomanianTSO informed that there will be no firm capacities in direction to Ukraine due to their obligation to provide firm capacities to Bulgaria, which hinders the reverse flowpossibility

Synchronization of quality parameters of natural gas

In case of transportation of natural gas from Romania to Ukraine there is a need to align quality parameters, prescribed by legislation of Romania and Ukraine. Theissue is not yet solved and hinders physical transportation of gas from Romania to Ukraine

Transportation of natural gas via Moldova

There are existing risks of continued transportation of natural gas between Ukraine and Moldova, as well as transportation of gas through Transnistria due touncertain legal status of Tiraspoltransgas and unbundling of TSOs in Moldova.

Page 16: Reverse Flow Project on the Trans Balkan Corridor...Reverse Flow Project on the Trans Balkan Corridor Implementation of the Reverse Flow Project on the Trans Balkan corridor CESEC

16

Thank you for your attention!