retrofitting scrubber and lng technologies to … prizas 2012/marchain workshop 2012_2.pdf–...
TRANSCRIPT
Finalised-DBAB205397Doc.ID: Revision: Status:29/ © Wärtsilä
RETROFITTING SCRUBBER AND LNGTECHNOLOGIES TO EXISTING SHIPS
PASI PAJULA, WÄRTSILÄ FINLAND -ENVIRONMENTAL SOLUTIONSMARCHAIN GREEN PROPULSION WORKSHOP 2012, KLAIPEDA,
LITHUANIA
13 december 2012 / Marchain workshop Pasi Pajula
Wärtsilä Environmental SolutionsA new organization part of Ship Power
Ballast WaterManagement SystemsJoe Thomas, Director
Exhaust Gas CleaningSigurd Jenssen,
Director
RetrofitLeonardo Sonzio,
Director
Water and Inert GasSystems
Geir Hellum, Director
Three product Business Units:
• R&D and technical management• Manufacturing operations• Product sales to new builds• Product delivery management (PM / sales order processing)• After sales
Project Business Unit:
• Project sales• FEED• Project management• Project engineering
Environmental SolutionsJuha Kytöla, VP
Wärtsilä and Hamworthy combined unique strengths
13 december 2012 / Marchain workshop Pasi Pajula
Finalised-DBAB205397Doc.ID: Revision: Status:29 © Wärtsilä/
As of February 2006, IMO SOx Emission Control Areas (SECA) where ships must limit their emissions includes Baltic Sea, North Sea and English Channel: 1% max in 2010 and 0,1% from 2015. Since 2010, EC set a cap of 0,1% sulfur in all EU ports.
USA, Hawaii and CanadaIn March 2009, a proposal was submitted to IMO for a SOx and NOxEmission Control Area.Accepted in March 2010, and it will come effective in August 2012.
• 200 miles from coast.• Fuel Sulphur initially limited to 1%,
then 0.1% from 2015, all ships. • NOX Tier III (Tier I minus 80 %)
in 2016, for all new buildings.
Other ECA currently being discussed:Coasts of Mexico, Coasts of Alaska and Great Lakes, Singapore, Hong Kong, Korea, Australia, Black Sea, Mediterranean Sea (2014), Tokyo Bay (in 2015)
Emission Controlled Areas
13 december 2012 / Marchain workshop Pasi Pajula
Finalised-DBAB205397Doc.ID: Revision: Status:29 © Wärtsilä/
Reduce emissions - What are the options?
Back in the day’sHFO or MDO
Today and in the futureWhat to select?
… and in the end it all boils down to CAPEX-OPEX
MDONOx Tier 3
compliant engine+ Low sulphur fuel
HFOAftertreatment
ScrubbersSCR
GASGas as fuel
13 december 2012 / Marchain workshop Pasi Pajula
Environmental solutions - Exhaust gascleaning products for marine use
Sox emissions ->Wet scrubbers (Open loop, closed loop and hybrid)
Nox emissions -> SCR/NOR catalysators
DF engines
13 december 2012 / Marchain workshop Pasi Pajula
Closed loop scrubber
Closed loop with NaOH
Effluentmonitoring
Alkali feedmodule
Bleed-offtreatment units
Alkali (NaOH) tank, 14 days
autonomy
Sea water heatexchanger
Sea water pump
Scrubber unit
By-pass valves
Emission monitoring
Exhaust gas fan module
Sludge tank
Scrubbing waterpump module
Holding tank(optional)
Freshwater in
13 december 2012 / Marchain workshop Pasi Pajula
Open loop scrubber Engine Exhaust
Gas
Scrubbed Exhaust Gas
Possible plume control
Laser Gas Analyser
HMI Control Cabinet
Water Monitoring
Scrubber Supply pump In port reaction
water pump
Sludge Tank
De-aeration vessel
Optional Return pump Water treatment
Water monitoring
Wash water discharge
Sea waterSea water from scrubberSludgeControl data
Scrubber unit
13 december 2012 / Marchain workshop Pasi Pajula
Alkalinity in the Baltic Sea
• Open sea alkalinity• Surface data (0… 15 m)• Data from 2001-2005
• Typical open sea alcalinity outside Baltic Sea is ca. 2200 – 2400 µmol/L
Sweden
Finland
13 december 2012 / Marchain workshop Pasi Pajula
Scrubber system layout design, closed loop & hybrid
13 december 2012 / Marchain workshop Pasi Pajula
Scrubber system layout design, open loop
13 december 2012 / Marchain workshop Pasi Pajula
CONTAINERSHIPS 7 EGC RETROFITTurn – key reference
• Customer and background– Containerships (Finland)– First Closed Loop commercial project
• Scope of supply– Wärtsilä Closed Loop Scrubber– CEMS*
• “Turn – key” project responsibility– Engineering, procurement, construction– Complete installation: scrubber room prefabrication and installation, equipment container prefabrication and installation, relocation of equipment, piping work, electrical and automation integration, etc…
• Modification to water treatment ongoing (root cause identified, modification tested for 1500 hrs with successful results, final modifications ongoing)
* CEMS = Continous Emission Monitoring System
13 december 2012 / Marchain workshop Pasi Pajula
Containerships VII Scrubber tower lifted onboard
Installed Completion of commissioning: End of 2011
Scrubber system design, general issues to check
Scrubber system selection -> Operating area of the ship
System design, Fuel consumption and dividence between main-/auxiliary engines
Physical constraints for scrubber unit placement
Eg. In case funnel extension -> sightlines from the bridge, navigation light masts, satellite connections, gps, radar…
Physical constraints for scrubber system equipment placement
Tank sizing (desired autonomy) vs. tank availability.
Vessel stability (eg. RoRo´s)
Power reserve (power production and main switchboard spare fuses)
Weight and windsurface area increase effect to vessel equipment no.
Ex-and specific firezones, component placement, penetrations eg, with cables or pipes
Flag administration work safety requirements
Classification society requirements , Additional notations effect
Ie. Comfort class, clean design.13 december 2012 / Marchain workshop Pasi Pajula
TARBIT LNG CONVERSIONTurn – key reference
• Customer and background– Tarbit– Chemical Tanker (Bit Viking)– First LNG conversion ever done– First LNGPac and GVU delivery– 75% of project funded by the Norwegian NOx fund
• Scope of supply– DF conversion of 2xW6L46– Complete LNG system (tanks, piping, gas valve units, inerting system)– Automation upgrade– Fire fighting system upgrade
• “Turn – key” project responsibility– Engineering, procurement, construction– Complete installation: engine conversions, reinforcement of deck, tank installation, piping work, electrical and automation integration, etc…
• Ship successfully sailing since summer 2011
13 december 2012 / Marchain workshop Pasi Pajula
Bit Viking conversion
Bunker stations
LNG tanks
Tank room and aux room
13 december 2012 / Marchain workshop Pasi Pajula
Bit Viking conversion• Pipes• Supports• Insulation• Foundation steelwork• Access gangways• Cabling
13 december 2012 / Marchain workshop Pasi Pajula
Lifting operation at yard• Rented Floating crane as yard
lifting capacity restricted• Weight of empty tank: 220 ton
• 2,3 times the weight of 6L50DF
13 december 2012 / Marchain workshop Pasi Pajula
LNG conversion design, general issues to check
Engine convertibility vs. new engines
Physical constraints for placement of LNG storage tanks vs. desired autonomy
Hull structures below LNG tanks
Pipe routing (double wall piping)
Placement for GVU and other components
Exhaust gas lines –> Rupture disc arrangement
Vessel stability
Weight increase impact on equipment number of the vessel.
Ex-and specific firezones, component placement, penetrations eg, with cables or pipes
Flag administration work safety requirements
Classification society requirements
13 december 2012 / Marchain workshop Pasi Pajula
Finalised-DBAB205397Doc.ID: Revision: Status:29/ © Wärtsilä
Thank You!
13 december 2012 / Marchain workshop Pasi Pajula