restore is mnd draft reva v4

Upload: jonnydavies

Post on 31-May-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/14/2019 restore IS MND Draft revA v4

    1/26

    CONTENTS

    1 CALIFORNIA ENVIRONMENTAL QUALITY ACT PROCESS 3

    1.1 Introduction 31.2 Discretionary Action Subject to CEQA review 3

    1.3 Purpose and Objective 3

    1.4 Approach 3

    2 PROJECT DESCRIPTION 4

    2.1 Background 4

    2.2 Proposed Project Location 4

    2.3 Proposed Project Description 5

    2.4 System Installation 6

    2.5 Project Alternatives Evaluated and Rejected 7

    2.6 Regulatory Approvals and Permit Requirements 8

    3 ENVIRONMENTAL IMPACTS 9

    3.1 Aesthetics 10

    3.2 Agricultural Resources 11

    3.3 Air Quality 12

    3.4 Biological Resources 17

    3.5 Cultural Resources 20

    3.6 Geology and Soils 22

    3.7 Hazards and Hazardous Materials 24

    3.8 Hydrology and Water Quality 26

    3.9 Land Use Planning 29

    3.10 Mineral Resources 31

    3.11 Noise32

    3.12 Impacts 33

    3.13 Population and Housing 343.14 Public Services 35

    3.15 Recreation 36

    3.16 Transportation and Traffic 37

    3.17 Utilities and Service Systems 39

    3.18 Mandatory Findings of Significance 40

  • 8/14/2019 restore IS MND Draft revA v4

    2/26

    4 REFERENCES 43

    4.1 Bibliography 43

    4.2 Persons Consulted 43

    4.3 Document Preparers 43

    FIGURES

    TABLES

    APPENDICES

  • 8/14/2019 restore IS MND Draft revA v4

    3/26

    1 CALIFORNIA ENVIRONMENTAL QUALITY ACT PROCESS

    1.1 INTRODUCTION

    Whenever a public agency undertakes a discretionary action, it must determine whether the action is

    subject to the California Environmental Quality Act (CEQA). A discretionary action is one where a

    governmental agency can use its judgment in deciding whether and how to carry out or approve a project.A project subject to such judgmental controls is called a discretionary project (Title 14. California Code

    of Regulations, Section 15357). If CEQA applies to the project, the agency must evaluate the potential

    effects of the project on the environment.

    An Initial Study provides the Lead Agency with a basis for deciding whether to prepare an Environmental

    Impact Report or a Negative Declaration for a proposed project. The Initial Study process also enables the

    applicant or Lead Agency to modify the project to avoid or reduce adverse impacts, thereby enabling the

    project to qualify for a Negative Declaration. When mitigation measures proposed in the Initial Study are

    incorporated into the project, before the Lead Agencys approval and before circulation to the public, a

    Mitigated Negative Declaration may be adopted by the agency.

    1.2 DISCRETIONARY ACTION SUBJECTTO CEQA REVIEW

    Ohlone College proposes to (1) repair and rehabilitate water damage to campus facilities; and (2) install

    subsurface hydrologic improvements to improve groundwater flow in the subsurface to alleviate flooding

    of campus facilities.

    The proposed repairs to existing facilities and replacement of damaged or non-functioning drainage and

    related structures would not change the function of the facilities, would not create any expansions or

    alterations to the existing uses and, would pose no impact on the environment. Consequently, the

    proposed repairs, replacement and reconstruction activities are exempt from CEQA review by sections

    15301 (Existing Facilities), 15302 (Replacement or Reconstruction) and 15304 (Minor Alterations to

    Land) of Article 19, Categorical Exemptions, of the CEQA guidelines and are not included in the scope of

    this document.

    therefore, the primary focus subject of this document.

  • 8/14/2019 restore IS MND Draft revA v4

    4/26

    2.3 PROPOSED PROJECT DESCRIPTION

    aged by water infiltration and intrusion and replace or repair damaged or non-functioning subsurface

    drainage systems. The repairs are exempt from CEQA review as discusde proposed subsurface hydrologic

    improvements would reduce the potential for groundwater intrusion into the College buildings by routing

    a portion of the groundwater past the buildings that are vulnerable to subsurface water intrusion. Theproposed system would include a northern and southern drain, each consisting of non-perforated and

    perforated pipe segments installed at 80 to 100 feet below grade, and connecting to an infiltration gallery

    to transport groundwater around the campus structures via gravity. The perforated and non-perforated

    drain pipes would most likely be high-density polyethylene (HDPE) of a thickness that can withstand the

    stress of drawing them into placeinstalling them via the horizontal directional drilling (HDD). Alterve

    sufficient rigidity and strength to withstand the pressures at the depth of 80 to 100 feet of theation

    2.

    A horizontal drain consi

    A horizontal drain consi

    2.3.2 Access Ports

  • 8/14/2019 restore IS MND Draft revA v4

    5/26

    2.4.4 Trenching

    2.6 REGULATORY APPROVALSAND PERMIT REQUIREMENTS

    Activities within Agency's

    Jurisdiction

    Agency Action/Requirement

    Ohlone College Board of Trustees Project approval. CEQAcompliance.

    Project approval

    Approval.

    Enforce of air quality plans and

    compliance with CEQA

    Guidelines.

    Plan review and approval

    Review and approval

    Consultation. Compliance with

    State Historic Preservation Act.

  • 8/14/2019 restore IS MND Draft revA v4

    6/26

    3 ENVIRONMENTAL IMPACTS

    Potential Impact(s) Mitigation Measure(s)

    No significant impactswere identified.

    None required

    2. Agriculture

    Resources

    No impacts were identified None required

    3. Air Quality for detailed discussion) No

    other significant impacts

    were identified

    A2.1

    No impacts were identified None required

    5. Cultural Resources No significant impactswere identified.

    None required

    6. Geology / Soils No significant impacts

    were identified.

    None required

    7. Hazards & Hazardous

    MaterialsNo impacts were identified None required

    8. Hydrology and Water

    Quality

    No significant impacts

    were identified.

    None required

    9. Land Use Planning No impacts were

    identified.

    None required

    10. Mineral Resources No impacts were

    identified.

    None required

    11. Noise No significant impacts

    were identified.

    None required

    12. Population / Housing No impacts were

    identified.

    None required

    13. Public Services No impacts were

    identified.

    None required

    14. Recreation No impacts wereidentified.

    None required

    15. Transportation/Traffic No impacts were

    identified.

    None required

    16. Utilities / ServiceSystems

    No impacts wereidentified.

    None required

    17. Mandatory Findings

    of Significance

    No significant impacts

    were identified.

    None required

  • 8/14/2019 restore IS MND Draft revA v4

    7/26

    Less-Than-

    Significant

    with

    Mitigation

    Incorporated

    Less-Than-

    Significant

    Impact No Impact

    2. Substantially damage scenic resources,

    including, but not limited to, trees, rock

    outcroppings, and historic buildings within a

    state scenic highway?

    3. Substantially degrade the existing visual

    character or quality of the site and its

    surroundings?

    4. Create a new source of substantial light or

    glare, which would adversely affect day or

    nighttime views in the area?

    Substantan-Significant Impact.

    Item 4. No Impact.

    3.2 AGRICULTURAL RESOURCES

    Less-Than-

    Significant

    withMitigation

    Incorporated

    Less-Than-Significant

    Impact No Impact

    2. Conflict with existing zoning for agricultural

    use, or a Williamson Act contract?

    3. Involve other changes in the existing

  • 8/14/2019 restore IS MND Draft revA v4

    8/26

    environment which, due to their location or

    nature, could result in conversion of

    Farmland, to non-agricultural use?

    Less-Than-

    Significant

    withMitigation

    Incorporated

    Less-Than-Significant

    Impact No Impact

    2. Violate any air quality standard or contribute

    substantially to an existing or projected air

    quality violation?

    3. Result in a cumulatively considerable net

    increase of any criteria pollutant for which

    the project region is non-attainment under anapplicable federal or state ambient air quality

    standard (including releasing emissionswhich exceed quantitative thresholds for

    ozone precursors)?

    4. Expose sensitive receptors to substantial

    pollutant concentrations?

    5. Create objectionable odors affecting a

    substantial number of people?

    3.3.2 Impacts

    or obst

  • 8/14/2019 restore IS MND Draft revA v4

    9/26

    Violate n-Significant Impact with Mitigation Incorporated.

    PM10 Emissions

    utant of greatest concern with respect to construction activities. There are a number of feasible controlmeasures that can be reasonably implemeedol measures rather than detailed quantification of emissions

    (BAAQMD, 1999, p.14). The BAAQMD has identified a set of feasible PM10 control measures for

    construction activities. The determatQMD CEQA Guidelines (as appropriate, depending on the size of

    the project area) are implemented, then air pollutant emissions from construction activities would be

    considered a less than significant impact (BAAQMD, 1999, p.15). Table 3-2 provides the Basic Control

    Measures (from Table 2 ofhe10

    Applicable to Proposed Project?

    YesCover all trucks hauling soil, sand, and other loose materials or

    require all trucks to maintain at least two feet of freeboard.

    Yes

    Pave, apply water three times daily, or apply (non-toxic) soil

    stabilizers on all unpaved access roads, parking areas and staging

    areas at construction sites.

    NoSite is paved

    Sweep daily (with water sweepers) all paved access roads, parking

    areas and staging areas at construction sites.

    Yes

    Sweep streets daily (with water sweepers) if visible soil material iscarried onto adjacent public streets.

    Yes (however, no visible soil is expected onadjacent streets)

    No. Applicable to construction areas greater

    than 4 acres

    Enclose, cover, water twice daily or apply (non-toxic) soil binders

    to exposed stockpiles (dirt, sand, etc.).

    No. Applicable to construction areas greater

    than 4 acres

    Limit traffic speeds on unpaved roads to 15 mph. No. Applicable to construction areas greater than 4 acresInstall sandbags or other erosion control measures to prevent silt

    runoff to public roadways.

    No. Applicable to construction areas greater

    than 4 acres

    Replant vegetation in disturbed areas as quickly as possible. No. Applicable to construction areas greater

    than 4 acres

    No.Suspend excavation and grading activity when winds

    (instantaneous gusts) exceed 25 mph.

    No.

    Limit the area subject to excavation, grading and other

    construction activity at any one time.

    YesConstruction activities will be

    conducted one pipe segment at a time.

    Implementation of BAAQMD Fa

    x (BAAQMD,1999, p. 16). Table 3-3 compares the total project emissions to these emission thresholds.

  • 8/14/2019 restore IS MND Draft revA v4

    10/26

    Table 3-3. Air Emissions from Construction Operations Compared to BAAQMD CEQA

    Significance Thresholds

    Total Project Operation Emissions BAAQMD Significance Threshold

    (lbs/day)

    3.6 80

    ROG 15 80

    NO 80

    B

    B

    Construction emissions will not reach the significance thresholds established in the BAAQMD CEQA

    Guidelines; thus, the project will not substantially contribute to an existing or projected air quality

    violation. Likewise the project will not violate any air quality standard, as it will be conducted in

    compliance with all applicable BAAQMD regulations, permit conditions and will include appropriate

    controls during construction activities.

    Expose san-Significant Impact with Mitigation.

    nit equipment idling to minimize air emissions.

    MITIGATION MEASURE A2: Stage equipment exhaust away from building air intakes.

    ns.

    Create oan-Significant Impact with Mitigation.

    Stage equipment exhau

    Instruct equipment op

    Less-Than-

    Significant

    with

    Mitigation

    Incorporated

    Less-Than-

    Significant

    Impact No Impact

    2. Have a substantial adverse effect on any

    riparian habitat or other sensitive natural

    community identified in local or regional

  • 8/14/2019 restore IS MND Draft revA v4

    11/26

  • 8/14/2019 restore IS MND Draft revA v4

    12/26

    Have a san-Significant Impact.

    rikirke, listed as an endangered species in California, has been identified as having a potential presence in

    the general vicinity of the proposed project based on available on foode and t been observed on the site ;

    however, the activity footprint would be l imited to an opening with a diameter of 36 inches (Figure 5) andwould be of short duration. While the activity may create a short-term disturbance during installation of

    the drainage pipe, it is not likely to have a significant effect on the avian species, which would avoid the

    small area for a short duration.

    Three additional species (California Red-legged Frog, California Tiger Salamander, and Western Pond

    Turtle) may be foud 100 feet from the Upper Pond and 500 feet from the South Pond and would be of

    short duration, therefore, these activities would not impact these species.s, policies, or regulations or by

    the California Dept. of Fish and Game or U.S. Fish and Wildlife Service. No Impact.

    of Ripa

    Interferct.

    No Impact.

    CiIt is not anticipated that any such classification of tree will be removed during the project. Therefore

    the proposed project would have no impact on such plans or ordinances.

    Conflictct.

    prd therefore it will not conflict with any adopted protection plansa

    Less-Than-

    Significant

    with

    Mitigation

    Incorporated

    Less-Than-

    Significant

    Impact No Impact

    2. Cause a substantial adverse change in the

    significance of an archaeological resourcepursuant to 15064.5?

    3. Directly or indirectly destroy a unique

    paleontological resource or site or unique

    geologic feature?

    4. Disturb any human remains, including thoseinterred outside of formal cemeteries?

  • 8/14/2019 restore IS MND Draft revA v4

    13/26

    nmgle and Colonial Revival styles. This house is on the City of Fremont list of primary historic resources.A "planted alameda" of olive trees (Olive Alley) runs perpendicular from Mission Boulevard eastward to

    and just past the historic structure. These trees are probably roughly contemporaneous with the house and

    thus about 100 years old.

    Although no surface manifestations have been reported, there is evidence that a buried archaeological site

    may exist on Ohlone College property, in an orchard near Mission Boev

    a substantial adverse change in the significance of a historical resource as defined in 15064.5 . Less-

    Than-Significant with Mitigation Incorporated

    ystem (Figure 2). No modifications to the structure aould occur asation.

    MITIGATION MEASURE C1: Obtain approval for trenching in the "planted alameda" historic

    landscape from the State Historic Preservation Officer prior to beginning of construction activities.

    verse ch

    surface, they aresubsurface are unlikely to be found at these depths, therefore the project would not cause

    disturbanc

    f trenchingate

    If archaeological res

    Item 3. Directly or indirectly destroy a unique paleontological resource or site or unique geologic

    feature. No Impact.

    Disturb an-Significant Impact with Mitigation Incorporated.

    f trenching

    If human remains are tact the State Historic Preservation Officer and consult with the BbtaA as

    necessaryprior to

    Less-Than-

    Significant

    with

    Mitigation

    Incorporated

    Less-Than-

    Significant

    Impact No Impact

    i. Rupture of a known earthquake fault, as

  • 8/14/2019 restore IS MND Draft revA v4

    14/26

    delineated on the most recent Alquist-

    Priolo Earthquake Fault Zoning Map

    issued by the State Geologist for the area

    or based on other substantial evidence of

    a known fault? Refer to Division ofMines and Geology Special Publication

    42.ii.Strong seismic ground shaking?

    iii. Seismic-related ground failure, includingliquefaction?

    iv. Landslides?

    2. Result in substantial soil erosion or the loss

    of topsoil?

    3. Be located on a geologic unit or soil that is

    unstable, or that would become unstable as a

    result of the project, and potentially result in

    on- or off-site landslide, lateral spreading,

    subsidence, liquefaction, or collapse?

    4. Be located on expansive soil, as defined inTable 18-1-B of the Uniform Building Code

    (1994), creating substantial risk to life or

    property?

    5. Have soils incapable of adequately

    supporting the use of septic tanks or

    alternative wastewater disposal systems

    where sewers are not available for the

    disposal of waste water?

    3.5.2 Impacts

    3.6 HAZARDSAND HAZARDOUS MATERIALS

    Less-Than-

    Significant

    with

    Mitigation

    Incorporated

    Less-Than-

    Significant

    Impact No Impact

    2. Create a significant hazard to the public or

    the environment through reasonably

  • 8/14/2019 restore IS MND Draft revA v4

    15/26

    foreseeable upset and accident conditions

    involving the release of hazardous materials

    into the environment?

    3. Emit hazardous emissions or handle

    hazardous or acutely hazardous materials,

    substances, or waste within mile of an

    existing or proposed school?

    4. Be located on a site which is included on a

    list of hazardous materials sites compiledpursuant to Government Code Section

    65962.5 and, as a result, would it create a

    significant hazard to the public or the

    environment?

    5. For a project located within an airport land

    use plan or, where such a plan has not been

    adopted, within 2 miles of a public airport or

    public use airport, would the project result ina safety hazard for people residing or

    working in the project area?

    6. For a project within the vicinity of a private

    airstrip, would the project result in a safety

    hazard for people residing or working in the

    project area?

    7. Impair implementation of or physically

    interfere with an adopted emergency

    response plan or emergency evacuation plan?

    8. Expose people or structures to a significant

    risk of loss, injury or death involving

    wildland fires, including where wildlands areadjacent to urbanized areas or where

    residences are intermixed with wildlands?

    Create act

    Create a

    Emit hazct.

    acutely hazardous materials or substances.

  • 8/14/2019 restore IS MND Draft revA v4

    16/26

    Be located No Impact.

    The proposed project would not be located on sited listed pursuant to Government Code Section 65962.5,

    is not within an airport land use plan or within 2 miles of a public airport or public use airport, and is notwithin the vicinity of a private airstrip.

    Expose pct.

    Less-Than-

    Significant

    with

    Mitigation

    Incorporated

    Less-Than-

    Significant

    Impact No Impact

    2. Substantially deplete groundwater supplies or

    interfere substantially with groundwaterrecharge such that there would be a net

    deficit in aquifer volume or a lowering of the

    local groundwater table level (e.g., the

    production rate of pre-existing nearby wells

    would drop to a level which would not

    support existing land uses or planned uses for

    which permits have been granted?

    3. Substantially alter the existing drainagepattern of the site or area, including through

    the alteration of the course of a stream or

    river, or substantially increase the rate or

    amount of surface runoff in a manner which

    would result in erosion and/or sedimentation

    on- or off-site?

    4. Substantially alter the existing drainage

    pattern of the site or area, including through

    the alteration of the course of a stream or

    river, or substantially increase the rate or

    amount of surface runoff in a manner whichwould result in flooding on- or off-site?

    5. Create or contribute runoff water which

    would exceed the capacity of existing orplanned stormwater drainage systems or

    provide substantial additional sources of

    polluted runoff?

    6. Otherwise substantially degrade water

  • 8/14/2019 restore IS MND Draft revA v4

    17/26

    quality?

    7. Place housing within a 100-year flood hazard

    area as mapped on a Federal Flood HazardBoundary or Flood Insurance Rate Map or

    other flood hazard delineation map?

    Groundwater

    3.7.2 Impacts

    ater qualImpact with Mitigation.

    eant practices would be implemented to ensure that construction soil and drilling fluids do not enter

    stormwater conveyances. All drilling fluids would be containerized and recirculated. Soil cuttings would

    be coaiRegional Water Quality Control Board )R(RWQCB) if the construction area were to exceed the

    threshold for notification (1 acre).

    THIS SHOULD BE A MITIGATIONllwould develop and a Storm WaLess-Than-Significant Impact.

    ined to alter the flow pattern of the subsurface water flow so as to reduce the potential infiltration of water

    into the building structures of the College, the resulting change in pattern is not anticipated to have any

    effect outside the boundaries of the College campus. There would be no net increase or decrease in the

    volume of groundwater flowing throughing nearby wells would not experience any decrease inproduction rates.

    Createct

    tormwater drainageewer system.

    Otherwisn-Significant Impact.

    Place ho

  • 8/14/2019 restore IS MND Draft revA v4

    18/26

    Less-Than-

    Significant

    with

    Mitigation

    Incorporated

    Less-Than-

    Significant

    Impact No Impact

    2. Conflict with applicable environmental plan,

    policy, or regulation of an agency with

    jurisdiction over the project (including, but

    not limited to the general plan, specific plan,

    local coastal program, or zoning ordinance)

    adopted for the purpose of avoiding or

    mitigating an environmental effect?

    3. Conflict with any applicable habitat

    conservation plan or natural community

    conservation plan?

    3.8.2 Impacts

    Less-Than-

    Significant

    with

    Mitigation

    Incorporated

    Less-Than-

    Significant

    Impact No Impact

    2. Result in the loss of availability of a locally-important mineral resource recovery site

    delineated on a local general plan, specific

    plan, or other land use plan?

  • 8/14/2019 restore IS MND Draft revA v4

    19/26

    Less-Than-

    Significant

    with

    Mitigation

    Incorporated

    Less-Than-

    Significant

    Impact No Impact

    2. Exposure of persons to or generation ofexcessive groundborne vibration or

    groundborne noise levels?

    3. A substantial permanent increase in ambient

    noise levels in the project vicinity above

    levels existing without the project?

    4. A substantial temporary or periodic increase

    in ambient noise levels in the project vicinity

    above levels existing without the project?

    5. For a project located within an airport land

    use plan or, where such a plan has not been

    adopted, within 2 miles of a public airport orpublic use airport, would the project expose

    people residing or working in the project area

    to excessive noise levels?

    6. For a project within the vicinity of a private

    airstrip, would the project expose people

    residing or working in the project area toexcessive noise levels?

  • 8/14/2019 restore IS MND Draft revA v4

    20/26

    shall be would be implemented where practicable: (1) all construction equipment to be powered by

    internal combustion engines that are properly muffled and maintained; (2) prohibit unnecessary idling of

    internal combustion engines, and (3) selected quiet construction equipment whenever possible.

    (1) all construction equipment powered by internal com

    No Impact.

    Less-Than-Significant

    with

    Mitigation

    Incorporated

    Less-Than-

    Significant

    Impact No Impact

    2. Displace substantial numbers of existing

    housing, necessitating the construction of

    replacement housing elsewhere?

    3. Displace substantial numbers of people,

    necessitating the construction of replacement

    housing elsewhere?

  • 8/14/2019 restore IS MND Draft revA v4

    21/26

    Less-Than-

    Significant

    with

    Mitigation

    Incorporated

    Less-Than-

    Significant

    Impact No Impact

    2. Police protection?

    3. Schools?

    4. Parks?

    5. Other public facilities?

    Schools? Pa

    Less-Than-

    Significantwith

    Mitigation

    Incorporated

    Less-Than-

    Significant

    Impact No Impact

    2. Does the project include recreational

    facilities or require the construction or

    expansion of recreational facilities which

  • 8/14/2019 restore IS MND Draft revA v4

    22/26

    might have an adverse physical effect on the

    environment?

    Would thn Significant Impact.

    Does then Significant Impact.

  • 8/14/2019 restore IS MND Draft revA v4

    23/26

    Less-Than-

    Significant

    with

    Mitigation

    Incorporated

    Less-Than-

    Significant

    Impact No Impact

    2. Exceed, either individually or cumulatively, a

    level of service standard established by the

    county congestion management agency fordesignated road or highways?

    3. Result in a change in air traffic patterns,

    including either an increase in traffic levels

    or a change in location that results in

    substantial safety risks?

    4. Substantially increase hazards due to a design

    feature (e.g., sharp curves or dangerous

    intersections) or incompatible uses (e.g., farm

    equipment)?

    5. Result in inadequate emergency access?

    6. Result in inadequate parking capacity?

    7. Conflict with adopted policies, plans, or

    programs supporting alternative

    transportation (e.g., bus turnouts, bicycle

    racks)?

    Cause an in

    During the construction phase of the project, additional vehicles would be entering the project site,

    including a drilling rig, a water truck, forklifts, bulldozers, two or more diesel trucks or gasoline trucks

    and a number of passenger automobiles. All vehicles, excluding the trucks and automobiles, wouldremain at the site during the construction activities and would not impact traffic on the nearby roadways

    and intersections. The remaining trucks and vehicles would be used for project support and may make

    limited day trips during the construction phase of the project. The increase in traffic due to the project

    vehicles would be minimal and would not result in a change in traffic patterns or levels. The proposed

    project would cause no change in local air traffic patterns.

  • 8/14/2019 restore IS MND Draft revA v4

    24/26

    3.16 UTILITIESAND SERVICE SYSTEMS

    Less-Than-

    Significant

    with

    Mitigation

    Incorporated

    Less-Than-

    Significant

    Impact No Impact

    2. Require or result in the construction of new

    water or wastewater treatment facilities

    or expansion of existing facilities, theconstruction of which could cause

    significant environmental effects?

    3. Require or result in the construction of new

    stormwater drainage facilities or expansion

    of existing facilities, the construction of

    which could cause significant environmentaleffects?

    4. Have sufficient water supplies available

    to serve the project from existing

    entitlements and resources, or are new

    or expanded entitlements needed?

    5. Be served by a landfill with sufficientpermitted capacity to accommodate the

    projects solid waste disposal needs?

    6. Comply with federal, state, and local statutes

    and regulations related to solid waste?

    No Impact.

    Require

  • 8/14/2019 restore IS MND Draft revA v4

    25/26

    No Impact.

    Be serven-significant Impact.

    Complyct.

    Less-Than-

    Significant

    with

    Mitigation

    Incorporated

    Less-Than-

    Significant

    Impact No Impact

    3. Does the project have environmental effects

    which will cause substantial adverse effects

    on human beings, either directly or

    indirectly?

    Does thehan Significant Impact.

    eironment, including These impacts would be temporary in nature and would be mitigated to less than

    ctions xx and xx. to a level of non-significance.

    Item 2. Less-Than-Significant Impact.

    te problems associated with rain infiltration into campus facilities. These repairs would complement the

    proposed project, as they would return the facilities to their intended conditions, while the subsurface

    improvements would prevent future water damage.

  • 8/14/2019 restore IS MND Draft revA v4

    26/26

    4.2 PERSONS CONSULTED

    4.3.1 Connection to infiltration gallery.