resources performance time project planning phase : generating tasks & identifying...

8
resources Performance time Project Planning Phase : Generating Tasks & Identifying Responsibilities 1

Upload: benedict-cooper

Post on 02-Jan-2016

212 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Resources Performance time Project Planning Phase : Generating Tasks & Identifying Responsibilities 1

resources

Performancetime

Project Planning Phase : Generating Tasks & Identifying Responsibilities

1

Page 2: Resources Performance time Project Planning Phase : Generating Tasks & Identifying Responsibilities 1

resources

Performancetime

The phases and it’s steps

IN ITIATION ANDDEFINITION

PLANNING

EXECUTIONAND CONTROL

CLOSE OUT

Step 1 : Define the project

Step 2: Generate TasksStep 3: Determine Roles and ResponsibilitiesStep 4: Define Task InterdependencesStep 5: Develop ScheduleStep 6: Generate BudgetStep 7: Allocate ResourcesStep 8: Develop Risk Management

Step 9: Track and Manage the Project

Step 10: Perform Post-Project Review

Page 3: Resources Performance time Project Planning Phase : Generating Tasks & Identifying Responsibilities 1

resources

Performancetime

Work Breakdown Structure

Page 4: Resources Performance time Project Planning Phase : Generating Tasks & Identifying Responsibilities 1

resources

Performancetime

4

Work Breakdown Structure

• “…a visual model generated and utilized by the project team, which breaks down project requirements (end items, tasks, resources) into manageable work units.” (Warner 1998)

Page 5: Resources Performance time Project Planning Phase : Generating Tasks & Identifying Responsibilities 1

resources

Performancetime

5

WBS Structure

• Develop hierarchical breakdown of project– No standard approach - project dependent– Corporate conventions should be followed– Successively breakdown the project into

smaller work packages• Summation of all work packages at the

lowest respective levels constitutes project

• WBS should follow project deliverables

Page 6: Resources Performance time Project Planning Phase : Generating Tasks & Identifying Responsibilities 1

resources

Performancetime

6

WBS - Indented Format

1.0 Project 1.1 Major Project Subsystem 1

1.1.1 Task 1 1.1.1.1 Subtask 1

1.1.1.1.1 Work Package 11.1.1.1.1.1 Activity

1.1.2 Task 2 1.1.2.1 Subtask 2

1.1.2.1.1 Work Package 11.1.2.1.2 Work Package 2

Page 7: Resources Performance time Project Planning Phase : Generating Tasks & Identifying Responsibilities 1

resources

Performancetime

7

WBS - Graphical (Tree) Format

Level 0 Project

Subsystem 1 (1.1)

Subsystem 2(1.2)Level 1

Task 11.1.1

Task 21.1.2

Task 11.2.1Level 2

Level 3Subtask 1

1.1.1.1Subtask 2

1.1.1.2

Level 4Work Package 1

1.1.1.1.1Work Package 2

1.1.1.1.2

Level 5Activity 1

1.1.1.1.1.1Activity 2

1.1.1.1.1.2

Page 8: Resources Performance time Project Planning Phase : Generating Tasks & Identifying Responsibilities 1

resources

Performancetime

8

Watch Out!!!

• A WBS is not a Laundry List of Things to do (resulting in Micro-Management)

• Decompose until you can:– Describe the task using a single action

verb– Assign single task ownership– Describe a single deliverable– Small enough to reasonably estimate