research article effect of over zone feeding on rail...
TRANSCRIPT
![Page 1: Research Article Effect of Over Zone Feeding on Rail ...downloads.hindawi.com/journals/mpe/2016/6304726.pdf · Time (s) (b) Traction power of a train in a zone F : Characteristic](https://reader034.vdocuments.us/reader034/viewer/2022051913/6004ab4a263c6a53d326360c/html5/thumbnails/1.jpg)
Research ArticleEffect of Over Zone Feeding on Rail Potential andStray Current in DC Mass Transit System
Guifu Du, Chonglin Wang, Jianhua Liu, Guoxin Li, and Dongliang Zhang
School of Information and Electrical Engineering, China University of Mining and Technology, Xuzhou 221008, China
Correspondence should be addressed to Jianhua Liu; [email protected]
Received 25 October 2015; Revised 30 January 2016; Accepted 7 February 2016
Academic Editor: Mitsuhiro Okayasu
Copyright © 2016 Guifu Du et al.This is an open access article distributed under theCreative CommonsAttribution License, whichpermits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
DC traction power system with running rails as reflux conductor has been adopted in Guangzhou Metro Line 8. During theoperation of the Guangzhou Metro Line, a high rail potential has been observed, and the leakage of stray current increasessignificantly. Because of the electrical connectivity of the catenary, over zone feeding of traction current may exist when multipletrains run in multiple traction substations. Guangzhou Metro Line 8 suspects that over zone feeding of traction current is themajor cause of the high rail potential. In this paper, a unified chain model of DC traction power system is proposed to simulate thedistribution of rail potential and stray current. Field tests and simulations have been carried out to study whether over zone feedinghas an impact on rail potential and stray current. Results show that over zone feeding widely exists in DC traction power systemand that the rail potential and stray current can be reduced effectively by preventing the over zone feeding of traction current.
1. Introduction
In 1500V DC traction power system of Guangzhou MetroLine 8, the train obtains power from the catenary, and therunning rails are used as return conductor for traction cur-rent. Ungrounded scheme of the negative return conductorwith over voltage protection device (OVPD) is adopted in theline. There will be a potential between the running rails andthe ground, known as rail potential, which is caused by theresistance of running rails and traction current transmission[1–3]. A high rail potential may cause damage to humansafety, and it will increase the leakage of return current atthe same level of rail-to-ground insulation, known as straycurrent. Then, electrochemical corrosion will be exacerbated[4]. A high rail potential, up to 90V or higher, has beenobserved during the operation of DC mass transit system inmultiple lines of Guangzhou Metro [5]. OVPD is adoptedin order to control rail potential by connecting the runningrails to the substation ground [2]. However, it is activatedfrequently, up to hundreds of times, during the operationof Guangzhou Metro Line. Some OVPDs are turned on andkeep the running rails grounded, in which case the currentleakage from theOVPDcan reach 800A [6]. It is a great threat
to the operational safety of the line and the protection of straycurrent.
The causes and control methods have been researchedon rail potential and stray current by some scholars. Relativeresearches show that [3, 7, 8], by reducing the resistanceof the running rail, increasing the voltage level of tractionpower system, and shortening the distance between substa-tions, the rail potential and stray current can be reduced.Furthermore, different grounding schemes of the DC masstransit system, including ungrounded, solidly grounded, anddiode-grounded, have an influence on the rail potential andstray current [2, 3, 9]. In Taipei rapid transit systems, theimpedance bond between Blue and Red-Green line is provedto be a cause of high rail potential and stray current [10, 11].Moreover, the researches show that running modes of trainhave an impact on rail potential and stray current [12]. Railpotential is relatively high during acceleration and brakeof the train and the maximum rail potential occurs at theposition of the train. Simulation model of rail potential andstray current has been studied inmany researches. In lumpedparameter model of rail potential and stray current [1, 10,13], a segment of 100m is sufficient and accurate for thesimulation, but the conductance matrixes of multiple zones
Hindawi Publishing CorporationMathematical Problems in EngineeringVolume 2016, Article ID 6304726, 15 pageshttp://dx.doi.org/10.1155/2016/6304726
![Page 2: Research Article Effect of Over Zone Feeding on Rail ...downloads.hindawi.com/journals/mpe/2016/6304726.pdf · Time (s) (b) Traction power of a train in a zone F : Characteristic](https://reader034.vdocuments.us/reader034/viewer/2022051913/6004ab4a263c6a53d326360c/html5/thumbnails/2.jpg)
2 Mathematical Problems in Engineering
will be very large, and the speed of calculation will be slow.In distributed parameter model of rail potential and straycurrent [3, 9, 12], traction current of each node is obtainedfrom flow calculation of DC traction power system. Theaccuracy of power flow calculation depends on the precisemodification of the reflux system parameter. Nevertheless,the flow calculation and the evaluation of rail potential are notcombined with each other. In order that more factors can beconsidered in assessment of rail potential and stray current,new simulation models have been proposed by scholars. Railpotential and stray current are modeled by a finite elementmethod in [14], and the introduction of an equipotentialconnection between the reinforcement bars of the adjacentsegments is proposed to prevent corrosion phenomena. Acommercial software platform (CDEGS) can be used inassessing the more complex stray current with the effect ofcrosstrack regeneration supply [15]. With the same platform,a topologically accurate model in cut-and-cover sections ofDC metro systems is presented to evaluate the dynamic straycurrent picture [16]. In [17], the factors, such as the traincharacteristics, time tabling, headway, and multiple trains’movement, are considered in the assessment of rail potentialand stray current.
In view of above contributions, the work presented inthis paper reinforces the effect of over zone feeding on railpotential and stray current. The regenerative power fed backto the catenary frombraking trainmay be consumed by trainsrunning in other zones owing to the electrical connectivityof the catenary and unilateral conductivity of the 24-pulserectifier units [18, 19]. Distribution of the regenerative poweris related to the powers and positions of other trains and theregenerative energy absorbing device. In this paper, the effectof over zone feeding on rail potential and stray current istested in Guangzhou Metro Line 8. A multiconductor modelof DC traction power system is established based on theactual features of the system. For the realization of fast andaccurate calculation, lumped parameters of reflux system inthe model are modified based on lumped parameter modeland distributed parameter model. A chain model of DCtraction power system is proposed to unify the complicatedoperation modes of traction substation and train. Rail poten-tial and stray current affected by over zone feeding can beanalyzed by the simulation model.
2. System Description
Field tests of over zone feeding on rail potential have beencarried out in Guangzhou Metro Line 8. The total length ofGuangzhou Metro Line 8 is 18.48 km. It includes 7 tractionsubstations and 6 train stations. Configuration of GuangzhouMetro Line 8 is shown in Figure 1.
The high-voltage system for Guangzhou Metro Line 8is 110 kV. It is stepped down to 33 kV by the Bulk SupplySubstation. Then the 33 kV is supplied for the rectifier unitsand the train substation. No-load voltage of the rectifier unitsis 1593V, which is distributed to the catenaries of the up-lineand down-line. Traction current of the train comes from thecatenary and returns to the negative bus of the rectifier units
Wanshengwei
Pazhou
Xingangdong
Modiesha
ChigangKecun
LujiangZhongda
Xiaogang
ChanggangBaogang Dadao
Shayuan
Fenghuang
Xincun
Traction substation and train stationTrain station
N
Figure 1: Configuration of Guangzhou Metro Line 8.
by running rails and negative return cable. Schematic of DCmass transit system is shown in Figure 2.
A 24-pulse diode transformer rectifier is widely used inDC mass transit system to reduce harmonic components.Insulated joints are set between catenaries of adjacent powersupply zones to ensure the power supplying safely, reliably,and flexibly. DC circuit-breakers B1∼B4 connect the positivebus of the rectifier units to the catenaries on both sides of theinsulated joint. The presence of DC bus and circuit-breakersleads to the electrical continuity of catenaries; therefore, alltraction substations can supply power formultiple trains. Up-line rail and down-line rail are connected by cross-bondingcables at intervals of 400m∼500m. Buried conductors areset in the ballast bed to collect stray current. Most tractioncurrent flows back to the negative bus of rectifier unitsthrough the running rails and the rest of it flows from theburied conductor or ground.
Power distribution is affected by the characteristics oftraction substation and train. External characteristic of trac-tion substation is influenced by impedance parameters ofrectifier unit, impedance voltage of rectifier transformer,connectionmodes of rectifier, and so forth [19]. In this paper,output characteristic of the rectifier unit is simplified to lineI in Figure 3(a). Line II indicates that the catenary voltage attraction substation is higher than the no-load voltage𝑈
0, and
the traction substation is out of operation.A train’s running mode in one zone is actually divided
into three stages: acceleration, which requires high tractioncurrent; coasting, which requires low traction current; decel-eration, which may require regenerative braking and feedthe current back to catenary. The position and power oftrain running in line can be obtained by train movementcalculation. A typical curve of traction power when onetrain runs in a zone of 1.2 km is shown in Figure 3(b). Theregenerative energy of train is partly consumed by the train,the left of which is fed back to the catenary and causes thecatenary voltage rise for the unilateral conductivity of rectifierunits. Energy absorbing device is usually set at the tractionsubstation or train to absorb regenerative energy and limitthe catenary voltage in the presence of train regenerativebraking. It will be activated to maintain the catenary voltagewhen the voltage reaches the limited point 𝑈lim. ConsistentwithGuangzhouMetro Line 8, regenerative energy absorbingdevice is set on the train in the simulation model.
![Page 3: Research Article Effect of Over Zone Feeding on Rail ...downloads.hindawi.com/journals/mpe/2016/6304726.pdf · Time (s) (b) Traction power of a train in a zone F : Characteristic](https://reader034.vdocuments.us/reader034/viewer/2022051913/6004ab4a263c6a53d326360c/html5/thumbnails/3.jpg)
Mathematical Problems in Engineering 3
+− DC bus
Rectifier units
Insulated joint Up-line rail
Up-line catenary
Down-line catenary
+−
Down-line rail
Buried conductor
Earth
Train
Cross-bonding cable
B1
B2B3
B4DC circuit breaker
Negative return cableOVPDOVPD
Cross section 1
Cross section 2
Cross section 3
Cross section 4
x1 x2 x3 x4
AC 33kV
Figure 2: Schematic of DC mass transit system.
I
II
Udc
Umax
U0
UdN
Umin
0 IdN Id
(a) Output characteristic of traction substation
Deceleration
Acceleration
Coasting
−6000
−4000
−2000
0
2000
4000
6000
Trac
tion
pow
er (k
W)
20 40 60 800Time (s)
(b) Traction power of a train in a zone
Figure 3: Characteristic of traction substation and train.
As shown in Figure 4, OVPD is installed in the substationto monitor the voltage between rail and local earth continu-ously for personal safety. The device will be activated if themeasured voltage exceeds a preset voltage-time character-istic. Operating characteristic of the OVPD in GuangzhouMetro Line 8 is shown in Table 1.
3. Field Tests and Results
Field tests have been carried out at Wanshengwei Station andPazhou Station inGuangzhouMetro Line 8 to assess the effectof over zone feeding on rail potential. Since Wanshengwei
Station is a train station without rectifier units, variation oftraction current is relatively clear in single-side feeding zonefrom Pazhou Station to Wanshengwei Station. The distancebetween Wanshengwei Station and Pazhou Station is 1.8 km.
3.1. Field Tests of Traction Current. Connectionmodes of DCcircuit-breakers B1∼B4 are shown in Figure 2. Positive valueof traction current in DC circuit-breakers is running frompositive bus of the rectifier units to the catenary. Field testshave been carried out in Pazhou Station.
Traction currents in B1∼B4 of Pazhou Station are shownin Figure 5 when a train Tr1 starts fromWanshengwei Station
![Page 4: Research Article Effect of Over Zone Feeding on Rail ...downloads.hindawi.com/journals/mpe/2016/6304726.pdf · Time (s) (b) Traction power of a train in a zone F : Characteristic](https://reader034.vdocuments.us/reader034/viewer/2022051913/6004ab4a263c6a53d326360c/html5/thumbnails/4.jpg)
4 Mathematical Problems in Engineering
A
V
Negative bus
Earth
Figure 4: Schematic of the OVPD.
Table 1: Operating characteristic of the OVPD.
Symbol Values Operating characteristic
U> 92 VDC Switches on with 0.1 s delayand switches off after 10 s.
U≫ 150 VDC Switches on with no delayand switches off after 10 s.
U⋙ 600 VDCSwitches on with no delayand remains on until beingswitched off artificially
Table 2: Proportion of traction current coming from over zonefeeding during Tr1 accelerates.
Time (s) 13.4 17.1 20.8 24.3 51.3Traction current (A) 3048 2936 3216 3264 3725CTR (%) 36.6 37.0 35.0 35.3 36.6
to Pazhou Station in up-line from 06:23:40 to 06:25:10 inDecember 21, 2012.
Since the zone is single-side feeding, all traction currentof Tr1 flows from B2. Tr1 accelerates from WanshengweiStation during 0.0 s∼55.0 s, in which period current flowingfrom B2 is positive. The currents flowing from B3 and B4 arenegative. At this moment, there is no regenerative brakingtrain in line and the currents flowing from B3 and B4are traction current provided by other substations. Tractioncurrent of Tr1 provided by Pazhou Station is shown as 𝐼
𝑠in
Figure 5, and currents flowing from B3 and B4 come fromover zone feeding.
CTR is defined to describe the proportion of tractioncurrent coming from over zone feeding. We describe it as
CTR = (𝐼
𝑐𝑡
𝐼
𝑡
) × 100%, (1)
where 𝐼𝑐𝑡is the traction current provided by other traction
substations except substations in the zone of train runningand 𝐼𝑡is traction current of the train.
Table 2 shows the CTR when traction current of Tr1is high. Referring to Table 2 and Figure 5, proportions oftraction current coming from over zone feeding are low andrelatively stable during 0.0 s∼55.0 s. Current coming from
B1
B2
B3, B4
10 20 30 40 50 60 70 800Time (s)
−2000
−1000
0
1000
2000
3000
4000
Trac
tion
curr
ent (
A)
Is
Figure 5: Traction current of Pazhou Substation.
B1
B3
B4
B2
−3000
−2000
−1000
0
1000
2000
3000
4000Tr
actio
n cu
rren
t (A
)
10 20 30 40 50 60 70 80 900Time (s)
Is
Figure 6: Traction current of Pazhou Station.
over zone feeding is mainly provided by traction substationsother than Pazhou Station.
Figure 6 shows traction currents in B1∼B4 of PazhouStation from 08:10:35 to 08:12:05 in December 21, 2012.
Traction currents in B1∼B4 of Pazhou Station are shownin Figure 6. A train Tr2 accelerates from Pazhou Station toXingangdong Station in up-line during 0.0 s∼33.0 s. In thisperiod, traction currents of B1 and B2 are 0.0 A for there is notrain running in the single-side feeding zone. Tr3 acceleratesfrom Wanshengwei Station to Pazhou Station at 43.0 s, andit absorbs energy from the catenary. At the same time, Tr2begins regenerative braking and feeds energy back to thecatenary. Then the regenerative current of Tr2 is fed to Tr3over the zone. Current flowing from B3 is much higher thanthat shown in Figure 5 in this period.
Traction current provided by Pazhou Substation is shownas 𝐼𝑠in Figure 6. Traction current coming from over zone
feeding increases greatly for there is an accelerating trainTr3 nearby the regenerative braking train Tr2. Table 3 shows
![Page 5: Research Article Effect of Over Zone Feeding on Rail ...downloads.hindawi.com/journals/mpe/2016/6304726.pdf · Time (s) (b) Traction power of a train in a zone F : Characteristic](https://reader034.vdocuments.us/reader034/viewer/2022051913/6004ab4a263c6a53d326360c/html5/thumbnails/5.jpg)
Mathematical Problems in Engineering 5
Table 3: Proportion of traction current coming from over zonefeeding during Tr3 accelerates.
Time (s) 52.7 56.3 60.8 63.5 63.6Traction current (A) 2989 2873 2981 3047 3033CTR (%) 59.2 89.3 73.6 72.4 73.5
the CTR when traction current of Tr3 is high. With the sameamplitude of train current, the CTR is much higher than thatin Table 2. CTR reaches 89.3% at 56.3 s when the tractioncurrent of Tr3 is 2873A.
Field tests of traction current show that over zone feedingexists widely in DC mass transit system for the electricalconnectivity of the catenary. The extent of over zone feedingis related to various factors, including the density of trains inline, the power of trains, and the distance of traction substa-tions. Traction current coming fromover zone feedingwill belarge when the density of trains is high and the acceleratingtrain is in a high coincidence with the regenerative brakingtrain.
3.2. Field Tests of Rail Potential. Field tests of rail potentialaffected by over zone feeding have been carried out at Wan-shengwei Station; at the same time, traction currents in B1∼B4 of Pazhou Station are recorded. OVPD at WanshengweiStation is activated frequently during the operation of the line.
As shown in Figure 7, parameters have been tested inthree processes when train accelerates from WanshengweiStation to Pazhou Station in up-line. The parameters includetractions current in B1∼B4 of Pazhou Station, proportionof train current coming from over zone feeding, and railpotential at Wanshengwei Station.
In Figures 7(a)∼7(c), traction current of the acceleratingtrain is shown as B2, and there is little difference in the maxi-mum amplitude of B2. However, the OVPD at WanshengweiStation is activated at different moments of the acceleratingprocesses.
As shown in Figure 7(a), there is no regenerative brakingtrain nearby the accelerating Tr4. Therefore, traction currentof Tr4 coming fromover zone feeding is low and stable, whichis provided by traction substations other than Pazhou Station.In this process, the rail potential is low and the OVPD is notactivated.
Parameters are shown in Figure 7(b) during the accelera-tion of Tr5. From 0.0 s to 2.6 s, a large proportion of tractioncurrent comes from over zone feeding, while the amplitudeof traction current coming from over zone feeding is low.Therefore, rail potential increases gradually but does notreach the limit𝑈 > of OVPD. Traction current of Tr5 reachesthe maximum from 7.2 s to 10.7 s and remains stable duringthis period. Nevertheless, the traction current coming fromover zone feeding increases continuously. The rail potentialof Wanshengwei Station reaches the limit 𝑈 > and OVPD isactivated at the time 9.3 s. After 10.0 s, OVPD switches off.
Figure 7(c) shows the parameters during the accelerationof Tr6. Proportion of train current coming from over zonefeeding is low and stable from the time 0.0 s to 12.0 s. During
12.0 s∼13.8 s, traction current of Tr6 is low, and CTR increasesrapidly to 100% for there is a train Tr7 regenerative brakingin the zone of Pazhou Station to Xingangdong Station.From 14.5 s to 16.2 s, CTR decreases while amplitude oftraction current coming from over zone feeding is increasing.Traction current amplitude of Tr6 reaches the maximumat 16.2 s, while the amplitude of traction current comingfrom over zone feeding is increasing continuously. The railpotential of Wanshegwei Station reaches the limit 𝑈 > andOVPD is activated at 16.7 s and it switches off after 10.0 s.
Results of field tests show that, in the same accelerationprocess, disparity exists in rail potential with different extentof over zone feeding. However, it is difficult to carry out thetests of real-time positions and currents of trains. A dynamicmodel is proposed to analyze the rail potential and straycurrent affected by over zone feeding in this paper.
4. Modeling of Rail Potential andStray Current
Rail potential and stray current are associated with thedistribution of power in DC traction power system. In thispaper, a computational method of rail potential and straycurrent is proposed, which consists of two steps. Firstly, achainmodel equivalent to the lumpedparametermodel of thesystem is proposed to carry out the power flow of the system.Secondly, rail potential and stray current are calculated bydistributed parameter model of the reflux system, and theboundary conditions are obtained from power flow.
DC traction power system shown in Figure 2 can beexpressed as the equivalent model shown in Figure 8.The catenary, traction substation, and train are lumpedparameters, and the rail, buried conductor, and earth aredistributed parameters.The up-line and down-line catenariesare independent in the interval and are connected by the DCpositive bus at each traction substation. Output characteristicof the rectifier units is shown in Figure 3(a). The train isequivalent to a constant power model at each movement inthe up-line, as 𝑃
2, or in down-line, as 𝑃
4shown in Figure 8.
The power and position of the train can be obtained fromtrain movement calculation. 𝑃
2𝑟or 𝑃4𝑟
is energy absorbingdevice set on the train, which can be equivalent to a variableresistor. Due to the cross-bonds in the interval, the rails inup-line and down-line are equivalent to one conductor.
The mathematical problem can be described as follows:the model includes lumped parameters (catenary, tractionsubstation, and train) and distributed parameters (rail, buriedconductor, and earth). The location and external character-istics of each traction substation are predetermined. Thereare multiple trains running dynamically in up-line or down-line, which are modeled as constant power source in eachmovement. The power changing with time 𝑝(𝑡) and theposition changing with time 𝑥(𝑡) of each train can beobtained by train movement calculation. In the model, therail potential at each position changing with time 𝑢
𝑟(𝑥, 𝑡), the
potential of buried conductor at each position changing withtime𝑢
𝑠(𝑥, 𝑡), the current in rail at each position changingwith
![Page 6: Research Article Effect of Over Zone Feeding on Rail ...downloads.hindawi.com/journals/mpe/2016/6304726.pdf · Time (s) (b) Traction power of a train in a zone F : Characteristic](https://reader034.vdocuments.us/reader034/viewer/2022051913/6004ab4a263c6a53d326360c/html5/thumbnails/6.jpg)
6 Mathematical Problems in Engineering
B1
B2
B3, B4
5 10 15 20 250Time (s)
5 10 15 20 250Time (s)
5 10 15 20 250Time (s)
0
50
100
Rail
pote
ntia
l (V
)
0
50
100
CTR
−2000
0
2000
4000
Trac
tion
curr
ent (
A)
(a) Traction current and rail potential when Tr4 accelerates
B3B4
B2
OVPD switches on
B1
−2000
0
2000
4000
Trac
tion
curr
ent (
A)
0
50
100
CTR
0
50
100
Rail
pote
ntia
l (V
)
5 10 15 20 250Time (s)
5 10 15 20 250Time (s)
5 10 15 20 250Time (s)
(b) Traction current and rail potential when Tr5 accelerates
0 5 10 15 20 25Time (s)
0 5 10 15 20 25Time (s)
0 5 10 15 20 25Time (s)
B3
B4
B2 B1
OVPD switches on
−4000−2000
020004000
Trac
tion
curr
ent (
A)
0
50
100
CTR
0
50
100
Rail
pote
ntia
l (V
)
(c) Traction current and rail potential when Tr6 accelerates
Figure 7: Test results of traction current and rail potential.
time 𝑖𝑟(𝑥, 𝑡), and the stray current in buried conductor at each
position changing with time 𝑖𝑠(𝑥, 𝑡) need to be calculated.
The distribution of 𝑢𝑟(𝑥), 𝑢
𝑠(𝑥), 𝑖𝑟(𝑥), 𝑖𝑠(𝑥) at a certain
movement can be calculated as follows.
4.1. Modification of Equivalent Reflux Parameters. The dis-tributed parameters of reflux system must be converted tolumped parameters for the calculation of power flow, and
then, rail potential and stray current can be assessed in thedistributed parametermodel on basis of boundary conditionscalculated by power flow. The distributed parameter modeland the equivalent lumped parameter model are shown inFigure 8.
For the realization of fast and accurate calculation, mod-ification of reflux system parameters is proposed based onlumped parameter model and distributed parameter modelof the reflux system.
![Page 7: Research Article Effect of Over Zone Feeding on Rail ...downloads.hindawi.com/journals/mpe/2016/6304726.pdf · Time (s) (b) Traction power of a train in a zone F : Characteristic](https://reader034.vdocuments.us/reader034/viewer/2022051913/6004ab4a263c6a53d326360c/html5/thumbnails/7.jpg)
Mathematical Problems in Engineering 7
Rail
Cross section 1
Cross section 2
Cross section 3
Cross section 4
Cross section 5
Cross section N
Up-line catenary
Buried conductor
Earth
Distributed parameter model
Lumpedparameter model
Down-line catenary
P2r P2
zd1 zd2 zd3 zd4
P1 P3P4r P4 P5 PN
zu1 zu2 zu3 zu4Uu1 Uu2 Uu3 Uu4 Uu5 UuN
yw1 yw2 yw3 yw4 yw5 ywN
Ud1 Ud2 Ud3 Ud4 Ud5 UdN
yc1yc3 yc5 ycN
Us1 Is1 Us2Is2 Us3 Us4 Us5 UsN
Ur1 Ir1 Ur2Ir2 Ur3 Ur4 Ur5 UrNir(x)
is(x)
us(x)
Rr · dx
Rs · dx
Gp · dx
ir(x + dx)
ur(x + dx)
is(x + dx)
us(x + dx)
dx
x x + dx
Ur1 Ir1
Us1Is1
Ir2
Is2
zr1
zs1
zr2
zs2
zr3
zs3
zr4
zs4(yg1)/2
(yp1)/2
(yg1)/2
(yp1)/2
(yg3)/2
(yp3)/2
(ygN)/2
(ypN)/2
· · ·
· · ·
· · ·
· · ·
x1 x2 x3 x4 x5 xN
ur(x) Gs · dx
Figure 8: Model of DC traction power system.
Distributed parameter model of reflux system is shownin Figure 8 and 𝑢
𝑟(𝑥), 𝑢
𝑠(𝑥), 𝑖𝑟(𝑥), and 𝑖
𝑠(𝑥) at 𝑥 in the
distributed parametermodel are derived fromKirchhoff ’s law[2, 9, 12] as follows:
𝑑𝑢
𝑟(𝑥)
𝑑𝑥
= −𝑅
𝑟⋅ 𝑖
𝑟(𝑥) ,
𝑑𝑢
𝑠(𝑥)
𝑑𝑥
= −𝑅
𝑠⋅ 𝑖
𝑠(𝑥) ,
𝑑𝑖
𝑟(𝑥)
𝑑𝑥
= −𝐺
𝑠⋅ 𝑢
𝑟(𝑥) + 𝐺
𝑠⋅ 𝑢
𝑠(𝑥) ,
𝑑𝑖
𝑠(𝑥)
𝑑𝑥
= 𝐺
𝑠⋅ 𝑢
𝑟(𝑥) − (𝐺
𝑝+ 𝐺
𝑠) ⋅ 𝑢
𝑠(𝑥) ,
(2)
where 𝑅𝑟is longitudinal resistance of the rail, 𝑅
𝑠is longitu-
dinal resistance of the buried conductor, 𝐺𝑠is longitudinal
insulation conductance of rail to buried conductor, and 𝐺𝑝is
longitudinal insulation conductance of buried conductor toearth.
Solutions of differential equations are shown in thefollowing:
[
[
[
[
[
[
𝑢
𝑟 (𝑥)
𝑢
𝑠(𝑥)
𝑖
𝑟 (𝑥)
𝑖
𝑠(𝑥)
]
]
]
]
]
]
= H[
[
[
[
[
[
[
𝐶
1𝑒
−𝛼𝑥
𝐶
2𝑒
𝛼𝑥
𝐶
3𝑒
−𝛽𝑥
𝐶
4𝑒
𝛽𝑥
]
]
]
]
]
]
]
, (3)
where
H =
[
[
[
[
[
[
[
[
[
[
[
1 1 1 1
𝛼
𝑅
𝑟
−
𝛼
𝑅
𝑟
𝛽
𝑅
𝑟
−
𝛽
𝑅
𝑟
1 −
𝛼
2
𝐺
𝑠𝑅
𝑟
1 −
𝛼
2
𝐺
𝑠𝑅
𝑟
1 −
𝛽
2
𝐺
𝑠𝑅
𝑟
1 −
𝛽
2
𝐺
𝑠𝑅
𝑟
𝑟
𝛼−𝑟
𝛼𝑟
𝛽−𝑟
𝛽
]
]
]
]
]
]
]
]
]
]
]
,
𝑟
𝛼=
𝐺
𝑝
𝛼
−
𝛼
𝑅
𝑟
−
𝐺
𝑝𝛼
𝐺
𝑠𝑅
𝑟
,
![Page 8: Research Article Effect of Over Zone Feeding on Rail ...downloads.hindawi.com/journals/mpe/2016/6304726.pdf · Time (s) (b) Traction power of a train in a zone F : Characteristic](https://reader034.vdocuments.us/reader034/viewer/2022051913/6004ab4a263c6a53d326360c/html5/thumbnails/8.jpg)
8 Mathematical Problems in Engineering
𝑟
𝛽=
𝐺
𝑝
𝛽
−
𝛽
𝑅
𝑟
−
𝐺
𝑝𝛽
𝐺
𝑠𝑅
𝑟
,
𝛼 =
√
𝑚 + 𝑛
2
+
√
(𝑚 − 𝑛)
2
4
+ 𝑚𝑘,
𝛽 =
√
𝑚 + 𝑛
2
−
√
(𝑚 − 𝑛)
2
4
+ 𝑚𝑘,
𝑚 = 𝐺
𝑠𝑅
𝑟,
𝑛 = 𝑅
𝑠(𝐺
𝑠+ 𝐺
𝑝) ,
𝑘 = 𝑅
𝑠𝐺
𝑠,
(4)
and𝐶1∼ 𝐶
4can be obtained from the boundary conditions at
𝑥 = 𝑥
1and 𝑥 = 𝑥
2. In the distributed parameter model, at the
position 𝑥 = 𝑥1, the boundary conditions are 𝑢
𝑟(𝑥
1) = 𝑈
𝑟1,
𝑢
𝑠(𝑥
1) = 𝑈
𝑠1, 𝑖𝑟(𝑥
1) = 𝐼
𝑟1, and 𝑖
𝑠(𝑥
1) = 𝐼
𝑠1.
So, at position 𝑥 = 𝑥1,
H
[
[
[
[
[
[
[
[
𝐶
1𝑒
−𝛼𝑥1
𝐶
2𝑒
𝛼𝑥1
𝐶
3𝑒
−𝛽𝑥1
𝐶
4𝑒
𝛽𝑥1
]
]
]
]
]
]
]
]
=
[
[
[
[
[
[
[
𝑈
𝑟1
𝑈
𝑠1
𝐼
𝑟1
𝐼
𝑠1
]
]
]
]
]
]
]
. (5)
Then,
[
[
[
[
[
[
[
𝐶
1
𝐶
2
𝐶
3
𝐶
4
]
]
]
]
]
]
]
= H−1[
[
[
[
[
[
[
𝑈
𝑟1
𝑈
𝑠1
𝐼
𝑟1
𝐼
𝑠1
]
]
]
]
]
]
]
[𝑒
𝛼𝑥1𝑒
−𝛼𝑥1𝑒
𝛽𝑥1𝑒
−𝛽𝑥1]
=
[
[
[
[
[
[
[
[
𝑒
𝛼𝑥1(ℎ
11𝑈
𝑟1+ ℎ
12𝑈
𝑠1+ ℎ
13𝐼
𝑟1+ ℎ
14𝐼
𝑠1)
𝑒
−𝛼𝑥1(ℎ
21𝑈
𝑟1+ ℎ
22𝑈
𝑠1+ ℎ
23𝐼
𝑟1+ ℎ
24𝐼
𝑠1)
𝑒
𝛽𝑥1(ℎ
31𝑈
𝑟1+ ℎ
32𝑈
𝑠1+ ℎ
33𝐼
𝑟1+ ℎ
34𝐼
𝑠1)
𝑒
−𝛽𝑥1(ℎ
41𝑈
𝑟1+ ℎ
42𝑈
𝑠1+ ℎ
43𝐼
𝑟1+ ℎ
44𝐼
𝑠1)
]
]
]
]
]
]
]
]
,
(6)
where ℎ11∼ ℎ
44are elements ofH−1.
At the position 𝑥 = 𝑥2, 𝐼𝑟2can be expressed as follows:
𝐼
𝑟2= (1 −
𝛼
2
𝐺
𝑠𝑅
𝑟
)𝐶
1𝑒
−𝛼𝑥2+ (1 −
𝛼
2
𝐺
𝑠𝑅
𝑟
)𝐶
2𝑒
𝛼𝑥2
+ (1 −
𝛽
2
𝐺
𝑠𝑅
𝑟
)𝐶
3𝑒
−𝛽𝑥2+ (1 −
𝛽
2
𝐺
𝑠𝑅
𝑟
)𝐶
4𝑒
𝛽𝑥2
= 𝑘
1𝑈
𝑟1+ 𝑘
2𝑈
𝑠1+ 𝑘
3𝐼
𝑟1+ 𝑘
4𝐼
𝑠1.
(7)
Based on the system parameters, 𝑘1, 𝑘2, 𝑘3, and 𝑘
4are the
function of segment length (𝑥2− 𝑥
1).
In the lumped parametermodel shown in Figure 8, 𝐼𝑟2can
be expressed as follows:
𝐼
𝑟2= 𝑈
𝑟1[
𝑦
𝑔1
2
+
𝑦
𝑔1
2
+
𝑦
2
𝑔1𝑧
𝑟1
4
+
𝑦
2
𝑔1𝑧
𝑠1
4
] − 𝑈
𝑠1[
𝑦
𝑔1
2
+
𝑦
𝑔1
2
+
𝑦
2
𝑔1𝑧
𝑟1
4
+
𝑦
2
𝑔1𝑧
𝑠1
4
+
𝑦
𝑔1𝑦
𝑝1𝑧
𝑠1
4
] + 𝐼
𝑟1[1
+
𝑦
𝑔1𝑧
𝑟1
2
] − 𝐼
𝑠1[
𝑦
𝑔1𝑧
𝑠1
2
] .
(8)
The equivalent lumped parameters of the reflux systemcan be expressed as follows according to (8) and (7):
𝑦
𝑔1
2
=
𝑘
1
1 + 𝑘
3+ 𝑘
4
,
𝑧
𝑟1=
(𝑘
3− 1) (𝑘
4+ 𝑘
3+ 1)
𝑘
1
,
𝑦
𝑝1
2
=
𝑘
2− 𝑘
1
𝑘
4
,
𝑧
𝑠1=
𝑘
4(1 + 𝑘
3+ 𝑘
4)
𝑘
1
.
(9)
The lumped parameters in each section of Figure 8 can beupdated by the length 𝐿 of the section based on (9).
With this modification method, the distributed param-eter model of reflux system between two cross sections canbe equivalent to lumped parameter model. In this process,voltage and current at the ports keep constant to ensure theaccuracy of the equivalent parameters.
4.2. Flow Calculation Based on Unified Chain Model
4.2.1.Model Description. Ahuge number of nodes exist in themodel shown in Figure 8.The admittancematrix of themodelwill be changed in flow calculation with different operationmodes of the traction substation and train. On basis of chainmodel in AC traction power system [20, 21], equivalent chainmodel of DC traction power system divided by cross sectionis shown in Figure 9.
Nodal voltage equation of the chain model is shown asfollows:
![Page 9: Research Article Effect of Over Zone Feeding on Rail ...downloads.hindawi.com/journals/mpe/2016/6304726.pdf · Time (s) (b) Traction power of a train in a zone F : Characteristic](https://reader034.vdocuments.us/reader034/viewer/2022051913/6004ab4a263c6a53d326360c/html5/thumbnails/9.jpg)
Mathematical Problems in Engineering 9
U1 U2 U3 UNZ1 Z2 Z3 ZN−1
I1 I2 I3 INY1 Y2 Y3 YN
Cross section 1
Cross section 2
Cross section 3
Cross section N
Figure 9: Chain model of DC traction power system.
[
[
[
[
[
[
[
[
[
[
[
Y1+ Z−11
−Z−11
−Z−11
Z−11+ Y2+ Z−12
−Z−12
−Z−12
Z−12+ Y3+ Z−13
−Z−13
d d d
−Z−1𝑁−1
Z−1𝑁−1
+ Y𝑁
]
]
]
]
]
]
]
]
]
]
]
[
[
[
[
[
[
[
[
[
[
U1
U2
U3
.
.
.
U𝑁
]
]
]
]
]
]
]
]
]
]
=
[
[
[
[
[
[
[
[
[
[
I1
I2
I3
.
.
.
I𝑁
]
]
]
]
]
]
]
]
]
]
. (10)
The submatrixes in (10) can be defined as follows:
Y𝑛=
[
[
[
[
[
[
[
[
[
[
[
[
[
𝑦
𝑤𝑛+ 𝑦
𝑐𝑛−𝑦
𝑤𝑛−𝑦
𝑐𝑛0 𝑈
𝑏𝑛
−𝑦
𝑤𝑛𝑦
𝑤𝑛0 0 0
−𝑦
𝑐𝑛0 𝑦
𝑐𝑛+
𝑦
𝑔(𝑛−1)+ 𝑦
𝑔𝑛
2
−𝑦
𝑔(𝑛−1)− 𝑦
𝑔𝑛
2
−𝑈
𝑏𝑛
0 0
−𝑦
𝑔(𝑛−1)− 𝑦
𝑔𝑛
2
𝑦
𝑔(𝑛−1)+ 𝑦
𝑔𝑛+ 𝑦
𝑝(𝑛−1)+ 𝑦
𝑝𝑛
2
0
𝑏
𝑟𝑛0 −𝑏
𝑟𝑛0 0
]
]
]
]
]
]
]
]
]
]
]
]
]
, (11)
Z−1𝑛= diag( 1
𝑧
𝑑𝑛
,
1
𝑧
𝑢𝑛
,
1
𝑧
𝑟𝑛
,
1
𝑧
𝑠𝑛
, 0) , (12)
U𝑛= [𝑈
𝑑𝑛; 𝑈
𝑢𝑛; 𝑈
𝑟𝑛; 𝑈
𝑠𝑛; 𝑦
𝑧𝑛] , (13)
I𝑛= [𝐼
𝑑𝑛; 𝐼
𝑢𝑛; 𝐼
𝑟𝑛; 𝐼
𝑠𝑛; 𝑈
𝑏𝑛] . (14)
At the cross section 𝑛 (1 < 𝑛 < 𝑁), the unified admittancesubmatrix Y
𝑛can be defined as (11). 𝑦
𝑤𝑛is a state variable
of the node type, 𝑦𝑤𝑛
= 0 indicates that this is a crosssection of train, and the catenaries of up-line and down-lineare independent. 𝑦
𝑤𝑛= 1𝑒5 indicates that this is a cross
section of traction substation, and the catenaries of up-lineand down-line are connected with each other. 𝑦
𝑐𝑛is self-
admittance of the power source at cross section 𝑛. At thecross section of train, 𝑦
𝑐𝑛= 0, and at the cross section of
traction substation, 𝑦𝑐𝑛= 1/𝑅eq. 𝑦𝑔𝑛 and 𝑦𝑝𝑛 can be obtained
by (9) with the length of segment from cross section 𝑛 tocross section (𝑛 + 1). 𝑏
𝑟𝑛is a state variable of train’s running
mode, 𝑏𝑟𝑛= 1 indicates that the train is in regenerative
braking, and the energy absorbing device is in operation;otherwise, 𝑏
𝑟𝑛= 0. 𝑈
𝑏𝑛is the limited voltage 𝑈lim. 𝑦𝑔(𝑛−1) =
𝑦
𝑝(𝑛−1)= 0 at cross section 𝑛 = 1, and 𝑦
𝑔𝑛= 𝑦
𝑝𝑛= 0 at cross
section 𝑛 = 𝑁.The submatrix of multiconductor impedance between
cross section 𝑛 and cross section (𝑛 + 1) (1 ≤ 𝑛 < 𝑁) Z𝑛
can be defined as (12), where 𝑧𝑑𝑛= 𝑧
𝑢𝑛= (𝑥
(𝑛+1)− 𝑥
𝑛)𝑅
𝑤, 𝑅𝑤
is the longitudinal resistance of the catenary. 𝑧𝑟𝑛and 𝑧𝑠𝑛can
be modified by (9) with (𝑥(𝑛+1)
− 𝑥
𝑛).
At the cross section 𝑛 (1 ≤ 𝑛 ≤ 𝑁), the unifiedsubmatrix of node voltage U
𝑛can be defined as (13). 𝑦
𝑧𝑛is
the admittance of the energy absorbing devicewhich can keepthe voltage of the catenary in𝑈lim at the cross section of train.𝑈
𝑑𝑛, 𝑈𝑢𝑛, 𝑈𝑠𝑛, and 𝑈
𝑟𝑛, respectively, represent the voltage of
down-line catenary to earth, voltage of up-line catenary toearth, voltage of rail to earth, and voltage of buried conductorto earth at cross section 𝑛.
![Page 10: Research Article Effect of Over Zone Feeding on Rail ...downloads.hindawi.com/journals/mpe/2016/6304726.pdf · Time (s) (b) Traction power of a train in a zone F : Characteristic](https://reader034.vdocuments.us/reader034/viewer/2022051913/6004ab4a263c6a53d326360c/html5/thumbnails/10.jpg)
10 Mathematical Problems in Engineering
At the cross section 𝑛 (1 ≤ 𝑛 ≤ 𝑁), the unified submatrixof node current-injection I
𝑛can be defined as (14). 𝐼
𝑑𝑛, 𝐼𝑢𝑛, 𝐼𝑟𝑛,
and 𝐼𝑠𝑛, respectively, represent the current-injection of down-
line catenary node, current-injection of up-line catenarynode, current-injection of rail node, and current-injection ofthe buried conductor node.𝑈
𝑏𝑛is consistent with that in (11).
The complicated operation modes of train and tractionsubstation can be unified by the submatrix (11)∼(14), and theflow calculation can be efficient.
4.2.2. Flow Calculation by Unified Chain Model. At a certainmovement, the flow calculation of DC traction power systemcan be carried out using iterative methods based on (10). Atthe step 𝑖 = 1, the traction substations are out of operationand U(1)
𝑛= [𝑈
0; 𝑈
0; 0; 0; 0]. At cross section of traction
substation, I(1)𝑛= [𝑈
0/𝑅eq; 0; −𝑈0/𝑅eq; 0; 0]. At cross section
of up-line train, I(1)𝑛
= [0; 𝑃
𝑛/(𝑈
(1)
𝑢𝑛− 𝑈
(1)
𝑟𝑛); −𝑃
𝑛/(𝑈
(1)
𝑢𝑛−
𝑈
(1)
𝑟𝑛); 0; 0], while at cross section of down-line train, I(1)
𝑛=
[𝑃
𝑛/(𝑈
(1)
𝑢𝑛− 𝑈
(1)
𝑟𝑛); 0; −𝑃
𝑛/(𝑈
(1)
𝑢𝑛− 𝑈
(1)
𝑟𝑛); 0; 0]. 𝑃
𝑛is the power
of the train at cross section 𝑛 in this movement. U(2)𝑛
canbe obtained by (10) from G(1)
𝑛U(2)𝑛
= I(1)𝑛
and then thecoefficient matrix G(2)
𝑛and current-injection submatrix I(2)
𝑛
can be updated based onU(2)𝑛.The iterationwill continue until
the step 𝑖whenU(𝑖)𝑛−U(𝑖−1)𝑛
at each cross section is lower thanthe voltage convergence precision 𝜉.
The changes of the submatrixes in the iteration are shownas follows.
In the 𝑖 step at cross section 𝑛 of traction substation, when𝑈
(𝑖)
𝑑𝑛− 𝑈
(𝑖)
𝑟𝑛< 𝑈
0, 𝑦𝑤𝑛= 1𝑒5, 𝑦
𝑐𝑛= 1/𝑅eq, 𝑈𝑏𝑛 = 0, and I
𝑛=
[𝑈
0/𝑅eq; 0; −𝑈0/𝑅eq; 0; 0], and when 𝑈(𝑖)
𝑑𝑛− 𝑈
(𝑖)
𝑟𝑛≥ 𝑈
0, 𝑦𝑤𝑛=
1𝑒5, 𝑦𝑐𝑛= 0, I𝑛= [0; 0; 0; 0; 0], 𝑈
𝑏𝑛= 0, and 𝑏
𝑛= 0.
In the 𝑖 step at cross section𝑚 of train, when𝑈(𝑖)𝑑𝑚−𝑈
(𝑖)
𝑟𝑚<
𝑈lim, then 𝑦𝑤𝑚 = 0, 𝑦𝑐𝑚 = 0, 𝑏𝑛 = 0, and 𝑈𝑏𝑛 = 0; when𝑈
(𝑖)
𝑑𝑚− 𝑈
(𝑖)
𝑟𝑚≥ 𝑈lim, then 𝑦𝑤𝑚 = 0, 𝑦𝑐𝑚 = 0, 𝑏𝑛 = 1, and
𝑈
𝑏𝑛= 𝑈lim. When the train is in up-line, I
𝑚= [0; 𝑃
𝑚/(𝑈
(𝑖)
𝑢𝑚−
𝑈
(𝑖)
𝑟𝑚); −𝑃
𝑚/(𝑈
(𝑖)
𝑢𝑚−𝑈
(𝑖)
𝑟𝑚); 0; 0], and when the train is in down-
line, I𝑚= [𝑃
𝑚/(𝑈
(𝑖)
𝑑𝑚− 𝑈
(𝑖)
𝑟𝑚); 0; −𝑃
𝑚/(𝑈
(𝑖)
𝑑𝑚− 𝑈
(𝑖)
𝑟𝑚); 00]. 𝑃
𝑚is
train’s power in this moment.After the flow calculation,U
𝑛and I𝑛at each cross section
can be obtained and be used as boundary conditions for thecalculation of rail potential and stray current.
4.3. Distribution of Rail Potential and Stray Current. The railpotential, potential of buried conductor, current in rail, andstray current in cross section 𝑛 to cross section (𝑛 + 1) (1 ≤𝑛 < 𝑁) are, respectively, defined as 𝑢
𝑟𝑛(𝑥), 𝑢𝑠𝑛(𝑥), 𝑖𝑟𝑛(𝑥), and
𝑖
𝑠𝑛(𝑥). They can be expressed as follows:
[
[
[
[
[
[
[
𝑢
𝑟𝑛(𝑥)
𝑢
𝑠𝑛(𝑥)
𝑖
𝑟𝑛 (𝑥)
𝑖
𝑠𝑛 (𝑥)
]
]
]
]
]
]
]
= H[
[
[
[
[
[
[
𝐶
𝑛1𝑒
−𝛼𝑥
𝐶
𝑛2𝑒
𝛼𝑥
𝐶
𝑛3𝑒
−𝛽𝑥
𝐶
𝑛4𝑒
𝛽𝑥
]
]
]
]
]
]
]
, (15)
where 𝑥𝑛≤ 𝑥 ≤ 𝑥
(𝑛+1)andH is shown in (3).
The boundary conditions of the model can be obtained at𝑥 = 𝑥
𝑛, and 𝑥 = 𝑥
(𝑛+1). At 𝑥 = 𝑥
𝑛, 𝑢𝑟𝑛(𝑥
𝑛) = 𝑈
𝑟𝑛, 𝑢𝑠𝑛(𝑥
𝑛) =
𝑈
𝑠𝑛. At 𝑢𝑟𝑛(𝑥
(𝑛+1)) = 𝑈
𝑟(𝑛+1), and 𝑢
𝑠(𝑥
(𝑛+1)) = 𝑈
𝑠(𝑛+1).
Then 𝐶𝑛1∼ 𝐶
𝑛4can be obtained as follows:
[
[
[
[
[
[
𝐶
𝑛1
𝐶
𝑛2
𝐶
𝑛3
𝐶
𝑛4
]
]
]
]
]
]
= M−1[
[
[
[
[
[
𝑈
𝑟𝑛
𝑈
𝑠𝑛
𝑈
𝑟(𝑛+1)
𝑈
𝑠(𝑛+1)
]
]
]
]
]
]
, (16)
where
M
=
[
[
[
[
[
[
[
[
[
[
[
[
𝑒
𝛼𝑥𝑛
𝑒
−𝛼𝑥𝑛
𝑒
𝛽𝑥𝑛
𝑒
−𝛽𝑥𝑛
𝛼
𝑅
𝑟
𝑒
𝛼𝑥𝑛
−
𝛼
𝑅
𝑟
𝑒
−𝛼𝑥𝑛
𝛽
𝑅
𝑟
𝑒
𝛽𝑥𝑛
−
𝛽
𝑅
𝑟
𝑒
−𝛽𝑥𝑛
𝑒
𝛼𝑥(𝑛+1)
𝑒
−𝛼𝑥(𝑛+1)
𝑒
𝛽𝑥(𝑛+1)
𝑒
−𝛽𝑥(𝑛+1)
𝛼
𝑅
𝑟
𝑒
𝛼𝑥(𝑛+1)
−
𝛼
𝑅
𝑟
𝑒
−𝛼𝑥(𝑛+1)
𝛽
𝑅
𝑟
𝑒
𝛽𝑥(𝑛+1)
−
𝛽
𝑅
𝑟
𝑒
−𝛽𝑥(𝑛+1)
]
]
]
]
]
]
]
]
]
]
]
]
.
(17)
The distribution of rail potential and stray current inmultitrains and multisubstations at a certain movement canbe simulated. Based on 𝑝(𝑡) and 𝑥(𝑡) of the trains in line ateach movement, 𝑢
𝑟(𝑥, 𝑡), 𝑢
𝑠(𝑥, 𝑡), 𝑖
𝑟(𝑥, 𝑡), and 𝑖
𝑠(𝑥, 𝑡) can be
simulated.
5. Simulation Results
Simulations of rail potential and stray current affected byover zone feeding are presented in this paper. Parametersof the equivalent model in the simulations are as follows:no-load voltage of the traction substation 𝑈
0= 1593V,
equivalent resistance of the traction substation𝑅eq = 0.054Ω,trigger voltage of the regenerative energy absorbing device𝑈lim = 1800V, 𝑅
𝑤= 0.01Ω/km, 𝑅
𝑟= 0.03Ω/km,
𝑅
𝑠= 0.02Ω/km, 𝐺
𝑠= 0.2 S/km, and 𝐺
𝑝= 0.2 S/km,
and the voltage convergence precision in the iteration 𝜉 =0.01V. Configuration and technical parameters used for trainmovement calculation are provided by Guangzhou MetroLine 8 and the time step in trainmovement calculation is 0.2 s.There are two trains (Tr1, Tr2) running in line powered bythree traction substations (StationA, StationB, and StationC)with the positions 𝑆A = 0m, 𝑆B = 2000m, and 𝑆C = 4000min the simulation model. OVPD is not set in the model.
5.1. Analysis of Over Zone Feeding. Multitrains and multi-substations are in parallel operation in DC traction powersystem. Simulations and analysis of over zone feeding havebeen carried out in this paper.
In the simulation, two trains run in the line from StationA to Station C, and the dwell time at Station B is 30.0 s. Thestarting times of Tr1 and Tr2 from Station A to Station C are,respectively, 0.0 s and 220.0 s. The powers and positions ofTr1 and Tr2 obtained from the train movement calculation,𝑃
1(𝑡), 𝑃2(𝑡), 𝑆1(𝑡), and 𝑆
2(𝑡), are shown in Figure 10(a). Tr1
![Page 11: Research Article Effect of Over Zone Feeding on Rail ...downloads.hindawi.com/journals/mpe/2016/6304726.pdf · Time (s) (b) Traction power of a train in a zone F : Characteristic](https://reader034.vdocuments.us/reader034/viewer/2022051913/6004ab4a263c6a53d326360c/html5/thumbnails/11.jpg)
Mathematical Problems in Engineering 11
P2
P1
S2
S1
50 100 150 200 250 300 3500Time (s)
−6000−4000−2000
020004000
Pow
er (k
W)
50 100 150 200 250 300 3500Time (s)
0
1000
2000
3000
4000
Dist
ance
(m)
(a) Train diagram in the simulation
50 100 150 200 250 300 3500Time (s)
Station 1Station 2
Station 3
1500
1550
1600
1650
1700
1750
1800
1850
Pote
ntia
l of s
ubst
atio
ns (V
)(b) Potential of catenary at three substations
50 100 150 200 250 300 3500Time (s)
Station 1Station 2
Station 3
−500
0
500
1000
1500
2000
2500
Trac
tion
curr
ent o
f sub
stat
ions
(A)
(c) Traction current of three substations
50 100 150 200 250 300 3500Time (s)
Train 1Train 2
Device 1Device 2
−4000
−3000
−2000
−1000
0
1000
2000
3000
Trac
tion
curr
ent o
f tra
ins (
A)
(d) Traction current of trains
Train 1Train 2
50 100 150 200 250 300 3500Time (s)
0102030405060708090
100110
CTR
(%)
(e) Proportion of over zone feeding
Figure 10: Simulation results of over zone feeding.
![Page 12: Research Article Effect of Over Zone Feeding on Rail ...downloads.hindawi.com/journals/mpe/2016/6304726.pdf · Time (s) (b) Traction power of a train in a zone F : Characteristic](https://reader034.vdocuments.us/reader034/viewer/2022051913/6004ab4a263c6a53d326360c/html5/thumbnails/12.jpg)
12 Mathematical Problems in Engineering
4000
2000
0Distance (m) −100
−80
−60
−40
−20
0
20
40
60
80
100
−100
−50
0
50
100
Rail
pote
ntia
l (V
)
Time (s)
0100
200300
400
(a) Variation of rail potential
0100 200 300 400
40002000
0Distance (m)Time (s)
−0.25
−0.2
−0.15
−0.1
−0.05
0
0.05
0.1
0.15
0.2
0.25
−0.4
−0.3
−0.2
−0.1
0
0.1
0.2
0.3
Pote
ntia
l of b
urie
d co
nduc
tor (
V)
(b) Potential of buried conductor
0200
400
40003000200010000Distance (m)Time (s)
0
2
4
6
8
10
−2
0
2
4
6
8
10
12
Stra
y cu
rren
t at b
urie
d co
nduc
tor (
A)
(c) Variation of stray current at buried conductor
Figure 11: Simulation results of rail potential and stray current.
arrives at Station B at the time 112.2 s and runs from StationB to Station C after 30.0 s dwell. Tr2 runs from Station A toStation B during the time of 220.0 s∼332.2 s. The variation ofpotential and current at the traction substations and trains areshown in Figures 10(b)∼10(e).
As shown in Figure 10, when Tr1 accelerates from StationA during 0.0 s∼87.4 s, train current of Tr1 comes from threetraction substations with different proportions. The propor-tion of traction current coming from over zone feedingchanges with the position of Tr1, but in a low amplitude from5.07% to 16.03%. When Tr1 begins regenerative braking at87.4 s, the potential of catenary rises rapidly to 1800V andthe regenerative energy absorbing device on Tr1 is activatedto absorb the energy. When Tr2 accelerates from Station Ato Station B from 220.0 s to 229.6 s, potentials and currentsof three substations are consistent with the process of Tr1.From the time 229.6 s to 254.6 s, regenerative braking ofTr1 has a significant impact on simulation results. Most ofthe regenerative current of Tr1 is fed back to the catenaryand supplied to Tr2; meanwhile, the current coming fromtraction substations decreases greatly. At 229.8 s, the distancebetween Tr1 and Tr2 is 3656.6m and traction current of
Tr2 is 2506.0A. Regenerative current of Tr1 is 3094.0 A, and1788.0 A of which is supplied for Tr2. The proportion oftraction current coming from over zone feeding in Tr2 is71.3%. In this case, the length of current transmission for Tr2is much longer than that when Tr1 accelerates from StationA to Station B. The maximum current of over zone feedingis 1824.4 A at 234.4 s, in which time the distance between Tr1and Tr2 is 3686.4m. When the potential of catenary reachesthe𝑈lim at the position of Tr2, the rest of regenerative currentwill be absorbed by the energy absorbing device on the train.Simulation results show that traction current coming fromover zone feeding is greatly affected by the running modes ofmultitrains and the regenerative energy saving devices.
5.2. Effects of Over Zone Feeding on Rail Potential and StrayCurrent. Field tests and simulation results show that overzone feeding will increase the length of traction currenttransmission. Simulations of rail potential and stray currentaffected by over zone feeding have been carried out with thetrain diagram shown in Figure 10(a). The variation of railpotential, potential of buried conductor, and stray current areshown in Figure 11.
![Page 13: Research Article Effect of Over Zone Feeding on Rail ...downloads.hindawi.com/journals/mpe/2016/6304726.pdf · Time (s) (b) Traction power of a train in a zone F : Characteristic](https://reader034.vdocuments.us/reader034/viewer/2022051913/6004ab4a263c6a53d326360c/html5/thumbnails/13.jpg)
Mathematical Problems in Engineering 13
0
1000
2000
3000
4000D
istan
ce (m
)
−5000
0
5000
Pow
er (k
W)
50 100 150 200 250 300 350 4000Time (s)
50 100 150 200 250 300 350 4000Time (s)
S2-1S1
S2-3S2-2
P2-1P1
P2-3P2-2
(a) Three train diagrams in simulation
50 100 150 200 250 300 350 4000Time (s)
−20
0
20
40
60
80
100
Rail
pote
ntia
l (V
)Case 2-2Case 2-1 Case 2-3
(b) Comparison of rail potential at 𝑥 = 200m
Figure 12: Comparison of rail potential in different train diagrams.
Table 4: Summary of simulation results for different diagrams (𝑥 =200m).
Items Cases𝑆
2-1 𝑆
2-2 𝑆
2-3
Max. rail potential (V) 30.26 98.00 31.53Max. stray current (A) 0.64 2.37 0.71Max. buried conductor potential (V) 0.08 0.29 0.08Traction current of train (A) 2624.0 2659.0 2600.1CTR of train current (%) 5.6 68.58 6.3
Figure 11(a) shows the rail potential at each positionchanging with time. At the same position, such as 𝑥 = 0m,the rail potential when Tr2 accelerates from 220.0 s to 244.6 sis much higher than that when Tr1 accelerates from 0.0 sto 24.6 s. The highest rail potential occurs at the positionof the train. The potential of buried conductor illustratedin Figure 11(b) shows the same trend as Figure 11(a). InFigure 11(c), stray current with larger proportion of currentcoming from over zone feeding is much higher than that witha lower proportion, and the highest stray current occurs at themiddle of Tr1 and Tr2. Figures 11(a)∼11(c) show that over zonefeeding has a great impact on rail potential and stray current.
The extent of over zone feeding will be changed in differ-ent train diagrams. As shown in Figure 12(a), three diagramsare set in the simulation. In the diagrams Tr2 starts at 150.0 s,220.0 s, and 254.6 s, respectively. Figure 12(b) shows thesimulation results of rail potential at 𝑥 = 200m in differentdiagrams.
Summary of simulation results on rail potential is shownin Table 4. Comparing the simulation results at 𝑥 = 200min three diagrams, significant differences of maximum railpotential and stray current exist with different extent of overzone feeding. Maximum rail potential is 98.00V when Tr2runs with the diagram 𝑆
2-2. At this point of time, the traction
current of Tr2 is 2659.0A, 68.58% of which comes fromover zone feeding. As a comparison,maximum rail potentialsare 30.26V and 31.53V, respectively, when Tr2 runs withdiagrams 𝑆
2-1 and 𝑆
2-3.
Extent of over zone feeding also can be changed bydifferent starting voltage of the regenerative energy absorbingdevice. Three cases are set in the simulation with different𝑈lim in the same train diagram shown in Figure 10(a). In Case1 and Case 2, 𝑈lim are 1800V and 1700V, respectively, andin Case 3, the regenerative energy is all absorbed by energysaving device on the train instead of being fed back to thecatenary. Figure 13 shows the simulation results in three cases.
Figure 13(a) shows the proportions of traction currentcoming from over zone feeding in three cases when Tr2 runsfrom Station A to Station B. From 244.4 s to 254.4 s, CTRof Case 1 and Case 2 are in the same value. CTR of Case1, Case 2, and Case 3 is the same from 254.4 s to 350 s. Inacceleration process of Tr2 from 229.8 s to 244.4 s, CTR ofCase 1 is the highest of the three cases; therefore, the tractioncurrent comes from over zone feeding for Tr1 is the highest.Figure 13(b) shows that the maximum amplitude of tractioncurrent coming from over zone feeding in three cases is1903.1 A, 1240.4A, and 167.6 A, respectively, with the samedistance of transmission. Figure 13(c) shows the simulationresults of rail potential at 𝑥 = 200m in three cases. Maximum
![Page 14: Research Article Effect of Over Zone Feeding on Rail ...downloads.hindawi.com/journals/mpe/2016/6304726.pdf · Time (s) (b) Traction power of a train in a zone F : Characteristic](https://reader034.vdocuments.us/reader034/viewer/2022051913/6004ab4a263c6a53d326360c/html5/thumbnails/14.jpg)
14 Mathematical Problems in Engineering
50 100 150 200 250 300 3500Time (s)
0
10
20
30
40
50
60
70
80
90
100
110
CTR
(%)
Case 2Case 1 Case 3
(a) CTR in different cases
Current absorbed by energy absorbing device on train
50 100 150 200 250 300 3500Time (s)
−3000
−2000
−1000
0
1000
2000
3000
Curr
ent f
rom
ove
r zon
e fee
ding
(A)
Traction current of the trainCase 1
Case 2Case 3
(b) Current from over zone feeding in different cases
Case 1Case 2
Case 3
−20
0
20
40
60
80
100
Rail
pote
ntia
l (V
)
50 100 150 200 250 300 3500Time (s)
(c) Comparison of rail potential at 𝑥 = 200m
Figure 13: Comparison of rail potential in different cases.
rail potentials in Case 1, Case 2, and Case 3 are 98.00V,64.89V, and 31.59V, respectively, andmaximum stray currentat 𝑥 = 200m in three cases is 2.37 A, 1.54A, and 0.71 A,respectively.
On basis of the simulation results, rail potential and straycurrent are highly influenced by the extent of over zonefeeding which can be changed by train diagrams or differentstarting voltage of the regenerative energy absorbing device.
6. Summary and Conclusion
In this paper, influence of over zone feeding on rail potentialand stray current has been proposed in DC mass transitsystem and results of field tests and simulations have beenpresents. Conclusions can be drawn as follows:
(1) The phenomenon of over zone feeding exists widelyin DC mass transit system for electrical connectivityof the catenary. Extent of over zone feeding is relatedto the running mode of the trains in line, and it willbe exacerbated when the braking energy fed back tothe catenary is absorbed by other running trains. Inextreme cases, all traction current of the acceleratingtrain comes from the energy fed back by the brakingtrain. When the braking energy fed back to thecatenary surpasses the absorption capability of otherrunning trains, voltage of the catenary will increaserapidly, therefore, triggering the energy saving device.
(2) Rail potential and stray current are highly related toover zone feeding, which will be higher when theextent of over zone feeding is exacerbated in the same
![Page 15: Research Article Effect of Over Zone Feeding on Rail ...downloads.hindawi.com/journals/mpe/2016/6304726.pdf · Time (s) (b) Traction power of a train in a zone F : Characteristic](https://reader034.vdocuments.us/reader034/viewer/2022051913/6004ab4a263c6a53d326360c/html5/thumbnails/15.jpg)
Mathematical Problems in Engineering 15
traction current of the train. According to the sim-ulating results, the maximum rail potential is 31.53Vwhen the proportion of traction current coming fromover zone feeding is 6.3%, while the maximum railpotential is 98.00V when the proportion is 68.58%.
(3) The extent of over zone feeding will be changed bydifferent train diagrams or different starting voltage ofthe energy absorbing device and these methods canbe applied to the control of rail potential and straycurrent.
(4) The dynamic analysis model proposed in this papercan be effectively used in analyzing the effect of overzone feeding on rail potential and stray current withmultiple trains running in multiple zones.
Conflict of Interests
The authors declare that there is no conflict of interestsregarding the publication of this paper.
Acknowledgments
This work is supported by the National Natural ScienceFoundation of China (Grant no. 51147011), the JiangsuProvincial Natural Science Foundation of China (Grant no.BK20130187), and the Research and Innovation Program ofPostgraduates of Jiangsu Province (KYLX 1383).
References
[1] J. G. Yu and C. J. Goodman, “Modelling of rail potential riseand leakage current in DC rail transit systems,” in Proceedingsof the IEE Colloquium on Stray Current Effects of DC Railwaysand Tramways, London, UK, October 1990.
[2] J. G. Yu, “The effects of earthing strategies on rail potentialand stray currents in DC transit railways,” in Proceedings ofthe International Conference on Developments in Mass TransitSystems, Conference Publication no. 453, pp. 303–309, London,UK, April 1998.
[3] C.-H. Lee and H.-M. Wang, “Effects of grounding schemes onrail potential and stray currents in Taipei Rail Transit Systems,”IEE Proceedings: Electric Power Applications, vol. 148, no. 2, pp.148–154, 2001.
[4] I. Cotton, C. Charalambous, P. Aylott, and P. Ernst, “Straycurrent control in DC mass transit systems,” IEEE Transactionson Vehicular Technology, vol. 54, no. 2, pp. 722–730, 2005.
[5] W. Ping, “Analysis on rail potential in transit,” Modern UrbanTransit, no. 2, pp. 67–73, 2014.
[6] M. Yinshan, “Frame protection breakdown caused by refusingaction of rail potential limit equipment,” Urban Rapid RailTransit, no. 3, pp. 92–94, 2008.
[7] Y. C. Liu and J. F. Chen, “Control scheme for reducing railpotential and stray current in MRT systems,” IEE Proceedings-Electric Power Applications, vol. 152, no. 3, pp. 612–618, 2005.
[8] C.-H. Lee, “Evaluation of the maximum potential rise in Taipeirail transit systems,” IEEE Transactions on Power Delivery, vol.20, no. 2, pp. 1379–1384, 2005.
[9] C.-H. Lee and C.-J. Lu, “Assessment of grounding schemes onrail potential and stray currents in a DC transit system,” IEEE
Transactions on Power Delivery, vol. 21, no. 4, pp. 1941–1947,2006.
[10] Y.-S. Tzeng and C.-H. Lee, “Analysis of rail potential and straycurrents in a direct-current transit system,” IEEE Transactionson Power Delivery, vol. 25, no. 3, pp. 1516–1525, 2010.
[11] S.-L. Chen, S.-C. Hsu, C.-T. Tseng, K.-H. Yan, H.-Y. Chou, andT.-M. Too, “Analysis of rail potential and stray current for TaipeiMetro,” IEEE Transactions on Vehicular Technology, vol. 55, no.1, pp. 67–75, 2006.
[12] S.-Y. Xu, W. Li, and Y.-Q. Wang, “Effects of vehicle runningmode on rail potential and stray current in DC mass transitsystems,” IEEETransactions onVehicular Technology, vol. 62, no.8, pp. 3569–3580, 2013.
[13] C. L. Pires, S. I. Nabeta, and J. R. Cardoso, “ICCG methodapplied to solve DC traction load flow including earthingmodels,” IET Electric Power Applications, vol. 1, no. 2, pp. 193–198, 2007.
[14] A. Dolara, F. Foiadelli, and S. Leva, “Stray current effectsmitigation in subway tunnels,” IEEE Transactions on PowerDelivery, vol. 27, no. 4, pp. 2304–2311, 2012.
[15] C. A. Charalambous, I. Cotton, and P. Aylott, “Modeling forpreliminary stray current design assessments: the effect ofcrosstrack regeneration supply,” IEEE Transactions on PowerDelivery, vol. 28, no. 3, pp. 1899–1908, 2013.
[16] C. A. Charalambous and P. Aylott, “Dynamic stray currentevaluations on cut-and-cover sections of DC metro systems,”IEEE Transactions on Vehicular Technology, vol. 63, no. 8, pp.3530–3538, 2014.
[17] A. Ogunsola, L. Sandrolini, and A. Mariscotti, “Evaluation ofstray current from a DC-electrified railway with integratedelectric-electromechanical modeling and traffic simulation,”IEEE Transactions on Industry Applications, vol. 51, pp. 5431–5441, 2015.
[18] Y.-S. Tzeng and R.-N. Wu, “Electric network solutions of dctransit systems with inverting substations,” IEEE Transactionson Vehicular Technology, vol. 47, no. 4, pp. 1405–1412, 1998.
[19] Y.-S. Tzeng, N. Chen, and R.-N. Wu, “Modes of operation inparallel-connected 12-pulse uncontrolled bridge rectifiers with-out an interphase transformer,” IEEE Transactions on IndustrialElectronics, vol. 44, no. 3, pp. 344–355, 1997.
[20] M. Wu, “Uniform chain circuit model for traction networks ofelectric railways,” Proceedings of the Csee, vol. 30, no. 28, pp. 52–58, 2010.
[21] Y. Cai, M. R. Irving, and S. H. Case, “Compound matrixpartitioning andmodification for the solution of branched auto-transformer traction feeds,” IEE Proceedings—Electric PowerApplications, vol. 143, no. 3, pp. 251–257, 1996.
![Page 16: Research Article Effect of Over Zone Feeding on Rail ...downloads.hindawi.com/journals/mpe/2016/6304726.pdf · Time (s) (b) Traction power of a train in a zone F : Characteristic](https://reader034.vdocuments.us/reader034/viewer/2022051913/6004ab4a263c6a53d326360c/html5/thumbnails/16.jpg)
Submit your manuscripts athttp://www.hindawi.com
Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014
MathematicsJournal of
Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014
Mathematical Problems in Engineering
Hindawi Publishing Corporationhttp://www.hindawi.com
Differential EquationsInternational Journal of
Volume 2014
Applied MathematicsJournal of
Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014
Probability and StatisticsHindawi Publishing Corporationhttp://www.hindawi.com Volume 2014
Journal of
Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014
Mathematical PhysicsAdvances in
Complex AnalysisJournal of
Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014
OptimizationJournal of
Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014
CombinatoricsHindawi Publishing Corporationhttp://www.hindawi.com Volume 2014
International Journal of
Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014
Operations ResearchAdvances in
Journal of
Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014
Function Spaces
Abstract and Applied AnalysisHindawi Publishing Corporationhttp://www.hindawi.com Volume 2014
International Journal of Mathematics and Mathematical Sciences
Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014
The Scientific World JournalHindawi Publishing Corporation http://www.hindawi.com Volume 2014
Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014
Algebra
Discrete Dynamics in Nature and Society
Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014
Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014
Decision SciencesAdvances in
Discrete MathematicsJournal of
Hindawi Publishing Corporationhttp://www.hindawi.com
Volume 2014 Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014
Stochastic AnalysisInternational Journal of