Changing of Basic date same as to Rescheduling date in mass using COHV : Step 1: Run MD04 t-code and check the rescheduling dates for each production order and also check what is the exceptional message(10/15), Here basic start date is different compare to rescheduling date with exceptional message 10, so we have to change this basic start date same as to rescheduling date using COHV.

Upload: mahendranpsiva

Post on 04-Sep-2015

4 views

Category:

Documents


3 download

DESCRIPTION

rescheduling

TRANSCRIPT

Changing of Basic date same as to Rescheduling date in mass using COHV :Step 1:

Run MD04 t-code and check the rescheduling dates for each production order and also check what is the exceptional message(10/15),

Here basic start date is different compare to rescheduling date with exceptional message 10, so we have to change this basic start date same as to rescheduling date using COHV.

Step 2: Run OPU3 t-code and select your order type and set data like below and save.

Step 3:

Run COHV t-code and check the basic start dates.

Select mass processing option(Ctrl f8) and set the data like below and select adopt.

Select orders which we want to change Basic start date.

After selecting orders execute the process(f8).

Now basic start dates same as rescheduling date.

Check once again in MD04 the basic start date ,