Requirements, Resource Planning and Management for Decrewing/Recrewing Scenarios of the International Space Station David A. Bach [email protected] Barrios Technology, Inc. NASA Johnson Space Center

Upload: others

Post on 22-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Requirements, Resource Planning and Management for ...iaass.space-safety.org/wp-content/uploads/sites/28/... · Lessons Learned 2 . BACKGROUND •On August 24, 2011, the propulsion

Requirements, Resource Planning and Management for Decrewing/Recrewing

Scenarios of the International Space Station

David A. Bach [email protected] Barrios Technology, Inc.

NASA – Johnson Space Center

Page 2: Requirements, Resource Planning and Management for ...iaass.space-safety.org/wp-content/uploads/sites/28/... · Lessons Learned 2 . BACKGROUND •On August 24, 2011, the propulsion

TOPICS COVERED

• August 2011 Decrewing Background and History

• Increment Support

• Priority Integration

• Recommendations and Lessons Learned

2

Page 3: Requirements, Resource Planning and Management for ...iaass.space-safety.org/wp-content/uploads/sites/28/... · Lessons Learned 2 . BACKGROUND •On August 24, 2011, the propulsion

BACKGROUND

• On August 24, 2011, the propulsion unit of the Soyuz-U rocket carrying 44 Progress (44P) failed. The rocket and cargo was lost.

• The failure occurred, five months into the six month Expedition 27/28 Mission.

• No crew or ground personnel were injured.

3

Expedition 28 Crew

Page 4: Requirements, Resource Planning and Management for ...iaass.space-safety.org/wp-content/uploads/sites/28/... · Lessons Learned 2 . BACKGROUND •On August 24, 2011, the propulsion

WHAT HAPPENED

• Subsequent Russian launches using the Soyuz rocket (-U and -FG series) were suspended pending analysis and Russian Commission results.

• The two Soyuz vehicles docked to ISS for the Expedition 28 crew were unaffected by the failure of 44P.

4

Launch of 43P - June 21, 2011

Page 5: Requirements, Resource Planning and Management for ...iaass.space-safety.org/wp-content/uploads/sites/28/... · Lessons Learned 2 . BACKGROUND •On August 24, 2011, the propulsion

5

Page 6: Requirements, Resource Planning and Management for ...iaass.space-safety.org/wp-content/uploads/sites/28/... · Lessons Learned 2 . BACKGROUND •On August 24, 2011, the propulsion

6

As Flown Post-44P Incident Flight Program / Port Utilization Plan

Baselined Flight Program / Port Utilization Plan PLANNED & EXECUTED FLIGHT PROGRAMS

Page 7: Requirements, Resource Planning and Management for ...iaass.space-safety.org/wp-content/uploads/sites/28/... · Lessons Learned 2 . BACKGROUND •On August 24, 2011, the propulsion

DECREW ASSESSMENT TEAMS

• Joint Operations Panel established with Splinter teams to assess decrewing, sustained uncrewed operations, and subsequent recrewing of the ISS

• Splinters were chaired by various ISSP teams

7

26S departs the ISS on September 16, 2011. Expedition 29 begins with only 3 crew members onboard for 61 days (four times longer than originally planned).

Page 8: Requirements, Resource Planning and Management for ...iaass.space-safety.org/wp-content/uploads/sites/28/... · Lessons Learned 2 . BACKGROUND •On August 24, 2011, the propulsion

ASSESSMENT GUIDELINES

• Existing ISS Program and Flight Rule documentation was used by the Splinters in developing crew and ground actions.

8

Fossum works with Robonaut 2 in the Destiny laboratory . Fossum and Furukawa performed checkout and operations with R2.

Page 9: Requirements, Resource Planning and Management for ...iaass.space-safety.org/wp-content/uploads/sites/28/... · Lessons Learned 2 . BACKGROUND •On August 24, 2011, the propulsion

VEHICLE MANIFEST & CONSUMABLES SPLINTER

• ISSP Representatives chaired the Vehicle Manifest and Consumables splinter.

• Splinter’s two main goals were: 1. Review trash projected to be on

the ISS at the time of decrewing, and develop mitigation plans if any trash posed risks to a decrewed ISS,

2. Identify any hardware or consumables that would need to be manifested on the vehicle that recrewed ISS.

9

Expedition 29 Flight Engineer Furukawa amongst stowage in the PMM

Page 10: Requirements, Resource Planning and Management for ...iaass.space-safety.org/wp-content/uploads/sites/28/... · Lessons Learned 2 . BACKGROUND •On August 24, 2011, the propulsion

WASTE DISPOSAL PLANNING

• Manifest Splinter Team identified high priority items that needed to be disposed of on 42P.

• Items generated between 42P departure and decrewing would require coordination for “long term” stowage on ISS or for disposal in the БО of 27S.

10

42P departing the ISS on October 29, 2011. 42P was the last disposal vehicle prior to the decrewing decision to be made based on 28S arrival, scheduled for November 16, 2011.

29S docked to the Rassvet Mini-Research Module 1 (MRM1) in foreground, 47P in background docked to the Functional Cargo Block(FGB).

Instrumentation and Propulsion Module [ПАО]

Descent Module [CA]

Orbital Compartment [БО]

Page 11: Requirements, Resource Planning and Management for ...iaass.space-safety.org/wp-content/uploads/sites/28/... · Lessons Learned 2 . BACKGROUND •On August 24, 2011, the propulsion

CONSUMABLES PLANNING – USED

Analysis of ISS consumables was performed for both Short and Long Term decrewing and for two categories of consumables:

1. Consumables used throughout the decrewed phase or prior to recrewing, Propellant (required to maintain

vehicle altitude, attitude, velocity, and perform Debris Avoidance Maneuvers),

Nitrogen (lost through tank and ISS stack leakage rates),

Oxygen (lost through tank and ISS stack leakage rates)

11

View from the Cupola across the Unity Node 1 to the Quest Airlock. Three of five High Pressure Gas Tanks and the Starboard Solar Arrays are in view.

Page 12: Requirements, Resource Planning and Management for ...iaass.space-safety.org/wp-content/uploads/sites/28/... · Lessons Learned 2 . BACKGROUND •On August 24, 2011, the propulsion

CONSUMABLES PLANNING – EXPIRING

2. Consumables not used during decrew phase, however may expire prior to recrew, Water, Water (liquid) Containers

(EДВs and CWCs), Recycle Filter Tank Assemblies

and Advanced Recycle Filter Tank Assemblies,

Food, Crew Provisions, Waste Hardware (Solid Waste

Containers, Filter Inserts, Toilet Inserts).

12

CWC Water Stowage bags

Stack of EДВs in Russian Segment

Page 13: Requirements, Resource Planning and Management for ...iaass.space-safety.org/wp-content/uploads/sites/28/... · Lessons Learned 2 . BACKGROUND •On August 24, 2011, the propulsion

DECREW / RECREW CONFIGURATION

• Hardware required for recrewing the ISS would be flown with the new crew, on a vehicle arriving close to their recrewing time, available through appropriate stowage locations. – Manifest updates would be

addressed as required and based on decrewing duration.

• The different modules and systems were configured keeping to the established Uncrewed Priorities to enable for a recrewing, continued science during a decrewed phase, and maintaining sufficient redundancies.

13

Expedition 29 Commander Mike Fossum in the LAB installing the Secondary Power Distribution Assembly Jumper. The SPDA jumper would provide a redundant power path should it be needed during a decrewed ISS phase.

Page 14: Requirements, Resource Planning and Management for ...iaass.space-safety.org/wp-content/uploads/sites/28/... · Lessons Learned 2 . BACKGROUND •On August 24, 2011, the propulsion

PRIORITIZATION OF TASKS

• Decrewing requirements were identified by the JOP teams, and through the nominal process, integrated to the standard Increment Requirements documents.

• Through the execution of the priorities, Expedition 29 was able to both prepare for a potential decrewing, while maintaining crew and vehicle health, and completing utilization tasks.

14

Fossum installing the Advanced Recycle Filter Tank Assembly on Oct 10, 2011. The priority for checkout of the ARFTA was elevated following the 44P accident.

Page 15: Requirements, Resource Planning and Management for ...iaass.space-safety.org/wp-content/uploads/sites/28/... · Lessons Learned 2 . BACKGROUND •On August 24, 2011, the propulsion

RETURN TO FULL CREW COMPLEMENT

• Following the successful launching and docking of both 45P and 28S, the ISS teams stood down from further decrewing activities.

• The 6-crew stage after 28S arrival lasted 4.5 days, followed by one month of 3-crew operations prior to 29S arrival in December.

• The crews were able to meet the high priority ISSP objectives, including performing an average of more than 35 hrs per week utilization over both Increments.

15

28S successfully docked to the ISS on Nov 16, 2011. The six crewmembers had 4.5 crew days together prior

to 27S undocking on Nov 22, 2011.

29S arrived on Dec 23, 2011, bringing the ISS to its nominal 6-crew compliment again. 28S undocked on April 27, 2012.

Page 16: Requirements, Resource Planning and Management for ...iaass.space-safety.org/wp-content/uploads/sites/28/... · Lessons Learned 2 . BACKGROUND •On August 24, 2011, the propulsion

Thank you. Questions?

16

REQUIREMENTS, RESOURCE PLANNING AND MANAGEMENT FOR DECREWING/RECREWING SCENARIOS OF THE INTERNATIONAL SPACE STATION

David A. Bach (1), Susan N. Brand (2), Pete Hasbrook (3) (1)Barrios Technology, LTD. NASA-JSC. Mail Code OP/MAPI, 2101 NASA Parkway, Houston, TX 77058, USA

Email: [email protected] (2)NASA-JSC. Mail Code OC3, 2101 NASA Parkway, Houston, TX 77058, USA

Email: [email protected] (3)NASA-JSC. Mail Code OZ12, 2101 NASA Parkway, Houston, TX 77058, USA

Email: [email protected]