required contract provisions€¦ · west warwick, ri 02893 contact person: david velilla, (401)...

145
GENERAL PROVISIONS – CONTRACT SPECIFIC

Upload: others

Post on 26-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

GENERAL PROVISIONS – CONTRACT SPECIFIC

Page 2: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

CS-1

SPECIFICATIONS – CONTRACT SPECIFIC

Page 3: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

CS-2

INDEX

SPECIFICATIONS – CONTRACT SPECIFIC

RIC No. 2017-CB-070

PARAGRAPH TITLE PAGE

1 Brief Scope of Work CS-3

2 List of Contract Drawings CS-4

3 Utility and Municipal Notification and Coordination CS-6

4 Specialty Items CS-7

5 Notice to Contractors CS-7

6 Sequence of Construction and Schedule CS-11

7 Lump Sum Bid Items CS-13

8 Transportation Management Plan CS-13

9 Environmental Permits CS-13

10 Coordination with Other Contracts CS-13

11 Steel Fabrication and Delivery CS-14

Appendix A Contractor Submittal List CS-15

Appendix B Transportation Management Plan CS-20

Appendix C Storm Water Pollution Prevention Plan (SWPPP) CS-56

Appendix D Pavement Cores CS-57

pfowler
Text Box
113
Page 4: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

CS-3

1. BRIEF SCOPE OF WORK

RI Contract No. 2017-CB-070, RI Federal Aid Project No. BRO-0472(001), for the Superstructure

Replacement of Horton Farm Road Bridge No. 472 over I-195 corridor in the City of East

Providence, County of Providence. The work will be completed using the Accelerated Bridge

Construction (ABC) method. ABC will be accomplished by the use of, but not limited to,

prefabricated modular girder units and prefabricated deck panels for the superstructure and precast

concrete elements for the approach slabs. Construction will include, but not be limited to the

complete demolition of the existing bridge superstructure, including, but not limited to pier cap,

pier columns, and pier footings, top of abutment backwalls, wingwall barriers, and approach slabs

to the limits shown on the contract drawings. The bridge work will be completed in two stages.

For each stage, the work for the bridge superstructure shall include the installation of the

superstructure comprising two steel plate girder modular units, single plate girders and precast

concrete deck panels. Ultra-High Performance Concrete (UHPC) will be utilized for the transverse

closure pours between the deck panel and for the longitudinal closure pours between the Stage 1

and Stage 2 deck panels. Non-shrink grout will be utilized for the shear stud block-outs. The bridge

concrete traffic barrier will be cast-in-place onto the deck panels. The work for the bridge

substructure shall include, but not limited to, the installation of cast-in-place pier footings, pier

columns, pier caps, new approach slab supports at the backwalls, wingwall barriers and endposts,

and precast concrete elements for the approach slabs for both north and south abutments. The

precast concrete elements will be connected using cast-in-place closure pours. Additional

substructure work includes the demolition and concrete repair of portions of the existing concrete

abutment faces and wingwall faces.

RI Federal Aid Project No. STP-RESF(360), for the I-195 corridor improvements shall also

include, but is not limited to roadway micro-milling and overlay, full depth roadway construction

at utility trenches, cleaning and flushing storm drain pipes, cleaning and repairing storm drain

structures, adjusting storm drain structures frames, removal of existing guide signs and

replacement with new signs, removal of existing roadway lighting and replacement with new

lighting along I-195, associated ramps, and on Horton Farm Road Bridge 472. The work on

Horton Farm Road at the Bridge 472 approaches shall include, but is not limited to roadway

micro-milling and overlay, and full-depth construction The roadway work for this project will in

general consist of erosion and sediment control, clearing and grubbing, saw cutting, pavement

removal, excavation and grading, trimming and fine grading, dust control, bituminous pavement,

gravel borrow for subbase course, curbing, sidewalk, pavement markings, drainage, landscaping,

plantable soil borrow and seed, traffic control, uniform traffic persons, flag persons, temporary

construction signs, temporary closures, maintenance and protection of traffic, signs, guard rail

replacement, lighting, and construction field office.

Page 5: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

CS-4

2. LIST OF CONTRACT DRAWINGS

Volume 1 of 2 Horton Farm Road Bridge No. 472 Highway Plans

Sheet No. Description

1 Cover Sheet

2 Standard Plan Symbols & Standard Legend

3 Standard Notes ‐ 1

4 Standard Notes ‐ 2

5 Job-Specific Plan Symbols, Legend & Notes

6 Key Plan

7‐11 Typical Sections

12‐22 General Plans

23-24 General Details

25-35 Drainage Plan & Utility Plans

36 Drainage Details

37-47 Location Plans

48-51 Traverse Plans

52-53 Profile – Lane F (Horton Farm Road)

54 Grade Plan – Lane F (Horton Farm Road)

55-65 Lighting Plans

66-71 Lighting Details

72-82 Signing and Striping Plans

83-93 Guide Sign Placement Plans

94 Traffic Sign Summary

95 Guide sign Cross Sections

96-97 Sign Panel Details

98-100 Detour Plans

101-136 Maintenance and Protection of Traffic Plans

137 Temporary Traffic Control Mobile Operation

138 Construction Sign Summary

139-144 Cross Sections – Lane “F” (Horton Farm Road)

Volume 2 of 2 Horton Farm Road Bridge No. 472 Bridge Plans

Sheet No. Description

1 Cover Sheet & Index

2 Bridge Abbreviations & General Legend

3 Profiles

4 General Bridge Notes Sheet 1 of 3

5 General Bridge Notes Sheet 2 of 3

6 General Bridge Notes Sheet 3 of 3

7 General Plan and Elevation

8 Typical Bridge and Approach Sections

9 Construction Staging & Demolition Details Sheet 1 of 3

10 Construction Staging & Demolition Details Sheet 2 of 3

Page 6: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

CS-5

11 Construction Staging & Demolition Details Sheet 3 of 3

12 Anchored Precast Concrete Barrier for Temporary Traffic Control

13 Temporary Protective Shielding Details

14 Abutment and Pier Demolition Plan

15 North Abutment Rehabilitation and Backwall Demolition

16 South Abutment Rehabilitation and Backwall Demolition

17 Wingwall Demolition and Rehabilitation Details Sheet 1 of 3

18 Wingwall Demolition and Rehabilitation Details Sheet 2 of 3

19 Wingwall Demolition and Rehabilitation Details Sheet 3 of 3

20 Pier Demolition

21 Rehabilitation Details

22 North Abutment Plan and Elevation

23 South Abutment Plan and Elevation

24 Abutment Details

25 Wingwall Details Sheet 1 of 2

26 Wingwall Details Sheet 2 of 2

27 Wingwall Details Sheet 3 of 3

28 Geogrid plan and Details

29 Pier Plan and Elevation

30 Pier Sections and Details Sheet 1 of 2

31 Pier Sections and Details Sheet 2 of 2

32 Precast Tolerance Details

33 Framing Plan

34 Girder Elevation and Details

35 Steel Details

36 Diaphragm Details

37 Camber Table

38 Deck Grades

39 Deck Panel Layout Plan

40 Deck Reinforcement Details

41 Deck Panel Details Sheet 1 of 2

42 Deck Panel Details Sheet 2 of 2

43 Closure Pour Reinforcement Plan

44 Bearing Details Sheet 1 of 3

45 Bearing Detail Sheet 2 of 3

46 Bearing Detail Sheet 3 of 3

47 Roadway Joints

48 Light Standard Details

49 Snow Fence Details

50 End Post Details

51 Boring Logs Sheet 1 of 2

52 Boring Logs Sheet 2 of 2

53 Test Pit Logs

Page 7: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

CS-6

3. UTILITY AND MUNICIPAL NOTIFICATION AND COORDINATION

Upon award, the Contractor shall notify all applicable utility companies relative to their anticipated

construction start date. Immediately following the Pre‐construction Conference, the Contractor shall

initiate any and all required utility notifications. The Contractor shall coordinate his work to ensure

that all utility cut‐offs may proceed without delay. The Contractor’s attention is drawn to the

accelerated project delivery method and the need to ensure that all notification and coordination are

completed as not to interfere with the project milestones

COX COMMUNICATIONS

9 J.P. Murphy Hwy.

West Warwick, RI 02893

Contact person: David Velilla, (401) 615‐1284

EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS

145 Taunton Avenue

East Providence, RI 02914

All Correspondence to: Stephen H. Coutu, Director of Public Works, 435‐7701

EAST PROVIDENCE FIRE DEPARTMENT

913 Broadway

East Providence, RI 02914

All correspondence to: Chief Joseph J. Klucznik, 435‐7677

Contact Person: Robert Powers, Superintendent of Fire Alarm, (401)435-1939

EAST PROVIDENCE WATER DEPARTMENT

60 Commerce Way

East Providence, RI 02914

All correspondence to: Kenneth Booth, Water Utilities Superintendent (401)435‐7741

NATIONAL GRID (ELECTRIC)

280 Melrose Street

Providence, RI 02907

All correspondence to: Thomas Capobianco, (401) 784‐7248

Contact Person: George N. Bolden

NATIONAL GRID (GAS)

40 Sylvan Road

Waltham, MA 02451

All correspondence to:

Construction: Steve Meighan, (401)525-5694, [email protected]

Engineering: Jim Paulette (401)465-8580, [email protected]

VERIZON

85 High Street

Floor 1

Page 8: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

CS-7

Pawtucket, RI 02860

All correspondence to: Anthony Filomeno, State Highway Administrator, (401)727‐9543

The Contractor shall contact DIG SAFE (1‐888‐344‐7233) prior to commencing with construction.

The locations of existing utilities have been shown on the Plans using the best available

information and are approximate only. The Contractor shall verify the exact locations of all

existing utilities and service connections both underground and overhead in accordance with DIG

SAFE and the city of East Providence prior to commencing any work that may impact the utilities

in the area. Any damage to the utilities, which are detailed by DIG SAFE or shown on the Plans,

shall be the Contractor’s responsibility. The cost to repair such damage shall be borne by the

Contractor.

The Contractor is responsible for protecting the existing underground conduits that are located

within the project area. If these conduits are damaged by construction operations, it shall be the

responsibility of the Contractor to replace these conduits as directed by the Engineer.

4. SPECIALTY ITEMS

The following items are hereby designated as “Specialty Items”

1. Pavement Markings

2. Guardrail

3. Structural Steel

4. Chain Link Fence

5. Electrical

6. Sign Panels

7. Sign Structure

8. Paving

9. Bridge Bearings

5. NOTICE TO CONTRACTORS

1. Due to the use of ABC method of delivery for this project, the contractor attention is

directed to the following activities, among others, anticipated as being on the

Critical Path for Project completion:

• Submittal, reviewing and approval of all prefabricated concrete deck

panels, Individual Girders, as well as the substructure Precast Concrete

Elements PCEs

• Fabrication of the precast concrete deck panels, as well as the PCEs for the

approach slabs.

• Critical submittals are flagged as structural steel fabrication and erection

shop drawings, crane submittals, reinforcing steel, demolition plans,

Sequence plan, temporary protective shields, concrete mix, UHPC,

temporary shoring, and bearing.

Page 9: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

CS-8

• Critical submittals will be reviewed by the Engineer and returned to the

Contractor for appropriate action within Twenty Eight (28) calendar days

of submission.

2. The Contractor shall not be permitted to close the easterly lanes of Horton

Farm Road to traffic or start any demolition activities prior to complete

fabrication of all precast concrete deck panels and PCEs, including all

construction material and equipment required for the construction of the new

bridge.

3. Once the Engineer’s approval is granted to proceed with Stage 1, the

Contractor will be permitted to close the easterly lanes of Horton Farm

Road in accordance with the Contract Documents to begin the Stage 1

Demolition and Construction work.

4. The Contractor shall provide a storage/laydown site for storing the

prefabricated bridge elements at the Contractors own expense. The

Contractor shall submit the location of the storage/laydown site for review

and approval to the Department prior to the commencement of work.

Compensation for out of state inspection service shall be in accordance with

RI Standard Specifications Section 809.

5. The Contractor’s attention is directed to the following contract milestones;

Milestone

#1 - Interim Completion Date #1 – Full Bridge Open to Traffic

#2 - Substantial Completion

• Milestone #1 is defined as the completed bridge structure with all lanes on

Horton Farm Road open to all traffic.

• Milestone #2 is defined as Substantial Completion per specification 101.71 and

including all of the Works of the Bridge, final striping as well as Horton Farm

Road and I-195 work.

6. The Contractor shall furnish the Engineer with time-lapse high end imaging

documenting all of the construction activities starting with Stage 1

demolition and ending with the completion of Milestone #2.

7. The Contractor must provide all of the required detours in accordance with

the TMP during the staged construction of the Horton Farm Road Bridge

472.

8. Due to the nature of the ABC project delivery method, NO winter shutdown

is allowed.

9. The Contractor is reminded of the ABC nature of this contract and shall note

specification “105.02 Plans and Shop Drawings”. The Contractor shall submit

duplicate Shop Drawings (two copies per submittal) directly to the attention

of the Consulting Engineer (Louis Berger, 117 Kendrick Street, Suite #400,

Needham, MA 02494, Attn: Phineas Fowler, PE) simultaneously with each

of his official submittals to the Department.

Page 10: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

CS-9

10. The Contractor shall submit Requests for Information (RFI) through the

RIDOT’s Project Management Portal.

11. Strict adherence to the regulatory agencies’ permit requirements is

mandatory.

12. The Department has obtained all necessary permits to build the job as shown

in the contract documents. Proposals by the Contractor which require

modifications to the permits shall be at the Contractor’s expense.

13. The Contractor shall coordinate through RIDOT if modification is required

for any permit that is included in this Contract.

14. Approval of the work schedule and time schedule by the Department is

required before the start of any construction or other work associated with

this contract.

15. The Contractor shall notify the Department in writing at least fourteen (14)

days in advance of any intended lane restrictions and/or closures so that

adequate public notice can be given. Upon the Engineer’s approval, the

Contractor shall coordinate the required traffic control.

16. The Contractor may work 24 hours a day, 7 days per week as long as the work

is within the General Restrictions shown in the TMP for lane closures and as

approved by the Engineer. For night time construction activities, the

Contractor shall obtain approval from the City of East Providence and must

comply with local noise ordinance.

17. The construction operations of this Project must be coordinated with the local

community public officials. Upon award of the Contract and approval of the

schedule, but prior to the commencement of construction, the Contractor shall

coordinate the requirements for Uniformed Traffic Control Persons with the

Engineer who will coordinate with state and local police departments.

18. The Contractor shall maintain power to the Interstate Route 195 lighting

system located within the areas in which vehicular traffic is maintained during

each construction phase.

19. The Contractor is advised that the signs and other traffic control devices

shown on the Maintenance and Protection of Traffic Plans and Details are

minimum requirements. The Contractor shall be responsible to supplement

these as required to ensure the public’s safety. Prior to beginning work that

affects traffic, the Contractor shall furnish and install the required signs and

other traffic control devices. Signs that impact the construction zone and need

to be relocated shall be replaced in kind.

20. In cases of emergency and/or as directed by the Engineer, the Contractor shall

move equipment to allow for the passage of emergency vehicles and/or open

closed lanes to maintain traffic flow.

21. All work must be performed in a manner that causes the least disruption to

existing vehicular and pedestrian traffic for as short a period of time as

possible. When work commences in such areas, it shall be expeditiously

completed without unnecessary interruptions. Unless otherwise permitted in

writing by the Engineer.

Page 11: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

CS-10

22. The Contractor shall backfill or shall place steel plates, as approved by the

Engineer, capable of supporting HS-25 wheel loading over all trenches and

excavations that are not protected by barrier at the end of each work day

except when otherwise directed by the Engineer. There shall be no additional

compensation for backfilling, re-excavating and/or plating these trenches.

Use of steel plates is restricted to local roads.

23. All temporary construction signs shall be removed, covered or otherwise

concealed when they are not needed to properly warn drivers and/or

pedestrians. This includes the periods between erecting the signs and the start

of operations, as well as when a phase is completed or suspended. The

Contractor shall be compensated for this under Item Code 937.0200,

“Maintenance and Movement Traffic Protection”.

24. The measurement and payment for all traffic control devices and for the

maintenance and movement of traffic protective devices will be made under

the appropriate bid items at the Contract unit bid prices.

25. Temporary construction signs shall not be placed so they encroach on open

lanes of traffic. Signs shall be trimmed when placed on median barriers to

avoid encroaching on open travel lanes. This work shall be considered

incidental and no extra payment shall be made.

26. All temporary signs shall be erected so that they are not obstructed by barrels

or cones.

27. The Storm Water Pollution Prevention Plan (SWPPP) details the anticipated

erosion & sediment controls required for this project. The Contractor must

designate a SWPPP contact person, experienced in storm water management

on large construction sites, who is available on site throughout the life of the

project, and who has the authority to direct Contractor’s personnel and/or

subcontractor’s personnel in carrying out corrective actions requested by

RIDOT’s SWPPP Inspector and/or Resident Engineer. The Contractor’s

designated SWPPP contact person must be available to oversee all SWPPP

related activities and to accompany the RIDOT’s SWPPP Inspector, as

requested, when inspections are performed. All applicable sections of the

SWPPP must be signed by the Contractor and applicable subcontractors prior

to Notice to Proceed.

28. Erosion and sediment controls shall be installed prior to the initiation of any

earthwork. Installation shall not begin more than 30 days prior to the

scheduled start of earthwork in the vicinity of the controls. During the first 90

days following the initiation of earthwork, if the Engineer calls for the

replacement of any controls which were installed more than 30 days prior to

initiation of earthwork, due to deterioration of the materials, this shall be the

responsibility of the Contractor, and shall be accomplished at no cost to the

State.

Page 12: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

CS-11

6. SEQUENCE OF ACCELERATED BRIDGE CONSTRUCTION AND SCHEDULE

The following is the suggested sequence of work of major items and is not inclusive of all work

items or other sequence of work:

Stage 1

• Horton Farm Road Traffic Control and Mobilization, Implement Horton Farm Road

Traffic Control Plan (TCP) Stage 1.

• Install Support of Excavation at the North and South Approach of the Bridge prior to

switching traffic on to the West Side.

• I-195 Pre-Demolition Activities -Set up Traffic Control on I-195.

• Switch Traffic to West Side of Bridge.

• Horton Farm Road Pre-Demolition Activities – Saw cut existing East Side Pavement and

Concrete Deck

• Stage 1A. Demolition of Southeast Quadrant of the Superstructure during weekend

crossovers.

• Stage 1B. Demolition of Northeast Quadrant of the Superstructure during weekend

crossovers.

• Stage 1C. Demolition of existing East Pier Cap, Columns, and Footings; Demolition of

existing Top of Backwalls, and Wingwall Barriers on the North and South Abutment

Side; and Excavation for North and South Approach Slabs.

• Construct the New East Pier; Install New Approach Slab Supports at the Backwalls, and

Wingwall Barriers on the North and South Abutment Side; and Install Crushed Stone Fill

Wrapped in Geogrid for the Approach Areas.

• Stage 1D. Erect Prefabricated SE Girders (Modular Unit with Side Shielding attached for

Installation of Safety Barrier, Individual Girder and Diaphragms) during weekend

crossovers at night.

• Stage 1E. Erect Prefabricated NE Girders (Modular Unit with Side Shielding attached for

Installation of Safety Barrier, Individual Girder and Diaphragms) during weekend

crossovers.

• Stage 1F. Place Deck Panels 1 thru 8.

• Stage 1G. Place Deck Panels 9 thru 13 for the Southeast Quadrant during weekend

crossovers.

• Place Panel Closure Pours.

• Place End Closure Pour.

• Place Southeast Approach Slab.

• Stage IH. Place Deck Panels 14 thru 18 for Northeast Quadrant during weekend

crossovers.

• Place Panel Closure Pours.

• Place End Closure Pour

Page 13: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

CS-12

• Place Safety Barrier

• Place Northeast Approach Slab.

• Install Waterproofing, Wearing Surface, Striping and New Light Standards.

• Completion of Stage 1.

Stage 2

• Horton Farm Road Traffic Control and Mobilization, Implement Horton Farm Road

Traffic Control Plan (TCP) Stage 2.

• Switch Traffic to East Side of Bridge.

• Stage 2A. Demolition of Southwest Quadrant of Superstructure during weekend

crossovers.

• Stage 2B. Demolition of Northwest Quadrant of Superstructure during weekend

crossovers.

• Stage 2C. Demolition of existing West Pier Cap, Columns, and Footings; Demolition of

existing Top of Backwalls, and Wingwall Barriers on the North and South Abutment

Side; Excavation for North and South Approach Slabs.

• Construct the New West Pier; Install New Approach Slab Supports at the Backwalls and

Wingwall Barriers on the North and South abutment Side; Install Crushed Stone Fill

Wrapped in Geogrid for the Approach Areas.

• Stage 2D. Erect Prefabricated SW Girders (Modular Unit with Side Shielding attached for

Installation of Safety Barrier, Individual Girder, and Diaphragms) during weekend

crossovers at night.

• Stage 2E. Erect Prefabricated NW Girders (Modular Unit with Side Shielding attached for

Safety Barrier Construction, Individual Girder and Diaphragms) during weekend

crossovers.

• Stage 2F. Place Deck Panels 19 thru 27.

• Stage 2G. Place Deck Panels 28 thru 32 for the Southwest Quadrant during weekend

crossovers.

• Place Panel Closure Pours.

• Place End Closure Pour

• Place Closure Pour Forms between Southeast and Southwest Decks during weekend

crossovers.

• Place Southwest Approach Slab.

• Stage 2H. Place Deck Panels 33 thru 37 for the Northwest Quadrant during weekend

crossovers.

• Place Panel Closure Pours.

• Place End Closure Pour

• Place Longitudinal Closure Pours

• Place Safety Barrier

• Install Waterproofing, Wearing Surface and Striping.

• Place Northwest Approach Slab.

• Completion of Stage 2.

Page 14: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

CS-13

• Interim Completion #1: Open Full Bridge to Traffic

• Complete Concrete Surface Repair at Abutments and Wingwalls.

• Complete I-195 Roadway Mill and Pave Work at the Bridge.

• Substantial Completion.

7. LUMP SUM BID ITEMS

The Contractor shall note that numerous bridge items on this project are paid for on a lump sum

basis or are included for payment under other lump sum item(s). In general these include but are

not limited to:

• The construction of the new Bridge 472 superstructure in its entirety.

• The construction of the new Bridge 472 substructure to the limits shown on plans.

• The removal and disposal of the existing Bridge 472 superstructure in its entirety.

• The removal and disposal of the existing Bridge 472 substructure to the limits shown on

plans.

8. TRANSPORTATION MANAGEMENT PLAN

Included as an appendix (Appendix B) to these Contract Specific General Provisions is the

Transportation Management Plan (TMP) for this project. The TMP lays out the set of coordinated

transportation management strategies that will be used to manage the work zone safety and

mobility impacts of this project. In the event of a discrepancy between information in the TMP

and information elsewhere in the Contract Documents, the former shall govern.

The Departmentʹs latest Training Guidelines for Personnel Responsible for Work Zone Safety &

Mobility are available under the ʺTrainingʺ section at

http://www.dot.ri.gov/business/contractorsandconsultants.php

9. ENVIRONMENTAL PERMITS

Environmental Permits required for this project are on the following pages:

Appendix C: Storm Water Pollution Prevention Plan (SWPPP)

10. COORDINATION WITH OTHER CONTRACTS

It shall be the Contractor’s responsibility to coordinate, cooperate and schedule his work and all

segments thereof with the Engineer, other contractors, utility owners, and applicable local

authorities, so as to minimize impacts to the construction schedule.

Page 15: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

CS-14

11. STEEL FABRICATION AND DELIVERY

The Contractor shall schedule the work such that all structural steel for the Bridge is fabricated,

coated, delivered to the Department approved pre-assembly shop/site for prefabrication of the

concrete deck panels. This shall include girders, diaphragms, and other miscellaneous members.

The steel shall be stockpiled at a location, secured by the Contractor on land that is in the

Contractor’s control. The location shall be fenced. The Contractor may stockpile the steel on site

however the Department will not consider any claims for costs or delays for stockpiling on site.

The Department will not accept responsibility for the security of the steel if it is stockpiled on site.

The steel shall be stockpiled in such a manner so as not to damage or deform it, or mark the surface.

The contractor shall provide all cribbing, trailers, loading, unloading, fencing, and security. The

Contractor shall be liable for repairing all damage, including graffiti, to the satisfaction of the

Engineer.

At the time of the execution of the Contract, the successful bidder must furnish the Department

with a Contract Bond by the steel fabrication subcontractor for the structural steel and the work

associated with meeting the requirements in the previous two paragraphs, in a sum equal to the

value of the steel and the work. The bond shall meet all other requirements of section 103.05 of

the Rhode Island Department of Transportation Standard Specifications for Road and Bridge

Construction.

The cost for securing the location, fabricating, delivering, stockpiling, loading and unloading, and

securing the steel shall be incidental to the contract. No additional payment shall be made for the

requirements stated above.

Page 16: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

CS-15

APPENDIX “A”

CONTRACTOR SUBMITTAL LIST

Page 17: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

CS-16

TABLE A

Contractor Submittal List

Submittal

No.

Description Date

Submitted

to RIDOT

Date

Returned to

Contractor

Date

Returned

to RIDOT

Comments

CSL‐0011 Bridge Demolition:

Equipment and

Detailed Sequence of

Work

CSL-0021 Remove and Dispose

Existing

Superstructure

CSL-0031 Remove and Dispose

Existing

Substructure

CSL‐0042 Crane Submittals

CSL‐0051 Temporary

Protective Shielding

CSL‐006 3 Concrete: Mix

Designs, Placing and

Methods and

Equipment, Curing

Plan and Methods,

Personnel Resources

CSL‐0072 Reinforcing Steel,

Splices and Inserts

CSL‐0081 Concrete Forms

CSL‐0092 Structural Steel

CSL‐0101 Drill and Grout

Reinforcing

CSL‐0112 Bridge Bearing

Assemblies

CSL‐0122 Beam Erection

Procedures

CSL‐0133 Bridge Name/Seal

Tablets

CSL‐0143 Controlled Low

Strength Material

CSL‐0153 Concrete Surface

Repair

CSL-0163 Accelerated Bridge

Construction

Schedule

Page 18: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

CS-17

Submittal

No.

Description Date

Submitted

to RIDOT

Date

Returned to

Contractor

Date

Returned

to RIDOT

Comments

CSL-0172 Temporary Earth

Support System

Design

CSL-0182 Temporary Shoring

CSL-0192 Miscellaneous

Metals

CSL-0203 Leveling Devices

CSL‐0213 Expansion Strip Seal

Joint Assemblies

CSL‐0223 Structural Steel Paint

Systems

CSL‐0233 Welding Procedures

CSL-0241 Method for

Controlling Water

Run-off

CSL-0251 Executed SWPPP

with Certifications of

All Contractor

Personnel and

Subcontractor

Personnel

CSL-0261 Earthwork Sequence

of Construction and

Proposed Equipment

CSL-0273 Hot Mix Asphalt

CSL-0282 Mass Concrete

CSL-0292 Quality Control Plan

for Bridge

Superstructure

CSL-0303 Fabricator

Qualification for

Bridge

Superstructure

CSL-0312 Shop Drawings for

Prefabricated Deck

Panels

CSL-0322 Erection Plan for

Prefabricated Deck

Panels.

Page 19: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

CS-18

Submittal

No.

Description Date

Submitted

to RIDOT

Date

Returned to

Contractor

Date

Returned

to RIDOT

Comments

CSL-0333 Quality Control Plan

for Bridge

Substructure

CSL-0343 Precast Fabricator

Qualification for

Bridge Substructure

CSL-0352 Shop Drawings for

Precast Concrete

Elements

CSL-0362 Erection Plan for

Bridge Substructure

CSL-0371 Temporary Service

for Highway

Lighting

CSL-0383 Deck Waterproofing

Membrane

CSL-0393 Concrete Surface

Treatment

(Protective Coating)

CSL-0402 Shear Connectors

CSL-0411 Pedestrian Chain

Link Fence

CSL-0421 Bridge Identification

and Minimum

Clearance Signs

CSL-0433 Castings - CB Frame

& Grate

CSL-0443 Quality Control Plan

Hot Mix Asphalt

CSL-0453 Joint Sealant

CSL-0461 Precast Concrete

Barrier

CSL-0473 Sedimentation Fence

CSL-0481 SWPPP

CSL-0493 Handholes

CSL-0502 Highway Lighting

Bracket Arm &

Luminaire

CSL-0512 Overhead and

Ground Mounted

Guide Signs

CSL-0522 Overhead Guide

Sign Supports

Page 20: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

CS-19

Submittal

No.

Description Date

Submitted

to RIDOT

Date

Returned to

Contractor

Date

Returned

to RIDOT

Comments

CSL-0533 Reinforced Concrete

Pipe

CSL-0542 Snow Fence

CSL-0552 UHPC Quality

Control Plan

CSL-0563 UHPC Trial Batch

Test Results

CSL-0572 UHPC Construction

Procedures

CSL-0582 UHPC Formwork

Notes:

1. Submit for information only. Rhode Island P.E. stamp required.

2. Submit for review and approval. Rhode Island P.E. stamp required.

3. Submit for review and approval. For materials submission, if on RIDOT Approved Materials

List, a cut sheet and C of C shall be submitted “For Info Only”. If product is not on the list,

material data shall be submitted for review and approval.

Page 21: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

CS-20

APPENDIX “B”

TRANSPORTATION MANAGEMENT PLAN

Page 22: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

LEVEL 1 Project Name:

TRANSPORTATION RI Design Contract No(s):

MANAGEMENT RI Construction Contract No(s):

PLANMunicipalities:

Submission: Date:

Section Title Page Number

2

6

10

12

14

15

16

17

18

19

19

20

Project Information............................................................................................................................

Traffic Conditions Prior to Start of Work........................................................................................................

Expected Traffic Conditions During the Work......................................................................................................

Transportation Management Strategies

Transportation Operations Plan............................................................................................

Performance Monitoring Plan.................................................................................................

Changes to TMP & Contingency Plans................................................................................................

Traffic-Related Work Restrictions....................................................................................

Temporary Traffic Control Plans......................................................................................................

Public Information Plan.......................................................................................................................

Improvements to I-195 and Bridge 472

PROJECT

SIGNIFICANT

TABLE OF CONTENTS

Insert Project Photo/Worm Here

List of Attachments....................................................................................................................................

City of East Providence

90% 17-Jul-2017

TMP Roles and Responsibilities..................................................................................................

TMP Approvals.....................................................................................................................................

RIDOT Level 1 TMP 472 DRAFT 20170726 Template Rev. 11-06-09 Page 1 of 35

dbouchard
Text Box
100%
dbouchard
Text Box
2017-CB-070
dbouchard
Text Box
98107
Page 23: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Name: Name:

Title: Title:

Unit: Company/Unit:

Office Phone: Office Phone:

Mobile Phone: Mobile Phone:

E-Mail: E-Mail:

Name: Name:

Title: Title:

Unit: Company/Unit:

Office Phone: Office Phone:

Mobile Phone: Mobile Phone:

E-Mail: E-Mail:

[email protected]@dot.ri.gov

PHONE E-MAIL

To be contacted via RIDOT notification form (FAX to 222-4225 / 222-5640) min. 48 hours prior to the implementation of lane

closures and detours. Will update RIDOT 511 system as necessary.Task Description / Responsibilities:

Task Description / Responsibilities:

To be contacted via RIDOT notification form (FAX to 222-3905) min. 48 hours prior to the implementation of lane closures

and detours. Will update/issue RIDOT travel advisories web site / news releases as necessary.

TMP Development Managers

TMP Implementation Managers

CONSULTANTRIDOT

RIDOT

Anthony Pompei Phineas Fowler

Project Manager Project Manager

Bridge Engineering

RIDOT / TMC 401-222-5826

COMPANY / UNIT

RIDOT / Communications

RIDOT / Communications

TMP ROLES AND RESPONSIBILITIES

TMP Implementation Task Leaders

401-222-1362

Project design managers who oversee the development of this TMP

CONTRACTOR

Other parties responsible for completing specific transportation management tasks required by this TMP

(401)222-2053 (781)-707-7424

NAME / TITLE (if individual is named)

[email protected]

Louis Berger Group

[email protected]

Project construction managers with the primary responsibility & authority for implementation of this TMP

401-222-2450

Task Description / Responsibilities:

[email protected]

Task Description / Responsibilities:

To be contacted via RIDOT notification form (FAX to 222-5648) min. 48 hours prior to the implementation of lane closures

and detours. If necessary, will assist in coordinating the strategies included in the Public Information Plan.

RIDOT Level 1 TMP 472 DRAFT 20170726 Template Rev. 11-06-09 Page 2 of 35

Page 24: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Task Description / Responsibilities:

Task Description / Responsibilities:

Task Description / Responsibilities:

Task Description / Responsibilities:

Task Description / Responsibilities:

Task Description / Responsibilities:

Task Description / Responsibilities:

Task Description / Responsibilities:

Task Description / Responsibilities:

TMP Implementation Task Leaders (continued)

NAME / TITLE (if individual is named) E-MAILCOMPANY / UNIT PHONE

Task Description / Responsibilities:

Task Description / Responsibilities:

Task Description / Responsibilities:

RIDOT Level 1 TMP 472 DRAFT 20170726 Template Rev. 11-06-09 Page 3 of 35

Page 25: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Role / Notification/Consultation

Requirements:

Role / Notification/Consultation

Requirements:

Role / Notification/Consultation

Requirements:

Role / Notification/Consultation

Requirements:

NAME / TITLE (if individual is named) COMPANY / UNIT

Role / Notification/Consultation

Requirements:

Role / Notification/Consultation

Requirements:

Erik Skadberg, City Engineer

Role / Notification/Consultation

Requirements:

Role / Notification/Consultation

Requirements:

PHONE E-MAIL

TMP Stakeholder Contacts

TMP Stakeholders to be consulted or coordinated with during the work

Role / Notification/Consultation

Requirements:

Role / Notification/Consultation

Requirements:

Role / Notification/Consultation

Requirements:

Role / Notification/Consultation

Requirements:

Role / Notification/Consultation

Requirements:

Role / Notification/Consultation

Requirements:

[email protected]

Role / Notification/Consultation

Requirements:

City of East Providence (401) 435-7500

RIDOT Level 1 TMP 472 DRAFT 20170726 Template Rev. 11-06-09 Page 4 of 35

Page 26: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

(401)435-7677

(401) 435-7683

(401) 435-7600

(401) 432-1000

(401) 438-3170

(401) 438-2452

(401)444-7700

(401) 444-1000

AGENCY / UNIT PHONE

Emergency Service Contacts

Emergency service agencies/providers expected to be impacted by the project work zones

NAME / TITLE (if individual is named)

City of East Providence Police

Special Details / Requirements:

East Providence Medical Center

Special Details / Requirements:

City of East Providence Emergency

Medical Services Coordinator

Special Details / Requirements:

Special Details / Requirements:

Special Details / Requirements:

Special Details / Requirements:

Special Details / Requirements:

Rhode Island State Police

Special Details / Requirements:

Bradley Hospital

Special Details / Requirements:

Special Details / Requirements:

Special Details / Requirements:

Special Details / Requirements:

Rhode Island Hospital

Our Lady of Fatima Hospital

City of East Providence Fire Dept

E-MAIL

RIDOT Level 1 TMP 472 DRAFT 20170726 Template Rev. 11-06-09 Page 5 of 35

Page 27: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

PROJECT WIDE – HIGHWAY WORK

The work shall include, but not be limited to road construction which includes gravel borrow subbase

course, bituminous pavement, sawcutting, curbing, sidewalk, pavement marking, drainage, site separation;

clearing and grubbing, removal of pavement, excavation and embankment, erosion control, trimming and

fine grading, dewatering, handling and disposal of contaminated soil, dust control, landscaping; plantable

soil and seed, plantings, uniform traffic persons, flagpersons, temporary construction signs, detours,

temporary closures, maintenance and protection of traffic, permanent signing, lighting, and barrier

installation, field office, mobilization, and all other incidentals, complete and accepted, as required by the

Engineer.

HORTON FARM ROAD BRIDGE NO. 472 RECONSTRUCTION

The bridge work in the contract shall include the replacement of Horton Farm Road Bridge No. 472. The work

shall include the demolition of the entire existing bridge superstructure and abutment backwalls, the partial

demolition of the abutments and pier to the limits shown on the contract drawings, and the demolition of the

wingwall parapets. The work for the bridge superstructure shall include the installation of plate girders,

precast concrete deck panels, closure pours, and cast-in-place concrete parapets on the deck. The work for

the bridge substructure shall include the installation of precast backwalls for the abutments, precast

approach slabs, cast-in-place bridge seats for the abutments and pier, and cast-in-place concrete parapets

on the wingwalls.

PROJECT INFORMATION

Brief Project Description

The work will take place on I-195 between Broadway and the Massachusetts State Line. Resurfacing of the

highway and ramps will affect mainline and entering/exiting traffic. The Horton Farm Road ramp bridge

superstructure will be replaced as part of this project. Travel over the bridge will be restricted to one lane for

the extent of the work. A closure and detour of Ramp FR-1 will be available as necessary to provide

additional work space during the evening hours.

While some work will be completed outside of existing roadway limits most portions of the work will require

temporary restrictions of traffic including lane closures, shoulder closures, lane shifts, road/ramp closures,

and detours. The duration of each such restriction will vary depending on the work operation and will range

from long-term (e.g. stationary lane shifts for construction of ramps and bridges) to short term (e.g. mobile

lane closures for installation of pavement markings.

General Work Limits

RIDOT Level 1 TMP 472 DRAFT 20170726 Template Rev. 11-06-09 Page 6 of 35

Page 28: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

3,150'I-195

ROADWAY NAME or INTERSECTION FROM

WORK ZONE LOCATIONS

TO APPROX. LENGTH

Massachusetts State LineBroadwayI-195 8,800'

Warren AveHorton Farm Road Ramps

RIDOT Level 1 TMP 472 DRAFT 20170726 Template Rev. 11-06-09 Page 7 of 35

Page 29: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

1. Approval of the work schedule and time schedule by the Department is required before the start of any construction or other work associated

with this contract.

2. The Contractor shall note that nighttime work, unless otherwise noted as required, is allowed.

3. The construction operations of this Project must be coordinated with the local community public officials. Upon award of the Contract and

approval of the schedule, but prior to the construction, the Contractor shall coordinate requirements for Uniformed Traffic Control Persons with the

Engineer who will coordinate with state and local police departments.

4. The Contractor shall maintain power to the Interstate Route 195 lighting system located within the areas in which vehicular traffic is maintained

during each construction phase.

5. The Contractor is advised that the signs and other traffic control devices shown on the Maintenance and Protection of Traffic Plans and Details

are minimum requirements. The Contractor shall be responsible to supplement these as required to ensure the public’s safety. Prior to beginning

work that affects traffic, the Contractor shall furnish and install the required signs and other traffic control devices.

6. In cases of emergency and/or as directed by the Engineer, the Contractor shall move equipment to allow for the passage of emergency vehicles

and/or open closed lanes to maintain traffic flow.

7. The Contractor shall notify the Department in writing at least fourteen (14) days in advance of any intended lane restrictions and/or closures so

that adequate public notice can be given. Upon the Engineer’s approval, the Contractor shall coordinate the required traffic control.

8. All work must be performed in a manner that causes the least disruption to existing vehicular and pedestrian traffic for as short a period of time

as possible. When work commences in such areas, it shall be expeditiously completed without unnecessary interruptions.

9. The Contractor shall backfill or shall place steel plates, as approved by the Engineer, capable of supporting HS-25 wheel loading over all trenches

and excavations that are not protected by barrier at the end of work each day except when otherwise directed by the Engineer. There shall be no

additional compensation for backfilling, re-excavating and/or plating these trenches. Use of steel plates is restricted to local roads.

10. All temporary construction signs shall be removed, covered or otherwise concealed when they are not needed to properly warn drivers and/or

pedestrians. This includes the periods between erecting the signs and the start of operations, as well as when a phase is completed or suspended.

The Contractor shall be compensated for this under Item Code 937.0200, “Maintenance and Movement Traffic Protection”.

11. The measurement and payment for all traffic control devices and for the maintenance and movement of traffic protective devices will be made

under the appropriate bid items at the Contract unit bid prices.

13. Temporary construction signs shall not be placed so they encroach on open lanes of traffic. Signs shall be trimmed when placed on median

barriers to avoid encroaching on open travel lanes. This work shall be considered incidental and no extra payment shall be made.

14. All temporary signs shall be erected so that they are not obstructed by barrels or cones.

General Project Schedule & Construction Sequence*

*The information in this section is not intended to and shall not supersede the approved schedule and milestone/completion dates for the project.

RIDOT Level 1 TMP 472 DRAFT 20170726 Template Rev. 11-06-09 Page 8 of 35

Page 30: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

DETAILS / DATES / LOCATIONSACTIVITY

OTHER ACTIVITIES IN PROJECT VICINITY

WITH POTENTIAL FOR CAUSING SIGNIFICANT CUMULATIVE IMPACTS

RIDOT Level 1 TMP 472 DRAFT 20170726 Template Rev. 11-06-09 Page 9 of 35

Page 31: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

TRAFFIC CONDITIONS PRIOR TO START OF WORK

Traffic Data

RIDOT Level 1 TMP 472 DRAFT 20170726 Template Rev. 11-06-09 Page 10 of 35

Page 32: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Varies

Crash Data

Intersection Control

Local Community Issues and Concerns

None known at this time.

RIDOT Level 1 TMP 472 DRAFT 20170726 Template Rev. 11-06-09 Page 11 of 35

Page 33: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

EXPECTED TRAFFIC CONDITIONS DURING THE WORK

Traffic Data

RIDOT Level 1 TMP 472 DRAFT 20170726 Template Rev. 11-06-09 Page 12 of 35

dbouchard
Rectangle
Page 34: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

None known at this time.

Anticipated Demands from Other Activities in Vicinity of Project

RIDOT Level 1 TMP 472 DRAFT 20170726 Template Rev. 11-06-09 Page 13 of 35

Page 35: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

No lane and/or shoulder closures allowed after 1:00 PM on the Friday preceding a holiday weekend.Easter Sunday - No lane and/or shoulder closures allowed on Saturday. No lane and/or shoulder closures allowed on Sunday.*New Years Day, Independence Day & Christmas Day - No lane and/or shoulder closures allowed after 1:00 PM on the day before the holiday. No lane and/or shoulder closures allowed on the holiday.Dr. Martin Luther Kind Jr. Day, Memorial Day, Labor Day, Columbus Day & Veteran's Day

No lane and/or shoulder closures allowed on Saturday and Sunday. No lane and/or shoulder closures allowed on Monday.*Thanksgiving Day - No lane and/or shoulder closures allowed after 1:00 PM on the Wednesday preceding Thanksgiving Day. No lane and/or shoulder closures allowed on Thanksgiving Day. No land and/or shoulderclosures allowed on Friday and Saturday. No lane and/or shoulder closures allowed on Sunday.*

*Up to 10 PM

TRAFFIC-RELATED WORK RESTRICTIONS

General Restrictions

Holiday Restrictions

See attached 'Lane Closure Limitations' for number of lanes that must remain open to traffic during all times

of the week.

RIDOT Level 1 TMP 472 DRAFT 20170726 Template Rev. 11-06-09 Page 14 of 35

Page 36: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

TMPPlan Set

√ x

√ x

√ x

√ x

√ x

√ x

TMPPlan Set

x

Stage 1B x

Stage 1C x

Stage 1D x

Stage 2A x

Stage 2B x

Stage 2C x

Stage 2D x

Resurfacing x

RIDOT-DEVELOPED TYPICAL TTC PLANS

Work Beyond the Shoulder

Lane Shift - Limited Access

Lane Closure - Limited Access

Double Lane Closure - Limited Access

Lane Closure - Four Lane Road

1-Side Lane Shift - Two Lane Road

TEMPORARY TRAFFIC CONTROL PLANS

These RIDOT- and/or Designer-Developed TTC Plans will be used during the work on this projectIncluded in:

DESIGNER-DEVELOPED TTC PLANS

Mobile Operation

2-Side Lane Shift - Two Lane Road

Included in:

Stage 1A

Others (list) -

Shoulder Closure - Two Lane Road

Lane Closure - Two Lane Road

Shoulder Closure - Limited Access

RIDOT Level 1 TMP 472 DRAFT 20170726 Template Rev. 11-06-09 Page 15 of 35

Page 37: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

SELECTED STRATEGIES

Highway advisory radio (HAR)

notification forms. Portable CMSs to be furnished by Contractor and programmed/installed at locations shown

RIDOT travel advisories news releases

RIDOT travel advisories web site

Road User Information Strategies

RIDOT 511 traveler information system

SELECTED STRATEGIES

Changeable message signs (CMS)

based on submitted notification forms.

Permanent (existing) RIDOT HAR systems to be updated by RIDOT TMC Operators as applicable

in the plans.

RIDOT TMP Imp. Mngr. to send RIDOT notification form to RIDOT TMC min. 48 hrs. in advance of restrictions.

RIDOT TMC to include appropriate restriction information in 511 phone and web services.

Permanent RIDOT CMSs to be used by RIDOT TMC Operators as applicable based on submitted

RESPONSIBILITIES / REQUIREMENTS / SPECIAL CONSIDERATIONS

Public Awareness Strategies

Communications to post appropriate information on RIDOT travel advisories web page.

Communications to include appropriate information in weekly news releases.

RESPONSIBILITIES / REQUIREMENTS / SPECIAL CONSIDERATIONS

RIDOT TMP Imp. Mngr. to send RIDOT notification form to Communications min. 48 hrs. in advance of restrictions.

RIDOT TMP Imp. Mngr. to send RIDOT notification form to Communications min. 48 hrs. in advance of restrictions.

PUBLIC INFORMATION PLAN

These strategies will be used to provide information concerning the project to road users and the community

RIDOT Level 1 TMP 472 DRAFT 20170726 Template Rev. 11-06-09 Page 16 of 35

Page 38: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

TRANSPORTATION OPERATIONS PLAN

These strategies will be used to provide improved transportation operations/safety within project work zones

SELECTED STRATEGIES

Speed limit reduction/variable speed limits Per plans

RESPONSIBILITIES / REQUIREMENTS / SPECIAL CONSIDERATIONS

Per plans

Traffic/Incident Management & Enforcement Strategies

Work Zone Safety Management Strategies

RESPONSIBILITIES / REQUIREMENTS / SPECIAL CONSIDERATIONS

On street parking restrictions shall be coordinated with the City of East Providence.

State police will be parked within the work zone at locations shown on the plans

RESPONSIBILITIES / REQUIREMENTS / SPECIAL CONSIDERATIONS

Per plans

Demand Management Strategies

SELECTED STRATEGIES

SELECTED STRATEGIES

Parking restrictions

RIDOT Transportation Management Center

Dedicated (paid) police enforcement

SELECTED STRATEGIES

RESPONSIBILITIES / REQUIREMENTS / SPECIAL CONSIDERATIONS

Crash attenuators

Corridor/Network Management Strategies

the project work zones

RIDOT TMC Operators, using existing CCTV cameras, will coordinate and manage traffic and incidents in and around

Temporary traffic barrier

RIDOT Level 1 TMP 472 DRAFT 20170726 Template Rev. 11-06-09 Page 17 of 35

Page 39: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

RESPONSIBILITIES / REQUIREMENTS / SPECIAL CONSIDERATIONS

Team meetings

Surveillance: Traffic queues/delays

timely notifications where required.

The Consultant TMP Development Manager will arrange to monitor queues/delays during the crossover implementation

Project-Specific Performance Monitoring Strategies

General Monitoring Requirements

SELECTED STRATEGIES

PERFORMANCE MONITORING PLAN

as directed by the RIDOT TMP Development Manager.

The RIDOT TMP Implementation Manager or his/her responsible designee should (1) inspect the project workzones at initial setup, at the start of each subsequent work day, and just prior to extended breaks in the work (e.g.,weekends) for conformance with the Temporary Traffic Control Plans, the ATSSA Quality Guidelines for Temporary

Traffic Control Devices and Features , and where applicable, the other transportation management strategiesidentified above and (2) document all work zone-related feedback and complaints that are received from the public.

The Contractor's TMP Implementation Manager is responsible for keeping the portion of the project being used bypublic traffic in a condition that (1) safely and adequately accommodates such traffic and (2) is in accordance with theTraffic-Related Work Restrictions, the Temporary Traffic Control Plans, and where appropriate, the othertransportation management strategies identified above.

project impacts and will verify that all appropriate stakeholders and project officials have been receiving

of the project work zones to date. At these meetings, attendees will discuss how well the TMP is managing the

Engineer, and the Traffic Management Chief on a regular basis to discuss and assess the safety and mobility impacts

The RIDOT TMP Implementation Manager will meet with the Construction Management Chief, the State Traffic

RIDOT Level 1 TMP 472 DRAFT 20170726 Template Rev. 11-06-09 Page 18 of 35

Page 40: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Signature: Signature: Signature:

Date: Date: Date:

Initials Date Date Revision # Initials Date

CHIEF ENGINEERDEPUTY CHIEF ENGINEER

Revision #

STATE TRAFFIC ENGINEER

All approvals must be obtained prior to start of work

TMP APPROVALS

If at any time (1) a significant deviation from any of the strategies included in the TMP (e.g., the use of an alternate construction sequence) isdesired by one or more members of the project implementation team, (2) field observations and/or data suggest that impacts to road users are orwill be unacceptable, or (3) one or more performance requirements established in the TMP are not being met in the field, the RIDOT TMPImplementation Manager shall report the situation to his/her supervisor or Division/Section/Unit manager. The supervisor / manager willcoordinate with the State Traffic Engineer, the Traffic Management Chief, the TMP Development and/or Implementation Manager(s), the ChiefEngineer, and/or other interested parties as appropriate and/or necessary to consider and determine whether revised and/or alternate strategiesshould be implemented in an effort to lessen the adverse safety and/or mobility impacts of the project. If the supervisor / manager deems thatstrategy changes should be implemented, the changes shall be documented in a revised version of the TMP and the Traffic Management Chief,the State Traffic Engineer, and the Chief Engineer must approve of the revised TMP prior to their implementation.

When unexpected events (e.g., crashes, inclement weather, unforeseen traffic demands, etc.) occur in a project work zone where one or morelanes are closed, the RIDOT TMP Implementation Manager or his/her responsible designee should (1) determine whether or not the laneclosure(s) can/should be removed in order to improve traffic operations and/or minimize delays and (2) if deemed appropriate, take action toremove the lane closure(s).

Kazem Farhoumand, PeRobert Rocchio, PE

If a significant deviation from any of the strategies included in the TMP is requested by the Contractor, unless directed otherwise by the RIDOTthe Contractor is responsible for preparing and submitting to the RIDOT TMP Implementation Manager appropriate documentation (e.g., designcalculations, analysis reports, Temporary Traffic Control Plans, etc.) showing that the requested change(s) are (1) feasible and (2) expected toresult in safety and mobility impacts that are no more adverse than the impacts resulting from the strategies already included in the latestapproved TMP. The RIDOT will review and consider the submittal(s) as described in the preceding paragraph and will determine whether thechanges should be implemented. If the requested changes are approved by the RIDOT, unless otherwise directed by the RIDOT the Contractorshall prepare and submit to the RIDOT TMP Implementation Manager a revised version of the latest approved TMP in both printed and electronic(Microsoft® Excel) format that documents all of the approved changes. Work to implement the changes shall not begin until the TrafficManagement Chief, the State Traffic Engineer, and the Chief Engineer have approved of the revised TMP.

CHANGES TO TMP & CONTINGENCY PLANS

Project Specific Contingencies

Frank Carrao III, PE

Revision # Initials

RIDOT Level 1 TMP 472 DRAFT 20170726 Template Rev. 11-06-09 Page 19 of 35

Page 41: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

1. Lane closure limitations

LIST OF ATTACHMENTS

RIDOT Level 1 TMP 472 DRAFT 20170726 Template Rev. 11-06-09 Page 20 of 35

Page 42: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

PUBLIC INFORMATION STRATEGIES

Page 43: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

PUBLIC AWARENESS STRATEGIES

RIDOT travel advisories news releasesRIDOT travel advisories web siteBrochures and mailersOther press releases/media alertsPaid advertisementsPublic information centerDedicated telephone hotlineDedicated project web sitePublic meetings/hearingsCommunity task forcesConsultation/coordination w/ stakeholdersWork zone education and safety campaignsRideshare promotionsSupplemental visual information

Page 44: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

ROAD USER INFORMATION STRATEGIES

RIDOT 511 traveler information systemCommercial radio traffic reportsChangeable message signs (CMS)Dynamic driver feedback speed display signHighway advisory radio (HAR)Highway information network (web-based)Freight travel information

Page 45: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

TRANSPORTATION OPERATIONS STRATEGIES

Page 46: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

DEMAND MANAGEMENT STRATEGIES

Transit service improvementsTransit incentivesShuttle servicesRidesharing/carpooling incentivesPark-and-ride promotionHigh-occupancy vehicle (HOV) lanesToll/congestion pricingRamp meteringParking supply managementVariable work hoursTelecommuting

Page 47: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

CORRIDOR/NETWORK MANAGEMENT STRATEGIES

Signal timing/coordination improvementsStreet/intersection improvementsBus turnoutsTurn restrictionsParking restrictionsTruck/heavy vehicle restrictionsSeparate truck lanesReversible lanesDynamic lane closure systemRamp meteringRailroad crossing traffic control

Page 48: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

WORK ZONE SAFETY MANAGEMENT STRATEGIES

Speed limit reduction/variable speed limitsTemporary traffic barrierMovable traffic barrier systemsCrash attenuatorsTemporary rumble stripsIntrusion alarmsWarning lightsAutomated Flagger Assistance Devices(AFADs)Project safety task force/committeeRoad safety audits (design)Project on-site safety trainingSafety awards/incentives

Page 49: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

TRAFFIC/INCIDENT MANAGEMENT & ENFORCEMENT STRATEGIES

Dedicated project work zone ITSRIDOT Transportation Management CenterHelicopter for aerial surveillanceTraffic screensLocation reference markersTow/freeway service patrolSurvey equipment for major incidentsPhotogrammetry for major incidentsEstablish available local detour routesContract support for incident managementIncident/emergency management coordinatorIncident/emergency response planDedicated (paid) police enforcementCooperative police enforcementAutomated enforcement

Page 50: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

PERFORMANCE MONITORING STRATEGIES

Team meetingsWindshield surveysPublic surveysSurveillance: Traffic countsSurveillance: Traffic queues/delaysSurveillance: Travel timesSurveillance: Crash dataAssessment: MobilityAssessment: SafetyRoad safety audits (construction)

Page 51: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

TRAFFIC CONTROL STRATEGIES

Page 52: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

TRAFFIC CONTROL DEVICES

Temporary construction signsArrow panelsChannelizing devices - DrumsChannelizing devices - ConesChannelizing devices - BarricadesChannelizing devices - Tubular markersLinear Delineation PanelsTemporary pavement markingsTrafficpersonsFlagpersonsTemporary traffic signalsLighting devices

Page 53: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Project Name: RIC No(s).

Submission: Date:

Total Temporary Traffic Control Device/Personnel Estimated Cost:

Total Public Information Plan Implementation Estimated Cost:

Total Transportation Operations Plan Implementation Estimated Cost:

Total Performance Monitoring Plan Implementation Estimated Cost:

TOTAL TMP IMPLEMENTATION COST:

TMP IMPLEMENTATION COST ESTIMATES

Temporary Traffic Control Devices / Personnel

ITEM EST. COST ITEM EST. COST

$0

Public Information Plan Strategies

ITEM EST. COST ITEM EST. COST

$0

Transportation Operations Plan Strategies

ITEM EST. COST ITEM EST. COST

$0

Performance Monitoring Plan Strategies

Notes

$0

$0

ITEM EST. COST ITEM EST. COST

Page 54: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

POST-CONSTRUCTION WORK ZONE PERFORMANCE ASSESSMENT

Describe Areas of the TMP that were Most Successfully Implemented & Why

Describe Areas of the TMP that were Least Successfully Implemented & Why

Summarize/Describe all Changes Necessary to Correct Oversight of the Original TMP

Improvements to I-195 and Bridge 472

TRANSPORTATION MANAGEMENT PLAN

This assessment shall be completed by the RIDOT TMP Implementation Manager upon completion of the work to

document lessons learned and provide recommendations on how to improve the TMP process and/or modify

guidelines. The responses should allow the reviewer of this completed Assessment to understand the

successes/failures of the project TMP itself and its requirements.

Summarize the Type and Frequency of Legitimate Complaints Received

Summarize the Effectiveness of Each Change Made to the TMP

RIDOT Level 1 TMP 472 DRAFT 20170726 Page 33 of 35

Page 55: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

This completed assessment shall be forwarded to the Chief Engineer following approval below.

Name:

Title:

Unit:

Signature:

Date:

Describe/Summarize Road User Mobility Impacts Observed During Work

RIDOT TMP Implementation Manager Approval

Suggested TMP Improvements or Changes for Future Similar Projects

Describe/Summarize Crashes and Incidents that Occurred During the Work

Describe/Summarize Road Safety Impacts Observed During Work

RIDOT Level 1 TMP 472 DRAFT 20170726 Page 34 of 35

Page 56: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Location From To Sunday Monday Tuesday Wednesday Thursday Friday Saturday

0:00:00 6:00:00 3L 2L 2L 2L 2L 2L 3L6:00:00 9:00:00 3L 3L 3L 3L 3L 3L 3L9:00:00 15:00:00 2L 3L 3L 3L 3L 3L 2L15:00:00 19:00:00 3L 3L 3L 3L 3L 3L 3L19:00:00 24:00:00 2L 2L 2L 2L 2L 2L 3L

0:00:00 6:00:00 3L 2L 2L 2L 2L 2L 3L6:00:00 9:00:00 3L 2L 2L 2L 2L 2L 3L9:00:00 15:00:00 2L 2L 2L 2L 2L 2L 2L15:00:00 19:00:00 3L 3L 3L 3L 3L 3L 3L19:00:00 24:00:00 2L 2L 2L 2L 2L 2L 3L

0:00:00 6:00:00 3L 2L 2L 2L 2L 2L 3L6:00:00 9:00:00 3L 3L 3L 3L 3L 3L 3L9:00:00 15:00:00 2L 3L 3L 3L 3L 3L 2L15:00:00 19:00:00 3L 3L 3L 3L 3L 3L 3L19:00:00 24:00:00 2L 2L 2L 2L 2L 2L 3L

0:00:00 6:00:00 3L 2L 2L 2L 2L 2L 3L6:00:00 9:00:00 3L 3L 3L 3L 3L 3L 3L9:00:00 15:00:00 2L 2L 2L 2L 2L 2L 2L15:00:00 19:00:00 3L 3L 3L 3L 3L 3L 3L19:00:00 24:00:00 2L 2L 2L 2L 2L 2L 3L

0:00:00 6:00:00 1L 1L 1L 1L 1L 1L 1L6:00:00 9:00:00 1L 1L 1L 1L 1L 1L 1L9:00:00 15:00:00 1L 1L 1L 1L 1L 1L 1L15:00:00 19:00:00 1L 1L 1L 1L 1L 1L 1L19:00:00 24:00:00 1L 1L 1L 1L 1L 1L 1L

TIME OF DAY

Location From To Sunday Monday Friday Saturday

0:00:00 6:00:00 1L 1L 2L 1L6:00:00 9:00:00 2L 3L 3L 2L9:00:00 15:00:00 2L 3L 3L 2L15:00:00 19:00:00 2L 3L 3L 2L19:00:00 24:00:00 2L 2L 2L 2L

0:00:00 6:00:00 1L 1L 2L 1L6:00:00 9:00:00 2L 3L 3L 2L9:00:00 15:00:00 2L 3L 3L 2L15:00:00 21:00:00 2L 3L 3L 2L21:00:00 24:00:00 2L 2L 2L 2L

LEGEND:

ALL All travel lanes and shoulders shall remain open to traffic

1L A minimum of one 11-foot wide travel lane shall remain open to traffic in each direction

2L A minimum of two 11-foot wide travel lane shall remain open to traffic

3L A minimum of three 11-foot wide travel lane shall remain open to traffic

NOTES:

1 The set-up and break-down of temporary traffic contraol devices within a traveled way or shoulder shall be construed as a closure of that traveled way of shoulder.

2 The provisions noted herein shall not free the Contractor from his responsibility to conduct all work in such a manner that assures the lease possible obstruction to traffic.

3 Access must be maintained to all ramps, side streest and commercial driveways at all times with the exception of Ramp FR-1 which may be detoured

ATTACHMENT A: GENERAL RESTRICTIONS

I-195 MAINLINE AND BRIDGE 472EAST PROVIDENCE

I-195 EASTBOUND

(West of Exit 7 Off Ramp)

MIMUMUM NUMBER OF LANES & SHOULDERS TO REMAIN OPEN TO TRAFFIC

DAY OF WEEKTIME OF DAY

TRAFFIC DURING THE CROSSOVER PHASES ONLY

DAY OF WEEK

I-195 EASTBOUND

I-195 WESTBOUND

I-195 EASTBOUND

(East of Exit 7 Off Ramp)

I-195 WESTBOUND

(West of Horton Farm

Ramp)

I-195 WESTBOUND

(East of Horton Farm

Ramp)

I-195 WESTBOUND ON-

RAMP (Horton Farm)

1,2,3

Page 57: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

CS-56

APPENDIX “C”

STORM WATER POLLUTION PREVENTION PLAN (SWPPP)

Page 58: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan For:

Improvements to I-195, Superstructure Replacement Bridge 472 East Providence, RI

Owner:

RI DEPARTMENT OF TRANSPORTATION FRANK CORRAO, III, P.E.

2 CAPITOL HILL

PROVIDENCE, RI 02903

401-222-2468

Operator: TO BE DETERMINED UPON CONTRACT AWARD

Company Name

Name

Address

City, State, Zip Code

Telephone Number

Estimated Project Dates: Start Date: January 2018 (Notice-to-Proceed)

Completion Date: June 2019

SWPPP Prepared By:

Louis Berger

166 Valley Street, Building 5

Providence, RI, 02909

401-521-5980

SWPPP Preparation Date: September 2017

RIDOTVersion 2.20120529

Page 59: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

ii

OWNER CERTIFICATION RIPDES Construction General Permit – Section V.G

I certify under penalty of law that this document and all attachments were prepared

under the direction or supervision in accordance with a system designed to assure that

qualified personnel properly gather and evaluate the information submitted. Based on

my inquiry of the person or persons who manage the system, or those persons directly

responsible for gathering the information, the information submitted is, to the best of my

knowledge and belief, true, accurate, and complete.

I am aware that there are significant penalties for submitting false information, including

the possibility of fine and imprisonment for knowing violations. I am aware that it is the

responsibility of the owner/operator to implement and amend the SWPPP as

appropriate in accordance with the requirements of the RIPDES Construction General

Permit.

________________________________________________________ Owner Signature: Date

Owner Name: Frank Corrao III, P.E. Owner Title: Deputy Chief Engineer Company Name: Rhode Island Department of Transportation

Page 60: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

iii

OPERATOR CERTIFICATION Upon contract award, the OPERATOR must sign this certification statement before construction may begin.

RIPDES Construction General Permit – Section V.G

I certify under penalty of law that this document and all attachments were prepared

under the direction or supervision in accordance with a system designed to assure that

qualified personnel properly gather and evaluate the information submitted. Based on

my inquiry of the person or persons who manage the system, or those persons directly

responsible for gathering the information, the information submitted is, to the best of my

knowledge and belief, true, accurate, and complete.

I am aware that there are significant penalties for submitting false information, including

the possibility of fine and imprisonment for knowing violations. I am aware that it is the

responsibility of the owner/operator to implement and amend the SWPPP as

appropriate in accordance with the requirements of the RIPDES Construction General

Permit.

______________________________________________________________________

Operator Signature: Date

Contractor Representative: Name

Contractor Title: Title

Contractor Company Name: Company

Page 61: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

iv

Table of Contents OWNER CERTIFICATION ...............................................................................................ii OPERATOR CERTIFICATION ........................................................................................ iii INTRODUCTION ............................................................................................................. 1 ADDITIONAL RESOURCES ........................................................................................... 2 SECTION 1: SITE DESCRIPTION .................................................................................. 3

1.1 Project/Site Information ...................................................................................... 3 1.2 Nature and Sequence of Construction Activity ................................................... 4

1.3 Existing and Proposed Soils, Slopes, Vegetation, and Drainage Patterns ......... 5 1.4 Construction Site Estimates ............................................................................... 6 1.5 Receiving Waters ............................................................................................... 6

1.6 Allowable Non-Storm Water Discharges ............................................................ 7 1.7 Existing Data of Known Discharges from Site .................................................... 8 1.8 Endangered Species Certification/Natural Heritage Areas ................................. 8

1.9 Historic Preservation/Cultural Resources ........................................................... 8 1.10 Site Features and Sensitive Areas to be Protected......................................... 9 1.11 Potential Sources of Pollution ....................................................................... 10

1.12 Site Plans ...................................................................................................... 11 SECTION 2: EROSION AND SEDIMENTATION CONTROLS .................................... 13

2.1 Minimize Disturbed Area and Protect Natural Features and Soil ..................... 13 2.2 Phase Construction Activity .......................................................................... 14 2.3 Control Stormwater Flowing Onto and Through the Project ............................. 15

2.4 Stabilizing Soils ................................................................................................ 15

2.5 Protect Slopes .................................................................................................. 17 2.6 Protect Storm Drain Inlets ................................................................................ 17 2.7 Protect Storm Drain Outfalls............................................................................. 18

2.8 Establish Perimeter Controls and Sediment Barriers ....................................... 19 2.9 Retain Sediment On-Site and Control Dewatering Practices ........................... 20

2.10 Monitoring Weather Conditions ..................................................................... 20 2.11 Additional BMPs............................................................................................ 20 2.12 Construction Site Erosion and Sediment Control BMPs ............................... 21

SECTION 3: GOOD HOUSEKEEPING BMPS .............................................................. 22 3.1 Off-site Tracking of Sediments ......................................................................... 22

3.2 Waste Disposal ................................................................................................ 23 3.3 Spill Prevention and Control Plan ..................................................................... 24 3.4 Control of Allowable Non-Storm Water Discharges .......................................... 25

3.5 Establish Proper Building Material Staging Areas ............................................ 25 3.6 Designate Washout Areas ............................................................................... 26 3.7 Establish Proper Equipment/Vehicle Fueling and Maintenance Practices ....... 26 3.8 Dust Control ..................................................................................................... 26

3.9 Sweeping ......................................................................................................... 27 3.10 Additional BMPs............................................................................................ 28 3.11 Construction Site Good Housekeeping BMPs .............................................. 28

SECTION 4: POST-CONSTRUCTION BMPs ............................................................... 29

Page 62: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

v

4.1 Post-Construction BMPs .................................................................................. 29 SECTION 5: MAINTENANCE and INSPECTIONS ....................................................... 30

5.1 Maintenance..................................................................................................... 30

5.2 Inspections ....................................................................................................... 30 5.3 Corrective Actions ............................................................................................ 32

SECTION 6: Amendments ............................................................................................ 33 SECTION 7: Recordkeeping ......................................................................................... 34 SECTION 8: Party Certifications ................................................................................... 35

SWPPP APPENDICES ................................................................................................. 37 Attachment A – General Location Map .................................................................... 37 Attachment B – Site Plans ....................................................................................... 37 Attachment C – Copy of RIPDES General Permit ................................................... 37 Attachment D – Copy of RIPDES NOI ..................................................................... 37

Attachment E – Copy of Regulatory Permits ........................................................... 37 Attachment F – Inspection Form ............................................................................. 37

Attachment G – Amendments Log .......................................................................... 37

Attachment H – Additional Information (i.e. documentation) .................................... 37

SWPPP Inspection Report .......................................................................................... 43

AMENDMENT LOG ...................................................................................................... 50

Page 63: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

1

INTRODUCTION This Construction Site Storm Water Pollution Prevention Plan (SWPPP) has been prepared for the State of Rhode Island Department of Transportation (RIDOT) pursuant to the Rhode Island Department of Environmental Management (RIDEM) Rhode Island Pollutant Discharge Elimination System (RIPDES) Program regulations (amended February 5, 2003). Pursuant to Rule 32 of the RIPDES Regulations, projects proposing to discharge storm water must seek authorization under a RIPDES General Permit. In accordance with the General Permit for Storm Water Discharge Associated with Construction Activity (General Permit), projects that disturb one (1) or more acres require the preparation of a SWPPP and RIDEM authorization following RIPDES review of a Notice of Intent (NOI). This SWPPP provides guidance for complying with the terms and conditions required under the General Permit, however, this document does not negate or eliminate the need to understand and adhere to all applicable RIPDES regulations. The purpose of erosion and sedimentation best management practices (BMPs) is to prevent pollutants from leaving the construction site and entering waterways or environmentally sensitive areas during and after construction. This SWPPP has been prepared prior to the initiation of construction activities to address anticipated worksite conditions. The best management practices (BMPs) depicted on the site plan and described in this narrative should be considered the minimum measures required to control erosion, sedimentation, and stormwater runoff at the site. Since construction is a dynamic process with changing site conditions, it is the operator’s responsibility to manage the site during the construction phases so as to prevent pollutants from leaving the site. This may require the owner or operator to revise and amend the SWPPP during construction to address varying site and/or weather conditions, such as by adding or realigning erosion or sediment controls, to ensure the SWPPP remains compliant with the General Permit. Records of these changes must be added to the amendment log attached to the SWPPP, and to the site plans as “red-lined” drawings. The RIDOT Resident Engineer and designated Inspector are required to review the SWPPP and sign the Party Certification pages (Section 8). The prime contractor and all subcontractors involved in earthwork or exterior construction activities are also required to review the SWPPP and sign the certification pages before construction begins.

It is the responsibility of the RIDOT Resident Engineer to maintain the SWPPP, including all attachments, amendments and inspection records, at the project field office and to make all records available for inspection by RIDEM during construction. (RIPDES Construction General Permit – Section II.A.)

Any questions regarding the SWPPP, BMPs, inspection requirements, or any other facet of this document may be addressed to the RIDOT Natural Resources Unit at 401-222-2023.

Please note: Even if practices are correctly installed on a site according to the approved plan, the site is only in compliance when erosion and sedimentation are effectively controlled throughout the entire site.

Page 64: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

2

ADDITIONAL RESOURCES Rhode Island Department of Transportation Natural Resources Unit 2 Capitol Hill, Room 368 Providence, RI 02903 401-222-2023 http://www.dot.ri.gov/programs/stormwater/index.asp

Rhode Island Department of Environmental Management Office of Water Resources 235 Promenade Street Providence, RI 02908 (401) 222-3961 http://www.dem.state.ri.us/programs/benviron/water/index.htm RIDEM RIPDES website http://www.dem.state.ri.us/programs/benviron/water/permits/ripdes/index.htm

RIDEM Water Quality website (for 303(d) and TMDL listings) http://www.dem.ri.gov/programs/benviron/water/quality/index.htm

RIDEM Rhode Island Natural Heritage Program http://www.dem.ri.gov/programs/bpoladm/plandev/heritage/index.htm

RIDEM Geographic Data Viewer – Environmental Resource Map http://www.dem.ri.gov/maps/index.htm

RIDEM RI Stormwater Design and Installation Standards Manual (as amended) http://www.dem.state.ri.us/programs/benviron/water/permits/ripdes/stwater/t4guide/desman.htm

RIDEM, USDA Soil Conservation Service, and RI State Conservation Committee Soil Erosion and Sediment Control Handbook (as amended) http://www.dot.ri.gov/documents/enviro/stormwater/Soil_Erosion_Sediment_Control_Handbook.pdf

Rhode Island Department of Transportation Standard Specifications for Road and Bridge Design and Other Specifications and Standard Details http://www.dot.ri.gov/engineering/standards/index.asp

Natural Resources Conservation Service - Rhode Island Soil Survey Program http://www.ri.nrcs.usda.gov/technical/soils.html

EPA NPDES SWPPP website http://cfpub.epa.gov/npdes/stormwater/swppp.cfm#guide

EPA National Menu of Stormwater Best Management Practices http://cfpub.epa.gov/npdes/stormwater/menuofbmps

Page 65: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

3

SECTION 1: SITE DESCRIPTION RIPDES Construction General Permit – Section IV.E.1

1.1 Project/Site Information

Project/Site Name:

Improvements To I-195, ABC Bridge No. 472 over I-195 Superstructure Replacement, East Providence, Rhode Island

Project Overview: RI Contract No. 2017-CB-070, RI Federal Aid Project No. STP-RESF(360) for the Improvements to I-195 corridor (from Broadway to State Line) and Replacement of Horton Farm Road Bridge No. 472 over I-195 corridor in the City of East Providence, County of Providence. The work for the I-195 corridor shall include, but is not limited to roadway micro-milling and overlay, full depth roadway construction at utility trenches, cleaning and flushing storm drain pipes, cleaning and repairing storm drain structures, adjusting storm drain structures frames, removal of existing guide signs and replacement with new signs, removal of existing roadway lighting and replacement with new lighting along I-195 and associated ramps. The work on Horton Farm Road at the Bridge 472 approaches shall include, but is not limited to roadway micro-milling and overlay, and full-depth construction The roadway work for this project will in general consist of erosion and sediment control, clearing and grubbing, saw cutting, pavement removal, excavation and grading, trimming and fine grading, dust control, bituminous pavement, gravel borrow for subbase course, curbing, sidewalk, pavement markings, drainage, landscaping, plantable soil borrow and seed, traffic control, uniform traffic persons, flag persons, temporary construction signs, temporary closures, maintenance and protection of traffic, signs, guard rail replacement, lighting, and construction field office.

The bridge work in this contract, RI Federal Aid Project No. BRO-0472(001), shall include the complete replacement of Horton Farm Road Bridge No. 472. The work includes the complete demolition of the existing bridge superstructure, including, but not limited to pier footings, pier columns, pier caps, top of the abutment backwalls, wingwall barriers, approach slabs, to the limits shown on the contract drawings. The work for the new bridge superstructure shall include the installation of prefabricated deck panels that will be supported by steel plate girders. The concrete traffic barrier will be cast in place onto the deck panels. The prefabricated deck panels will be connected on site by the use of Ultra High Performance Concrete for the closure pours and shear stud blockouts. The work for the bridge substructure shall include, but not limited to, the replacement of the pier footings, pier columns, pier caps, abutment backwalls, wingwall barriers, and approach slabs for both north and south abutments.

Project Street/Location:

The project site (shown in red below) is located in East Providence, RI. The bridge is located on Horton Farm Road.

Page 66: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

4

1.2 Nature and Sequence of Construction Activity

RIPDES Construction General Permit – IV.E.1.b

Site Mobilization: Work under this sequence of activities includes the installation of site

erosion and sedimentation controls, clearing and grubbing, installation of field offices, installation

of temporary fencing, installation of temporary utilities, and storage of construction materials. The

approximate duration of this phase is expected to be one month.

Roadway Improvements: Work under this sequence of activities includes the micro-milling

and overlay of I-195, cleaning and adjusting of storm drain structures, guard rail replacement and

installation of roadway lighting. The approximate duration of this phase is expected to be three (3)

months.

Bridge Demolition: Work under this sequence of activities includes the demolition, removal

and disposal of the existing bridge superstructure, pier substructure, removal of existing the

abutments backwalls, approach slabs, wingwall barriers, and removal and disposal of bituminous

Page 67: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

5

pavements, removal and disposal of existing site features. The approximate duration of this

phase is expected to be thirty (30) days.

Bridge Construction: The work associated with this portion of the project includes the

installation of the new bridge superstructure using prefabricated deck panels that will be

supported by steel plate girders, the concrete traffic barrier on the bridge, the pier substructure,

abutment backwalls, wingwall barriers, and approach slabs. The approximate duration of this

phase is expected to be three (3) months.

Site Restoration: The work associated with this portion of the project includes site restoration.

Fine grading, loaming and seeding will occur. Temporary erosion controls will be removed, as

well as temporary construction aides will be demobilized. The approximate duration of this phase

is expected to be one (1) month.

Estimated Project Start Date: January 2018 (Notice to Proceed)

Estimated Project Completion Date: June 2019

Estimated Number of Months: 17 Months

1.3 Existing and Proposed Soils, Slopes, Vegetation, and Drainage Patterns

Soil type(s): RIPDES Construction General Permit – IV.E.1.e

According to a review of the USDA Natural Resources Conservation Service soils map for Providence County, Rhode Island, on-site soils along I-195 corridor consist of Udorthents (UD) soil type. UD soil type consists of moderately well drained to excessively drained soils. The hazard of erosion for UD soil type is low.

A section of I-195 corridor at the eastern limits of the site, between Horton Farm Road (Bridge 472) and County Street/Warren Avenue, consist of Udorthents (UD), Paxton Fine Sandy Loam (PaB) and Merrimac Fine Sandy Loam (MmB) soil types. UD soil type consists of moderately well drained to excessively drained soils and. The hazard of erosion for UD soil type is low. The permeability of PaB soil type is slow or very slow in the substratum. The hazard of erosion for PaB soil type is moderate. MmB soil type consists of somewhat excessively drained soils and the permeability of the soil is moderately rapid. The hazard of erosion for MmB soil type is moderate.

Slopes:

Existing: Areas around Bridge 472 abutments will require grading and utility installation areas along the I-195 corridor edges (north and south) will require grading. The slopes of grading or filling areas vary with a maximum of 2:1 slope (50%).

Proposed: There is no change to existing slopes at areas impacted by construction activities. The slopes of grading or filling areas vary with a maximum of 2:1 slope (50%).

Vegetation/Impervious Area:

Existing: The vegetative areas impacted by construction activities consist of grass areas. The impervious areas impacted by construction activities consist of bituminous pavement roadways.

Page 68: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

6

Proposed: There is no change to vegetative and impervious areas impacted by construction activities. The roadway work consists of micro-milling and overlay. The vegetative areas will be grass seeded.

Drainage Patterns:

Existing: Stormwater runoff from I-195 and Horton Farm Road (Bridge 472) roadway side slopes (vegetated areas) is directed to the I-195 closed drainage system via grass swales. Stormwater runoff from I-195 roadway surface flows through closed drainage system (catch basins, curb inlets, manholes and storm drains) to East Providence’s municipal separate storm drain system (MS4) at multiple tie-in locations: Broadway, Warren Ave, Wellington Street, East Shore Expressway,

Proposed: There is no change to existing drainage patterns.

1.4 Construction Site Estimates

RIPDES Construction General Permit – IV.E.1.c & IV.E.1.d

The following are estimates of the construction site:

Total Project Area 75 acres

Construction Site Area to be disturbed 6.5 acres

Percentage impervious area before construction 38 %

Runoff coefficient before construction 0.81

Percentage impervious area after construction 38 %

Runoff coefficient after construction 0.81

1.5 Receiving Waters

Receiving waters:

RIPDES Construction General Permit – III.A.7

List/description of receiving waters:

Runnins River- Existing topography indicates runoff from construction site flows east to river.

Storm sewer systems:

RIPDES Construction General Permit – III.A.7

Will construction site stormwater flow to any separate storm sewer systems?

Yes No

If yes, list the separate storm sewer systems and if permits/permission is required:

East Providence’s municipal separate storm drain system (MS4) - It is anticipated that existing storm drain system shown on existing plans discharges to the Runnins River during wet weather events.

Page 69: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

7

303(d)/TMDL waters:

RIPDES Construction General Permit – Section IV

Will project site stormwater flow to any 303(d) listed or TMDL water body (include both active construction and post-construction flow)?

Yes No

If yes, list & provide description of 303(d)/TMDL waters and applicable TMDL requirements:

Runnins River, State of Rhode Island 2014 303(d) List of Impaired Waters, TMDL is scheduled for 2026.

Special Resource Protection Waters (SRPWs):

Will construction site stormwater flow to any Special Resource Protection Waters (include both active construction and post-construction flow)?

Yes No

If yes, list & provide description of Special Resource Protection Waters:

State of Rhode Island Water Quality Regulations, Appendix D, Amended December 2010. SRPW Categories: Recreation, Ecological Habitat, Critical Habitat (Rare and Endangered Species), and Conservation Area.

Cold Water Fisheries:

Will construction site stormwater flow to any cold water fishery water body (include both active construction and post-construction flow)?

Yes No

If yes, list & provide description of Cold Water Fisheries:

1.6 Allowable Non-Storm Water Discharges

RIPDES Construction General Permit – IV.E.1.g

Are there allowable non-storm water discharges on or near the project area?

Yes No

List of allowable non-stormwater discharges:

It is anticipated that water will be used during the installation of concrete and bituminous pavements. Water will also be used for irrigation purposes to establish the seeding during vegetative restoration.

Are there any known or contaminated discharges, including dewatering operations, on or near the project area?

Yes No If yes, list the discharges and the RIPDES individual permit number(s) or RIPDES Remediation General Permit Authorization number(s) associated with these discharges.

Page 70: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

8

RIPDES individual permit number : N/A

RIPDES Remediation General Permit Authorization number: N/A

1.7 Existing Data of Known Discharges from Site

RIPDES Construction General Permit – IV.E.1.h

Are there known storm water discharges from the project area?

Yes No

Describe how this determination was made:

Existing topography indicates that stormwater runoff from construction site flows east to Runnins River. Also, surface runoff from the roadway corridor within the project site flows into East Providence’s municipal separate storm drain system (MS4) through the closed storm drain system. It is anticipated that existing storm drain system shown on site plans discharges to Runnins River during wet weather events.

If yes, list discharges and locations:

Seven RIDOT stormwater outfalls - west of Bridge 472 (DOT-NARR454, DOT-NARR453, DOT-NARR452, DOT-NARR451, DOT-NARR450, DOT-WARR020, DOT-NARR455)Three RIDOT stormwater outfalls – east of Bridge 472 (DOT-I95W02, DOT-WARR018, DOT-WARR021)

Is there existing data on the quality of the known storm water discharges?

Yes No

If yes, provide data:

1.8 Endangered Species Certification/Natural Heritage Areas

RIPDES Construction General Permit – Section V Are there any Natural Heritage Areas being disturbed by the construction activity or will discharges be directed to the Natural Heritage Area as a result of the construction activity?

Yes No

If yes, describe or refer to documentation which determines the likelihood of an impact on this area and the steps that will be taken to address any impacts.

1.9 Historic Preservation/Cultural Resources

Are there any historic properties, historic cemeteries or cultural resources on or near the construction site?

Yes No

Describe how this determination was made and summarize RIDOT-CRU review comments:

Page 71: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

9

The determination was based on 2013 National Register of Historic Places Map by National Park Service.

If yes, describe or refer to documentation which determines the likelihood of an impact on this historic property, historic cemetery or cultural resource and the steps taken to address that impact including any conditions or mitigation measures that were approved by other parties.

1.10 Site Features and Sensitive Areas to be Protected

Sensitive areas and measures that will be implemented to protect them:

This site does not contain any unique features or sensitive areas to be preserved.

Page 72: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

10

1.11 Potential Sources of Pollution

RIPDES Construction General Permit – IV.E.1.f

Anticipated on this Project

Operation/ Location Stormwater Pollutants

Y Clearing, grading, excavating, and unstabilized areas

Sediment; Trash/Debris

N Construction Entrance Sediment

Y Soil Stockpiles Sediment

Y Paving operations Sediment; Trash/Debris

Y Concrete washout and waste Heavy metals; pH; Trash/Debris

Y Structure construction/ painting/ cleaning

Nutrients; pH; Trash/Debris; Toxic chemicals

Y Demolition and debris disposal Sediment; Trash/Debris

N Dewatering operations Sediment; Nutrients

N Drilling and blasting operations Sediment; pH; Trash/Debris

Y Material delivery and storage Sediment; Nutrients; Heavy metals; pH; Pesticides/Herbicides; Oil/Grease; Trash/Debris; Toxic chemicals

Y Material use during building process Nutrients; heavy metals; pH; pesticides/herbicides; oil/grease; trash/debris; toxic chemicals

Y Solid waste/ trash/ debris trash/debris; toxic chemicals

N Hazardous waste heavy metals; pH; pesticides/herbicides; oil/grease; toxic chemicals

N Contaminated spills Nutrients; heavy metals; pH; pesticides/herbicides; oil/grease; toxic chemicals

N Sanitary/septic waste Nutrients; pH; Bacteria/Viruses; toxic chemicals

N Vehicle/equipment fueling and maintenance

Oil/Grease; Toxic chemicals

Y Vehicle/equipment use and storage Oil/Grease; Toxic chemicals

Y Landscaping operations Sediment; Nutrients; Trash/Debris

N Off-site LUHPPL run-on Industrial toxins; oil/grease; heavy metals; fuel; salt; hazardous materials

N/A Other:

Page 73: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

11

1.12 Site Plans

RIPDES Construction General Permit – IV.E.1.a

TITLE & DATE OF PLAN SET(S): Improvements to I-195, ABC Bridge No. 472 over I-195 Superstructure Replacement, Disturbance Areas – September 2017

Plan/Sheet #(s) Required Information Disturbance Areas Plans Sheet 1 of 11

Total Project Area, including all grading and/or excavation, and a defined Limit of Disturbance.

Disturbance Areas Plans Sheets 1 thru 11

Pre- and post-development drainage patterns including (but not limited to): sub-watershed limits, direction(s) of stormwater flow, locations of storm drain inlets and outfalls, existing and proposed conveyance systems (i.e. grass

channels, swales, closed drainage system)

The location and name of the receiving waters &/or separate storm sewer system

and the ultimate receiving waters (i.e. name of major watershed basin)

Disturbance Areas Plans Sheets 5, 8, 9 & 10

Location of resource protection areas including waters of the State, wetlands lakes,

ponds, coastal shoreline features and required setbacks (e.g. buffers, water supply wells, septic systems). Indicate below whether or not the areas have been verified in the field.

None Location of environmentally sensitive features/areas to be preserved &/or

protected (i.e. endangered species habitats, historic sites, natural heritage areas, Qualified Pervious Areas (QPAs)) (Section 1.10)

Disturbance Areas Plans Sheets 1 thru 11

Boundaries of existing vegetation to remain undisturbed

Disturbance Areas Plans Sheets 1 thru 11

The location of all impervious structures (existing and proposed roads, buildings,

and other structures)

Disturbance Areas Sheets 1 thru 11 & Construction Plans

Locations and timing of stabilization measures including phased clearing and

grubbing based on scheduled activities

Disturbance Areas Sheets 1 thru 11 & Construction Plans

The location of all structural erosion, sediment and runoff control BMPs (i.e.

sediment basins, outlet protection, etc.)

Disturbance Areas Sheets 1 thru 11 & Construction Plans

Locations of all non-structural BMPs (i.e. perimeter controls, check dams, storm

drain protection, etc.)

None The location of all permanent post-construction BMPs (i.e. WVTS, filtration

systems, etc)

Constraint Map, indicating areas within the project limits which are unsuitable for

material storage areas, equipment storage areas, designated concrete washout areas, dumpsters, stockpiles, fueling locations, etc. (i.e. locations where these activities will not occur, and recommendations of where they may occur) **(RECOMMEND SEPARATE PLAN SHEET)** Designated areas will not be within regulated wetlands, or within 50-feet of the storm drain system.

The location of spill prevention and response equipment

FIELD VERIFICATION INFORMATION

Date: Insert Date By: Insert Person/Company

Page 74: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

12

Verified by DEM: N/A No Yes Wetland Permit Issued: No Yes # _______________

Page 75: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

13

SECTION 2: EROSION AND SEDIMENTATION CONTROLS RIPDES Construction General Permit – Section IV.E.2.a

The purpose of erosion controls is to prevent sediment from moving onto, around, or off of the construction site. Properly installed and maintained erosion controls are the primary defense against sediment pollution.

Sedimentation controls are a second line of defense against moving sediment. The purpose is to prevent moving sediment from leaving the construction site and entering environmentally important areas.

Runoff controls are used to slow the velocity of concentrated water flows. By intercepting and diverting stormwater runoff to a stabilized outlet or treatment BMP, erosion and sedimentation are reduced.

Please note: Even if practices are correctly installed on a site according to the approved plan, the site is only in compliance when sediment and pollutants are effectively controlled throughout the entire site. If controls are repeatedly failing, it is the responsibility of the Resident Engineer and Construction Contractor to develop a corrective action plan that may include different controls than is depicted on the Approved Plan Set.

2.1 Minimize Disturbed Area and Protect Natural Features and Soil

As far as is practicable, existing vegetation will be protected and left in place, in accordance with the clearing limits shown on the approved Plans. Prior to any land disturbance activities commencing on the site, the Contractor will physically mark limits of disturbance (LOD) on the site and any areas to be protected within the site, so that workers can see the areas to be protected.

Natural vegetation shall be preserved on site where possible. This shall prevent erosion by providing continuous anchoring of the soil.

BMP Description: Topsoil stripped from the immediate construction area will be stockpiled as identified on the site plans. The stockpile will be in an area that will not interfere with construction phases and at least 15 feet away from areas of concentrated flows or pavement. The slopes of the stockpile will not exceed 2:1 to prevent erosion. A silt fence will be installed around the perimeter of the stockpile, in accordance with the RIDOT Stockpile Management Specifications. The stockpile will be temporarily stabilized with erosion controls. Installation Schedule: Topsoil stockpiles will be established during grading activities. Temporary stabilization will be applied immediately after the slopes of the stockpile have been graded and construction equipment transverses the slopes. Maintenance and Inspection: The area will be inspected weekly for erosion and immediately after storm events. Areas on or around the stockpile that have eroded will be stabilized immediately with erosion controls. Maintenance and inspection procedures for the silt fence are as described in RIDOT standard specifications.

Page 76: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

14

2.2 Phase Construction Activity

Proper sequencing of construction activities is essential to maximize the effectiveness of erosion and sediment control measures. The purpose is to reduce the amount and duration of soil exposed to erosion by wind, rain, runoff, and vehicle tracking.

Construction sequencing and timing of construction activities will include:

1. Installation of all erosion and sediment controls that are required to be in place and functional before any earthwork begins. This will be done in accordance with Sections 201, 206 through 211 of the RIDOT Standard Specifications.

2. Upon acceptable completion of site preparation and installation of erosion and sediment controls, site construction activities may commence. Routine inspection and maintenance and/or modification of erosion and sediment controls while earthwork is being done is required.

3. Final stabilization of any disturbed areas after earthwork has been completed.

Phase I – BEFORE EARTHWORK

Site Mobilization: Work under this sequence of activities includes the installation of site erosion and

sedimentation controls, clearing and grubbing, installation of field offices, installation of temporary

fencing, installation of temporary utilities, and storage of construction materials. The approximate

duration of this phase is expected to be one month. The anticipated start date is July 2017.

Temporary erosion and sediment control (TESC) measures will be installed in this phase prior to

construction activities. To prevent run-off of untreated stormwater and sediment from entering city

stormwater or sewer facilities, nearby water bodies, or adjacent properties, the following temporary

construction BMPs will be used:

1. Hay or straw bales barriers

2. Sediment fences

3. Filters for storm drain inlet protection

Phase II – DURING EARTHWORK

Bridge Demolition: Work under this sequence of activities includes the demolition, removal and disposal of the existing bridge superstructure, pier substructure, removal of existing the abutments backwalls, approach slabs, wingwall barriers, and removal and disposal of bituminous pavements, removal and disposal of existing site features. The approximate duration of this phase is expected to be thirty (30) days.

Bridge Construction: The work associated with this portion of the project includes the installation

of the new bridge superstructure using prefabricated deck panels that will be supported by steel plate girders, the concrete traffic barrier on the bridge, the pier substructure, abutment backwalls, wingwall barriers, and approach slabs. The approximate duration of this phase is expected to be three (3) months.

Roadway Improvements: Work under this sequence of activities includes the micro-milling and

overlay of I-195, cleaning and adjusting of storm drain structures, guard rail replacement

Page 77: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

15

and installation of roadway lighting. The approximate duration of this phase is expected to be three (3) months.

To prevent run-off of untreated stormwater and sediment from entering city stormwater or sewer

facilities, nearby water bodies, or adjacent properties, the following temporary construction BMPs will be used:

1. Hay or straw bales barriers 2. Sediment fences 3. Filters for storm drain inlet protection

The approximate duration of this phase is expected to be thirteen (13) months. The anticipated start

date is August 2017.

Phase III – FINAL STABILIZATION

Site Restoration: The work associated with this portion of the project includes site restoration. Fine

grading, loaming and seeding will occur. Temporary erosion controls will be removed, as well as

temporary construction aides will be demobilized. The approximate duration of this phase is expected

to be one (1) month. The anticipated end date is October 2018.

2.3 Control Stormwater Flowing Onto and Through the Project

Structural BMPs will be used to prevent stormwater flow from coming onto the project area, and to divert and slow on-site stormwater flow from exposed soils to limit erosion, runoff, and the discharge of pollutants from the site.

Control measures &/or methods that may be used include diversion ditches or berms, compost filter socks, fiber rolls, gravel bag berms, slope drains, check dams, and riprap.

BMP Description: Sediment fences and straw or hay bales shall be placed across construction ditches during construction to limit the transport of sediment into drainage systems and waterways, in accordance with RIDOT standards 9.3.0. Installation Schedule: Construction ditches will be protected with silt fence and bales of straw or hay at all times during construction. Maintenance and Inspection: The area will be inspected weekly for erosion and immediately after storm events. The area will be inspected for erosion and accumulation of debris and sediment. Debris and sediment shall be removed and eroded embankments shall be repaired immediately.

2.4 Stabilizing Soils

Phased Clearing & Grubbing:

Page 78: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

16

Only areas that can be reasonably expected to have active construction work being performed within 21-days of disturbance will be cleared/grubbed at any one time. It is NOT acceptable to clear and grub the entire construction site if disturbed portions will not be active within the 21-day time-frame.

Clearing/Grubbing will not take place during a rain event if erosion is likely to occur; nor will it occur if a rain event is forecasted and appropriate erosion controls can not be installed prior to the storm and in accordance with section 201, 206 through 211 of the RIDOT standard specifications.

No undisturbed areas will be cleared of existing vegetation after October 15th of any calendar year or during any period of full or limited winter shutdown. All disturbed soils exposed prior to October 15 of any calendar year will be seeded or protected by that date. Any such areas that do not have adequate vegetative stabilization, as determined by the resident engineer or environmental inspector, by November 15 of any calendar year, must be stabilized through the use of erosion control matting or hay mulch, in accordance with specifications contained within the RI Soil Erosion and Sediment Control Handbook (as amended). If work continues within any of these areas during the period from October 15 through April 15, care must be taken to ensure that only the area required for that Day’s work is exposed, and all erodible soil must be restabilized within 5 working days.

As per RIDOT Standard Specification 201.03.1 – Clearing and Grubbing: After clearing, and by the end of each day's grubbing operation, the Contractor will install erosion control measures that are indicated on the Plans or as directed by the Engineer. Such erosion control measures will be installed in strict accordance with the requirements of SECTIONS 206, 207, and 208 of these Specifications, PERIMETER EROSION CONTROLS, CHECK DAMS, and TEMPORARY DEWATERING BASINS, respectively.

Initiating Stabilization Practices

As per RIPDES General Permit (Construction Activity) Section IV.E.2.a: Upon completion and acceptance of site preparation and initial installation of erosion and sediment controls the operator will initiate appropriate stabilization practices during all phases of construction on all disturbed areas as soon as possible but not more than fourteen (14) days after the construction activity in that area has temporarily or permanently ceased, unless the activity is to resume within twenty one (21) days.

Any disturbed areas that will not have active construction activity occurring within twenty one (21) days must be stabilized using the BMPs depicted on the approved plan set and in accordance with RIDOT Standard Specifications Section L.02 – Seeding, Section L.05 - Seed Stabilizers and Section M.18 – Landscape Materials (M.18.08 – Mulch and M.18.09 – Seed Stabilizer Materials).

Maintaining Stabilization

Controls and methods that may be used to maintain soil stabilization include the placement of geotextiles, erosion control blankets/mats, and temporary seeding. If the stabilization BMPs fail and erosion occurs, then alternative control measures &/or methods may need to be substituted, with approval of the RIDOT Resident Engineer and the RIDOT Natural Resources Unit.

The following stabilization practices shall be implemented and maintained during the duration of the construction: Temporary Stabilization: While no further clearing and grubbing is proposed, erosion controls will limit the amount of exposed soils to active work areas. When no longer active, work areas will be fully stabilized prior to proceeding to additional work phases. Soil stockpiles and disturbed portions of the Construction Project Area where construction will cease for more than 14 days shall be temporarily stabilized with hydroseed in order to prevent slope erosion. Hydroseed shall consist of wood fibers, seed fertilizer, and stabilizing emulsion and shall be applied at a rate of

Page 79: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

17

eight pounds per 100 square feet. In winter (non-growing season), straw, jute netting and other commercially available matting shall be implemented on all exposed surfaces. Permanent Stabilization: Disturbed portions of the Subject Project Area where construction activities permanently ceases shall be stabilized by paving, placement of gravel, or planting as soon as practical, but no later than 14 calendar days of a temporary or permanent cessation of work. In winter (non-growing season), straw, spray on applications and other commercially available matting shall be implemented on all exposed surfaces.

2.5 Protect Slopes

Controls will be used to protect slopes from erosion from concentrated stormwater flow.

Slopes that will have concentrated stormwater flow will be protected using the BMPs depicted on the approved plan set and in accordance with RIDOT Standard Specifications Sections 202, 206 – 211, or any method approved of by the RIDOT Resident Engineer and the RIDOT Natural Resources Unit.

Control measures &/or methods that may be used to protect slopes include pipe slope drains, compost filter socks, fiber rolls, gravel bag berms, erosion control mats/blankets, and temporary vegetative cover.

BMP Description: Control matting shall be used on slopes 3:1 or steeper and in sloped planted areas subject to high wind exposure. Matting shall be installed in accordance with the manufacturer’s instructions and specifications. This matting shall serve to stabilize these steeper slopes and prevent erosion prior to the slope stabilization. The matting shall also assist in maintaining the soil moisture necessary to support dense vegetative plantings proposed for some of the steeper slopes. These dense plantings are proposed where environmental commitments require visual screening or where grass mowing would otherwise be difficult. On long cross slopes, compost filter socks shall be installed across the slope in order to intercept silt that flowed by the matting. The proposed filter socks as well as other blankets shall be properly staked to stabilize them and that the ends shall be overlapped a sufficient distance to prevent entrained sediment from bypassing the control. Installation Schedule: Matting shall be installed once the planted slopes have reached final grade. Maintenance and Inspection: The erosion control matting will be inspected weekly for erosion and immediately after storm events to determine if cracks, tears, or breaches have formed in the fabric; if so, the matting will be repaired or replaced immediately. Good contact with the soil must be maintained and erosion should not occur under the matting. Any areas where the matting is not in close contact with the ground will be repaired or replaced.

2.6 Protect Storm Drain Inlets

Storm drain inlet protection measures will be used to prevent soil and debris from entering storm drain inlets. These measures are usually temporary and are implemented before a site is disturbed. ALL stormwater inlets &/or catch basins that are operational during construction and may receive sediment-laden stormwater flow from the construction site must be protected using any of the BMPs outlined in the RIDOT Standard Specifications Section 209 – Storm Drain Protection, or any method approved of by the RIDOT Resident Engineer and the RIDOT Natural Resources Unit.

Control measures &/or methods that may be used include compost filter socks, fiber rolls, gravel bag berms, or catch basin inserts.

Page 80: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

18

BMP Description: Existing storm drain inlets (catch basins and drop inlets) will be protected from sediment by installing filters (woven polypropylene geotextile material) as specified in the contract specifications Section 206. Installation Schedule: Catch basins and drop inlets filters shall be installed before construction activities begin on-site. Maintenance and Inspection: Catch basins and drop inlets filters will be inspected weekly and immediately after storm events. If the filter becomes clogged with sediment, the filter will be removed and cleaned or replaced per the manufacturer’s recommendations.

BMP Description: Catch basins with grates that are to be exposed to sediment from the subgrade shall be protected with baled hay or straw staked in place around the inlet in accordance with RIDOT Standard 9.8.0. Installation Schedule: Baled Hay or straw shall be installed before construction activities begin on-site. Maintenance and Inspection: Baled Hay or straw will be inspected weekly and immediately after storm events to ensure that there are no gaps. If gaps or tears are found during the inspection, the baled hay or straw will be repaired or replaced immediately. Accumulated sediment will be removed and hauled off-site for disposal.

2.7 Protect Storm Drain Outfalls

Outfall protection will be used to prevent scour or severe erosion at discharge points. Outfalls often have high velocity, high volume flows, and require strong materials that will withstand the forces of the water. The function of these BMPs is to protect the soil surface, reduce velocity, and promote infiltration. Storm drain outlet BMPs also offer a last line of protection against sediment entering environmentally sensitive areas.

All stormwater outfalls that may discharge sediment-laden stormwater flow from the construction site must be protected.

Control measures &/or methods that may be used include compost filter socks, fiber rolls, gravel bag berms, or hay bales/silt fence.

BMP Description: Headwalls and flared ends shall be protected with baled hay or straw staked in place around the outlet in accordance with the construction details provided on the contract drawings and in accordance with RIDOT Standard 9.1.0. Installation Schedule: Baled Hay or straw shall be installed before construction activities begin on-site. Maintenance and Inspection: Baled Hay or straw will be inspected weekly and immediately after storm events to ensure that there are no gaps. If gaps or tears are found during the inspection, the baled hay or straw will be repaired or replaced immediately. Accumulated sediment will be removed and hauled off-site for disposal.

Page 81: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

19

2.8 Establish Perimeter Controls and Sediment Barriers

Perimeter controls will be used to prevent soil erosion and stop sediment from leaving the site. Perimeter controls will be installed, and maintained, as depicted on the approved plan set and in accordance with RIDOT Standard Specifications Section 201, 206 – 211, Perimeter Erosion Controls (installation) and Section 212 – Maintenance and Cleaning of Erosion and Pollution Controls (maintenance).

Control measures &/or methods that may be used include compost filter socks, fiber rolls, gravel bag berms, or hay bales/silt fence.

Perimeter controls shall be established at the limit of work at bottom of slopes (steeper than 4:1) and at areas adjacent to resource areas to prevent the erosion and migration of sediment during construction. BMP Description: Baled hay or straw staked in place shall be installed at the limit of work to protect adjacent resource areas (wetlands and drainage swales) in accordance with RIDOT Standard 9.1.0. Installation Schedule: Baled Hay or straw shall be installed before construction activities begin on-site. Maintenance and Inspection: Baled Hay or straw will be inspected weekly and immediately after storm events to ensure that there are no gaps. If gaps or tears are found during the inspection, the baled hay or straw will be repaired or replaced immediately. Accumulated sediment will be removed and hauled off-site for disposal. BMP Description: Baled hay or straw check dams staked in place shall be installed across ditches and swales to limit the transport of sediment into drainage systems and waterways at locations identified in the contract drawings and in accordance with RIDOT Standard 9.4.0. Installation Schedule: Baled Hay or straw check dams shall be installed before construction activities begin on-site. Maintenance and Inspection: Baled Hay or straw check dams will be inspected weekly and immediately after storm events to ensure that there are no gaps. If gaps or tears are found during the inspection, the baled hay or straw will be repaired or replaced immediately. Accumulated sediment will be removed and hauled off-site for disposal. BMP Description: Sediment fences and straw or hay bales shall be installed at the limit of work to protect adjacent resource areas (wetlands and drainage swales) in accordance with RIDOT standards 9.3.0. Installation Schedule: Silt fence and bales of straw or hay shall be installed before construction activities begin on-site. Maintenance and Inspection: Silt fence and straw or hay bales will be inspected weekly and immediately after storm events to ensure that there are no gaps or tears. If gaps or tears are found during the inspection, the silt fence and baled hay or straw will be repaired or replaced immediately. Accumulated sediment will be removed and hauled off-site for disposal.

Page 82: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

20

2.9 Retain Sediment On-Site and Control Dewatering Practices

Sediment traps, basins, and barriers are used to retain sediment on the site to protect streams, lakes, drainage systems, and adjacent property. These devices are used at the outlets of channels, diversions, and other runoff conveyance measures to allow sediment-filled water to pool and sediment to settle. These measures are often used as the last line of defense to stop sediment from leaving the site. The dewatering of non-contaminated non-stormwater (i.e. groundwater) or accumulated precipitation discharge of sediment-laden water into storm drains, streams, lakes or wetlands prior to sediment removal is prohibited. The dewatering of contaminated non-stormwater cannot be discharged without prior notice and approval from either the Rhode Island Department of Environmental Management (RIDEM) or the Coastal Resources Management Council (CRMC). Should dewatering of contaminated water be occurring on this construction project, appropriate permits will have been obtained, and will be included as part of the Contract Documents.

BMP Description: Storm drain outlet headwalls and flared ends shall be protected with sediment trap of baled hay or straw staked in place around the outlet in accordance with the construction details provided on the contract drawings and in accordance with RIDOT Standard 9.1.0. Installation Schedule: Baled Hay or straw shall be installed before construction activities begin on-site. Maintenance and Inspection: Baled Hay or straw will be inspected weekly and immediately after storm events to ensure that there are no gaps. If gaps or tears are found during the inspection, the baled hay or straw will be repaired or replaced immediately. Accumulated sediment will be removed and hauled off-site for disposal.

There are no dewatering activities required for the installation of the new bridge/utilities and the micro-milling and overlay of I-195 roadway.

2.10 Monitoring Weather Conditions

Care will be taken to avoid having unstabilized areas exposed during precipitation events. Weather forecasts will be routinely checked, and in the case of an expected precipitation event of over 0.25-inches over a 24-hour period, all BMPs will be inspected, and maintained as necessary, prior to the weather event.

In the case of an extreme weather forecast (greater than one-inch of rain over a 24-hour period), additional erosion/sediment controls will be installed where appropriate.

The weather station that will be utilized is Fox Point (KRIPROVI19)

2.11 Additional BMPs

BMP Description: Pavement cleaning and sweeping shall be applied in accordance with RIDOT Standard Specifications Section 931 to remove sediments and other contaminants from the paved surfaces.

Page 83: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

21

Installation Schedule: Pavement cleaning and sweeping will occur weekly and before forecasted storm events on I-195 and ramps within the project limits. Maintenance and Inspection: All materials collected during pavement cleaning and sweeping will be disposed of at an off-site location by the contractor.

2.12 Construction Site Erosion and Sediment Control BMPs

It is expected that this table will be amended as needed throughout the construction project.

Location/Station BMP Description/ Standard Spec Ref

Maintenance Requirement Phase

Perimeter

Baled Hay Erosion Checks/Silt Fence. 206.01.3/9.3.0

212.03.1 Sediment accumulated greater than half way up bale; break through or significant strain of barrier

All Phases

Page 84: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

22

SECTION 3: GOOD HOUSEKEEPING BMPS RIPDES Construction General Permit – Section IV.E.2.c

The purpose of good housekeeping is to prevent daily construction activities from causing pollution.

Describe the key good housekeeping and pollution prevention measures that will be implemented to control pollutants in stormwater. Examples BMPs include the proper management of waste, material handling and storage, and equipment/vehicle fueling/washing/maintenance operations.

Include RIDOT Standard Specification or Standard Detail reference with maintenance requirements.

3.1 Off-site Tracking of Sediments

RIPDES Construction General Permit – IV.E.2.c.i

Any construction site access point will employ the BMPs depicted on the approved plan set and in accordance with RIDOT Standard Specifications Section 211 – Construction Accesses, or any method approved of by the RIDOT Resident Engineer and the RIDOT Natural Resources Unit. Construction accesses will be used in conjunction with the stabilization of construction roads to reduce the amount of mud picked up by construction vehicles. All RI STD 9.9.0 Construction Access roads will be constructed prior to any roadway accepting construction traffic.

If a Construction Access BMP is not designated on the plans, it is still the responsibility of the Operator to ensure that no sediment is tracked off of the construction site by any vehicles leaving the site. Additional control measures that may be used, upon approval, include a vehicle washing station and daily street sweeping.

The Operator will remain responsible for the clean-up of any mud or dirt that is tracked onto streets or paved areas, even with the installation of gravel construction entrances. Inspect access for excessive sediment build up. Remove sediment and rebuild the exit as necessary to retain effectiveness and prevent off-site tracking. Additional street cleaning may be required if unable to retain sediment on site.

BMP Description: Anti-tracking pads consisting of crushed stone and geogrid material shall be installed at the exits of the construction laydown area, as identified on the Site Plans, in accordance with RIDOT Standard 9.9.0 to prevent to prevent the off-site transport of sediment by construction vehicles. Additional anti-tracking pads will be installed at construction exit locations as requested by the RIDOT Resident Engineer. Installation Schedule: The stabilized exits will be installed before construction begins on the site. The anti-tracking pads will be placed on the pavement or gravel and will remain until all areas of the site have been stabilized. Maintenance and Inspection: The exits will be inspected weekly and after storm events or heavy use. The exits will be maintained in a condition that will prevent tracking or flowing of sediment onto I-195 and ramps within project limits. This could require adding additional crushed stone to the exit. All sediment tracked, spilled, dropped, or washed onto I-195 and ramps will be swept up immediately and hauled off-site for disposal. Sediment will be swept from the anti-tracking pad at least weekly, or more often if necessary. If excess sediment has clogged the pad, the exit will be top dressed with new crushed stone. Replacement of the entire pad might be necessary when the pad becomes completely filled with sediment. The pad will be reshaped as needed for drainage

Page 85: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

23

and runoff control. Broken road pavement as a result of construction activities on roadways immediately adjacent to the project site will be repaired immediately. The removed stone and sediment from the pad will be hauled off-site for disposal.

3.2 Waste Disposal

RIPDES Construction General Permit – IV.E.2.c.ii

Building materials and other construction site wastes will be properly managed and disposed of to prevent the discharge of solid materials from wind and precipitation. All types of waste generated at the site will be disposed of in a manner consistent with State Law and/or regulations.

The waste collection area will not be within any of the constraint areas located on the “Constraint Map” (Section 1.12) and will be approved by the RIDOT Resident Engineer.

All waste containers will be covered to avoid contact with wind and precipitation.

Waste collection will be scheduled frequently enough to prevent containers from overfilling.

All construction site wastes will be collected, removed, and disposed of in accordance with applicable regulatory requirements and only at authorized disposal sites.

Equipment and containers will be checked for leaks, corrosion, support or foundation failure, or other signs of deterioration. Those that are found to be defective will be immediately repaired or replaced.

BMP Description: All non-hazardous waste materials will be collected and disposed of into metal trash dumpsters placed in the contractor laydown area. Dumpsters will have a secure watertight lid, be placed away from stormwater conveyances and drains, and meet RIDEM, Division of Waste Management regulations. Only trash and construction debris from the site will be deposited in the dumpster. No construction materials will be buried on-site. All personnel will be instructed, during tailgate training sessions, regarding the correct disposal of trash and construction debris. Notices that state these practices will be posted in the office trailer and the individual who manages day-today site operations will be responsible for seeing that these practices are followed. Installation Schedule: Trash dumpsters will be installed once the contractor laydown area has been established. Maintenance and Inspection: The dumpsters will be inspected weekly and immediately after storm events. The dumpster will be emptied weekly and taken to designated off-site disposal location. If trash and construction debris are exceeding the dumpster’s capacity, the dumpsters will be emptied more frequently.

BMP Description: Hazardous materials will be stored and disposed of off-site in accordance with RIDOT Standard Specifications Section 107.17 and RIDEM regulations and requirements. All hazardous waste materials (i.e. oil filters, petroleum products, and equipment maintenance fluids) shall be stored in structurally sound and sealed shipping containers, within a hazardous materials storage area. Hazardous materials shall be stored in appropriate and clearly marked containers and segregated from other non-hazardous materials. Secondary containment shall be provided

Page 86: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

24

for all hazardous waste materials, and shall consist of commercially available spill pallets. All hazardous materials shall be disposed of in accordance with RIDEM regulations and requirements. Hazardous waste shall not be disposed of into the on-site solid waste dumpsters. All personnel shall be instructed, during tailgate training sessions, regarding proper procedures for hazardous waste disposal. Notices that state these procedures shall be posted in the office trailer and the individual who manages day-to-day operations shall be responsible for seeing that these procedures are followed. Installation Schedule: Shipping containers used to store hazardous waste materials will be installed once the hazardous materials storage area has been established. Maintenance and Inspection: The hazardous waste material storage areas will be inspected weekly and after storm events. The storage areas will be kept clean, well-organized, and equipped with ample cleanup supplies as appropriate for the materials being stored. Material safety data sheets, material inventory, and emergency contact numbers will be maintained in the office trailer.

3.3 Spill Prevention and Control Plan

RIPDES Construction General Permit – IV.E.2.c.iii

Spills and leaks will be avoided through frequent inspection of equipment and material storage areas. Heavy equipment and other vehicles will be routinely inspected for leaks and repaired as necessary. Material storage areas will be routinely inspected for leaky containers, open containers, or improper storage techniques that may lead to spills or leaks. Appropriate cleanup procedures and supplies will be available on-site.

Spills will be cleaned up immediately and following proper response procedures and in accordance with any applicable regulatory requirements. At no time will spills be cleaned and flushed down storm drains or in to any environmentally sensitive area (i.e. stream, pond, wetland).

Equipment/vehicle fueling and repair/maintenance operations or hazardous material storage will not take place within any of the constraint areas located on the “Constraint Map” (Section 1.12) and will be approved by the RIDOT Resident Engineer.

BMP Description:

o Employee Training: All employees will be trained via biweekly tailgate sessions.

o Vehicle Maintenance: Vehicles and equipment will be maintained off-site. All vehicles and equipment including subcontractor vehicles will be checked for leaking oil and fluids. Vehicles leaking fluids will not be allowed on-site. Drip pans will be placed under all vehicles and equipment that are parked overnight.

o Hazardous Material Storage and Disposal: Hazardous materials will be stored and disposed of off-site in accordance with RIDOT Standard Specifications Section 107.17 and RIDEM regulations and requirements.

o Spill Kits: Spill kits will be within the materials storage area and concrete washout areas.

o Spills: All spills will be cleaned up immediately upon discovery. Spent absorbent materials and rags will be hauled off-site immediately after the spill is cleaned up for disposal. Spills large enough to discharge to surface water will be reported to the National Response Center at 1-800-424-8802.

Page 87: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

25

o Material safety data sheets, a material inventory, and emergency contact information will be maintained at the on-site project trailer.

Installation Schedule: The spill prevention and control procedures will be implemented once construction begins on-site.

Maintenance and Inspection: All personnel will be instructed, during tailgate training sessions, regarding the correct procedures for spill prevention and control. Notices that state these practices will be posted in the office trailer, and the individual who manages day-to-day site operations will be responsible for seeing that these procedures are followed.

3.4 Control of Allowable Non-Storm Water Discharges

RIPDES Construction General Permit – IV.E.2.c.iv

Non-storm water discharges must also be controlled to reduce the likelihood of contamination of the ‘clean’ water. Allowable discharges should be kept separate from stormwater flow through the use of BMPs.

For contaminated non-stormwater discharge(s), the requirements and regulations of the associated RIPDES individual permit or RIPDES Remediation General Permit must be adhered to at all times.

Any changes in construction activities that produce other allowable non-stormwater discharges will be identified, and the SWPPP will be amended and the appropriate erosion and sediment control will be implemented.

3.5 Establish Proper Building Material Staging Areas

RIPDES Construction General Permit – IV.E.2.c.v

Stock pile management consists of procedures and practices designed to minimize or eliminate the discharge of stockpiled material (soil, topsoil, base material, rubble) from entering drainage systems or water courses.

Stock piles will not be located within any of the constraint areas located on the “Constraint Map” (Section 1.12) and will be approved by the RIDOT Resident Engineer. They will have side slopes no greater than 30% and stockpiles of erodible material will be seeded and ringed with RI STD 9.1.0 to stabilize (or RIDOT approved equivalent: berms, dikes, fiber rolls, compost socks, sandbag, gravel bags).

If soil stockpiles are not stabilized with vegetation, then they must be securely covered at the end of each workday.

All chemicals and/or hazardous waste material must be stored properly and legally in covered areas, with containment systems constructed in or around the storage areas. Areas must be designated for materials delivery and storage. Designated areas will not be located within any of the constraint areas located on the “Constraint Map” (Section 1.12) and will be approved by the RIDOT Resident Engineer.

INSERT TEXT

Page 88: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

26

3.6 Designate Washout Areas

RIPDES Construction General Permit – IV.E.2.c.v

Concrete mixer trucks and chutes will be washed in a designated area or concrete wastes will be properly disposed of off-site. Washout areas for concrete, paint or any other material will not be within any of the constraint areas located on the “Constraint Map” (Section 1.12) and will be approved by the RIDOT Resident Engineer.

Temporary concrete washout areas must be constructed and maintained to contain all water and concrete waste generated by washout operations. A sign should be placed at the washout site to inform concrete equipment operators of the facility location. Facilities must be cleaned or replaced when they reach 75% capacity.

At no time will any material (concrete, paint, chemicals) be washed into storm drains, open ditches, streets, streams, wetlands, or any environmentally sensitive area. The site operator must ensure that construction waste is properly and legally disposed of, to avoid exposure to precipitation, at the end of each working day. Designated areas will not be located within any of the constraint areas located on the “Constraint Map” (Section 1.12) and will be approved by the RIDOT Resident Engineer.

INSERT TEXT

3.7 Establish Proper Equipment/Vehicle Fueling and Maintenance Practices

RIPDES Construction General Permit – IV.E.2.c.v

Vehicle fueling, maintenance and/or washing will occur off-site, or in designated areas. Designated areas will not be located within any of the constraint areas located on the “Constraint Map” (Section 1.12) and will be approved by the RIDOT Resident Engineer.

Areas will be clearly designated, and berms, sandbags, or other barriers will be used around the perimeter of the maintenance area to prevent storm water contamination.

Construction vehicles will be inspected frequently for leaks. Repairs will take place immediately. Disposal of all used oil, antifreeze, solvents and other automotive-related chemicals will be according to applicable regulations; at no time will any material be washed down the storm drain or in to any environmentally sensitive area.

INSERT TEXT

3.8 Dust Control

RIPDES Construction General Permit – IV.E.2.c.v

Dust control procedures and practices will be used to suppress dust on a construction site during the construction process, as applicable. Precipitation, temperature, humidity, wind velocity and direction will determine amount and frequency of applications. However, the best method of controlling dust is to prevent dust production. This can best be accomplished by limiting the amount of bare soil exposed at one time. RIDOT Standard Specifications Section 907 – Dust Control – will be followed.

Page 89: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

27

Dust Control methods may include watering, surface roughening, wind barriers, walls, and covers.

BMP Description: Dust from the site will be controlled in accordance with RIDOT Standard Specifications Section 907. Water and/or calcium chloride will be applied to disturbed areas. An average of one gallon of water per square yard of exposed area will be considered for each treatment. The exact number of applications and amount of water and/or calcium chloride shall be based upon field and weather conditions. Installation Schedule: Dust control will be implemented as needed once site grading has been initiated and during windy conditions (forecasted or actual wind conditions of 20 mph or greater) while site grading is occurring. The work shall be done upon order of the Resident Engineer. Maintenance and Inspection: At least one mobile unit will be available at all times to distribute potable water and/or calcium chloride to control dust on the project area. Each mobile unit will be equipped with a positive shutoff valve to prevent over watering of the disturbed area.

3.9 Sweeping

RIPDES Construction General Permit – IV.E.2.c.v

Sweeping of streets, roads, highways and parking lots that have accumulated significant amounts of pollutants (construction site sediment, trash, debris) will be done as necessary, or as directed by the RIDOT Resident Engineer. When construction exits are not keeping construction site sediment from the roadway, sweeping will be done on a daily basis. Disposal of collected sweeping material will follow RIDOT Standard Specifications Section 931 – Cleaning and Sweeping Pavement.

BMP Description: Anti-tracking pads consisting of crushed stone and geogrid material shall be installed at the exits of the construction laydown area, as identified on the Site Plans, in accordance with RIDOT Standard 9.9.0 to prevent to prevent the off-site transport of sediment by construction vehicles. Additional anti-tracking pads will be installed at construction exit locations as requested by the RIDOT Resident Engineer. Installation Schedule: The stabilized exits will be installed before construction begins on the site. The anti-tracking pads will be placed on the pavement or gravel and will remain until all areas of the site have been stabilized. Maintenance and Inspection: The exits will be inspected weekly and after storm events or heavy use. The exits will be maintained in a condition that will prevent tracking or flowing of sediment onto I-195 and ramps within project limits. This could require adding additional crushed stone to the exit. All sediment tracked, spilled, dropped, or washed onto I-195 and ramps will be swept up immediately and hauled off-site for disposal. Sediment will be swept from the anti-tracking pad at least weekly, or more often if necessary. If excess sediment has clogged the pad, the exit will be top dressed with new crushed stone. Replacement of the entire pad might be necessary when the pad becomes completely filled with sediment. The pad will be reshaped as needed for drainage and runoff control. Broken road pavement as a result of construction activities on roadways immediately adjacent to the project site will be repaired immediately. The removed stone and sediment from the pad will be hauled off-site for disposal.

Page 90: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

28

3.10 Additional BMPs

There are no additional BMPs required for the replacement of Bridge 472, utilities installation and micro-milling and overlay of I-195.

3.11 Construction Site Good Housekeeping BMPs

It is expected that this table will be amended as needed throughout the construction project.

Location/Station BMP Description/ Standard Spec Ref Maintenance Requirement Phase

Construction Site Entrance/Exit

Rock/RipRap entrance pad 211.03/9.9.0

Replenish/Replace aggregate if it becomes clogged with sediment and is no longer effectively preventing sediment from being tracked into street

All Phases

Adjacent Roads

Public roads adjacent to a construction site will be clean at the end of each day 211.01.1

Street Sweep if construction site sediment is visible

All Phases

Site Wide Pick up of construction trash and debris

All loose trash and debris must be disposed of properly at the end of each working day

All Phases

Page 91: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

29

SECTION 4: POST-CONSTRUCTION BMPs RIPDES Construction General Permit – Section IV.E.2.b

Post-Construction Best Management Practices are BMPs that are installed during the Construction Phase of a project to manage storm water flow after the construction project is completed.

Measures must be installed during the construction project to protect permanent or long term BMPs as they are installed so that they will function properly when they are brought online at the end of the construction phase.

Such long-term BMPs may include: infiltration basins, open vegetated swales and natural depressions, vegetated buffer strips, and detention/ retention structures. Controls may also be needed to prevent or minimize erosion at outfall locations or along the length of vegetated channels to reduce velocity flow from the structure to the receiving waters.

Control measures that may need to be implemented during the construction phase typically include measures to ensure proper installation of the long-term BMPs. Examples include: ensuring proper material staging areas, equipment routing (i.e. do not allow construction equipment to compact areas where infiltration BMPs will be installed), and final cleaning of structural BMPs before construction finalization.

4.1 Post-Construction BMPs

Post-construction BMPs are not proposed for this project as the majority of the project involves resurfacing existing roadway (I-195), replacing an existing bridge (No. 472) and associated improvements. There is no net increase of impervious areas at the project site.

Page 92: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

30

SECTION 5: MAINTENANCE and INSPECTIONS RIPDES Construction General Permit – Section IV.E.2.d

5.1 Maintenance

Maintenance procedures for erosion and sedimentation controls and stormwater management structures/facilities are described on the plans, in Section 212 of the RHODE ISLAND DEPARTMENT OF TRANSPORTATION Standard Specifications for Road and Bridge Construction 2004 EDITION (as amended), and in the Stormwater Management Analysis documentation. As cited:

212.03 CONSTRUCTION METHODS. Erosion and pollution controls will be maintained by the Contractor to the satisfaction of the Engineer. Erosion and pollution controls must be able to prevent, under normal weather conditions, both the movement of soil materials and the intrusion of sediment-laden discharges into environmentally sensitive areas. Construction will not commence or continue until all specified erosion and pollution controls are in place, properly installed and accepted by the Engineer. Erosion and pollution controls will be routinely inspected by the Engineer. The Engineer will notify the Contractor immediately if problems develop. The Contractor will commence cleaning and maintenance measures no later than the next consecutive calendar day after receiving a directive from the Engineer to perform such measures. The Contractor will aggressively and expeditiously perform such cleaning and maintenance work until the original problem is remedied to the complete satisfaction of the Engineer. In the event of a weekend storm, the Contractor must have resources available to restore, and, if necessary, to replace any damaged controls.

The Contractor is required to have a full-time, on-site designated contact person responsible for working with the RIDOT Resident Engineer and the RIDOT designated Inspector to resolve SWPPP-related issues.

5.2 Inspections

RIPDES Construction General Permit – Section II.B & Section II.D Minimum Monitoring and Reporting Requirements All storm water control measures, disturbed areas, areas used for the storage of materials that are exposed to precipitation (including unstabilized soil stockpiles), discharge locations, and locations where vehicles enter or exit the site must be inspected at least once every seven (7) calendar days and within twenty-four (24) hours after any storm event which generates at least 0.25-inches of precipitation per twenty four (24) hour period and/or after a significant amount of runoff or snowmelt. An appropriate rain gauge (as identified in Section 2.4 of this SWPPP)) will be utilized for the determination of the storm events.

It is the responsibility of the RIDOT Resident Engineer to coordinate with the designated SWPPP Inspector listed in SECTION 8 of this document to initiate site inspections. Inspections will begin as soon as the Contractor is mobilized and on site.

Page 93: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

31

General Notes

The RIDOT Designated Inspector will prepare a separate inspection report for each inspection.

The Inspection Reference Number will be a combination of the Construction Contract Number - consecutively numbered inspections. ex/ Inspection reference number for the 4th inspection of a project would be: 2011-AA-BBB-4

Each report will be signed and dated by the Inspector and forwarded to the Engineer within 24 hours of the inspection.

Each report will be signed and dated by the Engineer and forwarded to the Contractor’s designated representative.

Each report will be signed and dated by the Contractor upon receipt.

If Corrective Actions are required, the Contractor will initiate appropriate measures within 24 hours of receiving of the inspection report.

It is the responsibility of the RIDOT Resident Engineer to maintain a copy of the SWPPP, copies of all completed inspection reports, and amendments as part of the SWPPP documentation at the project field office during construction.

Submitting Reports to NRU The Inspector will submit all Inspection Reports to:

RIDOT Natural Resources Unit Two Capitol Hill, Rm. 323

Providence, RI 02903 At a minimum, the inspection reports must be submitted on a monthly basis, and must include:

A copy of each completed, dated, and signed inspection report

Associated photos – each photo should be dated and have a unique identification # and written description indicating where it is located within the project area. If a close up photo is required, it should be preceded with a photo including both the detail area and some type of visible fixed reference point. Photos should be annotated with Station numbers and other identifying information where needed.

A copy of the daily rainfall summary data for the month as reported by the selected rain gauge. One copy of the monthly inspection report will be printed double-sided (except for photo or plan sheet pages), and forwarded to the NRU by no later than the 10th of the month following the end of the reporting period. Content, frequency, &/or submission format of inspection reports may be changed with approval of the applicable Natural Resources Unit personnel for the Project. A copy of the inspection report is attached.

REFERENCE ATTACHMENT

Page 94: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

32

5.3 Corrective Actions

RIPDES Construction General Permit – Section II.C If, in the opinion of the Engineer, corrective action is required, the Engineer will note it on the inspection report and will notify and direct the Contractor to take corrective action and make all necessary repairs whenever maintenance of the erosion and pollution controls is required. In accordance with the SWPPP and Section 212 of the RIDOT Standard Specifications, the Contractor will commence with the requisite cleaning and maintenance measures no later than the next consecutive calendar day after receiving such a directive from the Engineer, and will aggressively and expeditiously perform such cleaning and maintenance work until the original problem is remedied to the complete satisfaction of the Engineer. In accordance with the General Permit and the SWPPP, non-compliance issues will be addressed no later than seven (7) calendar days from the date of inspection. If the Engineer decides on any given day that those erosion and pollution controls specified in the Contract are not in place or have not been adequately maintained as specified in this Section, the daily charge set forth in Special Provision Code 212.1000 will be deducted from monies due the Contractor as a charge for failure to comply with this Specification. Moreover, the stated daily charge will continue each consecutive calendar day thereafter until the deficiencies noted have been corrected to the complete satisfaction of the Engineer.

Page 95: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

33

SECTION 6: Amendments RIPDES Construction General Permit – Section IV.D This SWPPP is intended to be a working document. It is expected that amendments will be required throughout the construction of the project. Even if practices are installed on a site according to the approved plan, the site is only in compliance when erosion and sedimentation are effectively controlled throughout the entire site. The SWPPP will be amended whenever there is a change in design, construction, operation, maintenance or other procedure which has a significant effect on the potential for the discharge of pollutants, or if the SWPPP proves to be ineffective in achieving its objectives (i.e. the selected BMPs are not effective in controlling erosion or sedimentation). All revisions must be recorded in the Record of Amendments Log Sheet within the SWPPP, and dated red-line drawings and/or a detailed written description must be appended to the SWPPP. Inspection Forms must be revised to reflect all amendments. Update the Revision Date and the Version # in the footer of the Report to reflect amendments made. All SWPPP Amendments, except minor non-technical revisions, must be approved by the Resident Engineer. Attach a copy of the Amendment log

REFERENCE ATTACHMENT

Page 96: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

34

SECTION 7: Recordkeeping RIPDES Construction General Permit – Section II.A & Section II.D

It is the RIDOT Resident Engineer’s responsibility to have the following documents at the Field Office and immediately available for RIDEM review upon request:

A copy of the fully signed and dated SWPPP, which includes:

o The signed and certified NOI form or permit application form INCLUDED AS ATTACHMENT ______

o A copy of the RIPDES General Permit INCLUDED AS ATTACHMENT ______

o A copy of any regulatory permits (RIDEM Freshwater Wetlands Permit, CRMC, RIDEM Water Quality, etc) INCLUDED AS ATTACHMENT ______

o SWPPP Amendment Log INCLUDED AS ATTACHMENT ______

Copies of all signed and dated Inspection reports

Page 97: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

35

SECTION 8: Party Certifications RIPDES Construction General Permit – Section V.G

All parties working for the Rhode Island Department of Transportation are required to comply with the Stormwater Pollution Prevention Plan (SWPPP) for any work that is performed on-site. Any person or group who violates any condition of the SWPPP may be subject to substantial penalties or loss of contract. Contractors and Sub-Contractors are encouraged to advise all employees working on this project of the requirements of the SWPPP. A copy of the SWPPP is available for your review at the RIDOT Field Office, or may be obtained from the RIDOT Natural Resources Office by calling (401) 222-2023.

The prime contractor and each subcontractor engaged in activities at the construction site that could impact stormwater must be identified and sign the following certification statement.

Page 98: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

Stormwater Pollution Prevention Plan (SWPPP)

Improvements to I-195, Superstructure Replacement Bridge 472

36

I acknowledge that I have read and understand the terms and conditions of the SWPPP for the above designated project and agree to follow the BMPs and practices described in the SWPPP.

RIDOT Resident Engineer:

Insert Company or Organization Name

Insert Name & Title

Insert Address ____________________________

Insert City, State, Zip Code signature/date

Insert Telephone Number, Insert Fax/Email

RIDOT SWPPP Inspector:

Insert Company or Organization Name

Insert Name & Title

Insert Address ____________________________

Insert City, State, Zip Code signature/date

Insert Telephone Number, Insert Fax/Email

Contractor SWPPP Contact:

Insert Company or Organization Name

Insert Name & Title

Insert Address ____________________________

Insert City, State, Zip Code signature/date

Insert Telephone Number, Insert Fax/Email

SubContractor SWPPP Contact:

Insert Company or Organization Name

Insert Name & Title

Insert Address ____________________________

Insert City, State, Zip Code signature/date

Insert Telephone Number, Insert Fax/Email

Insert more contact/signature lines as necessary

Page 99: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

RIDOTVersion 2.20120529

SWPPP APPENDICES Attach the following documentation to the SWPPP:

Attachment A – General Location Map

Attachment B – Site Plans

Attachment C – Copy of RIPDES General Permit

Attachment D – Copy of RIPDES NOI

Attachment E – Copy of Regulatory Permits

Attachment F – Inspection Form

Attachment G – Amendments Log

Attachment H – Additional Information (i.e. documentation)

Page 100: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

louisberger.com

RI Department of Transportation

Improvements to I-195, ABC Bridge No. 472 over I-195 Superstructure Replacement

SWPPP

ATTACHMENT A

General Location Map

Page 101: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

¯

Figure 1Improvements to I-195

Superstructure Replacement Bridge No. 472

Site Location

Sources:ESRI BING Map Service, 2016.

Site located in East Providence, RI Quadrangle

Louis Berger, 2017.

Providence

Kent

Bristol

September 2017

Project Area

Coordinate System:Rhode Island State Plane, Feet

Datum: NAD 1983 20110 1,000500

Feet

Page 102: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

¯

Figure 2Improvements to I-195

Superstructure Replacement Bridge No. 472

Roads

Sources:ESRI BING Road Map

Service, 2016.Louis Berger, 2017

Providence

Kent

Bristol

September 2017

Project Area

Coordinate System:Rhode Island State Plane, Feet

Datum: NAD 1983 20110 1,000500

Feet

Page 103: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

louisberger.com

RI Department of Transportation

Improvements to I-195, ABC Bridge No. 472 over I-195 Superstructure Replacement

SWPPP

ATTACHMENT B

Site Plans

Page 104: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

EAST PROVIDENCE, RHODE ISLAND

DEPARTMENT OF TRANSPORTATION

RHODE ISLAND

DISTURBANCE AREAS

SHEET 1 OF 11

Page 105: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

EAST PROVIDENCE, RHODE ISLAND

DEPARTMENT OF TRANSPORTATION

RHODE ISLAND

DISTURBANCE AREAS

SHEET 2 OF 11

Page 106: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

EAST PROVIDENCE, RHODE ISLAND

DEPARTMENT OF TRANSPORTATION

RHODE ISLAND

DISTURBANCE AREAS

SHEET 3 OF 11

Page 107: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

EAST PROVIDENCE, RHODE ISLAND

DEPARTMENT OF TRANSPORTATION

RHODE ISLAND

DISTURBANCE AREAS

SHEET 4 OF 11

Page 108: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

EAST PROVIDENCE, RHODE ISLAND

DEPARTMENT OF TRANSPORTATION

RHODE ISLAND

DISTURBANCE AREAS

SHEET 5 OF 11

Page 109: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

EAST PROVIDENCE, RHODE ISLAND

DEPARTMENT OF TRANSPORTATION

RHODE ISLAND

DISTURBANCE AREAS

SHEET 6 OF 11

Page 110: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

EAST PROVIDENCE, RHODE ISLAND

DEPARTMENT OF TRANSPORTATION

RHODE ISLAND

DISTURBANCE AREAS

SHEET 7 OF 11

Page 111: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

DISTURBANCE AREAS

SHEET 8 OF 11

EAST PROVIDENCE, RHODE ISLAND

DEPARTMENT OF TRANSPORTATION

RHODE ISLAND

Page 112: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

EAST PROVIDENCE, RHODE ISLAND

DEPARTMENT OF TRANSPORTATION

RHODE ISLAND

DISTURBANCE AREAS

SHEET 9 OF 11

Page 113: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

EAST PROVIDENCE, RHODE ISLAND

DEPARTMENT OF TRANSPORTATION

RHODE ISLAND

DISTURBANCE AREAS

SHEET 10 OF 11

Page 114: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

EAST PROVIDENCE, RHODE ISLAND

DEPARTMENT OF TRANSPORTATION

RHODE ISLAND

DISTURBANCE AREAS

SHEET 11 OF 11

Page 115: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

louisberger.com

RI Department of Transportation

Improvements to I-195, ABC Bridge No. 472 over I-195 Superstructure Replacement

SWPPP

ATTACHMENT C

Copy of RIPDES General Permit

Page 116: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

louisberger.com

RI Department of Transportation

Improvements to I-195, ABC Bridge No. 472 over I-195 Superstructure Replacement

SWPPP

ATTACHMENT D

Copy of RIPDES NOI

Page 117: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

louisberger.com

RI Department of Transportation

Improvements to I-195, ABC Bridge No. 472 over I-195 Superstructure Replacement

SWPPP

ATTACHMENT E

Copy of Regulatory Permits

Page 118: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

louisberger.com

RI Department of Transportation

Improvements to I-195, ABC Bridge No. 472 over I-195 Superstructure Replacement

SWPPP

ATTACHMENT F

Inspection Form

Page 119: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

louisberger.com

RI Department of Transportation

Improvements to I-195, ABC Bridge No. 472 over I-195 Superstructure Replacement

SWPPP

ATTACHMENT G

Amendments Log

Page 120: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

louisberger.com

RI Department of Transportation

Improvements to I-195, ABC Bridge No. 472 over I-195 Superstructure Replacement

SWPPP

ATTACHMENT H

Additional Information (i.e. documentation)

Page 121: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

RIDOTVersion 2.20120529

SWPPP Inspection Report

Instructions For all projects with one (1) acre or greater of soil disturbance, RIDOT is required to develop and enforce a Site-Specific Storm Water Pollution Prevention Plan (SWPPP) in order to remain in compliance with the Rhode Island Pollutant Discharge Elimination System General Permit for Stormwater Discharges Associated with Construction Activities (RIPDES Construction General Permit). As part of the SWPPP, a site-specific inspection report must be created and utilized.

Preparing the Inspection Report This inspection report template has been provided by RIDOT for the development of the site-specific SWPPP Inspection Report. It must be customized for each individual Project to meet the requirements of the RIPDES Construction General Permit. It is expected that this Inspection Report will be prepared as part of the preparation of the site-specific SWPPP. This inspection report template is designed to be customized according to the SWPPP document (initially) and then customized based on conditions at the site. Review the site-specific SWPPP and the Plans to develop the inspection report. On a copy of the site plan, number all stormwater BMPs and areas of the site that will be inspected. Include both structural (basins, outlet protection, swales, etc) and non-structural (construction entrances, perimeter barriers, trash areas, etc) BMPs and areas that will be inspected. Also identify all point source outfalls, areas of highly erodable soils, and the priority natural resource areas (i.e. streams, wetlands, mature trees, etc). List each BMP or area to be inspected separately in the site-specific BMP section of the inspection report. An appropriate rain gauge must be identified and utilized for the determination of the storm events. Rain gauges may be found on www.wunderground.com, www.nws.noaa.gov (or similar sites).

Page 122: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

RIDOTVersion 2.20120529

SWPPP Inspection Report Instructions for:

Resident Engineer

The RIDOT Resident Engineer (RE) must review the SWPPP and sign the Certification Statement for RIDOT Resident Engineer in Section 8. If the RE has any questions, contact the RIDOT Natural Resources Unit at 401-222-2023.

It is the responsibility of the RIDOT Resident Engineer to initiate contact with the Inspector to start the SWPPP Inspections BEFORE EARTHWORK BEGINS. The Inspector (typically a Consultant) will have been identified at the Pre-Construction meeting. Earthwork is NOT allowed to proceed until a SWPPP Inspection of the site has been completed.

After an Inspection has been performed, the RE must sign the ‘acknowledgement’ certification on Page 1 of the Inspection Report at time of receipt from the Inspector.

The RE must review the Inspection Report within 24-hours of receipt.

o If the RE agrees with the Inspection report, the RE must:

Fill out the “NOTICE TO CONTACTOR” box on the last page of the Report

Have the Contractor sign the ‘acknowledgement’ certification on Page 1

Make a copy of the Inspection Report with all 3 signatures for the Contractor’s use AND provide a copy to the Inspector

o If the RE disagrees with a corrective action item, the RE must:

Document objection with each item and provide justifiable reason in the inspection report. The contractor will not responsible for initiating corrective actions for such items. The RIDOT Natural Resources Unit will review such items if warranted.

Fill out the “NOTICE TO CONTACTOR” box on the last page of the Report

Have the Contractor sign the ‘acknowledgement’ certification on Page 1

Make a copy of the Inspection Report with all 3 signatures for the Contractor’s use AND provide a copy to the Inspector

It is the responsibility of the RIDOT Resident Engineer to maintain a copy of the SWPPP, copies of all completed & signed inspection reports, and amendments as part of the SWPPP documentation at the project field office during construction.

Page 123: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

RIDOTVersion 2.20120529

SWPPP Inspection Report Instructions for:

INSPECTORS

The RIDOT-designated inspector must sign the Certification Statement for RIDOT SWPPP Inspector in Section 8 of the Storm Water Pollution Prevention Plan (SWPPP).

A separate inspection report will be prepared for each inspection.

Complete any items that will remain constant, such as the project information and BMP locations and descriptions. Then print out multiple copies (double-sided!) of this customized inspection report to use during the inspections.

The Inspection Reference Number shall be a combination of the Construction Contract Number - consecutively numbered inspections. ex/ Inspection reference number for the 4th inspection of a project would be: 2006-AA-BBB-4

Check the rain gauge for past & future weather data prior to inspection. Minimum Monitoring and Reporting Requirements

“…the site must be inspected at least once every seven (7) calendar days and within twenty-four (24) hours after any storm event which generates at least 0.25-inches of precipitation per twenty four (24) hour period and/or after a significant amount of runoff or snowmelt.” (RIPDES CGP)

When conducting the inspection, walk the site by following the site map and numbered BMPs locations for inspection. Also note whether the overall site issues have been addressed.

Associated photos – each photo should be dated and have a unique identification # and written description indicating where it is located within the project area. If a close up photo is required, it should be preceded with a photo including both the detail area and some type of visible fixed reference point. Photos should be annotated with Station numbers and other identifying information where needed.

For each inspection, the Inspector must determine if the Construction site is in compliance with the CGP, or not. The Inspector must check the appropriate check-box on Page 1 of the inspection report.

Each report must be signed and dated by the Inspector, and forwarded to the Engineer within 24-hours of the inspection.

Page 124: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

RIDOTVersion 2.20120529

SWPPP Inspection Report Instructions for:

INSPECTORS (continued)

The inspector will submit a Monthly Inspection Report to: RIDOT Natural Resources Unit, Two Capitol Hill, Rm. 323, Providence, RI 02903 At a minimum, the inspection reports must be submitted on a monthly basis, and must include:

A copy of each completed, dated, and signed inspection report

A copy of the daily rainfall summary data for the month as reported by the selected rain gauge (ex/ the monthly calendar from www.wunderground.com).

One copy of the Monthly Inspection Report will be printed double-sided (except for photo or plan sheet pages), and forwarded to the NRU by no later than the 10th of the month following the end of the reporting period.

Content, frequency, &/or submission format of inspection reports may be changed with approval of the applicable Natural Resources Unit personnel for the Project.

Page 125: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

RIDOTVersion 2.20120529

SWPPP Inspection Report Instructions for:

Contractor The Contractor must sign the ‘acknowledgement’ certification on Page 1 of the Inspection

Report at time of receipt from the Resident Engineer.

The RE will provide a copy of the signed Inspection Report to the Contractor.

The Inspection Report serves as your RIDOT directive to proceed with corrective actions.

In accordance with the SWPPP and Section 212 of the RIDOT Standard Specifications, the Contractor will commence with the requisite cleaning and maintenance measures no later than the next consecutive calendar day after receiving such a directive from the Engineer, and will aggressively and expeditiously perform such cleaning and maintenance work until the original problem is remedied to the complete satisfaction of the Engineer.

Progress on Corrective Action items will be documented by the Inspector in subsequent inspections.

Inspector, Resident Engineer, & Contractor Amendments The SWPPP shall be amended whenever there is a change in design, construction, operation, maintenance or other procedure which has a significant effect on the potential for the discharge of pollutants, or if the SWPPP proves to be ineffective in achieving its objectives. SWPPP Amendments may be recommended by any party, but all amendments must be approved by the Resident Engineer. The revision must be recorded in the Record of Amendments Log Sheet within the SWPPP, and dated red-line drawings and/or a detailed written description must be appended to the SWPPP. Inspection Forms must be revised to reflect all amendments by the Inspector. Questions Questions may be addressed to the RIDOT Natural Resources Unit, 2 Capitol Hill, Providence, RI 02903. 401-222-2023

Page 126: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

RIC NO: 2017-CB-070 INSPECTION REF #:

RIDOTVersion 2.20120529

SWPPP Inspection Report Project Information

Name/Location

RIDOT Project Manager RIDOT Resident Engineer

Contractor SWPPP Contact

E&S Sub-Contractor SWPPP Contact

Inspection Information

Inspector

Inspection Date Start/End Time

Inspection Type Weekly Pre-storm event During storm event Post-storm event Violation

Weather Information

Rain Gauge:

Last Rain Event Date: Duration (hrs): Approximate Rainfall (in):

Current Weather at time of this inspection:

Weather Forecast at time of this inspection: (when is next precipitation or wind event anticipated?)

Certification Statements

Inspector: (check one) I, as the designated Inspector, certify that this site has been inspected and is in compliance with the site-specific

SWPPP.

I, as the designated Inspector, certify that this site has been inspected and I have made the determination that the

site requires corrective actions before it will be compliant with the site-specific SWPPP. The required corrective actions are

noted within this inspection report.

Print Name: Signature: Date:

Resident Engineer:

I, the RIDOT Resident Engineer, acknowledge the receipt of this SWPPP inspection report, and understand the requirements set forth in the RIDOT Standard Specifications and the Contract Documents regarding the implementation

and maintenance of erosion and sedimentation controls.

Print Name: Signature: Date:

Contractor:

I, the designated Contractor representative, acknowledge the receipt of this SWPPP inspection report, and understand the

requirements set forth in the RIDOT Standard Specifications and the Contract Documents regarding the implementation and maintenance of erosion and sedimentation controls.

Print Name: Signature: Date:

Page 127: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

RIC NO: 2017-CB-070 INSPECTION REF #:

RIDOTVersion 2.20120529

Site-specific BMPs Number the structural and non-structural BMPs identified in the SWPPP on the site map and list them below (add as necessary). Bring a copy of this inspection form and numbered site map with you during your inspections. This list will help ensure that you are inspecting all required BMPs at your site. FILL THIS TABLE USING THE SWPPP TABLES 2.14 & 3.11

Location/Station BMP Description Installed & Operating Properly?

Assoc. Photo/

Figure #

Corrective Action

1

Yes No

2

Yes No

3

Yes No

4

Yes No

5

Yes No

6

Yes No

7

Yes No

8

Yes No

9

Yes No

10

Yes No

11

Yes No

12

Yes No

13

Yes No

14

Yes No

15

Yes No

(add more as necessary)

Page 128: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

RIC NO: 2017-CB-070 INSPECTION REF #:

RIDOTVersion 2.20120529

Overall Site Issues Below are some general site issues that should be assessed during inspections. Please customize this list as needed for conditions at the site. If item is not applicable, please note why.

EROSION AND SEDIMENTATION BMP INSPECTION

Installed & Operating

correctly?

Assoc. Photo/

Figure #

CORRECTIVE ACTION

2.1 Are Limits of Disturbance clearly

marked?

Yes No

N/A

2.1

Are natural resource areas (e.g., streams, wetlands, trees, etc.)

protected with barriers or similar BMPs?

Yes No

N/A

2.2 Is construction sequencing being

followed?

Yes No

N/A

2.3

Are structural BMPs properly

installed to control stormwater flow on the construction site?

Yes No

N/A

2.4

Is clearing/grubbing only

occurring in areas that will have active work within 21-days?

Yes No

N/A

2.4 Is clearing/grubbing taking place inside the Apr 15 - Oct 15 window?

Yes No

N/A

2.4 Do unstabilized areas have appropriate controls in place?

Yes No

N/A

2.5 Are all slopes protected from concentrated stormwater flow?

Yes No

N/A

2.6 Are storm drain inlets properly

protected?

Yes No

N/A

2.7 Are storm drain outfalls properly protected?

Yes No

N/A

2.8

Are perimeter controls and

sediment barriers adequately installed and maintained?

Yes No

N/A

2.9 Are discharge points and receiving waters free of sediment deposits?

Yes No

N/A

2.10 Is weather forecast being checked regularly?

Yes No

N/A

Page 129: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

RIC NO: 2017-CB-070 INSPECTION REF #:

RIDOTVersion 2.20120529

Notes on Erosion and Sediment Controls:

GOOD HOUSEKEEPING BMP INSPECTION

Installed &

Operating correctly?

Assoc. Photo/

Figure #

CORRECTIVE ACTION

3

.1

Are BMPs effectively limiting sediment from

being tracked into the street?

Yes No

N/A

3

.2

Is trash/litter from work areas collected

and placed in covered containers regularly?

Yes No

N/A

3

.3

Are on-site equipment, vehicles, containers,

and storage areas free from leaks?

Yes No

N/A

3

.3

Are materials that are potential stormwater contaminants stored inside or under cover?

Yes No

N/A

3

.4

Are non-storm water discharges free

from contamination?

Yes No

N/A

3.

5

Are stockpiles covered (either with

temporary vegetation or tarps), ringed with barrier BMPs, and

located at least 50 feet away from natural resources and storm drains?

Yes No

N/A

36

Are washout facilities (e.g. paint,

concrete) available, clearly marked, and maintained and located at least 50-feet away

from natural resources and storm drains?

Yes No

N/A

3

.7

Are vehicle and equipment fueling, cleaning, and maintenance areas free from

leaks and located at least 50-feet away from natural resources and storm drains?

Yes No

N/A

3

.8

Is dust being controlled on-site? Yes No

N/A

3.

9

Is sweeping being used to keep sediment

off roads and parking lots?

Yes No

N/A

PROCEURAL BMP INSPECTION

Installed &

Operating

correctly?

Assoc.

Photo/

Figure # Corrective Action

4.1 Are permanent BMPs being protected

during the active construction phase?

Yes No

N/A

5.1 Are all structural BMPs being

maintained in accordance with RIDOT Yes No

Page 130: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

RIC NO: 2017-CB-070 INSPECTION REF #:

RIDOTVersion 2.20120529

Standard Spec Section 212?

5.2 Are inspections taking place every 7-

days & after storm events? Yes No

5.3 Have previous Corrective Actions been

initiated & completed by the Contractor?

Yes No

N/A

6.0 Are SWPPP Amendments being logged? Yes No

N/A

7.0

Are the SWPPP and ALL inspection

reports being kept at the RIDOT Field Office?

Yes No

Page 131: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

RIC NO: 2017-CB-070 INSPECTION REF #:

RIDOTVersion 2.20120529

Photo Log: (Associated photos – each photo should be dated and have a unique identification # and written description indicating where it is located within the project area. If a close up photo is required, it should be preceded with a photo including both the detail area and some type of visible fixed reference point. Photos should be annotated with Station numbers and other identifying information where needed.) Photo #: Station:

(insert Photo here) Description:

Photo #: Station:

(insert Photo here) Description:

Photo #: Station:

(insert Photo here) Description:

Photo #: Station:

(insert Photo here) Description:

Photo #: Station:

(insert Photo here) Description:

Photo #: Station:

(insert Photo here) Description:

(add more as necessary)

Page 132: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

RIC NO: 2017-CB-070 INSPECTION REF #:

RIDOTVersion 2.20120529

General Field Comments:

NOTICE TO CONTRACTOR

This SWPPP Inspection Report, completed by a RIDOT-designated inspector, indicates that this construction site is:

COMPLIANT

NON-COMPLIANT

This document serves as your RIDOT directive to proceed with corrective actions that have been outlined above.

The SWPPP, Construction Contract documents, and the RIDOT Standard Specifications state that non-compliance issues shall be addressed no later than (7) seven calendar days from

date of inspection. In accordance with the SWPPP and Section 212 of the RIDOT Standard Specifications, the contractor shall commence with the requisite cleaning and maintenance

measures no later than the next calendar day after receiving such a directive from the

engineer.

Date work to begin:

Date work to be completed:

R.E. initials: ____________ R.E. Comments:

Date: ____________

Page 133: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

RIDOTVersion 2.20120529

AMENDMENT LOG ALL AMENDMENS MUST BE APPROVED BY RIDOT RESIDENT ENGINEER

Describe amendment to be made to SWPPP, the date, and the person/title making the amendment. ALL amendments must be approved by the RIDOT Resident Engineer. Amendment

Number

Date Description of Amendment Amended

by:

Person/Title

R.E.

initials

1

2

3

4

5

6

7

8

9

10

11

12

13

14

Page 134: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East

CS-57

APPENDIX “D”

PAVEMENT CORES

pfowler
Text Box
CS-133
Page 135: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East
Page 136: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East
Page 137: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East
Page 138: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East
Page 139: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East
Page 140: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East
Page 141: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East
Page 142: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East
Page 143: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East
Page 144: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East
Page 145: REQUIRED CONTRACT PROVISIONS€¦ · West Warwick, RI 02893 Contact person: David Velilla, (401) 615 ‐1284 . EAST PROVIDENCE DEPARTMENT OF PUBLIC WORKS . 145 Taunton Avenue East